Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/09/... · Also...
Transcript of Oklahoma Capitol Restoration Projectcapitolrestore.ok.gov/wp-content/uploads/2017/09/... · Also...
Oklahoma Capitol Restoration Project
2300 N Lincoln Blvd. Oklahoma City, OK 73105
August 2017 – Monthly Progress Report
MONTHLY OVERVIEW
� Generator Set
� Drywall Installations Near
Completion throughout
ground level - south
� SW Elevator Shaft Nearly
Complete
� Mechanical Room
Reconfiguration – Complete
� Southwest Doghouse Wall &
Finish Floor Installation
Complete
� Secretary of State – Door
Frames, Ceiling Grid, and
Floor Prep Complete
REPORT CONTENTS
Cover Letter
Executive Summary
Preconstruction Status
Construction Schedule
Request for Information
Submittal Log
Construction Photos
2601 NW Expressway, Suite 501W 73107 | t 405.254.1050 f 405.254.1055 | www.manhattanconstruction.com
Manhattan Job #
3707
Design/Builder:
Project Owner:
Oklahoma Capitol Restoration
2300 N Lincoln Blvd. Oklahoma City, OK 73105
August 2017 - Monthly
Progress Report
Cover Letter
Tab 1 Executive Summary
Tab 2 Preconstruction Status
• Document deliverable status
Tab 3 Construction Schedule
• Schedule narrative
• Critical Items
• Schedule Update
Tab 4 Requests for Information (RFIs)
• RFI Summary Log
Tab 5 Submittal Log
• Submittal Package Summary Log
Tab 6 Construction Photos
• Detailed progress photos – current month
EXECUTIVE SUMMARY
SECTION 1
Monthly Progress Report – Oklahoma Capitol Restoration
August 2017
1-1
Monthly Progress Report For
Oklahoma Capitol Restoration August 2017
For Phase 3.3 construction, the key to success in August was completion of all rough-in activities and arrival of all major mechanical equipment. With five different crane mobilizations, all rooftop-mounted equipment has now been set, all structural steel from the new elevator machine room hoisted for erection, and all the components to the emergency generator have been set into place. Along with these activities, all ductwork has been installed throughout the West wing for future fresh air distribution as well as ducting through the SW doghouse for the new Rotunda conditioning system. Also during the month of August, all new equipment installations in the main mechanical room were completed so that the west entry framing & finish work can conclude. Below is a recap of the major construction & design milestones that are upcoming and their completion status:
1. Start Up New Condensing Water Pumps Achieved August 18, 2017
2. Sanitary Sewer Main Tie-In Complete Achieved June 26, 2017
3. Framing For Shaftwalls at Elevator Achieved July 28, 2017
4 Millwork Trim Installations - Sec. of State & Ground Level Projected September 11, 2017
5. Ceilings Complete at Ground Level Corridor Projected September 12, 2017
6. Limestone Column Delivery for Ground Level Corridor Project September 18, 2017
7. Elevator Installation Begins Projected September 18, 2017
8. ELECTRIAL OUTAGE – Complete Projected October 22, 2017
9. Marble Flooring Installation at Ground Level Corridor Projected November 1, 2017
10. Doors & Hardware Installations for Sec. of State & GL Projected November 1, 2017
Prime Contract Status The prime contract has been updated with Contract Amendment #2 to include funding for the entirety of the Priority 1 scope. Priority 2 funding bill HB 3168 was passed on May 26, 2016. On February 15, 2017, Contract Amendment #3 was executed to incorporate Priority 2 design & the reallocation of construction sequences to seamlessly integrate Priority 1 & 2 scopes of work into the overall project. Design Status Planning & development of the full interior restoration project is ongoing. Programming & Schematic Design efforts are now complete with tenant planning and initial document review complete for all areas of the building. Work is ongoing toward the 65% Design Development documents for the project. All project documents should be 65% complete by year-end.
EXECUTIVE SUMMARY
SECTION 1
Monthly Progress Report – Oklahoma Capitol Restoration
August 2017
1-2
As tenant space planning is ending, work to further define historic displays, art lighting, wayfinding systems, and exhibit design is now commencing. This work will involve several entities including the Arts Council, Tourism, and the History Center. The focus of these planning efforts will be to enhance the visitor experience in the Capitol and display the many aspects of Oklahoma heritage. Buyout Status Priority 1 buyout efforts are underway and will continue as the drawing packages are completed. All buyout is now complete for Phase 3.3 construction. Phase 4.0 & 4.1 documents are now in pricing. Construction Progress & Schedule Status Priority 1 Scope Several critical activities to the Ground Level construction schedule were completed in August. This includes rough-in completion at the main corridor and tenant spaces to the south, installation of all remaining mechanical room equipment & startup, along with completion of all ceiling framing, blocking and rough-in for the corridor. All preparation work for the October electrical outage is coming to an end as the new buss duct has been connected and new sub-panels have been installed top to bottom in the SW doghouse. Ceiling drywall & trim installations will kick off in early September with limestone column installations & marble flooring following close behind. Secretary of State construction continues to move forward on pace with the ground level. In August, all walls received the initial finish paint, door frames were completed, plaster work commenced at the Rotunda, and HVAC units were started. All millwork finishes will be installed in September, with flooring & final paint wrapping up all work activities throughout October & November. Request for Information (RFI’s) Current RFI Summary Log attached in Tab 4. Submittals Current Submittal Log attached in Tab 5. Cost Events & Authorization Requests There are currently no open proposals for the project.
Prepared by: Andrea Gossard, Project Manager
PRECONSTRUCTION & DESIGN STATUS
SECTION 2
Monthly Progress Report – Oklahoma Capitol Restoration
August 2017
2-1
Document Deliverables:
• 35% SD Submittal – Group 5 Tenants was submitted for review on July 25, 2017
• 95% CD Submittal – Phase 4.0 was submitted for review on August 18. 2017.
• Master Planning Capitol Color Palette was submitted for review on August 21, 2017
• 95% CD Submittal – Phase 4.1 was submitted for review on August 28, 2017.
Design Status Report:
,
Frankfurt Short Bruza Architects Engineers Planners
Monthly Project Status Report
Date: August 30, 2017 Project: 15151DB – Capitol Interior Restoration
To: Name Kyle Nelson
Company/Position Manhattan Construction Co.
Phone 405.254.1050
Email [email protected]
From: Roger Klein, FSB Project Manager Re: Monthly Project Status Report – August 2017
This project status report is being provided to you to document our status on the current
Capitol Restoration Project, as required by OMES.
DESIGN PROGRESS
During August 2017 the Design Build Team continued to produce Design Documents for the
Interior Restoration at the Capitol. FSB has been working to complete the Design and
Construction documents for Phases 4 and 5. The Phase 6 scope has been developed; the
schematic design effort is complete and was submitted to the Owner team on July 25, 2017.
PRECONSTRUCTION & DESIGN STATUS
SECTION 2
Monthly Progress Report – Oklahoma Capitol Restoration August 2017
2-2
Phases 3.2 and 3.3 are in construction and nearing completion. The Phase 3.3 Construction
documents included The State Election Board, The Ethics Commission, Capitol Fitness Center,
House Print, Maintenance Offices and Storage, and Secretary of State.
Phase 4 Design includes OMES Facilities, OMES State Finance, LSB, Photographer, Arts Council,
the Lt. Governor, along with the Senate’s Ground Floor and 4th and 5th floors of the East Wing.
The 95% Construction Documents were submitted August 18, 2017. An early material
procurement package for the 6th floor Senate was issued June 30, 2017, and the 95%
Construction documents were issued August 28, 2017.
Phase 5 Design Development documents are now underway. This phase includes the Governor,
the Treasurer, Judicial, Capitol Press, Tourism, Food Service, the House of Representatives
spaces, all remaining Senate spaces, OMES Storage, and Capitol Press. Construction documents
for Phase 5 are scheduled to be in production until October 2018, with a 65% Construction
Document submission to be issued in November 2017.
The Phase 6 Schematic Design documents were submitted in July 2017 and are currently in
review. Phase 6 scope includes the 2nd Floor Judicial Court Room, the Capitol Exhibit Space, the
Multi-purpose Room, the State Auditor Office, and the Sixth Floor Utility/Support Space.
Design development and construction document production began August 7, 2017 and is
scheduled to be complete June 2018.
On August 3, the FSB Design Team met with Manhattan Construction, OMES, AE1, and the Arts
Council to continue to define the Historic Display Areas and Capitol Art Zones. The team
discussed an agenda that included steps to establish a redefined Visitor Experience at the
Capitol, a review of areas designated for Historical Display and Art Zones, and to engage the
Key Stakeholders responsible for the decision making. Also discussed were Goals, Objectives
and Expectations for the displays. A timeline was discussed for scheduling workshops,
meetings, and the programing and design effort required to meet the infrastructure installation
required during construction.
PRECONSTRUCTION & DESIGN STATUS
SECTION 2
Monthly Progress Report – Oklahoma Capitol Restoration August 2017
2-3
In August, the FSB design team has continued the design effort for the interior finishes needed
for the Phase 3.3 construction space as well as throughout the Rotunda. A full scale mockup of
a section of the public ground level corridor has been constructed, reviewed, and modified to
achieve the approval of all material finishes being installed through the ground level. FSB
continued to collaborate with the historic paint consultant EverGreene Architectural Arts, on
the interior design and paint color pallet for public & historic spaces throughout the Capitol..
On August 8, FSB with Jeff EverGreene and Terry VanderWell of EverGreene Arts presented the
recommended final color palette to Manhattan, OMES, and AE1. On August 21, the Final Color
Design booklet was submitted for approval that includes the proposed color palette for the
public spaces from the ground level through fifth floors.
On August 22nd, Mary Slater with EverGreene Arts returned to the Capitol to test additional
selected areas for color sampling including the House and Senate Chambers, The Supreme
Court, and the Blue Room. FSB architects and Steve Kelley, Historic Preservation consultant,
were also on hand to help identify the Historic locations. Manhattan Construction assembled
scaffolding at these locations to allow access at the upper wall moldings and ceilings. Sampling
through the week consisted of chemically stripping away layers of paint of to expose the
historic paint or glaze. In other areas paint samples were taken by driving a small steel punch
into the existing plaster to extract the paint layers in a cross section to be analyzed by
microscopy. A report will be issued to identify the historic paint pallet. FSB and EverGreene will
color match the pallet for historic restoration and color design.
FSB and EverGreene Arts present the Historic color pallet design at FSB Architects
PRECONSTRUCTION & DESIGN STATUS
SECTION 2
Monthly Progress Report – Oklahoma Capitol Restoration August 2017
2-4
Mary Slater with EverGreene Arts at the Capitol Supreme Court
Color investigation by EverGreene Arts at the House Chambers
PRECONSTRUCTION & DESIGN STATUS
SECTION 2
Monthly Progress Report – Oklahoma Capitol Restoration August 2017
2-5
On August 24th, the Design-Build met with Amy Maddox of Cortina Media Design to begin to
develop the Media Design and Wayfinding scope for the Capitol. Cortina has been responsible
for media production at many notable projects such as The U.S. Capitol, and The Murrah
Federal Building Bombing Memorial. The team discussed developing a concept for possible
media exhibits in the Capitol including Interactive Digital Signage and Wayfinding, and a Digital
Mobile App Tour. The Wayfinding Media would include an Interactive Capitol Directory that
would aid in finding your representative, upcoming legislation, and help navigate the Capitol.
The mobile App would allow the visitor to access Capitol Art, Architecture, History, and Capitol
tours through their personal mobile device. The team discussed the concept summary
including content outlines, script design, production, hardware programing, installation, and
system management.
Capitol Wayfinding meeting and tour with Amy Maddox of Cortina Media Design
End of Report
CONSTRUCTION SCHEDULE
SECTION 3
Monthly Progress Report – Oklahoma Capitol Restoration August 2017
3-1
Phase 3.2 & 3.3 – Ground Level – West Infrastructure & Finishes
Schedule Status: By the end of August, the ground level construction spaces are beginning to take their final shape. Walls are receiving their initial coats of finish paint, all drywall wall ceilings are in place, and even the southwest doghouse has made the transition to finish elements. The month of September will have three primary focuses: Final preparations for the electrical outage, kicking off installation of the new elevator, and installation of wall & ceiling trim throughout the main corridor making way for flooring to begin in October. Work is also progressing quickly in numerous locations beyond the public spaces of ground level, the fitness center locker rooms are being prepare for tile installations, House maintenance & storage walls and ceilings are complete and ready for flooring preparations, and the generator areaway structure is now complete with generator assembly underway. The future home for Secretary of State moves along steadily with ceiling grid, lighting, and door frames installed over the past month. Final plans have also been prepared for the 6th floor Senate staff offices, work is set to kick off in this area just after the Labor Day holiday break. Critical Schedule Events: Nearly all critical schedule events correlate with material procurement items. Below is a tracking log of all major material delivery items currently on the schedule:
Item Description Estimated Installation Date
Estimated Delivery Date
Actual Delivery Date
SW Doghouse Buss Duct 7/21/17 6/20/17 6/30/17
Ground Level West Corridor – Finishes 8/21/17 8/21/17 9/8/17
Rooftop Air Handlers & Condensing Units 8/31/17 7/15/17 7/24/17
DOAS Units 8/31/17 8/30/17 8/19/17
Generator 9/11/17 8/17/17 8/19/17
SW Elevator Rails, Cab & Motor 9/15/17 9/15/17
SW Elevator Doors & Finishes 11/27/17 11/27/17
6th Floor Stair Structure 10/30/17 10/30/17
6th Floor Handicap Lift 1/2/18 1/2/18
Milestone Description Baseline Schedule
Last Month’s Update
Current Month Update
Gain or Loss this Month
Structure Complete at Generator 6/16/17 7/19/17 7/19/17 -5 Structure Complete at SW Doghouse 5/26/17 8/14/17 9/15/17 +31 Elevator Installation Begins – SW Doghouse 9/14/17 10/3/17 9/18/17 -15 DOAS Rooftop Units Set 8/30/17 8/21/17 8/19/17 -2 SW Outside Air Riser Installations Complete 8/16/17 9/12/17 9/12/17 0 Limestone Column Installations 10/6/17 10/13/17 9/18/17 -25
Marble Flooring Installations 11/3/17 10/27/17 11/21/17 +24 6th Floor Senate Framing Begins 9/6/17 9/6/17 9/6/17 0
Activity ID Activity Name Orig Dur
RemDur
Start Finish
DesignDesign1219 1129 21-Apr-17 A 01-Feb-22
Master PlanMaster Plan1219 1129 21-Apr-17 A 01-Feb-22
Construction DocumentsConstruction Documents437 347 21-Apr-17 A 03-Jan-19
Package 3 - First Floor N, E, SPackage 3 - First Floor N, E, S15 14 18-Aug-17 A 08-Sep-17
D-M01-1630 Owner 100% Review 15 14 18-Aug-17 A 08-Sep-17
Package 4 - Floors 2 through 5Package 4 - Floors 2 through 5437 347 21-Apr-17 A 03-Jan-19
D-M01-1560 DD (65% CD's) 220 136 21-Apr-17 A 05-Mar-18
D-M01-1680 Owner 65% Review 15 15 06-Mar-18 26-Mar-18
D-M01-1690 CD's 100% 181 181 27-Mar-18 11-Dec-18
D-M01-1720 Owner 100% Review 15 15 12-Dec-18 03-Jan-19
Package 5 - Ground N, E, SPackage 5 - Ground N, E, S231 217 28-Jul-17 A 27-Jun-18
D-M01-1580 Owner Review 20 1 28-Jul-17 A 21-Aug-17
D-M01-1640 DD (65% CD's) 43 43 22-Aug-17 20-Oct-17
D-M01-1660 Owner 65% Review 15 15 23-Oct-17 10-Nov-17
D-M01-1670 CD's 100% 143 143 13-Nov-17 06-Jun-18
D-M01-1700 Owner 100% Review 15 15 07-Jun-18 27-Jun-18
Fire Marshall PermitsFire Marshall Permits36 36 21-Aug-17 10-Oct-17
6th Floor Senate6th Floor Senate36 36 21-Aug-17 10-Oct-17
D-M01-1750 MCC Submit FM Set 1 1 21-Aug-17 21-Aug-17
D-M01-1755 FM Review / Approve Building Permit 15 15 22-Aug-17 12-Sep-17
D-M01-1760 Release FA / FS Design Drawings 10 10 13-Sep-17 26-Sep-17
D-M01-1765 FM Review / Approve FS 10 10 27-Sep-17 10-Oct-17
D-M01-1770 FM Review / Approve FA 10 10 27-Sep-17 10-Oct-17
Master Plan MilestonesMaster Plan Milestones1015 1015 01-Feb-18 01-Feb-22
Legislative Session MilestonesLegislative Session Milestones1015 1015 01-Feb-18 01-Feb-22
M-M01-1005 2018 Session Begins (Construction Ends) 0 0 01-Feb-18
M-M01-1010 2018 Session Ends (Construction Starts) 0 0 01-Jun-18
M-M01-1015 2019 Session Begins (Construction Ends) 0 0 01-Feb-19
M-M01-1020 2019 Session Ends (Construction Starts) 0 0 31-May-19
M-M01-1025 2020 Session Starts (Construction Ends) 0 0 03-Feb-20
M-M01-1030 2020 Session Ends (Construction Starts) 0 0 01-Jun-20
M-M01-1035 2021 Session Starts (Construction Ends) 0 0 01-Feb-21
M-M01-1040 2021 Session Ends (Construction Starts) 0 0 01-Jun-21
M-M01-1045 2022 Session Begins (Construction Ends) 0 0 01-Feb-22
SequencesSequences1255 1028 28-Sep-16 A 07-Sep-21
J A J A J A A A A J A J A J A A J A J A J
2017 2018 2019 2020 2021 2022 2023
Owner 100% Review
DD (65% CD's)
Owner 65% Review
CD's 100%
Owner 100% Review
Owner Review
DD (65% CD's)
Owner 65% Review
CD's 100%
Owner 100% Review
MCC Submit FM Set
FM Review / Approve Building Permit
Release FA / FS Design Drawings
FM Review / Approve FS
FM Review / Approve FA
2018 Session Begins (Construction Ends)
2018 Session Ends (Construction Starts)
2019 Session Begins (Construction Ends)
2019 Session Ends (Construction Starts)
2020 Session Starts (Construction Ends)
2020 Session Ends (Construction Starts)
2021 Session Starts (Construction Ends)
2021 Session Ends (Construction Starts)
2022 Session Begins (Construction End
Start Date 23-Feb-15
Finish Date 30-Dec-22
Data Date 21-Aug-17
Run Date 30-Aug-17
Page 1 of 33
3707-CR29
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
Prerequisite Phase 3 - Basement Prep & Long Lead ProcurementPrerequisite Phase 3 - Basement Prep & Long Lead Procurement275 18 28-Sep-16 A 14-Sep-17
Material ProcurementMaterial Procurement275 18 28-Sep-16 A 14-Sep-17
Procurement Phase SummariesProcurement Phase Summaries171 25 28-Sep-16 A 14-Sep-17
PROC3-LEAD Procurement - Prerequisite Phase 3 171 25 28-Sep-16 A 14-Sep-17
ElevatorsElevators80 18 06-Jun-17 A 14-Sep-17
PROC3-1400 Fab & Deliver - Elevators 80 18 06-Jun-17 A 14-Sep-17
PROC3-1535 Fab & Deliver Mach Rm Steel 10 5 14-Aug-17 A 25-Aug-17
Buss DuctBuss Duct80 6 03-Mar-17 A 28-Aug-17
PROC3-1430 Fab & Deliver - Buss Duct 80 6 03-Mar-17 A 28-Aug-17
GeneratorGenerator130 5 04-Jan-17 A 25-Aug-17
PROC3-1440 Fab & Deliver - Generator 130 5 04-Jan-17 A 25-Aug-17
RTURTU30 2 02-Jun-17 A 22-Aug-17
PROC3-1450 Fab & Deliver - DOAS 30 2 02-Jun-17 A 22-Aug-17
AHUAHU50 2 21-Mar-17 A 22-Aug-17
PROC3-1470 Fab & Deliver - AHU 50 2 21-Mar-17 A 22-Aug-17
Sequence 1Sequence 1528 321 03-Oct-16 A 26-Nov-18
Material ProcurementMaterial Procurement523 316 24-Oct-16 A 15-Nov-18
Procurement Phase SummariesProcurement Phase Summaries519 452 24-Oct-16 A 15-Nov-18
S-S01-1070 Procurement - Sequence 1 519 452 24-Oct-16 A 15-Nov-18
MockupMockup21 1 17-May-17 A 21-Aug-17
P-S01-2235 Owner/AE1 Review Paint Colors 21 1 17-May-17 A 21-Aug-17
Mechanical RoomMechanical Room119 2 02-Mar-17 A 22-Aug-17
P-S01-1170 Fab & Deliver - Condensing Units (Rooftop) 60 2 02-Mar-17 A 22-Aug-17
P-S01-1440 Fab & Deliver - DOAS Units (Rooftop) 80 2 02-Jun-17 A 22-Aug-17
Public CorridorPublic Corridor377 316 30-May-17 A 15-Nov-18
P-S01-1560 Fab & Deliver - Security Devices 30 1 30-May-17 A 21-Aug-17
P-S01-2240 Order On Hold Per Final Count - H8 Light Fixture 120 76 05-Jun-17 A 07-Dec-17
P-S01-1640 Fab & Deliver - H8 Light Fixture 240 240 08-Dec-17 15-Nov-18
P-S01-2245 Order On Hold Per Final Count - H3 Light Fixture 120 76 05-Jun-17 A 07-Dec-17
P-S01-1680 Fab & Deliver - H3 Light Fixture 120 120 08-Dec-17 29-May-18
P-S01-1720 Fab & Deliver - KArt Light Fixture 120 11 25-Jul-17 A 05-Sep-17
P-S01-2265 Rebid - Marble Flooring 17 7 07-Aug-17 A 29-Aug-17
P-S01-2180 Contracting & Submittal Prep - Marble Flooring 5 5 30-Aug-17 06-Sep-17
P-S01-1810 MCC Receive / Review Submittal - Marble Flooring 5 5 07-Sep-17 13-Sep-17
P-S01-1820 AE2 (FSB) Receive / Review Submittal - Marble Flooring 10 3 14-Sep-17 18-Sep-17
P-S01-1830 AE1 (Mass) Receive / Review Submittal - Marble Flooring 15 5 19-Sep-17 25-Sep-17
J A J A J A A A A J A J A J A A J A J A J
2017 2018 2019 2020 2021 2022 2023
Procurement - Prerequisite Phase 3
Fab & Deliver - Elevators
Fab & Deliver Mach Rm Steel
Fab & Deliver - Buss Duct
Fab & Deliver - Generator
Fab & Deliver - DOAS
Fab & Deliver - AHU
Procurement - Sequence 1
Owner/AE1 Review Paint Colors
Fab & Deliver - Condensing Units (Rooftop)
Fab & Deliver - DOAS Units (Rooftop)
Fab & Deliver - Security Devices
Order On Hold Per Final Count - H8 Light Fixture
Fab & Deliver - H8 Light Fixture
Order On Hold Per Final Count - H3 Light Fixture
Fab & Deliver - H3 Light Fixture
Fab & Deliver - KArt Light Fixture
Rebid - Marble Flooring
Contracting & Submittal Prep - Marble Flooring
MCC Receive / Review Submittal - Marble Flooring
AE2 (FSB) Receive / Review Submittal - Marble Flooring
AE1 (Mass) Receive / Review Submittal - Marble Flooring
Start Date 23-Feb-15
Finish Date 30-Dec-22
Data Date 21-Aug-17
Run Date 30-Aug-17
Page 2 of 33
3707-CR29
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
P-S01-1840 Fab & Deliver - Marble Flooring 30 40 26-Sep-17 20-Nov-17
P-S01-1850 MCC Receive / Review Submittal - Acoustic Wall Fabric/ Assembly 5 5 21-Aug-17 25-Aug-17
P-S01-1860 AE2 (FSB) Receive / Review Submittal - Acoustic Wall Fabric/ Assembly 10 10 28-Aug-17 11-Sep-17
P-S01-1870 AE1 (Mass) Receive / Review Submittal - Acoustic Wall Fabric/ Assembly 15 15 12-Sep-17 02-Oct-17
P-S01-1880 Fab & Deliver - Acoustic Wall Fabric/ Assembly 30 30 03-Oct-17 13-Nov-17
P-S01-1920 Fab & Deliver - Limestone Veneer Columns 30 15 28-Jul-17 A 11-Sep-17
P-S01-2270 Rebid - Granite Base 17 7 07-Aug-17 A 29-Aug-17
P-S01-2200 Contracting & Submittal Prep - Granite Base 10 10 30-Aug-17 13-Sep-17
P-S01-1930 MCC Receive / Review Submittal - Granite Base 5 5 14-Sep-17 20-Sep-17
P-S01-1940 AE2 (FSB) Receive / Review Submittal - Granite Base 10 10 21-Sep-17 04-Oct-17
P-S01-1950 AE1 (Mass) Receive / Review Submittal - Granite Base 15 15 05-Oct-17 25-Oct-17
P-S01-1960 Fab & Deliver - Granite Base 30 30 26-Oct-17 08-Dec-17
ConstructionConstruction503 321 03-Oct-16 A 26-Nov-18
Schedule Driven MilestonesSchedule Driven Milestones195 195 19-Feb-18 26-Nov-18
M-S01-1010 Interim Substantial Completion - House S. / Fitness / Public Corridor / Generator 0 0 19-Feb-18
M-S01-1050 Interim Substantial Completion - Mechanical Room 0 0 19-Feb-18
M-S01-1020 Interim Substantial Completion - House Print 0 0 11-Apr-18*
M-S01-1030 Interim Substantial Completion - Election 0 0 11-Apr-18*
M-S01-1040 Interim Substantial Completion - Ethics 0 0 11-Apr-18*
M-S01-1060 Interim Substantial Completion - SW Dog House 0 0 11-Apr-18*
M-S01-1090 Sequence 1 New Construction Ends 0 0 26-Nov-18
Construction Phase SummariesConstruction Phase Summaries510 234 03-Oct-16 A 11-Apr-18
S-S01-1000 Construction - Sequence 1 510 234 03-Oct-16 A 11-Apr-18
SW Dog House (Elevator)SW Dog House (Elevator)167 163 18-Jul-17 A 11-Apr-18
C-S01-1460 Install Hoistway Walls Flrs B-6 15 24 07-Aug-17 A 22-Sep-17
C-S01-6680 Install Temp Deck at 6th Flr Penthouse 5 2 28-Aug-17 29-Aug-17
C-S01-1440 Install New Structure @ Elevator Penthouse 20 20 30-Aug-17 27-Sep-17
C-S01-1530 Install Hoistway Smoke / Heat Detection 2 2 25-Sep-17 26-Sep-17
C-S01-1540 Install Hoistway Fire Suppression 3 3 27-Sep-17 29-Sep-17
C-S01-1020 Install Elevator Rails 15 15 28-Sep-17 26-Oct-17
C-S01-1550 Install Hoistway Lighting 2 2 02-Oct-17 03-Oct-17
C-S01-1570 Remove Elevator Hoistway Scaffold 5 5 27-Oct-17 02-Nov-17
C-S01-1560 Install Elevator Cab & Motor 80 45 03-Nov-17 10-Jan-18
C-S01-1110 Install Elevator Door Fronts 25 25 19-Dec-17 24-Jan-18
C-S01-1120 Install Elevator Cab Finishes 20 20 25-Jan-18 21-Feb-18
C-S01-1130 Elevator Test & Balance 5 5 22-Feb-18 28-Feb-18
C-S01-4290 Complete MCC / FSB Punch List 10 15 22-Feb-18 14-Mar-18
C-S01-1140 DOL Final Inspection on Elevator 1 1 01-Mar-18 01-Mar-18
J A J A J A A A A J A J A J A A J A J A J
2017 2018 2019 2020 2021 2022 2023
Fab & Deliver - Marble Flooring
MCC Receive / Review Submittal - Acoustic Wall Fabric/ Assembly
AE2 (FSB) Receive / Review Submittal - Acoustic Wall Fabric/ Assembly
AE1 (Mass) Receive / Review Submittal - Acoustic Wall Fabric/ Assembly
Fab & Deliver - Acoustic Wall Fabric/ Assembly
Fab & Deliver - Limestone Veneer Columns
Rebid - Granite Base
Contracting & Submittal Prep - Granite Base
MCC Receive / Review Submittal - Granite Base
AE2 (FSB) Receive / Review Submittal - Granite Base
AE1 (Mass) Receive / Review Submittal - Granite Base
Fab & Deliver - Granite Base
Interim Substantial Completion - House S. / Fitness / Public Corridor / Generator
Interim Substantial Completion - Mechanical Room
Interim Substantial Completion - House Print
Interim Substantial Completion - Election
Interim Substantial Completion - Ethics
Interim Substantial Completion - SW Dog House
Sequence 1 New Construction Ends
Construction - Sequence 1
Install Hoistway Walls Flrs B-6
Install Temp Deck at 6th Flr Penthouse
Install New Structure @ Elevator Penthouse
Install Hoistway Smoke / Heat Detection
Install Hoistway Fire Suppression
Install Elevator Rails
Install Hoistway Lighting
Remove Elevator Hoistway Scaffold
Install Elevator Cab & Motor
Install Elevator Door Fronts
Install Elevator Cab Finishes
Elevator Test & Balance
Complete MCC / FSB Punch List
DOL Final Inspection on Elevator
Start Date 23-Feb-15
Finish Date 30-Dec-22
Data Date 21-Aug-17
Run Date 30-Aug-17
Page 3 of 33
3707-CR29
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-S01-4300 Complete AE1 / Owner Punch List 10 30 01-Mar-18 11-Apr-18
C-S01-3920 Fire Marshal Final - SW Dog House 1 1 02-Mar-18 02-Mar-18
C-S01-7190 Install Stone Hard Flooring 4 2 14-Aug-17 A 22-Aug-17
C-S01-1510 Prime & 1st Coat 15 15 21-Aug-17 11-Sep-17
C-S01-1520 Surface Mount All Electrical / MEP 15 15 12-Sep-17 02-Oct-17
C-S01-1590 Install HVAC Flrs G-6 45 21 18-Jul-17 A 19-Sep-17
C-S01-1610 Install Vertical IT / Low Voltage Pathways 30 11 25-Jul-17 A 05-Sep-17
C-S01-6995 Install Hose Cabinets Flrs G-6 15 15 21-Aug-17 11-Sep-17
ElectricalElectrical111 50 19-Apr-17 A 30-Oct-17
C-S01-1115 SW DH Build Out 42 48 23-Aug-17 30-Oct-17
C-S01-1435 Install Buss Duct Tap Box - SW DH Elec Build Out 3 3 23-Aug-17 25-Aug-17
C-S01-1425 Install Branch Panels - SW DH Elec Build Out 7 7 23-Aug-17 31-Aug-17
C-S01-1445 Install Buss Duct - SW DH Elec Build Out 2 3 29-Aug-17 31-Aug-17
C-S01-1455 Install Buss Duct Disconnet - SW DH Elec Build Out 2 2 01-Sep-17 05-Sep-17
C-S01-1465 Run Overhead Piping - SW DH Elec Build Out 14 14 01-Sep-17 21-Sep-17
C-S01-1475 Pull Feeders to Branch Panels - SW DH Elec Build Out 7 7 22-Sep-17 02-Oct-17
C-S01-1485 Terminate Wiring at Tapbox - SW DH Elec Build Out 3 3 03-Oct-17 05-Oct-17
C-S01-1495 Terminate Panel Boards and Main Switch - SW DH Elec Build Out 4 4 06-Oct-17 11-Oct-17
C-S01-1505 Install Grounding - SW DH Elec Build Out 7 7 12-Oct-17 30-Oct-17
C-S01-1105 Main Electric Room Build Out 111 28 19-Apr-17 A 28-Sep-17
C-S01-1305 Run Overhead Piping for Normal - Main Elec Rm Build Out 18 9 08-Aug-17 A 31-Aug-17
C-S01-1385 Pull Wire and Terminate EM Gear - Main Elec Rm Build Out 5 5 18-Aug-17 A 25-Aug-17
C-S01-1145 Install for Fire Pump Feeder 8 8 28-Aug-17 07-Sep-17
C-S01-1395 Pull Wire and Terminate Normal Gear - Main Elec Rm Build Out 5 5 01-Sep-17 08-Sep-17
C-S01-1405 Terminate Main Gear - Main Elec Rm Build Out 14 14 11-Sep-17 28-Sep-17
C-S01-6480 Demo Overhead Bus Duct 2 2 06-Oct-17 07-Oct-17
C-S01-6500 Install Bus Duct to OG&E Vault 1 1 08-Oct-17 08-Oct-17
C-S01-6460 OMES - Power Shut Down 7 7 13-Oct-17 19-Oct-17
C-S01-6470 OG&E Disconnect Power to Building 1 1 13-Oct-17* 13-Oct-17
C-S01-6490 Terminate Existing Main Gear 2 2 14-Oct-17 15-Oct-17
C-S01-6510 Terminate Tap Boxes 1 1 16-Oct-17 16-Oct-17
C-S01-6520 OG&E Terminate at Vault 3 3 16-Oct-17 18-Oct-17
C-S01-1185 OG&E Restore Permanent Power 0 0 19-Oct-17
C-S01-6530 OMES / MCC Restore Building Services 2 2 20-Oct-17 21-Oct-17
C-S01-1195 Commissioning of New Gear 3 3 20-Oct-17 24-Oct-17
Mechanical RoomMechanical Room164 126 27-Jun-17 A 19-Feb-18
C-S01-4140 Overhead Electrical Rough In 5 1 27-Jun-17 A 02-Nov-17
C-S01-4230 MEP Device Out 5 5 21-Aug-17 25-Aug-17
C-S01-4150 Overhead Sprinkler Rough In 5 10 21-Aug-17 01-Sep-17
J A J A J A A A A J A J A J A A J A J A J
2017 2018 2019 2020 2021 2022 2023
Complete AE1 / Owner Punch List
Fire Marshal Final - SW Dog House
Install Stone Hard Flooring
Prime & 1st Coat
Surface Mount All Electrical / MEP
Install HVAC Flrs G-6
Install Vertical IT / Low Voltage Pathways
Install Hose Cabinets Flrs G-6
SW DH Build Out
Install Buss Duct Tap Box - SW DH Elec Build Out
Install Branch Panels - SW DH Elec Build Out
Install Buss Duct - SW DH Elec Build Out
Install Buss Duct Disconnet - SW DH Elec Build Out
Run Overhead Piping - SW DH Elec Build Out
Pull Feeders to Branch Panels - SW DH Elec Build Out
Terminate Wiring at Tapbox - SW DH Elec Build Out
Terminate Panel Boards and Main Switch - SW DH Elec Build Out
Install Grounding - SW DH Elec Build Out
Main Electric Room Build Out
Run Overhead Piping for Normal - Main Elec Rm Build Out
Pull Wire and Terminate EM Gear - Main Elec Rm Build Out
Install for Fire Pump Feeder
Pull Wire and Terminate Normal Gear - Main Elec Rm Build Out
Terminate Main Gear - Main Elec Rm Build Out
Demo Overhead Bus Duct
Install Bus Duct to OG&E Vault
OMES - Power Shut Down
OG&E Disconnect Power to Building
Terminate Existing Main Gear
Terminate Tap Boxes
OG&E Terminate at Vault
OG&E Restore Permanent Power
OMES / MCC Restore Building Services
Commissioning of New Gear
Overhead Electrical Rough In
MEP Device Out
Overhead Sprinkler Rough In
Start Date 23-Feb-15
Finish Date 30-Dec-22
Data Date 21-Aug-17
Run Date 30-Aug-17
Page 4 of 33
3707-CR29
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-S01-4310 Complete MCC / FSB Punch List 10 10 21-Aug-17 01-Sep-17
C-S01-4250 Install Access Controll / Security 5 5 30-Aug-17 06-Sep-17
C-S01-4240 Seal Concrete Floor 3 10 20-Sep-17 03-Oct-17
C-S01-4170 Install Hand Sink 2 2 04-Oct-17 05-Oct-17
C-S01-4210 Install Doors & Hardware 2 2 04-Oct-17 05-Oct-17
C-S01-4320 Complete AE1 / Owner Punch List 10 10 06-Oct-17 27-Oct-17
C-S01-4220 Install Light Fixtures 5 5 03-Nov-17 09-Nov-17
C-S01-2960 Fire Marshal Final - Mechanical Room 1 1 19-Feb-18 19-Feb-18
C-S01-3930 Turnover Mechanical Room (Awaiting Public Corridor Open) 0 0 19-Feb-18
Public CorridorPublic Corridor371 321 08-May-17 A 26-Nov-18
C-S01-1980 Construction - Public Corridor 156 126 08-May-17 A 19-Feb-18
C-S01-3030 Overhead Electrical Rough In 10 10 26-Jun-17 A 01-Sep-17
C-S01-3100 Rough In Lights 5 10 01-Aug-17 A 01-Sep-17
C-S01-3040 Overhead Sprinkler Rough In 10 5 07-Aug-17 A 25-Aug-17
C-S01-3135 Complete Floor Demolition (Slab) @ West Entry 5 1 08-Aug-17 A 21-Aug-17
C-S01-3145 F/R/P Floor @ West Entry 3 3 22-Aug-17 24-Aug-17
C-S01-3155 Frame Walls @ West Entry 5 5 25-Aug-17 31-Aug-17
C-S01-7050 Electrical In Wall Rough In @ West Entry 3 3 01-Sep-17 06-Sep-17
C-S01-3115 Install K1 Lights 4 4 06-Sep-17 11-Sep-17
C-S01-7160 Hang Sheetrock Ceiling 5 10 06-Sep-17 19-Sep-17
C-S01-7055 Hang Sheetrock & Plywood @ West Entry 2 2 07-Sep-17 08-Sep-17
C-S01-7060 Tape, Bed & 1st Coat @ West Entry 3 3 11-Sep-17 13-Sep-17
C-S01-3130 Level Five Finish Walls & Ceilings With Paint 5 20 11-Sep-17 06-Oct-17
C-S01-3120 Crown Moulding & Wall Trim 5 20 14-Sep-17 11-Oct-17
C-S01-7065 Install Limestone Columns 26 26 18-Sep-17 31-Oct-17
C-S01-4010 MEP Trim Outs 5 5 04-Oct-17 10-Oct-17
C-S01-4020 Install Temp Lights 5 5 04-Oct-17 10-Oct-17
C-S01-7225 Power Outage - No Work To Occur During This Time 7 7 13-Oct-17 19-Oct-17
C-S01-3140 Install Mud Bed for Marble Floor 5 20 23-Oct-17 17-Nov-17
C-S01-3150 Install Marble Floors 5 30 21-Nov-17 05-Jan-18
C-S01-7045 Grout & Grind Marble Floors 15 15 08-Jan-18 26-Jan-18
C-S01-4040 Final Paint 5 15 15-Jan-18 02-Feb-18
C-S01-4270 Complete MCC / FSB Punch List 10 10 22-Jan-18 02-Feb-18
C-S01-3160 Install Granite Base 5 5 29-Jan-18 02-Feb-18
C-S01-4000 Install Doors & Hardware 5 5 29-Jan-18 02-Feb-18
C-S01-4050 Install Wall Panels 5 5 05-Feb-18 09-Feb-18
C-S01-4060 Install Access Controll / Security 5 5 12-Feb-18 16-Feb-18
C-S01-4280 Complete AE1 / Owner Punch List 10 10 12-Feb-18 23-Feb-18
C-S01-1990 Open Corridor 1A (Main Corridor) & Close Corridor 1B 0 0 19-Feb-18*
J A J A J A A A A J A J A J A A J A J A J
2017 2018 2019 2020 2021 2022 2023
Complete MCC / FSB Punch List
Install Access Controll / Security
Seal Concrete Floor
Install Hand Sink
Install Doors & Hardware
Complete AE1 / Owner Punch List
Install Light Fixtures
Fire Marshal Final - Mechanical Room
Turnover Mechanical Room (Awaiting Public Corridor Open)
Construction - Public Corridor
Overhead Electrical Rough In
Rough In Lights
Overhead Sprinkler Rough In
Complete Floor Demolition (Slab) @ West Entry
F/R/P Floor @ West Entry
Frame Walls @ West Entry
Electrical In Wall Rough In @ West Entry
Install K1 Lights
Hang Sheetrock Ceiling
Hang Sheetrock & Plywood @ West Entry
Tape, Bed & 1st Coat @ West Entry
Level Five Finish Walls & Ceilings With Paint
Crown Moulding & Wall Trim
Install Limestone Columns
MEP Trim Outs
Install Temp Lights
Power Outage - No Work To Occur During This Time
Install Mud Bed for Marble Floor
Install Marble Floors
Grout & Grind Marble Floors
Final Paint
Complete MCC / FSB Punch List
Install Granite Base
Install Doors & Hardware
Install Wall Panels
Install Access Controll / Security
Complete AE1 / Owner Punch List
Open Corridor 1A (Main Corridor) & Close Corridor 1B
Start Date 23-Feb-15
Finish Date 30-Dec-22
Data Date 21-Aug-17
Run Date 30-Aug-17
Page 5 of 33
3707-CR29
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-S01-2910 Fire Marshal Final - House S. / Fitness / Public Corridor / Generator 1 1 19-Feb-18 19-Feb-18
C-S01-4360 Install Historic Lights 5 5 16-Nov-18 26-Nov-18
House StorageHouse Storage90 66 01-Aug-17 A 21-Nov-17
C-S01-1680 Hang Sheetrock 5 2 01-Aug-17 A 22-Aug-17
C-S01-1700 Tape / Bed / Paint Sheetrock 10 9 14-Aug-17 A 31-Aug-17
C-S01-1690 Install Door Frames 1 5 18-Aug-17 A 25-Aug-17
C-S01-1720 Install Ceiling Grid / Border 3 3 28-Aug-17 30-Aug-17
C-S01-1730 Install Lighting 3 3 31-Aug-17 05-Sep-17
C-S01-1740 Install Diffusers 3 3 31-Aug-17 05-Sep-17
C-S01-1750 Trim Sprinklers 3 3 31-Aug-17 05-Sep-17
C-S01-1760 Install Speakers (By Owner) 3 3 31-Aug-17 05-Sep-17
C-S01-1770 Trim Out Fire Alarm Devices 3 3 31-Aug-17 05-Sep-17
C-S01-1940 Tile Break Room & Res troom 3 3 01-Sep-17 06-Sep-17
C-S01-1710 LV / FA / IT Complete 0 0 06-Sep-17
C-S01-1790 Drop Ceiling Tile 1 1 06-Sep-17 06-Sep-17
C-S01-1810 Test & Balance 7 7 06-Sep-17 14-Sep-17
C-S01-1820 Install Floor Finish 3 10 06-Sep-17 19-Sep-17
C-S01-1850 Final Paint 5 5 07-Sep-17 13-Sep-17
C-S01-1880 Trim Out Security Devices 2 2 14-Sep-17 15-Sep-17
C-S01-1870 Hang Doors & Install Hardware 2 2 20-Sep-17 21-Sep-17
C-S01-1780 Install Base & Casing 5 5 20-Sep-17 26-Sep-17
C-S01-1830 Install Cabinets / Millwork 5 5 20-Sep-17 26-Sep-17
C-S01-1900 Install Glazing / Stops 1 1 22-Sep-17 22-Sep-17
C-S01-1840 Set Countertops 5 5 27-Sep-17 03-Oct-17
C-S01-1860 Install Plumbing Fixtures 3 3 04-Oct-17 06-Oct-17
C-S01-1800 Conditioned Air Available 0 0 23-Oct-17
C-S01-1890 Complete MCC / FSB Punch List 10 10 23-Oct-17 03-Nov-17
C-S01-1920 Touch Up Paint 1 1 06-Nov-17 06-Nov-17
C-S01-1910 Final Clean 1 1 07-Nov-17 07-Nov-17
C-S01-1930 Complete AE1 / Owner Punch List 10 10 08-Nov-17 21-Nov-17
FitnessFitness85 66 14-Aug-17 A 21-Nov-17
C-S01-2150 Hang Sheetrock 5 5 14-Aug-17 A 25-Aug-17
C-S01-2160 Install Door Frames 1 1 23-Aug-17 23-Aug-17
C-S01-2170 Tape / Bed / Paint Sheetrock 10 10 28-Aug-17 11-Sep-17
C-S01-2180 Install Ceiling Grid / Border 3 3 12-Sep-17 14-Sep-17
C-S01-2200 Install Lighting 3 3 12-Sep-17 14-Sep-17
C-S01-2250 Install Floor Finish 3 3 12-Sep-17 14-Sep-17
C-S01-2330 Hang Doors & Install Hardware 2 2 15-Sep-17 18-Sep-17
C-S01-2210 Install Diffusers 3 3 15-Sep-17 19-Sep-17
J A J A J A A A A J A J A J A A J A J A J
2017 2018 2019 2020 2021 2022 2023
Fire Marshal Final - House S. / Fitness / Public Corridor / Generator
Install Historic Lights
Hang Sheetrock
Tape / Bed / Paint Sheetrock
Install Door Frames
Install Ceiling Grid / Border
Install Lighting
Install Diffusers
Trim Sprinklers
Install Speakers (By Owner)
Trim Out Fire Alarm Devices
Tile Break Room & Res troom
LV / FA / IT Complete
Drop Ceiling Tile
Test & Balance
Install Floor Finish
Final Paint
Trim Out Security Devices
Hang Doors & Install Hardware
Install Base & Casing
Install Cabinets / Millwork
Install Glazing / Stops
Set Countertops
Install Plumbing Fixtures
Conditioned Air Available
Complete MCC / FSB Punch List
Touch Up Paint
Final Clean
Complete AE1 / Owner Punch List
Hang Sheetrock
Install Door Frames
Tape / Bed / Paint Sheetrock
Install Ceiling Grid / Border
Install Lighting
Install Floor Finish
Hang Doors & Install Hardware
Install Diffusers
Start Date 23-Feb-15
Finish Date 30-Dec-22
Data Date 21-Aug-17
Run Date 30-Aug-17
Page 6 of 33
3707-CR29
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-S01-2220 Trim Sprinklers 3 3 15-Sep-17 19-Sep-17
C-S01-2230 Install Speakers (By Owner) 3 3 15-Sep-17 19-Sep-17
C-S01-2240 Trim Out Fire Alarm Devices 3 3 15-Sep-17 19-Sep-17
C-S01-2320 Install Lockers 5 5 15-Sep-17 21-Sep-17
C-S01-2190 Tile Res trooms 15 15 15-Sep-17 05-Oct-17
C-S01-2340 Install Glazing / Stops 1 1 19-Sep-17 19-Sep-17
C-S01-2260 LV / FA / IT Complete 0 0 20-Sep-17
C-S01-2270 Drop Ceiling Tile 1 1 20-Sep-17 20-Sep-17
C-S01-2280 Test & Balance 7 7 20-Sep-17 28-Sep-17
C-S01-2300 Final Paint 5 5 21-Sep-17 27-Sep-17
C-S01-2350 Trim Out Security Devices 2 2 28-Sep-17 29-Sep-17
C-S01-2360 Set Countertops 5 5 06-Oct-17 12-Oct-17
C-S01-2290 Conditioned Air Available 0 0 23-Oct-17
C-S01-2370 Install Plumbing Fixtures 3 3 23-Oct-17 25-Oct-17
C-S01-2310 Complete MCC / FSB Punch List 10 10 23-Oct-17 03-Nov-17
C-S01-2380 Touch Up Paint 1 1 06-Nov-17 06-Nov-17
C-S01-2390 Final Clean 1 1 07-Nov-17 07-Nov-17
C-S01-2400 Complete AE1 / Owner Punch List 10 10 08-Nov-17 21-Nov-17
C-S01-2040 Install Hot Water Heater 2 2 12-Sep-17 13-Sep-17
C-S01-2420 Install Bathroom Partitions & Accessories 3 3 26-Oct-17 30-Oct-17
ElectionElection97 97 22-Nov-17 11-Apr-18
C-S01-2430 Lay Out Walls 1 1 22-Nov-17 22-Nov-17
C-S01-2460 Rough In Sprinklers 5 5 27-Nov-17 01-Dec-17
C-S01-2470 Rough In Mechanicial Pipe 5 5 27-Nov-17 01-Dec-17
C-S01-2480 Install U/G Plumbing 5 5 27-Nov-17 01-Dec-17
C-S01-2440 Rough In O/H Electric 10 10 27-Nov-17 08-Dec-17
C-S01-2450 Rough In O/H Mechanical w/ HP 15 15 27-Nov-17 15-Dec-17
C-S01-2490 Frame Walls 7 7 04-Dec-17 12-Dec-17
C-S01-2510 Rough In In Walls 10 10 13-Dec-17 27-Dec-17
C-S01-2520 Frame Hard Lids 5 5 28-Dec-17 04-Jan-18
C-S01-2530 Hang Sheetrock 10 10 05-Jan-18 18-Jan-18
C-S01-2540 Install Door Frames 3 3 19-Jan-18 23-Jan-18
C-S01-2550 Tape / Bed / Paint Sheetrock 10 10 19-Jan-18 01-Feb-18
C-S01-2560 Install Ceiling Grid / Border 3 3 02-Feb-18 06-Feb-18
C-S01-2580 Tile Break Room 5 5 02-Feb-18 08-Feb-18
C-S01-2570 Install Base & Casing 10 10 02-Feb-18 15-Feb-18
C-S01-2590 Install Lighting 3 3 07-Feb-18 09-Feb-18
C-S01-2600 Install Diffusers 3 3 07-Feb-18 09-Feb-18
C-S01-2610 Trim Sprinklers 3 3 07-Feb-18 09-Feb-18
J A J A J A A A A J A J A J A A J A J A J
2017 2018 2019 2020 2021 2022 2023
Trim Sprinklers
Install Speakers (By Owner)
Trim Out Fire Alarm Devices
Install Lockers
Tile Res trooms
Install Glazing / Stops
LV / FA / IT Complete
Drop Ceiling Tile
Test & Balance
Final Paint
Trim Out Security Devices
Set Countertops
Conditioned Air Available
Install Plumbing Fixtures
Complete MCC / FSB Punch List
Touch Up Paint
Final Clean
Complete AE1 / Owner Punch List
Install Hot Water Heater
Install Bathroom Partitions & Accessories
Lay Out Walls
Rough In Sprinklers
Rough In Mechanicial Pipe
Install U/G Plumbing
Rough In O/H Electric
Rough In O/H Mechanical w/ HP
Frame Walls
Rough In In Walls
Frame Hard Lids
Hang Sheetrock
Install Door Frames
Tape / Bed / Paint Sheetrock
Install Ceiling Grid / Border
Tile Break Room
Install Base & Casing
Install Lighting
Install Diffusers
Trim Sprinklers
Start Date 23-Feb-15
Finish Date 30-Dec-22
Data Date 21-Aug-17
Run Date 30-Aug-17
Page 7 of 33
3707-CR29
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-S01-2620 Install Speakers (By Owner) 3 3 07-Feb-18 09-Feb-18
C-S01-2630 Trim Out Fire Alarm Devices 3 3 07-Feb-18 09-Feb-18
C-S01-2650 LV / FA / IT Complete 0 0 12-Feb-18
C-S01-2660 Drop Ceiling Tile 1 1 12-Feb-18 12-Feb-18
C-S01-2670 Test & Balance 5 5 12-Feb-18 16-Feb-18
C-S01-2680 Conditioned Air Available 0 0 12-Feb-18
C-S01-2690 Final Paint 3 3 13-Feb-18 15-Feb-18
C-S01-2700 Complete MCC / FSB Punch List 10 10 13-Feb-18 26-Feb-18
C-S01-2740 Trim Out Security Devices 2 2 16-Feb-18 19-Feb-18
C-S01-2640 Install Floor Finish 10 10 27-Feb-18 12-Mar-18
C-S01-2720 Hang Doors & Install Hardware 2 2 13-Mar-18 14-Mar-18
C-S01-2710 Install Cabinets 5 5 13-Mar-18 19-Mar-18
C-S01-2730 Install Glazing / Stops 1 1 15-Mar-18 15-Mar-18
C-S01-2750 Set Countertops 1 1 20-Mar-18 20-Mar-18
C-S01-2760 Install Plumbing Fixtures 3 3 21-Mar-18 23-Mar-18
C-S01-2770 Touch Up Paint 1 1 26-Mar-18 26-Mar-18
C-S01-2780 Final Clean 1 1 27-Mar-18 27-Mar-18
C-S01-2790 Complete AE1 / Owner Punch List 10 10 28-Mar-18 10-Apr-18
C-S01-2800 Install Built Ins 10 10 13-Feb-18 26-Feb-18
C-S01-2950 Fire Marshal Final - Election 1 1 11-Apr-18 11-Apr-18
EthicsEthics97 97 22-Nov-17 11-Apr-18
C-S01-3540 Lay Out Walls 1 1 22-Nov-17 22-Nov-17
C-S01-3570 Rough In Sprinklers 5 5 27-Nov-17 01-Dec-17
C-S01-3580 Rough In Mechanicial Pipe 5 5 27-Nov-17 01-Dec-17
C-S01-3590 Install U/G Plumbing 5 5 27-Nov-17 01-Dec-17
C-S01-3550 Rough In O/H Electric 10 10 27-Nov-17 08-Dec-17
C-S01-3560 Rough In O/H Mechanical w/ HP 15 15 27-Nov-17 15-Dec-17
C-S01-3600 Frame Walls 3 3 04-Dec-17 06-Dec-17
C-S01-3610 Rough In In Walls 10 10 07-Dec-17 20-Dec-17
C-S01-3620 Frame Hard Lids 2 2 21-Dec-17 22-Dec-17
C-S01-3630 Hang Sheetrock 5 5 26-Dec-17 02-Jan-18
C-S01-3640 Install Door Frames 2 2 03-Jan-18 04-Jan-18
C-S01-3650 Tape / Bed / Paint Sheetrock 10 10 03-Jan-18 16-Jan-18
C-S01-3660 Install Ceiling Grid / Border 3 3 17-Jan-18 19-Jan-18
C-S01-3680 Tile Break Room 5 5 17-Jan-18 23-Jan-18
C-S01-3670 Install Base & Casing 7 7 17-Jan-18 25-Jan-18
C-S01-3690 Install Lighting 3 3 22-Jan-18 24-Jan-18
C-S01-3700 Install Diffusers 3 3 22-Jan-18 24-Jan-18
C-S01-3710 Trim Sprinklers 3 3 22-Jan-18 24-Jan-18
J A J A J A A A A J A J A J A A J A J A J
2017 2018 2019 2020 2021 2022 2023
Install Speakers (By Owner)
Trim Out Fire Alarm Devices
LV / FA / IT Complete
Drop Ceiling Tile
Test & Balance
Conditioned Air Available
Final Paint
Complete MCC / FSB Punch List
Trim Out Security Devices
Install Floor Finish
Hang Doors & Install Hardware
Install Cabinets
Install Glazing / Stops
Set Countertops
Install Plumbing Fixtures
Touch Up Paint
Final Clean
Complete AE1 / Owner Punch List
Install Built Ins
Fire Marshal Final - Election
Lay Out Walls
Rough In Sprinklers
Rough In Mechanicial Pipe
Install U/G Plumbing
Rough In O/H Electric
Rough In O/H Mechanical w/ HP
Frame Walls
Rough In In Walls
Frame Hard Lids
Hang Sheetrock
Install Door Frames
Tape / Bed / Paint Sheetrock
Install Ceiling Grid / Border
Tile Break Room
Install Base & Casing
Install Lighting
Install Diffusers
Trim Sprinklers
Start Date 23-Feb-15
Finish Date 30-Dec-22
Data Date 21-Aug-17
Run Date 30-Aug-17
Page 8 of 33
3707-CR29
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-S01-3720 Install Speakers (By Owner) 3 3 22-Jan-18 24-Jan-18
C-S01-3730 Trim Out Fire Alarm Devices 3 3 22-Jan-18 24-Jan-18
C-S01-3740 LV / FA / IT Complete 0 0 25-Jan-18
C-S01-3750 Drop Ceiling Tile 1 1 25-Jan-18 25-Jan-18
C-S01-3760 Test & Balance 5 5 25-Jan-18 31-Jan-18
C-S01-3770 Conditioned Air Available 0 0 25-Jan-18
C-S01-3790 Final Paint 3 3 26-Jan-18 30-Jan-18
C-S01-3780 Install Floor Finish 10 10 26-Jan-18 08-Feb-18
C-S01-3800 Complete MCC / FSB Punch List 10 10 26-Jan-18 08-Feb-18
C-S01-3810 Trim Out Security Devices 2 2 31-Jan-18 01-Feb-18
C-S01-3830 Hang Doors & Install Hardware 2 2 09-Feb-18 12-Feb-18
C-S01-3820 Install Cabinets 5 5 09-Feb-18 15-Feb-18
C-S01-3840 Install Glazing / Stops 1 1 13-Feb-18 13-Feb-18
C-S01-3850 Set Countertops 1 1 16-Feb-18 16-Feb-18
C-S01-3860 Install Plumbing Fixtures 3 3 19-Feb-18 21-Feb-18
C-S01-3870 Touch Up Paint 1 1 22-Feb-18 22-Feb-18
C-S01-3880 Final Clean 1 1 23-Feb-18 23-Feb-18
C-S01-3890 Complete AE1 / Owner Punch List 10 10 26-Feb-18 09-Mar-18
C-S01-3910 Fire Marshal Final - Ethics 1 1 11-Apr-18 11-Apr-18
House PrintHouse Print97 97 22-Nov-17 11-Apr-18
C-S01-3170 Lay Out Walls 1 1 22-Nov-17 22-Nov-17
C-S01-3180 Rough In O/H Electric 5 5 27-Nov-17 01-Dec-17
C-S01-3200 Rough In Sprinklers 5 5 27-Nov-17 01-Dec-17
C-S01-3210 Rough In Mechanicial Pipe 5 5 27-Nov-17 01-Dec-17
C-S01-3220 Install U/G Plumbing 5 5 27-Nov-17 01-Dec-17
C-S01-3190 Rough In O/H Mechanical w/ HP 10 10 27-Nov-17 08-Dec-17
C-S01-3230 Frame Walls 1 1 04-Dec-17 04-Dec-17
C-S01-3250 Rough In In Walls 2 2 05-Dec-17 06-Dec-17
C-S01-3260 Frame Hard Lids 1 1 07-Dec-17 07-Dec-17
C-S01-3270 Hang Sheetrock 1 1 08-Dec-17 08-Dec-17
C-S01-3280 Install Door Frames 1 1 11-Dec-17 11-Dec-17
C-S01-3290 Tape / Bed / Paint Sheetrock 3 3 11-Dec-17 13-Dec-17
C-S01-3300 Install Ceiling Grid / Border 3 3 14-Dec-17 18-Dec-17
C-S01-3310 Install Base & Casing 3 3 14-Dec-17 18-Dec-17
C-S01-3320 Tile Break Room 3 3 14-Dec-17 18-Dec-17
C-S01-3340 Install Diffusers 1 1 19-Dec-17 19-Dec-17
C-S01-3350 Trim Sprinklers 1 1 19-Dec-17 19-Dec-17
C-S01-3360 Install Speakers (By Owner) 1 1 19-Dec-17 19-Dec-17
C-S01-3370 Trim Out Fire Alarm Devices 1 1 19-Dec-17 19-Dec-17
J A J A J A A A A J A J A J A A J A J A J
2017 2018 2019 2020 2021 2022 2023
Install Speakers (By Owner)
Trim Out Fire Alarm Devices
LV / FA / IT Complete
Drop Ceiling Tile
Test & Balance
Conditioned Air Available
Final Paint
Install Floor Finish
Complete MCC / FSB Punch List
Trim Out Security Devices
Hang Doors & Install Hardware
Install Cabinets
Install Glazing / Stops
Set Countertops
Install Plumbing Fixtures
Touch Up Paint
Final Clean
Complete AE1 / Owner Punch List
Fire Marshal Final - Ethics
Lay Out Walls
Rough In O/H Electric
Rough In Sprinklers
Rough In Mechanicial Pipe
Install U/G Plumbing
Rough In O/H Mechanical w/ HP
Frame Walls
Rough In In Walls
Frame Hard Lids
Hang Sheetrock
Install Door Frames
Tape / Bed / Paint Sheetrock
Install Ceiling Grid / Border
Install Base & Casing
Tile Break Room
Install Diffusers
Trim Sprinklers
Install Speakers (By Owner)
Trim Out Fire Alarm Devices
Start Date 23-Feb-15
Finish Date 30-Dec-22
Data Date 21-Aug-17
Run Date 30-Aug-17
Page 9 of 33
3707-CR29
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-S01-3330 Install Lighting 3 3 19-Dec-17 21-Dec-17
C-S01-3380 Install Floor Finish 3 3 19-Dec-17 21-Dec-17
C-S01-3410 Test & Balance 3 3 20-Dec-17 22-Dec-17
C-S01-3390 LV / FA / IT Complete 0 0 22-Dec-17
C-S01-3400 Drop Ceiling Tile 1 1 22-Dec-17 22-Dec-17
C-S01-3450 Install Cabinets 1 1 22-Dec-17 22-Dec-17
C-S01-3460 Hang Doors & Install Hardware 1 1 22-Dec-17 22-Dec-17
C-S01-3420 Conditioned Air Available 0 0 22-Dec-17
C-S01-3490 Set Countertops 1 1 26-Dec-17 26-Dec-17
C-S01-3470 Install Glazing / Stops 1 1 26-Dec-17 26-Dec-17
C-S01-3430 Final Paint 3 3 26-Dec-17 28-Dec-17
C-S01-3440 Complete MCC / FSB Punch List 5 5 26-Dec-17 02-Jan-18
C-S01-3500 Install Plumbing Fixtures 1 1 27-Dec-17 27-Dec-17
C-S01-3480 Trim Out Security Devices 1 1 29-Dec-17 29-Dec-17
C-S01-3510 Touch Up Paint 2 2 03-Jan-18 04-Jan-18
C-S01-3520 Final Clean 1 1 05-Jan-18 05-Jan-18
C-S01-3530 Complete AE1 / Owner Punch List 10 10 08-Jan-18 19-Jan-18
C-S01-3900 Fire Marshal Final - House Print 1 1 11-Apr-18 11-Apr-18
GeneratorGenerator106 106 21-Aug-17 22-Jan-18
C-S01-7200 Set Trench Box East of Enclosure 1 1 21-Aug-17 21-Aug-17
C-S01-7215 MCC Remove/ Demo Existing Deck 1 1 21-Aug-17 21-Aug-17
C-S01-2980 Install Grate 5 10 21-Aug-17 01-Sep-17
C-S01-7205 Waterproof East of Enc losure 2 2 22-Aug-17 23-Aug-17
C-S01-7220 Remove Rust off Existing Beams & Paint 4 4 22-Aug-17 25-Aug-17
C-S01-7210 Backfill East of Enclosure 1 1 24-Aug-17 24-Aug-17
C-S01-2990 Set Generator 0 0 25-Aug-17
C-S01-2885 JE Dunn - Waterproof West Plaza 5 5 28-Aug-17 01-Sep-17
C-S01-1000 Install Duct to Generator 15 15 28-Aug-17 18-Sep-17
C-S01-2895 JE Dunn - FRP West Plaza Deck 3 3 05-Sep-17 07-Sep-17
C-S01-1080 Install Mechanical Piping to Generator 15 15 19-Sep-17 09-Oct-17
C-S01-3010 Install Electical Piping to Generator 20 20 10-Oct-17 14-Nov-17
C-S01-1135 Feeder Install for Generator Feeds 7 7 15-Nov-17 27-Nov-17
C-S01-1175 Final Tie into Generator 35 35 15-Nov-17 08-Jan-18
C-S01-3000 Install Electrical to Generator 3 3 28-Nov-17 30-Nov-17
C-S01-4330 Complete MCC / FSB Punch List 10 10 28-Nov-17 11-Dec-17
C-S01-1205 Commissioning of New Generator 3 3 09-Jan-18 11-Jan-18
C-S01-4340 Complete AE1 / Owner Punch List 10 10 09-Jan-18 22-Jan-18
Sequence 2Sequence 2400 400 08-Sep-17 05-Apr-19
J A J A J A A A A J A J A J A A J A J A J
2017 2018 2019 2020 2021 2022 2023
Install Lighting
Install Floor Finish
Test & Balance
LV / FA / IT Complete
Drop Ceiling Tile
Install Cabinets
Hang Doors & Install Hardware
Conditioned Air Available
Set Countertops
Install Glazing / Stops
Final Paint
Complete MCC / FSB Punch List
Install Plumbing Fixtures
Trim Out Security Devices
Touch Up Paint
Final Clean
Complete AE1 / Owner Punch List
Fire Marshal Final - House Print
Set Trench Box East of Enclosure
MCC Remove/ Demo Existing Deck
Install Grate
Waterproof East of Enc losure
Remove Rust off Existing Beams & Paint
Backfill East of Enclosure
Set Generator
JE Dunn - Waterproof West Plaza
Install Duct to Generator
JE Dunn - FRP West Plaza Deck
Install Mechanical Piping to Generator
Install Electical Piping to Generator
Feeder Install for Generator Feeds
Final Tie into Generator
Install Electrical to Generator
Complete MCC / FSB Punch List
Commissioning of New Generator
Complete AE1 / Owner Punch List
Start Date 23-Feb-15
Finish Date 30-Dec-22
Data Date 21-Aug-17
Run Date 30-Aug-17
Page 10 of 33
3707-CR29
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
ConstructionConstruction400 400 08-Sep-17 05-Apr-19
Construction Phase SummariesConstruction Phase Summaries400 400 08-Sep-17 05-Apr-19
C-S02-1010 Install Fire Pump 1 1 08-Sep-17 08-Sep-17
C-S02-1020 OMES / JEDUNN to Complete Water Proofing at Loading Dock 0 0 10-Apr-18
S-S02-1000 Construction - Sequence 2 360 360 11-Apr-18 05-Apr-19
Sequence 3Sequence 3285 285 06-Apr-19 15-Jan-20
ConstructionConstruction285 285 06-Apr-19 15-Jan-20
Construction Phase SummariesConstruction Phase Summaries285 285 06-Apr-19 15-Jan-20
S-S03-1000 Construction - Sequence 3 285 285 06-Apr-19 15-Jan-20
Sequence 4Sequence 4285 285 27-Nov-20 07-Sep-21
ConstructionConstruction285 285 27-Nov-20 07-Sep-21
Construction Phase SummariesConstruction Phase Summaries285 285 27-Nov-20 07-Sep-21
S-S04-1000 Construction - Sequence 4 285 285 27-Nov-20 07-Sep-21
CoreCore1417 1361 05-Jun-17 A 30-Dec-22
Risers / Fresh AirRisers / Fresh Air509 314 05-Jun-17 A 13-Nov-18
ConstructionConstruction509 314 05-Jun-17 A 13-Nov-18
Schedule Driven MilestonesSchedule Driven Milestones263 263 31-Oct-17 13-Nov-18
M-C01-1025 Risers Complete - SW 0 0 31-Oct-17
M-C01-1000 Risers Complete - NW 0 0 30-Nov-17
M-C01-1005 Risers Complete - North 0 0 05-Jan-18
M-C01-1010 Risers Complete - South 0 0 19-Mar-18
M-C01-1020 Risers Complete - NE 0 0 18-Sep-18
M-C01-1015 Risers Complete - SE 0 0 13-Nov-18
Construction Phase SummariesConstruction Phase Summaries733 450 05-Jun-17 A 13-Nov-18
S-C01-1000 Construction - Risers / Fresh Air 729 450 05-Jun-17 A 13-Nov-18
S-C01-1015 Construction - SW Risers 139 50 05-Jun-17 A 09-Oct-17
S-C01-1025 Construction - NW Risers 183 102 07-Jun-17 A 30-Nov-17
S-C01-1040 Construction - North Risers 115 123 05-Sep-17 05-Jan-18
S-C01-1045 Construction - South Risers 120 120 20-Nov-17 19-Mar-18
S-C01-1035 Construction - NE Risers 233 231 31-Jan-18 18-Sep-18
S-C01-1030 Construction - SE Risers 289 287 31-Jan-18 13-Nov-18
SW - Offices 508 and 510 Outside AirSW - Offices 508 and 510 Outside Air19 19 21-Aug-17 15-Sep-17
C-C01-4535 Demo and Install Temp Roof Penetration Curb Cap 1 1 21-Aug-17 21-Aug-17
C-C01-4540 Install Outside Air Level 5 to Roof 2 2 22-Aug-17 23-Aug-17
J A J A J A A A A J A J A J A A J A J A J
2017 2018 2019 2020 2021 2022 2023
Install Fire Pump
OMES / JEDUNN to Complete Water Proofing at Loading Dock
Construction - Sequence 2
Construction - Sequence 3
Construction - Sequence 4
Risers Complete - SW
Risers Complete - NW
Risers Complete - North
Risers Complete - South
Risers Complete - NE
Risers Complete - SE
Construction - Risers / Fresh Air
Construction - SW Risers
Construction - NW Risers
Construction - North Risers
Construction - South Risers
Construction - NE Risers
Construction - SE Risers
Demo and Install Temp Roof Penetration Curb Cap
Install Outside Air Level 5 to Roof
Start Date 23-Feb-15
Finish Date 30-Dec-22
Data Date 21-Aug-17
Run Date 30-Aug-17
Page 11 of 33
3707-CR29
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-C01-3760 Install Shaft Walls / Access Panels 4 4 24-Aug-17 29-Aug-17
C-C01-4545 Tape, Bed, Paint 5 5 30-Aug-17 06-Sep-17
C-C01-4550 Re-Install Floor Finishes 2 2 07-Sep-17 08-Sep-17
C-C01-4555 Test Smoke / Fire Damper 1 1 11-Sep-17 11-Sep-17
C-C01-4560 Remove Temp Walls 2 2 12-Sep-17 13-Sep-17
C-C01-4565 Final Clean 2 2 14-Sep-17 15-Sep-17
SW - Rooms 200, 206 Outside AirSW - Rooms 200, 206 Outside Air4 3 18-Aug-17 A 23-Aug-17
C-C01-1385 Remove Temp Walls 2 1 18-Aug-17 A 21-Aug-17
C-C01-1390 Final Clean 2 2 22-Aug-17 23-Aug-17
SW - Stairwell Restroom Outside AirSW - Stairwell Restroom Outside Air45 45 22-Aug-17 24-Oct-17
C-C01-4620 Redesign Stairwell 10 10 22-Aug-17 05-Sep-17
C-C01-4575 Fire Caulk / Seal Floor Penetration @ Riser 3 3 06-Sep-17 08-Sep-17
C-C01-4580 Install Smoke / Fire Damper 5 5 11-Sep-17 15-Sep-17
C-C01-4585 Install Shaft Walls / Access Panels 5 5 18-Sep-17 22-Sep-17
C-C01-4590 Tape, Bed, Paint 5 5 25-Sep-17 29-Sep-17
C-C01-4595 Re-Install Ceiling Grid & Tile 3 3 02-Oct-17 04-Oct-17
C-C01-4600 Re-Install Floor Finishes 3 3 05-Oct-17 09-Oct-17
C-C01-4605 Test Smoke / Fire Damper 1 1 10-Oct-17 10-Oct-17
C-C01-4610 Remove Temp Walls 2 2 11-Oct-17 12-Oct-17
C-C01-4615 Final Clean 2 2 23-Oct-17 24-Oct-17
SW - Room 205 Outside AirSW - Room 205 Outside Air10 10 21-Aug-17 01-Sep-17
C-C01-4570 Install Main E/W Outside Air Duct 10 10 21-Aug-17 01-Sep-17
SW - Rooms 301 & 305A Outside AirSW - Rooms 301 & 305A Outside Air30 15 14-Aug-17 A 11-Sep-17
C-C01-1420 Install Shaft Walls / Access Panels 4 2 14-Aug-17 A 22-Aug-17
C-C01-1425 Tape, Bed, Paint 4 4 23-Aug-17 28-Aug-17
C-C01-1430 Re-Install Ceiling Grid & Tile 2 2 29-Aug-17 30-Aug-17
C-C01-1435 Re-Install Floor Finishes 2 2 31-Aug-17 01-Sep-17
C-C01-1440 Test Smoke / Fire Damper 1 1 05-Sep-17 05-Sep-17
C-C01-1445 Remove Temp Walls 2 2 06-Sep-17 07-Sep-17
C-C01-1450 Final Clean 2 2 08-Sep-17 11-Sep-17
SW - Rooms 401, 411 Outside AirSW - Rooms 401, 411 Outside Air16 12 17-Aug-17 A 06-Sep-17
C-C01-1485 Tape, Bed, Paint 4 3 17-Aug-17 A 23-Aug-17
C-C01-1490 Re-Install Ceiling Grid & Tile 2 2 24-Aug-17 25-Aug-17
C-C01-1495 Re-Install Floor Finishes 2 2 28-Aug-17 29-Aug-17
C-C01-1500 Test Smoke / Fire Damper 1 1 30-Aug-17 30-Aug-17
C-C01-1505 Remove Temp Walls 2 2 31-Aug-17 01-Sep-17
C-C01-1510 Final Clean 2 2 05-Sep-17 06-Sep-17
SW - Womens Restroom Outside AirSW - Womens Restroom Outside Air51 51 21-Aug-17 31-Oct-17
J A J A J A A A A J A J A J A A J A J A J
2017 2018 2019 2020 2021 2022 2023
Install Shaft Walls / Access Panels
Tape, Bed, Paint
Re-Install Floor Finishes
Test Smoke / Fire Damper
Remove Temp Walls
Final Clean
Remove Temp Walls
Final Clean
Redesign Stairwell
Fire Caulk / Seal Floor Penetration @ Riser
Install Smoke / Fire Damper
Install Shaft Walls / Access Panels
Tape, Bed, Paint
Re-Install Ceiling Grid & Tile
Re-Install Floor Finishes
Test Smoke / Fire Damper
Remove Temp Walls
Final Clean
Install Main E/W Outside Air Duct
Install Shaft Walls / Access Panels
Tape, Bed, Paint
Re-Install Ceiling Grid & Tile
Re-Install Floor Finishes
Test Smoke / Fire Damper
Remove Temp Walls
Final Clean
Tape, Bed, Paint
Re-Install Ceiling Grid & Tile
Re-Install Floor Finishes
Test Smoke / Fire Damper
Remove Temp Walls
Final Clean
Start Date 23-Feb-15
Finish Date 30-Dec-22
Data Date 21-Aug-17
Run Date 30-Aug-17
Page 12 of 33
3707-CR29
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-C01-4690 Redesign Women's Restroom 10 10 21-Aug-17 01-Sep-17
C-C01-4625 Install Temp Walls 2 2 05-Sep-17 06-Sep-17
C-C01-4630 Demo Walls & Ceilings 4 4 07-Sep-17 12-Sep-17
C-C01-4635 Saw Cut Floor 1 1 13-Sep-17 13-Sep-17
C-C01-4640 Install Outside Air Riser 5 5 14-Sep-17 20-Sep-17
C-C01-4645 Fire Caulk / Seal Floor Penetration @ Riser 2 2 21-Sep-17 22-Sep-17
C-C01-4650 Install Smoke / Fire Damper 4 4 25-Sep-17 28-Sep-17
C-C01-4655 Install Shaft Walls / Access Panels 4 4 29-Sep-17 04-Oct-17
C-C01-4660 Tape, Bed, Paint 4 4 05-Oct-17 10-Oct-17
C-C01-4665 Re-Install Ceiling Grid & Tile 2 2 11-Oct-17 12-Oct-17
C-C01-4670 Re-Install Floor Finishes 2 2 23-Oct-17 24-Oct-17
C-C01-4675 Test Smoke / Fire Damper 1 1 25-Oct-17 25-Oct-17
C-C01-4680 Remove Temp Walls 2 2 26-Oct-17 27-Oct-17
C-C01-4685 Final Clean 2 2 30-Oct-17 31-Oct-17
SW - Rooms 500A & 500 Outside AirSW - Rooms 500A & 500 Outside Air17 17 19-Sep-17 11-Oct-17
C-C01-1540 Install Shaft Walls / Access Panels 4 4 19-Sep-17 22-Sep-17
C-C01-1545 Tape, Bed, Paint 4 4 25-Sep-17 28-Sep-17
C-C01-1550 Re-Install Ceiling Grid & Tile 2 2 29-Sep-17 02-Oct-17
C-C01-1555 Re-Install Floor Finishes 2 2 03-Oct-17 04-Oct-17
C-C01-1560 Test Smoke / Fire Damper 1 1 05-Oct-17 05-Oct-17
C-C01-1565 Remove Temp Walls 2 2 06-Oct-17 09-Oct-17
C-C01-1570 Final Clean 2 2 10-Oct-17 11-Oct-17
SW - 6th FloorSW - 6th Floor20 20 21-Aug-17 18-Sep-17
C-C01-1585 Saw Cut Floor 5 5 21-Aug-17 25-Aug-17
C-C01-1590 Install Outside Air Riser 5 5 28-Aug-17 01-Sep-17
C-C01-1660 Fire Caulk / Seal Floor Penetration @ Riser 5 5 05-Sep-17 11-Sep-17
C-C01-1595 Install Smoke / Fire Damper 5 5 12-Sep-17 18-Sep-17
SW - RooftopSW - Rooftop43 33 23-Aug-17 09-Oct-17
C-C01-1000 Set Roof Top Equipment (SW) 3 3 23-Aug-17 25-Aug-17
C-C01-1010 Install SW Roof Top Equipment 40 20 28-Aug-17 25-Sep-17
C-C01-1020 Start Up SW Roof Top Equipment 10 10 26-Sep-17 09-Oct-17
NW - Offices 548, 540A, 539 Outside AirNW - Offices 548, 540A, 539 Outside Air25 25 21-Aug-17 25-Sep-17
C-C01-1270 OMES (House Employees) Move In 4 4 21-Aug-17 24-Aug-17
C-C01-3795 Install Shaft Walls / Access Panels 5 5 19-Sep-17 25-Sep-17
NW - Room 109.37 Outside AirNW - Room 109.37 Outside Air2 1 21-Aug-17 21-Aug-17
C-C01-1790 Final Clean 2 1 21-Aug-17 21-Aug-17
NW - Rooms 240, 242, 250, Supreme Court Outside AirNW - Rooms 240, 242, 250, Supreme Court Outside Air30 13 17-Aug-17 A 07-Sep-17
C-C01-1830 Tape, Bed, Paint 5 2 17-Aug-17 A 22-Aug-17
J A J A J A A A A J A J A J A A J A J A J
2017 2018 2019 2020 2021 2022 2023
Redesign Women's Restroom
Install Temp Walls
Demo Walls & Ceilings
Saw Cut Floor
Install Outside Air Riser
Fire Caulk / Seal Floor Penetration @ Riser
Install Smoke / Fire Damper
Install Shaft Walls / Access Panels
Tape, Bed, Paint
Re-Install Ceiling Grid & Tile
Re-Install Floor Finishes
Test Smoke / Fire Damper
Remove Temp Walls
Final Clean
Install Shaft Walls / Access Panels
Tape, Bed, Paint
Re-Install Ceiling Grid & Tile
Re-Install Floor Finishes
Test Smoke / Fire Damper
Remove Temp Walls
Final Clean
Saw Cut Floor
Install Outside Air Riser
Fire Caulk / Seal Floor Penetration @ Riser
Install Smoke / Fire Damper
Set Roof Top Equipment (SW)
Install SW Roof Top Equipment
Start Up SW Roof Top Equipment
OMES (House Employees) Move In
Install Shaft Walls / Access Panels
Final Clean
Tape, Bed, Paint
Start Date 23-Feb-15
Finish Date 30-Dec-22
Data Date 21-Aug-17
Run Date 30-Aug-17
Page 13 of 33
3707-CR29
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-C01-1835 Re-Install Ceiling Grid & Tile 3 3 23-Aug-17 25-Aug-17
C-C01-1840 Re-Install Floor Finishes 3 3 28-Aug-17 30-Aug-17
C-C01-1845 Test Smoke / Fire Damper 1 1 31-Aug-17 31-Aug-17
C-C01-1850 Remove Temp Walls 2 2 01-Sep-17 05-Sep-17
C-C01-1855 Final Clean 2 2 06-Sep-17 07-Sep-17
NW - Mech RmNW - Mech Rm63 36 13-Jul-17 A 10-Oct-17
C-C01-4735 Redesign Mech Rm 10 10 13-Jul-17 A 01-Sep-17
C-C01-4695 Install Smoke / Fire Damper 5 5 05-Sep-17 11-Sep-17
C-C01-4700 Install Shaft Walls / Access Panels 5 5 12-Sep-17 18-Sep-17
C-C01-4705 Tape, Bed, Paint 5 5 19-Sep-17 25-Sep-17
C-C01-4710 Re-Install Ceiling Grid & Tile 3 3 26-Sep-17 28-Sep-17
C-C01-4715 Re-Install Floor Finishes 3 3 29-Sep-17 03-Oct-17
C-C01-4720 Test Smoke / Fire Damper 1 1 04-Oct-17 04-Oct-17
C-C01-4725 Remove Temp Walls 2 2 05-Oct-17 06-Oct-17
C-C01-4730 Final Clean 2 2 09-Oct-17 10-Oct-17
NW - Rooms 328 & 338 Outside AirNW - Rooms 328 & 338 Outside Air26 11 19-Aug-17 A 05-Sep-17
C-C01-1895 Tape, Bed, Paint 4 2 19-Aug-17 A 22-Aug-17
C-C01-1900 Re-Install Ceiling Grid & Tile 2 2 23-Aug-17 24-Aug-17
C-C01-1905 Re-Install Floor Finishes 2 2 25-Aug-17 28-Aug-17
C-C01-1910 Test Smoke / Fire Damper 1 1 29-Aug-17 29-Aug-17
C-C01-1915 Remove Temp Walls 2 2 30-Aug-17 31-Aug-17
C-C01-1920 Final Clean 2 2 01-Sep-17 05-Sep-17
NW - Rooms 433, 442 Outside AirNW - Rooms 433, 442 Outside Air28 16 17-Aug-17 A 12-Sep-17
C-C01-1955 Install Shaft Walls / Access Panels 4 3 17-Aug-17 A 23-Aug-17
C-C01-1960 Tape, Bed, Paint 4 4 24-Aug-17 29-Aug-17
C-C01-1965 Re-Install Ceiling Grid & Tile 2 2 30-Aug-17 31-Aug-17
C-C01-1970 Re-Install Floor Finishes 2 2 01-Sep-17 05-Sep-17
C-C01-1975 Test Smoke / Fire Damper 1 1 06-Sep-17 06-Sep-17
C-C01-1980 Remove Temp Walls 2 2 07-Sep-17 08-Sep-17
C-C01-1985 Final Clean 2 2 11-Sep-17 12-Sep-17
NW - Mens Restroom Outside AirNW - Mens Restroom Outside Air45 45 21-Aug-17 23-Oct-17
C-C01-4795 Redesign Men's Restroom 10 10 21-Aug-17 01-Sep-17
C-C01-4740 Saw Cut Floor 1 1 05-Sep-17 05-Sep-17
C-C01-4745 Install Outside Air Riser 5 5 06-Sep-17 12-Sep-17
C-C01-4750 Fire Caulk / Seal Floor Penetration @ Riser 2 2 13-Sep-17 14-Sep-17
C-C01-4755 Install Smoke / Fire Damper 4 4 15-Sep-17 20-Sep-17
C-C01-4760 Install Shaft Walls / Access Panels 4 4 21-Sep-17 26-Sep-17
C-C01-4765 Tape, Bed, Paint 4 4 27-Sep-17 02-Oct-17
J A J A J A A A A J A J A J A A J A J A J
2017 2018 2019 2020 2021 2022 2023
Re-Install Ceiling Grid & Tile
Re-Install Floor Finishes
Test Smoke / Fire Damper
Remove Temp Walls
Final Clean
Redesign Mech Rm
Install Smoke / Fire Damper
Install Shaft Walls / Access Panels
Tape, Bed, Paint
Re-Install Ceiling Grid & Tile
Re-Install Floor Finishes
Test Smoke / Fire Damper
Remove Temp Walls
Final Clean
Tape, Bed, Paint
Re-Install Ceiling Grid & Tile
Re-Install Floor Finishes
Test Smoke / Fire Damper
Remove Temp Walls
Final Clean
Install Shaft Walls / Access Panels
Tape, Bed, Paint
Re-Install Ceiling Grid & Tile
Re-Install Floor Finishes
Test Smoke / Fire Damper
Remove Temp Walls
Final Clean
Redesign Men's Restroom
Saw Cut Floor
Install Outside Air Riser
Fire Caulk / Seal Floor Penetration @ Riser
Install Smoke / Fire Damper
Install Shaft Walls / Access Panels
Tape, Bed, Paint
Start Date 23-Feb-15
Finish Date 30-Dec-22
Data Date 21-Aug-17
Run Date 30-Aug-17
Page 14 of 33
3707-CR29
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-C01-4770 Re-Install Ceiling Grid & Tile 2 2 03-Oct-17 04-Oct-17
C-C01-4775 Re-Install Floor Finishes 2 2 05-Oct-17 06-Oct-17
C-C01-4780 Test Smoke / Fire Damper 1 1 09-Oct-17 09-Oct-17
C-C01-4785 Remove Temp Walls 2 2 10-Oct-17 11-Oct-17
C-C01-4790 Final Clean 2 2 12-Oct-17 23-Oct-17
NW - Room 549 Outside AirNW - Room 549 Outside Air37 37 21-Aug-17 11-Oct-17
C-C01-4800 Demo and Install Temp Roof Penetration Curb Cap 1 1 21-Aug-17 21-Aug-17
C-C01-4805 Install Outside Air Level 5 to Roof 2 2 22-Aug-17 23-Aug-17
C-C01-2020 Install Shaft Walls / Access Panels 4 4 19-Sep-17 22-Sep-17
C-C01-2025 Tape, Bed, Paint 4 4 25-Sep-17 28-Sep-17
C-C01-2030 Re-Install Ceiling Grid & Tile 2 2 29-Sep-17 02-Oct-17
C-C01-2035 Re-Install Floor Finishes 2 2 03-Oct-17 04-Oct-17
C-C01-2040 Test Smoke / Fire Damper 1 1 05-Oct-17 05-Oct-17
C-C01-2045 Remove Temp Walls 2 2 06-Oct-17 09-Oct-17
C-C01-2050 Final Clean 2 2 10-Oct-17 11-Oct-17
NW - 6th FloorNW - 6th Floor20 20 21-Aug-17 18-Sep-17
C-C01-2065 Saw Cut Floor 5 5 21-Aug-17 25-Aug-17
C-C01-2070 Install Outside Air Riser 5 5 28-Aug-17 01-Sep-17
C-C01-2075 Fire Caulk / Seal Floor Penetration @ Riser 5 5 05-Sep-17 11-Sep-17
C-C01-2080 Install Smoke / Fire Damper 5 5 12-Sep-17 18-Sep-17
NW - RooftopNW - Rooftop71 71 21-Aug-17 30-Nov-17
C-C01-3835 Set Roof Top Curb 7 7 21-Aug-17 29-Aug-17
C-C01-1275 Set Roof Top Equipment (NW) 3 3 30-Aug-17 01-Sep-17
C-C01-1060 Install NW Roof Top Equipment 40 30 26-Sep-17 14-Nov-17
C-C01-1070 Start Up NW Roof Top Equipment 10 10 15-Nov-17 30-Nov-17
North - Rooms 104, 107 & 106 Outside AirNorth - Rooms 104, 107 & 106 Outside Air41 41 05-Sep-17 31-Oct-17
C-C01-2640 Install Temp Walls 2 2 05-Sep-17 06-Sep-17
C-C01-2645 Demo Walls & Ceilings 4 4 07-Sep-17 12-Sep-17
C-C01-2650 Saw Cut Floor 1 1 13-Sep-17 13-Sep-17
C-C01-2655 Install Outside Air Riser 5 5 14-Sep-17 20-Sep-17
C-C01-2660 Fire Caulk / Seal Floor Penetration @ Riser 2 2 21-Sep-17 22-Sep-17
C-C01-2665 Install Smoke / Fire Damper 4 4 25-Sep-17 28-Sep-17
C-C01-2670 Install Shaft Walls / Access Panels 4 4 29-Sep-17 04-Oct-17
C-C01-2675 Tape, Bed, Paint 4 4 05-Oct-17 10-Oct-17
C-C01-2680 Re-Install Ceiling Grid & Tile 2 2 11-Oct-17 12-Oct-17
C-C01-2685 Re-Install Floor Finishes 2 2 23-Oct-17 24-Oct-17
C-C01-2690 Test Smoke / Fire Damper 1 1 25-Oct-17 25-Oct-17
C-C01-2695 Remove Temp Walls 2 2 26-Oct-17 27-Oct-17
J A J A J A A A A J A J A J A A J A J A J
2017 2018 2019 2020 2021 2022 2023
Re-Install Ceiling Grid & Tile
Re-Install Floor Finishes
Test Smoke / Fire Damper
Remove Temp Walls
Final Clean
Demo and Install Temp Roof Penetration Curb Cap
Install Outside Air Level 5 to Roof
Install Shaft Walls / Access Panels
Tape, Bed, Paint
Re-Install Ceiling Grid & Tile
Re-Install Floor Finishes
Test Smoke / Fire Damper
Remove Temp Walls
Final Clean
Saw Cut Floor
Install Outside Air Riser
Fire Caulk / Seal Floor Penetration @ Riser
Install Smoke / Fire Damper
Set Roof Top Curb
Set Roof Top Equipment (NW)
Install NW Roof Top Equipment
Start Up NW Roof Top Equipment
Install Temp Walls
Demo Walls & Ceilings
Saw Cut Floor
Install Outside Air Riser
Fire Caulk / Seal Floor Penetration @ Riser
Install Smoke / Fire Damper
Install Shaft Walls / Access Panels
Tape, Bed, Paint
Re-Install Ceiling Grid & Tile
Re-Install Floor Finishes
Test Smoke / Fire Damper
Remove Temp Walls
Start Date 23-Feb-15
Finish Date 30-Dec-22
Data Date 21-Aug-17
Run Date 30-Aug-17
Page 15 of 33
3707-CR29
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-C01-2700 Final Clean 2 2 30-Oct-17 31-Oct-17
North - Rooms 230, 237 & 238 Outside AirNorth - Rooms 230, 237 & 238 Outside Air41 41 14-Sep-17 09-Nov-17
C-C01-2705 Install Temp Walls 2 2 14-Sep-17 15-Sep-17
C-C01-2710 Demo Walls & Ceilings 4 4 18-Sep-17 21-Sep-17
C-C01-2715 Saw Cut Floor 1 1 22-Sep-17 22-Sep-17
C-C01-2720 Install Outside Air Riser 5 5 25-Sep-17 29-Sep-17
C-C01-2725 Fire Caulk / Seal Floor Penetration @ Riser 2 2 02-Oct-17 03-Oct-17
C-C01-2730 Install Smoke / Fire Damper 4 4 04-Oct-17 09-Oct-17
C-C01-2735 Install Shaft Walls / Access Panels 4 4 10-Oct-17 23-Oct-17
C-C01-2740 Tape, Bed, Paint 4 4 24-Oct-17 27-Oct-17
C-C01-2745 Re-Install Ceiling Grid & Tile 2 2 30-Oct-17 31-Oct-17
C-C01-2750 Re-Install Floor Finishes 2 2 01-Nov-17 02-Nov-17
C-C01-2755 Test Smoke / Fire Damper 1 1 03-Nov-17 03-Nov-17
C-C01-2760 Remove Temp Walls 2 2 06-Nov-17 07-Nov-17
C-C01-2765 Final Clean 2 2 08-Nov-17 09-Nov-17
North - Rooms 312, 314 & 312 Corridor Outside AirNorth - Rooms 312, 314 & 312 Corridor Outside Air41 41 25-Sep-17 20-Nov-17
C-C01-2770 Install Temp Walls 2 2 25-Sep-17 26-Sep-17
C-C01-2775 Demo Walls & Ceilings 4 4 27-Sep-17 02-Oct-17
C-C01-2780 Saw Cut Floor 1 1 03-Oct-17 03-Oct-17
C-C01-2785 Install Outside Air Riser 5 5 04-Oct-17 10-Oct-17
C-C01-2790 Fire Caulk / Seal Floor Penetration @ Riser 2 2 11-Oct-17 12-Oct-17
C-C01-2795 Install Smoke / Fire Damper 4 4 23-Oct-17 26-Oct-17
C-C01-2800 Install Shaft Walls / Access Panels 4 4 27-Oct-17 01-Nov-17
C-C01-2805 Tape, Bed, Paint 4 4 02-Nov-17 07-Nov-17
C-C01-2810 Re-Install Ceiling Grid & Tile 2 2 08-Nov-17 09-Nov-17
C-C01-2815 Re-Install Floor Finishes 2 2 10-Nov-17 13-Nov-17
C-C01-2820 Test Smoke / Fire Damper 1 1 14-Nov-17 14-Nov-17
C-C01-2825 Remove Temp Walls 2 2 15-Nov-17 16-Nov-17
C-C01-2830 Final Clean 2 2 17-Nov-17 20-Nov-17
North - Rooms 432A, 432B, 429 & Snackbar Outside AirNorth - Rooms 432A, 432B, 429 & Snackbar Outside Air53 53 04-Oct-17 19-Dec-17
C-C01-2835 Install Temp Walls 4 4 04-Oct-17 09-Oct-17
C-C01-2840 Demo Walls & Ceilings 5 5 10-Oct-17 24-Oct-17
C-C01-2845 Saw Cut Floor 2 2 25-Oct-17 26-Oct-17
C-C01-2850 Install Outside Air Riser 7 7 27-Oct-17 06-Nov-17
C-C01-2855 Fire Caulk / Seal Floor Penetration @ Riser 3 3 07-Nov-17 09-Nov-17
C-C01-2860 Install Smoke / Fire Damper 5 5 10-Nov-17 16-Nov-17
C-C01-2865 Install Shaft Walls / Access Panels 5 5 17-Nov-17 27-Nov-17
C-C01-2870 Tape, Bed, Paint 5 5 28-Nov-17 04-Dec-17
C-C01-2875 Re-Install Ceiling Grid & Tile 3 3 05-Dec-17 07-Dec-17
J A J A J A A A A J A J A J A A J A J A J
2017 2018 2019 2020 2021 2022 2023
Final Clean
Install Temp Walls
Demo Walls & Ceilings
Saw Cut Floor
Install Outside Air Riser
Fire Caulk / Seal Floor Penetration @ Riser
Install Smoke / Fire Damper
Install Shaft Walls / Access Panels
Tape, Bed, Paint
Re-Install Ceiling Grid & Tile
Re-Install Floor Finishes
Test Smoke / Fire Damper
Remove Temp Walls
Final Clean
Install Temp Walls
Demo Walls & Ceilings
Saw Cut Floor
Install Outside Air Riser
Fire Caulk / Seal Floor Penetration @ Riser
Install Smoke / Fire Damper
Install Shaft Walls / Access Panels
Tape, Bed, Paint
Re-Install Ceiling Grid & Tile
Re-Install Floor Finishes
Test Smoke / Fire Damper
Remove Temp Walls
Final Clean
Install Temp Walls
Demo Walls & Ceilings
Saw Cut Floor
Install Outside Air Riser
Fire Caulk / Seal Floor Penetration @ Riser
Install Smoke / Fire Damper
Install Shaft Walls / Access Panels
Tape, Bed, Paint
Re-Install Ceiling Grid & Tile
Start Date 23-Feb-15
Finish Date 30-Dec-22
Data Date 21-Aug-17
Run Date 30-Aug-17
Page 16 of 33
3707-CR29
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-C01-2880 Re-Install Floor Finishes 3 3 08-Dec-17 12-Dec-17
C-C01-2885 Test Smoke / Fire Damper 1 1 13-Dec-17 13-Dec-17
C-C01-2890 Remove Temp Walls 2 2 14-Dec-17 15-Dec-17
C-C01-2895 Final Clean 2 2 18-Dec-17 19-Dec-17
North - Rooms 533, 535A, 536 & 537 Outside AirNorth - Rooms 533, 535A, 536 & 537 Outside Air47 47 27-Oct-17 05-Jan-18
C-C01-2900 Install Temp Walls 4 4 27-Oct-17 01-Nov-17
C-C01-2905 Demo Walls & Ceilings 5 5 02-Nov-17 08-Nov-17
C-C01-2910 Saw Cut Floor 2 2 09-Nov-17 10-Nov-17
C-C01-2915 Install Outside Air Riser 7 7 13-Nov-17 21-Nov-17
C-C01-2920 Fire Caulk / Seal Floor Penetration @ Riser 3 3 22-Nov-17 28-Nov-17
C-C01-2925 Install Smoke / Fire Damper 5 5 29-Nov-17 05-Dec-17
C-C01-2930 Install Shaft Walls / Access Panels 5 5 06-Dec-17 12-Dec-17
C-C01-2935 Tape, Bed, Paint 5 5 13-Dec-17 19-Dec-17
C-C01-2940 Re-Install Ceiling Grid & Tile 3 3 20-Dec-17 22-Dec-17
C-C01-2945 Re-Install Floor Finishes 3 3 26-Dec-17 28-Dec-17
C-C01-2950 Test Smoke / Fire Damper 1 1 29-Dec-17 29-Dec-17
C-C01-2955 Remove Temp Walls 2 2 02-Jan-18 03-Jan-18
C-C01-2960 Final Clean 2 2 04-Jan-18 05-Jan-18
North - 6th FloorNorth - 6th Floor20 20 13-Nov-17 12-Dec-17
C-C01-2975 Saw Cut Floor 5 5 13-Nov-17 17-Nov-17
C-C01-2980 Install Outside Air Riser 5 5 20-Nov-17 28-Nov-17
C-C01-2985 Fire Caulk / Seal Floor Penetration @ Riser 5 5 29-Nov-17 05-Dec-17
C-C01-2990 Install Smoke / Fire Damper 5 5 06-Dec-17 12-Dec-17
South - OMES Storage & Photographer Temp Storage Outside AirSouth - OMES Storage & Photographer Temp Storage Outside Air65 65 20-Nov-17 22-Feb-18
C-C01-3030 Install Temp Walls 5 5 20-Nov-17 28-Nov-17
C-C01-3035 Demo Walls & Ceilings 5 5 29-Nov-17 05-Dec-17
C-C01-3040 Saw Cut Floor 5 5 06-Dec-17 12-Dec-17
C-C01-3045 Install Outside Air Riser 5 5 13-Dec-17 19-Dec-17
C-C01-3050 Fire Caulk / Seal Floor Penetration @ Riser 5 5 20-Dec-17 27-Dec-17
C-C01-3055 Install Smoke / Fire Damper 5 5 28-Dec-17 04-Jan-18
C-C01-3060 Install Shaft Walls / Access Panels 5 5 05-Jan-18 11-Jan-18
C-C01-3065 Tape, Bed, Paint 5 5 12-Jan-18 18-Jan-18
C-C01-3070 Re-Install Ceiling Grid & Tile 5 5 19-Jan-18 25-Jan-18
C-C01-3075 Re-Install Floor Finishes 5 5 26-Jan-18 01-Feb-18
C-C01-3080 Test Smoke / Fire Damper 5 5 02-Feb-18 08-Feb-18
C-C01-3085 Remove Temp Walls 5 5 09-Feb-18 15-Feb-18
C-C01-3090 Final Clean 5 5 16-Feb-18 22-Feb-18
South - Hall of Gov & Lt Governor Reception Outside AirSouth - Hall of Gov & Lt Governor Reception Outside Air42 42 13-Dec-17 12-Feb-18
J A J A J A A A A J A J A J A A J A J A J
2017 2018 2019 2020 2021 2022 2023
Re-Install Floor Finishes
Test Smoke / Fire Damper
Remove Temp Walls
Final Clean
Install Temp Walls
Demo Walls & Ceilings
Saw Cut Floor
Install Outside Air Riser
Fire Caulk / Seal Floor Penetration @ Riser
Install Smoke / Fire Damper
Install Shaft Walls / Access Panels
Tape, Bed, Paint
Re-Install Ceiling Grid & Tile
Re-Install Floor Finishes
Test Smoke / Fire Damper
Remove Temp Walls
Final Clean
Saw Cut Floor
Install Outside Air Riser
Fire Caulk / Seal Floor Penetration @ Riser
Install Smoke / Fire Damper
Install Temp Walls
Demo Walls & Ceilings
Saw Cut Floor
Install Outside Air Riser
Fire Caulk / Seal Floor Penetration @ Riser
Install Smoke / Fire Damper
Install Shaft Walls / Access Panels
Tape, Bed, Paint
Re-Install Ceiling Grid & Tile
Re-Install Floor Finishes
Test Smoke / Fire Damper
Remove Temp Walls
Final Clean
Start Date 23-Feb-15
Finish Date 30-Dec-22
Data Date 21-Aug-17
Run Date 30-Aug-17
Page 17 of 33
3707-CR29
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-C01-3850 Install Scaffold 5 5 13-Dec-17 19-Dec-17
C-C01-3095 Install Temp Walls 2 2 20-Dec-17 21-Dec-17
C-C01-3100 Demo Walls & Ceilings 4 4 22-Dec-17 28-Dec-17
C-C01-3105 Saw Cut Floor 1 1 29-Dec-17 29-Dec-17
C-C01-3110 Install Outside Air Riser 5 5 02-Jan-18 08-Jan-18
C-C01-3115 Fire Caulk / Seal Floor Penetration @ Riser 2 2 09-Jan-18 10-Jan-18
C-C01-3120 Install Smoke / Fire Damper 4 4 11-Jan-18 16-Jan-18
C-C01-3125 Install Shaft Walls / Access Panels 4 4 17-Jan-18 22-Jan-18
C-C01-3130 Tape, Bed, Paint 4 4 23-Jan-18 26-Jan-18
C-C01-3135 Re-Install Ceiling Grid & Tile 2 2 29-Jan-18 30-Jan-18
C-C01-3140 Re-Install Floor Finishes 2 2 31-Jan-18 01-Feb-18
C-C01-3145 Test Smoke / Fire Damper 1 1 02-Feb-18 02-Feb-18
C-C01-3150 Remove Temp Walls 2 2 05-Feb-18 06-Feb-18
C-C01-3855 Remove Scaffold 2 2 07-Feb-18 08-Feb-18
C-C01-3155 Final Clean 2 2 09-Feb-18 12-Feb-18
South - Rotunda 4th & 5th FloorOutside AirSouth - Rotunda 4th & 5th FloorOutside Air55 55 02-Jan-18 19-Mar-18
C-C01-3860 Install Scaffold 5 5 02-Jan-18 08-Jan-18
C-C01-3160 Install Temp Walls 4 4 09-Jan-18 12-Jan-18
C-C01-3165 Demo Walls & Ceilings 5 5 15-Jan-18 19-Jan-18
C-C01-3170 Saw Cut Floor 2 2 22-Jan-18 23-Jan-18
C-C01-3175 Install Outside Air Riser 7 7 24-Jan-18 01-Feb-18
C-C01-3180 Fire Caulk / Seal Floor Penetration @ Riser 3 3 02-Feb-18 06-Feb-18
C-C01-3185 Install Smoke / Fire Damper 5 5 07-Feb-18 13-Feb-18
C-C01-3190 Install Shaft Walls / Access Panels 5 5 14-Feb-18 20-Feb-18
C-C01-3195 Tape, Bed, Paint 5 5 21-Feb-18 27-Feb-18
C-C01-3200 Re-Install Ceiling Grid & Tile 3 3 28-Feb-18 02-Mar-18
C-C01-3205 Re-Install Floor Finishes 3 3 05-Mar-18 07-Mar-18
C-C01-3210 Test Smoke / Fire Damper 1 1 08-Mar-18 08-Mar-18
C-C01-3215 Remove Temp Walls 2 2 09-Mar-18 12-Mar-18
C-C01-3225 Remove Scaffold 3 3 13-Mar-18 15-Mar-18
C-C01-3220 Final Clean 2 2 16-Mar-18 19-Mar-18
South - 6th Floor Outside AirSouth - 6th Floor Outside Air20 20 24-Jan-18 20-Feb-18
C-C01-3235 Saw Cut Floor 5 5 24-Jan-18 30-Jan-18
C-C01-3240 Install Outside Air Riser 5 5 31-Jan-18 06-Feb-18
C-C01-3245 Fire Caulk / Seal Floor Penetration @ Riser 5 5 07-Feb-18 13-Feb-18
C-C01-3250 Install Smoke / Fire Damper 5 5 14-Feb-18 20-Feb-18
NE - Secretary of State - (Copy Room & Reception) Outside AirNE - Secretary of State - (Copy Room & Reception) Outside Air36 36 31-Jan-18 21-Mar-18
C-C01-3290 Install Temp Walls 2 2 31-Jan-18 01-Feb-18
C-C01-3295 Demo Walls & Ceilings 3 3 02-Feb-18 06-Feb-18
J A J A J A A A A J A J A J A A J A J A J
2017 2018 2019 2020 2021 2022 2023
Install Scaffold
Install Temp Walls
Demo Walls & Ceilings
Saw Cut Floor
Install Outside Air Riser
Fire Caulk / Seal Floor Penetration @ Riser
Install Smoke / Fire Damper
Install Shaft Walls / Access Panels
Tape, Bed, Paint
Re-Install Ceiling Grid & Tile
Re-Install Floor Finishes
Test Smoke / Fire Damper
Remove Temp Walls
Remove Scaffold
Final Clean
Install Scaffold
Install Temp Walls
Demo Walls & Ceilings
Saw Cut Floor
Install Outside Air Riser
Fire Caulk / Seal Floor Penetration @ Riser
Install Smoke / Fire Damper
Install Shaft Walls / Access Panels
Tape, Bed, Paint
Re-Install Ceiling Grid & Tile
Re-Install Floor Finishes
Test Smoke / Fire Damper
Remove Temp Walls
Remove Scaffold
Final Clean
Saw Cut Floor
Install Outside Air Riser
Fire Caulk / Seal Floor Penetration @ Riser
Install Smoke / Fire Damper
Install Temp Walls
Demo Walls & Ceilings
Start Date 23-Feb-15
Finish Date 30-Dec-22
Data Date 21-Aug-17
Run Date 30-Aug-17
Page 18 of 33
3707-CR29
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-C01-3300 Saw Cut Floor 1 1 07-Feb-18 07-Feb-18
C-C01-3305 Install Outside Air Riser 5 5 08-Feb-18 14-Feb-18
C-C01-3310 Fire Caulk / Seal Floor Penetration @ Riser 2 2 15-Feb-18 16-Feb-18
C-C01-3315 Install Smoke / Fire Damper 3 3 19-Feb-18 21-Feb-18
C-C01-3320 Install Shaft Walls / Access Panels 5 5 22-Feb-18 28-Feb-18
C-C01-3325 Tape, Bed, Paint 5 5 01-Mar-18 07-Mar-18
C-C01-3330 Re-Install Ceiling Grid & Tile 3 3 08-Mar-18 12-Mar-18
C-C01-3335 Re-Install Floor Finishes 2 2 13-Mar-18 14-Mar-18
C-C01-3340 Test Smoke / Fire Damper 1 1 15-Mar-18 15-Mar-18
C-C01-3345 Remove Temp Walls 2 2 16-Mar-18 19-Mar-18
C-C01-3350 Final Clean 2 2 20-Mar-18 21-Mar-18
NE - Treasurers Office (Charlie Hover) Outside AirNE - Treasurers Office (Charlie Hover) Outside Air40 40 08-Feb-18 04-Apr-18
C-C01-3355 Install Temp Walls 2 2 08-Feb-18 09-Feb-18
C-C01-3360 Demo Walls & Ceilings 3 3 12-Feb-18 14-Feb-18
C-C01-3365 Saw Cut Floor 1 1 15-Feb-18 15-Feb-18
C-C01-3370 Install Outside Air Riser 5 5 16-Feb-18 22-Feb-18
C-C01-3375 Fire Caulk / Seal Floor Penetration @ Riser 2 2 23-Feb-18 26-Feb-18
C-C01-3380 Install Smoke / Fire Damper 3 3 27-Feb-18 01-Mar-18
C-C01-3385 Install Shaft Walls / Access Panels 5 5 02-Mar-18 08-Mar-18
C-C01-3390 Tape, Bed, Paint 5 5 09-Mar-18 15-Mar-18
C-C01-3395 Re-Install Ceiling Grid & Tile 3 3 16-Mar-18 20-Mar-18
C-C01-3400 Re-Install Floor Finishes 2 2 21-Mar-18 22-Mar-18
C-C01-3405 Test Smoke / Fire Damper 1 5 23-Mar-18 29-Mar-18
C-C01-3410 Remove Temp Walls 2 2 30-Mar-18 02-Apr-18
C-C01-3415 Final Clean 2 2 03-Apr-18 04-Apr-18
NE - Room 309.1B Outside AirNE - Room 309.1B Outside Air36 36 16-Feb-18 06-Apr-18
C-C01-3420 Install Temp Walls 2 2 16-Feb-18 19-Feb-18
C-C01-3425 Demo Walls & Ceilings 3 3 20-Feb-18 22-Feb-18
C-C01-3430 Saw Cut Floor 1 1 23-Feb-18 23-Feb-18
C-C01-3435 Install Outside Air Riser 5 5 26-Feb-18 02-Mar-18
C-C01-3440 Fire Caulk / Seal Floor Penetration @ Riser 2 2 05-Mar-18 06-Mar-18
C-C01-3445 Install Smoke / Fire Damper 3 3 07-Mar-18 09-Mar-18
C-C01-3450 Install Shaft Walls / Access Panels 5 5 12-Mar-18 16-Mar-18
C-C01-3455 Tape, Bed, Paint 5 5 19-Mar-18 23-Mar-18
C-C01-3460 Re-Install Ceiling Grid & Tile 3 3 26-Mar-18 28-Mar-18
C-C01-3465 Re-Install Floor Finishes 2 2 29-Mar-18 30-Mar-18
C-C01-3470 Test Smoke / Fire Damper 1 1 02-Apr-18 02-Apr-18
C-C01-3475 Remove Temp Walls 2 2 03-Apr-18 04-Apr-18
C-C01-3480 Final Clean 2 2 05-Apr-18 06-Apr-18
J A J A J A A A A J A J A J A A J A J A J
2017 2018 2019 2020 2021 2022 2023
Saw Cut Floor
Install Outside Air Riser
Fire Caulk / Seal Floor Penetration @ Riser
Install Smoke / Fire Damper
Install Shaft Walls / Access Panels
Tape, Bed, Paint
Re-Install Ceiling Grid & Tile
Re-Install Floor Finishes
Test Smoke / Fire Damper
Remove Temp Walls
Final Clean
Install Temp Walls
Demo Walls & Ceilings
Saw Cut Floor
Install Outside Air Riser
Fire Caulk / Seal Floor Penetration @ Riser
Install Smoke / Fire Damper
Install Shaft Walls / Access Panels
Tape, Bed, Paint
Re-Install Ceiling Grid & Tile
Re-Install Floor Finishes
Test Smoke / Fire Damper
Remove Temp Walls
Final Clean
Install Temp Walls
Demo Walls & Ceilings
Saw Cut Floor
Install Outside Air Riser
Fire Caulk / Seal Floor Penetration @ Riser
Install Smoke / Fire Damper
Install Shaft Walls / Access Panels
Tape, Bed, Paint
Re-Install Ceiling Grid & Tile
Re-Install Floor Finishes
Test Smoke / Fire Damper
Remove Temp Walls
Final Clean
Start Date 23-Feb-15
Finish Date 30-Dec-22
Data Date 21-Aug-17
Run Date 30-Aug-17
Page 19 of 33
3707-CR29
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
NE - 4th Floor Outside AirNE - 4th Floor Outside Air21 21 01-Jun-18 29-Jun-18
C-C01-3490 Demo Walls & Ceilings 4 4 01-Jun-18 06-Jun-18
C-C01-3495 Saw Cut Floor 1 1 07-Jun-18 07-Jun-18
C-C01-3500 Install Outside Air Riser 5 5 08-Jun-18 14-Jun-18
C-C01-3505 Fire Caulk / Seal Floor Penetration @ Riser 2 2 15-Jun-18 18-Jun-18
C-C01-3510 Install Smoke / Fire Damper 4 4 19-Jun-18 22-Jun-18
C-C01-3515 Install Shaft Walls / Access Panels 4 4 25-Jun-18 28-Jun-18
C-C01-3535 Test Smoke / Fire Damper 1 1 29-Jun-18 29-Jun-18
NE - 5th Floor Outside AirNE - 5th Floor Outside Air35 35 08-Jun-18 27-Jul-18
C-C01-3550 Install Temp Walls 2 2 08-Jun-18 11-Jun-18
C-C01-3555 Demo Walls & Ceilings 4 4 12-Jun-18 15-Jun-18
C-C01-3560 Saw Cut Floor 1 1 18-Jun-18 18-Jun-18
C-C01-3800 Lay Out Steel 1 1 18-Jun-18 18-Jun-18
C-C01-3805 Install Steel 5 5 18-Jun-18 22-Jun-18
C-C01-3565 Install Outside Air Riser 5 5 19-Jun-18 25-Jun-18
C-C01-3570 Fire Caulk / Seal Floor Penetration @ Riser 2 2 26-Jun-18 27-Jun-18
C-C01-3575 Install Smoke / Fire Damper 4 4 28-Jun-18 03-Jul-18
C-C01-3580 Install Shaft Walls / Access Panels 4 4 05-Jul-18 10-Jul-18
C-C01-3585 Tape, Bed, Paint 4 4 11-Jul-18 16-Jul-18
C-C01-3590 Re-Install Ceiling Grid & Tile 2 2 17-Jul-18 18-Jul-18
C-C01-3595 Re-Install Floor Finishes 2 2 19-Jul-18 20-Jul-18
C-C01-3600 Test Smoke / Fire Damper 1 1 23-Jul-18 23-Jul-18
C-C01-3605 Remove Temp Walls 2 2 24-Jul-18 25-Jul-18
C-C01-3610 Final Clean 2 2 26-Jul-18 27-Jul-18
NE - 6th FloorNE - 6th Floor20 20 19-Jun-18 17-Jul-18
C-C01-3625 Saw Cut Floor 5 5 19-Jun-18 25-Jun-18
C-C01-3630 Install Outside Air Riser 5 5 26-Jun-18 02-Jul-18
C-C01-3635 Fire Caulk / Seal Floor Penetration @ Riser 5 5 03-Jul-18 10-Jul-18
C-C01-3640 Install Smoke / Fire Damper 5 5 11-Jul-18 17-Jul-18
NE - RooftopNE - Rooftop60 60 25-Jun-18 18-Sep-18
C-C01-3840 Set Roof Top Curb 7 7 25-Jun-18 03-Jul-18
C-C01-3825 Set Roof Top Equipment (NE) 3 3 05-Jul-18 09-Jul-18
C-C01-1090 Install NE Roof Top Equipment 40 40 10-Jul-18 04-Sep-18
C-C01-1100 Start Up NE Roof Top Equipment 10 10 05-Sep-18 18-Sep-18
SE - 122 Break Room & 121 Cubicles North Outside AirSE - 122 Break Room & 121 Cubicles North Outside Air35 35 31-Jan-18 20-Mar-18
C-C01-2120 Install Temp Walls 2 2 31-Jan-18 01-Feb-18
C-C01-2125 Demo Walls & Ceilings 4 4 02-Feb-18 07-Feb-18
C-C01-2130 Saw Cut Floor 1 1 08-Feb-18 08-Feb-18
J A J A J A A A A J A J A J A A J A J A J
2017 2018 2019 2020 2021 2022 2023
Demo Walls & Ceilings
Saw Cut Floor
Install Outside Air Riser
Fire Caulk / Seal Floor Penetration @ Riser
Install Smoke / Fire Damper
Install Shaft Walls / Access Panels
Test Smoke / Fire Damper
Install Temp Walls
Demo Walls & Ceilings
Saw Cut Floor
Lay Out Steel
Install Steel
Install Outside Air Riser
Fire Caulk / Seal Floor Penetration @ Riser
Install Smoke / Fire Damper
Install Shaft Walls / Access Panels
Tape, Bed, Paint
Re-Install Ceiling Grid & Tile
Re-Install Floor Finishes
Test Smoke / Fire Damper
Remove Temp Walls
Final Clean
Saw Cut Floor
Install Outside Air Riser
Fire Caulk / Seal Floor Penetration @ Riser
Install Smoke / Fire Damper
Set Roof Top Curb
Set Roof Top Equipment (NE)
Install NE Roof Top Equipment
Start Up NE Roof Top Equipment
Install Temp Walls
Demo Walls & Ceilings
Saw Cut Floor
Start Date 23-Feb-15
Finish Date 30-Dec-22
Data Date 21-Aug-17
Run Date 30-Aug-17
Page 20 of 33
3707-CR29
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-C01-2135 Install Outside Air Riser 5 5 09-Feb-18 15-Feb-18
C-C01-2140 Fire Caulk / Seal Floor Penetration @ Riser 2 2 16-Feb-18 19-Feb-18
C-C01-2145 Install Smoke / Fire Damper 4 4 20-Feb-18 23-Feb-18
C-C01-2150 Install Shaft Walls / Access Panels 4 4 26-Feb-18 01-Mar-18
C-C01-2155 Tape, Bed, Paint 4 4 02-Mar-18 07-Mar-18
C-C01-2160 Re-Install Ceiling Grid & Tile 2 2 08-Mar-18 09-Mar-18
C-C01-2165 Re-Install Floor Finishes 2 2 12-Mar-18 13-Mar-18
C-C01-2170 Test Smoke / Fire Damper 1 1 14-Mar-18 14-Mar-18
C-C01-2175 Remove Temp Walls 2 2 15-Mar-18 16-Mar-18
C-C01-2180 Final Clean 2 2 19-Mar-18 20-Mar-18
SE - Governors Waiting, Travis & Gary, Blue Room Outside AirSE - Governors Waiting, Travis & Gary, Blue Room Outside Air47 47 09-Feb-18 16-Apr-18
C-C01-2185 Install Temp Walls 4 4 09-Feb-18 14-Feb-18
C-C01-2190 Demo Walls & Ceilings 5 5 15-Feb-18 21-Feb-18
C-C01-2195 Saw Cut Floor 2 2 22-Feb-18 23-Feb-18
C-C01-2200 Install Outside Air Riser 7 7 26-Feb-18 06-Mar-18
C-C01-2205 Fire Caulk / Seal Floor Penetration @ Riser 3 3 07-Mar-18 09-Mar-18
C-C01-2210 Install Smoke / Fire Damper 5 5 12-Mar-18 16-Mar-18
C-C01-2215 Install Shaft Walls / Access Panels 5 5 19-Mar-18 23-Mar-18
C-C01-2220 Tape, Bed, Paint 5 5 26-Mar-18 30-Mar-18
C-C01-2225 Re-Install Ceiling Grid & Tile 3 3 02-Apr-18 04-Apr-18
C-C01-2230 Re-Install Floor Finishes 3 3 05-Apr-18 09-Apr-18
C-C01-2235 Test Smoke / Fire Damper 1 1 10-Apr-18 10-Apr-18
C-C01-2240 Remove Temp Walls 2 2 11-Apr-18 12-Apr-18
C-C01-2245 Final Clean 2 2 13-Apr-18 16-Apr-18
SE - Rooms 309.36 & 309 Middle Corridor Outside AirSE - Rooms 309.36 & 309 Middle Corridor Outside Air35 35 26-Feb-18 13-Apr-18
C-C01-2380 Install Temp Walls 2 2 26-Feb-18 27-Feb-18
C-C01-2385 Demo Walls & Ceilings 4 4 28-Feb-18 05-Mar-18
C-C01-2390 Saw Cut Floor 1 1 06-Mar-18 06-Mar-18
C-C01-2395 Install Outside Air Riser 5 5 07-Mar-18 13-Mar-18
C-C01-2400 Fire Caulk / Seal Floor Penetration @ Riser 2 2 14-Mar-18 15-Mar-18
C-C01-2405 Install Smoke / Fire Damper 4 4 16-Mar-18 21-Mar-18
C-C01-2410 Install Shaft Walls / Access Panels 4 4 22-Mar-18 27-Mar-18
C-C01-2415 Tape, Bed, Paint 4 4 28-Mar-18 02-Apr-18
C-C01-2420 Re-Install Ceiling Grid & Tile 2 2 03-Apr-18 04-Apr-18
C-C01-2425 Re-Install Floor Finishes 2 2 05-Apr-18 06-Apr-18
C-C01-2430 Test Smoke / Fire Damper 1 1 09-Apr-18 09-Apr-18
C-C01-2435 Remove Temp Walls 2 2 10-Apr-18 11-Apr-18
C-C01-2440 Final Clean 2 2 12-Apr-18 13-Apr-18
SE - 4th Floor Outside AirSE - 4th Floor Outside Air21 21 01-Jun-18 29-Jun-18
J A J A J A A A A J A J A J A A J A J A J
2017 2018 2019 2020 2021 2022 2023
Install Outside Air Riser
Fire Caulk / Seal Floor Penetration @ Riser
Install Smoke / Fire Damper
Install Shaft Walls / Access Panels
Tape, Bed, Paint
Re-Install Ceiling Grid & Tile
Re-Install Floor Finishes
Test Smoke / Fire Damper
Remove Temp Walls
Final Clean
Install Temp Walls
Demo Walls & Ceilings
Saw Cut Floor
Install Outside Air Riser
Fire Caulk / Seal Floor Penetration @ Riser
Install Smoke / Fire Damper
Install Shaft Walls / Access Panels
Tape, Bed, Paint
Re-Install Ceiling Grid & Tile
Re-Install Floor Finishes
Test Smoke / Fire Damper
Remove Temp Walls
Final Clean
Install Temp Walls
Demo Walls & Ceilings
Saw Cut Floor
Install Outside Air Riser
Fire Caulk / Seal Floor Penetration @ Riser
Install Smoke / Fire Damper
Install Shaft Walls / Access Panels
Tape, Bed, Paint
Re-Install Ceiling Grid & Tile
Re-Install Floor Finishes
Test Smoke / Fire Damper
Remove Temp Walls
Final Clean
Start Date 23-Feb-15
Finish Date 30-Dec-22
Data Date 21-Aug-17
Run Date 30-Aug-17
Page 21 of 33
3707-CR29
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-C01-2450 Demo Walls & Ceilings 4 4 01-Jun-18 06-Jun-18
C-C01-2455 Saw Cut Floor 1 1 07-Jun-18 07-Jun-18
C-C01-2460 Install Outside Air Riser 5 5 08-Jun-18 14-Jun-18
C-C01-2465 Fire Caulk / Seal Floor Penetration @ Riser 2 2 15-Jun-18 18-Jun-18
C-C01-2470 Install Smoke / Fire Damper 4 4 19-Jun-18 22-Jun-18
C-C01-2475 Install Shaft Walls / Access Panels 4 4 25-Jun-18 28-Jun-18
C-C01-2495 Test Smoke / Fire Damper 1 1 29-Jun-18 29-Jun-18
SE - 5th Floor Outside AirSE - 5th Floor Outside Air35 35 08-Jun-18 27-Jul-18
C-C01-2510 Install Temp Walls 2 2 08-Jun-18 11-Jun-18
C-C01-2515 Demo Walls & Ceilings 4 4 12-Jun-18 15-Jun-18
C-C01-2520 Saw Cut Floor 1 1 18-Jun-18 18-Jun-18
C-C01-3815 Lay Out Steel 1 1 18-Jun-18 18-Jun-18
C-C01-3820 Install Steel 5 5 18-Jun-18 22-Jun-18
C-C01-2525 Install Outside Air Riser 5 5 19-Jun-18 25-Jun-18
C-C01-2530 Fire Caulk / Seal Floor Penetration @ Riser 2 2 26-Jun-18 27-Jun-18
C-C01-2535 Install Smoke / Fire Damper 4 4 28-Jun-18 03-Jul-18
C-C01-2540 Install Shaft Walls / Access Panels 4 4 05-Jul-18 10-Jul-18
C-C01-2545 Tape, Bed, Paint 4 4 11-Jul-18 16-Jul-18
C-C01-2550 Re-Install Ceiling Grid & Tile 2 2 17-Jul-18 18-Jul-18
C-C01-2555 Re-Install Floor Finishes 2 2 19-Jul-18 20-Jul-18
C-C01-2560 Test Smoke / Fire Damper 1 1 23-Jul-18 23-Jul-18
C-C01-2565 Remove Temp Walls 2 2 24-Jul-18 25-Jul-18
C-C01-2570 Final Clean 2 2 26-Jul-18 27-Jul-18
SE - 6th Floor Outside AirSE - 6th Floor Outside Air20 20 19-Jun-18 17-Jul-18
C-C01-2585 Saw Cut Floor 5 5 19-Jun-18 25-Jun-18
C-C01-2590 Install Outside Air Riser 5 5 26-Jun-18 02-Jul-18
C-C01-2595 Fire Caulk / Seal Floor Penetration @ Riser 5 5 03-Jul-18 10-Jul-18
C-C01-2600 Install Smoke / Fire Damper 5 5 11-Jul-18 17-Jul-18
SE - RooftopSE - Rooftop100 100 25-Jun-18 13-Nov-18
C-C01-3845 Set Roof Top Curb 5 5 25-Jun-18 29-Jun-18
C-C01-3830 Set Roof Top Equipment (SE) 3 3 10-Jul-18 12-Jul-18
C-C01-1110 Install SE Roof Top Equipment 40 40 05-Sep-18 30-Oct-18
C-C01-1120 Start Up SE Roof Top Equipment 10 10 31-Oct-18 13-Nov-18
SW - Rooms 404 & 408 CondensateSW - Rooms 404 & 408 Condensate29 4 17-Jul-17 A 24-Aug-17
C-C01-3955 Patch Walls as Required 3 2 17-Jul-17 A 22-Aug-17
C-C01-3960 Re-Install Ceiling 1 1 23-Aug-17 23-Aug-17
C-C01-3965 Remove Temp Walls 1 1 24-Aug-17 24-Aug-17
SW - Rooms 507 & 503 CondensateSW - Rooms 507 & 503 Condensate11 11 25-Aug-17 11-Sep-17
J A J A J A A A A J A J A J A A J A J A J
2017 2018 2019 2020 2021 2022 2023
Demo Walls & Ceilings
Saw Cut Floor
Install Outside Air Riser
Fire Caulk / Seal Floor Penetration @ Riser
Install Smoke / Fire Damper
Install Shaft Walls / Access Panels
Test Smoke / Fire Damper
Install Temp Walls
Demo Walls & Ceilings
Saw Cut Floor
Lay Out Steel
Install Steel
Install Outside Air Riser
Fire Caulk / Seal Floor Penetration @ Riser
Install Smoke / Fire Damper
Install Shaft Walls / Access Panels
Tape, Bed, Paint
Re-Install Ceiling Grid & Tile
Re-Install Floor Finishes
Test Smoke / Fire Damper
Remove Temp Walls
Final Clean
Saw Cut Floor
Install Outside Air Riser
Fire Caulk / Seal Floor Penetration @ Riser
Install Smoke / Fire Damper
Set Roof Top Curb
Set Roof Top Equipment (SE)
Install SE Roof Top Equipment
Start Up SE Roof Top Equipment
Patch Walls as Required
Re-Install Ceiling
Remove Temp Walls
Start Date 23-Feb-15
Finish Date 30-Dec-22
Data Date 21-Aug-17
Run Date 30-Aug-17
Page 22 of 33
3707-CR29
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-C01-3970 Install Temp Walls 2 2 25-Aug-17 28-Aug-17
C-C01-3975 Demo Walls / Ceilings 2 2 29-Aug-17 30-Aug-17
C-C01-3980 Core Drill 1 1 31-Aug-17 31-Aug-17
C-C01-3985 Install Condensate Drain 1 1 01-Sep-17 01-Sep-17
C-C01-3990 Patch Walls as Required 3 3 05-Sep-17 07-Sep-17
C-C01-3995 Re-Install Ceiling 1 1 08-Sep-17 08-Sep-17
C-C01-4000 Remove Temp Walls 1 1 11-Sep-17 11-Sep-17
NW - Room 109.20 CondensateNW - Room 109.20 Condensate11 11 12-Sep-17 26-Sep-17
C-C01-4005 Install Temp Walls 2 2 12-Sep-17 13-Sep-17
C-C01-4010 Demo Walls / Ceilings 2 2 14-Sep-17 15-Sep-17
C-C01-4015 Core Drill 1 1 18-Sep-17 18-Sep-17
C-C01-4020 Install Condensate Drain 1 1 19-Sep-17 19-Sep-17
C-C01-4025 Patch Walls as Required 3 3 20-Sep-17 22-Sep-17
C-C01-4030 Re-Install Ceiling 1 1 25-Sep-17 25-Sep-17
C-C01-4035 Remove Temp Walls 1 1 26-Sep-17 26-Sep-17
North - LSB West Wall of Server Closet CondensateNorth - LSB West Wall of Server Closet Condensate11 11 27-Sep-17 11-Oct-17
C-C01-4040 Install Temp Walls 2 2 27-Sep-17 28-Sep-17
C-C01-4045 Demo Walls / Ceilings 2 2 29-Sep-17 02-Oct-17
C-C01-4050 Core Drill 1 1 03-Oct-17 03-Oct-17
C-C01-4055 Install Condensate Drain 1 1 04-Oct-17 04-Oct-17
C-C01-4060 Patch Walls as Required 3 3 05-Oct-17 09-Oct-17
C-C01-4065 Re-Install Ceiling 1 1 10-Oct-17 10-Oct-17
C-C01-4070 Remove Temp Walls 1 1 11-Oct-17 11-Oct-17
North - Rooms 322 & 323 CondensateNorth - Rooms 322 & 323 Condensate17 17 12-Oct-17 03-Nov-17
C-C01-4075 Install Temp Walls 2 2 12-Oct-17 23-Oct-17
C-C01-4080 Demo Walls / Ceilings 2 2 24-Oct-17 25-Oct-17
C-C01-4085 Core Drill 1 1 26-Oct-17 26-Oct-17
C-C01-4090 Install Condensate Drain 1 1 27-Oct-17 27-Oct-17
C-C01-4095 Patch Walls as Required 3 3 30-Oct-17 01-Nov-17
C-C01-4100 Re-Install Ceiling 1 1 02-Nov-17 02-Nov-17
C-C01-4105 Remove Temp Walls 1 1 03-Nov-17 03-Nov-17
North 430 East Closet CondensateNorth 430 East Closet Condensate11 11 06-Nov-17 20-Nov-17
C-C01-4110 Install Temp Walls 2 2 06-Nov-17 07-Nov-17
C-C01-4115 Demo Walls / Ceilings 2 2 08-Nov-17 09-Nov-17
C-C01-4120 Core Drill 1 1 10-Nov-17 10-Nov-17
C-C01-4125 Install Condensate Drain 1 1 13-Nov-17 13-Nov-17
C-C01-4130 Patch Walls as Required 3 3 14-Nov-17 16-Nov-17
C-C01-4135 Re-Install Ceiling 1 1 17-Nov-17 17-Nov-17
J A J A J A A A A J A J A J A A J A J A J
2017 2018 2019 2020 2021 2022 2023
Install Temp Walls
Demo Walls / Ceilings
Core Drill
Install Condensate Drain
Patch Walls as Required
Re-Install Ceiling
Remove Temp Walls
Install Temp Walls
Demo Walls / Ceilings
Core Drill
Install Condensate Drain
Patch Walls as Required
Re-Install Ceiling
Remove Temp Walls
Install Temp Walls
Demo Walls / Ceilings
Core Drill
Install Condensate Drain
Patch Walls as Required
Re-Install Ceiling
Remove Temp Walls
Install Temp Walls
Demo Walls / Ceilings
Core Drill
Install Condensate Drain
Patch Walls as Required
Re-Install Ceiling
Remove Temp Walls
Install Temp Walls
Demo Walls / Ceilings
Core Drill
Install Condensate Drain
Patch Walls as Required
Re-Install Ceiling
Start Date 23-Feb-15
Finish Date 30-Dec-22
Data Date 21-Aug-17
Run Date 30-Aug-17
Page 23 of 33
3707-CR29
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-C01-4140 Remove Temp Walls 1 1 20-Nov-17 20-Nov-17
South - Gift Shop Front Lobby CondensateSouth - Gift Shop Front Lobby Condensate11 11 21-Nov-17 07-Dec-17
C-C01-4145 Install Temp Walls 2 2 21-Nov-17 22-Nov-17
C-C01-4150 Demo Walls / Ceilings 2 2 27-Nov-17 28-Nov-17
C-C01-4155 Core Drill 1 1 29-Nov-17 29-Nov-17
C-C01-4160 Install Condensate Drain 1 1 30-Nov-17 30-Nov-17
C-C01-4165 Patch Walls as Required 3 3 01-Dec-17 05-Dec-17
C-C01-4170 Re-Install Ceiling 1 1 06-Dec-17 06-Dec-17
C-C01-4175 Remove Temp Walls 1 1 07-Dec-17 07-Dec-17
NE - 100 NE Breakroom CondensateNE - 100 NE Breakroom Condensate11 11 31-Jan-18 14-Feb-18
C-C01-4180 Install Temp Walls 2 2 31-Jan-18 01-Feb-18
C-C01-4185 Demo Walls / Ceilings 2 2 02-Feb-18 05-Feb-18
C-C01-4190 Core Drill 1 1 06-Feb-18 06-Feb-18
C-C01-4195 Install Condensate Drain 1 1 07-Feb-18 07-Feb-18
C-C01-4200 Patch Walls as Required 3 3 08-Feb-18 12-Feb-18
C-C01-4205 Re-Install Ceiling 1 1 13-Feb-18 13-Feb-18
C-C01-4210 Remove Temp Walls 1 1 14-Feb-18 14-Feb-18
NE - Cashier 1 East Column & Room 218 CondensateNE - Cashier 1 East Column & Room 218 Condensate11 11 15-Feb-18 01-Mar-18
C-C01-4215 Install Temp Walls 2 2 15-Feb-18 16-Feb-18
C-C01-4220 Demo Walls / Ceilings 2 2 19-Feb-18 20-Feb-18
C-C01-4225 Core Drill 1 1 21-Feb-18 21-Feb-18
C-C01-4230 Install Condensate Drain 1 1 22-Feb-18 22-Feb-18
C-C01-4235 Patch Walls as Required 3 3 23-Feb-18 27-Feb-18
C-C01-4240 Re-Install Ceiling 1 1 28-Feb-18 28-Feb-18
C-C01-4245 Remove Temp Walls 1 1 01-Mar-18 01-Mar-18
NE - Rooms 309.2C & 309.6 CondensateNE - Rooms 309.2C & 309.6 Condensate11 11 02-Mar-18 16-Mar-18
C-C01-4250 Install Temp Walls 2 2 02-Mar-18 05-Mar-18
C-C01-4255 Demo Walls / Ceilings 2 2 06-Mar-18 07-Mar-18
C-C01-4260 Core Drill 1 1 08-Mar-18 08-Mar-18
C-C01-4265 Install Condensate Drain 1 1 09-Mar-18 09-Mar-18
C-C01-4270 Patch Walls as Required 3 3 12-Mar-18 14-Mar-18
C-C01-4275 Re-Install Ceiling 1 1 15-Mar-18 15-Mar-18
C-C01-4280 Remove Temp Walls 1 1 16-Mar-18 16-Mar-18
NE - Rooms 423A & 425 CondensateNE - Rooms 423A & 425 Condensate11 11 19-Mar-18 02-Apr-18
C-C01-4285 Install Temp Walls 2 2 19-Mar-18 20-Mar-18
C-C01-4290 Demo Walls / Ceilings 2 2 21-Mar-18 22-Mar-18
C-C01-4295 Core Drill 1 1 23-Mar-18 23-Mar-18
C-C01-4300 Install Condensate Drain 1 1 26-Mar-18 26-Mar-18
J A J A J A A A A J A J A J A A J A J A J
2017 2018 2019 2020 2021 2022 2023
Remove Temp Walls
Install Temp Walls
Demo Walls / Ceilings
Core Drill
Install Condensate Drain
Patch Walls as Required
Re-Install Ceiling
Remove Temp Walls
Install Temp Walls
Demo Walls / Ceilings
Core Drill
Install Condensate Drain
Patch Walls as Required
Re-Install Ceiling
Remove Temp Walls
Install Temp Walls
Demo Walls / Ceilings
Core Drill
Install Condensate Drain
Patch Walls as Required
Re-Install Ceiling
Remove Temp Walls
Install Temp Walls
Demo Walls / Ceilings
Core Drill
Install Condensate Drain
Patch Walls as Required
Re-Install Ceiling
Remove Temp Walls
Install Temp Walls
Demo Walls / Ceilings
Core Drill
Install Condensate Drain
Start Date 23-Feb-15
Finish Date 30-Dec-22
Data Date 21-Aug-17
Run Date 30-Aug-17
Page 24 of 33
3707-CR29
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-C01-4305 Patch Walls as Required 3 3 27-Mar-18 29-Mar-18
C-C01-4310 Re-Install Ceiling 1 1 30-Mar-18 30-Mar-18
C-C01-4315 Remove Temp Walls 1 1 02-Apr-18 02-Apr-18
NE - Rooms 528 & 527B CondensateNE - Rooms 528 & 527B Condensate11 11 03-Apr-18 17-Apr-18
C-C01-4320 Install Temp Walls 2 2 03-Apr-18 04-Apr-18
C-C01-4325 Demo Walls / Ceilings 2 2 05-Apr-18 06-Apr-18
C-C01-4330 Core Drill 1 1 09-Apr-18 09-Apr-18
C-C01-4335 Install Condensate Drain 1 1 10-Apr-18 10-Apr-18
C-C01-4340 Patch Walls as Required 3 3 11-Apr-18 13-Apr-18
C-C01-4345 Re-Install Ceiling 1 1 16-Apr-18 16-Apr-18
C-C01-4350 Remove Temp Walls 1 1 17-Apr-18 17-Apr-18
SE - Governors Waiting & Restroom CondensateSE - Governors Waiting & Restroom Condensate11 11 31-Jan-18 14-Feb-18
C-C01-4355 Install Temp Walls 2 2 31-Jan-18 01-Feb-18
C-C01-4360 Demo Walls / Ceilings 2 2 02-Feb-18 05-Feb-18
C-C01-4365 Core Drill 1 1 06-Feb-18 06-Feb-18
C-C01-4370 Install Condensate Drain 1 1 07-Feb-18 07-Feb-18
C-C01-4375 Patch Walls as Required 3 3 08-Feb-18 12-Feb-18
C-C01-4380 Re-Install Ceiling 1 1 13-Feb-18 13-Feb-18
C-C01-4385 Remove Temp Walls 1 1 14-Feb-18 14-Feb-18
SE - Rooms 309.28 & 309.23E CondensateSE - Rooms 309.28 & 309.23E Condensate11 11 15-Feb-18 01-Mar-18
C-C01-4390 Install Temp Walls 2 2 15-Feb-18 16-Feb-18
C-C01-4395 Demo Walls / Ceilings 2 2 19-Feb-18 20-Feb-18
C-C01-4400 Core Drill 1 1 21-Feb-18 21-Feb-18
C-C01-4405 Install Condensate Drain 1 1 22-Feb-18 22-Feb-18
C-C01-4410 Patch Walls as Required 3 3 23-Feb-18 27-Feb-18
C-C01-4415 Re-Install Ceiling 1 1 28-Feb-18 28-Feb-18
C-C01-4420 Remove Temp Walls 1 1 01-Mar-18 01-Mar-18
SE - Rooms 418 & 414 CondensateSE - Rooms 418 & 414 Condensate11 11 02-Mar-18 16-Mar-18
C-C01-4425 Install Temp Walls 2 2 02-Mar-18 05-Mar-18
C-C01-4430 Demo Walls / Ceilings 2 2 06-Mar-18 07-Mar-18
C-C01-4435 Core Drill 1 1 08-Mar-18 08-Mar-18
C-C01-4440 Install Condensate Drain 1 1 09-Mar-18 09-Mar-18
C-C01-4445 Patch Walls as Required 3 3 12-Mar-18 14-Mar-18
C-C01-4450 Re-Install Ceiling 1 1 15-Mar-18 15-Mar-18
C-C01-4455 Remove Temp Walls 1 1 16-Mar-18 16-Mar-18
SE - Rooms 522B & 520 CondensateSE - Rooms 522B & 520 Condensate11 11 19-Mar-18 02-Apr-18
C-C01-4460 Install Temp Walls 2 2 19-Mar-18 20-Mar-18
C-C01-4465 Demo Walls / Ceilings 2 2 21-Mar-18 22-Mar-18
J A J A J A A A A J A J A J A A J A J A J
2017 2018 2019 2020 2021 2022 2023
Patch Walls as Required
Re-Install Ceiling
Remove Temp Walls
Install Temp Walls
Demo Walls / Ceilings
Core Drill
Install Condensate Drain
Patch Walls as Required
Re-Install Ceiling
Remove Temp Walls
Install Temp Walls
Demo Walls / Ceilings
Core Drill
Install Condensate Drain
Patch Walls as Required
Re-Install Ceiling
Remove Temp Walls
Install Temp Walls
Demo Walls / Ceilings
Core Drill
Install Condensate Drain
Patch Walls as Required
Re-Install Ceiling
Remove Temp Walls
Install Temp Walls
Demo Walls / Ceilings
Core Drill
Install Condensate Drain
Patch Walls as Required
Re-Install Ceiling
Remove Temp Walls
Install Temp Walls
Demo Walls / Ceilings
Start Date 23-Feb-15
Finish Date 30-Dec-22
Data Date 21-Aug-17
Run Date 30-Aug-17
Page 25 of 33
3707-CR29
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-C01-4470 Core Drill 1 1 23-Mar-18 23-Mar-18
C-C01-4475 Install Condensate Drain 1 1 26-Mar-18 26-Mar-18
C-C01-4480 Patch Walls as Required 3 3 27-Mar-18 29-Mar-18
C-C01-4485 Re-Install Ceiling 1 1 30-Mar-18 30-Mar-18
C-C01-4490 Remove Temp Walls 1 1 02-Apr-18 02-Apr-18
Attic SpaceAttic Space700 700 01-Jul-18 30-May-20
ConstructionConstruction700 700 01-Jul-18 30-May-20
Construction Phase SummariesConstruction Phase Summaries700 700 01-Jul-18 30-May-20
S-C02-1000 Construction - Attic Space 700 700 01-Jul-18* 30-May-20
Stairs / Public RestroomsStairs / Public Restrooms730 730 01-Jan-19 30-Dec-20
ConstructionConstruction730 730 01-Jan-19 30-Dec-20
Construction Phase SummariesConstruction Phase Summaries730 730 01-Jan-19 30-Dec-20
S-C03-1000 Construction - Stairs / Public Restrooms 730 730 01-Jan-19* 30-Dec-20
RotundaRotunda1095 1095 01-Jan-20 30-Dec-22
ConstructionConstruction1095 1095 01-Jan-20 30-Dec-22
Construction Phase SummariesConstruction Phase Summaries1095 1095 01-Jan-20 30-Dec-22
S-C04-1000 Construction - Rotunda 1095 1095 01-Jan-20* 30-Dec-22
Hole in FloorHole in Floor364 364 01-Jun-20 30-May-21
ConstructionConstruction364 364 01-Jun-20 30-May-21
Construction Phase SummariesConstruction Phase Summaries364 364 01-Jun-20 30-May-21
S-C05-1000 Construction - Hole in Floor 364 364 01-Jun-20* 30-May-21
Visitor's EntranceVisitor's Entrance1479 1479 21-Aug-17 07-Sep-21
ConstructionConstruction1479 1479 21-Aug-17 07-Sep-21
Construction Phase SummariesConstruction Phase Summaries1479 1479 21-Aug-17 07-Sep-21
S-C06-0900 Construction - By Others 930 930 21-Aug-17* 07-Mar-20
S-C06-1000 Construction - Visitor Entrance 549 549 08-Mar-20* 07-Sep-21
TenantsTenants1243 1170 20-Apr-17 A 30-Mar-22
1st Floor Secretary of State1st Floor Secretary of State174 101 20-Apr-17 A 15-Jan-18
Material ProcurementMaterial Procurement50 36 28-Jul-17 A 10-Oct-17
Floor CoveringFloor Covering40 36 15-Aug-17 A 10-Oct-17
P-T01-1155 Fab & Deliver - Carpet 40 36 15-Aug-17 A 10-Oct-17
J A J A J A A A A J A J A J A A J A J A J
2017 2018 2019 2020 2021 2022 2023
Core Drill
Install Condensate Drain
Patch Walls as Required
Re-Install Ceiling
Remove Temp Walls
Construction - Attic Space
Construction - Stairs / Public Restrooms
Construction - Rotund
Construction - Hole in Floor
Construction - By Others
Construction - Visitor Entrance
Fab & Deliver - Carpet
Start Date 23-Feb-15
Finish Date 30-Dec-22
Data Date 21-Aug-17
Run Date 30-Aug-17
Page 26 of 33
3707-CR29
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
P-T01-1150 Fab & Deliver - Marble Tile 15 15 30-Aug-17 20-Sep-17
Doors / HardwareDoors / Hardware40 35 14-Aug-17 A 09-Oct-17
P-T01-1125 Fab & Deliver - Doors & Hardware 40 35 14-Aug-17 A 09-Oct-17
MillworkMillwork20 18 28-Jul-17 A 14-Sep-17
P-T01-1095 Fab & Deliver - Painted Trim (Painted in Shop) 10 1 28-Jul-17 A 21-Aug-17
P-T01-1080 Fab & Deliver - MIllwork 20 18 17-Aug-17 A 14-Sep-17
ConstructionConstruction174 101 20-Apr-17 A 15-Jan-18
Schedule Driven MilestonesSchedule Driven Milestones0 0 15-Jan-18 15-Jan-18
M-T01-1045 Interim Substantial Completion - Secretary of State 0 0 15-Jan-18
Construction Phase SummariesConstruction Phase Summaries152 148 20-Apr-17 A 15-Jan-18
S-T01-1000 Construction - 1st Floor Secretary of State 152 148 20-Apr-17 A 15-Jan-18
Secretary of StateSecretary of State108 101 10-Aug-17 A 15-Jan-18
C-T01-1150 Install Ceiling Grid with Borders 5 5 10-Aug-17 A 25-Aug-17
C-T01-1160 Above Ceiling Inspections 3 1 17-Aug-17 A 21-Aug-17
C-T01-1135 Install Door Frames 3 3 21-Aug-17 23-Aug-17
C-T01-1145 Install Base / Case / Crown 10 10 22-Aug-17 05-Sep-17
C-T01-1155 Overhead Device Out 3 3 23-Aug-17 25-Aug-17
C-T01-1250 Install Sub Floor 5 5 23-Aug-17 29-Aug-17
C-T01-1140 Plaster in Rotunda 30 30 24-Aug-17 05-Oct-17
C-T01-1025 80% Fire Marshall Inspection 0 0 29-Aug-17
C-T01-1170 Drop Ceiling Tile 2 2 30-Aug-17 31-Aug-17
C-T01-1165 Install Marble Tile 15 15 21-Sep-17 11-Oct-17
C-T01-1175 Install Carpet / LVT / SDT 10 10 11-Oct-17 01-Nov-17
C-T01-1180 Test & Balance 7 7 02-Nov-17 10-Nov-17
C-T01-1185 Install Millwork 10 10 02-Nov-17 15-Nov-17
C-T01-1190 Install Countertops 5 4 16-Nov-17 21-Nov-17
C-T01-1195 Hang Doors & Install Hardware 2 2 22-Nov-17 27-Nov-17
C-T01-1200 Final Paint 10 10 22-Nov-17 07-Dec-17
C-T01-1205 MCC Pre-punch 10 10 22-Nov-17 07-Dec-17
C-T01-1210 Install Glazing 4 4 27-Nov-17 30-Nov-17
C-T01-1030 100% Fire Marshall Inspection (Final) 0 0 27-Nov-17
C-T01-1215 FSB / OMES Punchlist 10 10 08-Dec-17 21-Dec-17
C-T01-1220 AE1 / Owner Punchlist 15 15 22-Dec-17 15-Jan-18
C-T01-1225 Owner Move In 0 0 15-Jan-18
6th Floor Senate6th Floor Senate189 133 02-Jun-17 A 28-Feb-18
Material ProcurementMaterial Procurement92 93 21-Jul-17 A 03-Jan-18
OAU & Heat PumpsOAU & Heat Pumps21 21 11-Sep-17 09-Oct-17
J A J A J A A A A J A J A J A A J A J A J
2017 2018 2019 2020 2021 2022 2023
Fab & Deliver - Marble Tile
Fab & Deliver - Doors & Hardware
Fab & Deliver - Painted Trim (Painted in Shop)
Fab & Deliver - MIllwork
Interim Substantial Completion - Secretary of State
Construction - 1st Floor Secretary of State
Install Ceiling Grid with Borders
Above Ceiling Inspections
Install Door Frames
Install Base / Case / Crown
Overhead Device Out
Install Sub Floor
Plaster in Rotunda
80% Fire Marshall Inspection
Drop Ceiling Tile
Install Marble Tile
Install Carpet / LVT / SDT
Test & Balance
Install Millwork
Install Countertops
Hang Doors & Install Hardware
Final Paint
MCC Pre-punch
Install Glazing
100% Fire Marshall Inspection (Final)
FSB / OMES Punchlist
AE1 / Owner Punchlist
Owner Move In
Start Date 23-Feb-15
Finish Date 30-Dec-22
Data Date 21-Aug-17
Run Date 30-Aug-17
Page 27 of 33
3707-CR29
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
P-T02-1000 MCC Receive / Review Submittal - Heat Pumps 1 1 11-Sep-17 11-Sep-17
P-T02-1030 AE2 (FSB) Receive / Review Submittal - Heat Pumps 10 10 12-Sep-17 25-Sep-17
P-T02-1035 Fab & Deliver - Heat Pumps 10 10 26-Sep-17 09-Oct-17
Floor CoveringFloor Covering69 69 11-Sep-17 18-Dec-17
P-T02-1015 Solicit & Advertise Flooring for Bid 19 19 11-Sep-17 05-Oct-17
P-T02-1050 Flooring Contracting 10 10 06-Oct-17 19-Oct-17
P-T02-1085 Fab & Deliver - Marble Tile 15 15 20-Oct-17 09-Nov-17
P-T02-1090 Fab & Deliver - Carpet 40 40 20-Oct-17 18-Dec-17
Doors / HardwareDoors / Hardware40 36 15-Aug-17 A 10-Oct-17
P-T02-1125 Fab & Deliver - Door Frames 15 11 15-Aug-17 A 05-Sep-17
P-T02-1145 Fab & Deliver - Doors & Hardware 40 36 15-Aug-17 A 10-Oct-17
MillworkMillwork50 50 11-Sep-17 17-Nov-17
P-T02-1040 Millwork Pricing & Submittal Prep 10 10 11-Sep-17 22-Sep-17
P-T02-1065 MCC Receive / Review Submittal - MIllwork 10 10 25-Sep-17 06-Oct-17
P-T02-1095 AE2 (FSB) Receive / Review Submittal - MIllwork 10 10 09-Oct-17 20-Oct-17
P-T02-1115 Fab & Deliver - Base / Case / Crown 5 5 23-Oct-17 27-Oct-17
P-T02-1120 Fab & Deliver - Painted Trim (Painted in Shop) 10 10 23-Oct-17 03-Nov-17
P-T02-1140 Fab & Deliver - MIllwork 20 20 23-Oct-17 17-Nov-17
StairsStairs79 79 11-Sep-17 03-Jan-18
P-T02-1020 Pricing Stairs 19 19 11-Sep-17 05-Oct-17
P-T02-1055 Stairs Contracting & Submittal Prep 10 10 06-Oct-17 19-Oct-17
P-T02-1075 MCC Receive / Review Submittal - Stairs 10 10 20-Oct-17 02-Nov-17
P-T02-1105 AE2 (FSB) Receive / Review Submittal -Stairs 10 10 03-Nov-17 16-Nov-17
P-T02-1130 Fab & Deliver - Stairs 30 30 17-Nov-17 03-Jan-18
ChairliftChairlift90 91 21-Jul-17 A 29-Dec-17
P-T02-1025 Pricing Chairlift 19 1 21-Jul-17 A 21-Aug-17
P-T02-1060 Chairlift Contracting & Submittal Prep 10 10 22-Aug-17 05-Sep-17
P-T02-1080 MCC Receive / Review Submittal - Chairlift 10 10 06-Sep-17 19-Sep-17
P-T02-1110 AE2 (FSB) Receive / Review Submittal -Chairlift 10 10 20-Sep-17 03-Oct-17
P-T02-1135 Fab & Deliver - Chairlift 60 60 04-Oct-17 29-Dec-17
ConstructionConstruction189 133 02-Jun-17 A 28-Feb-18
Schedule Driven MilestonesSchedule Driven Milestones64 64 28-Nov-17 28-Feb-18
M-T02-1010 LV / FA / IT Complete 0 0 28-Nov-17
M-T02-1015 Interim Substantial Completion - 6th Floor Senate 0 0 28-Feb-18
Construction Phase SummariesConstruction Phase Summaries181 187 02-Jun-17 A 23-Feb-18
S-T02-1000 Construction - 6th Floor Senate 181 187 02-Jun-17 A 23-Feb-18
6th Floor Senate6th Floor Senate167 133 10-Jul-17 A 28-Feb-18
C-T02-1265 Re-Design for Existing Condtions 15 5 10-Jul-17 A 25-Aug-17
J A J A J A A A A J A J A J A A J A J A J
2017 2018 2019 2020 2021 2022 2023
MCC Receive / Review Submittal - Heat Pumps
AE2 (FSB) Receive / Review Submittal - Heat Pumps
Fab & Deliver - Heat Pumps
Solicit & Advertise Flooring for Bid
Flooring Contracting
Fab & Deliver - Marble Tile
Fab & Deliver - Carpet
Fab & Deliver - Door Frames
Fab & Deliver - Doors & Hardware
Millwork Pricing & Submittal Prep
MCC Receive / Review Submittal - MIllwork
AE2 (FSB) Receive / Review Submittal - MIllwork
Fab & Deliver - Base / Case / Crown
Fab & Deliver - Painted Trim (Painted in Shop)
Fab & Deliver - MIllwork
Pricing Stairs
Stairs Contracting & Submittal Prep
MCC Receive / Review Submittal - Stairs
AE2 (FSB) Receive / Review Submittal -Stairs
Fab & Deliver - Stairs
Pricing Chairlift
Chairlift Contracting & Submittal Prep
MCC Receive / Review Submittal - Chairlift
AE2 (FSB) Receive / Review Submittal -Chairlift
Fab & Deliver - Chairlift
LV / FA / IT Complete
Interim Substantial Completion - 6th Floor Senate
Construction - 6th Floor Senate
Re-Design for Existing Condtions
Start Date 23-Feb-15
Finish Date 30-Dec-22
Data Date 21-Aug-17
Run Date 30-Aug-17
Page 28 of 33
3707-CR29
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
C-T02-1045 Rough-In Overhead Electric 5 5 28-Aug-17 01-Sep-17
C-T02-1040 Layout, Frame Walls & Install Door Frames 15 15 06-Sep-17 26-Sep-17
C-T02-1060 Rough-In In Wall 5 5 27-Sep-17 03-Oct-17
C-T02-1070 Frame Hard Lids 5 5 27-Sep-17 03-Oct-17
C-T02-1095 Rough-In @ Hard Lids 5 5 04-Oct-17 10-Oct-17
C-T02-1050 Rough-In Overhead Mechanical 5 5 10-Oct-17 24-Oct-17
C-T02-1100 Overhead @ Hardlids & In-Wall Inspec tions 3 3 11-Oct-17 23-Oct-17
C-T02-1085 Rough-In Fire Suppression 5 5 23-Oct-17 27-Oct-17
C-T02-1065 Rough-In Mechanical Piping 5 5 23-Oct-17 27-Oct-17
C-T02-1075 Insulate Mechanical 10 10 23-Oct-17 03-Nov-17
C-T02-1080 50% Fire Marshall Inspection 0 0 27-Oct-17
C-T02-1105 Hang Sheetrock 7 7 06-Nov-17 14-Nov-17
C-T02-1110 Tape / Bed / Paint Sheetrock 10 10 13-Nov-17 28-Nov-17
C-T02-1125 Install Base / Case / Crown 10 10 22-Nov-17 07-Dec-17
C-T02-1130 Install Ceiling Grid with Borders 5 5 29-Nov-17 05-Dec-17
C-T02-1150 Install Marble Tile @ Restroom 5 5 29-Nov-17 05-Dec-17
C-T02-1135 Overhead Device Out 3 3 01-Dec-17 05-Dec-17
C-T02-1140 80% Fire Marshall Inspection 0 0 05-Dec-17
C-T02-1145 Above Ceiling Inspections 2 2 06-Dec-17 07-Dec-17
C-T02-1155 Drop Ceiling Tile 2 2 08-Dec-17 11-Dec-17
C-T02-1160 Install Carpet / LVT / SDT 10 10 19-Dec-17 03-Jan-18
C-T02-1165 Install Millwork 5 5 27-Dec-17 03-Jan-18
C-T02-1055 Installation of Chairlift 40 40 02-Jan-18 26-Feb-18
C-T02-1175 Install Countertops 2 2 04-Jan-18 05-Jan-18
C-T02-1180 Hang Doors & Install Hardware 2 2 04-Jan-18 05-Jan-18
C-T02-1260 Installation of Stairs 40 40 04-Jan-18 28-Feb-18
C-T02-1170 Test & Balance 7 7 08-Jan-18 16-Jan-18
C-T02-1185 Final Paint 10 10 08-Jan-18 19-Jan-18
C-T02-1190 MCC Pre-punch 10 10 08-Jan-18 19-Jan-18
C-T02-1205 FSB / OMES Punchlist 10 10 22-Jan-18 02-Feb-18
C-T02-1210 AE1 / Owner Punchlist 15 15 05-Feb-18 23-Feb-18
C-T02-1215 Owner Move In 0 0 23-Feb-18
C-T02-1200 100% Fire Marshall Inspection (Final) 0 0 28-Feb-18
1st Floor OMES East1st Floor OMES East212 194 16-Jan-18 28-Jul-18
ConstructionConstruction212 194 16-Jan-18 28-Jul-18
Construction Phase SummariesConstruction Phase Summaries212 194 16-Jan-18 28-Jul-18
S-T03-1000 Construction - OMES East 212 194 16-Jan-18 28-Jul-18
J A J A J A A A A J A J A J A A J A J A J
2017 2018 2019 2020 2021 2022 2023
Rough-In Overhead Electric
Layout, Frame Walls & Install Door Frames
Rough-In In Wall
Frame Hard Lids
Rough-In @ Hard Lids
Rough-In Overhead Mechanical
Overhead @ Hardlids & In-Wall Inspec tions
Rough-In Fire Suppression
Rough-In Mechanical Piping
Insulate Mechanical
50% Fire Marshall Inspection
Hang Sheetrock
Tape / Bed / Paint Sheetrock
Install Base / Case / Crown
Install Ceiling Grid with Borders
Install Marble Tile @ Restroom
Overhead Device Out
80% Fire Marshall Inspection
Above Ceiling Inspections
Drop Ceiling Tile
Install Carpet / LVT / SDT
Install Millwork
Installation of Chairlift
Install Countertops
Hang Doors & Install Hardware
Installation of Stairs
Test & Balance
Final Paint
MCC Pre-punch
FSB / OMES Punchlist
AE1 / Owner Punchlist
Owner Move In
100% Fire Marshall Inspection (Final)
Construction - OMES East
Start Date 23-Feb-15
Finish Date 30-Dec-22
Data Date 21-Aug-17
Run Date 30-Aug-17
Page 29 of 33
3707-CR29
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
5th Floor Senate East5th Floor Senate East245 245 29-Jul-18 30-Mar-19
ConstructionConstruction245 245 29-Jul-18 30-Mar-19
Construction Phase SummariesConstruction Phase Summaries245 245 29-Jul-18 30-Mar-19
S-T04-1000 Construction - 5th Floor Senate East 245 245 29-Jul-18 30-Mar-19
4th Floor Senate East4th Floor Senate East245 245 29-Jul-18 30-Mar-19
ConstructionConstruction245 245 29-Jul-18 30-Mar-19
Construction Phase SummariesConstruction Phase Summaries245 245 29-Jul-18 30-Mar-19
S-T05-1000 Construction - 4th Floor Senate East 245 245 29-Jul-18 30-Mar-19
2nd Floor Governor2nd Floor Governor365 365 28-Feb-19 27-Feb-20
ConstructionConstruction365 365 28-Feb-19 27-Feb-20
Construction Phase SummariesConstruction Phase Summaries365 365 28-Feb-19 27-Feb-20
S-T06-1000 Construction - 2nd Floor Governor 365 365 28-Feb-19 27-Feb-20
Court of Criminal AppealsCourt of Criminal Appeals365 365 28-Feb-19 27-Feb-20
ConstructionConstruction365 365 28-Feb-19 27-Feb-20
Construction Phase SummariesConstruction Phase Summaries365 365 28-Feb-19 27-Feb-20
S-T07-1000 Construction - Court of Criminal Appeals 365 365 28-Feb-19 27-Feb-20
1st Floor OMES North1st Floor OMES North242 242 31-Mar-19 27-Nov-19
ConstructionConstruction242 242 31-Mar-19 27-Nov-19
Construction Phase SummariesConstruction Phase Summaries242 242 31-Mar-19 27-Nov-19
S-T08-1000 Construction - OMES North 242 242 31-Mar-19 27-Nov-19
1st Floor Photographer1st Floor Photographer181 181 31-Mar-19 27-Sep-19
ConstructionConstruction181 181 31-Mar-19 27-Sep-19
Construction Phase SummariesConstruction Phase Summaries181 181 31-Mar-19 27-Sep-19
S-T09-1000 Construction - 1st Floor Photographer 181 181 31-Mar-19 27-Sep-19
1st Floor LSB1st Floor LSB181 181 31-Mar-19 27-Sep-19
ConstructionConstruction181 181 31-Mar-19 27-Sep-19
Construction Phase SummariesConstruction Phase Summaries181 181 31-Mar-19 27-Sep-19
S-T10-1000 Construction - 1st Floor LSB 181 181 31-Mar-19 27-Sep-19
2nd Floor Judicial2nd Floor Judicial427 305 29-Jul-19 28-May-20
ConstructionConstruction427 305 29-Jul-19 28-May-20
J A J A J A A A A J A J A J A A J A J A J
2017 2018 2019 2020 2021 2022 2023
Construction - 5th Floor Senate East
Construction - 4th Floor Senate East
Construction - 2nd Floor Governor
Construction - Court of Criminal Appeals
Construction - OMES North
Construction - 1st Floor Photographer
Construction - 1st Floor LSB
Start Date 23-Feb-15
Finish Date 30-Dec-22
Data Date 21-Aug-17
Run Date 30-Aug-17
Page 30 of 33
3707-CR29
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
Construction Phase SummariesConstruction Phase Summaries427 305 29-Jul-19 28-May-20
S-T11-1000 Construction - 2nd Floor Judicial 427 305 29-Jul-19 28-May-20
2nd Floor House West2nd Floor House West245 245 29-Jul-19 29-Mar-20
ConstructionConstruction245 245 29-Jul-19 29-Mar-20
Construction Phase SummariesConstruction Phase Summaries245 245 29-Jul-19 29-Mar-20
S-T12-1000 Construction - 2nd Floor House West 245 245 29-Jul-19 29-Mar-20
2nd Floor Senate North2nd Floor Senate North245 245 29-Jul-19 29-Mar-20
ConstructionConstruction245 245 29-Jul-19 29-Mar-20
Construction Phase SummariesConstruction Phase Summaries245 245 29-Jul-19 29-Mar-20
S-T13-1000 Construction - 2nd Floor Senate North 245 245 29-Jul-19 29-Mar-20
2nd Floor Treasurer2nd Floor Treasurer184 184 28-Sep-19 29-Mar-20
ConstructionConstruction184 184 28-Sep-19 29-Mar-20
Construction Phase SummariesConstruction Phase Summaries184 184 28-Sep-19 29-Mar-20
S-T14-1000 Construction - 2nd Floor Treasurer 184 184 28-Sep-19 29-Mar-20
1st Floor Lt Governor1st Floor Lt Governor184 184 28-Sep-19 29-Mar-20
ConstructionConstruction184 184 28-Sep-19 29-Mar-20
Construction Phase SummariesConstruction Phase Summaries184 184 28-Sep-19 29-Mar-20
S-T15-1000 Construction - 1st Floor Lt Governor 184 184 28-Sep-19 29-Mar-20
3rd Floor House West3rd Floor House West244 244 28-Sep-19 28-May-20
ConstructionConstruction244 244 28-Sep-19 28-May-20
Construction Phase SummariesConstruction Phase Summaries244 244 28-Sep-19 28-May-20
S-T16-1000 Construction - 3rd Floor House West 244 244 28-Sep-19 28-May-20
3rd Floor Senate North3rd Floor Senate North244 244 28-Sep-19 28-May-20
ConstructionConstruction244 244 28-Sep-19 28-May-20
Construction Phase SummariesConstruction Phase Summaries244 244 28-Sep-19 28-May-20
S-T17-1000 Construction - 3rd Floor Senate North 244 244 28-Sep-19 28-May-20
1st Floor Gov Elect1st Floor Gov Elect213 213 28-Feb-20 27-Sep-20
ConstructionConstruction213 213 28-Feb-20 27-Sep-20
Construction Phase SummariesConstruction Phase Summaries213 213 28-Feb-20 27-Sep-20
S-T18-1000 Construction - 1st Floor Gov Elect 213 213 28-Feb-20 27-Sep-20
J A J A J A A A A J A J A J A A J A J A J
2017 2018 2019 2020 2021 2022 2023
Construction - 2nd Floor Judicial
Construction - 2nd Floor House West
Construction - 2nd Floor Senate North
Construction - 2nd Floor Treasurer
Construction - 1st Floor Lt Governor
Construction - 3rd Floor House West
Construction - 3rd Floor Senate North
Construction - 1st Floor Gov Elect
Start Date 23-Feb-15
Finish Date 30-Dec-22
Data Date 21-Aug-17
Run Date 30-Aug-17
Page 31 of 33
3707-CR29
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
1st Floor Auditor1st Floor Auditor152 152 28-Feb-20 28-Jul-20
ConstructionConstruction152 152 28-Feb-20 28-Jul-20
Construction Phase SummariesConstruction Phase Summaries152 152 28-Feb-20 28-Jul-20
S-T19-1000 Construction - 1st Floor Auditor 152 152 28-Feb-20 28-Jul-20
4th Floor Senate North4th Floor Senate North182 182 28-Feb-20 27-Aug-20
ConstructionConstruction182 182 28-Feb-20 27-Aug-20
Construction Phase SummariesConstruction Phase Summaries182 182 28-Feb-20 27-Aug-20
S-T20-1000 Construction - 4th Floor Senate North 182 182 28-Feb-20 27-Aug-20
419 A & B419 A & B182 182 28-Feb-20 27-Aug-20
ConstructionConstruction182 182 28-Feb-20 27-Aug-20
Construction Phase SummariesConstruction Phase Summaries182 182 28-Feb-20 27-Aug-20
S-T21-1000 Construction - 419 A & B 182 182 28-Feb-20 27-Aug-20
511 A511 A182 182 28-Feb-20 27-Aug-20
ConstructionConstruction182 182 28-Feb-20 27-Aug-20
Construction Phase SummariesConstruction Phase Summaries182 182 28-Feb-20 27-Aug-20
S-T22-1000 Construction - 511 A 182 182 28-Feb-20 27-Aug-20
1st Floor Multipurpose1st Floor Multipurpose153 153 29-Jul-20 28-Dec-20
ConstructionConstruction153 153 29-Jul-20 28-Dec-20
Construction Phase SummariesConstruction Phase Summaries153 153 29-Jul-20 28-Dec-20
S-T23-1000 Construction - 1st Floor Multipurpose 153 153 29-Jul-20 28-Dec-20
5th Floor Senate North5th Floor Senate North245 245 29-Jul-20 30-Mar-21
ConstructionConstruction245 245 29-Jul-20 30-Mar-21
Construction Phase SummariesConstruction Phase Summaries245 245 29-Jul-20 30-Mar-21
S-T24-1000 Construction - 5th Floor Senate North 245 245 29-Jul-20 30-Mar-21
5th Floor Conf. Rooms South5th Floor Conf. Rooms South245 245 29-Jul-20 30-Mar-21
ConstructionConstruction245 245 29-Jul-20 30-Mar-21
Construction Phase SummariesConstruction Phase Summaries245 245 29-Jul-20 30-Mar-21
S-T25-1000 Construction - 5th Floor Conference Rooms South 245 245 29-Jul-20 30-Mar-21
4th Floor House Committee N4th Floor House Committee N245 245 29-Jul-20 30-Mar-21
ConstructionConstruction245 245 29-Jul-20 30-Mar-21
J A J A J A A A A J A J A J A A J A J A J
2017 2018 2019 2020 2021 2022 2023
Construction - 1st Floor Auditor
Construction - 4th Floor Senate North
Construction - 419 A & B
Construction - 511 A
Construction - 1st Floor Multipurpose
Construction - 5th Floor Senate North
Construction - 5th Floor Conference Rooms South
Start Date 23-Feb-15
Finish Date 30-Dec-22
Data Date 21-Aug-17
Run Date 30-Aug-17
Page 32 of 33
3707-CR29
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
Activity ID Activity Name Orig Dur
RemDur
Start Finish
Construction Phase SummariesConstruction Phase Summaries245 245 29-Jul-20 30-Mar-21
S-T26-1000 Construction - 4th Floor House Committe North 245 245 29-Jul-20 30-Mar-21
4th Floor Press North4th Floor Press North245 245 29-Jul-20 30-Mar-21
ConstructionConstruction245 245 29-Jul-20 30-Mar-21
Construction Phase SummariesConstruction Phase Summaries245 245 29-Jul-20 30-Mar-21
S-T27-1000 Construction - 4th Floor Press North 245 245 29-Jul-20 30-Mar-21
4 & 5th Large Conf. Rms South4 & 5th Large Conf. Rms South245 245 29-Jul-20 30-Mar-21
ConstructionConstruction245 245 29-Jul-20 30-Mar-21
Construction Phase SummariesConstruction Phase Summaries245 245 29-Jul-20 30-Mar-21
S-T28-1000 Construction - 4 & 5th Large Conference Rooms South 245 245 29-Jul-20 30-Mar-21
4th Floor House West4th Floor House West245 245 29-Jul-20 30-Mar-21
ConstructionConstruction245 245 29-Jul-20 30-Mar-21
Construction Phase SummariesConstruction Phase Summaries245 245 29-Jul-20 30-Mar-21
S-T29-1000 Construction - 4th Floor House West 245 245 29-Jul-20 30-Mar-21
5th Floor House West5th Floor House West245 245 29-Jul-20 30-Mar-21
ConstructionConstruction245 245 29-Jul-20 30-Mar-21
Construction Phase SummariesConstruction Phase Summaries245 245 29-Jul-20 30-Mar-21
S-T30-1000 Construction - 5th Floor House West 245 245 29-Jul-20 30-Mar-21
6th Floor House West6th Floor House West181 181 28-Feb-21 27-Aug-21
ConstructionConstruction181 181 28-Feb-21 27-Aug-21
Construction Phase SummariesConstruction Phase Summaries181 181 28-Feb-21 27-Aug-21
S-T31-1000 Construction - 6th Floor House West 181 181 28-Feb-21 27-Aug-21
Senate ChambersSenate Chambers245 245 29-Jul-21 30-Mar-22
ConstructionConstruction245 245 29-Jul-21 30-Mar-22
Construction Phase SummariesConstruction Phase Summaries245 245 29-Jul-21 30-Mar-22
S-T32-1000 Construction - Senate Chambers 245 245 29-Jul-21 30-Mar-22
House ChambersHouse Chambers245 245 29-Jul-21 30-Mar-22
ConstructionConstruction245 245 29-Jul-21 30-Mar-22
Construction Phase SummariesConstruction Phase Summaries245 245 29-Jul-21 30-Mar-22
S-T33-1000 Construction - House Chambers 245 245 29-Jul-21 30-Mar-22
J A J A J A A A A J A J A J A A J A J A J
2017 2018 2019 2020 2021 2022 2023
Construction - 4th Floor House Committe North
Construction - 4th Floor Press North
Construction - 4 & 5th Large Conference Rooms South
Construction - 4th Floor House West
Construction - 5th Floor House West
Construction - 6th Floor House West
Construction - Senate Chambers
Construction - House Chambers
Start Date 23-Feb-15
Finish Date 30-Dec-22
Data Date 21-Aug-17
Run Date 30-Aug-17
Page 33 of 33
3707-CR29
TASK filter: Not Complete.
Actual Level of Effort
Actual Work
Remaining Work
Suspension
Remaining LOE
Critical Remaining Work
Milestone
Critical Milestones
Oklahoma Capitol Restoration-Interior RehabiliationOklahoma City, Oklahoma
MCC Project #3707
RFI LOG
SECTION 4
Monthly Progress Report – Oklahoma Capitol Restoration August 2017
4-1
RFI # Subject Author
Company
Answer
Company
Date
Created
Date
Req'd
Date Resp Dwg
Impact
001 Existing Wall Condition 8/4/2015 8/14/2015 Not Sure8/11/2015Manhattan Construction Company
Frankfurt Short Bruza
002 Demo Existing 6" Concrete Wall 8/13/2015 8/14/2015 Not Sure8/20/2015Manhattan Construction Company
Frankfurt Short Bruza
003 Slab Infills details 8/25/2015 8/28/2015 Not Sure9/1/2015Manhattan Construction Company
Frankfurt Short Bruza
004 MC Feeder Cables 8/27/2015 9/8/2015 Not Sure9/3/2015Manhattan Construction Company
Frankfurt Short Bruza
005 New Door Lay Out Senate 3rd Floor 8/28/2015 8/28/2015 Not Sure9/4/2015Manhattan Construction Company
Frankfurt Short Bruza
006 Bid Questions 9/1/2015 9/2/2015 Not Sure9/8/2015Manhattan Construction Company
Frankfurt Short Bruza
007 Tie in of Existing Plumbing 3rd Floor 9/3/2015 9/10/2015 Not Sure9/10/2015Manhattan Construction Company
Frankfurt Short Bruza
008 House UPS 9/9/2015 9/18/2015 Not Sure9/15/2015Manhattan Construction Company
Frankfurt Short Bruza
009 Door Hardware Specs vs Plans 9/14/2015 9/22/2015 Not Sure9/18/2015Manhattan Construction Company
Frankfurt Short Bruza
010 Lead Paint Abatement 9/25/2015 10/12/2015 Not Sure9/29/2015Manhattan Construction Company
Mass Architects, Inc.
011 Building Envelope 9/25/2015 10/12/2015 Not Sure9/29/2015Manhattan Construction Company
Mass Architects, Inc.
012 Voltage for H1, H1E, H2, H2E 9/30/2015 10/1/2015 Not Sure10/2/2015Manhattan Construction Company
Frankfurt Short Bruza
013 New Paint Schedule 10/22/2015 10/29/2015 Not Sure10/29/2015Manhattan Construction Company
Frankfurt Short Bruza
014 Keying 11/3/2015 1/4/2016 Not Sure11/18/2015Manhattan Construction Company
Mass Architects, Inc.
015 Exterior Windows 11/3/2015 1/4/2016 Not Sure11/18/2015Manhattan Construction Company
Mass Architects, Inc.
016 Color Selection Fabric Wrapped Panels 11/12/2015 11/17/2015 Not Sure11/17/2015Manhattan Construction Company
Frankfurt Short Bruza
017 Security 11/12/2015 11/24/2015 Not Sure11/27/2015Manhattan Construction Company
Mass Architects, Inc.
018 Capitol Maintenance 11/17/2015 3/25/2016 Not Sure11/23/2015Manhattan Construction Company
Mass Architects, Inc.
RFI LOG
SECTION 4
Monthly Progress Report – Oklahoma Capitol Restoration August 2017
4-2
RFI’s
018-R001
Capitol Maintenance - Water Infiltration 4/27/2016 5/12/2016 Not Sure5/17/2016Manhattan Construction Company
Mass Architects, Inc.
019 Structual Load 12/16/2015 12/22/2015 Not Sure12/23/2015Manhattan Construction Company
Frankfurt Short Bruza
020 H 109 Dog House Electrical Panel 4/25/2016 5/11/2016 Not Sure5/2/2016Manhattan Construction Company
Frankfurt Short Bruza
021 Window Infill 5/10/2016 5/17/2016 Not Sure5/12/2016Manhattan Construction Company
Frankfurt Short Bruza
022 Structural Infill Confirmation 5/11/2016 7/11/2016 Not Sure5/13/2016Manhattan Construction Company
Frankfurt Short Bruza
023 Mounting Heights 5/17/2016 5/19/2016 Not Sure5/24/2016Manhattan Construction Company
Frankfurt Short Bruza
024 Plaster at Rotunda 5/17/2016 5/19/2016 Not Sure5/20/2016Manhattan Construction Company
Frankfurt Short Bruza
025 Confirmation of Ceiling Height Room 109.11 5/17/2016 5/19/2016 No5/24/2016Manhattan Construction Company
Frankfurt Short Bruza
026 New Duct Chase Location 5/17/2016 5/19/2016 No5/20/2016Manhattan Construction Company
Frankfurt Short Bruza
027 Door 109.45 Swing Change 6/2/2016 6/3/2016 Not Sure6/9/2016Manhattan Construction Company
Frankfurt Short Bruza
028 Slab Penetration at Duct Chase 6/2/2016 6/21/2016 Not Sure6/10/2016Manhattan Construction Company
Frankfurt Short Bruza
029 Column Framing at Exterior Walls 6/2/2016 6/8/2016 Not Sure6/9/2016Manhattan Construction Company
Frankfurt Short Bruza
030 Structural In-fill Detail for NW Dog house 6/21/2016 6/24/2016 Not Sure6/24/2016Manhattan Construction Company
Frankfurt Short Bruza
031 109 Entry Clerk Return Air 6/29/2016 7/8/2016 Not Sure7/6/2016Manhattan Construction Company
Frankfurt Short Bruza
032 Urinal Mounting Heights 8/11/2016 8/17/2016 Not Sure8/18/2016Manhattan Construction Company
Frankfurt Short Bruza
RFI # Subject Author
Company
Answer
Company
Date
Created
Date
Req'd
Date Resp Dwg
Impact
033 Guardrails at Rotunda 10/4/2016 11/17/2016 Not Sure10/11/2016Manhattan Construction Company
Mass Architects, Inc.
034 Future Fiber Distribution Plans 10/10/2016 Not Sure10/17/2016Manhattan Construction Company
Mass Architects, Inc.
035 Elevator Pit Infill - Area 4 10/14/2016 11/4/2016 Not Sure10/21/2016Manhattan Construction Company
Frankfurt Short Bruza
036 Partial Footing Removal for Electrical Trenching 1/16/2017 1/27/2017 Not Sure1/23/2017Manhattan Construction Company
Frankfurt Short Bruza
7/10/2017
RFI LOG
SECTION 4
Monthly Progress Report – Oklahoma Capitol Restoration August 2017
4-3
RFI’s
Company
037 State Capitol Grounding 1/24/2017 1/27/2017 Not Sure1/31/2017Manhattan Construction Company
Frankfurt Short Bruza
038 Ground Rod Access Well 1/25/2017 2/20/2017 Not Sure2/1/2017OESCO Frankfurt Short Bruza
039 3.2 - Structural Clarifications 2/6/2017 2/21/2017 Not Sure2/13/2017Basden Steel Corporation Frankfurt Short Bruza
040 Variable Frequency Motor Controllers 2/9/2017 2/20/2017 Not Sure2/16/2017Manhattan Construction Company
Frankfurt Short Bruza
041 3.2 - Structural Clarifications 2/9/2017 2/21/2017 Not Sure2/16/2017Basden Steel Corporation Frankfurt Short Bruza
042 Structural Steel Connection 2/9/2017 2/22/2017 Not Sure2/16/2017Manhattan Construction Company
Frankfurt Short Bruza
043 3.2 - Stair Loads and Serviceability Confirmation 2/10/2017 2/22/2017 Not Sure2/17/2017Manhattan Construction Company
Frankfurt Short Bruza
044 Temporary Smoke Evacuation 2/14/2017 2/16/2017 Not Sure2/21/2017Manhattan Construction Company
Frankfurt Short Bruza
045 Miscellaneous Mechanical Piping Insulation 2/14/2017 2/20/2017 Not Sure2/21/2017Matherly Mechanical Contractors, LLC
Frankfurt Short Bruza
046 3.2 Stair and Railing Details 2/14/2017 2/22/2017 Not Sure2/21/2017Manhattan Construction Company
Frankfurt Short Bruza
047 3.2 Damper Clarifications 2/15/2017 2/16/2017 Not Sure2/22/2017Manhattan Construction Company
Frankfurt Short Bruza
048 3.2 Beam to Column Connection in Generator Area 2/21/2017 2/21/2017 Not Sure2/28/2017Manhattan Construction Company
Frankfurt Short Bruza
049 3.2 HSS8x4 Connections 2/24/2017 2/28/2017 Not Sure3/3/2017Manhattan Construction Company
Frankfurt Short Bruza
049-R001
3.2 HSS8x4 Connections 2/27/2017 3/13/2017 Not Sure3/6/2017Manhattan Construction Company
Frankfurt Short Bruza
050 3.2 - G-5 Diffuser Specification 2/24/2017 2/28/2017 Not Sure3/3/2017Manhattan Construction Company
Frankfurt Short Bruza
051 3.2 Duct Transition 2/28/2017 3/2/2017 Not Sure3/7/2017Manhattan Construction Company
Frankfurt Short Bruza
RFI # Subject Author
Company
Answer
Company
Date
Created
Date
Req'd
Date Resp Dwg
Impact
052 5th Floor SW Doghouse EM Bus Duct and Spiral Stair Conflict 3/8/2017 3/15/2017 Yes3/15/2017OESCO Frankfurt Short Bruza
053 3.2 FS Dampers at SW Doghouse 3/17/2017 3/22/2017 Not Sure3/24/2017Manhattan Construction Company
Frankfurt Short Bruza
054 RFI 054 - Electrical Panels BSE1 and BSE2 - Location Confirmation Request
3/30/2017 4/3/2017 Not Sure4/6/2017Manhattan Construction Company
Frankfurt Short Bruza
055 3.2 - Concrete Lintel at SW Elevator 4/3/2017 Not Sure4/10/2017Manhattan Construction Company
Frankfurt Short Bruza 4/14/2017
RFI LOG
SECTION 4
Monthly Progress Report – Oklahoma Capitol Restoration August 2017
4-4
RFI’s
Company
056 3.2 - Supply Grille Elevations at SW doghouse 4/4/2017 4/7/2017 Not Sure4/10/2017Manhattan Construction Company
Frankfurt Short Bruza
057 3.2 - Fire Smoke Damper at G-5 Supply Grille 4/5/2017 4/14/2017 Not Sure4/12/2017Manhattan Construction Company
Frankfurt Short Bruza
058 3.2 Steel Framing for ACCU's 4/13/2017 5/8/2017 Not Sure4/13/2017Manhattan Construction Company
Frankfurt Short Bruza
059 3.2 - Supply Air Duct Conflict in SW Doghouse 4/17/2017 4/28/2017 Not Sure4/24/2017Manhattan Construction Company
Frankfurt Short Bruza
060 3.2 - Slab Cores in SW Doghouse 4/19/2017 5/8/2017 Not Sure4/26/2017Manhattan Construction Company
Frankfurt Short Bruza
061 3.2 - Column to Beam Connx in SW Doghouse 5/5/2017 5/8/2017 Not Sure5/12/2017Manhattan Construction Company
Frankfurt Short Bruza
062 3.3 - Detail at Coffered Ceiling 5/9/2017 5/17/2017 Not Sure5/16/2017Manhattan Construction Company
Frankfurt Short Bruza
063 3.3 - Millwork Conflict in Office 122.5 5/9/2017 5/15/2017 Not Sure5/16/2017Manhattan Construction Company
Frankfurt Short Bruza
064 Clay Masonry Endwall Support 5/22/2017 6/23/2017 Not Sure5/29/2017Manhattan Construction Company
Frankfurt Short Bruza
065 Outside Air Wall Penetration Reinforcement 5/22/2017 6/9/2017 Not Sure5/29/2017Manhattan Construction Company
Frankfurt Short Bruza
066 Granite Removal for Waterproofing at Generator Areaway 5/24/2017 6/2/2017 Not Sure5/31/2017Manhattan Construction Company
Mass Architects, Inc.
067 3.2 & 3.3 - Finish Clarification 6/1/2017 6/8/2017 Not Sure6/8/2017Manhattan Construction Company
Frankfurt Short Bruza
068 3.3 - K1 Substitution in Area 122 6/22/2017 7/7/2017 Not Sure6/29/2017Manhattan Construction Company
Frankfurt Short Bruza
069 1SE1 Panel Clarification 6/28/2017 7/7/2017 Not Sure7/5/2017Manhattan Construction Company
Frankfurt Short Bruza
070 Dowels for Walls at Generator Areaway 6/28/2017 6/28/2017 Not Sure7/5/2017Manhattan Construction Company
Frankfurt Short Bruza
071 Generator Room Roof Structure Rust Remediation 7/5/2017 7/21/2017 No7/12/2017Manhattan Construction Frankfurt Short Bruza
Company
RFI # Subject Author
Company
Answer
Company
Date
Created
Date
Req'd
Date Resp Dwg
Impact
Company
072 Existing Beam Conflict for 6th Floor Framing 7/12/2017 7/14/2017 Not Sure7/19/2017Manhattan Construction Company
Frankfurt Short Bruza
073 East Elevator Rail to Beam Connection 7/13/2017 7/14/2017 Not Sure7/20/2017Manhattan Construction Company
Frankfurt Short Bruza
074 Fabric Wall Panels & Acoustic Plaster 7/20/2017 Not Sure7/27/2017Manhattan Construction Company
RFI LOG
SECTION 4
Monthly Progress Report – Oklahoma Capitol Restoration August 2017
4-5
RFI’s
Company
075 Stair Details at Machine Room 7/24/2017 8/22/2017 Not Sure7/31/2017Manhattan Construction Company
Frankfurt Short Bruza
076 Generator Exhaust Installation 7/31/2017 8/7/2017 Not Sure8/7/2017Manhattan Construction Company
Frankfurt Short Bruza
077 Generator Pad Detail 8/1/2017 8/11/2017 Not Sure8/8/2017Manhattan Construction Company
Frankfurt Short Bruza
078 Shower Wall in Men's G2.1 8/4/2017 8/14/2017 Not Sure8/11/2017Manhattan Construction Company
Mass Architects, Inc.
079 FSD's at Roof Penetrations 8/28/2017 8/29/2017 Not Sure9/4/2017Manhattan Construction Company
Frankfurt Short Bruza
81Total Number of RFIs for this project: 0
Total Created Total Outstanding
Company
Company
RFI # Subject Author
Company
Answer
Company
Date
Created
Date
Req'd
Date Resp Dwg
Impact
Company
Company
RFI # Subject Author
Company
Answer
Company
Date
Created
Date
Req'd
Date Resp Dwg
Impact
OUTSTANDING SUBMITTAL LOG
SECTION 5
Monthly Progress Report – Oklahoma Capitol Restoration August 2017
5-1
Submittals
Capitol Interior Restoration Project # 37072300 N Lincoln Blvd. Oklahoma City, OK 73105 Tel: 405-521-2147 Fax:
Number-Rev From Company Description To Company Sent Due Rec'd ActionDays +/-
Mass Architects, Inc.
290004-06 2023-0 Manhattan Construction Company 3.3 Interior Finish Carpentry - Secretary of State
Mass Architects, Inc. 7/25/2017 8/8/2017 Action Pending
290021-00 4253-0 Manhattan Construction Company 15151DB - Phase 6.0 35% SD Group 5 Mass Architects, Inc. 7/25/2017 8/8/2017 Action Pending
50022-00 4253-0 Manhattan Construction Company 15151DB Phase 4.0 95% CD's Mass Architects, Inc. 8/18/2017 9/1/2017 Action Pending
-50001-04 4313.13-1
Manhattan Construction Company Anchored Stone Masonry - Basement West Corridor - Shop Drawings
Mass Architects, Inc. 8/28/2017 9/11/2017 Action Pending
-50001-09 8433-0 Manhattan Construction Company Sound-Absorbing Wall Units Mass Architects, Inc. 8/28/2017 9/11/2017 Action Pending
-50024-00 4253-0 Manhattan Construction Company 15151 DB Phase 4.1 95% CD's Mass Architects, Inc. 8/28/2017 9/11/2017 Action Pending
-130004-23 8146.13-0
Manhattan Construction Company 4.1 Water to Air Heat Pumps Mass Architects, Inc. 9/5/2017 9/19/2017 Action Pending
-60002-09 3000-0 Manhattan Construction Company 3.3 - Tiling Mass Architects, Inc. 8/29/2017 9/12/2017 Action Pending
-60001-09 6813-0 Manhattan Construction Company 3.3 - Tile Carpeting Mass Architects, Inc. 8/29/2017 9/12/2017 Action Pending
-130003-26 0943-0 Manhattan Construction Company Haiku Wall Control - Product Data Mass Architects, Inc. 9/5/2017 9/19/2017 Action Pending
-130002-09 8433-0 Manhattan Construction Company 3.3 Sound Absorbing Wall Units - Samples
Mass Architects, Inc. 9/5/2017 9/19/2017 Action Pending
20023-00 4253-0 Manhattan Construction Company 15151DB Master Planning Capitol Color Palette
Mass Architects, Inc. 8/21/2017 9/4/2017 Action Pending
12Number of Submittal Packages in this Project:
PROGRESS PHOTOS
SECTION 6
Monthly Progress Report – Oklahoma Capitol Restoration
July 2017
6-1
Ground Level Framing and Sheetrock
PROGRESS PHOTOS
SECTION 6
Monthly Progress Report – Oklahoma Capitol Restoration July 2017
6-2
Pictured Left: Support
beams set at the new
generator areaway.
Generator Areaway Covering and Rust Remediation
Pictured Right: Rust
remediation taking place at
the old dungeon room.
Pictured Left: Grating
installed at the new
generator areaway.
PROGRESS PHOTOS
SECTION 6
Monthly Progress Report – Oklahoma Capitol Restoration July 2017
6-3
HVAC Rooftop Units Hoisted and Set with Crane
PROGRESS PHOTOS
SECTION 6
Monthly Progress Report – Oklahoma Capitol Restoration July 2017
6-4
Building Generator Hoisted and Set with Crane
PROGRESS PHOTOS
SECTION 6
Monthly Progress Report – Oklahoma Capitol Restoration July 2017
6-5
Secretary of State
Pictured Left: Plaster
completion outside the new
Secretary of State area.
Pictured Below: Painting at
the replica historic door
frames.
Pictured Left: Plaster work at
the south exterior wall of the
State room.
PROGRESS PHOTOS
SECTION 6
Monthly Progress Report – Oklahoma Capitol Restoration July 2017
6-6
Stonhard in SW Doghouse
Pictured: Stonhard floors
installed in all levels of the SW
doghouse.
PROGRESS PHOTOS
SECTION 6
Monthly Progress Report – Oklahoma Capitol Restoration July 2017
6-7
Supply/Return Grille Cut in at 5th Floor Rotunda
Pictured Right: Scaffold
erected outside House
Chamber to cut in the
supply/return grilles that will
condition the Rotunda.
Pictured Right: Finished
product of the grilles installed
outside the House Chambers.