original sketch elevation drawings
site - may 2008
june 2010 - construction commenced
august 2010 - floor framing
august 2010 - floor framing
september 2010 - the main frame erected
october 2010 - framing & roofing
late october 2010 - roofing completed
november 2010 - wall cladding
late november 2010 - services rough-in
december 2010 - lock up
february 2011 - the earth wall commences
march 2011
early autum mist 2011
april 2011
april 2011
may 2011
almost complete - end of may 2011
almost complete - end of may 2011
completed - june 2011
completed - june 2011
completed - june 2011
completed - june 2011
the grand opening tea party
Sydney OfficeLevel 6/69 Reservoir Street Surry Hills NSW 2010t. 02 8218 2113m. 0412 152 448
Victoria Office1 Yarra Street HawthornVIC 3122t. 03 8808 6444f. 03 9818 3977
Queensland OfficeUnit 4/5 Navigator Place Hendra QLD 4011 t. 07 3632 2550f. 07 3632 2599
www.smithtracey.com.au
+
| m a s t e r p l a n n e r s | a r c h i t e c t s | i n t e r i o r d e s i g n e r s