Operational experience with interlock systems during 3MeV commissioning phase
description
Transcript of Operational experience with interlock systems during 3MeV commissioning phase
![Page 1: Operational experience with interlock systems during 3MeV commissioning phase](https://reader036.fdocuments.net/reader036/viewer/2022062814/568166ba550346895ddac143/html5/thumbnails/1.jpg)
C O M M I S S I O N I N G A N D M E A S U R E M E N T S
OPERATIONAL EXPERIENCE WITH INTERLOCK
SYSTEMS DURING 3MEV COMMISSIONING PHASE
![Page 2: Operational experience with interlock systems during 3MeV commissioning phase](https://reader036.fdocuments.net/reader036/viewer/2022062814/568166ba550346895ddac143/html5/thumbnails/2.jpg)
45 KEV TO 3 MEV
ion source
RFQ
chopper line
Diagnostics line
spectrometer
beam dump
source : 45 keVLEBT 2
solenoids, 2 steerers
Beam currentBeam profileSlit and grid emitt (temporary)
RFQ : 3 MeV MEBT
11 quads3 bunchers2 choppers
Beam current at 2 locations
Wire scanners
![Page 3: Operational experience with interlock systems during 3MeV commissioning phase](https://reader036.fdocuments.net/reader036/viewer/2022062814/568166ba550346895ddac143/html5/thumbnails/3.jpg)
MOVABLE DIAGNOSTIC BENCH
Low energy bench (up to 12 MeV)
Spectrometer (0.2 %)Slit and Grid EmittanceToF (calibration)Bunch Shape MonitorHalo Monitor (chopping eff.)
![Page 4: Operational experience with interlock systems during 3MeV commissioning phase](https://reader036.fdocuments.net/reader036/viewer/2022062814/568166ba550346895ddac143/html5/thumbnails/4.jpg)
TRANSMISSION VS. RF POWERFOR DIFFERENT PRESSURE IN THE LEBT (NEUTRALISATION)
![Page 5: Operational experience with interlock systems during 3MeV commissioning phase](https://reader036.fdocuments.net/reader036/viewer/2022062814/568166ba550346895ddac143/html5/thumbnails/5.jpg)
TRANSVERSE EMITTANCE-DIRECT
Yellow = measured, pink = simulations
![Page 6: Operational experience with interlock systems during 3MeV commissioning phase](https://reader036.fdocuments.net/reader036/viewer/2022062814/568166ba550346895ddac143/html5/thumbnails/6.jpg)
LONG EMITTANCE -INDIRECT
BU.1 fixed
BU.2 varying BU.3 OFF
BSM
MeasurementReconstruction
RFQ
1000 1500 2000 2500 3000 3500 400010
15
20
25
30
35
40
45
Beam RMS phase vs Cavity amplitude
MeasurementsSimulationReconstructed
Buncher 2 Amplitude (A.U.)
Beam
RM
S ph
ase
(°)
![Page 7: Operational experience with interlock systems during 3MeV commissioning phase](https://reader036.fdocuments.net/reader036/viewer/2022062814/568166ba550346895ddac143/html5/thumbnails/7.jpg)
Expected : 21 keVReconstructed : 22 keV
Reconstruction technique and diagnostic performance were validated !
LONG EMITTANCE -INDIRECT
![Page 8: Operational experience with interlock systems during 3MeV commissioning phase](https://reader036.fdocuments.net/reader036/viewer/2022062814/568166ba550346895ddac143/html5/thumbnails/8.jpg)
Micro-bunches are shifted in the phase space by a voltage applied between two plates. Relatively low voltage to allow for short rise/fall time.Shift transferred in the real space at the dump – Appropriate phase advance.
Chopper principle
![Page 9: Operational experience with interlock systems during 3MeV commissioning phase](https://reader036.fdocuments.net/reader036/viewer/2022062814/568166ba550346895ddac143/html5/thumbnails/9.jpg)
The chopper is working
0 50 100 150 2000
1
2
3
4measurement 14.05.2013 simulations chopper off
simulations chopper on measurements 14.5.2013
L4L.QFC.03130 (A)
BC
T.04
040
(mA
)
Fall and rise time < 10 ns !
The chopper line dynamics is validated !
![Page 10: Operational experience with interlock systems during 3MeV commissioning phase](https://reader036.fdocuments.net/reader036/viewer/2022062814/568166ba550346895ddac143/html5/thumbnails/10.jpg)
THE BIS
BIS was connected only in the tunnel
It always worked when it was supposed to be
We got a demo and we understand how it works and we know how to read the tables (personally I find colour coding a bit tricky)
Most of the signals were connected to the BIS
Watchdog was connected only the last day
Sometime during the commissioning phase we need to allow for losses but….
![Page 11: Operational experience with interlock systems during 3MeV commissioning phase](https://reader036.fdocuments.net/reader036/viewer/2022062814/568166ba550346895ddac143/html5/thumbnails/11.jpg)
ON DECEMBER 12 AT 16:30 A SEVERE VACUUM LEAK WAS OBSERVED IN THE MEBT LINE. IT WAS LOCATED ON THE BELLOW DOWNSTREAM THE FIRST
BUNCHER CAVITY, ON THE LEFT SIDE WHEN LOOKING DOWN THE BEAM LINE.
![Page 12: Operational experience with interlock systems during 3MeV commissioning phase](https://reader036.fdocuments.net/reader036/viewer/2022062814/568166ba550346895ddac143/html5/thumbnails/12.jpg)
![Page 13: Operational experience with interlock systems during 3MeV commissioning phase](https://reader036.fdocuments.net/reader036/viewer/2022062814/568166ba550346895ddac143/html5/thumbnails/13.jpg)
BEAM IS FIRST SUSPECT
beam Beam current 12.5mAPulse length 300us, 1Hz
Misalignment at the RFQ output Xc=0.67mm yc=-0.35mmX’c=6mrad y’c=-11mrad
LEBT solenoids AQN to be set L4L.SNB.01050 87.01632L4L.SNB.01170 114.571488
MEBT quadrupoles AQN to be set
L4L.MQD.3110 (Q1) 147.2585251L4L.MQF.3210 (Q2) 0L4L.MQD.3310 (Q3) 0L4L.MQF.3410 -52.60076696L4L.MQF.3510 -46.48494016 L4L.MQD.3610 176.6553191L4L.MQF.3710 -119.998277L4L.MQD.3810 35.875L4L.MQF.3910 -31.47315951L4L.MQD.4010 54.05899705 L4L.MQF.4110 -52.24188791
![Page 14: Operational experience with interlock systems during 3MeV commissioning phase](https://reader036.fdocuments.net/reader036/viewer/2022062814/568166ba550346895ddac143/html5/thumbnails/14.jpg)
BEAM GOING INTO THE PAPER, SCRAPING ON THE LEFT SIDE . 16% LOST ON THE BELLOW
![Page 15: Operational experience with interlock systems during 3MeV commissioning phase](https://reader036.fdocuments.net/reader036/viewer/2022062814/568166ba550346895ddac143/html5/thumbnails/15.jpg)
CONFIRMED BY CESARE ! Angle a(deg)
Scaled energy deposition Ed(J/cm3/pulse)
Approximate DT (ºC/pulse)
1 174.52 46.76
5 871.56 233.54
10 1736.48 465.30
15 2588.19 693.52
20 3420.20 916.46
30 5000.00 1339.77
40 6427.88 1722.38
45 7071.07 1894.73
50 7660.44 2052.65
60 8660.25 2320.56
70 9396.93 2517.95
80 9848.08 2638.84
90 10000.00 2679.55
![Page 16: Operational experience with interlock systems during 3MeV commissioning phase](https://reader036.fdocuments.net/reader036/viewer/2022062814/568166ba550346895ddac143/html5/thumbnails/16.jpg)
COMBINATION OF UNLIKELY BUT POSSIBLE EVENTS
• A severe misalignment between the RFQ and the MEBT that was not present at the 3 MeV test stand and was later confirmed by survey
• An optic that favoured amplification of this misalignment whilst focusing the beam to sub mm size in the other direction
• A phase advance such that the loss occurred on the “wave” (or lip) of the bellow which is only 200 microns thick and it is an aperture limitation (25.1 mm vs 28 mm of adjacent vacuum chamber).
![Page 17: Operational experience with interlock systems during 3MeV commissioning phase](https://reader036.fdocuments.net/reader036/viewer/2022062814/568166ba550346895ddac143/html5/thumbnails/17.jpg)
ACTIONS • RFQ_MEBT were realigned . Add a protection on each jack in order to
prevent any manipulation of the alignment screw and ask SURVEY for a smoothing before new beam for the next diagnostic line positions
• That any measurement with settings that are very far from nominal should be firstly thoroughly simulated and done over few shots if they generate losses. Settings which generate losses should be allowed only in exceptional circumstances and in presence of the supervisor.
• The bellows are a point of weakness and their bore aperture should never be smaller than the adjacent vacuum chamber. It is proposed that all the bellows that don’t satisfy this criterion are progressively replaced at a convenient time. A protection of the bellow could also be put in place.
![Page 18: Operational experience with interlock systems during 3MeV commissioning phase](https://reader036.fdocuments.net/reader036/viewer/2022062814/568166ba550346895ddac143/html5/thumbnails/18.jpg)
7.000 8.000 9.000 10.000 11.000 12.000 13.000 14.000 15.000 16.000
-2-1.8-1.6-1.4-1.2
-1-0.8-0.6-0.4-0.2
00.20.40.60.8
11.21.41.61.8
2 L4 lissage radiale 3MeV
Ecarts lors de la mesureEcarts après alignement
Dcum (m)
dR (
mm
)
LEBT RFQ MEBT
sens faisceau; écarts "+" vers le passage