Offshore Windpark DanTysk - kiwi-kiel.de · Kieler Branchenfokus Windindustrie | 2015.02.03...
Transcript of Offshore Windpark DanTysk - kiwi-kiel.de · Kieler Branchenfokus Windindustrie | 2015.02.03...
. Kieler Branchenfokus Windindustrie | 2015.02.03
Offshore Windpark DanTysk
Cost-Effective Foundations
Design to Installation
Kieler Branchenfokus: Winindustrie – 3.2.15
Confidentiality - None (C1) - Olaf Beeg Package Manager Civil Works DanTysk
. Kieler Branchenfokus Windindustrie | 2015.02.03
Confidentiality -
Vattenfall‘s Offshore Pipeline
• Onshore: 71,8 MW
• Offshore: 540 MW
• Estimated annual production: 1,847 GWh
United Kingdom
Onshore capacity: 720 MWTOTAL Offshore capacity: 1122 MW
Production: 5,213 GWh
Vattenfall shared
• Onshore: 274 MW
• Offshore: 54 MW
• Estimated annual production: 449 GWh
The Netherlands
• Onshore: 12 MW
• Offshore: 304 MW
• Estimated annual production: 1380 GWh
Germany
• Onshore: 249 MW
• Offshore: 96 MW
• Estimated annual production: 903 GWh
Denmark
• Onshore: 113 MW
• Offshore: 127 MW
• Estimated annual production: 634 GWh
Sweden
2 |
Confidentiality - None (C1) - Olaf Beeg Package Manager Civil Works DanTysk
. Kieler Branchenfokus Windindustrie | 2015.02.03
Confidentiality -
3 |
Vattenfalls Offshore Pipeline in Germany
• More than 1.500 MW
installation potential for
offshore wind farms in
the German North Sea
• Different development
stages
• Next project to come:
Sandbank (288 MW)
Confidentiality - None (C1) - Olaf Beeg Package Manager Civil Works DanTysk
. Kieler Branchenfokus Windindustrie | 2015.02.03
Confidentiality -
4 |
DanTysk – Foundations: From design to installation
Table of contents
1. Project overview
2. Foundation design
3. Foundation installation
4. Grouting
5. Noise mitigation
Confidentiality - None (C1) - Olaf Beeg Package Manager Civil Works DanTysk
. Kieler Branchenfokus Windindustrie | 2015.02.03
Confidentiality -
5 |
1) DanTysk – Project overview
Project Set-up and current status:
• Joint venture with Stadtwerke
München (49%) und Vattenfall (51%)
• Vattenfall has the lead in construction
and operation
• Project permit granted 2005
• 80 sites
• located ~70 km west of Sylt
• 90 km (~ 50 nm) to Esbjerg
• Water depth 21 - 32 m
• area 71 km²
• grid access granted (sylwin 1)
• Construction start 2013
Confidentiality - None (C1) - Olaf Beeg Package Manager Civil Works DanTysk
. Kieler Branchenfokus Windindustrie | 2015.02.03
Confidentiality -
6 |
1) DanTysk – Project overview: Wind Turbine Generator
What:
• 80 x SIEMENS 3,6 SWT 120
• -> 288 MW
• Energy yield more than 1,3 TWh/a
Siemens Wind Power
Confidentiality - None (C1) - Olaf Beeg Package Manager Civil Works DanTysk
. Kieler Branchenfokus Windindustrie | 2015.02.03
Confidentiality -
7 |
1) DanTysk – Project Overview: Instal. Vessel for WTG
What:
• “Pacific Osprey”Purpose build Jack-up vessel
• SWIRE Blue Ocean
• 6 legs, load capacity of 12 complete sets of WTG
SWIRE Blue Ocean
Confidentiality - None (C1) - Olaf Beeg Package Manager Civil Works DanTysk
. Kieler Branchenfokus Windindustrie | 2015.02.03
Confidentiality -
8 |
1) DanTysk – Project Overview: Offshore Substation
What:
• Offshore sub-station with jacket-
structure 33/155 kV
• Strukton/Hollandia to design,
manufacture and install
• Installation done with Seaway Heavy
Lifting “Oleg Strashnov” August 2013
Confidentiality - None (C1) - Olaf Beeg Package Manager Civil Works DanTysk
. Kieler Branchenfokus Windindustrie | 2015.02.03
Confidentiality -
9 |
1) DanTysk – Project Overview: Inter Array Cable
What:
• 120 km cable incl laying, pull-in and
burial
• Van Oord Dredging and Marine Contractors + Visser & Smit Marine
Contracting
• 3 cable dimensions, ring connectionVan Oord
Confidentiality - None (C1) - Olaf Beeg Package Manager Civil Works DanTysk
. Kieler Branchenfokus Windindustrie | 2015.02.03
1) DanTysk – Offshore Accommodation Platform (OAP)
What:
• Accommodation for 50
service technicians
(DanTysk & Sandbank)
• Nobiskrug to design,
manufacture and install
• Bridge connection to OSS
Confidentiality - None (C1) - Olaf Beeg Package Manager Civil Works DanTysk
. Kieler Branchenfokus Windindustrie | 2015.02.03
Confidentiality -
11 |
1) DanTysk – Project Overview: Foundations
What:
• 80 monopiles and transition pieces installed
• Aarsleff/Bilfinger Berger joint
venture(ABJV)
• Installation by Seafox 5
• Finalized 13.12.2013
ABJV
Confidentiality - None (C1) - Olaf Beeg Package Manager Civil Works DanTysk
. Kieler Branchenfokus Windindustrie | 2015.02.03
Confidentiality -
12 |
2) DanTysk – Foundations: Design
2.1) Design Basis / environmental conditions
Simple principle: Design drivers are always cost drivers
⇒ LEC reduction by smart engineering!
Main design drivers at DanTysk:
• Design Basis / environmental conditions: Soil, waves, wind, turbine loads
etc.
- Re-arrangement of park layout => Shift locations based on
geophysics, electrical/cable needs, wind yield
- New scour protection concept => Less rock dumping + more
monitoring
• Load iteration turbine � foundation
• Grouted connection
• Secondary steel / EquipmentABJV
Confidentiality - None (C1) - Olaf Beeg Package Manager Civil Works DanTysk
. Kieler Branchenfokus Windindustrie | 2015.02.03
Confidentiality -
13 |
2) DanTysk – Foundations: Design
2.2) Load iteration turbine ���� foundation
3 clusters; dependent on water depth and
reference waves
⇒ 1 conservative virtual location per cluster
(worst soil combined with deepest water)
⇒ 2 load iterations with Siemens => after
load results: check of loads at upper
bound (stiffest soil combined with lowest
water depth)
⇒ One interface load per cluster =>
detailed calculation of all locations in
cluster
Reference location cluster SCOWI/IMS
N
M
M
M
S
Confidentiality - None (C1) - Olaf Beeg Package Manager Civil Works DanTysk
. Kieler Branchenfokus Windindustrie | 2015.02.03
Confidentiality -
14 |
2) DanTysk – Foundations: Design
2.3) Grouted connection
Basic principle:
⇒ Cylindrical
⇒ Shear keys (weld beats)
⇒ horizontal and vertical
⇒ ZiE process based on German principles
⇒ Grout volume ~ 21 m³
⇒ Grouting temperature > 5°
Conservative design! => minimize risks!
COWI/IMS
Confidentiality - None (C1) - Olaf Beeg Package Manager Civil Works DanTysk
. Kieler Branchenfokus Windindustrie | 2015.02.03
Confidentiality -
15 |
3) DanTysk – Foundations Installation
3.1 ) Installation Timeline - general facts
Step Planned time Real time (average)
Positioning / Jack up 3 h 3,0 h
Upending /placing pile 3 h 6,1 h
Positioning hammer 1 h 0,8 h
Drive pile 3 h 1,9 h
Remove hammer 1 h 0,5 h
Lifting TP + adjusting 2 h 1,6 h
Grouting 5 h 5,0 h
Seafastening crane 1,5 h 1,7 h
Confidentiality - None (C1) - Olaf Beeg Package Manager Civil Works DanTysk
. Kieler Branchenfokus Windindustrie | 2015.02.03
Confidentiality -
16 |
3) DanTysk – Foundations Installation
27,00
29,00
31,00
33,00
35,00
37,00
39,00
41,00
43,0000:14:24
00:28:48
00:43:12
00:57:36
01:12:00
01:26:24
01:40:48
01:55:12
02:09:36
02:24:00
02:38:24
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80
Ein
dri
ng
tie
fe [
m]
Ne
tto
Ra
mm
zeit
[h
h:m
m:s
s]
Fortlaufende Monopile ID
Netto Rammzeit
Eindringtiefe
Piling timeline - all locations
2,0 h 30m
1,5 h
=> starting MP 15 reduced piling energy 1000 kJ max
+ 9,5 minutes average piling time
Confidentiality - None (C1) - Olaf Beeg Package Manager Civil Works DanTysk
. Kieler Branchenfokus Windindustrie | 2015.02.03
Confidentiality -
17 |
⇒ Clear definition of operational limits!
⇒ Which limits are agreed?
⇒ Where and how to be measured?
⇒ Weather forecast
⇒ Who takes which risk?
⇒ Additional MWS requirements
But: No compromise on HSE!
3.2) Basics to ease life offshore
3) DanTysk – Foundations Installation Critical steps
Confidentiality - None (C1) - Olaf Beeg Package Manager Civil Works DanTysk
. Kieler Branchenfokus Windindustrie | 2015.02.03
Confidentiality -
18 |
4) DanTysk – Foundations Installation Grouting
4.1 Basics
• ZiE process in Germany
• Detailed requirements for design/calculation, material, fabrication, surveillance, testing, installation etc.
� Improve engineering in all phases!
Confidentiality - None (C1) - Olaf Beeg Package Manager Civil Works DanTysk
. Kieler Branchenfokus Windindustrie | 2015.02.03
Confidentiality -
19 |
4) DanTysk – Foundations Installation Grouting
4.2 Temperature
• Temperature requirement: ≥ 5 C
• Water and air temperature < 5 C until End of April 2013
� Improve engineering in all phases! Material, installation processes and additional measures!
Confidentiality - None (C1) - Olaf Beeg Package Manager Civil Works DanTysk
. Kieler Branchenfokus Windindustrie | 2015.02.03
Confidentiality -
20 |
4) DanTysk – Foundations Installation Grouting
4.3 Grout hardening / Early age deformation
• Wave limits during hardening critical
• Initial wave limit: 1,6 m Hs => DTOW has taken action by own 3rd party calculations => 3 m Hs limit for the grout itself
• Remainig limiting factor: levelling tools
� Improve by smart engineering: Stability calculations and devices to stabilize TP temporary.
Confidentiality - None (C1) - Olaf Beeg Package Manager Civil Works DanTysk
. Kieler Branchenfokus Windindustrie | 2015.02.03
Confidentiality -
21 |
5) DanTysk – Foundations Installation Noise mitigation
Confidentiality - None (C1) - Olaf Beeg Package Manager Civil Works DanTysk
. Kieler Branchenfokus Windindustrie | 2015.02.03
Confidentiality -
22 |
5) DanTysk – Foundations Installation Noise mitigation
BBC DBBC DBBC
+ linear BC
TBBC
+ linear BC
DBBC - DFI
+ linear BC
DBBC + BBC
Confidentiality - None (C1) - Olaf Beeg Package Manager Civil Works DanTysk
. Kieler Branchenfokus Windindustrie | 2015.02.03
Confidentiality -
23 |
5) DanTysk – Foundations Installation Noise mitigation
High effort during the MP installation phase led to increased noise mitigation
Confidentiality - None (C1) - Olaf Beeg Package Manager Civil Works DanTysk
. Kieler Branchenfokus Windindustrie | 2015.02.03
Confidentiality -
24 |
5) DanTysk – Foundations Installation Noise mitigation
• BBC, DBBC, TBBC, DBBC + BBC
• Double-end feed-in (+ extra vessel)
• Closing holes
• Nozzle tests
• Re-drilling holes
• Airflow-meters
• Compressor tests
• Reduced piling energy
• Manometer tests
• Hydrosound + C-POD measurements
• Reference measurements
• Extra hydrosound measurements
Total costs 20 mio EUR
. Kieler Branchenfokus Windindustrie | 2015.02.03
Thanks for your attention!