Offshore Wind Energy in Germany: System Benefits and Cost ...
Transcript of Offshore Wind Energy in Germany: System Benefits and Cost ...
Offshore Wind Energy in Germany:
System Benefits and
Cost Reduction Potentials
Presentation of study results
from prognos/fichtner and Fraunhofer-IWES
DFBEE-WAB; Offshore-Konferenz, 20 Jan. 2014 Bremerhaven
Andreas WAGNER Stiftung OFFSHORE-WINDENERGIE German Offshore Wind Energy Foundation
2
I. German Offshore Wind Energy Foundation
o Independent, non-partisan institution to support the development of
offshore wind energy, founded in 2005
o Platform for offshore wind (and maritime) industry, for policy-makers
and research-oriented stakeholders
o Board of Trustees - key industry & policy stakeholders
o PR and public acceptance activities,
o Policy initiatives & studies
• OffWEA project
Consulting and support for the federal government in
realising and advancing the German offshore wind energy strategy
• WINDSPEED
• SEANERGY 2020
• Interreg Projects:
4POWER, South Baltic OFF.E.R.
I. The OffWEA Project
Consulting and support for the federal government in realising and
advancing the German offshore wind energy strategy.
The German Offshore Wind Energy Foundation and its project partners
on behalf of the Federal Ministry for the Environment
Project duration: 2011 - 2014
Information Platform
www.offshore-windenergie.net
Incl. calculation tool for offshore LCOE
http://www.offshore-windenergie.net/wirtschaft/stromgestehungskosten
3 © SOW E.ON Netz D. Gehring © SOW E.ON Netz D. Gehring © SOW E.ON Netz D. Gehring
II. Spatial Planning and Permitting for
Offshore Wind Farms in Germany (EEZ)
III. Status Quo Offshore Wind Licensing
95 applications for offshore wind farms in German EEZ (78 in North Sea), 33 projects licensed (incl. 3 prototype turbines) – Total capacity 8-10 GW
North Sea > 80 % of projects, Baltic Sea < 20 %
II. Status Quo Offshore Wind Construction
III. Offshore grid connection projects –
German North Sea
7
Riffgat
KS Diele
KS Dörpen West
UW Emden Borssum
BorWin2 BorWin1 BorWin4
HelWin1
HelWin2
DolWin2 DolWin1 DolWin3
alpha ventus
BorWin3
UW Inhausen
Nordergründe
KS Büttel
KS Emden/Ost
UW Hagermarsch
SylWin1
Project Capacity
(MW) Year of
operation
In operation
alpha ventus 60 2009
BorWin 1 400 2010
Riffgat (delayed by > 6 months) 108 Feb. 2014
Under construction/ awarded
BorWin2 800 2015
DolWin1 800 2014
DolWin2 900 2015
HelWin1 576 2014
HelWin2 690 2015
SylWin1 864 2014
Nordergründe 111 2015
DolWin3 900 2018
Ʃ built / awarded 6.209
In tender phase
BorWin3, BorWin4 1.800 ???
To be tendered until 2023 according to O-NEP2013
6 DC-connections 5.400 Source: TenneT, 2013, updates SOW 2014
Initial Offshore Grid Structure HVDC cable routes & platforms
8
IV. Study on cost reduction potentials of
offshore wind energy in Germany
Partners –
Commissioning organisations and companies
Published August 2013
9
IV. Study assumptions: 2 offshore wind scenarios at 3 different sites (North Sea)
10
Economies of scale - increasing competiton lead to higher cost reduction
potentials in scenario 2
IV. Projection of levellised cost of energy (LCOE) in €cent/kWh (real terms, example of site B)
11
IV. LCOE < 10 ct/kWh by 2023
On average, 31 % cost reduction (Scenario 1) and 39 % (Scenario 2)
12
Recommendations - Policy and Regulatory Environment
Stable legal and political framework conditions
Define standards for components and for grid connection (platforms)
Simplify certification and permitting criteria
Recommendations for Industry towards techology innovation:
Optimise plant technologies towards maximum energy yield/operational hours
Optimisation of existing support structures and development of new ones
Improve installation logistics
Intensify R&D efforts
Recommendations for
Industry stakeholders
to improve efficiency Development of joint installation
and O&M concepts
Intensified efforts for serial &
automated production
IV. Realising cost reduction potentials requires active commitment and participation of all stakeholders
13
IV. Long lead times for OWF development
4-6 Years
1-2 Years
2-4 Years
20 Years 5 Years
1-2 Years
Project
development
Financial
Negotiations
Construction Operation Phase Extension
of operation
Decommissi
oning
Total project lifetime 27-37 years
FID
Commissioning
Construction Permit
© Prognos/Fichtner, 2013
Idealized (!) Project Schedule
Stable, long-term reliable political framework essential!!!
1. Energiewende requires 800 TWh
from wind and solar (by 2050) –
can only be realized with large
offshore wind capacities!
2. Offshore wind leads to reduced cost
for flexibility measures – lowest
cost option by 2050
3. Offshore wind has considerable
power plant characteristics –
important for security of supply
(provision of balancing power, high
schedule reliability, etc.)
4. Stable, continuous expansion of
offshore wind capacities required to
harvest energy system benefits and
cost reduction potentials
Energy System Benefits of Offshore Wind
Key assumptions/results
14
Study launched in Nov. 2013,
(EWEA Offshore 2013)
Primary Energy Consumption 2050
80 % RE,
20 % fossil fuels
Electricity Production in 2050
Sharp increase due to higher shares
of CHP, e-mobility, Power to heat &
Power to gas.
95 % from RE
Fossil fuels mainly for balancing
requirements
Energy Mix Transformation in Germany
2011-2050
15 © Fraunhofer-IWES, 2013
RE Potential (Wind, PV) and its limitations
Generation Mix assumptions
Scenario input -
optimum distribution of wind/PV
Scenario Assumptions - Capacity (GW) and Electricity
Production (TWH) Optimized Onshore PV Growth
Growth Scen. Growth Scen. Scenario
16
Offshore wind e. share (%),
related to total wind e. production
Win
d (
on
- a
nd
off
sh
ore
) sh
are
(%
), r
ela
ted
to
FE
E (
win
d,
PV
co
mb
ine
d)
© Fraunhofer-IWES, 2013
Scenario Results Overview of annual flexibility costs and LCOE (2050) in the scenarios
17
Optimized Growth Scenario:
€ 1-6.2 bn total cost savings/year
Optimized Growth Scenario:
€ 2.9 – 5.6 bn flexibility cost savings/year
Power Plant Characteristics - Offshore wind:
Steady electricity production/high availability
VI. Legal Framework for Offshore Wind Energy The Renewable Energy Act - EEG
Support for renewable energy since 2000 – EEG (RE Act) - specifies remuneration,
technology differentiation Issues in the past for offshore wind (prior to 2009)
No investments due to insufficient remuneration for offshore wind energy (9,1 ct/kWh)
EEG of 2008 (entered into force on 1st Jan. 2009)
Increase of initial Feed-in-Tariff (FiT) to 13.0 ct/kWh,
plus starter bonus of 2 ct, granted for 12 years
after commissionig (if commissioning before 1 January 2016)
EEG of 2011(entered into force on 1st Jan. 2012)
Compressed FiT:
Option to claim an increased initial rate of 19 ct/kWh –
only granted for 8 years after commissioning,
afterwards FiT drops to 3.5 ct/kWh
Important boost for investment decisions
New issues since 2013 – Federal elections Sep. 2013
“Electricity price brake” (Strompreisbremse) – public debate
Currently, proposals on EEG (RE Act) reform until summer 2014 –
2-year-extension of compressed FiT proposed
19
VI. Offshore Wind Energy in Germany –
An illustration of initial positive results
Positive operational results: - alpha ventus: > 4.450 full load hours in 2011 (267 GWh) 15 % above expectations, - Baltic I – similar results; turbine availability 98 %
Important contribution to energy system reliability!
1 billion Euro already invested along the German coast - Port infrastructure, production facilities (offshore turbines/components), construction vessels, (converter) platforms etc. Vast opportunities for maritime industries!
10 billion Euro investment for Offshore Wind Farms 8 OWP under construction by end of 2013
1/3 cost reduction potential by 2023 – provided a steady project pipeline can be triggered by legal framework
18,000 jobs created by 2012 (98,000 jobs in onshore wind) Need for new and adjusted professional and vocational training
and university education courses!
20
THANK YOU!
Andreas Wagner, managing director
Berlin Office Schiffbauerdamm 19, 10117 Berlin
Phone: +49-30-27595-141
Fax: +49-30-27595142
Varel Office
Oldenburger Str. 65, 26316 Varel
Phone: +49-4451-9515-161
Fax: +49-4451-9515-249
Studies available at:
www.offshore-stiftung.de www.offshore-windenergie.net