Budgeting Sustainably for PPPs and Traditional Capital Projects in the Medium and Long-term
Isabel Rial
Fiscal Affairs Department, IMF [email protected]
OECD Annual Meeting for PPP Officials, February 17, 2014
The views expressed in this presentation are those of the author and do not necessarily represent those of the IMF or IMF policy.
Outline
I. Why is budgeting for public investment and PPPs from a long-term perspective important?
II. What should we aim at?
III. What can be done?
IV. Final remarks
2
I. Why is budgeting important?
Why is budgeting for public investment and PPPs from a long-term perspective important?
Two main reasons: – Efficiency of public spending
• Adequate budgeting is key to ensure efficiency both in traditional public investment and PPPs
– Fiscal risk management • Avoid “fiscal surprises”
3
I. Why is budgeting important? a. Efficiency of public spending
• Limited fiscal space in advanced economies led to a declining trend of public investment and capital stock.
• This trend may hinder medium- and long-term growth and endanger the sustainability of required fiscal consolidation.
4
0
1
2
3
4
5
6
7
8
9
1970-90 1990-2000 2000-08 2009-12
Advanced economiesEmerging market economiesLow-income countries
General Government Investment(Percent of GDP)
Sources: Penn World Tables (2012); OECD; and IMF staff estimates.
Source: WEO database, October 2013.
7174798285868990
99100103
117124127
157238
0 50 100 150 200 250
NetherlandsAustria
HungaryGermany
CanadaSpain
United KingdomFranceIceland
BelgiumUnited States
IrelandPortugal
ItalyGreece
Japan
Debt-to-GDP Ratio(2012, in percent of GDP)
I. Why is budgeting important? a. Efficiency of public spending
• Higher public spending does not necessarily translates fully into productive capital assets [Gupta and others (2013)]
• There is room to stabilize public capital stock by improving the efficiency of public investment – The Public Investment Management Index (PIMI), the core of the
efficiency-adjustment, shows that project selection and budgeting are crucial to ensure efficiency
• Eliminating inefficiencies in public investment processes can go a long way in meeting the infrastructure gap worldwide.
5
I. Why is budgeting important? a. Efficiency of public spending
• Yet, addressing inefficiencies may not be enough to stabilize public capital stock…..
• Governments could rely further on PPPs…
• But, efficiency gains can only be achieved if they are pursued for “good reasons”, where PPP projects compete for budget resources on a level playing field.
6
I. Why is budgeting important? b. Fiscal risk management
• During the global financial crisis, PPPs have been a significant source of unexpected increases in governments’ debt and contingent liabilities.
• PPP "surprises" in countries where PPP stock magnitude was largest revealed large hidden risks (e.g., Portugal)
• Given high levels of public debt in most AE, caution is warranted to avoid choosing PPPs for the wrong reasons….
• Adequate budgeting plays a critical role in managing fiscal risks from public capital, including PPPs.
7
*Only includes Central Government SOE debt pre 2007
40
60
80
100
120
40
60
80
100
120
1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011
SOE & PPP reclassifications
Non-SOE & PPP General Government debt
SOE & PPP debt outside the General Government
General Government gross debt
Arrears
I. Why is budgeting important? b. Fiscal risk management
Example: General Government Debt in Portugal* (percent of GDP, 1997-2011)
Sources of Unexpected Increase in General Government Debt (percent of GDP, 2007-2010)
FRA DEU NLD ESP PRT GBR USA GRC IRL ISL AVE*
Underlying fiscal position 1.7 3.2 -2.4 1.8 11.3 3.7 8.1 16.3 1.3 10.9 6.0
Revisions to 2007 deficit & debt 1.7 1.8 -0.9 -0.1 0.1 1.5 7.1 2.5 1.6 4.0 4.7
Changes to government boundary -0.7 1.4 -0.2 0.6 9.4 1.9 0.9 11.2 -0.1 2.5 1.1
Cash-accrual adjustments 0.7 0.0 -1.3 1.3 1.7 0.3 0.0 2.6 -0.2 4.5 0.2
Exogenous shocks 8.4 12.8 14.2 15.4 8.1 17.0 6.3 40.0 60.2 39.5 9.8
Macroeconomic shocks 8.3 4.7 5.2 13.0 4.4 8.9 3.8 38.4 35.7 -3.3 6.0
Financial sector interventions 0.0 8.1 9.0 2.5 3.6 8.1 2.5 1.6 24.5 42.8 3.8
Policy changes 2.3 3.8 1.9 4.9 4.7 1.1 6.4 -8.0 -9.9 -4.3 4.7
Other factors 2.1 -0.3 6.5 1.9 3.7 6.2 8.3 -6.7 7.5 21.6 5.9
Total Unexpected Increase in Debt 14.4 19.5 20.2 24.0 27.8 28.0 29.1 41.7 59.1 67.7 26.4
* GDP-weighted average 9
Unreported Deficits
SoEs & PPPs
Arrears
Macroeconomic Risks
Contingent Liabilities
Stimulus / Consolidation
Issues Revealed by the Crisis
I. Why is budgeting important? b. Fiscal risk management
• Budget investment decisions should be determined primarily by
policy priorities, cost-benefits analysis, and long-term affordability, and not by the timing of cash flows
• Avoid the “accounting bias” towards PPPs
• All investment projects should be treated equally, irrespective of the ultimate financing method
10
II. What should we aim at?
11
• Ensure that full life-costs of a project are taken into account at project approval
– While this is relevant for all investment projects, whether they are implemented as PPP or as traditional investment…
– …it is particularly a concern for PPPs due to long construction and contract periods
II. What should we aim at?
What can governments do to ensure that long-term budget affordability and not the timing of the cash flows drives investment decisions?
At a budgeting level, some options include:
• Up-front budget recognition for all financial commitments – Medium-term budget framework where PPPs are treated
as publicly financed projects – Commitment budgeting
• Impose budgetary limits
12
III. What can be done?
• Medium-term budget framework (MTBF) where PPPs are
treated as publicly financed projects – Can be implemented in both accrual and cash budgeting process – Requires budget authorization for the acquisition of investment
assets created by PPPs during the construction period – Yet, if the construction of an asset stretches beyond the time
horizon covered by the MTBF…. – …. it does not ensure that the full financial implications of the
project are considered when the investment decision is taken
13
III. What can be done?
• Commitment appropriation
– Two kinds of authorizations: • Spending appropriation: authorizes spending in current year • Commitment appropriation: authorizes to commit public resources
for future years – Addresses the affordability issue
• Draws attention to the full costs of all investment projects • Government requires budget authorization before entering any
long-term contract • Parliament is informed and could limit fiscal implications of
investment decisions – Helps reducing the bias in favor of PPPs, albeit not totally
14
III. What can be done?
• Budgetary limits
– Limits on long-term commitments (direct liabilities) • If up-front budget recognition is not possible, it could be
compensated by budgetary limits on the level of PPP commitments
• Limits could be measured on the basis of total net present value of long-term costs and/or total annual payments for projects already approved
– Limits on total guarantees (contingent liabilities) • Should be estimated at the time that commitments are authorized
and monitored during the whole project life-cycle
15
III. What can be done?
• To avoid efficiency losses, and “fiscal surprises” PPPs and
traditional public investment should be aligned in a medium to long-term planning framework
• Governments have sought to compensate for weaknesses of budgetary controls and accountability in investment projects in various ways (e.g., improving accounting practices, disseminating better information, etc.)
• Yet, stronger budgetary planning, selection, and approval procedures are necessary to support high quality public spending while ensuring fiscal sustainability
16
IV. Final remarks