Northfield 3rd Business and Industrial Park
Purpose:
• Present project background and planning process.
• Review preferred master plans and receive community input
We want to know what you think! Please ask questions and fill out a comment card!
Thank you!
Welcome!Open House
Thursday, September 23, 2010
Northfield 3rd Business and Industrial Park
Establishing the Need for Master Plan
Northfield 3rd Business and Industrial Park
Site Selection
Northfield 3rd Business and Industrial Park
Infrastructure Planning
Northfield 3rd Business and Industrial Park
Distinctive character…Future development needs to “fit”Northfield
• Appropriate scale and character • Supportive, not competitive with downtown• Sustainable• Mix of uses• Take advantage of intellectual capital
Northfield 3rd Business and Industrial Park
Site Analysis
530 Acres
450 Acres
4 Landowners
2 Landowners
Northfield 3rd Business and Industrial Park
North and South Sites – 980 acres total
Growth since 1990
Northfield 3rd Business and Industrial Park
Market Analysis• Business Segment Analysis
• Competitive Project Analysis
• Comparable Project Analysis
• Demand and Absorption Analysis
Northfield 3rd Business and Industrial Park
Market Analysis Conclusions• Qualities that have attracted businesses to Northfield
- Strong sense of place and community- Workforce is well-educated, loyal and reliable- Access to Mpls/St. Paul and the airport
• Qualities that may have hindered growth and retention- Not right on I-35- Lakeville, Eagan and Shakopee are closer to city and airport- Wage rates same as Twin Cities- Lack of city business assistance in the past- State tax structure- Build to suit only within market unless incentives are available
Northfield 3rd Business and Industrial Park
Market Analysis Conclusions• Need to differentiate from competitive market area
- More than raw land with potential for infrastructure- Master plan for high amenity park with good infrastructure/access- Strong design guidelines- Integrate land uses- Potential for co-generated power, heating and cooling- Seek synergies with existing companies in Northfield- Seek businesses interested in co-branding with city/colleges
Northfield 3rd Business and Industrial Park
Targeted Land Use Program (2030)Land Use Percentage (by SF) Building Program AcresIndustrial/Business Uses
Bulk Warehouse 15% 300,000 sf 30 acresOffice Warehouse 15% 300,000 sf 30 acresOffice Showroom 10% 200,000 sf 20 acresManufacturing 40% 800,000 sf 75 acresOther 20% 400,000 sf 38 acres(Data Center, Professional Office, R & D)
Other Potential Land Uses (based on input from market analysis, steering committee, city staff, community)Energy Park 20-30 acresConference Center 20-30 acresCorporate Campus 20-40 acresCommunity/Technical College 5-10 acresHotel Accommodations 5-10 acresCivic Uses (daycare, recreational, community center, other support uses) 10-25 acresResidential (alumni housing, senior housing, townhomes, live/work) 20-50 acresRetail (support retail) 5-10 acresOpen Space 20-25% 100-125 acresRight of Way 10-20% 50-100 acres
Northfield 3rd Business and Industrial Park
Visioning Charrette
Explore and discuss potential master plan alternatives for the business park sites.
Northfield 3rd Business and Industrial Park
Charrette Concepts
Northfield 3rd Business and Industrial Park
Concept Alternatives: North Site - Concept A
Illustrative Plan Parcel Plan
Northfield 3rd Business and Industrial Park
Concept Alternatives: North Site - Concept B
Illustrative Plan Parcel Plan
Northfield 3rd Business and Industrial Park
Concept Alternatives: North Site - Concept C
Illustrative Plan Parcel Plan
Northfield 3rd Business and Industrial Park
Concept Alternatives: South Site - Concept A
Illustrative Plan Parcel Plan
Northfield 3rd Business and Industrial Park
Concept Alternatives: South Site - Concept B
Illustrative Plan Parcel Plan
Northfield 3rd Business and Industrial ParkNorth Site: Parcel Plan
Balanced mix of land uses-Office-Industrial/Light Industrial-Civic-Retail-Housing-Open Space
Connected system of streets and trails
Open spaces, parks and greenways
Regional stormwater system
Workforce and lifecycle housing
Community gateway/identity
Sustainable development
Job creation = over 5,000 jobs
Annual tax revenue = $5.6 million
Preferred Master Plans - DRAFT
Northfield 3rd Business and Industrial Park
Preferred Master Plans - DRAFT
North Site: Development Program
Land Use Acres Building Program (SF)Industrial/Light Industrial 205.4 2,235,000 sfCommercial/Office 112.25 1,222,000 sfCommercial/Retail 6.6 70,000 sfLodging/Hotel 6.0 120 roomsMixed-Use 13.0
- retail 15,000 sf- office 100,000 sf- residential 200 du
High Density Residential 4.7 120 duMed. Density Residential 22.0 250 duPublic/Institutional 10.0 110,000 sfPublic Open Space 80.0Right of Way 70.0
Northfield 3rd Business and Industrial Park
Preferred Master Plans - DRAFT
North Site: Landscape Plan North Site: Circulation Plan
Northfield 3rd Business and Industrial ParkNorth Site: Phase One
Item Quantity Cost
Arterial (CR23) 4,000LF $2.6MCollector (type A) 2,000LF $1.25MCollector (type B) 7,000LF $4.3MUtilities in North Ave. LS $730KAddl Utilities in North Ave LS $250KRoundabout (Hwy 19/CR23) LS $1MLand Acquisition for roundabout LS $250KStormwater Improvements LS $500KWater Tower LS $345KGrading LS $1M
Total Cost (Phase One) $12.2M
Developable Acres (Phase One) 168.5 acres
Development Timeframe (Phase One) 15-20 years
Estimated Annual Tax Revenue (City) $1.9M
Estimated Number of Jobs Created 2703
Phasing Strategy - DRAFT
Northfield 3rd Business and Industrial ParkNorth Site: Phase Two
Item Quantity Cost
Local (type A) 3,800LF $2.5MLocal(type B) 5,600LF $2.7M
Total Cost (Phase Two) $5.2M
Developable Acres (Phase Two) 17.5 acres
Development Timeframe (Phase Two) 2-3 years
Estimated Annual Tax Revenue (City) $68K
Estimated Number of Jobs Created 314
Phasing Strategy - DRAFT
Northfield 3rd Business and Industrial ParkNorth Site: Phase Three
Item Quantity Cost
Collector (type A) 300LF $188KCollector (type B) 3,500LF $2.1MLocal (type B) 2,900LF $1.4MStormwater Improvements LS $200KGrading LS $250K
Total Cost (Phase Three) $4.2M
Developable Acres (Phase Three) 98.5 acres
Development Timeframe (Phase Three) 10-12 years
Estimated Annual Tax Revenue (City) $521K
Estimated Number of Jobs Created 1420
Phasing Strategy - DRAFT
Northfield 3rd Business and Industrial ParkNorth Site: Phase Four
Item Quantity Cost
Arterial (CR23) 2,400LF $1.5MCollector (type B) 6,600LF $4MStormwater Improvements LS $200KGrading LS $250K
Total Cost (Phase Four) $6.1M
Developable Acres (Phase Four) 100 acres
Development Timeframe (Phase Four) 10-12 years
Estimated Annual Tax Revenue (City) $285K
Estimated Number of Jobs Created 635
Phasing Strategy - DRAFT
Northfield 3rd Business and Industrial Park
Preferred Master Plans - DRAFT
South Site: Parcel Plan
Balanced mix of land uses-Office-Civic-Retail-Housing-Open Space
Minimize roadways/maximize trails
Parks and open spaces
Wildlife movement and habitat
Regional stormwater system
Creek system setbacks and restoration
Sustainable development
Job creation = over 4,000 jobs
Annual tax revenue = $4.4 million
Northfield 3rd Business and Industrial Park
Preferred Master Plans - DRAFT
South Site: Development Program
Land Use Acres Building Program (SF)Commercial/Office 160.75 1,750,000 sfCommercial/Retail 14.0 150,000 sfMed. Density Residential 27.75 300 duPublic/Institutional 5.5 60,000 sfPublic Open Space 207.0Right of Way 35.0
Northfield 3rd Business and Industrial Park
Preferred Master Plans - DRAFT
South Site: Landscape Plan South Site: Circulation Plan
Northfield 3rd Business and Industrial Park
Phasing Strategy - DRAFT
South Site: Phase One
Item Quantity Cost
Collector (type B) 2,800LF $1.7MStormwater Improvements LS $300KStreambank Enhancement LS $200KGrading LS $200K
Total Cost (Phase One) $2.4M
Developable Acres (Phase One) 57.5 acres
Development Timeframe (Phase One) 5-10 years
Estimated Annual Tax Revenue (City) $471K
Estimated Number of Jobs Created 1476
Northfield 3rd Business and Industrial ParkSouth Site: Phase Two
Item Quantity Cost
Arterial (CR 23/Decker Ave.) 6,600LF $4.3MCollector (type B) 3,500LF $2.1MLocal (type A) 1,450LF $930KStormwater Improvements LS $300KStreambank Enhancement LS $200KGrading LS $200K
Total Cost (Phase Two) $8M
Developable Acres (Phase Two) 94.25 acres
Development Timeframe (Phase Two) 10-12 years
Estimated Annual Tax Revenue (City) $825K
Estimated Number of Jobs Created 2325
Phasing Strategy - DRAFT
Northfield 3rd Business and Industrial ParkSouth Site: Phase Three
Item Quantity Cost
Local (type A) 3,650LF $2.3MLocal (type B) 1,600LF $735KStormwater Improvements LS $100KGrading LS $100K
Total Cost (Phase Three) $3.3M
Developable Acres (Phase Three) 28 acres
Development Timeframe (Phase Three) 3-5 years
Estimated Annual Tax Revenue (City) $562K
Estimated Number of Jobs Created NA
Phasing Strategy - DRAFT
Northfield 3rd Business and Industrial ParkSouth Site: Phase Four
Item Quantity Cost
Arterial (CR 23/Decker Ave.) 2,600LF $1.7Collector (type B) 4,200LF $2.6MStormwater Improvements LS $100KStreambank Enhancement LS $200K
Total Cost (Phase Four) $4.6M
Developable Acres (Phase Four) 28.5 acres
Development Timeframe (Phase Four) 3-5 years
Estimated Annual Tax Revenue (City) $250K
Estimated Number of Jobs Created 750
Phasing Strategy - DRAFT
Northfield 3rd Business and Industrial Park
Typical Street Sections - DRAFT
Northfield 3rd Business and Industrial Park
Development Guidelines - Draft Outline
Northfield 3rd Business and Industrial Park
General Objectives of the Guidelines
The general objectives of the Northfield Business and IndustrialPark Development Guidelines are to:
-Promote a functional and attractive environment-Ensure a high quality development-Protect and enhance private property values and investments-Protect public investments-Preserve the small-town character of Northfield-Employ sustainable design practices-Create distinctive and unique business and industrial parks within the City of Northfield
Northfield 3rd Business and Industrial Park
How the Guidelines are to be Used
The guidelines will provide direction to designers, developers, City staff, City commissions and decision makers regarding the City’s expectations for design excellence at the Northfield Business and Industrial Parks.
They provide review agencies with an implementation and planning tool that can be used to judge the merits of proposed projects at each of the business and industrial parks, informingthe design review and approval of individual development projects.
Northfield 3rd Business and Industrial Park
Goal
Category or Grouping
Topic
Description
Guidelines
Example
Northfield 3rd Business and Industrial Park
Northfield 3rd Business and Industrial Park
Northfield 3rd Business and Industrial Park
Northfield 3rd Business and Industrial Park
Northfield 3rd Business and Industrial Park
Northfield 3rd Business and Industrial Park
Implementation Overview
• Incorporate master plan recommendations into City policy documents
• Seek public financing opportunities to fund infrastructure investments
• Implement trunk roadway, utility and regional stormwater systems to serve development
• Develop incentives to attract development and encourage sustainable development practices
• Develop marketing strategies and aggressively target desired users
Northfield 3rd Business and Industrial Park
Next Steps• Master Plan and Development Standards
- Prepare Draft Master Plan and Development Guidelines
• Implementation Strategies - Public Finance Strategies- Phasing Strategies- Marketing Strategies
• Final Review and Approvals- Landowner Review- Public Open House- Steering Committee Review- Economic Development Authority Review- Planning Commission Review- City Council Review
Northfield 3rd Business and Industrial Park
Stay informed and send us your thoughts!
Contacts: Jody Gunderson, Economic Development Director801 Washington StreetNorthfield, MN [email protected]
Jeff McMenimen, Hoisington Koegler Group, Inc.123 North Third Street, Suite 100Minneapolis, MN [email protected]
Project Website: www.northfield-businesspark.com
Northfield 3rd Business and Industrial Park