Operations and Supply Chain...

16
1/29/2017 1 Managing Projects Chapter 14 Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 14 - 2 Chapter Objectives Be able to: Explain the difference between routine business activities and projects. Describe the five major phases of a project. Construct a Gantt chart and interpret the results. Construct a project network diagram and calculate the earliest and latest start and finish times for all activities. Identify the critical activities and paths in a network. Crash a project.

Transcript of Operations and Supply Chain...

Page 1: Operations and Supply Chain Strategiespmk3153.weebly.com/uploads/9/0/7/4/90746065/bozarth_opscm3_pp…Project Management ... Responsibilities given to middle managers have been ...

1/29/2017

1

Managing Projects

Chapter 14

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 14 - 2

Chapter Objectives

Be able to: Explain the difference between routine business activities and

projects. Describe the five major phases of a project. Construct a Gantt chart and interpret the results. Construct a project network diagram and calculate the earliest

and latest start and finish times for all activities. Identify the critical activities and paths in a network. Crash a project.

Page 2: Operations and Supply Chain Strategiespmk3153.weebly.com/uploads/9/0/7/4/90746065/bozarth_opscm3_pp…Project Management ... Responsibilities given to middle managers have been ...

1/29/2017

2

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 14 - 3

Project

Project – A temporary endeavor undertaken to create a unique product, service, or result.

Projects have clear starting and ending points after which

the people and resources dedicated to the project are reassigned.

Projects are non-routine, can be large or small, and may be difficult to manage.

Projects typically require significant levels of cross-functional and interorganizational coordination.

© 2008 Project Management Institute

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 14 - 4

Project Management

Project Management – The application of knowledge, skills, tools, and techniques to project activities to meet project requirements. © 2008 Project Management Institute

Page 3: Operations and Supply Chain Strategiespmk3153.weebly.com/uploads/9/0/7/4/90746065/bozarth_opscm3_pp…Project Management ... Responsibilities given to middle managers have been ...

1/29/2017

3

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 14 - 5

Project Management Trends

The faster pace of strategic change

New product lines are introduced more often to fight off competitors.

Information technology solutions become quickly out-of-date.

Customer and supplier networks quickly change.

The changing role of middle management

The role has decreased due to more advanced information systems handling many of the tasks.

Responsibilities given to middle managers have been pushed down to supervisors and employees.

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 14 - 6

Project Phases

Concept phase

Project definition phase

Planning phase

Performance phase

Postcompletion phase

Figure 14.1

Page 4: Operations and Supply Chain Strategiespmk3153.weebly.com/uploads/9/0/7/4/90746065/bozarth_opscm3_pp…Project Management ... Responsibilities given to middle managers have been ...

1/29/2017

4

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 14 - 7

Project Phases

Concept Phase Broad definition and scope

Budget estimates within 30%

Project definition Phase

Tentative schedules and budgets, organization, key personnel and resource requirements

Budget estimates refined within 5% to 10%

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 14 - 8

Project Phases

Planning phase Detailed plans, timing, budgets and resources Milestones

Project management tools and techniques

Performance phase Execution and control

Postcompletion phase “Wrap-up” Reassignment of project resources

Page 5: Operations and Supply Chain Strategiespmk3153.weebly.com/uploads/9/0/7/4/90746065/bozarth_opscm3_pp…Project Management ... Responsibilities given to middle managers have been ...

1/29/2017

5

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 14 - 9

Project Management Tools

Gantt charts – Graphical tools used to show expected start and end times for project activities and to track actual progress against these time targets.

Network diagrams – Graphical tools that show the logical linkages between activities in a project.

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 14 - 10

Gantt Charts

Activities can occur simultaneously and some have predecessors that must be completed beforehand.

Table 14.2

Page 6: Operations and Supply Chain Strategiespmk3153.weebly.com/uploads/9/0/7/4/90746065/bozarth_opscm3_pp…Project Management ... Responsibilities given to middle managers have been ...

1/29/2017

6

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 14 - 11

Gantt Charts

Shows that the project should be completed by the end of Week 18 and when specific activities should

start and finish.

Figure 14.2

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 14 - 12

Network Diagrams

Critical-path method – A network-based technique in which there is a single time estimate for each activity.

Program evaluation and review technique (PERT) – A network-based technique in which there are multiple time estimates for each activity.

Page 7: Operations and Supply Chain Strategiespmk3153.weebly.com/uploads/9/0/7/4/90746065/bozarth_opscm3_pp…Project Management ... Responsibilities given to middle managers have been ...

1/29/2017

7

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 14 - 13

Constructing a Network Diagram

Identify each unique activity in a project by a capital letter that corresponds only to that activity.

Represent each activity in the project by a node that shows the estimate length. (Activity on node (AON) diagram.)

If an activity has an immediate predecessor(s), show the relationship by connecting the two activities with an arrow.

Determine the earliest start time (ES) and earliest finish time (EF) for each activity by performing a forward pass.

Determine the latest finish time (LF) and latest starting time (LS) for each activity by doing a backward pass.

Determine the critical activities and path(s) in the project.

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 14 - 14

Network Diagrams

Critical path – A network path that has the longest, or is tied for the longest, linked sequence of activities.

Project duration – The duration of a project is equal to the duration of the critical path.

Network path – A logically linked sequence of activities in a network diagram.

Critical activities – Project activities for which the earliest start time and latest start time are equal.

Page 8: Operations and Supply Chain Strategiespmk3153.weebly.com/uploads/9/0/7/4/90746065/bozarth_opscm3_pp…Project Management ... Responsibilities given to middle managers have been ...

1/29/2017

8

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 14 - 15

AON Example – Gina3000

Use the following data to develop a network diagram:

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 14 - 16

AON Example – Gina3000

Network Diagram

Figure 14.4

Page 9: Operations and Supply Chain Strategiespmk3153.weebly.com/uploads/9/0/7/4/90746065/bozarth_opscm3_pp…Project Management ... Responsibilities given to middle managers have been ...

1/29/2017

9

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 14 - 17

AON Example – Gina3000

Identify the Paths: ACFGJ

ACDEGJ

ACDEHJ

ACDEIJ

BCFGJ

BCDEGJ

BCDEHJ

BCDEIJ

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 14 - 18

AON Times and Slack

Earliest Start Time (ES)

= Latest EF for all immediate predecessors

Earliest Finish Time (EF)

= ES + activity’s duration

Latest Start Time (LS)

= LF – activity’s duration

Latest Finish Time (LF)

= Earliest LS for all immediate successors

Slack = amount of allowable delay in an activity

= Equal to LS – ES or LF – EF for an activity

Page 10: Operations and Supply Chain Strategiespmk3153.weebly.com/uploads/9/0/7/4/90746065/bozarth_opscm3_pp…Project Management ... Responsibilities given to middle managers have been ...

1/29/2017

10

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 14 - 19

AON Example – Gina 3000

Calculate Earliest Start and Earliest Finish Times

Table 14.3

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 14 - 20

AON Example – Gina 3000

Calculate Latest Start and Latest Finish Times Table 14.4

Page 11: Operations and Supply Chain Strategiespmk3153.weebly.com/uploads/9/0/7/4/90746065/bozarth_opscm3_pp…Project Management ... Responsibilities given to middle managers have been ...

1/29/2017

11

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 14 - 21

AON Example – Gina 3000

Identify the Critical Path(s) ACFGJ = 13 weeks

ACDEGJ = 17 weeks

ACDEHJ = 17 weeks

ACDEIJ = 17 weeks

BCFGJ = 14 weeks

BCDEGJ = 18 weeks

BCDEHJ = 18 weeks

BCDEIJ = 18 weeks

The activities in these critical paths have no slack.

The project should be completed

in 18 weeks.

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 14 - 22

Crashing a Project

Crashing a Project – Shortening the overall duration of a project by reducing the time it takes to perform certain activities. List all network paths and their current lengths and mark all activities

that can be crashed.

Focus on the critical path or paths. Working one period at a time, choose the activity or activities that will shorten all critical paths at the least cost. The one rule is this: Never shorten an activity that is not on a critical path, regardless of the cost. Doing so will not shorten the project; it will only add costs.

Recalculate the lengths of all paths and repeat step 2 until the target project completion is reached or until all options have been exhausted.

Page 12: Operations and Supply Chain Strategiespmk3153.weebly.com/uploads/9/0/7/4/90746065/bozarth_opscm3_pp…Project Management ... Responsibilities given to middle managers have been ...

1/29/2017

12

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 14 - 23

Crashing Example 14.3 Courter Corporation

Use the following data to develop a schedule to complete the project within 23 weeks:

Table 14.5

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 14 - 24

Crashing Example 14.3 Courter Corporation

Network Diagram:

Figure 14.6

Page 13: Operations and Supply Chain Strategiespmk3153.weebly.com/uploads/9/0/7/4/90746065/bozarth_opscm3_pp…Project Management ... Responsibilities given to middle managers have been ...

1/29/2017

13

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 14 - 25

Crashing Example 14.3 Courter Corporation

Calculate ES, EF, LS, and LF for each activity

* Critical Activity Note: Critical Activities have a Slack = 0 Table 14.6

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 14 - 26

Crashing Example 14.3 Courter Corporation

Network Paths for the Project

ABEFGK – 25 weeks

ACDFGK – 24 weeks

AHIJ – 19 weeks

Page 14: Operations and Supply Chain Strategiespmk3153.weebly.com/uploads/9/0/7/4/90746065/bozarth_opscm3_pp…Project Management ... Responsibilities given to middle managers have been ...

1/29/2017

14

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 14 - 27

Crashing Example 14.3 Courter Corporation

Choose the activity(s) that will shorten all critical path(s) at the least cost:

ABEFGK – 25 weeks

• Activity B - shorten 1 week at a cost of $500

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 14 - 28

Crashing Example 14.3 Courter Corporation

Updated Network Paths for the Project

ABEFGK – 24 weeks

ACDFGK – 24 weeks

AHIJ – 19 weeks

Crashing cost: $500

Page 15: Operations and Supply Chain Strategiespmk3153.weebly.com/uploads/9/0/7/4/90746065/bozarth_opscm3_pp…Project Management ... Responsibilities given to middle managers have been ...

1/29/2017

15

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 14 - 29

Crashing Example 14.3 Courter Corporation

Choose the activity(s) that will shorten all critical path(s) at the least cost:

ABEFGK – 24 weeks

ACDFGK – 24 weeks

• Activity G - shorten 1 week at a cost of $700

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 14 - 30

Crashing Example 14.3 Courter Corporation

Updated Network Paths for the Project

ABEFGK – 23 weeks

ACDFGK – 23 weeks

AHIJ – 19 weeks

Crashing Cost = $500 + $700 = $1200

Page 16: Operations and Supply Chain Strategiespmk3153.weebly.com/uploads/9/0/7/4/90746065/bozarth_opscm3_pp…Project Management ... Responsibilities given to middle managers have been ...

1/29/2017

16

Copyright © 2013 Pearson Education, Inc. publishing as Prentice Hall 14 - 31

Project Management Resources

Project Management Software

Microsoft Project

PMI (Project Management Institute)

Sponsors education and certification Sponsors conferences, research, user groups Publishes Guide to the Project Management Body of

Knowledge (PMBOK®)

PMBOK® Part I: Various business processes for projects Part II: Nine project management knowledge areas