Oil & Gas Plant Construction, Project Execution Plan
-
Upload
david-h-moloney -
Category
Engineering
-
view
3.199 -
download
73
Transcript of Oil & Gas Plant Construction, Project Execution Plan
![Page 1: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/1.jpg)
Oil & Gas Plant Construction
Project Execution Plan
Details of how a Gas & Oil Plant is constructed, and how the progress, safety and quality is monitored and controlled. Also the measures to ensure that the site is environmentally friendly.
http://www.slideshare.net/DavidHMoloney/oil-gas-plant-construction-project-execution-planhttps://www.youtube.com/watch?v=PiRY0ERoXfI
6avid H Moloney
4th August 2016
Brief Description
The purpose of this presentation is to give an understanding of the Methods, Plant and Sequence to construct a Gas & Oil Plant .
This presentation can be used to engage Stakeholders and to get the Site Teams commitment to the programme. Also can be used for Induction Training and as a way to capture and share knowledge.
Project Execution Plan (PEP) details how a project will be executed, monitored and controlled.
High in Educational Value and easily understood. Recommended for Continuing Professional Development (CPD)
This Video Presentation is innovative and has many beneficial uses.
![Page 2: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/2.jpg)
Table of Contents
![Page 3: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/3.jpg)
Contents
![Page 4: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/4.jpg)
Gas Processing Facility
Earthworks includes Excavation, Trenches, Haulage, Grading Backfilling, Filling & Compaction
Earthworks
![Page 5: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/5.jpg)
Excavate & Load Tipper Trucks
![Page 6: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/6.jpg)
Trench Excavation with Stepped Faces
![Page 7: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/7.jpg)
Trench Excavation with Battered Faces
![Page 8: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/8.jpg)
Tipper Trucks Unloading
![Page 9: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/9.jpg)
Spreading & Compaction Clay fillE
art
hw
ork
s
![Page 10: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/10.jpg)
Spreading & Compaction Clay fillE
art
hw
ork
s
![Page 11: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/11.jpg)
Backfill TrenchE
art
hw
ork
s
![Page 12: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/12.jpg)
Dozer Pushing ClayE
art
hw
ork
s
![Page 13: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/13.jpg)
Dozer Ripping GroundE
art
hw
ork
s
![Page 14: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/14.jpg)
Excavator with Hydraulic RockbreakerE
art
hw
ork
s
![Page 15: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/15.jpg)
Excavate & Load, Cart, Tip & Return
Brief Description
Cycle Time for 7km haulage distance using an Excavator 45 tonne weight and Dumper with a 40 tonne capacity, the cycle time is 34 minutes
Eart
hw
ork
s
7 minutes
14 minutes
3 minutes
14 minutes 7 km
7 km
![Page 16: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/16.jpg)
CABC ( Crushed aggregate base course )E
art
hw
ork
s
Mixing Plant
Testing Compaction
Site Trial
![Page 17: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/17.jpg)
Mixing CABCE
art
hw
ork
s
![Page 18: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/18.jpg)
Spreading & Compaction CABC ( Crushed aggregate base course )E
art
hw
ork
s
![Page 19: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/19.jpg)
Spreading & Compaction CABC ( Crushed aggregate base course ) E
art
hw
ork
s
![Page 20: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/20.jpg)
Spreading & Compaction CABC ( Crushed aggregate base course )E
art
hw
ork
s
![Page 21: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/21.jpg)
Rock - Excavability
The excavability of rock depends mainly on the rock strength and the layer thickness. This diagram shows excavation methods for rock of various strengths and thicknesses, with a free face.
ⓒ David H Moloney
![Page 22: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/22.jpg)
Contents
![Page 23: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/23.jpg)
Insitu Piling Construction - Plant & Methods
3D image to show Plant.
For construction details see my YouTube Channel
Plant & Equipment
Crawler CranePiling HammerCasing Piling RigConcrete PumpConcrete Mixer TrucksTremie PipeReinforcement Cage
![Page 24: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/24.jpg)
Piling Construction - Plant, Methods & SequenceP
iling
![Page 25: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/25.jpg)
Piling Construction - Plant & MethodsP
iling
![Page 26: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/26.jpg)
Pile Load Test
ⓒ David H Moloney
Pili
ng
![Page 27: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/27.jpg)
Sheet Pile Shaft Temporary to Support Excavation
Drive Sheet Piles Excavate & install bracing
Construct Concrete Structure Backfill, remove bracing & sheet piles
ⓒ David H Moloney
![Page 28: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/28.jpg)
Sheet pile Temporary Shaft
ⓒ David H Moloney
Genera
l Item
s
3D Animation to show Sequence
![Page 29: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/29.jpg)
Secant Pile Construction - Sequence, Plant & Methods
3D image to show Sequence, Method & Plant.
For construction details see my YouTube Channel
ⓒ David H Moloney
![Page 30: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/30.jpg)
Diaphragm Wall Construction - Sequence, Plant & Methods
3D image to show Sequence, Method & Plant.
For construction details see my YouTube Channel
ⓒ David H Moloney
![Page 31: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/31.jpg)
Contents
![Page 32: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/32.jpg)
Jetty for Oil Tankers
ⓒ David H Moloney
Marin
e
![Page 33: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/33.jpg)
Quay Wall
ⓒ David H Moloney
Marin
e
![Page 34: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/34.jpg)
Breakwater
ⓒ David H Moloney
Marin
e
![Page 35: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/35.jpg)
Dredging & Reclamation
ⓒ David H Moloney
Marin
e
![Page 36: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/36.jpg)
Contents
![Page 37: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/37.jpg)
Reinforced Wall Construction Sequence
3D image to show Sequence, Method & Plant.
ⓒ David H Moloney
![Page 38: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/38.jpg)
Reinforced Wall Construction Sequence
ⓒ David H Moloney
Concre
te
![Page 39: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/39.jpg)
Reinforced Structure Construction Sequence
ⓒ David H Moloney
Concre
te
![Page 40: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/40.jpg)
Reinforced Construction Tank Sequence David H Moloney
ⓒ David H Moloney
![Page 41: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/41.jpg)
Oil InterceptorM
iscella
ne
ous
Used to capture oil / fuel from leaks or spillages that are washed down drains every time it rains.
![Page 42: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/42.jpg)
Oil InterceptorC
oncre
te
![Page 43: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/43.jpg)
Excavation for Underground Pump stationE
art
hw
ork
s
Brief Description
Faces of excavation Stepped &
Well-point Dewatering used.
![Page 44: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/44.jpg)
Contents
![Page 45: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/45.jpg)
Main Equipment
Path of Construction 45
Slug CatcherGenerators – Gas Turbine Flares
Liquid Train Gas Train Compressors
![Page 46: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/46.jpg)
The Pipe Racks carries pipes and cables. The pipes contain gas and liquids that are transported to and from the different processes.
Pipe Rack
![Page 47: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/47.jpg)
Piperack Construction Animation
The Pipe Racks carry pipes and cables between the different processes..
![Page 48: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/48.jpg)
Pipe Rack
![Page 49: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/49.jpg)
Pipe Rack - Expansion Loop
49
![Page 50: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/50.jpg)
Gas Processing Facility
Hanging Scaffold
Stairway Tower
Pipe Rack – Scaffold Underslung
![Page 51: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/51.jpg)
Pipe Rack under construction
![Page 52: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/52.jpg)
The slug catcher buffers the incoming gas and liquid, from the wellheads, it also separates the gas from the liquid.
Slug Catcher
![Page 53: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/53.jpg)
Slug Catcher Construction Sequence Animation
Separates the Gas from the Oil & WaterAlso to dissipate any pressure surges
![Page 54: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/54.jpg)
Slug Catcher
![Page 55: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/55.jpg)
Storage of Oil & Water
Steel Circular Tanks Construction
![Page 56: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/56.jpg)
Steel Storage Tank
ⓒ David H Moloney
Str
uctu
ral S
teel
![Page 57: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/57.jpg)
Steel Circular Storage Tank – Construction ⓒ David H Moloney
![Page 58: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/58.jpg)
Contents
![Page 59: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/59.jpg)
Piping Spool Fabrication
Piping Spools are pre-fabricated from pipes and pipe fittings in fabrication shops to reduce on site fabrication costs and provide better quality.
![Page 60: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/60.jpg)
Spool Fabrication in Workshop P
ipew
ork
![Page 61: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/61.jpg)
Pipe Spools examples
![Page 62: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/62.jpg)
Spool Fabrication on site P
ipew
ork
![Page 63: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/63.jpg)
Post Weld Heat Treatment
Non Destructive Testing
Cut
Bevel
Fit-up
Weld
NDT
PWHT
Blasting
Painting
Spool Fabrication Steps
![Page 64: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/64.jpg)
Welding Trials
![Page 65: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/65.jpg)
Welding
Fit up Clamp
![Page 66: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/66.jpg)
Spool Fabrication - Pipe Rolling & Cutting Table P
ipew
ork
![Page 67: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/67.jpg)
Spool Fabrication Spool Rolling & Welding P
ipew
ork
W. Soule & Company USA
![Page 68: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/68.jpg)
Spool Fabrication - Automatic Welding with Pipe RollingP
ipew
ork
W. Soule & Company USA
![Page 69: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/69.jpg)
Welding Positioner / TurntableP
ipew
ork
Anyeke.com.my
![Page 70: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/70.jpg)
Contents
![Page 71: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/71.jpg)
Erect Flares / Columns & Vessels
![Page 72: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/72.jpg)
Cranes Heavy Lift Animation
Lift column from the horizontal and
rotate into the vertical
![Page 73: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/73.jpg)
Gas Processing Facility
Erect Flares / Columns & Vessels - 3D Simulation
![Page 74: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/74.jpg)
Flares / Columns / Vessels Erection
Path of Construction 74
Demag CC180-1 300 t crawler crane
72m boom & 42m luffing jib
Tandem Lift to tilt flare from horizontal to vertical
Trunnions
Main Lift Crane
Tail Crane
![Page 75: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/75.jpg)
Contents
![Page 76: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/76.jpg)
Electrical Sub Station 3D Model
3D Model – Used to provide a better understanding
![Page 77: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/77.jpg)
Main Substation Horizontal Cross section
Transformer Bays
HVAC RoomHeat, Ventilation, & Air Conditioning
Battery RoomUPS Room
Local Equipment Room
Chillers
![Page 78: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/78.jpg)
Electrical Sub Station
3D Model - Horizontal cross sections moving upwards
![Page 79: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/79.jpg)
Electrical Sub Station
3D Model - Vertical cross sections moving along building
![Page 80: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/80.jpg)
Structural Steel Building Single Storey
3D images to show Construction Sequence.
ⓒ David H Moloney
Step 1 Set-out Grid Lines Step 2 Holding Down Bolts Step 3 Erect 1st Bay
Step 4 Erect 2nd Bay Step 5 Erect following Bays
![Page 81: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/81.jpg)
Steel Building Single Storey
ⓒ David H Moloney
Str
uctu
ral S
teel
![Page 82: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/82.jpg)
Structural Steel Building Multi Storey
ⓒ David H Moloney
Step 1 Set-out Grid Lines Step 2 Holding Down Bolts Step 3 Erect 1st level use core for stability
Step 4 Complete 1st Level Step 5 Erect following Levels Step 6 Plumb & Align Structure
3D images to show Construction Sequence.
![Page 83: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/83.jpg)
Roof Covering
ⓒ David H Moloney
Str
uctu
ral S
teel
Brief Description
Sequence is
Fix bottom sheet
Fix Vapour barrier
Fix Top Hat section and clips
Fit Insulation
Fix top sheet
![Page 84: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/84.jpg)
Roof Covering
ⓒ David H Moloney
Str
uctu
ral S
teel
![Page 85: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/85.jpg)
Roof Covering
ⓒ David H Moloney
Str
uctu
ral S
teel
![Page 86: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/86.jpg)
Roof Covering
ⓒ David H Moloney
Str
uctu
ral S
teel
![Page 87: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/87.jpg)
Contents
![Page 88: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/88.jpg)
Onshore Gas Pipeline Construction Sequence
Gas Processing Facility
![Page 89: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/89.jpg)
Construction of Azerbaijan Oil Pipeline 42” by 450km. Overview Construction Sequence
A typical sequence of activities is- surveying and setting out, preparing the land, stringing out the pipes along the route, excavating the trench, welding and laying the pipes, backfilling the trench with the excavated soil, and reinstating the land to its original condition..
Crossing Railway, Roads, Rivers, etc.Pump Station
![Page 90: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/90.jpg)
Oil Pipeline 42”Contents
Overview Surveying & Setting OutClearing & GradingDouble Jointing i.e. welding 2 pipes togetherStringing out PipesBend Pipes for changes in direction sideways and up & downWelding Pipes into a string, Test Weld by X Ray.Anti-corrosion Coat to JointsTrenching i.e. excavate trenchLowering pipe string into trenchBackfilling TrenchReinstatement of Pipeline ROW (Right-of-Way)Reinstatement of River BanksCrossing - Horizontal Directional DrillingCrossing - Thrust BoringCrossing - River Hydrotest & PiggingTie-in i.e. connect to existing pipelineMiscellaneous
Pause Slides to Read
![Page 91: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/91.jpg)
Overview Pipeline Construction Animation
To see animations, view YouTube film.
![Page 92: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/92.jpg)
Cable laying 132KVa Electric
![Page 93: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/93.jpg)
Cable LayingP
ipew
ork
Brief Description
132 kVa Cable laying .
![Page 94: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/94.jpg)
Cable Laying P
ipew
ork
![Page 95: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/95.jpg)
Cable Laying P
ipew
ork
![Page 96: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/96.jpg)
Cable Laying P
ipew
ork
![Page 97: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/97.jpg)
Contents
![Page 98: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/98.jpg)
Horizontal Directional DrillingP
ipew
ork
Brief Description
Horizontal Directional Drilling under a taxiway.
Process
1. A pilot hole id drilled to the designed profile
2. A reamer is pulled back through the hole to enlarge it
3. A pipe string is pulled into the hole.
![Page 99: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/99.jpg)
Horizontal Directional DrillingP
ipew
ork
![Page 100: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/100.jpg)
Crossings – River, Motorway & RailP
ipew
ork
![Page 101: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/101.jpg)
Overview Pipeline Crossings Construction Animation
![Page 102: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/102.jpg)
Micro TunnellingT
unnels
![Page 103: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/103.jpg)
Micro Tunnelling Sequence David H Moloney
ⓒ David H Moloney
Tunnels
![Page 104: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/104.jpg)
Contents
![Page 105: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/105.jpg)
Includes Sequence, Methods & Equipment
Road Construction
![Page 106: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/106.jpg)
Road Construction Sequence Animation
![Page 107: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/107.jpg)
Asphalt Pavement
![Page 108: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/108.jpg)
Includes Sequence, Methods & Equipment
Fencing & Gates
![Page 109: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/109.jpg)
Fencing
ⓒ David H Moloney
Sequence of Construction
Clear Scrub & Grade ground
Fix Corner & Strainer Posts
Fix Intermediate Posts
Fix Line Wire, Chain-link & Razer wire
Concrete ground beam
![Page 110: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/110.jpg)
FencingM
iscella
ne
ous
![Page 111: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/111.jpg)
FencingM
iscella
ne
ous
![Page 112: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/112.jpg)
FencingM
iscella
ne
ous
![Page 113: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/113.jpg)
FencingM
iscella
ne
ous
![Page 114: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/114.jpg)
Contents
![Page 115: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/115.jpg)
Setting out & Surveying
![Page 116: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/116.jpg)
Setting out & Surveying
![Page 117: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/117.jpg)
Contents
![Page 118: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/118.jpg)
Emergency Phone Numbers & Response H
ealth,
Safe
ty &
Environm
ent
![Page 119: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/119.jpg)
HSE Monitoring & Reporting - Dashboard Dashboard is a single page, graphical representation of
current HSE Issues and historical trends
Health,
Safe
ty &
Environm
ent
![Page 120: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/120.jpg)
Safety PrecautionsH
ealth,
Safe
ty &
Environm
ent
![Page 121: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/121.jpg)
Safety DocumentsH
ealth,
Safe
ty &
Environm
ent
Safe System of Work.
To provide a safe system of work is a legal requirement. What this means is that before you ask an employee to do a
job. You ensure that he has received training, has the appropriate personal protective equipment, the work area is safe
and he is unlikely to be injured or cause damage by carrying out the assigned task.
Project Management Plan for Health, Safety, Security and Environment. also Known as (HSSE Plan)
The Project HSSE Management Plan details how safety on site will be managed.
Project Procedures for Health, Safety, Security & Environment
Details the safe way to undertake a task
Methods Statements
Are prepared in advance of starting work, to plan a Safe System of Work on site for all activities that carries a risk. The
contents of a Method Statement, typically include:- Scope & Location of the Works, Programme, Roles & Responsibilities
of Staff. Resources, Work Methodologies and Risk Assessment.
Slide 1 of 2
![Page 122: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/122.jpg)
Safety DocumentsH
ealth,
Safe
ty &
Environm
ent
Safety Risk Assessments
Are prepared to identify and evaluate risks, to adopt control measures to reduce or eliminate risks.
COSHH Sheet
The purpose of the Control Of Substances Hazardous to Health sheet is to identify how to prevent or adequately control
workers exposure to hazardous substances.
Permit to Work.
Is a management system used to control high risk activities by ensuring safety measures are in place prior to starting
work.
Types of work for which permits will be required include:
Excavation and the digging of trenches.
Working at height, including on roofs.
Working in confined spaces, for example entering a manhole.
Hot work, which is welding, soldering or cutting steel with angle grinders or by gas torch.
Slide 2 of 2
![Page 123: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/123.jpg)
Safety Training on Site M
iscella
ne
ous
The purpose of safety training is to provide the knowledge necessary to
perform a job safely
![Page 124: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/124.jpg)
Safety Training Matrix M
iscella
ne
ous
The purpose of safety training is to provide the knowledge necessary to
perform a job safely
![Page 125: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/125.jpg)
Emergency Response Drill H
SE
Drills and exercises are used to rehearse anticipated emergency scenarios
![Page 126: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/126.jpg)
Exposed Existing Underground Utilities
ⓒ David H Moloney
![Page 127: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/127.jpg)
Existing Underground Utilities & Overhead Cables - Safety Measures
ⓒ David H Moloney
Health,
Safe
ty &
Environm
ent
![Page 128: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/128.jpg)
Trench - Safety Measures H
ealth,
Safe
ty &
Environm
ent
![Page 129: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/129.jpg)
Trench - Safety Measures
ⓒ David H Moloney
Health,
Safe
ty &
Environm
ent
![Page 130: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/130.jpg)
Site Safety Posters examplesH
ealth,
Safe
ty &
Environm
ent
![Page 131: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/131.jpg)
Personal Protective Equipment (PPE)H
ealth,
Safe
ty &
Environm
ent
Personal protective equipment (PPE) is protective clothing, helmets, goggles, or other garments or equipment designed to protect the wearer from injury or infection
![Page 132: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/132.jpg)
Environmentally Friendly Site Air, Noise, Water & Soil PollutionH
ealth,
Safe
ty &
Environm
ent
![Page 133: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/133.jpg)
Water Pollution PreventionH
ealth,
Safe
ty &
Environm
ent
![Page 134: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/134.jpg)
Segregation of Waste H
ealth,
Safe
ty &
Environm
ent
Segregation of waste for proper disposal and recycling. Less waste goes to landfill and hazardous waste is treated to make it safe.
Colour Code for Skips & Bins
![Page 135: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/135.jpg)
Putting Waste Concrete to use
ⓒ David H Moloney
Health,
Safe
ty &
Environm
ent
Precast bases for signs and hoarding, Precast blocks for walls.
![Page 136: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/136.jpg)
Contents
![Page 137: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/137.jpg)
Staff Directory
Brief Description
List of staff and their
contact details
![Page 138: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/138.jpg)
Daily Work Record
Brief Description
Daily Work Records showing the
allocation of resources, materials and
work activities carried out daily.
![Page 139: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/139.jpg)
Organogram
Brief Description
Shown are the line and
lateral relationships
between the various team
members and their relative
position in the site
organisation.
![Page 140: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/140.jpg)
Filing System
![Page 141: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/141.jpg)
Quotations Comparison Sheet
![Page 142: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/142.jpg)
Staff Responsibility Matrix
![Page 143: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/143.jpg)
Contents
![Page 144: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/144.jpg)
Quality Assurance Dashboard Dashboard is a single page, graphical representation of
current statistics and historical trends
![Page 145: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/145.jpg)
Site LaboratoryG
enera
l item
s
![Page 146: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/146.jpg)
Contents
![Page 147: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/147.jpg)
Progress Monitoring & Reporting - Dashboard
ⓒ David H Moloney
Dashboard is a single page, graphical representation of current progress and historical trends
![Page 148: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/148.jpg)
Programme for Construction
Gantt Charts to plan and schedule projects
![Page 149: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/149.jpg)
Primary Substation-
Chiller Plant
Pump House
IRRIGATION WATER TANKS
Irrigation Pump House-
POTABLE/FIRE WATER TANK
Programme using Timeline & 3D Images
Airport Central Utility Yard
![Page 150: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/150.jpg)
Pump House
Piling
![Page 151: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/151.jpg)
Primary Substation-711
Chiller Plant-714Pump House-715
Irrigation Pump House-716
![Page 152: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/152.jpg)
Primary Substation-711
Chiller Plant-714Pump House-715
IRRIGATION WATER TANK
Irrigation Pump House-716
![Page 153: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/153.jpg)
Primary Substation-711
Chiller Plant-714Pump House-715
IRRIGATION WATER TANK
Irrigation Pump House-716
![Page 154: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/154.jpg)
Primary Substation-711
Chiller Plant-714Pump House-715
IRRIGATION WATER TANK
Irrigation Pump House-716
![Page 155: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/155.jpg)
Primary Substation-711
Chiller Plant-714Pump House-715
IRRIGATION WATER TANK
Irrigation Pump House-716
POTABLE/FIRE WATER TANK
![Page 156: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/156.jpg)
Time Chainage Diagram The chart has two axis: one for time and the other for location
A legend explains meaning of the colours, symbols and line types
Sample Only
![Page 157: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/157.jpg)
Histogram Charts for Resources & Outputs
Concrete, Manpower, TBM,
Manpower per Discipline Concrete per Location
Numbers for each month of the Project Quantity for each month of the Project
ⓒ David H Moloney
![Page 158: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/158.jpg)
Plant & Equipment List & Worker’s Job Titles
ⓒ David H Moloney
![Page 159: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/159.jpg)
Contents
![Page 160: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/160.jpg)
Temporary Contractors Site Facilities
ⓒ David H Moloney
Brief Description
Site Offices, Camp Accommodation for 1,250 workers, Canteen, Recreation, Fabrication shops, Stores, Plant Yard. In five locations along the route.
![Page 161: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/161.jpg)
Welfare Facilities
ⓒ David H Moloney
Genera
l Item
s
Toilets – Washing
Canteen, Drying Room, Toilet & Generator
![Page 162: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/162.jpg)
Site Hoarding examples
ⓒ David H Moloney
Genera
l Item
s
![Page 163: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/163.jpg)
Temporary Electricity Supply & Tower Lights
ⓒ David H Moloney
Genera
l Item
s
![Page 164: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/164.jpg)
Wheel Wash Drive-through
ⓒ David H Moloney
Genera
l Item
s
Used to wash the wheels of trucks prior to leaving site.
![Page 165: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/165.jpg)
Wheel Wash Drive-throughG
enera
l Item
s
![Page 166: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/166.jpg)
Weighbridge & Sheeting Access
ⓒ David H Moloney
Genera
l Item
s
Access tower for covering tipper truck bodies to prevent air pollution.
![Page 167: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/167.jpg)
Dust Suppression
ⓒ David H Moloney
Genera
l Item
s
Wetting the ground to prevent dust blowing in the wind
![Page 168: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/168.jpg)
Dewatering
ⓒ David H Moloney
Genera
l Item
s
Brief Description
Construction dewatering is the removal or
drainage of groundwater and or surface /
rain water usually by pumping to keep the
works dry.
![Page 169: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/169.jpg)
Dewatering
ⓒ David H Moloney
Genera
l Item
s
![Page 170: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/170.jpg)
Quarry & Aggregate Production
3D image to show Sequence, Method & Plant. ⓒ David H Moloney
Rock is blasted free from a quarry face and fragmented. The blasted rock is crushed and screened to produce different size ranges of aggregates
![Page 171: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/171.jpg)
Quarry & Aggregate ProductionG
enera
l Item
s
![Page 172: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/172.jpg)
Concrete Batching Plant David H Moloney
ⓒ David H Moloney
Concrete batching plant comprises - concrete mixer, control cabin, silos for cement and fly ash, aggregate bins and conveyor belt system to feed the mixer. Also aggregate storage bays and water storage tanks. The mixing is computer controlled and has a dynamic screen display, showing the process. Material storage capacity to match two days concrete production
![Page 173: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/173.jpg)
Concrete Batching Plant
ⓒ David H Moloney
Concre
te
![Page 174: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/174.jpg)
Concrete Batching Yard 3 Nr MixersG
enera
l Item
s
![Page 175: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/175.jpg)
Concrete MixG
enera
l Item
s
A concrete mix contains 5 major
elements: cement, water, coarse
aggregates, fine aggregates (sand) and
air in different proportion. Additional
elements such as pozzolanic materials (fly
ash, silica fumes or slag) and chemical
admixtures can also be incorporated to
the mix to increase its properties.
![Page 176: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/176.jpg)
Reinforcement Cutting & Bending Yard David H Moloney
ⓒ David H Moloney
Reinforcement in 12 m lengths. Delivery in 3 ton Bundles Reinforcement cut to length by Shearing Machine
Reinforcement Bent to Shape by Bending Machine Reinforcement that is cut and bent is Bundled for delivery to work site
![Page 177: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/177.jpg)
Reinforcement Cutting & Bending
ⓒ David H Moloney
Concre
te
![Page 178: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/178.jpg)
Contents
![Page 179: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/179.jpg)
Notes
![Page 180: Oil & Gas Plant Construction, Project Execution Plan](https://reader034.fdocuments.net/reader034/viewer/2022042421/58f9ad72760da3da068b984a/html5/thumbnails/180.jpg)
Production by David H Moloney
My YouTube Channel link: https://www.youtube.com/channel/UCeJR9J7svhBd-C0ZoAH2fhQ
ⓒ David H Moloney