October, 2009
Controls System
Kevin Brown/Brian Oerter
October, 2009
Internal Review
October, 2009
2
Controls Overview
• Power Supply Control• Network, Timing Links, & Console Equipment• Machine Protection• Instrumentation Support• Vacuum & Cryo Support• Access Controls• Costs Derived Primarily From Recent EBIS And ERL Projects
October, 2009
3
Power Supply Control Hardware
• Provide Control for 315 Power Supplies• 3 Nineteen Inch Racks• 6 VME Chassis With Processors, Memory, & Utility Modules• 35 PSCs (VME Based)• 2 Sixteen Port Digis• 6 Timing Boards (V202, VME Based)• 6 Fanout Boards (V194, VME Based)• 206 PSIs• Misc. Cables & Panels• 12 Beam Sync Trigger Modules (V124, VME Based)
October, 2009
4
Network, Link, & Console Hardware
• Upgrade Network Trunk• 1 Nineteen Inch Network Rack• 2 Fiber Terminal Boxes• 2 Network Switches• 8 Power Reset Boxes• 6 Fan Outs For Timing & Data Links• 4 Servers• 6 Work Stations• 1 Printer• 3 Tables• Misc. Cables & Panels
October, 2009
5
Machine Protection Hardware
• 3 National Instruments 8 Slot RIO (Reconfigurable I/O) Chassis• 3 RIO Power Supplies• 24 RIO I/O Modules• Misc. Cables
October, 2009
6
Instrumentation Support Hardware
• 9 VME Chassis With Processors, Memory, & Utility Modules• 2 Network Switches• 2 Sixteen Port Digis• 3 GPIB/Enet Interfaces• 6 Analog Input Boards (3122, VME Based)• 7 Motion Controllers (VX2, VME Based)• 8 Analog Output Boards (4140, VME Based)• 50 VMIC I/O Panels• 5 Timing Boards (V202, VME Based)• 39 Digital Output Boards (2170, VME Based)• 39 Digital Input Boards ( 1160, VME Based)• Misc. Cables• Includes Support For 2 Polarimeters
October, 2009
7
Vacuum & Cryo Support Hardware
• 1 VME Chassis With Processor, Memory, & Utility Module• 2 Network Switches• 1 Analog Input Boards (3122, VME Based)• 4 Motion Controllers (VX2, VME Based)• 1 Digital Output Boards (2170, VME Based)• 1 Digital Input Boards ( 1160, VME Based)• Misc. Cables
October, 2009
Access Controls Hardware
• Two Entrance Doors – Outfitted with new MagLock and magnetic sealed switch technology i.e., as 4GE1, 4GE2 etc.
• Emergency Stop Machine (Crash) system• Critical Device interface for Critical Devices such as RF power supply
contactors(x-ray hazard), Beam shutters (prompt radiation hazard)• ODH mitigation and warning system• Audible and visual warning systems• Area Sweep check station system• Remote gate entry system - Iris recognition, key tree• Digital video system for Remote Access.
* The MeRHIC safety system will be connected and programmed into existing 2 O'clock PASS Peer11 A and B Divisions, which shall be re-programmed to perform MeRHIC area safety functions
October, 2009
Estimate by phase with contingency
WBS 1.9 SummaryControls
Direct Labor
Direct Material
Contingency $
Contingency %
Total Direct dollars
Burdened Labor
Burdened Material
Contingency $ Burdened
Total Burdened
dollars
PED/EDIA 0 0
Construction 937 1,231 844 39% 3,012 1,354 1,442 1,089 3,884
Installation 0 0
Commissioning 0 0
Total 937 1,231 844 39% 3,012 1,354 1,442 1,089 3,884
FY09 Direct K dollars FY09 Burdened K dollars
October, 2009
Labor hours, FTEs, $
WBS 1.9 SummaryControls
Total Hours
Building Trades
Central Shops Designer Engineer Technician
Direct dollars
Burdened dollars
PED/EDIA 0
Construction 13,042 32 1,040 2,880 6,990 2,100 937 1,354
Installation
Commissioning
Total 13,042 32 1,040 2,880 6,990 2,100 937 1,354FTEs 7.4 0.0 0.6 1.6 4.0 1.2
Labor (FY09$K) no contingencyHours Estimated
October, 2009
Estimated Material $
WBS 1.9 SummaryControls
Purchases<$25K
Purchases >$25K< $600K
Purchases > $600K Travel Total
FY09 Burdened K
dollars
PED/EDIA
Construction 407 824 - - 1,231 1,442
Installation
Commissioning 0
Total Dollars 407 824 0 0 1,231 1,442
FY09 Direct K dollars