Organics Waste Processing Facility Construction Progress Update May 12, 2011
Organics Waste Processing Facility Construction Progress Update January 17, 2011.
-
date post
19-Dec-2015 -
Category
Documents
-
view
216 -
download
0
Transcript of Organics Waste Processing Facility Construction Progress Update January 17, 2011.
![Page 1: Organics Waste Processing Facility Construction Progress Update January 17, 2011.](https://reader036.fdocuments.net/reader036/viewer/2022062516/56649d2f5503460f94a076f3/html5/thumbnails/1.jpg)
Organics Waste Processing Facility Construction Progress Update
January 17, 2011
![Page 2: Organics Waste Processing Facility Construction Progress Update January 17, 2011.](https://reader036.fdocuments.net/reader036/viewer/2022062516/56649d2f5503460f94a076f3/html5/thumbnails/2.jpg)
Organics Waste Processing Facility Construction Progress Update
January 17, 2011
T tunnel wall along Gridline 6 and V with cold weather protection
![Page 3: Organics Waste Processing Facility Construction Progress Update January 17, 2011.](https://reader036.fdocuments.net/reader036/viewer/2022062516/56649d2f5503460f94a076f3/html5/thumbnails/3.jpg)
Organics Waste Processing Facility Construction Progress Update
January 17, 2011
Veneer brick installation for Administration Building
![Page 4: Organics Waste Processing Facility Construction Progress Update January 17, 2011.](https://reader036.fdocuments.net/reader036/viewer/2022062516/56649d2f5503460f94a076f3/html5/thumbnails/4.jpg)
Organics Waste Processing Facility Construction Progress Update
January 17, 2011
Scaffolds for brick veneer installation around Administration Building
![Page 5: Organics Waste Processing Facility Construction Progress Update January 17, 2011.](https://reader036.fdocuments.net/reader036/viewer/2022062516/56649d2f5503460f94a076f3/html5/thumbnails/5.jpg)
Organics Waste Processing Facility Construction Progress Update
January 17, 2011
Administration building taking shape
![Page 6: Organics Waste Processing Facility Construction Progress Update January 17, 2011.](https://reader036.fdocuments.net/reader036/viewer/2022062516/56649d2f5503460f94a076f3/html5/thumbnails/6.jpg)
Organics Waste Processing Facility Construction Progress Update
January 17, 2011
Frame installation for pre-engineered building over tunnels begins
![Page 7: Organics Waste Processing Facility Construction Progress Update January 17, 2011.](https://reader036.fdocuments.net/reader036/viewer/2022062516/56649d2f5503460f94a076f3/html5/thumbnails/7.jpg)
Organics Waste Processing Facility Construction Progress Update
January 17, 2011
Frame installation for pre-engineered building over tunnels
![Page 8: Organics Waste Processing Facility Construction Progress Update January 17, 2011.](https://reader036.fdocuments.net/reader036/viewer/2022062516/56649d2f5503460f94a076f3/html5/thumbnails/8.jpg)
Organics Waste Processing Facility Construction Progress Update
January 17, 2011
Frame installation for pre-engineered building over tunnels nearly completed