October 3-4 2017 Tasiastanalyst & investor tour: Developing a … · 2017-10-03 · 1 1 KINROSS...

45
KINROSS GOLD CORPORATION Tasiast analyst & investor tour: Developing a world-class mine October 3-4 2017

Transcript of October 3-4 2017 Tasiastanalyst & investor tour: Developing a … · 2017-10-03 · 1 1 KINROSS...

1www.kinross.com

1

KINROSS GOLD CORPORATIONTasiast analyst & investor tour: Developing a world-class mine

October 3-4

2017

2www.kinross.com

2

CAUTIONARY STATEMENT ON FORWARD-LOOKING INFORMATION

All statements, other than statements of historical fact, contained or incorporated by reference in or made in giving this presentation and responses toquestions, including but not limited to any information as to the future performance of Kinross, constitute “forward looking statements” within the meaning ofapplicable securities laws, including the provisions of the Securities Act (Ontario) and the provisions for “safe harbor” under the United States PrivateSecurities Litigation Reform Act of 1995 and are based on expectations, estimates and projections as of the date of this presentation. Forward-lookingstatements contained in this presentation include those statements on slides with, and statements made under, the headings “Tasiast Mill Expansion”,“Developing a World-Class Mine”, and include, without limitation, statements with respect to mine life extensions, costs and timing of development activities,future production, production costs of sales, all-in sustaining cost and capital expenditures, continuous improvement and other cost savings opportunities, aswell as references to other possible events including, without limitation, possible events; opportunities; statements with respect to possible events oropportunities; estimates (including, without limitation, gold / mineral resources, gold / mineral reserves and mine life) and the realization of such estimates;future development, mining activities, production and growth, including but not limited to cost and timing; success of exploration or development ofoperations; the results of any studies including, without limitation, feasibility studies; the future price of gold and silver; currency fluctuations; expected capitalrequirements; government regulation; and environmental risks. The words “assumption”, “budget”, “encouraging”, “enhancing”, “estimate”, “expect”,“feasibility”, “focus”, “forward”, “future”, “goal”, “indicate”, “on track”, “opportunity”, “phased”, “plan”, “positive”, “potential”, “prospective”, “progressing”,“project”, “risk”, or “study”, or variations of or similar such words and phrases or statements that certain actions, events or results may, can, could, would,should, might, indicates, or will be taken, and similar expressions identify forward looking statements. Forward-looking statements are necessarily basedupon a number of estimates and assumptions that, while considered reasonable by Kinross as of the date of such statements, are inherently subject tosignificant business, economic and competitive uncertainties and contingencies. Many of these uncertainties and contingencies can affect, and could cause,Kinross’ actual results to differ materially from those expressed or implied in any forward looking statements made by, or on behalf of, Kinross. Statementsrepresenting management’s financial and other outlook have been prepared solely for purposes of expressing their current views regarding the Company’sfinancial and other outlook and may not be appropriate for any other purpose. There can be no assurance that forward looking statements will prove to beaccurate, as actual results and future events could differ materially from those anticipated in such statements. All of the forward looking statements made inthis presentation are qualified by these cautionary statements, and those made in our filings with the securities regulators of Canada and the U.S., includingbut not limited to those cautionary statements made in the “Risk Factors” section of our most recently filed Annual Information Form, the “Risk Analysis”section of our FYE 2016 and Q2 2017 Management’s Discussion and Analysis, and the “Cautionary Statement on Forward-Looking Information” in our newsrelease dated September 18, 2017, to which readers are referred and which are incorporated by reference in this presentation, all of which qualify any and allforward‐looking statements made in this presentation. These factors are not intended to represent a complete list of the factors that could affect Kinross.Kinross disclaims any intention or obligation to update or revise any forward‐looking statements or to explain any material difference between subsequentactual events and such forward‐looking statements, except to the extent required by applicable law.

Other information

Where we say "we", "us", "our", the "Company", or "Kinross" in this presentation, we mean Kinross Gold Corporation and/or one or more or all of itssubsidiaries, as may be applicable.

The technical information about the Company’s mineral properties contained in this presentation has been prepared under the supervision of Mr. John Sims,an officer of the Company who is a “qualified person” within the meaning of National Instrument 43-101.

3www.kinross.com

3WELCOME TO THE TASIAST MINE TOURTom Elliott – Senior Vice-President, Investor Relations & Corporate Development 3

4www.kinross.com

4

Presenters and Q&A Panel

Mike Sylvestre Regional Vice-President, Africa

Guy Bourassa Vice-President and Project Director, Tasiast Project

Paul Tomory Chief Technical Officer

John Sims Vice-President, Resource Geology & Brownfields Exploration (Q.P.)

Tom Elliott Senior Vice-President, Investor Relations & Corporate Development

INTRODUCTIONS & AGENDA4

5www.kinross.com

5

• Highly prospective district with significant exploration potential World-class orebody: 8.0M oz. of proven and

probable reserves, 3.1M oz. of measured & indicated gold resources and 0.4M oz. of inferred resource estimates(i)

Accelerating drill program following encouraging results & initiating Tasiast Sud pre-feasibility study

• Improvements at the existing operation enhancing future value Achieving reductions in mining and processing

costs Expect positive trend to continue

• Expansion projects expected to transform Tasiast into a large, low-cost producer Excellent progress on Phase One Proceeding with Phase Two

DEVELOPING A WORLD-CLASS MINE

TASIAST HIGHLIGHTS

(i) As at December 31, 2016. Please refer to Kinross’ Annual Mineral Reserve and Mineral Resource Statement, available on our website at www.Kinross.com.

6www.kinross.com

6

DEVELOPING A WORLD-CLASS MINE

TASIAST: HISTORICAL CONTEXT

Focus has been to right-size the processing capacity to capture the full value and potential of Tasiast’s large mineral resource estimate

2014 2015 2016 2017 2018 2019 2020

Feasibility Study Results38k t/d scenario

Capex estimate: $1.6B

Initiated studies on two-phased expansion Financially disciplined approach to expansion

using existing infrastructure

Two-phased expansion study results

Phase One approvedCapex estimate: $300MPhase Two proceeds to

feasibility studyCapex estimate: $620M

Phase Two feasibility study results

Phase Two approvedRevised capex estimate: $590M

Phase One expected to reach

commercial production in

Q2 2018

Phase Twoexpected to reach

commercial production in

Q3 2020

* Capital estimates on this slide do not include estimated capitalized stripping

7www.kinross.com

7

map

MAURITANIA: LOCATION7

Mauritania

Canary Islands

Algeria

Mali

Western Sahara

Morocco

Senegal

Tasiast

Nouakchott(capital)

8www.kinross.com

8GEOLOGY & EXPLORATIONJohn Sims - Vice-President, Resource Geology & Brownfields Exploration (Q.P.) 8

9www.kinross.com

9

• Aouéouat greenstone belt hosts all of the known Tasiast deposits and most of current exploration prospects

80 km x 8 km

312 km2 mining lease

3,118 km2 exploration licences

• Aouéouat belt shares similarities with other Late Archaean terranes, such as:

Yilgarn in Australia

Abitibi in Canada

GEOLOGY & EXPLORATION

GEOLOGY OVERVIEW

Tasiast Geology

Tasiast mine

Tasiast Sud

10 km5 km0 km 15 km 20 km

10www.kinross.com

10

GEOLOGY & EXPLORATION

TASIAST CROSS-SECTION

Felsite SedimentsBIF

Lithology

Diorite (GDI)

Dyke

Plan view

A’

Looking North - West Branch AA’ cross-section (12.5m window)

Resource pit outline

Reserve pit outlineSeptember 2017

pit outline

A

A’A

11www.kinross.com

11

GEOLOGY & EXPLORATION

TASIAST SUDEncouraging results from C6.13 and C6.15 in the Tasiast Sud Area

C6.13

C6.15

Tamaya

Sadraya

C6.14

• Tamaya: approximately 335k oz. of measured & indicated gold resources(i) defined in 2015

• Recent drilling in the Tasiast Sud area has focused on the C6.13 and C6.15 deposits in the Tasiast Sudarea

Located ~10 km south of the Tasiast mine and west of the Tamaya deposit

• Completed 13,000 metres of drilling in H1 2017

Majority of material at both targets is within a banded iron formation (similar to Piment)

C6.13 defined over approximately 2 km of strike; open to the north and south

C6.15 defined over 3 km of strike

(i) Please refer to Kinross’ Annual Mineral Reserve and Mineral Resource Statement, available on our website at www.Kinross.com, and associated assumptions.

12www.kinross.com

12

GEOLOGY & EXPLORATION

TASIAST SUD: 2017/2018 DRILL PROGRAM

1km

C6.13

C6.15

Tamaya

Sadraya

C6.14

N

Mafic DykeIron FormationSiltstoneGreywackeMica-SchistFelsiteAmphiboliteDioriteTalc Trem SchistGranodiorite

LEGEND

• Following positive results in H1 2017, accelerated drill program underway in H2 2017

Focus is on definition drilling and resource expansion

Goal of potential mineral resource additions at year-end

• Initiated a pre-feasibility study for a Tasiast Suddump leach operation that combines material from Tamaya, C6.13 and C6.15

High grade CIL material expected to be transported to Tasiast 30,000 t/d mill

LegendExplorationResource definition

AB

C

13www.kinross.com

13

GEOLOGY & EXPLORATION

CROSS SECTIONS: C6.13 & C6.15C6.13 (A)

C6.15 (C) • C6.13 and C6.15 geology composed of: Sedimentary rocks Felsic rocks Muscovite rich mica schist Iron-Formation rock units

• Mineralization is located at the flanks of the fold exclusively within banded iron formation units and at their contacts with mica schist (Greywacke with high muscovite alteration)

C6.13 (B)

TOFR

100m

Mica schist

12

4

5

71234567

15m @ 4.64 g/t Au17m @ 11.42 g/t Au12m @ 1.66 g/t Au8m @ 1.05 g/t Au33m @ 0.41 g/t Au15m @ 1.09 g/t Au8m @ 0.69 g/t Au

3 6 Iron Formation

NW SE

Greywacke

Mica schist

Iron Formation

1234567

7m @ 0.36 g/t Au13m @ 1.04 g/t Au8m @ 0.66 g/t Au9m @ 0.42 g/t Au9m @ 0.9 g/t Au3m @ 0.38 g/t Au6m @ 0.88 g/t Au2m @ 1.19 g/t Au8

8

TOFRSiltstone

12

4 53

76

SW NE

100m

4

6

7

8

7m @ 2.68g/t Au9m @ 2.15 g/t Au15m @ 2.14 g/t Au8m @ 3.03 g/t Au5m @ 2.98 g/t Au9m @ 4.74 g/t Au2m @1.25 g/t Au7m @2.34 g/t Au4m @ 2.32 g/t Au

123456789

12

3

4 5 67

89

100m

NW SE

Iron Formation

TOFR

Mica schist

14www.kinross.com

14

GEOLOGY & EXPLORATION

DRILLING STATISTICS

2013 2014 2015 2016 H1 2017 Planned for H2 2017

Planned for 2018

C6.13 4,481 3,070 75 2,332 7,947 13,000

C6.14 3,500 3,700

C6.15 5,606 2,423 4,479 15,000 37,800

C6.16 2,109 3,801 75 640 3,600

Sadraya 1,999 2,687 9,400

Tamaya 6,852 7,358 14,147 774

Total 22,548 18,651 14,297 5,659 13,200 28,000 54,500

Tasiast Sud area has been a large focus of exploration and resource definition activities

Tasiast Sud drill hole data by year (metres)

15www.kinross.com

15CURRENT OPERATIONMike Sylvestre – Regional Vice-President, Africa 15

16www.kinross.com

16TASIAST SITE LAYOUT

MINE TOUR AGENDA

Camp

West Branch Pit

Airstrip

Power Plant

Phase One tailings facility

Current tailings facility ADR plant

Dump leach

Piment pits

New crusher

New stockpile

New SAG mill

Phase One and Two expansions

Truck shop

1 2

4

3

5

N

67

8

910

17www.kinross.com

17

CURRENT OPERATION

OVERVIEWMINING

• Conventional open-pit

• Ore currently sourced from two pits:

Piment

West Branch

• Average mining rate: ~200k t/d

CURRENT FLEET

• 7 CAT 6060 shovels

• 42 CAT 793D haul trucks

PROCESSING

• Existing CIL: averaging 8,500 t/d

• Dump leach

18www.kinross.com

18

• Conducted comprehensive reviews of crushing and grinding circuit to identify opportunities for improvement

• Completed upgrades to the crushing circuit to provide smaller product size with higher fine material content

• Increased availability of crushing and conveying circuit through improved maintenance practices

• Increased availability of milling circuit with implementation of a new reline/shutdown strategy and improved maintenance practices Together, these improvements have resulted in increased throughput:

Averaging above 8,500 t/d (20% increase)

Strong mill throughput a result of continuous improvement efforts

CURRENT OPERATION

IMPROVED MILL PERFORMANCE

19www.kinross.com

19

 3,000

 5,000

 7,000

 9,000

Aug‐13 Nov‐13 Feb‐14 May‐14 Aug‐14 Nov‐14 Feb‐15 May‐15 Aug‐15 Nov‐15 Feb‐16 May‐16 Aug‐16 Nov‐16 Feb‐17 May‐17 Aug‐17

Mill now averages ~8,500 t/d and can reach as high as 9,000 t/d

Average from August 2013 to October 2015

Average from November 2015 to March 2017

~20% increase

May, June, July and August 2016 throughput impacted by work stoppage – values represent average daily during operating days.

CURRENT OPERATION

SIGNIFICANT OPERATIONAL IMPROVEMENTS

May-August 2016 impacted by work

stoppage

20www.kinross.com

20

CURRENT OPERATION

PRODUCTIVITY IMPROVEMENTS

Focus on productivity has resulted in lower costs

0.61 0.56

0.550.39

0.36

0.31

0.53

0.44

0.13

0.27

$2.18

$1.96

2015 H1 2017

Contractors & Admin• Outsourced some mining services

Labour• Increased labour productivity and reduced headcount

Drill / Blast Consumables• Optimized drill patterns for increased blasting

efficiencies

Other Fleet• Improved mobile maintenance practices resulting in

better equipment performance and lower costs• Improved useful life, leading to decreased maintenance

suppliesFleet Consumables• Increase in useful tire life, and lower fuel costs

Mining Cost ($/t mined)

21www.kinross.com

21

Study estimates(ii)Study estimates(ii)

$25.46

$22.84 $22.24

$15.16 $14.40

2015 2016 H1 2017 PFS FS

$2.18$2.05 $1.96

$2.37$2.25

2015 2016 H1 2017 PFS FS

CURRENT OPERATION

OPERATING EFFICIENCIES ENHANCING PROJECT

Recent operating and processing enhancements have positively benefitted both Phase One and Phase Two expansion projects

• Recent performance outperforming study estimates

• Further reduction in processing costs expected as Phase Two increases throughput to 30,000 t/d

Mining costs($ per tonne mined)

Processing costs($ per tonne milled)(i)

(i) Excludes processing costs associated with the dump leach.(ii) 30k t/d scenario. Estimated average for the period 2020-2030.

22www.kinross.com

22

Government has expressed its support for the expansion project:

"We support the Kinross decision toproceed with the Tasiast Phase Twoexpansion and the additional investmentand long-term benefits the project willbring to the country and our people."

Mohamed Abdel VetahMinister of Petroleum, Energy & Mines

CURRENT OPERATION

MAURITANIA HIGHLIGHTS

• Democratic republic that gained independence in 1960

• Mining-friendly jurisdiction: Well-developed, competitive mining law Mining is a major export industry Companies operating in Mauritania include:

SNIM, First Quantum, Algold

• Major foreign companies include: BP, Total, Kosmos Energy, Tullow Oil, Société

Générale Recent increase in oil and gas investment

• Multilateral agencies such as IMF and World Bank active in the country

• Kinross continues to maintain good relations with the government

Government royalty 3%

Income tax rate 25%

Mining Convention: Royalty & Income Tax

Kinross has successfully operated in Mauritania since 2010

23www.kinross.com

23

CURRENT OPERATION

CORPORATE RESPONSIBILITY AT TASIAST

Engaging with stakeholders

• Established stakeholder engagement programs consistent with Kinross standards and international best practice

• Integration of CR considerations in key operational functions

Competency-based hiring

Contractor Compliance Bureau

Local Business policy in Supply Chain Management

• Integrated good international ESIA practice in design of the expansion project

IFC Performance Standards

Cyanide Code certification

24www.kinross.com

24

• 90% of TMLSA employees are Mauritanians

• Investing in training and development programs. Since 2010, we have invested:

~$10 million to support local capacity building

~$20 million in training for our local employees

• One of the best safety performance records among Kinross sites

Building a workforce of Mauritanian nationals

CURRENT OPERATION

90% OF EMPLOYEES ARE MAURITANIAN

2016 Statistics(i)

90%of workforce composed of Mauritanian nationals

$175M of spending with in-country suppliers

$52M of in-country wages

(i) Source: Kinross 2016 Corporate Responsibility Data Supplement and Communication on Progress

25www.kinross.com

25

Employees

• Signed a new 3-year collective labour agreement with unionized employees in October 2016

• Targeting expats with strong background in developing national personnel

• Emphasizing a culture of safety and environmental compliance

Mauritanization Plan• Reached a mutually-acceptable

Mauritanization Plan to increase the number of local workers at Tasiast

Process is proceeding on schedule and achieving positive outcomes

• Identifying internal strength: implementing accelerated development plans for high potential employees

• Recruiting diaspora talent with strong and relevant professional experience

• Adapting Kinross training program to individual development needs

CURRENT OPERATION

BUILDING POSITIVE EMPLOYEE RELATIONSHIPS

26www.kinross.com

26TASIAST MILL EXPANSION: PHASE ONEGuy Bourassa - Vice-President & Project Director, Tasiast Project 26

27www.kinross.com

27

TASIAST EXPANSION PROJECT

PHASE ONE: EXPANSION TO 12,000 T/D

PHASE ONE FLOW SHEET

• Leverages existing mill infrastructure to increase throughput to 12,000 t/d from 8,000 t/d

• Includes installation of an oversized 40’ SAG mill and gyratory crusher

• Enhances processing of the harder, higher grade West Branch ore

Gyratory crusher

Ore stockpile

Oversized SAG mill

Existing ball mills

Leaching Refining

New Existing

28www.kinross.com

28

TASIAST MILL EXPANSION

PHASE ONE PROGRESSING WELL

• Mechanical installation progressing well: SAG mill shell fully in place Installation of gearless motor drive progressing Apron feeders for crusher & reclaim tunnel now

in place Conveyor installation progressing rapidly Installation of 3 new leach tanks almost complete

• Early commissioning progressing as planned: Oxygen plant fully commissioned and supporting

production New tailings facility expected to be operational

shortly• On schedule and on budget for full commercial

production in Q2 2018

Phase One construction approximately 70% complete

Primary Crusher

29www.kinross.com

29SAG MILL

PHASE ONE PROGRESSING WELL

30www.kinross.com

30CYCLONE TOWERS

PHASE ONE PROGRESSING WELL

31www.kinross.com

31LEACH TANKS

PHASE ONE PROGRESSING WELL

32www.kinross.com

32NEW TAILINGS FACILITY

PHASE ONE PROGRESSING WELL

33www.kinross.com

33TASIAST MILL EXPANSION: PHASE TWOPaul Tomory – Chief Technical Officer 33

34www.kinross.com

34

• Installation of an incremental 18,000 t/d of throughput capacity for a total combined capacity of 30,000 t/d

• Project consists of: • Replacing two 14’ ball mills with a new, larger 27’ ball mill• Expansion of power generation capacity by 35 MW• Adding new leaching, thickening and refining capacity• Additions to mining fleet• Upgrades to water supply infrastructure

TASIAST EXPANSION PROJECT

PHASE TWO: EXPANSION TO 30,000 T/D

PHASE TWO FLOW SHEET

Gyratory crusher

Ore stockpile

SAG mill New, larger ball mill

Additional leaching capacity

Thickening

New Existing

35www.kinross.com

35

Phase Two expansion expected to transform Tasiast into a world-class mine with low costs and a long estimated mine life

TASIAST MILL EXPANSION

PHASE TWO FEASIBILITY STUDY RESULTS

Estimates Combined Phase One and Phase TwoAverage annual production (2020-2024) 812,000 ounces

Production cost of sales (2020-2024) $440 per ounce

All-in sustaining cost (2020-2024) $655 per ounce

Capitalized stripping (non-sustaining) (2016-H1 2020) $560 million

Mine life 2029

Net present value(i)(ii) $1.43 billion

Phase Two Stand-AloneInitial capital expenditures $590 million

Internal rate of return(i)(ii) 24%

Note: figures on this slide reflect a $1,200 per ounce gold price assumption.(i) January 1, 2018 forward(ii) After tax, 5% discount rate.

36www.kinross.com

36

TASIAST MILL EXPANSION

FEASIBILTY STUDY SHOWS IMPROVED ECONOMICS

Incremental IRR of 24% for the Phase Two stand-alone project

Improved economics are expected as a result of:

Lower estimated initial capital

• Initial capital estimate reduced to $590M

• Down from PFS estimate of $620M

Improved operating cost estimates

• Productivity improvements

• Lower mining and processing costs

• Better input costs

Mine plan optimization

• Higher estimated average annual production in the first 5 years

• Bringing forward production shortens mine life by 1 year Results in G&A and fixed

costs savings

37www.kinross.com

37

TASIAST MILL EXPANSION

WEST BRANCH PLANNED MINING SEQUENCE

2018

2026

2019

2019

2018

20202020

2020

2019

20212021

2022

2023

2024

2024

2027

2025

2023

A’WB3 WB4 WB5

0 – 0.4

0.4 – 1.1

1.1 – 1.5

1.5 – 2

> 2

A’

PLAN VIEW

Au Grade (g/t)

Looking North

N

A

100 m

A

38www.kinross.com

38

TASIAST MILL EXPANSION

ADDITIONAL INFORMATION

‘20 ‘21 ‘22 ‘23 ‘24 ‘25 ‘26 ‘27 ‘28 ‘29

Total mined(Mt) 98 93 82 90 75 56 47 30 7 0

Strip ratio (Waste:Ore) 12.6 15.5 4.5 4.6 3.8 8.8 6.0 2.1 2.7 0.3

Grade processed(g/t) 2.1 1.5 2.9 3.0 3.0 1.4 1.9 2.0 0.9 0.8

Mill feed tonnesfrom stockpiles 4.4 5.3 - - - 5.2 4.4 1.8 9.0 9.9

Annual estimates

Life of mine estimatesLife of Mine Average

Sustaining capital $65/year

G&A $65/year

Recovery 93%

39www.kinross.com

39

TASIAST MILL EXPANSION

ANNUAL PRODUCTION ESTIMATESProduction expected to average 812,000 gold ounces over the first 5 years

(2020-2024)

Estim

ated

Pro

duct

ion

(thou

sand

oun

ces)

0

250

500

750

1,000

2016A 2017E 2018E 2019E 2020E 2021E 2022E 2023E 2024E 2025E 2026E 2027E 2028E 2029E

40www.kinross.com

40

TASIAST MILL EXPANSION

PHASE TWO CAPITAL ESTIMATEPhase Two initial capital cost expected to be $590 million

Estimated Initial Capital Cost

Estimate ($M)

Processing plant 137

Power supply 76

Water supply 50

Mining fleet 49

EPCM 27

Indirect, owner’s cost and taxes 120

Contingency 79

Miscellaneous 52

Total $590

Water Supply ($50M)• Raw water is currently supplied from brackish water

borefield located 64 km west of the mine

• Phase Two project includes upgrades to the water supply infrastructure:

New overland water pipeline

Pumping stations

Break tanks

Electrical infrastructure

• The new pipeline is expected to supply sufficient water for 30,000 t/d mill and continued dump leach

• Permit status: licensed to extract 30,000 m3/d from the bore fields through 2034

Power Supply ($76M)• Additional HFO fired power generation of ~60MW

41www.kinross.com

41

TASIAST MILL EXPANSION

ADVANCING PHASE TWO

• Project owner’s team established

• Finalizing commercial terms for EPCM package

• Currently advancing critical packages

• Initial construction expected to begin early 2018

Construction activities to ramp up following Phase One commissioning

Phase Two expansion expected to reach commercial production in Q3 2020

42www.kinross.com

42APPENDIXTASIAST PHASE TWO FEASIBILITY STUDY RESULTS 42

43www.kinross.com

43

Timeline Operational Metric Estimate

2020-2024(First 5 years of Phase Two

operation)

Total tonnes mined 438 millionStrip ratio 6.4Average CIL grade processed 2.5 grams per tonneAverage annual production 812,000 ouncesAverage mining cost $2.05 per tonneAverage processing cost $14.50 per tonneProduction cost of sales $440 per ounceAll-in sustaining cost $655 per ounce

2025-2029(Remaining life

of mine)

Total tonnes mined 141 million tonnesStrip ratio 4.8Average CIL grade processed 1.5 grams per tonneAverage annual production 457,000 ouncesAverage mining and re-handle cost $2.75 per tonneAverage processing cost $14.30 per tonneProduction cost of sales $680 per ounceAll-in sustaining cost $835 per ounce

2020-2029(Life of project)

Total tonnes mined 579 million tonnesStrip ratio 5.9Average CIL grade processed 2.0 grams per tonneAverage recovery 93%Average annual production 634,000 ouncesAverage mining cost $2.25 per tonneAverage processing cost $14.40 per tonneProduction cost of sales $530 per ounceAll-in sustaining cost $720 per ounce

TASIAST EXPANSION PROJECT

SUMMARY OF FEASIBILITY STUDY RESULTS

Estimated Initial Capital Cost

Operating Estimates (Phase One & Two combined)

Estimate ($ millions)

Processing plant 137

Power supply 76

Water supply 50

Mining fleet 49

EPCM 27

Indirect, owner’s cost and taxes 120

Contingency 79

Miscellaneous 52

Total $590

Standalone Phase Two Estimates

Estimate

Initial capital $590 million

Internal rate of return 24%

44www.kinross.com

44

GOLD PRICE SENSITIVITY ESTIMATES

TASIAST EXPANSION PROJECT

SENSITIVITIES

$1,100 $1,200 $1,300 $1,400IRR (Phase Two Standalone)(calculated January 1, 2018 forward)

19% 24% 28% 31%

NPV (Phase One and Two Combined)(after-tax, 5% discount; calculated January 1, 2018 forward)

$977M $1.43B $1.83B $2.22B

OIL PRICE SENSITIVITY ESTIMATES

$45/bbl $50/bbl $55/bbl $60/bbl $65/bbl

IRR (Phase Two Standalone)(calculated January 1, 2018 forward)

24.9% 24.6% 24.2% 23.9% 23.5%

NPV (Phase One and Two Combined)(after-tax, 5% discount; calculated January 1, 2018 forward)

$1.49B $1.46B $1.43B $1.39B $1.36B

45www.kinross.com

45

KINROSS GOLD CORPORATION 25 York Street, 17th Floor │Toronto, ON │ M5J 2V5www.kinross.com