OIL D-1.pptx E&P industry

download OIL D-1.pptx E&P industry

of 367

Transcript of OIL D-1.pptx E&P industry

  • 7/27/2019 OIL D-1.pptx E&P industry

    1/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    2/367

    PRODUCED WELL FLUID IS A MIXTURE OF

    OIL,GAS,WATER,SOLIDS etc.

    BUYERS HAVE CERTAIN REQUIREMENTS WHICH ARE

    TERMED AS SPECIFICATIONS FIELD PROCESSING ACHIEVES THIS BY PROCESSING

    THE WELL FLUID

  • 7/27/2019 OIL D-1.pptx E&P industry

    3/367

    WELLS

    WELL FLOW LINES

    RECEIVING MANIFOLD

    SEPARATION FACILITY

    STORAGE

    TRANSPORTATION

  • 7/27/2019 OIL D-1.pptx E&P industry

    4/367

    WELLS ARE CONNECTED TO A RECEIVING

    MANIFOLD BY FLOW LINES

    RECEIVING MANIFOLD HAS PROVISION TO DIVERT

    WELLS TO NECESSARY PROCESSING SYSTEM RECEIVING MANIFOLD CAN BE DESIGNED TO

    SPECIFIC REQUIREMENT DEPENDING UPON TYPE

    OF WELL FLUID

  • 7/27/2019 OIL D-1.pptx E&P industry

    5/367

    PROCESSING FACILITY COMPRISES OF:

    separation facility to separate oil, gas and water

    treatment of produced water, solids(if any) for their

    disposal

    auxiliaries like power generation, compressors,

    pumps, instrumentation, safety systems, fire

    fighting system

  • 7/27/2019 OIL D-1.pptx E&P industry

    6/367

    emergency systems means of evacuation etc.

    requirement will differ for onshore and offshore

    operation but basic processing system is same

    capital intensive

    can be custom made

  • 7/27/2019 OIL D-1.pptx E&P industry

    7/367

    SEPARATION SYSTEM OIL

    separators

    a. two phase

    b. three phase

    c. horizontal

    d. vertical

    e. spherical

  • 7/27/2019 OIL D-1.pptx E&P industry

    8/367

    separation can be single stage or multistage

    depending upon crude type and pressure

    separator is a pressure vessel which is designed to

    separate oil water and gas by gravity separation

    separator sizing is done based on crude quality

    separator type is decided by crude properties

  • 7/27/2019 OIL D-1.pptx E&P industry

    9/367

    separators are fitted with different internals tofacilitate separation

    provided with different instruments for pressure

    and level controldown stream may have a meter for measurement of

    quantity and taken to storage tank or separated oil

    may be taken for further treatment

  • 7/27/2019 OIL D-1.pptx E&P industry

    10/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    11/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    12/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    13/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    14/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    15/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    16/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    17/367

    VESSEL INTERNALS

    Inlet Diverters: Two main types: baffle plates and

    centrifugal diverters, baffle plate can be a spherical

    dish, flat plate, angle iron, cone, or anything that willaccomplish a rapid change in direction and velocity of

    the fluids and disengage the gas and liquid, design of

    the baffles is governed by the structural supports

    required to resist the impact-momentum load,advantage of using a half sphere or cone is , they create

    less disturbance than plates or angle iron, cutting down

    on re-entrainment or emulsifying problems.

  • 7/27/2019 OIL D-1.pptx E&P industry

    18/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    19/367

    Centrifugal inlet diverters use centrifugal force,rather than mechanical agitation, to disengage the

    oil and gas, have a cyclonic chimney or may use a

    tangential fluid race around the walls, these inletdiverters are proprietary but generally use an inlet

    nozzle sufficient to create a fluid velocity of about

    20 fps centrifugal diverters work well in initial gas

    separation and help to prevent foaming in crudes

  • 7/27/2019 OIL D-1.pptx E&P industry

    20/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    21/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    22/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    23/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    24/367

    Wave Breakers In long horizontal vessels it isnecessary to install wave breakers, which are

    nothing more than vertical baffles spanning the

    gas-liquid interface and perpendicular to the flow.Defoaming Plates Foam at the interface may occur

    when gas bubbles are liberated from the liquid.

    This foam can be stabilized with the addition of

    chemicals at the inlet. Many times a more effectivesolution is to force the foam to pass through a

    series of inclined parallel plates or tubes

  • 7/27/2019 OIL D-1.pptx E&P industry

    25/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    26/367

    Mist Extractor Liquid carryover occurs when freeliquid escapes with the gas phase, mist extractors

    are made of wire mesh, vanes, centrifugal force

    devices, or packing. wire mesh pads are made offinely woven mats of stainless steel wire wrapped

    into a tightly packed cylinder, liquid droplets

    impinge on the matted wires and coalesce,

  • 7/27/2019 OIL D-1.pptx E&P industry

    27/367

    effectiveness of wire mesh depends largely on the

    gas being in the proper velocity range, if the

    velocities are too high, the liquids knocked out will

    be re-entrained , if the velocities are low, the vaporjust drifts through the mesh element without the

    droplets impinging and coalescing

  • 7/27/2019 OIL D-1.pptx E&P industry

    28/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    29/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    30/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    31/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    32/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    33/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    34/367

    DRAG FORCE

    IF FLOW IS LAMINAR THEN

  • 7/27/2019 OIL D-1.pptx E&P industry

    35/367

    FOR TERBULENT FLOW

  • 7/27/2019 OIL D-1.pptx E&P industry

    36/367

    GAS CAPACITY

    HORIZONTAL SEPARATOTOR -SIZING

  • 7/27/2019 OIL D-1.pptx E&P industry

    37/367

    LIQUID CAPACITY

    SLENDERNESS RATIO

    SEAM TO SEAM LENGTH

    VERTICAL SEPARATOTOR SIZING

  • 7/27/2019 OIL D-1.pptx E&P industry

    38/367

    VERTICAL SEPARATOTOR -SIZING

    GAS CAPACITY

    GAS CAPACITY

  • 7/27/2019 OIL D-1.pptx E&P industry

    39/367

    SLENDERNESS RATIO

    SEAM TO SEAM LENGTH

  • 7/27/2019 OIL D-1.pptx E&P industry

    40/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    41/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    42/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    43/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    44/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    45/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    46/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    47/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    48/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    49/367

    SINGLE PHASE FLOW

    LIQUID

    GAS

    MULTIPHASE FLOW

    WELL FLOW LINES

    PROCESS LINES

  • 7/27/2019 OIL D-1.pptx E&P industry

    50/367

    MULTIPHASE FLOW

    BUBBLE

    PLUG

    STRATIFIED

    WAVY

    SLUG

    SPRAY

  • 7/27/2019 OIL D-1.pptx E&P industry

    51/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    52/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    53/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    54/367

    Pressure Drop for Liquid Flow.General Equation.

    d5 = (11.5 10-6) fLQl2 (SG)

    P

    where d= pipe inside diameter, in.,

    f= Moody friction factor, dimensionless,

    L = length of pipe, ft, Ql= liquid flow rate, B/D,

    SG = specific gravity of liquid relative to water,P = pressure drop, psi (total pressure drop).

  • 7/27/2019 OIL D-1.pptx E&P industry

    55/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    56/367

    Weymouth Equation: used for high-Reynolds-number flows

    Qg = 1.1d2.67 [P21 P2

    1 ]1/2

    [LSZT1 ]1/2

    where :Qg = gas-flow rate, MMscf/D, d = pipe insidediameter, in.,P1 = upstream pressure, psia, P2 =downstream pressure, psia,L = length, ft,

    T1 = temperature of gas at inlet, R S = specificgravity of gas, And Z = compressibility factor for gas,dimensionless.

  • 7/27/2019 OIL D-1.pptx E&P industry

    57/367

    Panhandle Equation.: used for moderate-Reynolds-number.

    Qg = 0.028E [ P21 P2

    2 2 ]0.51 d2.53

    [ S0.961ZTLm

    ] 0.51

    Where:E-efficiency factor (new pipe: 1.0; goodoperating conditions: 0.95; average operatingconditions: 0.85),Qg-gas-flow rate, MMscf/D, d-

    pipe ID, in., P1-pressure, psia, P2-downstreampressure, psia, Lm-length, miles, T- temperature ofgas at inlet,R, S-specific gravity of gas, Z-compressibility factor for gas, dimensionless

  • 7/27/2019 OIL D-1.pptx E&P industry

    58/367

    Spitzglass Equation. For vent lines

    Qg = 0.09[ hwd5]1/2

    [ SL(1 + 3.6/d + 0.03d)]1/2

    Where:Qg-gas-flow rate,MMscf/D,

    hW- pressure loss,inches of water, d-pipe ID, in.

    Assumptions: f-(1+ 3.6/d + 0.03d) (1/100),

    T-520R, P1-15 psia, Z = 1.0,P- 10% of P1

  • 7/27/2019 OIL D-1.pptx E&P industry

    59/367

    Simplified Gas Formula: recommended for most general-use flow applications.

    Weymouth Eqn.: for smaller-dia.pipe (generally, 12 in. and

    less), also recommended for shorter lengths of segments

    (

    1,000 psig) applications,and high Reynolds number.

    Panhandle Eqn.:for larger-dia.pipe (12-in.+diameter),also

    recommended for long runs of pipe (> 20 miles)like crosscountry transmission pipelines and for moderate Reynolds

    numbers.

    Spitzglass Eqn:for low-pressure vent lines< 12 in.in

    dia.(P

  • 7/27/2019 OIL D-1.pptx E&P industry

    60/367

    Simplified Friction Pressure-Drop providesanapproximate solution for friction pressure drop in two-phase-flow problems that meet the assumptionsstated.

    P =3.4 10-6 f LW 2M

    d5

    Where P = friction pressure drop, psi,

    f = Moody friction factor, dimensionless,

    L = length, ft, W = rate of flow of mixture, lbm/hr,

    M -density of the mixture, lbm/ft3, and d = pipe ID, in.

    API RP14E

  • 7/27/2019 OIL D-1.pptx E&P industry

    61/367

    The formula for rate of mixture flow is

    W = 3,180QgS + 14.6QL(SG)

    where

    Qg = gas-flow rate, MMscf/D,

    QL = liquid flow rate, B/D,

    S = specific gravity of gas at standard conditions,

    lbm/ft3

    (air = 1),And SG = specific gravity of liquid, relative to water,

    lbm/ft3.

  • 7/27/2019 OIL D-1.pptx E&P industry

    62/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    63/367

    The pressure drop at low flow rates associated with anuphill elevation change may be approximated with

    Equation

    PZ

    0.433(SG)Z ,

    Where PZ = pressure drop because of elevation

    increase in the segment, psi,

    SG = specific gravity of the liquid in the segment, relative

    to water, and Z = increase in elevation for segment, ft.The total pressure drop can then be approximated by

    the sum of the pressure drops for each uphill segment.

  • 7/27/2019 OIL D-1.pptx E&P industry

    64/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    65/367

    Once a design velocity is chosen, to determine the pipesize,

    d = [ (11.9 + ZT R/ 16.7P )QL]1/2

    [1,000V] 1/2Where d = pipe ID, in.,

    Z = compressibility factor, dimensionless,

    R = gas/liquid ratio, ft3/bbl,

    P = flowing pressure, psia,

    T = gas/liquid flowing temperature, R,

    V = maximum allowable velocity, ft/sec,

    And QL = liquid-flow rate, B/D.

  • 7/27/2019 OIL D-1.pptx E&P industry

    66/367

    FOR EROSIVE SERVICE FITTINGS

  • 7/27/2019 OIL D-1.pptx E&P industry

    67/367

    Multiphase-Line Sizing: minimum fluid velocity inmultiphase systems must berelatively high to keep theliquids moving and prevent or minimize slugging,recommended minimum velocity is 10 to 15 ft/sec,maximum recommended velocity is 60 ft/sec to inhibit

    noise and 50 ft/sec for CO2 corrosion inhibition. In two-phase flow, it is possible that liquid droplets in the flowstream will impact on the wall of the pipe causingerosion of the products of corrosion. This is callederosion/corrosion. Erosion of the pipe wall itself could

    occur if solid particles, particularly sand, are entrainedin the flow stream, guidelines from API RP14Eshould beused to protect against erosion/corrosion.

  • 7/27/2019 OIL D-1.pptx E&P industry

    68/367

    Wall-Thickness Calculations: B31.3 Code. ANSI/ASMEStandard B31.3 is avery stringent code with a high safetymargin. The B31.3 wall-thickness calculation formula is

    t = te + tth + [ Pdo ] [ 100 ]

    *2(SE PY) + *100 Tol]

    where t-minimum design wall thickness, in.,te-corrosionallowance, in.,tth-thread or groove depth, in. P-allowableinternal pressure in pipe, psi, do-outside diameter of pipe,in., S-allowable stress for pipe, psi E = longitudinal weld-jointfactor [1.0 seamless, 0.95 electric fusion weld, double butt,

    straight or spiral seam APL 5L, 0.85 electric resistance weld(ERW), 0.60 furnace butt weld],Y-derating factor (0.4 forferrous materials operating below 900F), andTol-manufacturers allowable tolerance, % (12.5 pipe up to 20in.-OD, 10 pipe > 20 in. OD, API 5L).

  • 7/27/2019 OIL D-1.pptx E&P industry

    69/367

    B31.4 Code. is used often as the standard of design forcrude-oil piping systems in facilities, such as pump stations,pigging facilities, measurement and regulation stations, andtank farms. The wall-thickness formula for Standard B31.4 is

    t = Pdo

    2(F ESY ),

    Where t = minimum design wall thickness, in., P = internalpressure in pipe, psi, do = OD of pipe, in.,SY = minimum yieldstress for pipe, psi, F = derating factor, 0.72 for all locations,

    and E = longitudinal weld-joint factor [1.0 seamless, ERW,double submerged arc weld and flash weld; 0.80 electricfusion (arc) weld and electric fusion weld, 0.60 furnace buttweld].

  • 7/27/2019 OIL D-1.pptx E&P industry

    70/367

    B31.8 Code. is often used as the standard of design fornatural-gas piping systems in facilities, such ascompressor stations, gas-treatment facilities,measurement and regulation stations, and tank farms.The B31.8 wall-thickness formula is

    t = Pdo2F ETSY

    Where t-minimum design wall thickness, in., P-internalpressure in pipe, psi, dO - OD of pipe, in.,

    SY - minimum yield stress for pipe, psi F-design factorE- longitudinal weld-joint factor and T-temperaturederating factor

  • 7/27/2019 OIL D-1.pptx E&P industry

    71/367

    DIFFERENT TYPE OF PIGS(for cleaning)

    foam

    rubber cups

    brush pigs etc.

    PIGGING OPERATION REQUIRES PIG LAUNCHERS

    AND RECEIVERS.

    SLUG CATHCERS ARE REQUIRED AT THE RECEIVINGEND OF THE PIG.

    INTELLEGENT PIGS (for health monitoring)

  • 7/27/2019 OIL D-1.pptx E&P industry

    72/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    73/367

    ROUTE:

    a)selection

    b) route survey

    c) right of way or use

    SPECIAL REQUIREMENTS:

    a) area

    b) highway , road , street crossingc) railway crossing

  • 7/27/2019 OIL D-1.pptx E&P industry

    74/367

    d) bridge crossing

    e) river, water streams

    f) wet lands and marshes etc

    ENVIRONMENTAL CONCERNS

    SAFTY CONCERNS

  • 7/27/2019 OIL D-1.pptx E&P industry

    75/367

    PIPE LINE CONSTRUCTION:

    PIPE LINE STORAGE AND TRANSPORTATION

    SITE PREPRATION

    LINE STRINGING

    TRENCHING

    WELDING(API 1104,ASME SECTION IX Boiler andpressure vessel code)

  • 7/27/2019 OIL D-1.pptx E&P industry

    76/367

    WELD TESTING

    JOINT AND PIPE LINE COATING

    PIPE LINE LOWERING

    BACKFILLING

    VARIOUS CROSSINGS

    FINAL TIE INS

    TESTING

  • 7/27/2019 OIL D-1.pptx E&P industry

    77/367

    WELDED PIPES ARE LOWERED FROM THE REAR OFTHE BARGE.

    IN SHALLOW WATERS PIPE IS S LAYED AND IN

    DEEPER WATERS IT IS J LAYED. IN S LAY PIPE IS WELDED IN HORIZONTAL POSITION

    AND LEAVES THE BARGS HORIZONTALLY.

    IN J LAY PIPE IS WELDED VERICALLY HELD AND PIPE

    LEAVES THE BARGE VERTICALLY

  • 7/27/2019 OIL D-1.pptx E&P industry

    78/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    79/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    80/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    81/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    82/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    83/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    84/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    85/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    86/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    87/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    88/367

    2PE607:Oil&GasPipelineDesign,Maintenance&Repair

    PIGGINGOPERATIONS

  • 7/27/2019 OIL D-1.pptx E&P industry

    89/367

    11PE607:Oil&GasPipelineDesign,Maintenance&Repair

    UTILITYPIGS

    FoampigsMandrelpigs

  • 7/27/2019 OIL D-1.pptx E&P industry

    90/367

    12PE607:Oil&GasPipelineDesign,Maintenance&Repair

    UTILITYPIGS

    Solidcastpigs Sphericalpigsorspheres

    IN LINE INSPECTION TOOLS

  • 7/27/2019 OIL D-1.pptx E&P industry

    91/367

    14PE607:Oil&GasPipelineDesign,Maintenance&Repair

    INLINEINSPECTIONTOOLS

  • 7/27/2019 OIL D-1.pptx E&P industry

    92/367

    16PE607:Oil&GasPipelineDesign,Maintenance&Repair

    ULTRASONICINSPECTIONTOOLS

  • 7/27/2019 OIL D-1.pptx E&P industry

    93/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    94/367

    LIQUID PROCESSING

  • 7/27/2019 OIL D-1.pptx E&P industry

    95/367

    an emulsion is a heterogeneous liquid that consistsof two immiscible liquids, one of which is intimately

    dispersed as droplets in the other, for an emulsion

    to exist, oil and water are the two mutually

    immiscible liquids, emulsifying agent in the form of

    small solid particles, paraffins, asphaltenes, etc., is

    present in the formation fluids, agitation occurs as

    fluid flows into the well bore, up the tubing, andthrough the surface choke.

  • 7/27/2019 OIL D-1.pptx E&P industry

    96/367

    TYPES:

    WATER IN OIL

    OIL IN WATER

    WATER IN OIL IN WATER

  • 7/27/2019 OIL D-1.pptx E&P industry

    97/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    98/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    99/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    100/367

    Prevention of Emulsions: Excluding all water fromthe oil while the oil is produced and/or preventingall agitation of well fluids would prevent emulsionfrom forming; however, because these both are

    impossible, or nearly so, emulsion production mustbe expected from wells, poor operating practicesincrease emulsification , operating practices thatinvolve the production of excess water because of

    poor cementing or reservoir management canincrease emulsion-treating problems, as can aprocess design that subjects the oil/water mixtureto excess turbulence

  • 7/27/2019 OIL D-1.pptx E&P industry

    101/367

    Emulsifying Agents: surface-active compounds thatattach to the water-droplet surface and lower theoil/water interfacial tension, some emulsifiers areasphaltic , barely soluble in oil and strongly

    attracted to water, they come out of solution andattach themselves to the droplets of water as thesedroplets are dispersed in the oil, asphalticemulsifiers form thick films around the water

    droplets and prevent droplet surfaces fromcontacting when they collide, thus preventingcoalescence.

  • 7/27/2019 OIL D-1.pptx E&P industry

    102/367

    Oil-wet solids (sand, silt, shale particles, paraffin,iron hydroxides, zinc compounds, aluminum sulfate,

    calcium carbonate, iron sulfide ,etc. collect at the

    oil/water interface) can act as emulsifiers, these

    substances usually originate in the oil formation,

    but can form because of an ineffective corrosion-

    inhibition program,

  • 7/27/2019 OIL D-1.pptx E&P industry

    103/367

    most crude-oil emulsions are dynamic and transitory,interfacial energy per unit of area is fairly high in

    petroleum emulsions compared to that in

    emulsions commonly encountered in other

    industries, so they are thermodynamically unstable

    in that the total free energy will decrease if the

    dispersed water coalesces and separates

  • 7/27/2019 OIL D-1.pptx E&P industry

    104/367

    Stability of Emulsions. Generally, crude oils with lowAPI gravity form more stable and higher-percentage-volume emulsions than do oils of highAPI gravity, asphaltic-based oils tend to emulsify

    more readily than do paraffin-based oils, emulsionsof high-viscosity crude oil usually are very stableand difficult to treat because the viscosity of the oilhinders movement of the dispersed water droplets

    and thus retards their coalescence, high-viscosity/high-density oils usually contain moreemulsifiers than do lighter oils.

  • 7/27/2019 OIL D-1.pptx E&P industry

    105/367

    Effect of Emulsions on Fluid Viscosity.: Emulsionsalways are more viscous than the clean oil in the

    emulsion, in oilfield emulsions, the ratio of the

    viscosity of an emulsion to that of the clean crude

    oil depends on the shear rate to which the

    emulsion has been subjected, for many emulsions

    and for the shear rates normally encountered in

    piping systems,

  • 7/27/2019 OIL D-1.pptx E&P industry

    106/367

    this ratio can be approximated using equation , if noother data are available.

    e

    / o

    = 1 + 2.5 f + 14.1 f2

    where e = viscosity of emulsion, cp; o = viscosityof clean oil, cp; and f = fraction of thedispersed

    phase.

  • 7/27/2019 OIL D-1.pptx E&P industry

    107/367

    Sampling and Analyzing : treating unit or systemperformance can be monitored by regularlywithdrawing and analyzing samples of the contents atmultiple levels in the vessel or multiple points in thesystem, particularly beneficial when treating emulsionsthat involve viscous oils, samples should berepresentative of the liquid from which they are taken,so emulsification should not be allowed to occur whenthe sample is extracted ,samples from a pressure zone

    can be taken without further emulsification of theliquids if the velocity of the discharging liquid iscontrolled

  • 7/27/2019 OIL D-1.pptx E&P industry

    108/367

    Bottle Tests Most Common Method

    Measure Sedimentation Rate

    Estimate Resultant Oil Quality

    Vary Chemical Type and Dosage

  • 7/27/2019 OIL D-1.pptx E&P industry

    109/367

    Electrostatic Bench Tests

    Measure Response of Emulsion to

    Electrostatic Field: Power Requirements

    & Sedimentation Rate

    Measure Resultant Oil Quality

    Vary Chemical Type & Dosage and

    Electrostatic Field Type

  • 7/27/2019 OIL D-1.pptx E&P industry

    110/367

    cc Oil

    cc Emulsion

    cc Water

    Chemical

    Dossage

    Mixing

    Heating to

    process

    temperature

    24 hours

    settling

    evaluation

    t = 0t = t

    1

    BOTTLE TEST

    100 cc

    Emulsion

  • 7/27/2019 OIL D-1.pptx E&P industry

    111/367

    Chemical Bottle Test Electrostatic Bench

    Test

    Water in Oil

    % By Difference

    BS&W

    Measured %

    A 2.2 2.12

    B 4.6 2.01

    C 5.3 1.62

    D 5.7 1.20

    E 6 2.35

    Red: Best Performance

  • 7/27/2019 OIL D-1.pptx E&P industry

    112/367

    EMULSION STABILITY

    HOW TO DESTABLIZE

    METHODS TO DESTABLIZE:

    1. HEATING2. CHEMICAL ADDITION

    3. SETTLING OF SEPARATED WATER

    a) NATURAL SETTLINGb) FORCED SETTLING

  • 7/27/2019 OIL D-1.pptx E&P industry

    113/367

    WHY HEATING: Using heat to treat crude-oilemulsions has four basic benefits:

    Heat reduces the viscosity of the oil, which allows

    the water droplets to collide with greater force and

    to settle more rapidly The chart can be used to

    estimate crude-oil viscosity/temperature

    relationships.

  • 7/27/2019 OIL D-1.pptx E&P industry

    114/367

    Crude-oil viscosities vary widely, and the curves onthis chart should be used only in the absence of

    specific data. Heat increases the droplets

    molecular movement, which helps coalescence by

    causing the dispersed-phase droplets to collide

    more frequently

  • 7/27/2019 OIL D-1.pptx E&P industry

    115/367

    Heat might deactivate the emulsifier (e.g., dissolveparaffin crystals), or might enhance the action of

    treating chemicals, causing the chemical to work

    faster and more thoroughly to break the film

    around the droplets of the dispersed phase of the

    emulsion. Heat also might increase the density

    difference between the oil and the water, thus

    accelerating settling. In general, at temperatures

    below 180F, adding heat will increase the density

    difference.

  • 7/27/2019 OIL D-1.pptx E&P industry

    116/367

    Heating well fluids is expensive. Adding heat cancause a significant loss of the lower-boiling point

    hydrocarbons (light ends). This causes shrinkage

    of the oil, or loss of volume. Because the light ends

    are boiled off, the remaining liquid has a lower API

    gravity and thus might have less value. The vapor

    leaving the oil phase can be vented to a vapor

    recovery system or compressed and sold with thegas. Either way, there probably will be a net income

    loss

  • 7/27/2019 OIL D-1.pptx E&P industry

    117/367

    Fuel is required to provide heat, and so the cost offuel must be considered. If the oil is above inlet-

    fluid temperature when it is discharged from the

    treating unit, it can be flowed through a heat

    exchanger with the incoming well fluid to transfer

    the heat to the cooler incoming well fluid. In some

    geographic areas, emulsion-heating requirements

    vary in accordance with daily and/ or seasonal

    atmospheric temperatures e.g., at night, during a

    rain, or in winter months

  • 7/27/2019 OIL D-1.pptx E&P industry

    118/367

    BENEFITS OF HEATING

  • 7/27/2019 OIL D-1.pptx E&P industry

    119/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    120/367

    the fuel required for treating depends on thetemperature rise, the amount of water in the oil,

    and the flow rate, heating a given volume of water

    requires approximately twice the energy needed to

    heat the same volume of oil, beneficial to separate

    free water from the emulsion to be treated,

  • 7/27/2019 OIL D-1.pptx E&P industry

    121/367

    the heat input for an insulated vessel (heat loss isassumed to be 10% of heat input) can be

    approximated

    Q = 16T(0.5qo

    o

    + qw

    w

    )

    where Q = heat input, Btu/hr, T = temperature

    increase, F, qo = oil flow rate, B/D, qw = water flow

    rate, B/D, o = specific gravity of oil, and w =

    specific gravity of water.

  • 7/27/2019 OIL D-1.pptx E&P industry

    122/367

    DISADVANTAGES:EXPENSIVE

    GAS EVOLUTION

    LOSS OF LIGHTER FRACTIONREDUCES API GRAVITY

    SOME TIME DECREASES GRAVITY DIFFERENCE IN

    PHASES

  • 7/27/2019 OIL D-1.pptx E&P industry

    123/367

    TYPES:Water soluble

    Oil soluble

    ACTION INJECTION

    Injection point

    Dilution CHEMICAL SELECTION

  • 7/27/2019 OIL D-1.pptx E&P industry

    124/367

    NATURAL AIDED

  • 7/27/2019 OIL D-1.pptx E&P industry

    125/367

    NATURAL SETTLING: COALSCING SYSTEM

    Plates

    Packing AGITATION

    SETTLING TIME

    AIDED SETTLINGElectrostatic coalescence

  • 7/27/2019 OIL D-1.pptx E&P industry

    126/367

    Gravity Settling. Gravity settling is the oldest,simplest, and most widely used method for treatingcrude-oil emulsions, density difference betweenthe oil and the water causes the water to settle

    through and out of the oil by gravity, gravitationalseparation of water from oil is controlled by thewell known Stokes law

    V =2gr2(D2- D1 ) /9 V-droplet falling velocity

    g-gravitation constant r-particle radiusD2-specificgravityof water D1-specific gravity of oil

    -viscosity of oil

  • 7/27/2019 OIL D-1.pptx E&P industry

    127/367

    parameters which control the falling velocity ofwater particle are the droplet size, densitydifference and viscosity of oil. Application of heatwill reduce the oil gravity as well as viscosity

    Rewriting Stokes equation in more easily usableform

    V= Cr2(D2 D1)/ value of C is 2.5665 x 10-2 when

    r-particle size in microns

    D2-specificgravityof water at conditions

    D1-specificgravityof oil at condition -viscosity of oilat conditions in centipoises.

  • 7/27/2019 OIL D-1.pptx E&P industry

    128/367

    Emulsion subjected to high voltage electrical fieldhigh voltage, water droplets polarize and align with

    electric force, the positive and negative poles of the

    droplets are brought adjacent to each other,

    electrical attraction brings the droplets togetherand causes them to coalesce.

  • 7/27/2019 OIL D-1.pptx E&P industry

    129/367

    droplets dispersed in oil that are subjected toalternating-current (AC) field become elongated

    along the lines of force, as voltage rises during the

    first half-cycle,droplets are relaxed during the low-

    voltage part of the cycle, the surface tension pullsthem back toward a spherical shape, effect repeats

    with each cycle, weakening the film so that it

    breaks more easily

  • 7/27/2019 OIL D-1.pptx E&P industry

    130/367

    force existing between droplets is mathematicallygiven by the following equation:

    F= K2d6/S4 (with Sd) F-attractive force betweendroplet K-Dielectric constant for the system -

    voltage gradient d-diameter of droplets-distance between droplet

    From this equation it is evident that in order toincrease the force between droplets to help them

    coalesce, it is required to increase that the appliedvoltage gradient, increase the droplet diameterdecrease the distance between droplet

  • 7/27/2019 OIL D-1.pptx E&P industry

    131/367

    . If the voltage gradient applied to a particulardroplet is increased beyond a certain critical voltage(E

    c) peculiar to the droplet, the droplet will distort

    sufficiently to rupture its film at a critical point

    causing the droplet to break into smaller ,submicronic droplets The critical voltage gradientcan be expressed for a particular droplet as

    Eck(T/d)1/2

    where Ec- Critical voltage gradient Dielectricconstant for the system T-Surface tension

    d-Diameter of droplet

  • 7/27/2019 OIL D-1.pptx E&P industry

    132/367

    VERTICAL HORIZONTAL

    WITH ONLY HEATING ARRANGEMENT

    WITH ELECTROSTATIC COALESCENCE

  • 7/27/2019 OIL D-1.pptx E&P industry

    133/367

    EMULSION ENTERS AT THE TOP IN GAS SEPARATIONCHAMBER

    EMULSION FLOWS THROUGH THE DOWNCOMES

    TO THE BOTTOM OF THE VESSEL

    EMULSION MOVES UP THROUGH HEATING SECTION

    WATER SEPARATION IN COALESCING SECTION

  • 7/27/2019 OIL D-1.pptx E&P industry

    134/367

    INTERPHASE CONTROLLER CONTROLS WATER LEVEL IF PROVIDED WITH ELECTRSTATIC COALESCER OIL

    MOVES ACROSS IT FOR FURTHER DEHYDRATION

    INTERPHASE CONTROLLER MAINTAINS WATERLEVEL

    WATER CAN BE DRIANED THROUGH WATER SIPHON

  • 7/27/2019 OIL D-1.pptx E&P industry

    135/367

    BATTERY OF VERTICAL TREATERS

  • 7/27/2019 OIL D-1.pptx E&P industry

    136/367

    BATTERY OF VERTICAL TREATERS

  • 7/27/2019 OIL D-1.pptx E&P industry

    137/367

    MOST WIDELY USED CONSTRUCTION SIMILAR TO FREE WATER KNOCK

    OUT VESSEL THOUGH NOT EXACTLY SAME

    HORIZONTAL OR VERTICAL FLOW CONFIGURATTION OIL AND WATER INTERPHASE CONTROLLERS

    MAINTAIN LEVELS

  • 7/27/2019 OIL D-1.pptx E&P industry

    138/367

    HORIZONTAL FLOW CONFIGURATION:EMULSION ENTERS AT THE TOP OF THE VESSEL

    FLOWS ALONG A LONGITUDINAL BAFFLE

    ENTERS HEATING SECTION FROM THE BOTTOMHEATED OIL TRAVELS THROUGH A SLOT IN THE

    PARTITION

  • 7/27/2019 OIL D-1.pptx E&P industry

    139/367

    FREE WATER AT THE BOTTOM FLOWS OUTCLEAN OIL FLOWS TO THE TOP AND

    COLLECTED

    VERTICAL FLOW CONFIGURATION:OIL ENTERS THROUGH FORNT SECTION AND FLOWS

    DOWN

    FREE WATER IS SEPARATED

  • 7/27/2019 OIL D-1.pptx E&P industry

    140/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    141/367

    OIL MOVES THROUGH THE WATER ALYER AND GOESTO THE TOP

    CLEAN OIL IS COLLECTED FROM THE TOP

    WATER DARINED OUT FROM THE BOTTOM

  • 7/27/2019 OIL D-1.pptx E&P industry

    142/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    143/367

    ELECTROSTATIC TREATERS

  • 7/27/2019 OIL D-1.pptx E&P industry

    144/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    145/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    146/367

    ELECTROSTATIC COALESCENCE DISCUSSED EARLIER COALESCING CHAMBER CONTAINS ELECTROSTATIC

    GRID

    ELECTROSTATIC GRID:

    AC

    COMBINATION

  • 7/27/2019 OIL D-1.pptx E&P industry

    147/367

    AC FIELDS USED ARE IN THE RAGE OF 12 TO 23 Kv.

    MOST EFFECTIVE FOR LARGER WATER DROPLETS

    DIFFERENT COFIGURATIONS:

    TWO GRID SYSTEM ALSO KNOWN AS SINGLE HOT

    DOUBLE AND TRIPLE HOT DESIGN ALSO AVAILABLE

  • 7/27/2019 OIL D-1.pptx E&P industry

    148/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    149/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    150/367

    EMUSION FLOWS THROUGH THE GRID ANDELECTRIC COALESCENCE TAKES PLACE

    SEPARATED WATER FLOWS DOWN AND CLEAN OIL

    GOES TO THE TOP

    DOUBLE AND TRIPLE HOT SYSTEMS INCREASE THE

    RETENTION TIME OF EMULSION ACROSS THE

    ENERGISED ELECTRODES THEREBY INCREASING

    EFFICIENCY

  • 7/27/2019 OIL D-1.pptx E&P industry

    151/367

    DIPOLAR ATTRACTION

    FILM STRETCHING

    WATER TOLERANCELIMITATIONSMINIMAL DROP MOVEMENT

    LOW CHARGE DENSITY

    LIMITS ON USEFUL FIELD STRENGTH

  • 7/27/2019 OIL D-1.pptx E&P industry

    152/367

    AC/DC TREATERS ELECTRODES ARE PARALLEL PLATES

    PLATES ARE CONNECTED TO TWO OPPOSITELY

    ORIENTED DIODES

    BOTH DIODES ARE CONNECTED TO SAME END OF

    TRANSFORMER SECONDARY WINDING

    PLATES ARE CHRGED ON ALTERNATE HALF CYCLES

    OF AC

  • 7/27/2019 OIL D-1.pptx E&P industry

    153/367

    AC/DC TREATERS ELECTRODES ARE PARALLEL PLATES

    PLATES ARE CONNECTED TO TWO OPPOSITELY

    ORIENTED DIODES

    BOTH DIODES ARE CONNECTED TO SAME END OF

    TRANSFORMER SECONDARY WINDING

    PLATES ARE CHRGED ON ALTERNATE HALF CYCLES

    OF AC

  • 7/27/2019 OIL D-1.pptx E&P industry

    154/367

    + -

    - + - +

    + -

    UPWARD

    OIL FLOW

    DC FIELD BENEFITS

    MOST AC FIELD BENEFITS PLUS

  • 7/27/2019 OIL D-1.pptx E&P industry

    155/367

    MOST AC FIELD BENEFITS, PLUS . . .

    DROPLET TRANSPORTNET ELECTROSTATIC CHARGE

    BUT. . .

    MUST AVOID ELECTROLYTIC REACTIONS

    WATER TOLERANCE IS REDUCED

  • 7/27/2019 OIL D-1.pptx E&P industry

    156/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    157/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    158/367

    ELECTRODE PLATES

    RAILS

    INSULATORHANGERS

  • 7/27/2019 OIL D-1.pptx E&P industry

    159/367

    DUAL POLARITY:Dual polarity AC/DC Electrostatic unit provides this

    needed electrical gradient. The use of AC in the low

    gradient area between the water interface and the

    charged electrode has proven to be essential in this

    higher water content area of the process. The

    droplets removed from the stream in this area are

    very large and respond quite readily to this

    changing field because their individual size and

    number places them closer together.

  • 7/27/2019 OIL D-1.pptx E&P industry

    160/367

    The application of dual polarity DC potential, bothpositive and negative to the high gradient area

    between the electrodes successfully coalesces the

    majority of even the one and two micron droplets

    resulting in a much lower water content in theclean oil.

  • 7/27/2019 OIL D-1.pptx E&P industry

    161/367

    Provides Combined AC/DC Fields

    For Combined Benefits

    Drop Polarization

    Film Rupture

    Water Tolerance

    Drop Movement

    Drop Charge Density

    Minimizes Induced Corrosion

    COMPARATIVE ANALYSIS

  • 7/27/2019 OIL D-1.pptx E&P industry

    162/367

    AC Field

    Proven technology in conventional

    desalting process

    Electrostatic dehydration/desalting

    under AC electric field

    Traditional desalting technology Lower comparative cost

    High oversizing design

    High sensitivity to emulsion tightness

    (high stability) and high water content

    High desalting multiple stagesrequirements

    Good technical support

    High control requirements

    Dual Polarity

    Proven technology in conventional

    desalting process

    Electrostatic dehydration/desalting

    under Dual polarity (AC/DC) electric

    field and electrodynamic desaltingprocess (exclusive technologies)

    Improved desalting technologies

    Higher comparative cost

    Optimal design (low oversizing)

    Low sensitivity to emulsion tightness(high stability) and high water content

    Low desalting multiple stages

    requirements

    Excelent technical support

    High control requirements

  • 7/27/2019 OIL D-1.pptx E&P industry

    163/367

    To reduce salt content in crude oil Source of salt:

    water produced along with oil

    some times produced oil contains salt crystals Desalting Why

    Salt may cause corrosion, foul equipment

    Contract requirement

  • 7/27/2019 OIL D-1.pptx E&P industry

    164/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    165/367

    Dilution waterfresh water

    water recycle

    Water mixed with crudemixing efficiency

    problem of water solubility in oil at elevated

    temperatures

  • 7/27/2019 OIL D-1.pptx E&P industry

    166/367

    In produced brine with a high salt concentration, itmight not be possible to treat the oil to a low

    enough water content ( < 0.2% is difficult to

    guarantee), desalting system such as the one

    shown schematically consists of a mixing device (inwhich fresh water is usedto wash the crude oil)

    and any of the electrostatic treating systems

    described(which then are used to dehydrate the oil

    to a low water content)

  • 7/27/2019 OIL D-1.pptx E&P industry

    167/367

    mixing dilution water with the produced waterlowers the effective value ofCswin eqn. if a single-

    stage desalting systemrequires too much dilution

    water or is unable to reach the desired salt

    concentration, then a two stage system is used,such as the one shown schematically

  • 7/27/2019 OIL D-1.pptx E&P industry

    168/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    169/367

    THE MIXING VALVE

  • 7/27/2019 OIL D-1.pptx E&P industry

    170/367

    Differential Pressure Controller

    Mixing Valve

    Crude

    Flow

    Static Mixer (Optional) is

    occasionally installedeither upstream or

    downstream of the

    mixing valve

    To Desalter

    DPC

    SIZING EQUATIONS

  • 7/27/2019 OIL D-1.pptx E&P industry

    171/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    172/367

    WATER DROPLET SIZEF ti f i it

  • 7/27/2019 OIL D-1.pptx E&P industry

    173/367

    Function of viscosity

    For conventional treaters

    For Electrostatic traters

  • 7/27/2019 OIL D-1.pptx E&P industry

    174/367

    Oil field processing generally consists of

    NATURALGASPROCESSING

  • 7/27/2019 OIL D-1.pptx E&P industry

    175/367

    Oil field processing generally consists of

    two categories of operations: Separation of natural gas from free liquids

    ( crude oil, brine ) and entrained solids,(sand).

    Removal of impurities from natural gasand any condensate form.

    NATURAL GASPROCESSING

    It is crucial link between natural gas production and its

  • 7/27/2019 OIL D-1.pptx E&P industry

    176/367

    g ptransportation to market

    Pipe line Quality Natural Gas Calorific Value 1035 (+ 50) Btu / cu feet

    Specified dew point temperature level

    H2S < 4 ppm, CO2 2-3%, H2O < 7 lb / MMSCF, N2,O2traces

    Free of particulate solids & liquid water

    Other key Byproducts of Natural Gas Processing Helium

    Carbon- di-oxide

    Hydrogen Sulphide

    I i l

  • 7/27/2019 OIL D-1.pptx E&P industry

    177/367

    It involves:-

    Simple Separation + Dehydration (Separation of hydrocarbon condensate, liquid water and

    solid particles) Gas Compression (Condensate Removal)

    (Involves removal of condensate by compression) Natural Gas Liquids (NGL) Recovery (NGL is recovered by coding to ease transportation)

    Gas Dehydration (Dehydration is the removal of water content to prevent

    formation of gas hydrates and to increase the calorific value Gas Sweetening (It is to remove acid gas (CO2, H2S) component as H2S is toxic

    and both are corrosive)

    The individual unit operations commonlyused in field handling natural gas are:

    Basic fields processing schemes:

  • 7/27/2019 OIL D-1.pptx E&P industry

    178/367

    Basic fields processing schemes:

    Prevention of hydrate formation Sweetening

    Dehydration

    Condensate recovery and hydrocarbon dewpoint control

    Compression

    Flow measurement

    Heating and cooling Pipe line transport of natural gas

  • 7/27/2019 OIL D-1.pptx E&P industry

    179/367

    Glycol and methanol are comparableMerits of methanol:

    It can be used at any temperature

    Recovery is marginally economically due to itslow cost and high vaporization losses.

    Lower capital investments

    Methanol can dissolve existing hydrates

    DE-MERITS OF METHANOL

    It is co-absorbed with water vapor by glycol

  • 7/27/2019 OIL D-1.pptx E&P industry

    180/367

    It is co-absorbed with water vapor by glycol,

    increasing glycol regeneration heat load. Aqueous methanol can corrode steel in glycol

    steel and re boiler.

    Methanol can also reduced the capacity of soliddesiccant pallets because methanol is readilyco-absorbed.

    Merits of glycol (TEG/DEG)

    It exhibits higher depression of hydrateformation temperature.

  • 7/27/2019 OIL D-1.pptx E&P industry

    181/367

    formation temperature.

    Cheaper where continuous injection isrequired.

    Can be recovered easily.

    Demerits of glycol

    Its not chosen below 15 F because of its highviscosity and difficulty of separation fromliquid HC

    Without intimate mixing glycol injection maynot prevent hydrate formation

  • 7/27/2019 OIL D-1.pptx E&P industry

    182/367

    not prevent hydrate formation .

    It can not attack or dissolve existing hydrates.

  • 7/27/2019 OIL D-1.pptx E&P industry

    183/367

    Removal of Acid Gases

    Permissible Acid Gas Concentration

    H2

    S concn < 4 ppm v (0.25 gr / 100scf)

    Max total sulfur content including mercaptans(RSH), Carbon Sulfide (COS), disulphide (RSSR) etcis usually 10 to 20 gr / 100 scf (160-200 ppmv)

    CO2

    concn 2-3%

    Batch Process

  • 7/27/2019 OIL D-1.pptx E&P industry

    184/367

    Iron Sponge, Chem Sweet, Sulpha Check

    Aqueous Amine Solutions Moethanolamine

    Diethanolamine

    Diglycolamine Methyl diethanolamine

    (Solutions are regenerated, are used to remove large amount ofSulfur and CO2)

    Mixed Solutions (Mix of Amine, Physical Solvent,Water Sulfinol, Ucarsol, Flexsorb & Optisol)

    (These Solution absorb organic sulfur and are capable of high acidgas loading)

    Physical Solvents Selaxol

    Rectisol Purisol

  • 7/27/2019 OIL D-1.pptx E&P industry

    185/367

    Purisol

    Fluor Solvent These can be regenerated without heat and

    simultaneously dry the gas (Used for bulk removal of CO2 frequently offshore)

    Hot Potassium Carbonate Solutions Hot Pot Catacarb etc.

    Direct Oxidation to Sulfur Stretford, Sulferox Locat

    (These Process practically eliminate H2S emissions)

    Adsorption

    Linde, Zeochem & Davison Chemical Molecular Sieves

  • 7/27/2019 OIL D-1.pptx E&P industry

    186/367

    For low acid gas concentration, gas is simultaneouslydried

    Membranes

    Example AVIR, Air Products, Cynara (Dow), Du Pont,

    Grace, International Permeation and Monsanto aremost suitable for bulk CO2 separation, especially whenthe feed gas concentration is very high

    In General,

    If S < 20 lb/day Batch Process If S > 100 lb / day Amine Solution

    Sulfur Content, lb / day = 1.34 (MMSCFD)(gr/H2S/100SCF)

    contactor

    over head

    coalescer sep.

    G/L

    HUT

    HP flareFuel gas

    LP

    flare

    9

    Gas from Compressor

    Fuel gas

    PIC

  • 7/27/2019 OIL D-1.pptx E&P industry

    187/367

    Reboiler

    M

    MRecirculation pump Booster pump

    Flash vesselscrubber

    Storage tank

    Ajay KumarNeelam

    1

    flow

    meter

    Rich glycol

    Closed drain

    Closed drain

    LP flare

    Stripping gas

    GlycolDehydration

    Unit

    TCV

  • 7/27/2019 OIL D-1.pptx E&P industry

    188/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    189/367

    RECTANGULAR HORIZONTAL

    VERTICAL

    SPHERICAL

  • 7/27/2019 OIL D-1.pptx E&P industry

    190/367

    OPEN FIXED ROOF

    FLOATING ROOF:

    EXTERNAL FLOATING ROOF

    INTERNAL FOATING ROOF

    CLOSED FOATING ROOF

  • 7/27/2019 OIL D-1.pptx E&P industry

    191/367

    RIVETED BOLTED

    SHOP WELDED

    FIELD WELDED

  • 7/27/2019 OIL D-1.pptx E&P industry

    192/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    193/367

    LIQUID GAS

  • 7/27/2019 OIL D-1.pptx E&P industry

    194/367

    ACCURACYLinearity

    Repeatability

    Resolution

    Turndown

    d ff f h l d

  • 7/27/2019 OIL D-1.pptx E&P industry

    195/367

    Accuracy: difference from the actual measurement andthe meter reading, accuracy is stated in followingterms:

    Repeatability :meters ability to reproduce samemeasurement for a set of constant conditions of flow

    rate, temperature, viscosity, density, pressure.Repeatability of a custody transfer meter should bewithin +/-.025% in 3 runs or +/- 0.05% of each other in5 consecutive prove runs.

    Linearity :ability to maintain a meter factor through-out

    the stated turndown. Depending on meter size andapplication this is typically +/-0.15% or +/-0.25% forcustody transfer use.

  • 7/27/2019 OIL D-1.pptx E&P industry

    196/367

    Resolution. is a measure of the smallest incrementof total flow that can be individually recognized bythe meter.

    Turndown.Turndown is the meters flow range

    capability. The flow range of the meter is the ratioof maximum flow to minimum flow over which the

    specified accuracy or linearity is maintained. a

    meter with a minimum flow rate of 100 bbl/hr and

    a maximum flow of 1,000 bbl/hr is said to have a

    10:1 turndown.

  • 7/27/2019 OIL D-1.pptx E&P industry

    197/367

    FLOW RATE PRESSURE

    TEMPERATURE

    VISCOSITY

    ACCURACY

  • 7/27/2019 OIL D-1.pptx E&P industry

    198/367

    DIRECT - POSITIVE DISPLACEMENT INDIRECT - INFERS FLOW

    P iti di l t fl t l k PD

  • 7/27/2019 OIL D-1.pptx E&P industry

    199/367

    Positive displacement flowmeters, also know as PDmeters, measure volumes of fluid flowing through bycounting repeatedly the filling and discharging ofknown fixed volumes. A typical positive displacementflowmeter comprises a chamber that obstructs theflow. Inside the chamber, a rotating/reciprocating

    mechanical unit is placed to create fixed-volumediscrete parcels from the passing fluid. Hence, thevolume of the fluid that passes the chamber can beobtained by counting the number of passing parcels orequivalently the number rounds of the

    rotating/reciprocating mechanical device. The volumeflow rate can be calculated from the revolution rate ofthe mechanical device.

  • 7/27/2019 OIL D-1.pptx E&P industry

    200/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    201/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    202/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    203/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    204/367

    TURBINE METERS CORIOLIS METERS

    PRINCIPLE :

    INFERS FLOW BY MEASURING SOME DYNAMIC

    PROPERTY OF THE FLOW STREAM

  • 7/27/2019 OIL D-1.pptx E&P industry

    205/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    206/367

    Measures density and mass flow rate

  • 7/27/2019 OIL D-1.pptx E&P industry

    207/367

    Measures density and mass flow rate

    Principle: As fluid moves through a vibratingtube(s),Coriolis force causes distortion which is directlyproportional to mass flow rate.

    Density is related to frequency, though not linearly, bythe following equation

    = C0 + C1T2

    Where,

    = Density of fluid

    C0 & C1 = Constants

    T = Tube time period

  • 7/27/2019 OIL D-1.pptx E&P industry

    208/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    209/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    210/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    211/367

    ORIFICE METER TURBINE METER

    CORIOLIS METER

    ULTRASONIC METER

  • 7/27/2019 OIL D-1.pptx E&P industry

    212/367

    Principle:differential pressure proportional to squire of flow

    rate

    Standards:

    AGA 3

    ISO 5167

  • 7/27/2019 OIL D-1.pptx E&P industry

    213/367

    BASIC EQUATION:qh =C

    (hw pf)1/2

    where: qh -quantity rate of flow at base conditions,

    cfh C-orifice flow constant,

    hw differential pressure in inches of water at 600F, pf

    absolute static pressure, psia

  • 7/27/2019 OIL D-1.pptx E&P industry

    214/367

    C =(Fb)(Fr)(Y)(Fpb)(Ftb)(Ftf)(Fg)(Fpv)(Fm)(Fl)(F)Where: (Fb) basic orifice factor, cfh(Fr) Reynolds

    number factor (Y) expansion factor (Fpb) pressure

    base factor (Ftb) temperature base factor (Ftf)

    flowing temperature factor (Fg) specific gravityfactor(Fpv) supercompressibility factor(Fm)

    manometer factor for mercury meter(Fl)gauge

    location factor,(F) orifice thermal expansion factor

  • 7/27/2019 OIL D-1.pptx E&P industry

    215/367

    Principle:Difference in transit time of high frequency sound

    waves travelling between a pair of fixed sound

    transducers with the flow and against the flow

    determines the flow

  • 7/27/2019 OIL D-1.pptx E&P industry

    216/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    217/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    218/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    219/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    220/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    221/367

    Sucker Rod Pump Assembly

    Tubing Anchor/CatcherSucker Rod

    Reservoir

  • 7/27/2019 OIL D-1.pptx E&P industry

    222/367

    High System Efficiency,

  • 7/27/2019 OIL D-1.pptx E&P industry

    223/367

    High System Efficiency,

    Optimization Controls Available,

    Economical to Repair and Service,

    Positive Displacement/Strong drawdown,

    Upgraded Materials Reduce CorrosionConcerns,

    Flexibility -Adjust Production Through StrokeLength and Speed,

    High Salvage Value for Surface & DownholeEquipment

  • 7/27/2019 OIL D-1.pptx E&P industry

    224/367

    Potential for Tubing and Rod Wear

    Gas-Oil Ratios

    Most Systems Limited to Ability of Rods to

    Handle Loads ( Volume Decreases As DepthIncreases

  • 7/27/2019 OIL D-1.pptx E&P industry

    225/367

    Wellhead Surface Drives

    Continuous & Threaded Sucker Rods

    Subsurface PC Pumps & Accessories

  • 7/27/2019 OIL D-1.pptx E&P industry

    226/367

    RotorStator

    SuckerRod

    Tubing

    Vertical Electric WellheadDrive

  • 7/27/2019 OIL D-1.pptx E&P industry

    227/367

    Low Capital Cost

    Low Surface Profile for Visual & Height

    Sensitive Areas

    High System Efficiency

    Simple Installation,

    Quiet operationPumps Oils and Waters with Solids

    Low Power Consumption

    Portable Surface Equipment

    Low Maintenance Costs

    Use In Horizontal/Directional Wells

  • 7/27/2019 OIL D-1.pptx E&P industry

    228/367

    Limited Depth capability

    Temperature Sensitivity to Produced Fluids

    Low Volumetric Efficiencies in High-GasEnvironments

    Potential for Tubing and Rod Coupling Wear

    Requires Constant Fluid Level above Pump

  • 7/27/2019 OIL D-1.pptx E&P industry

    229/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    230/367

  • 7/27/2019 OIL D-1.pptx E&P industry

    231/367

    Production Packer

    Side Pocket Mandrel withGas Lift Valve

    Produced oilInjection Gas In

    Completion Fluid

    Reservoir

  • 7/27/2019 OIL D-1.pptx E&P industry

    232/367

    High Degree of Flexibility andDesign Rates

    Wireline Retrievable

    Handles Sandy Conditions

    WellAllows For Full Bore

    Tubing Drift

    Surface Wellhead Equipment

    Requires Minimal Space

    Multi-Well Production From

    Single CompressorMultiple or Slim hole

    CompletionProduced

  • 7/27/2019 OIL D-1.pptx E&P industry

    233/367

    Needs High-Pressure Gas Well or

    Compressor

    One Well Leases May Be Uneconomical

    Fluid Viscosity

    Bottom hole Pressure

    High Back-Pressure

  • 7/27/2019 OIL D-1.pptx E&P industry

    234/367

    Wellhead EquipmentPower Cables

    Pumps & Motors

    Variable Speed DrivesGas Separators

    ESPs can be very effective at moving large volumes

  • 7/27/2019 OIL D-1.pptx E&P industry

    235/367

    of fluid with low GLRs, however, capital costs and run

    life must be fully understood to ensure profitability:

    high PI low GOR oil wells (up to 1000 scf/bbl withseparator)

    high water cut producers Casing size limits size and capacity

    Requires reliable electrical supply at reasonable cost

    Normally run on tubing, cable deployed for offshore

    Inadequate design as a result of poor IPR data

  • 7/27/2019 OIL D-1.pptx E&P industry

    236/367

    q g p

    gather data on first pump run for re-design

    Inadequate service facilities

    Scaling on impellers

    Solids erosion Inadequate gas separation > 10% throughpump

    Emulsion formation in pump

    High bottom hole temperatures

    high temperature insulation is available

  • 7/27/2019 OIL D-1.pptx E&P industry

    237/367

    Motor

    SealSection

    Pump

    Tubing

    MotorControlProduced Hydrocarbons Out

  • 7/27/2019 OIL D-1.pptx E&P industry

    238/367

    High Volume and Depth Capability

    High Efficiency Over 1,000 BPD

    Low Maintenance

    Minor Surface Equipment NeedsGood in Deviated Wells

    Adaptable in Casings > 4-1/2 Use for

    Well TestingVent

  • 7/27/2019 OIL D-1.pptx E&P industry

    239/367

    Available Electric Power

    Limited Adaptability to Major Changes inReservoir

    Difficult to Repair In the Field

    Free Gas and/or Abrasives

    High Viscosity

    Higher Pulling Costs

  • 7/27/2019 OIL D-1.pptx E&P industry

    240/367

    BROADLY DEFINED AS DETERIORATION OF

  • 7/27/2019 OIL D-1.pptx E&P industry

    241/367

    MATERIAL OR ITS PROPERTIES UNDER THE

    INFLUENCE OF ENVIRONMENT

    INEVITABLE PHNENOMENON

    IN OILFIELD OPERATIONS IT EXTENDS FROM WELLTO DELIVERY POINT

    INITIALLY NOT ENOUGH ATTENTION WAS GIVEN

    UNTIMELY FAILURE OF EQUIPMENT STARTED

  • 7/27/2019 OIL D-1.pptx E&P industry

    242/367

    ANALYSIS OF CAUSE LEAD TO CONCLUSION THAT

    CORROSION WAS THE CULPRIT

    PROBLEM MULTIPLIED WHEN NEWER

    TECHNOLOGIES LIKE STEAM INJECTION,INSITUCOMBUSTION,POLYMER INJECTION etc. WERE PUT

    TO USE

    DEEPER AND HIGH TEMPERATURE WELLS

    MULTIPLIED THE PROBLEM

    IMPORTANCE OF CORROSION The three main

  • 7/27/2019 OIL D-1.pptx E&P industry

    243/367

    reasons for the importance of corrosion are:

    economic, safety, and conservation.

    economic impact of corrosion result from the

    corrosion of piping, tanks, metal components ofmachines, ships, marine structures , etc

    safety of operating equipment by causing failure

  • 7/27/2019 OIL D-1.pptx E&P industry

    244/367

    (with catastrophic consequences) of, for example,

    pressure vessels , boilers , turbine blades and

    rotors, etc.

    Loss of metal by corrosion is a waste not only of themetal, but also of the energy, the water, and the

    human effort that was used to produce and

    fabricate

    Temperature

    Typical E&P processf

  • 7/27/2019 OIL D-1.pptx E&P industry

    245/367

    temperatures range from-100C to >200C

    Corrosion rates increasewith temperature

    Pressure

    Pressure: up to 10,000psi Increase partial pressure of

    dissolved gases

    Flowrate & flow regime

    High-flow: erosion and

    corrosion-erosion. Low-flow or stagnant

    conditions promote bacteria

    245

    CORROSION IN OIL FIELD

  • 7/27/2019 OIL D-1.pptx E&P industry

    246/367

    ENTIRE CHAIN OF OPERARITONS EXPOSED TO

  • 7/27/2019 OIL D-1.pptx E&P industry

    247/367

    CORROSION

    WELLS:

    Tubing

    Casing

    Down hole equipment like pumps, packers etc.

    WELL HEAD

    FLOW LINES

  • 7/27/2019 OIL D-1.pptx E&P industry

    248/367

    well fluid line

    process lines

    water injection lines etc.

    PROCESS EQUIPMENT

    STORAGE TANKS

    TRUNK LINES

    WATER HANDLING SYSTEMS

  • 7/27/2019 OIL D-1.pptx E&P industry

    249/367

    THERMODYNAMIC CRITERIA

    ELECTROCHEMICAL CRITERIA

  • 7/27/2019 OIL D-1.pptx E&P industry

    250/367

    H2S CORROSION

    250

    F ti f thi t ti F S f fil ft

  • 7/27/2019 OIL D-1.pptx E&P industry

    251/367

    Formation of a thin protective FeS surface film often meansgeneral corrosion rates are low on steels

    Main risk is localised pitting corrosion where film is damaged

    Pitting will be galvanically driven

    251

    H2

    S is soluble in water

  • 7/27/2019 OIL D-1.pptx E&P industry

    252/367

    2 Produces a weak acid and lowers the pH

    H2S H+ + SH-

    At low concentrations, H2S helps form protective FeSfilm

    Main risk is localised pitting corrosion which can berapid

    H2S also poisons combination of atomic hydrogen intomolecular hydrogen

    H+ + e- H

    H + H H2

    252

    X

    Atomic hydrogen -dangerous to steels!!

    H2 H+

    S2-

    Fe2+

    H

  • 7/27/2019 OIL D-1.pptx E&P industry

    253/367

    253

    HHH

    H

    H

    Higher Strength Steels YS > 500 MPa Low Strength Steels YS < 550 MPa

    Applied Stress No Applied Stress

    H2

    H2

    SH

    H

    FeS Film

    Metal Matrix

    Key parameters:

    pH and pH2S

    D i di f bHAZ WELD HAZ

  • 7/27/2019 OIL D-1.pptx E&P industry

    254/367

    Domain diagrams for carbonsteel

    Material hardness

    High strength steels and areas ofhigh hardness susceptible.

    Temperature Maximum susceptibility at low

    temperatures for carbon steels(15-25C), higher for CRAs (5-70C).

    Stress Cracking promoted by high

    stress levels e.g. residualwelding

    254

    Hardness readings

    Avoid wetness

    Mi i i h dUpgrade to CRAs

  • 7/27/2019 OIL D-1.pptx E&P industry

    255/367

    Minimise hardness

    Guidance on limitsin ISO 15156

    Optimisemicrostructure and

    minimise residualstresses

    Martensitic and duplexstainless steels have limitedresistance

    H2S limits for duplex and

    super-duplex steels arecomplex

    Function of temperature,pH, chlorides, pH2S

    Nickel-base alloys such as

    625 and 825 have highresistance

    Testing: NACE TM0177

    255

    Materials requirements

    Reference ISO 15156 and GP 06 20

  • 7/27/2019 OIL D-1.pptx E&P industry

    256/367

    Reference ISO 15156 and GP 06-20 pH2S and pH

    Temperature

    Chlorides

    Hardness limits Welding QA/QC (HIC)

    Maintain hardness limits

    HIC testing for plate products

    256

  • 7/27/2019 OIL D-1.pptx E&P industry

    257/367

    CO2 CORROSION

    257

    CO2

    always present inproduced fluids

  • 7/27/2019 OIL D-1.pptx E&P industry

    258/367

    2produced fluids

    Corrosive to carbon steelwhen water present

    Most CRAs have good

    resistance to CO2corrosion.

    258

    Mechanism

    CO2 + H2O H2CO3H2CO3 + e

    -HCO3- + H

    2H H2Fe Fe2+ + 2e-

    Fe + H2O + CO2 FeCO3 +H2

  • 7/27/2019 OIL D-1.pptx E&P industry

    259/367

    259

    Mesa corrosion

    Localised weld corrosionlow-assisted-corrosion (CO2)

    General & pitting corrosion

  • 7/27/2019 OIL D-1.pptx E&P industry

    260/367

    260

    6 CS production flowline (Magnus, 1983)

    25mm thick, 90bar, 30C, 2%CO2

    Heavily pitted pipe wall and welds (not necessarily uniform

    corrosion)

    Didnt fail removed due to crevice corrosion of hub sealingfaces

    Main factors

    pCO2 temperature velocity pH

    For an ideal gas mixture, the partial pressure is the

    pressure exerted by one component if it alone occupied

    the volume. Total pressure is the sum of the partial

    f h i h i

  • 7/27/2019 OIL D-1.pptx E&P industry

    261/367

    pCO2, temperature, velocity, pH- CO2 prediction model

    Temperature, (C) pCO2 (bar) Carbon steel corrosion rate(mm/yr)130 0.6 7

    75 0.6 6

    149 30 >50

    261

    pressures of each gas component in the mixture

    Produced sand can affect inhibitor efficiency

    Inhibitor adsorption loss

  • 7/27/2019 OIL D-1.pptx E&P industry

    262/367

    Inhibitor adsorption loss Sand (and other solid) deposits give increased risk of localised

    corrosion;

    Prevent access of corrosion inhibitor to the metal

    Provide locations for bacteria proliferation

    Galvanic effects (area under deposit at more negative potentialthan area immediately adjacent to deposit)

    Formation of concentration cells/gradients

    262

    Internal CO2 corrosion of carbon steel needs to be managed

    Usually mitigate by chemical inhibitors

  • 7/27/2019 OIL D-1.pptx E&P industry

    263/367

    Usually mitigate by chemical inhibitors Simple geometries only (mainly pipelines)

    Assume inhibitor availability (90-95%)

    Inhibited corrosion rate of 0.1mm/year

    Remaining time at full predicted corrosion rate Apply a corrosion allowance for the design life

    If calculated corrosion allowance >8mm use CRAs

    263

    Filming type

  • 7/27/2019 OIL D-1.pptx E&P industry

    264/367

    Filming type Retention time

    Continuous injection

    Adsorption onto clean

    surfaces

    264

    Clean steel

    CO2/H2S > 500 CO2 dominates

    500 CO /H S 20 i d CO /H S

  • 7/27/2019 OIL D-1.pptx E&P industry

    265/367

    H2S corrosion (CO2/H2S < 20)

    Initial corrosion rate high

    Protective FeS film quickly slows down corrosion to lowlevel

    The corrosion rate is much less than the Cassandra

    prediction

    265

    500 > CO2/H2S > 20 mixed CO2/H2S

    20 > CO2/H2S > 0.05 H2S dominates

    dissolved gases:

    oxygen

  • 7/27/2019 OIL D-1.pptx E&P industry

    266/367

    oxygen

    can cause severe corrosion even at very lowppm(less than 1 ppm)

    usually causes pittingsolubility a function of pressure andtemperature

    being a strong oxidizing agent, it will increasecorrosion rates in presence of other gases like

  • 7/27/2019 OIL D-1.pptx E&P industry

    267/367

    corrosion rates in presence of other gases like

    hydrogen sulfide, carbon dioxide

    carbon dioxide

    forms a weak acid with waternot so corrosive as compared to oxygen

    called sweet corrosion

    solubility a function of pressure and temperature

    i d i l bilit i d

  • 7/27/2019 OIL D-1.pptx E&P industry

    268/367

    increased pressure increases solubility, increased

    temperature reduces solubility

    hydrogen sulfide

    very soluble in water

    forms a weak acid

    reaction with iron produces iron sulfide

    ( hi h d it i th f f bl k d ) d

  • 7/27/2019 OIL D-1.pptx E&P industry

    269/367

    ( which deposits in the form of black powder) and

    hydrogen

    produced hydrogen may cause blistering

    combination of hydrogen sulfide and carbon dioxideis more aggressive

    even minute quantities of oxygen can be disastrous

    t ll b f d b lf t

  • 7/27/2019 OIL D-1.pptx E&P industry

    270/367

    may occur naturally or may be formed by sulfate

    reducing bacteria

    PHYSICAL VARIABLES:

    temperature rates generally increase

    pressure concentration of dissolved gases

    velocity

    stagnant or low velocity may have low rates but can

  • 7/27/2019 OIL D-1.pptx E&P industry

    271/367

    stagnant or low velocity may have low rates but can

    cause pitting

    higher velocities generally cause higher corrosion

    higher velocities in presence of suspended solids cancause corrosion-errosion

  • 7/27/2019 OIL D-1.pptx E&P industry

    272/367

    EROSION & EROSION-

    CORROSION

    272

    Gasiquid Various multi-phase flow regimespossible;

  • 7/27/2019 OIL D-1.pptx E&P industry

    273/367

    273

    LiquidGas

    Bubble (bubbly) flow

    Stratified flowGas

    LiquidAnnular flow

    Churn flow

    GasLiquid

    Plug flow

    Wave (wavy) flow

    Liquid GasSlug flow

    Mist (spray) flow

    erosion characteristics

    distribution of phases

    carrier phase for solids

    Flow regimes with particles in the gas

    show higher erosion rates than those

    with particles in the liquid phase.

    Erosion

    Caused by high velocity

  • 7/27/2019 OIL D-1.pptx E&P industry

    274/367

    y g yimpact & cutting action ofliquid and/or solidparticles

    Erosion failures can be

    rapid Erosion-corrosion

    Occurs in environmentsthat are both erosive andcorrosive.

    Erosion and corrosion canbe independent orsynergistic.

    274

    Erosion of tungsten carbide choke trim

    Areas wherever flow is restricted

    or disturbedT pieces bends chokes al es

  • 7/27/2019 OIL D-1.pptx E&P industry

    275/367

    T-pieces, bends, chokes, valves,weld beads

    Areas exposed to excessive flowrates

    Sand washing Washing infrequently allowing

    sand to accumulate

    High pressure drop during washingof separators

    Sea water systems

    High flow areas in water injection /cooling systems

    275

    Trinidad

    Algeria (duplex)

    Sand accumulation

    Build up of sand in a test

  • 7/27/2019 OIL D-1.pptx E&P industry

    276/367

    pseparator

    Pressure drop

    Large pressure drop acrosssand drain pipework during

    washing

    Rapid failure

    Occurred within 2 minutes ofopening the drain

    276

    Erosion at bend

    Sand allowed to accumulate inseparator

    Wash nozzles embedded in sandPCV ki l

  • 7/27/2019 OIL D-1.pptx E&P industry

    277/367

    PCV not working properly

    High pressure / flowrate

    Nozzle not erosion-resistant

    Erosion of wash nozzle

    Spray changed to a jet causingerosion of shell

    Local changes to operating proceduresnot communicated

    Frequency of sand washing

    Risk not captured or assessed inRBI

    277

    Water spray

    Water jet

  • 7/27/2019 OIL D-1.pptx E&P industry

    278/367

    278

    Progressivenozzledamage

    Occurs in environments that can be erosive and

    corrosive.

  • 7/27/2019 OIL D-1.pptx E&P industry

    279/367

    Erosion and corrosion can either be:

    independent of each other;

    wastage equals sum of individual wastage rates

    synergistic; wastage rate > sum of individual rates

    localised protective film breakdown at bends,elbows areas of turbulence

    279

  • 7/27/2019 OIL D-1.pptx E&P industry

    280/367

    Water speed or local turbulence damages or removesprotective film

    90-10 Cu-Ni susceptible to internal erosion-corrosion(impingement) at velocities >3.5ms-1

    Water-swept pits (horse-shoe shaped)

    280

    Occurs at high fluid velocities

    Formation & collapse of vapour

  • 7/27/2019 OIL D-1.pptx E&P industry

    281/367

    p pbubbles in liquid flow on metalsurface.

    No solids required

    Typical locations

    Pump impellers (rapid change inpressure which damages films)

    Stirrers, hydraulic propellers

    Use erosion resistant materials

    Stellite, tungsten carbide

    281

    UNIFORM CORROSION:

    idealized form of corrosion

  • 7/27/2019 OIL D-1.pptx E&P industry

    282/367

    idealized form of corrosion

    less damaging

    uniform thinning

    prevention:

    protective coating

    proper material selection, use inhibitors

    GALVANIC CORROSION:(BIMETTALIC CORROSION)

    two dissimilar metals with different corrosion

  • 7/27/2019 OIL D-1.pptx E&P industry

    283/367

    two dissimilar metals with different corrosion

    potential

    metal with lower potential will corrode first

    grooving of interface

    this principle is applied in beneficial way for

    corrosion control in cathodic protection

    Three conditions are required for galvanic corrosion;

    A conducting electrolyte (typically seawater).Two different metals in contact with the electrol te

  • 7/27/2019 OIL D-1.pptx E&P industry

    284/367

    Two different metals in contact with the electrolyte. An electrical connection between the two metals.

    Relative positions within the electrochemical series (forgiven electrolyte) provides driving potential and affectsrate.

    Corrosion of base metal (anode) stimulated by contact withnoble metal (cathode).

    Relative area of anode and cathode can significantly affectcorrosion rate.

    Higher conductivity increases corrosion e.g. presence ofsalts

    284

    Firewater CuNi / superduplex stainless steel

    connections. 4CuNi pipe with a 550mm

  • 7/27/2019 OIL D-1.pptx E&P industry

    285/367

    4 CuNi pipe with a 550mmisolation spool (i.e. 5x OD)

    Leaks experienced on CuNispools at welds

    Same problems with CuNi /6Mo

    285

    ETAP platform

    Techlok joints in a

  • 7/27/2019 OIL D-1.pptx E&P industry

    286/367

    firewater piping system

    Piping: super-duplex

    Seal rings: 17-4PH

    286

    Brass tubesheet in seawater

    service Brass is Cu Zn alloy

  • 7/27/2019 OIL D-1.pptx E&P industry

    287/367

    Brass is Cu-Zn alloy

    Cu is more noble than Zn

    Zn dissolvespreferentially leaving Cu

    behind Result

    Loss of strength

    Difficult to seal

    Remedy Add arsenic to the brass

    287

    Avoid dissimilar materials

    in seawater system designs MoC for later changes

    Electrical isolation between

    different alloy classes Install distance spools,

  • 7/27/2019 OIL D-1.pptx E&P industry

    288/367

    g

    Avoid small anode/largecathode

    Avoid graphite gaskets &seals

    Avoid connecting carbonsteel to titanium alloys

    Galvanic corrosion orhydrogen charging oftitanium may occur

    p ,separation of at least 20x pipediameters

    Solid non-conducting spoole.g. GRP

    Line the noble metalinternally with an electricallynon-conducting material e.g.rubber

    Apply a non-conducting

    internal coatingon the morenoble material. Extend coatingfor 20 pipe diameters.

    288

    Example : CuNi-Superduplex

  • 7/27/2019 OIL D-1.pptx E&P industry

    289/367

    289

    Apply a non-conducting internal coating on the more noble material.

    Distance spool: solid, non-conducting material e.g. GRP

    Distance spool: noble metal internally lined with an electrically non-conducting material such as rubber

  • 7/27/2019 OIL D-1.pptx E&P industry

    290/367

    OTHER CORROSION

    MECHANISMS

    290

    Chemicals can be corrosive

    Carbon steel OK for non-corrosivechemical piping, e.g. methanol

  • 7/27/2019 OIL D-1.pptx E&P industry

    291/367

    p p g, g

    Corrosive chemicals (e.g. concentratedsolutions of inhibitors and biocides)require CRAs vendor will specify

    316 SS is typical Notable exceptions:

    Hypochlorite: very corrosive, titanium orGRP piping required

    Avoid titanium alloys in dry methanol

    service due SCC

    291

    SCC of a titanium seal exposed topure methanol instead of 5%

    water content

    Carbon steel open drain pipework.

    Seepage of scale inhibitor (passing valve)

    S l i hibi H

  • 7/27/2019 OIL D-1.pptx E&P industry

    292/367

    292

    Scale inhibitor pH

  • 7/27/2019 OIL D-1.pptx E&P industry

    293/367

    switch off when notflowing

    Areas affected Impingement / turbulent

    areas Bends and low points

    Use quill/other mixer Upgrade material Thicker schedule

    Valve arrangement Make self-draining Enable quill removal

    293

    Main Flow

    Injected Fluid

    Impingement

    Environments less common in E&P

    Flare tips, fired heaters, boilers Oxidation

  • 7/27/2019 OIL D-1.pptx E&P industry

    294/367

    Oxidation

    Oxidation significant >530C

    Oxidation rate varies with temp,gas composition and alloy Crcontent

    Firetubes: usually CS, but Cr-Mo alloys needed for hightemps

    Flare tips: 310 SS, alloy 800H

    Other high temperature mechanisms

    sulphidation (H2S and SO2) carburizing, metal dusting, hot

    salt

    thermal fatigue and creep

    294

    Material: carbon/low-alloy steels

    Environment: aqueous amine systemsC ki d t id l t

  • 7/27/2019 OIL D-1.pptx E&P industry

    295/367

    Cracking due to residual stressesat/next to non-PWHTd weldments

    Cracking develops parallel to theweld

    Mitigation:

    PWHT all CS welds includingrepair and internal/externalattachment welds.

    Use solid/clad stainless steel 304 SS or 316 SS

    295

    Intergranular cracking

    Amine piping welds requirePWHT to avoid SCC

    Glycol usually regarded as benign

    Corrosion in glycol regeneration

    systems usually due to; Acid gases absorbed by rich glycol

  • 7/27/2019 OIL D-1.pptx E&P industry

    296/367

    Acid gases absorbed by rich glycolor

    Organic acids from oxidation ofglycol and thermal decomposition

    products Condensation of low pH water

    giving carbonic acid attack.

    Risk recognised in design

    On-skid: CRA piping & clad

    vessels However, off-skid piping mix of

    regular CS and LTCS

    296

    Combined action of cyclic tensile

    stress and a corrosiveenvironment

  • 7/27/2019 OIL D-1.pptx E&P industry

    297/367

    Fatigue is caused by cyclicstressing below the yield stress Cracks start at stress raisers Can occur due to vibration e.g.

    smallbore nozzles & withheavy valve attachments Presence of corrosive

    environment exacerbates theproblem Can lead to pitting, which acts

    as stress concentrators

    297

    2 A106 GrB carbon steel piping

  • 7/27/2019 OIL D-1.pptx E&P industry

    298/367

    Wet gas service, 1.2%CO2 and160ppm H2S

    Operating @ 120C and 70bar

    Elbow exposed to vibration (usedin a gas compression train)

    Crack located at 12 o'clock position

    Crack initiated internally

    298

  • 7/27/2019 OIL D-1.pptx E&P industry

    299/367

    EXTERNAL CORROSION

    SURFACE FACILITIES

    299

    External corrosion of unprotected steel surfaces

    External corrosion of coated surfaces

    C i d i l i (CUI)

  • 7/27/2019 OIL D-1.pptx E&P industry

    300/367

    Corrosion under insulation (CUI)

    Corrosion under fireproofing (CUF)

    Pitting & crevice Corrosion

    Environmental cracking

    300

    Bare steel surfaces

    At locations of coating breakdown

    Under deposits such as dirt, adhesive tape or nameplates Mating faces between pipe/pipe support saddles & clamps

  • 7/27/2019 OIL D-1.pptx E&P industry

    301/367

    Mating faces between pipe/pipe support saddles & clamps

    Isolated equipment not maintained or adequately mothballed

    Water sources include:

    sea spray and green water (FPSO or semi-sub)

    rain

    deluge water

    leaking process water

    condensation

    downwind of cooling towers.

    301

  • 7/27/2019 OIL D-1.pptx E&P industry

    302/367

    Damage can be extensive or localised.

    Corrosion can be general attack, pitting or cracking.

    Seen as flaking, cracking, and blistering of coating withcorrosion of the substrate.

    302

    Carbon/low alloy steels usuallycovered in compact scale/thickscab

    St i l t l h li ht t i

  • 7/27/2019 OIL D-1.pptx E&P industry

    303/367

    Stainless steels have light stains onthe surface possibly with stainedwater droplets and / or salts.

    Corroding copper alloys covered in

    blue/greencorrosion products.

    303

  • 7/27/2019 OIL D-1.pptx E&P industry

    304/367

    304

    25Cr super-duplex (PREN40)

    Seawater service 12 months exposure in

  • 7/27/2019 OIL D-1.pptx E&P industry

    305/367

    12 months exposure intropical climate

    External corrosion alongwelds

    Poor quality fabrication

    305

    Bolted joints

    Onshore and offshore: exposed to frequent wetting Low alloy bolts

  • 7/27/2019 OIL D-1.pptx E&P industry

    306/367

    Low alloy bolts

    General or localised corrosion

    Galvanic corrosion in stainless steel flanges

    CRA bolts susceptible to pitting and/or SCC

    Crevice corrosion under bolt heads and nuts

    Hydrogen embrittlement possible

    Fatigue

    306

  • 7/27/2019 OIL D-1.pptx E&P industry

    307/367

    307

    General corrosion Galvanic corrosion

    Crevice corrosion Stress corrosion cracking

    Corrosion General surface corrosion

    Galvanic corrosion e.g. 316 SS / carbon steel

  • 7/27/2019 OIL D-1.pptx E&P industry

    308/367

    g / Use of graphite gaskets

    Potential problems Failure of flanged connection

    due to corroded fasteners Joint leak

    Corrective actions Change gasket/fastener

    materials Replace graphite gaskets with

    non-asbestos or rubber material

    308

  • 7/27/2019 OIL D-1.pptx E&P industry

    309/367

    309

    Location of graphite gaskets

    Valves

    Valve handles Chain-wheels

    l b d

  • 7/27/2019 OIL D-1.pptx E&P industry

    310/367

    Valve body

    Structures

    Stairways and walkways

    Gratings, ladders,handrails

    Cable trays and unistruts

    Threaded plugs

    Valve bodies, xmas trees,

    piping Dissimilar metals

    310

    Deterioration of coating with time All paints let water through - continuously wet areas will fail

    Poor original surface preparation / paint application Mechanical damage

  • 7/27/2019 OIL D-1.pptx E&P industry

    311/367

    g Small area of damage can lead to major corrosion

    311

    CUI

    Water seeps into insulation andbecomes trapped, results in

  • 7/27/2019 OIL D-1.pptx E&P industry

    312/367

    becomes trapped, results inwetting and corrosion of themetal

    Carbon steel corrodes in the

    presence of water due to theavailability of oxygen.

    CUF

    Same mechanism except watergets behind the fireproofing.

    312

    Typical insulation types;

    Process Personnel protection

    ( )

  • 7/27/2019 OIL D-1.pptx E&P industry

    313/367

    (PP)

    Winterisation

    Acoustic

    Challenge the need Remove unnecessary

    insulation

    Replace PP with cages

    313

    Lobster-back joint

    Mitred joint

    Pre-formed bends

    4 gas compression recycle

    line Operating pressure, 35bar

  • 7/27/2019 OIL D-1.pptx E&P industry

    314/367

    3 bar pressure surge

    Temperature: 50C

    6.02mm nominal WT

    Rockwool insulation

    Extensive corrosion rupture

    Unusual, burst rather thanleaked

    314

    2 fuel gas piping outsideedge of platform - exposed

    CS, heat-traced, Rockwool

    Operating @ 5bar 45C

    Focus on internal corrosion

    Previous survey founddefect in an adjacent line.

    Failed line in survey but

  • 7/27/2019 OIL D-1.pptx E&P industry

    315/367

    315

    Operating @ 5bar, 45C,5.4mm NWT

    Failed during plant start-up

    External corrosion scale,CUI

    Failed line in survey butnot failed area.

    Features selected from

    onshore not site survey

    4 CS hydrocarbon line

    55C, inlet to PSV (153 bar)

    Th ll d l i i (TSA)

  • 7/27/2019 OIL D-1.pptx E&P industry

    316/367

    316

    Thermally-sprayed aluminium (TSA)

    CUI found, radiographed ok to refurbish.

    Found during needle-gunning (paint removal)

    Max pit depth 10mm

    Insulation permanently removed

    CS offshore vessel

    Operating at 85C and 11bar

  • 7/27/2019 OIL D-1.pptx E&P industry

    317/367

    PFP coating (passive fireprotection)

    Extensive corrosion

    scabbing on both sides ofvessel.

    Scaling runs in twohorizontal distinct linesalong each side.

    Scaling directly above

    lower seam of insulation location of water

    retention.

    317

    400x300x30mm

    400x100x25mm

    Stainless steels in marine

    environments (chlorides, O2) 316L stainless steel

    l d f

  • 7/27/2019 OIL D-1.pptx E&P industry

    318/367

    commonly used forinstrument tubing

    Particularly susceptible atsupports and fittings.

    Primary mitigation ismaterials selection (higherPREw)

    Tungum, 6Mo, super-duplex

    Alternative mitigationmethods (coating, cleaning),not easy or practical.

    318

    316 SS tubing super-duplex tubing

  • 7/27/2019 OIL D-1.pptx E&P industry

    319/367

    319

    316 SS (pitting/crevice corrosion) super-duplex (no pitting)

    Pitting and crevice

    corrosion of 316sspiping

  • 7/27/2019 OIL D-1.pptx E&P industry

    320/367

    Clamps

    Plastic retainingblocks

    320

    Mechanism same as internal chloride SCC however: Numerous variables influence susceptibility therefore

    guidance differs Material, stress, chlorides, oxygen and temperature

    N b l t id il bl k t d i

  • 7/27/2019 OIL D-1.pptx E&P industry

    321/367

    No absolute guidance available, seek expert advice

    321

    Chloride SCC is characterised by trans-

    granular crack paths

    UK HSE:

    Coat 22Cr duplex >80C NORSOK M-001 SCC temp limits:

    22Cr duplex >100C

  • 7/27/2019 OIL D-1.pptx E&P industry

    322/367

    22Cr duplex >100C

    25Cr super-duplex >110C

    Recent testing has shown failures at

    80C now recommend 70C as limit

    Reliant on external coati