Organization Scope . Actors includes - - Integrated ...
Transcript of Organization Scope . Actors includes - - Integrated ...
Integrated Product, Organization and Process
design
John Kunz
The big idea: Integrated Product, Organization and Process design can support, at least design, fabrication and assembly
Rate
Baseline
($K) Change
Year-1
(K$)
Revenue 100,000 2% 102,000
Cost of contracted work 85% 85,000 -2.0% 84,660
Cost of self-performed work 10% 10,000 2.0% 12,240
Gross Margin 5,000 5,100
Sales, G&A 2% 2,000 2,040
IT investment 70
Amortized costs of IT/yr 33% 23
Net income 3,000 3,037
Time to payback (years) 1.9
Net Income change (%) 1.2
*05-07-01
Finish
Final Program
Confirmation with
Pharmacology
Final Program
confirmation with LAR
KPFF
SRG Lab Task 37 Task 44 Project Mgt AEI Core Task 41 Task26 H Block Crew Task 23SRG / AEI
TechnicalAEI Core and
SRG LabHDCCO Costing
SRG
TechnicalKPFF
AEI Core
and TechHDCCO Core
Code Rev
ConsultantSolvent Tarter
H Block Crew
& Tech
SRG
Landscape
Tele Data
DesignCode Rev
Furniture
37.
*Reprogram
B#15 Shafts
34. *Finalize
Pharmacology
Program
33. *Finalize
LAR Program
32. *Finalize
Bio-Organic
Chemistry
Program
35. *Finalize
Protein Chemistry
Program 20. *Determine Scope of
package D including vivarium
changes
45. *Complete all
Basement/LAR Drawings
41. *Reprogram
bookends B#13 and
B#15
36. *Analyze
structural impacts
12. *Complete UG
utiliites
25. *Do Central Plant
design changes
19. *Determine vertical
utilities
22. *Complete catwalk drawings
52. Finalize landscape
26. *Finalize B#13 and
B#15
Exiting/architecural H
occupancy concept
*Lab and
vivarium
Programming
Complete
27. *Finalize B#13,
15 Shaft Size &
MEP Room
Locations
31.* AEI &
SRG
Determine
Design $/Time
Impact of
Change
23. *Reprogram
B#13 and B#15
Exterior Architecture
Bookend
Programming
Accepted by Genentech
Notice to proceed on
structural changes
Architect
program/MEP
oncepts
Established
By Design
Team
29. *Document
lab plan
1. *Redesign main MEP
distribution systems
SRG Management AEI Management
Genentech PM
SRG Lab Plan
Ken Mouchka
Task 27Task 38
Organization
5. *Finalize lab & Equipment
plans
Task 29
Task 28
30. *Approve
Change to
Design
Contract
21. *Prepare Plan Views for
Review of Concept w/City
39. *Finalize MEP
distribution and
section
Task4 Task22
Review 80%
documents
48. *Develop exiting
plan
49. Develop
reflected ceiling
plan
Turnover
reflected
ceiling plan to
AEI
Detailed Design 80 PC
Complete
3. Complete Tele Data Design
42. *Develop
Execution
Strategy
44. *Complete
B#14 Officing
Planning
18. *Detailed Lab
Program
Documentation
47. *Develop lab
DD plan
28. *Determine
segregation of lab
and tech space
G accept lab
equipment matrix
*Package B structural
modifications (CCD3A)
13. *Code Consultants
Review Concept for final
city Presentation
14. *HDCCO update Estimate of cost
of Program
Review skin changes w/db team
Lab Planning Program
Meetings with
Pharmacology
Lab planning Program Meeting with Protein
Chemistry
BMS Controls Meetings
(Weekly)
Lab Planning Program meeting with Bio
Organic 80% Drawing Review
Tele Data Coordination MeetingsSteel Detailing
Meetings
Genentech 80% Detailed Design
Review
Final Program
Confirmation with Officing
Weekly
Coordination
Meeting
Lab Planning Program
Meetings with Directors
50. Designate size, location of
13 MEP, teledata rooms
54. KPFF design
stairs for 13/1438. *SRG
Reprogram 13/14
interface, exiting,
stairs
43. *Changes in Steel
Forwarded to Steel
Detailers
46. *RA Furnture
Concept Complete
MEP, Teledata room design
*Design Budget &
Schedule for Changes
Approved
*Notice to proceed
with detailed design
24. *Complete B13,4 H
block occupancy
requirements on MEP
systems
17. *Risick
reprogram solvent
distribution and waste
Issue 80%
MEP CDs
(20) Incorporate
80% MEP review
comments
(19) Genentech review
80% drawings
53. Incorporate
comments, complete
Architectural detail
2. Initial redesign MEP branch
lateral distribution
G accept
13/14
Interface
*City Accept
exiting
*Package C
skin
modifications
55. KPFF design
stairs for 15/14
40. *SRG
Reprogram 15/14
interface, exiting,
stairs
B13 MEP HVAC,
conduit, piping mains
completed
MEP 80% Review
comments
incorporated
Package D and UG
addendum issued:
underground utilities,
vivarium catwalk
10. Draft Alternate means
15. Jeff reprogram HMIS
(3) *AEI design MEP
HVAC, Conduit &
piping mains B13
16. *HDCCO Determine
Schedule Impact
City Approval of
Alternate Means
for Program
8. Review Alternate
Means w/impact on LEL
and LFFH
(21-4) Finalize MEP Details,
update specs and p&ID's
(8) *Revise
MEP loads, MEP
Equipment
schedules
finalized
(13,15,16) MEP specs, P&ID's,
control sequences
Work Process
Meetings
(6) Coord B13 MEP
floor section
4. complete all Interior Architcture
*Cal OSHA Recommend
Determination of LFFH
51. Designate size, location
of 14 MEP, teledata rooms G accept
15/14
Interface
*Accept project
scope:budget
by Genentech
*City Approval of
H Concept
*Exterior
Programming
Accepted by Genentech
*Turnover lab and
vivarium DD plan
to AEI
Object AttributeRequirement
Relationship Requirement
Predicte
d value
Observed
value -2 -1 0 1 2
Product
Product Scope
Product Scope . Building Spaces includes -
Project Goals
Project Goal . Capacity (people) >= 60 - ?o
Project Goal . Cost (M$) = 70 - ?o
Building
Goal . Net Energy Use (K-
BTU/ft2) <= 250 - ?o
Building
Goal . Quality conformance
(%) >= 12 - ?o
Organization Scope
Organization Scope . Actors includes - -
Organization Goals
Organization Goal . Predicted . Cost (K$) - <= - ?o
Organization
Goal . Observed . Response
Latency (days) 3 <= - ?o
Organization
Goal . Predicted . Peak
Backlog (days) 3 <= - ?o
Organization
Goal . Predicted . rework
(FTE-days) - <= - ?o
Process
Process Goals
Process Goal . Peak Quality Risk < 0.50 - -
Process
Goal . Schedule Growth
(months) < - ?o
Process Goal . Completion Date <= 1/1/09 - ?o
Process Task . Action: Object
Process Task . Design: Actor Actor that designs
Process Task . Predict: Actor Actor that predicts
Process Task . Assess: Actor Actor that assesses
Process Task . Build: Actor Actor that builds
Function Product Behavior
Organization
Qualitative Threshhold values
11 July 2011 Chalmers Integrated Design 2
This week overview
Day Take-home
Monday Introduction:
Theory: integrated multi-disciplinary models and
analyses and multi-disciplinary Integrated Concurrent
Engineering;
Practice: lab; ICE session
Tuesday Theory: methods we now use to design organizations
as we design bridges;
Practice: lab
Thursday Theory: methods of integrated POP design and
analysis
Practice: initial presentations Object AttributeRequirement
Relationship Requirement
Predicte
d value
Observed
value -2 -1 0 1 2
Product
Product Scope
Product Scope . Building Spaces includes -
Project Goals
Project Goal . Capacity (people) >= 60 - ?o
Project Goal . Cost (M$) = 70 - ?o
Building
Goal . Net Energy Use (K-
BTU/ft2) <= 250 - ?o
Building
Goal . Quality conformance
(%) >= 12 - ?o
Organization Scope
Organization Scope . Actors includes - -
Organization Goals
Organization Goal . Predicted . Cost (K$) - <= - ?o
Organization
Goal . Observed . Response
Latency (days) 3 <= - ?o
Organization
Goal . Predicted . Peak
Backlog (days) 3 <= - ?o
Organization
Goal . Predicted . rework
(FTE-days) - <= - ?o
Process
Process Goals
Process Goal . Peak Quality Risk < 0.50 - -
Process
Goal . Schedule Growth
(months) < - ?o
Process Goal . Completion Date <= 1/1/09 - ?o
Process Task . Action: Object
Process Task . Design: Actor Actor that designs
Process Task . Predict: Actor Actor that predicts
Process Task . Assess: Actor Actor that assesses
Process Task . Build: Actor Actor that builds
Function Product Behavior
Organization
Qualitative Threshhold values
11 July 2011 Chalmers Integrated Design 3
The next two weeks we will …
• Do integrated design and analysis with VDC
and the ABC of your POP - FFB based on a
PBS, OBS and WBS using ICE, DEEPAND
and MACDADI …
11 July 2011 Chalmers Integrated Design 4
Monday Learning goals
• Get basic familiarity with the POP project framework of
VDC
• Product – Organization – Process (POP)
• Function – Form – Behavior (FFB)
• Understand class organization, opportunities, methods
and expectations
• Motivate interest in Integrated Design enabled by
VDC:
• Opportunities in practice
• Fun, power and job opportunities of models, model-
based analyses
11 July 2011 Chalmers Integrated Design 5
Chalmers Integrated Design Agenda: July 11
• Big ideas: Integrated design and analysis; VDC; ICE
• Introductions
• Models: how would you recognize one
• Business objectives
• Course objectives (and non-objectives)
• Course Organization
• ORID
*05-07-01
Finish
Final Program
Confirmation with
Pharmacology
Final Program
confirmation with LAR
KPFF
SRG Lab Task 37 Task 44 Project Mgt AEI Core Task 41 Task26 H Block Crew Task 23SRG / AEI
TechnicalAEI Core and
SRG LabHDCCO Costing
SRG
TechnicalKPFF
AEI Core
and TechHDCCO Core
Code Rev
ConsultantSolvent Tarter
H Block Crew
& Tech
SRG
Landscape
Tele Data
DesignCode Rev
Furniture
37.
*Reprogram
B#15 Shafts
34. *Finalize
Pharmacology
Program
33. *Finalize
LAR Program
32. *Finalize
Bio-Organic
Chemistry
Program
35. *Finalize
Protein Chemistry
Program 20. *Determine Scope of
package D including vivarium
changes
45. *Complete all
Basement/LAR Drawings
41. *Reprogram
bookends B#13 and
B#15
36. *Analyze
structural impacts
12. *Complete UG
utiliites
25. *Do Central Plant
design changes
19. *Determine vertical
utilities
22. *Complete catwalk drawings
52. Finalize landscape
26. *Finalize B#13 and
B#15
Exiting/architecural H
occupancy concept
*Lab and
vivarium
Programming
Complete
27. *Finalize B#13,
15 Shaft Size &
MEP Room
Locations
31.* AEI &
SRG
Determine
Design $/Time
Impact of
Change
23. *Reprogram
B#13 and B#15
Exterior Architecture
Bookend
Programming
Accepted by Genentech
Notice to proceed on
structural changes
Architect
program/MEP
oncepts
Established
By Design
Team
29. *Document
lab plan
1. *Redesign main MEP
distribution systems
SRG Management AEI Management
Genentech PM
SRG Lab Plan
Ken Mouchka
Task 27Task 38
Organization
5. *Finalize lab & Equipment
plans
Task 29
Task 28
30. *Approve
Change to
Design
Contract
21. *Prepare Plan Views for
Review of Concept w/City
39. *Finalize MEP
distribution and
section
Task4 Task22
Review 80%
documents
48. *Develop exiting
plan
49. Develop
reflected ceiling
plan
Turnover
reflected
ceiling plan to
AEI
Detailed Design 80 PC
Complete
3. Complete Tele Data Design
42. *Develop
Execution
Strategy
44. *Complete
B#14 Officing
Planning
18. *Detailed Lab
Program
Documentation
47. *Develop lab
DD plan
28. *Determine
segregation of lab
and tech space
G accept lab
equipment matrix
*Package B structural
modifications (CCD3A)
13. *Code Consultants
Review Concept for final
city Presentation
14. *HDCCO update Estimate of cost
of Program
Review skin changes w/db team
Lab Planning Program
Meetings with
Pharmacology
Lab planning Program Meeting with Protein
Chemistry
BMS Controls Meetings
(Weekly)
Lab Planning Program meeting with Bio
Organic 80% Drawing Review
Tele Data Coordination MeetingsSteel Detailing
Meetings
Genentech 80% Detailed Design
Review
Final Program
Confirmation with Officing
Weekly
Coordination
Meeting
Lab Planning Program
Meetings with Directors
50. Designate size, location of
13 MEP, teledata rooms
54. KPFF design
stairs for 13/1438. *SRG
Reprogram 13/14
interface, exiting,
stairs
43. *Changes in Steel
Forwarded to Steel
Detailers
46. *RA Furnture
Concept Complete
MEP, Teledata room design
*Design Budget &
Schedule for Changes
Approved
*Notice to proceed
with detailed design
24. *Complete B13,4 H
block occupancy
requirements on MEP
systems
17. *Risick
reprogram solvent
distribution and waste
Issue 80%
MEP CDs
(20) Incorporate
80% MEP review
comments
(19) Genentech review
80% drawings
53. Incorporate
comments, complete
Architectural detail
2. Initial redesign MEP branch
lateral distribution
G accept
13/14
Interface
*City Accept
exiting
*Package C
skin
modifications
55. KPFF design
stairs for 15/14
40. *SRG
Reprogram 15/14
interface, exiting,
stairs
B13 MEP HVAC,
conduit, piping mains
completed
MEP 80% Review
comments
incorporated
Package D and UG
addendum issued:
underground utilities,
vivarium catwalk
10. Draft Alternate means
15. Jeff reprogram HMIS
(3) *AEI design MEP
HVAC, Conduit &
piping mains B13
16. *HDCCO Determine
Schedule Impact
City Approval of
Alternate Means
for Program
8. Review Alternate
Means w/impact on LEL
and LFFH
(21-4) Finalize MEP Details,
update specs and p&ID's
(8) *Revise
MEP loads, MEP
Equipment
schedules
finalized
(13,15,16) MEP specs, P&ID's,
control sequences
Work Process
Meetings
(6) Coord B13 MEP
floor section
4. complete all Interior Architcture
*Cal OSHA Recommend
Determination of LFFH
51. Designate size, location
of 14 MEP, teledata rooms G accept
15/14
Interface
*Accept project
scope:budget
by Genentech
*City Approval of
H Concept
*Exterior
Programming
Accepted by Genentech
*Turnover lab and
vivarium DD plan
to AEI
Object AttributeRequirement
Relationship Requirement
Predicte
d value
Observed
value -2 -1 0 1 2
Product
Product Scope
Product Scope . Building Spaces includes -
Project Goals
Project Goal . Capacity (people) >= 60 - ?o
Project Goal . Cost (M$) = 70 - ?o
Building
Goal . Net Energy Use (K-
BTU/ft2) <= 250 - ?o
Building
Goal . Quality conformance
(%) >= 12 - ?o
Organization Scope
Organization Scope . Actors includes - -
Organization Goals
Organization Goal . Predicted . Cost (K$) - <= - ?o
Organization
Goal . Observed . Response
Latency (days) 3 <= - ?o
Organization
Goal . Predicted . Peak
Backlog (days) 3 <= - ?o
Organization
Goal . Predicted . rework
(FTE-days) - <= - ?o
Process
Process Goals
Process Goal . Peak Quality Risk < 0.50 - -
Process
Goal . Schedule Growth
(months) < - ?o
Process Goal . Completion Date <= 1/1/09 - ?o
Process Task . Action: Object
Process Task . Design: Actor Actor that designs
Process Task . Predict: Actor Actor that predicts
Process Task . Assess: Actor Actor that assesses
Process Task . Build: Actor Actor that builds
Function Product Behavior
Organization
Qualitative Threshhold values
11 July 2011 Chalmers Integrated Design 6
Traditional product models
+: Work in practice
: Ambiguities to
stakeholders
: computer analysis ...?
– Show value to owner
– List components
– Estimate cost
– Plan construction
– Identify interferences
11 July 2011 Chalmers Integrated Design 7
Models
• Physical
• Statistical
• Mathematical
Symbolic
Graphic
*05-07-01
Finish
Final Program
Confirmation with
Pharmacology
Final Program
confirmation with LAR
KPFF
SRG Lab Task 37 Task 44 Project Mgt AEI Core Task 41 Task26 H Block Crew Task 23SRG / AEI
TechnicalAEI Core and
SRG LabHDCCO Costing
SRG
TechnicalKPFF
AEI Core
and TechHDCCO Core
Code Rev
ConsultantSolvent Tarter
H Block Crew
& Tech
SRG
Landscape
Tele Data
DesignCode Rev
Furniture
37.
*Reprogram
B#15 Shafts
34. *Finalize
Pharmacology
Program
33. *Finalize
LAR Program
32. *Finalize
Bio-Organic
Chemistry
Program
35. *Finalize
Protein Chemistry
Program 20. *Determine Scope of
package D including vivarium
changes
45. *Complete all
Basement/LAR Drawings
41. *Reprogram
bookends B#13 and
B#15
36. *Analyze
structural impacts
12. *Complete UG
utiliites
25. *Do Central Plant
design changes
19. *Determine vertical
utilities
22. *Complete catwalk drawings
52. Finalize landscape
26. *Finalize B#13 and
B#15
Exiting/architecural H
occupancy concept
*Lab and
vivarium
Programming
Complete
27. *Finalize B#13,
15 Shaft Size &
MEP Room
Locations
31.* AEI &
SRG
Determine
Design $/Time
Impact of
Change
23. *Reprogram
B#13 and B#15
Exterior Architecture
Bookend
Programming
Accepted by Genentech
Notice to proceed on
structural changes
Architect
program/MEP
oncepts
Established
By Design
Team
29. *Document
lab plan
1. *Redesign main MEP
distribution systems
SRG Management AEI Management
Genentech PM
SRG Lab Plan
Ken Mouchka
Task 27Task 38
Organization
5. *Finalize lab & Equipment
plans
Task 29
Task 28
30. *Approve
Change to
Design
Contract
21. *Prepare Plan Views for
Review of Concept w/City
39. *Finalize MEP
distribution and
section
Task4 Task22
Review 80%
documents
48. *Develop exiting
plan
49. Develop
reflected ceiling
plan
Turnover
reflected
ceiling plan to
AEI
Detailed Design 80 PC
Complete
3. Complete Tele Data Design
42. *Develop
Execution
Strategy
44. *Complete
B#14 Officing
Planning
18. *Detailed Lab
Program
Documentation
47. *Develop lab
DD plan
28. *Determine
segregation of lab
and tech space
G accept lab
equipment matrix
*Package B structural
modifications (CCD3A)
13. *Code Consultants
Review Concept for final
city Presentation
14. *HDCCO update Estimate of cost
of Program
Review skin changes w/db team
Lab Planning Program
Meetings with
Pharmacology
Lab planning Program Meeting with Protein
Chemistry
BMS Controls Meetings
(Weekly)
Lab Planning Program meeting with Bio
Organic 80% Drawing Review
Tele Data Coordination MeetingsSteel Detailing
Meetings
Genentech 80% Detailed Design
Review
Final Program
Confirmation with Officing
Weekly
Coordination
Meeting
Lab Planning Program
Meetings with Directors
50. Designate size, location of
13 MEP, teledata rooms
54. KPFF design
stairs for 13/1438. *SRG
Reprogram 13/14
interface, exiting,
stairs
43. *Changes in Steel
Forwarded to Steel
Detailers
46. *RA Furnture
Concept Complete
MEP, Teledata room design
*Design Budget &
Schedule for Changes
Approved
*Notice to proceed
with detailed design
24. *Complete B13,4 H
block occupancy
requirements on MEP
systems
17. *Risick
reprogram solvent
distribution and waste
Issue 80%
MEP CDs
(20) Incorporate
80% MEP review
comments
(19) Genentech review
80% drawings
53. Incorporate
comments, complete
Architectural detail
2. Initial redesign MEP branch
lateral distribution
G accept
13/14
Interface
*City Accept
exiting
*Package C
skin
modifications
55. KPFF design
stairs for 15/14
40. *SRG
Reprogram 15/14
interface, exiting,
stairs
B13 MEP HVAC,
conduit, piping mains
completed
MEP 80% Review
comments
incorporated
Package D and UG
addendum issued:
underground utilities,
vivarium catwalk
10. Draft Alternate means
15. Jeff reprogram HMIS
(3) *AEI design MEP
HVAC, Conduit &
piping mains B13
16. *HDCCO Determine
Schedule Impact
City Approval of
Alternate Means
for Program
8. Review Alternate
Means w/impact on LEL
and LFFH
(21-4) Finalize MEP Details,
update specs and p&ID's
(8) *Revise
MEP loads, MEP
Equipment
schedules
finalized
(13,15,16) MEP specs, P&ID's,
control sequences
Work Process
Meetings
(6) Coord B13 MEP
floor section
4. complete all Interior Architcture
*Cal OSHA Recommend
Determination of LFFH
51. Designate size, location
of 14 MEP, teledata rooms G accept
15/14
Interface
*Accept project
scope:budget
by Genentech
*City Approval of
H Concept
*Exterior
Programming
Accepted by Genentech
*Turnover lab and
vivarium DD plan
to AEI
Object AttributeRequirement
Relationship Requirement
Predicte
d value
Observed
value -2 -1 0 1 2
Product
Product Scope
Product Scope . Building Spaces includes -
Project Goals
Project Goal . Capacity (people) >= 60 - ?o
Project Goal . Cost (M$) = 70 - ?o
Building
Goal . Net Energy Use (K-
BTU/ft2) <= 250 - ?o
Building
Goal . Quality conformance
(%) >= 12 - ?o
Organization Scope
Organization Scope . Actors includes - -
Organization Goals
Organization Goal . Predicted . Cost (K$) - <= - ?o
Organization
Goal . Observed . Response
Latency (days) 3 <= - ?o
Organization
Goal . Predicted . Peak
Backlog (days) 3 <= - ?o
Organization
Goal . Predicted . rework
(FTE-days) - <= - ?o
Process
Process Goals
Process Goal . Peak Quality Risk < 0.50 - -
Process
Goal . Schedule Growth
(months) < - ?o
Process Goal . Completion Date <= 1/1/09 - ?o
Process Task . Action: Object
Process Task . Design: Actor Actor that designs
Process Task . Predict: Actor Actor that predicts
Process Task . Assess: Actor Actor that assesses
Process Task . Build: Actor Actor that builds
Function Product Behavior
Organization
Qualitative Threshhold values
4 January 2011 CEE 111/211 8
Virtual Design and Construction: fundamental method of this integrated design and analysis class
• Use of integrated multi-disciplinary computer-based performance models and analyses of design–construction projects – Product (building, device, service)
– Organization
– Work Process
• to support (explicit, public) business
objectives – Describe: Visualize and describe project
– Explain reasons for designs and choices
– Evaluate choices
– Predict project performance
*05-07-01
Finish
Final Program
Confirmation with
Pharmacology
Final Program
confirmation with LAR
KPFF
SRG Lab Task 37 Task 44 Project Mgt AEI Core Task 41 Task26 H Block Crew Task 23SRG / AEI
TechnicalAEI Core and
SRG LabHDCCO Costing
SRG
TechnicalKPFF
AEI Core
and TechHDCCO Core
Code Rev
ConsultantSolvent Tarter
H Block Crew
& Tech
SRG
Landscape
Tele Data
DesignCode Rev
Furniture
37.
*Reprogram
B#15 Shafts
34. *Finalize
Pharmacology
Program
33. *Finalize
LAR Program
32. *Finalize
Bio-Organic
Chemistry
Program
35. *Finalize
Protein Chemistry
Program 20. *Determine Scope of
package D including vivarium
changes
45. *Complete all
Basement/LAR Drawings
41. *Reprogram
bookends B#13 and
B#15
36. *Analyze
structural impacts
12. *Complete UG
utiliites
25. *Do Central Plant
design changes
19. *Determine vertical
utilities
22. *Complete catwalk drawings
52. Finalize landscape
26. *Finalize B#13 and
B#15
Exiting/architecural H
occupancy concept
*Lab and
vivarium
Programming
Complete
27. *Finalize B#13,
15 Shaft Size &
MEP Room
Locations
31.* AEI &
SRG
Determine
Design $/Time
Impact of
Change
23. *Reprogram
B#13 and B#15
Exterior Architecture
Bookend
Programming
Accepted by Genentech
Notice to proceed on
structural changes
Architect
program/MEP
oncepts
Established
By Design
Team
29. *Document
lab plan
1. *Redesign main MEP
distribution systems
SRG Management AEI Management
Genentech PM
SRG Lab Plan
Ken Mouchka
Task 27Task 38
Organization
5. *Finalize lab & Equipment
plans
Task 29
Task 28
30. *Approve
Change to
Design
Contract
21. *Prepare Plan Views for
Review of Concept w/City
39. *Finalize MEP
distribution and
section
Task4 Task22
Review 80%
documents
48. *Develop exiting
plan
49. Develop
reflected ceiling
plan
Turnover
reflected
ceiling plan to
AEI
Detailed Design 80 PC
Complete
3. Complete Tele Data Design
42. *Develop
Execution
Strategy
44. *Complete
B#14 Officing
Planning
18. *Detailed Lab
Program
Documentation
47. *Develop lab
DD plan
28. *Determine
segregation of lab
and tech space
G accept lab
equipment matrix
*Package B structural
modifications (CCD3A)
13. *Code Consultants
Review Concept for final
city Presentation
14. *HDCCO update Estimate of cost
of Program
Review skin changes w/db team
Lab Planning Program
Meetings with
Pharmacology
Lab planning Program Meeting with Protein
Chemistry
BMS Controls Meetings
(Weekly)
Lab Planning Program meeting with Bio
Organic 80% Drawing Review
Tele Data Coordination MeetingsSteel Detailing
Meetings
Genentech 80% Detailed Design
Review
Final Program
Confirmation with Officing
Weekly
Coordination
Meeting
Lab Planning Program
Meetings with Directors
50. Designate size, location of
13 MEP, teledata rooms
54. KPFF design
stairs for 13/1438. *SRG
Reprogram 13/14
interface, exiting,
stairs
43. *Changes in Steel
Forwarded to Steel
Detailers
46. *RA Furnture
Concept Complete
MEP, Teledata room design
*Design Budget &
Schedule for Changes
Approved
*Notice to proceed
with detailed design
24. *Complete B13,4 H
block occupancy
requirements on MEP
systems
17. *Risick
reprogram solvent
distribution and waste
Issue 80%
MEP CDs
(20) Incorporate
80% MEP review
comments
(19) Genentech review
80% drawings
53. Incorporate
comments, complete
Architectural detail
2. Initial redesign MEP branch
lateral distribution
G accept
13/14
Interface
*City Accept
exiting
*Package C
skin
modifications
55. KPFF design
stairs for 15/14
40. *SRG
Reprogram 15/14
interface, exiting,
stairs
B13 MEP HVAC,
conduit, piping mains
completed
MEP 80% Review
comments
incorporated
Package D and UG
addendum issued:
underground utilities,
vivarium catwalk
10. Draft Alternate means
15. Jeff reprogram HMIS
(3) *AEI design MEP
HVAC, Conduit &
piping mains B13
16. *HDCCO Determine
Schedule Impact
City Approval of
Alternate Means
for Program
8. Review Alternate
Means w/impact on LEL
and LFFH
(21-4) Finalize MEP Details,
update specs and p&ID's
(8) *Revise
MEP loads, MEP
Equipment
schedules
finalized
(13,15,16) MEP specs, P&ID's,
control sequences
Work Process
Meetings
(6) Coord B13 MEP
floor section
4. complete all Interior Architcture
*Cal OSHA Recommend
Determination of LFFH
51. Designate size, location
of 14 MEP, teledata rooms G accept
15/14
Interface
*Accept project
scope:budget
by Genentech
*City Approval of
H Concept
*Exterior
Programming
Accepted by Genentech
*Turnover lab and
vivarium DD plan
to AEI
AEC IT investment by General Contractor
Rate
Baseline
($M) Change
Revenue 100,000 22%
Cost of work 85% 85,000 -2.0%
CM, Design, GC fees 10% 10,000 2.0%
Gross Margin 5,000
Sales, G&A 2% 2,000
IT investment 1,000
Amortized costs of IT/yr 33%
Net income 3,000
Time to payback (years)
Year-1
122,000
101,260
14,640
6,100
2,440
333
3,327
3.1
3-
year
payb
ack
Object AttributeRequirement
Relationship Requirement
Predicte
d value
Observed
value -2 -1 0 1 2
Product
Product Scope
Product Scope . Building Spaces includes -
Project Goals
Project Goal . Capacity (people) >= 60 - ?o
Project Goal . Cost (M$) = 70 - ?o
Building
Goal . Net Energy Use (K-
BTU/ft2) <= 250 - ?o
Building
Goal . Quality conformance
(%) >= 12 - ?o
Organization Scope
Organization Scope . Actors includes - -
Organization Goals
Organization Goal . Predicted . Cost (K$) - <= - ?o
Organization
Goal . Observed . Response
Latency (days) 3 <= - ?o
Organization
Goal . Predicted . Peak
Backlog (days) 3 <= - ?o
Organization
Goal . Predicted . rework
(FTE-days) - <= - ?o
Process
Process Goals
Process Goal . Peak Quality Risk < 0.50 - -
Process
Goal . Schedule Growth
(months) < - ?o
Process Goal . Completion Date <= 1/1/09 - ?o
Process Task . Action: Object
Process Task . Design: Actor Actor that designs
Process Task . Predict: Actor Actor that predicts
Process Task . Assess: Actor Actor that assesses
Process Task . Build: Actor Actor that builds
Function Product Behavior
Organization
Qualitative Threshhold values
11 July 2011 Chalmers Integrated Design 9
Multidisciplinary Design and Analysis – using VDC
Disciplines:
• Architecture
• Engineering
• Construction
• Operations
Stakeholders:
• Design – build
professionals
• Owner
• Others
Design
• Virtual
• Graphical
• Object-based
Analysis
• Model-based
when possible
• Quantitative
when possible
• Multi-
Stakeholder
• Graphical
description
11 July 2011 Chalmers Integrated Design 10
Integrated design and analysis Big Ideas
• Build VDC project models early and often, before committing large money or time
• What – Objectives, Designs and Behaviors of Product, process,
organization
• How: – Detailed: to show the product, process, organization entities that
use > 10% of project time, money
– Virtual: in the computer
– Visual: multi-discipline, multi-view, for multiple stakeholders
– Integrated: relating the product, organization and process
– Objective-based: set and track explicit public objectives
11
Plus-Delta of Civil Engineering
• Provides fixed physical
assets and wealth
• High global demand for
infrastructure and
housing
• Opportunity to impact
global climate challenge
significantly
12
Plus-Delta of Civil Engineering
• Provides fixed physical
assets and wealth
• High global demand for
infrastructure and
housing
• Opportunity to impact
global climate challenge
significantly
• Low productivity
compete with other ways
to spend $
• High energy use and
rising energy costs
• Structural reliability <<
societal need (Chile)
Persson, Sustainable City of
Tomorrow
Guilllermo Gomez, PUChile
US Department of Commerce,
compiled by P. Teicholz
13
An example: Malmo, Sweden
The best example of
sustainable development in
the world:
– Best design and analysis
methods (~2000)
– Best construction
methods
– Project provides some
good data on
performance vs.
predicted
But
• Energy: 20 of 20 buildings used more than predicted
– Prefabrication needed for intended energy performance
• Land: much greater density needed even for next project
– Development model did not last even a decade
• Data granularity: so coarse that improvement difficult to plan
• Human capital: people on project mostly lost to next phase
CEE 243 March 29 14
Malmo, Sweden: Actual energy
much worse than Predicted
CEE 243 March 29 15
Malmo, Sweden: Actual energy
much worse than Predicted
Fundamental issue: outcome reliability
• Structures (Chile, post-earthquake) -- good:
– ~500K/~5M homes damaged or destroyed: <2σ
– ~4 joint failures /~100 in (collapsed) buildings: 2σ
– 4/~10,000 post-1985 buildings collapsed in major
damage area: >3σ
• Energy – not good:
– 20/20 buildings used more energy than predicted –
Malmo, Sweden, 2001 (range 70 – 340% greater)
– 121 LEED buildings use 30% more energy per
square foot than average for U.S. buildings
• Neither structure nor energy performance meets
societal needs
16
Fundamental issue: process reliability
• Structures (Chile, post-earthquake)
– ~4 joint failures /~100 in (collapsed) buildings: 2σ
• Sources of failure - infrequent but important problems:
quality of joint construction, material composition, soft story
design, asymmetrical designs
• Energy:
– ↑ prediction variability:
• ↑ Inter-tool with same designer
• ↑ Inter-consultant with same tool
– ↑ component performance variability, e.g., infiltration from
leaky building joints (Malmo)
• Structure and energy performance:
– Good (historically), but
– Neither meets societal needs
17
18
AEC Breakthrough Objectives
Practice: 2002 Objective: 2015
Schedule 1-6 y Design
~1.5 y Construct
Variance 5-100%
1 y Design
< .5 y Construct
Variance < 5%
Cost Variance 5-30% Variance < 5%
Delivered quality Large Variance
Good?
Productivity impact?
0 variance, by POE
Great, by POE
++ productivity
Safety Good Better
Sustainability Poor 25% better than 2002
Globalization Some >= 50% of supply and
sales
19
(Multiple) Predictable performance objectives:
*Changed in 2010
Controllable Process
[Conformance to plans]
Outcome
[Performance]
Product, organization,
process designs
Latency: mean <= 1; 95% within 2
working days
Safety: 0 lost hours
Coordination activity:
planned, explicit, public,
informed > 90%
Field-generated Requests for
Information: 0
Schedule: 95% on-time
performance
Facility managed
Scope: 100% of items
with > 2% of value, time,
cost or energy
Rework volume: 0 (for field
construction work); objective = 10-
20% (virtual work)
Cost: >= 95% of
budgeted items within 2%
of budgeted cost
Prediction basis: > 80%
of predictions founded
*Function (quality) conformance
(%): >= 99%
Delivered Scope: 100%
satisfaction
Design versions: 2 or
more >= 80%
Schedule conformance (%): >=
80%
*Sustainability: >75%
better energy, water,
materials, than 2002,
profitably
Staff trained in VDC: >=
4/project
Cost conformance (%): >= 95%
11 July 2011 Chalmers Integrated Design 20
Wasted human, technical, and biological resources
Photos: Courtesy SPS
Source: http://mainegov-
images.informe.org/spo/recycle/focus/midmaine/landfill.jpg
11 July 2011 Chalmers Integrated Design 21
VDC models use and require lots of tools
Organization
Project specifications Revit
Bentley
Architecture
Tekla
Structures VDT MSP P6 POP MACDADI
Product functional objectives (goals) yes yes
Product systems and components scope yes yes some names
Product behavior specification and values yes yes
Organization functional objectives (goals) yes yes
Organization responsibility for components, systems
& tasks yes
Organization scope yes names names
Organization behavior specification and values yes yes
Process Task functional objectives (scope) yes yes
Process Task scope yes yes yes names
Process behavior specification and values yes yes
Project goals and assessed goodness yes yes
Project options yes
Project preferences, qualitative threshold values yes
Product Process Integrated project
Models
11 July 2011 Chalmers Integrated Design 22
VDC analyses use and require lots of tools
Organization
Project specifications Revit
Bentley
Architecture
Tekla
Structures VDT MSP P6 POP MACDADI
Model-based analysis
Product component interference (3D) yes yes
Product cost estimation - BldgExplorer IFC
Product daylight - Ecotect gbXML
Product energy - Bentley/EDSL Tas n/a direct
Product energy - Ecotect gbXML
Product energy - Equest IFC
Product energy - GBS gbXML
Product energy - IES plugin
Product energy - Riuska IFC
Product Quantity Takeoff (QTO) yes yes
Product Rentable space yes yes
Product Structural analysis - Revit Structures direct
Product Structural analysis -Tekla yes
Project actor risk yes
Project cost yes
Project task schedule risk yes
Project Time-space conflict (4D) - Jetstream direct
Product Process Integrated project
Models
11 July 2011 Chalmers Integrated Design 23
Integrated design and analysis – using VDC –
provides
Integrating theoretical framework to
• Describe functional intent and designs
• Describe and predict engineering behaviors
• Systematically manage projects and the
business using the predictions and observed
data, to
• Achieve measurable business objectives
11 July 2011 Chalmers Integrated Design 24
POP model content: POP models help make managerial levers visible to all
• Columns:
– Functions
• Program Function, Schedule, Cost, Sustainability, ….
– Form (Scope) -- design choices
• L-B: x10
• Product forms = content of a “BIM”
– Behaviors (predicted, observed)
• Functional performance
• Cost
• Value
• Schedule
• …
• Rows
– Product
– Organization
– Process (design +
construction)
Template
11 July 2011 Chalmers Integrated Design 25
In-class exercise
• For a new-generation cell phone, define:
– Product functions: product design intent, to include
• Power
• Telephone access
• Additional services
– Product design forms: designed scope, e.g., buttons, …
– Product behaviors: observable (or estimated) performance, e.g., actual buttons = 30
– MACDADI goodness summary
• See http://www.stanford.edu/class/cee111/Labs/POPLab.htm
POP model – for your new cell phone project
Function Form Behavior
Product
Organization
Process
11 July 2011 Chalmers Integrated Design 26
Function: intent, e.g., energy, connect to cell system, microphone
Form: design choice in response to functional objectives, e.g., battery, antenna,
Behavior: Results of analysis prediction, observation or assessment, e.g., $, …
11 July 2011 Chalmers Integrated Design 27
0
0.5
1
1.5
2
2.5
3Conformance to product objectives
Rentable area (ft2)
Product Cost (K$)
Energy (KBTU/sq-ft/year)
Conformance (Actor assignment toOrganization Function) (%)
Organization Cost (K$) Actor Backlog/ Latency (days)
Safety: near-risk incidents / week
Rework volume - construction phase(%)
Schedule Conformance (Actual 1-dayschedule to look-ahead plan) (%)
Cost conformance to weekly budget (%)
MACDADI Evaluation of Relative Design Option Goodness (+ is good)
Option 1: POP V1
Option 2: POP V2
Meets all objectives
ICE to apply POP/MACDADI in an hour
• Stations and Deliverables:
– POP model
– Product sketch
– Organization model
– Process model … Gantt chart that you draw with your
favorite tool
– Owner: resolve issues; Build presentation of models for
group; show MACDADI analyses chart
– Facilitator: seek POP and VDC model consistency and
quality
• Budget
– Groups of ~6
– 40 minutes for ICE interaction
– 20 minutes for presentations, discussion
11 July 2011 Chalmers Integrated Design 28
11 July 2011 Chalmers Integrated Design 29
POP Lab and Submission-1: Build POP model of a new cell phone
Assume that your physical product has functions and forms inspired by our class exercise for a cell phone
Assume functions and designs for Organization and Process to build and sell your new version
11 July 2011 Chalmers Integrated Design 30
Use of the iRoom
• Lab etiquette
• Computer cables
• Computer use
• Cluster computer
problems
• Project your desktop or
laptop to the main
iRoom screen
• Room layout
• See Lab use guidelines
11 July 2011 Chalmers Integrated Design 31
POP model content
• Columns:
– Functions
• Program Function, Schedule, Cost, Sustainability, ….
– Scope (Forms) (design choices)
• L-B: x10
• Product forms = content of a “BIM”
– Behaviors (predicted, observed)
• Functional performance
• Cost
• Value
• Schedule
• …
• Rows
– Product
– Organization
– Process (design +
construction)
Template
11 July 2011 Chalmers Integrated Design 32
Business uses of POP models
• At a glance, identify: – Most important (e.g., top-10) Functions and Scope (Forms)
of the Product, Organization, Process?
– Metrics to measure; current predicted behaviors?
• Identify product, organization and process elements with greatest risk. For the most important or highest risks, check that: – Product forms have associated actors and tasks with risks
that compound or mitigate the product element risk;
– Organization actors have associated forms and tasks with risks that compound or mitigate the actor risk;
– Process tasks have associated actors and product forms that mitigate the product element risk, not compound it.
• Evaluate goodness of design re objectives, alternatives
11 July 2011 Chalmers Integrated Design 33
Class overview: http://www.stanford.edu/~kunz/Chalmers/
11 July 2011 Chalmers Integrated Design 34
Course Objectives
Through class lecture, discussion, laboratory exercises, reading
and a class project,
• Use Integrated Concurrent Engineering (ICE) for very rapid and
effective project design;
• Build and interpret simple descriptive models of new Product -
Organization - Process (POP) projects using the Excel-based
POP/MACDADI tool;
• Build, interpret and optimize organization and process models
using the SimVision tool;
• Create checklists for process reliability
• Create a business plan to obtain significant funding
11 July 2011 Chalmers Integrated Design 35
Course Non-objectives
• Study every system ever built
• Study every visualization/AI/design/planning
technology
• Development expertise
• Preparation for technology research
• Survey understanding only
• Excessive work
11 July 2011 Chalmers Integrated Design 36
Agenda (Approximate)
Course organization
• Instructors:
– John Kunz ([email protected])
• Office Hours: after class, and anytime my office door is
open
– Ray Levitt ([email protected])
• Office Hours: after class
• Class Schedule: 10:00 - 12:00 and 1:00 to 3:00 on Monday,
Tuesdays and Thursday
• Classes will meet in the CIFE lab, Room 292, Y2E2, Please
work in groups of about three for ICE sessions and to prepare
submissions. Please read and take assessments on your own.
• Web site: http://www.stanford.edu/~kunz/Chalmers
11 July 2011 Chalmers Integrated Design 37
Grading
• Course requires thorough preparation of discussion based on class
interactions, homework and readings.
• Each point in every class assignment has same value: one point.
• Normally,
– "A" for 90% or more of the maximum total points received by any
student.
– "B" for 90% < maximum class score <= 80%.
– "C" for 80% < maximum class score <= 70%.
• Instructor discretion: ~10% of class grade
• Grading: we will check carefully for precise, succinct response to query
questions. – You can easily get a "B" simply by answering all the questions
– Answer each subquestion.
• Teams about 3-4 in size
• Assessment (on-line) is individual
• Please send all submissions to [email protected]
11 July 2011 Chalmers Integrated Design 38
Details
• Lab login id:
• Password:
• Break at 1:30 today
• Dinner in Palo Alto: Monday
or Thursday next week?
• Field trip to San Jose?
• SimVision app for your
laptop
11 July 2011 Chalmers Integrated Design 39
11 July 2011 Chalmers Integrated Design 40
(“R Drive”)
• Create your own subdirectory under
Classes\Chalmers directory of the R drive
• Use for your lab, homework, project
– Backed up regularly
11 July 2011 Chalmers Integrated Design 41
Generic Project POP model:
Learn the meanings of all these terms
• POP lab:
• http://www.stanford.edu/
class/cee111/Labs/POP
Lab.htm
• Function
• Scope, or Form
• Behavior
• Product
• Organization
• Process
• Project
• Objective Weight
• Qualitative Threshold values
• Assessed Behavior value
• Weighted Assessment
• MACDADI Analyses
ORID +/∆ Analysis
11 July 2011 Chalmers Integrated Design 42
Level of Questions
Purpose Questions to Answer
O Objective
Level
To examine the data
To identify factual information
What do you see?
What factual statements can you make based on the data?
R Reflective
Level
To encourage connections
To encourage free flow of ideas and imagination
What surprised you?
What encouraged you?
What discouraged you?
How does this make you feel?
I Interpretive
Level
To identify patterns and determine their significance or meaning
To articulate underlying insights
What does the data tell us? What are insights for you?
What is the good news?
What are limits? What else is there to learn?
D Decisional
Level
To propose next steps
To develop an action plan
To make decisions
To experience “coming together”
What are next steps?
What decisions can we make?
What is our action plan for moving forward?
ORID +/∆: Focused Conversation and Analysis
Objective
What do you
recall seeing?
Reflective
Positive
What do you
feel positive
about?
Reflective
Negative
What do you
find negative?
Interpretive
What sense do
you make of it?
Decisional
What
agreements
can be made
now?
(c) 2010 43
11 July 2011 Chalmers Integrated Design 44
Product design forms: 3D drawing
11 July 2011 Chalmers Integrated Design 45
Product design forms: Object-Oriented 3D BIM
Modeled objects:
• Walls
• Floors
• Windows
• Doors
• Columns
Content of POP form
model
11 July 2011 Chalmers Integrated Design 46
Organization, Process Models
Model (SV)
• Organization
• (Design) work process
Simulation behavior
predictions:
• Gantt chart
• Risks
*05-07-01
Finish
Final Program
Confirmation with
Pharmacology
Final Program
confirmation with LAR
KPFF
SRG Lab Task 37 Task 44 Project Mgt AEI Core Task 41 Task26 H Block Crew Task 23SRG / AEI
TechnicalAEI Core and
SRG LabHDCCO Costing
SRG
TechnicalKPFF
AEI Core
and TechHDCCO Core
Code Rev
ConsultantSolvent Tarter
H Block Crew
& Tech
SRG
Landscape
Tele Data
DesignCode Rev
Furniture
37.
*Reprogram
B#15 Shafts
34. *Finalize
Pharmacology
Program
33. *Finalize
LAR Program
32. *Finalize
Bio-Organic
Chemistry
Program
35. *Finalize
Protein Chemistry
Program 20. *Determine Scope of
package D including vivarium
changes
45. *Complete all
Basement/LAR Drawings
41. *Reprogram
bookends B#13 and
B#15
36. *Analyze
structural impacts
12. *Complete UG
utiliites
25. *Do Central Plant
design changes
19. *Determine vertical
utilities
22. *Complete catwalk drawings
52. Finalize landscape
26. *Finalize B#13 and
B#15
Exiting/architecural H
occupancy concept
*Lab and
vivarium
Programming
Complete
27. *Finalize B#13,
15 Shaft Size &
MEP Room
Locations
31.* AEI &
SRG
Determine
Design $/Time
Impact of
Change
23. *Reprogram
B#13 and B#15
Exterior Architecture
Bookend
Programming
Accepted by Genentech
Notice to proceed on
structural changes
Architect
program/MEP
oncepts
Established
By Design
Team
29. *Document
lab plan
1. *Redesign main MEP
distribution systems
SRG Management AEI Management
Genentech PM
SRG Lab Plan
Ken Mouchka
Task 27Task 38
Organization
5. *Finalize lab & Equipment
plans
Task 29
Task 28
30. *Approve
Change to
Design
Contract
21. *Prepare Plan Views for
Review of Concept w/City
39. *Finalize MEP
distribution and
section
Task4 Task22
Review 80%
documents
48. *Develop exiting
plan
49. Develop
reflected ceiling
plan
Turnover
reflected
ceiling plan to
AEI
Detailed Design 80 PC
Complete
3. Complete Tele Data Design
42. *Develop
Execution
Strategy
44. *Complete
B#14 Officing
Planning
18. *Detailed Lab
Program
Documentation
47. *Develop lab
DD plan
28. *Determine
segregation of lab
and tech space
G accept lab
equipment matrix
*Package B structural
modifications (CCD3A)
13. *Code Consultants
Review Concept for final
city Presentation
14. *HDCCO update Estimate of cost
of Program
Review skin changes w/db team
Lab Planning Program
Meetings with
Pharmacology
Lab planning Program Meeting with Protein
Chemistry
BMS Controls Meetings
(Weekly)
Lab Planning Program meeting with Bio
Organic 80% Drawing Review
Tele Data Coordination MeetingsSteel Detailing
Meetings
Genentech 80% Detailed Design
Review
Final Program
Confirmation with Officing
Weekly
Coordination
Meeting
Lab Planning Program
Meetings with Directors
50. Designate size, location of
13 MEP, teledata rooms
54. KPFF design
stairs for 13/1438. *SRG
Reprogram 13/14
interface, exiting,
stairs
43. *Changes in Steel
Forwarded to Steel
Detailers
46. *RA Furnture
Concept Complete
MEP, Teledata room design
*Design Budget &
Schedule for Changes
Approved
*Notice to proceed
with detailed design
24. *Complete B13,4 H
block occupancy
requirements on MEP
systems
17. *Risick
reprogram solvent
distribution and waste
Issue 80%
MEP CDs
(20) Incorporate
80% MEP review
comments
(19) Genentech review
80% drawings
53. Incorporate
comments, complete
Architectural detail
2. Initial redesign MEP branch
lateral distribution
G accept
13/14
Interface
*City Accept
exiting
*Package C
skin
modifications
55. KPFF design
stairs for 15/14
40. *SRG
Reprogram 15/14
interface, exiting,
stairs
B13 MEP HVAC,
conduit, piping mains
completed
MEP 80% Review
comments
incorporated
Package D and UG
addendum issued:
underground utilities,
vivarium catwalk
10. Draft Alternate means
15. Jeff reprogram HMIS
(3) *AEI design MEP
HVAC, Conduit &
piping mains B13
16. *HDCCO Determine
Schedule Impact
City Approval of
Alternate Means
for Program
8. Review Alternate
Means w/impact on LEL
and LFFH
(21-4) Finalize MEP Details,
update specs and p&ID's
(8) *Revise
MEP loads, MEP
Equipment
schedules
finalized
(13,15,16) MEP specs, P&ID's,
control sequences
Work Process
Meetings
(6) Coord B13 MEP
floor section
4. complete all Interior Architcture
*Cal OSHA Recommend
Determination of LFFH
51. Designate size, location
of 14 MEP, teledata rooms G accept
15/14
Interface
*Accept project
scope:budget
by Genentech
*City Approval of
H Concept
*Exterior
Programming
Accepted by Genentech
*Turnover lab and
vivarium DD plan
to AEI
11 July 2011 Chalmers Integrated Design 47
Integrated Concurrent Engineering (ICE)
Given
• Objective = “extreme collaboration”
(1 week)
• Excellent POP software
• Collocated team
• iRoom
• Good generic POP model
• SD (DD) phase
Performance change
XC
Good
traditio
nal
Latency
(secs)0
20000
40000
60000
Latency (secs)
Duration (days)
XC
Good traditional
0
50
100
150
200
250
300
Duration
Templates and checklists
Templates: standard
representations
• POP model: Function,
Form, Behavior of P, O, P
• Breakdown structures:
– Product
– Organization
– Process
• Task content: object,
action, resources (crew,
equipment)
Checklists: Tasks and OK
that was done well
• Run ICE sessions
• Create POP models
• Process to define project,
build BIM, exchange
data, do analyses (x5)
11 July 2011 Chalmers Integrated Design 48
Example Checklist Step in detailed
schedule Checks to make
before start of step
11 July 2011 Chalmers Integrated Design 50
How we spend time in meetings
DESCRIPTIVE (40%)
• When do we have access to
Area C?
• What wall sections do these
numbers refer to?
• Where are you placing the
crane?
EXPLANATIVE
(20%)
What drives the finish
times for the rides?
PREDICTIVE (10%)
Can we get access to the
lagoon a week earlier?
EVALUATIVE (30%)
Does this milestone
meet contract?
Submission-1: due midnight Tuesday
Task: describe and analyze your project and organization design
Submit a PowerPoint deck (group submission):
• Organization functional intent (POP function model
• Organization design (POP form and SimVision project baseline case
model); … annotated
• Predicted organization behavior .. SimVision predicted case
comparison charts
• Case comparison: Project Design Worksheet (page 3 lab)
• ORID analysis on what you learned this week
11 July 2011 Chalmers Integrated Design 51
11 July 2011 Chalmers Integrated Design 52
Skills for success
• Good engineer: design, analyze, manage
• Research methods
• Communication
– Written/Oral
– Programming
– Colleagues, sponsors, stakeholders
• Integrated use of quick-response, careful
analysis, reflection
11 July 2011 Chalmers Integrated Design 53
Speculations: VDC
Symbolic Model • Objectives • Testing • Representation • Reasoning • User Interfaces • Systems Interfaces
Pro
ject P
hase
Discipline
VDC will enable a small number of collaborating stakeholders
to do rapid Multidisciplinary Design and Analysis
11 July 2011 Chalmers Integrated Design 54
Monday Learning goals
• Get basic familiarity with the POP project framework of
VDC
• Product – Organization – Process (POP)
• Function – Form – Behavior (FFB)
• Understand class organization, opportunities, methods
and expectations
• Motivate interest in Integrated Design enabled by
VDC:
• Opportunities in practice
• Fun, power and job opportunities of models, model-
based analyses
11 July 2011 Chalmers Integrated Design 55
2011?, … 2015?
2011?, … 2015?
What do you have? … What do you want?
11 July 2011 Chalmers Integrated Design 56
This week overview
Day Take-home
Monday Introduction:
Theory: integrated multi-disciplinary models and
analyses and multi-disciplinary Integrated Concurrent
Engineering;
Practice: lab; ICE session
Tuesday Theory: methods we now use to design organizations
as we design bridges;
Practice: lab
Thursday Theory: methods of integrated POP design and
analysis
Practice: initial presentations Object AttributeRequirement
Relationship Requirement
Predicte
d value
Observed
value -2 -1 0 1 2
Product
Product Scope
Product Scope . Building Spaces includes -
Project Goals
Project Goal . Capacity (people) >= 60 - ?o
Project Goal . Cost (M$) = 70 - ?o
Building
Goal . Net Energy Use (K-
BTU/ft2) <= 250 - ?o
Building
Goal . Quality conformance
(%) >= 12 - ?o
Organization Scope
Organization Scope . Actors includes - -
Organization Goals
Organization Goal . Predicted . Cost (K$) - <= - ?o
Organization
Goal . Observed . Response
Latency (days) 3 <= - ?o
Organization
Goal . Predicted . Peak
Backlog (days) 3 <= - ?o
Organization
Goal . Predicted . rework
(FTE-days) - <= - ?o
Process
Process Goals
Process Goal . Peak Quality Risk < 0.50 - -
Process
Goal . Schedule Growth
(months) < - ?o
Process Goal . Completion Date <= 1/1/09 - ?o
Process Task . Action: Object
Process Task . Design: Actor Actor that designs
Process Task . Predict: Actor Actor that predicts
Process Task . Assess: Actor Actor that assesses
Process Task . Build: Actor Actor that builds
Function Product Behavior
Organization
Qualitative Threshhold values
Integrated Product, Organization and Process
design
John Kunz
The big idea: Integrated Product, Organization and Process design can support, at least design, fabrication and assembly
Rate
Baseline
($K) Change
Year-1
(K$)
Revenue 100,000 2% 102,000
Cost of contracted work 85% 85,000 -2.0% 84,660
Cost of self-performed work 10% 10,000 2.0% 12,240
Gross Margin 5,000 5,100
Sales, G&A 2% 2,000 2,040
IT investment 70
Amortized costs of IT/yr 33% 23
Net income 3,000 3,037
Time to payback (years) 1.9
Net Income change (%) 1.2
*05-07-01
Finish
Final Program
Confirmation with
Pharmacology
Final Program
confirmation with LAR
KPFF
SRG Lab Task 37 Task 44 Project Mgt AEI Core Task 41 Task26 H Block Crew Task 23SRG / AEI
TechnicalAEI Core and
SRG LabHDCCO Costing
SRG
TechnicalKPFF
AEI Core
and TechHDCCO Core
Code Rev
ConsultantSolvent Tarter
H Block Crew
& Tech
SRG
Landscape
Tele Data
DesignCode Rev
Furniture
37.
*Reprogram
B#15 Shafts
34. *Finalize
Pharmacology
Program
33. *Finalize
LAR Program
32. *Finalize
Bio-Organic
Chemistry
Program
35. *Finalize
Protein Chemistry
Program 20. *Determine Scope of
package D including vivarium
changes
45. *Complete all
Basement/LAR Drawings
41. *Reprogram
bookends B#13 and
B#15
36. *Analyze
structural impacts
12. *Complete UG
utiliites
25. *Do Central Plant
design changes
19. *Determine vertical
utilities
22. *Complete catwalk drawings
52. Finalize landscape
26. *Finalize B#13 and
B#15
Exiting/architecural H
occupancy concept
*Lab and
vivarium
Programming
Complete
27. *Finalize B#13,
15 Shaft Size &
MEP Room
Locations
31.* AEI &
SRG
Determine
Design $/Time
Impact of
Change
23. *Reprogram
B#13 and B#15
Exterior Architecture
Bookend
Programming
Accepted by Genentech
Notice to proceed on
structural changes
Architect
program/MEP
oncepts
Established
By Design
Team
29. *Document
lab plan
1. *Redesign main MEP
distribution systems
SRG Management AEI Management
Genentech PM
SRG Lab Plan
Ken Mouchka
Task 27Task 38
Organization
5. *Finalize lab & Equipment
plans
Task 29
Task 28
30. *Approve
Change to
Design
Contract
21. *Prepare Plan Views for
Review of Concept w/City
39. *Finalize MEP
distribution and
section
Task4 Task22
Review 80%
documents
48. *Develop exiting
plan
49. Develop
reflected ceiling
plan
Turnover
reflected
ceiling plan to
AEI
Detailed Design 80 PC
Complete
3. Complete Tele Data Design
42. *Develop
Execution
Strategy
44. *Complete
B#14 Officing
Planning
18. *Detailed Lab
Program
Documentation
47. *Develop lab
DD plan
28. *Determine
segregation of lab
and tech space
G accept lab
equipment matrix
*Package B structural
modifications (CCD3A)
13. *Code Consultants
Review Concept for final
city Presentation
14. *HDCCO update Estimate of cost
of Program
Review skin changes w/db team
Lab Planning Program
Meetings with
Pharmacology
Lab planning Program Meeting with Protein
Chemistry
BMS Controls Meetings
(Weekly)
Lab Planning Program meeting with Bio
Organic 80% Drawing Review
Tele Data Coordination MeetingsSteel Detailing
Meetings
Genentech 80% Detailed Design
Review
Final Program
Confirmation with Officing
Weekly
Coordination
Meeting
Lab Planning Program
Meetings with Directors
50. Designate size, location of
13 MEP, teledata rooms
54. KPFF design
stairs for 13/1438. *SRG
Reprogram 13/14
interface, exiting,
stairs
43. *Changes in Steel
Forwarded to Steel
Detailers
46. *RA Furnture
Concept Complete
MEP, Teledata room design
*Design Budget &
Schedule for Changes
Approved
*Notice to proceed
with detailed design
24. *Complete B13,4 H
block occupancy
requirements on MEP
systems
17. *Risick
reprogram solvent
distribution and waste
Issue 80%
MEP CDs
(20) Incorporate
80% MEP review
comments
(19) Genentech review
80% drawings
53. Incorporate
comments, complete
Architectural detail
2. Initial redesign MEP branch
lateral distribution
G accept
13/14
Interface
*City Accept
exiting
*Package C
skin
modifications
55. KPFF design
stairs for 15/14
40. *SRG
Reprogram 15/14
interface, exiting,
stairs
B13 MEP HVAC,
conduit, piping mains
completed
MEP 80% Review
comments
incorporated
Package D and UG
addendum issued:
underground utilities,
vivarium catwalk
10. Draft Alternate means
15. Jeff reprogram HMIS
(3) *AEI design MEP
HVAC, Conduit &
piping mains B13
16. *HDCCO Determine
Schedule Impact
City Approval of
Alternate Means
for Program
8. Review Alternate
Means w/impact on LEL
and LFFH
(21-4) Finalize MEP Details,
update specs and p&ID's
(8) *Revise
MEP loads, MEP
Equipment
schedules
finalized
(13,15,16) MEP specs, P&ID's,
control sequences
Work Process
Meetings
(6) Coord B13 MEP
floor section
4. complete all Interior Architcture
*Cal OSHA Recommend
Determination of LFFH
51. Designate size, location
of 14 MEP, teledata rooms G accept
15/14
Interface
*Accept project
scope:budget
by Genentech
*City Approval of
H Concept
*Exterior
Programming
Accepted by Genentech
*Turnover lab and
vivarium DD plan
to AEI
Object AttributeRequirement
Relationship Requirement
Predicte
d value
Observed
value -2 -1 0 1 2
Product
Product Scope
Product Scope . Building Spaces includes -
Project Goals
Project Goal . Capacity (people) >= 60 - ?o
Project Goal . Cost (M$) = 70 - ?o
Building
Goal . Net Energy Use (K-
BTU/ft2) <= 250 - ?o
Building
Goal . Quality conformance
(%) >= 12 - ?o
Organization Scope
Organization Scope . Actors includes - -
Organization Goals
Organization Goal . Predicted . Cost (K$) - <= - ?o
Organization
Goal . Observed . Response
Latency (days) 3 <= - ?o
Organization
Goal . Predicted . Peak
Backlog (days) 3 <= - ?o
Organization
Goal . Predicted . rework
(FTE-days) - <= - ?o
Process
Process Goals
Process Goal . Peak Quality Risk < 0.50 - -
Process
Goal . Schedule Growth
(months) < - ?o
Process Goal . Completion Date <= 1/1/09 - ?o
Process Task . Action: Object
Process Task . Design: Actor Actor that designs
Process Task . Predict: Actor Actor that predicts
Process Task . Assess: Actor Actor that assesses
Process Task . Build: Actor Actor that builds
Function Product Behavior
Organization
Qualitative Threshhold values