O AK R IDGE N ATIONAL L ABORATORY U. S. D EPARTMENT OF E NERGY 1 Commissioning and Initial Operating...
-
Upload
heather-ferguson -
Category
Documents
-
view
220 -
download
1
Transcript of O AK R IDGE N ATIONAL L ABORATORY U. S. D EPARTMENT OF E NERGY 1 Commissioning and Initial Operating...
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
1
Commissioning and Initial Operating Experience with the SNS Accelerator
Complex
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
2
Beam and Neutronics Project Completion goals were met 1013 protons
delivered to the target
The SNS Construction Project was formally Completed in June 2006
We have officially started SNS Operations
First Beam on Target, First Neutrons and Technical Project Completion Goals Met April 28, 2006
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
3
SNS Accelerator Complex
945 ns
1 ms macropulse
Cur
rent
mini-pulse
Cur
rent
1ms
Front-End:Produce a 1-msec
long, chopped, H- beam
1 GeV LINAC
Accumulator Ring: Compress 1 msec
long pulse to 700 nsec
Chopper system makes gaps
Ion Source2.5 MeV 1000 MeV87 MeV
CCLCCL SRF, =0.61SRF, =0.61 SRF, =0.81SRF, =0.81
186 MeV 387 MeV
DTLDTLRFQRFQ
Accumulator Ring
RTBT
Target
HEBT
Injection Extraction
RF
Collimators
Liquid Hg Target
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
4
SNS High-Level Design Parameters
Kinetic Energy GeV 1.0 Beam power on Target MW 1.4 Linac beam macro pulse duty factor % 6 Average macropulse H- current mA 26 Peak Linac Current mA 38 Linac average beam current mA 1.6 SRF cryo-module number 11+12 SRF cavity number 33+48 Peak surface field medium-beta MV/m 27.5 Peak surface field high-beta MV/m 35 Ring accumulation turns 1060 Ring current at end of accumulation A 25 Ring bunch intensity 10^14 1.5 Ring space-charge tune spread Q 0.15 Pulse length on target nsec 695
Ring is designed for 2 MW at 1 GeV; installed for 1.3 GeV (mostly)
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
5
The SNS Partnership
ORNL Accelerator Systems Division responsible for integration, installation, commissioning and operation
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
6
Spring 1999
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
7
Now
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
8
Front-End Systems
Front-End H- Injector was designed and built by LBNL
402.5 MHz Radiofrequency quadrupole accelerates beam to 2.5 MeV
Medium Energy Beam Transport matches beam to DTL1 input parameters
Front-end delivers 38 mA peak current, chopped 1 msec beam pulse
H- Ion Source has been tested at baseline SNS parameters in several endurance runs >40 mA, 1.2 msec, 60 Hz
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
9
Accumulator Ring and Transport Lines
Circum 248 mEnergy 1 GeVfrev 1 MHzQx, Qy 6.23,
6.20x, y -7.9, -6.9Accum turns 1060Final Intensity 1.5x1014
Peak Current 52 ARF Volts (h=1) 40 kV (h=2) 20 kVInjected p/p 0.27%Extracted p/p 0.67%
HEBT
Accumulator Ring
RTBT
Injection
Collimation
RF
Extraction
Target
Designed and built by Brookhaven National Lab
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
10
Ring and Transport Lines
HEBT Arc
Injection
Ring Arc
RTBT/Target
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
11
Target Region Within Core Vessel
Core Vessel water cooled shielding
Core Vessel Multi-channel flange
Outer Reflector Plug
Target
Target Module with jumpers
Moderators
Proton Beam
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
12
Normal Conducting Linac: Front-End Output Emittance and Bunch Length
MEBT inline emittance system allows routine measurement
Expect 0.3 mm mrad, rms, norm
Results ( mm mrad, rms, norm) X = 0.29 Y = 0.26
Bunch length measured with mode-locked laser system
RM
S B
unch
Len
gth
(deg
)
Rebuncher phase (deg)
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
13
DTL and CCL RF Setpoints by Phase Scan Signature Matching
CCL Module 2 RF Phase
BP
M P
hase
Diff
(de
g)
J. Galambos, A. Shishlo
To tune up the linac requires finding phase and amplitude setpoints for 95 RF systems within 1%/1 deg (specification)
Model-based methods utilizing time-of-flight data have been developed
Normal conducting linac phase and amplitude setpoints determined by Phase-Scan Signature Matching
Plot shows data (lines) compared to model (pts) for two CCL2 amplitudes
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
14
CCL Module 1 Longitudinal Bunch Shape Monitor Measurements
Measured values are close to the predicted bunch length
Measurements were motivated by earlier observations of a longer bunch, presumably due to longitudinal mismatch
BSM107 BSM111
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
15
Superconducting Linac Tuneup by Phase Scan
Fit varies input energy, cavity voltage and phase offset in the simulation to match measured BPM phase differences
Relies on absolute BPM phase calibration With a short, low intensity beam, results are insensitive to detuning cavities
intermediate to measurement BPMs
SCL phase scan for first cavitySolid = measured BPM phase diffDot = simulated BPM phase diffRed = cosine fit
Cavity phase
BP
M p
hase
diff
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
16
Low-level RF Feedforward Beam turn-on transient gives RF phase and amplitude variation
during the pulse, beyond bandwidth of feedback
LLRF Feedforward algorithms have been commissioned (Champion, Kasemir, Ma, Crofford)
Without Feed-forward With Feed-forward
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
17
SCL Operations: Fault Recovery (Galambos)
We have successfully tested a cavity fault recovery algorithm in which the phase of all downsteam cavities are adjusted in response to a change in setpoint of a given cavity
0
200
400
600
800
1000
1200
1400
1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81
Cavity
Ph
as
e C
ha
ng
e(d
eg
)
-300
-200
-100
0
100
200
300
400
1 7 13 19 25 31 37 43 49 55 61 67 73 79
Cavity
Ph
as
e C
ha
ng
e (
de
g)
-6
-4
-2
0
2
4
6
Me
as
ure
d E
rro
r (d
eg
)
Phase Change
Measured Error
Cavity 3a turned off
Final cavity phase found within 1 degree, output energy within 1 MeV
Turned on cavity 4a, reduced fields in 11 downstream cavities
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
18
Ring/RTBT/Target Commissioning Timeline January-May 2006
Jan. 12: Received approval for beam to Extraction Dump.
Jan. 13: First beam to Injection Dump.
Jan. 14: First beam around ring.
Jan. 15: >1000 turns circulating in ring
Jan. 16: First beam to Extraction Dump.
Jan. 26: Reached 1.26E13 ppp to Extraction Dump.
Feb. 11: ~8 uC bunched beam (5x1013 ppp)
Feb. 12: ~16 uC coasting beam (1x1014 ppp)
Feb. 13: End of Ring commissioning run
April 3-7: Readiness Review for RTBT/Target
April 27: Received approval for Beam on Target
April 28: First beam on target and CD4 beam demonstration
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
19
Accumulation and Extraction of 1.3x1013 protons/pulse (January 26, 2006)
Ring Beam Current Monitor
200 turn accumulation
extraction
Extraction Dump Current Monitor
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
20
Ring Orbit Correction: H,V Bumps are Due to Injection Kickers
Horizontal Orbit
BPM Amplitude
Vertical Orbit
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
21
Ring Optics Measurements: Betatron Phase Advance and Chromaticity
Vert Horiz
Natural Chromaticity (Design)
-6.9 -7.9
Natural Chromaticity (Measured)
-7.2 -8.2
Corrected Chromaticity (Meas)
0.0 0.1
Horizontal Fit
-30
-20
-10
0
10
20
30
1 4 7 10 13 16 19 22 25 28 31 34 37 40 43
Beam Position Monitor
Bet
atro
n P
has
e E
rro
r (d
egre
es)
Horizontal Data
Horizontal Fit
Vertical Fit
-30
-20
-10
0
10
20
30
1 4 7 10 13 16 19 22 25 28 31 34 37 40 43
Beam Position Monitor
Be
tatr
on
Ph
as
e E
rro
r (d
eg
ree
s)
Vertical Data
Vertical Fit
Plots show measured betatron phase error vs. model-based fit
Data indicates that the linear lattice is already very close to design
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
22
High Intensity Studies (Danilov, Cousineau, Plum)
Beam intensity records (protons/pulse): 5x1013 in bunched beam, transported to
target 1x1014 unbunched, coasting beam
We searched for instabilities by i) delaying extraction, ii) operating with zero chromaticity, iii) storing a coasting beam
No instabilities seen thus far in “normal” conditions
See instability centered at 6 MHz, growth rate 860 us for 1014 protons in the ring, driven, as predicted by extraction kicker impedance Zcalc 22-30 kOhm/m Zmeas 28 kOhm/m.
In coasting beam also see very fast instability at 0.2-1x1014 protons in the ring, consistent with e-p. Growth rate 20-200 turns. f 30-80 MHz depending on beam conditions.
Scaling these observations to nominal operating conditions predicts threshold > 2 MW for extraction kicker (as previously predicted)
0 50 100 1502
2.5
3
3.5
4
4.5
5
5.5
6
Turns
Log
(ma
gin
itu
de(7
5th
Ha
rmo
nic
))
Evolution of 75th Harmonic
Slow: Extraction Kicker
Fast: electron-proton
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
23
Phase Space PaintingStripping Foil
Injected BeamInitial Closed
OrbitFinal Closed
Orbit
X
px
Wei et. al., PAC 2001, 2560
X-Y space after 1060 Turns
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
24
Phase Space Painting
65 mm 80 mm
Beam on Target View Screen
Beam profiles in RTBT
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
25
Summary of Achieved Beam Parameters Parameter Baseline/
DesignAchieved in Commissioning/AP
Achieved in Operation
Units
Linac Transverse Output Emittance
0.4 0.3 (H), 0.3 (V) 0.4 mm-mrad (rms,norm)
CCL1 bunch length 3 4 4 degrees rms
Linac Peak Current 38 > 38 20 mA
Linac Output Energy 1000 1012 890 MeV
Linac Average Current 1.6 1.05 (DTL1 run) 0.003 (SCL run)
0.067 mA
Linac H-/pulse 1.6x1014 1.3x1014 (DTL1) 8.0x1013 (SCL run)1.0x1014 (Ring run)
4.3x1013 Ions/pulse
Linac Pulse length/Rep-rate/Duty Factor
1.0/60/6.0 1.0/60/3.8 (DTL1 run) 0.85/0.2/0.017 (SCL)
0.6/5/0.3 msec/Hz/%
Extracted protons/pulse 1.5x1014 0.96x1014 0.43x1014 Protons/pulse
Beam Power 1440 4 60 kW
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
26
Beam-Power-on-Target HistoryB
eam
Po
we
r [0
-65
kW
]
Beam power administratively limited to 10 kW until November 8
Feb 1, 2007May 1, 2006
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
27
FY 2007 Integrated Beam Power by Day and Cumulative
6.3 MW-hrs delivered in Run 2007-1
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
28
Technical Challenges: Equipment Reliability Beam Chopper Systems
Repeated failures in Low-energy and Medium-energy Beam Transport chopper systems
New, more robust, designs will be designed and manufactured this year (FY07 Accelerator Improvement Project)
High-Voltage Converter Modulators A number of weak components limit MTBF to 2700 Hrs Several prototype improvements are in test in single operational units Improvements will be deployed this year on full system of 14 modulators (FY07
Accelerator Improvement Project) Ion Source and Low Energy Beam Transport System Water Systems
Problems associated with clogging flow restrictors, failed gaskets, poor conductivity monitoring and control, etc.
Reliability improvements have been underway since CD-4 (also FY07 AIP) Cryogenic Moderator System
Thermal capacity degraded in 3 week cycle prior to December 2006 Manufacturer attempted repair in December Capacity improved, but some sign of degradation remains
Mercury Pump Seal failed end of November Operating the pump now with failed seal, mitigated by installation of a cover plate to
direct gas to the Mercury Off-Gas Treatment System Replacement Mercury Pump in expected to be available for installation in September
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
29
Technical Challenges: Beam Power Beam losses must be kept below 1 Watt/m to limit residual activation
We measure higher than desired losses in the Ring Injection area We are unable to simultaneously transport waste beams (from stripping
process) to the injection dump and properly accumulate in the ring Internal Review of Injection Dump performance was held in November and
follow-up meeting in December Short-term fixes allow >100 kW operation; mid-term fixes (April 2007) are in
preparation; long-term fix requires redesign of injection dump beamline and 2 new magnets
An aggressive accelerator physics program has reduced losses and activation while allowing increased beam power
We are not operating 9 Superconducting RF cavities (out of 81) out of concern for potential failures
Recent tests indicate that 6 of these 9 cavities are operable up to 15 Hz repetition rate
Those tests also show that the behaviour of individual cavities is the same at higher repetition rates, up to the full 60 Hz
We are building infrastructure to provide cryomodule repair and maintenance capabilities on-site. We are formulating plans to restore operation of all cavities, and to procure spare cryomodules
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
30
Outlook: Performance Goals
0
500
1000
1500
2000
2500
0 12 24 36Months
Bea
m P
ower
(kW
), P
rodu
ctio
n H
rs
50
55
60
65
70
75
80
85
90
95
Rel
iabi
lity
Beam Power GoalNeutron Production HoursReliability
FY08FY07 FY09
SNS Beam Power Upgrade Project will increase linac output energy to 1.3 GeV and provide 3 MW beam power
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
31
E-P Feedback Experiment at the PSR We formed a collaboration to carry out an experimental test of
active damping of the e-p instability at the LANL PSR (ORNL, LBNL, IU, LANL)
We deployed a broadband transverse feedback system designed and built by ORNL/SNS and demonstrated for the first time damping of an e-p instability in a long-bunch machine
We observed a 30% increase in e-p instability threshold with feedback on.
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
32
We have observed > 90% H- to proton stripping efficiency in proof-of-principle tests at SNS
Laser Beam
H- proton
H0 H0*
Step 1: Lorentz Stripping
Step 2: Laser Excitation Step 3: Lorentz Stripping
High-field Dipole Magnet
High-field Dipole Magnet
H- H0 + e- H0 (n=1) + H0* (n=3) H0* p + e-
Laser-Stripping Injection Proof-of-Principle Experiment
H- to protons
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
33
Yes, We’ve Had a Few Surprises RFQ resonant frequency shifted by 100 kHz
Never found the cause; retuned in 2003
Bunch length 3x design in CCL1; also had difficulty keeping DTL5 at design field Found a charred piece of paper in DTL Tank 5 in 2004
Large local losses and poor trajectory near SCL/HEBT transition Found large dipole deflection with orbit response studies Found current shunted around one quad coil
Beam is rotated about 6 degrees on target view screen
Excessive fundamental power through two SCL HOM feedthroughs; others impacted
Large local losses in injection dump line
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
34
Summary Completed 7 beam commissioning runs, amounting to
more than 1 year of dedicated beam commissioning and operating time
Achieved beam and neutron project completion requirements within project schedule
SNS construction project was formally completed in June 2006 on-budget and on-schedule
We are now in the early operations stage with local users
We are beginning to ramp up the beam power of the SNS accelerator complex
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
35
SNS Beam Diagnostic SystemsRING
44 Position 2 Ionization Profile70 Loss 1 Current 5 Electron Det. 12 FBLM2 Wire 1 Beam in Gap2 Video 1 Tune
RING44 Position 2 Ionization Profile70 Loss 1 Current 5 Electron Det. 12 FBLM2 Wire 1 Beam in Gap2 Video 1 Tune
SCL32 Position 86 Loss 9 Laser Wire24 PMT Neutron
SCL32 Position 86 Loss 9 Laser Wire24 PMT Neutron
RTBT17 Position36 Loss4 Current5 Wire1 Harp3 FBLM
RTBT17 Position36 Loss4 Current5 Wire1 Harp3 FBLM
HEBT29 Position 1 Prototype Wire-S46 BLM, 3 FBLM 4 Current
HEBT29 Position 1 Prototype Wire-S46 BLM, 3 FBLM 4 Current
IDump1 Position1 Wire 1 Current6 BLM
IDump1 Position1 Wire 1 Current6 BLM
EDump1 Current 4 Loss 1 Wire
EDump1 Current 4 Loss 1 Wire
LDump6 Loss6 Position1 Wire ,1 BCM
LDump6 Loss6 Position1 Wire ,1 BCM
CCL/SCL Transition2 Position 1 Wire1 Loss 1 Current
CCL/SCL Transition2 Position 1 Wire1 Loss 1 Current
CCL10 Position 9 Wire 8 Neutron, 3BSM,
2 Thermal28 Loss 3 Bunch
1 Faraday Cup 1 Current
CCL10 Position 9 Wire 8 Neutron, 3BSM,
2 Thermal28 Loss 3 Bunch
1 Faraday Cup 1 Current
OperationalOperational MEBT6 Position2 Current5 Wires2 Thermal Neutron3 PMT Neutron 1 fast faraday cup1 faraday/beam stopD-box videoD-box emittance D-box beam stop D-box apertureDifferential BCM
MEBT6 Position2 Current5 Wires2 Thermal Neutron3 PMT Neutron 1 fast faraday cup1 faraday/beam stopD-box videoD-box emittance D-box beam stop D-box apertureDifferential BCM
DTL10 Position 5 Wire 12 Loss 5 Faraday Cup 6 Current6 Thermal and 12 PMT Neutron
DTL10 Position 5 Wire 12 Loss 5 Faraday Cup 6 Current6 Thermal and 12 PMT Neutron
Not OperatingNot Operating
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
36
Baseline SNS Ion Source Performance • LBNL H- ion source + ORNL antennas• Source performed well during SNS
commissioning.• Successful commissioning would not
be possible without use of longer-lived antennas.
• 10-40 mA routinely delivered at ~0.1% duty-factor.
• Availability improved: 86% ~100% during later commissioning periods (target comm: 77 days).
• Largest availability gain redesigning LEBT insulatorsAntennas: Welton et al,
RSI 73 (2002) 1008
+
0
5
10
15
20
25
30
35
40
20-Sep 25-Sep 30-Sep 5-Oct 10-Oct 15-Oct0
5
10
15
20
25
30
35
40
45
27-Jun 2-Jul 7-Jul 12-Jul 17-Jul 22-Jul
Ave
rage
Bea
m C
urre
nt (m
A)
Beam attenuation ~5 mA/day Run #9 ran for 16 days / 33 mA / 0.4 mA/day.
3 Typical Test Runs Our Best Run(employs new operating procedure)
Catastrophic antenna failure
• ~10 lifetime tests performed at full 7% duty-factor and max current.
• Best results shown• Outcome: Insufficient beam
current, frequent antenna failures and poor beam stability with time
• Vigorous R&D program to meet SNS operational requirement of 40 mA and SNS-PUP requirement of 60 mA.
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
37
Recent Ion Source R&D Accomplishments Ionization Cone
Cs injection collar
Air ductCs
Line
Extractor electrode
ions
0.0
10.0
20.0
30.0
40.0
50.0
60.0
0 20 40 60 80
RF Power (kW)
H-
Cu
rren
t (m
A)
uncesiated
cesiated
Elemental Cs system 65 mA-1.2 ms, 70 mA-0.2 ms pulses
achieved at 10Hz!
~2x increase in RF power efficiency.
Multi-day runs show excellent beam stability.
Multiple cesiations show excellent reproducibility.
~5% droop and good ~30 us rise times.
Beam emittance is expected to be similar to baseline source.
Al2O3 insulator
Anode
Cooling channel
Plasma stream
Cathode Ions
0
10
20
30
40
50
60
70
80
0 20 40 60 80 100
RF Power (kW)
H-
Cu
rren
t (m
A)
Peak
Average
Multi-year lifetime achieved at DESY at <1% duty-factor
Plasma gun enhances H- ~50%
51 mA – 0.2 ms pulses achieved with no Cs and no B-field confinement.
65 mA – 0.2 ms, 50 mA – 1.2 ms pulses achieved with Cs and no confinement.
Welton et al, LINAC 2006, Knoxville
External Antenna & Plasma Gun
Welton et al, LINAC 2006, Knoxville
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
38
Energy Stability – Pulse to Pulse (J. Galambos)
RMS energy difference jitter is 0.35 MeV, extreme = + 1.3 MeV
Parameter list requirement is max jitter < +1.5 MeV
865 MeV beam
~ 1000 pulses
20 sec pulse
12 mA beam
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
39
SCL Laser Profile Measurements
SCL laser profiles (H + V) were available at 7 locations 3 at medium beta entrance, 3 at high beta entrance and 1
at the high beta end
Measured horizontal profile after SCL cryomodule 4
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
40
Neutrons: 4-methyl pyridine N-oxide 5 kWatt, 3 hour, ¼ detector, T = 3 K
4 eV
OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY
41
The Spallation Neutron Source The SNS is a short-pulse neutron source, driven by a 1.4 MW proton accelerator SNS will be the world’s leading facility for neutron scattering research with peak neutron flux
~20–100x ILL, Grenoble SNS construction project, a collaboration of six US DOE labs, was funded through DOE-BES
at a cost of 1.4 B$
SNS will have 8x beam power of ISIS, the world’s leading pulsed source
Stepping stone to other high power facilities