Nyngan Solar Farm Submissions Report Final v1

73
Submissions Report NYNGAN SOLAR FARM DECEMBER 2010 Picture height 2.75, Width 3.25cm Picture height 2.75, Width 3.25cm Picture height 4.5 width 6.5cm OR USE ONE PICTURE THAT FITS CLOSE TO THE TOTAL DIMENSIONS OF THIS TABLE!

Transcript of Nyngan Solar Farm Submissions Report Final v1

Page 1: Nyngan Solar Farm Submissions Report Final v1

 

 

 

 

Submissions Report 

NYNGAN SOLAR FARM 

 

 

 

DECEMBER 2010 

 

   

Picture height 2.75, 

Width 3.25cm 

Picture height 2.75, 

Width 3.25cm 

Picture height 4.5 width 6.5cm 

 

OR USE ONE PICTURE THAT FITS CLOSE TO THE TOTAL DIMENSIONS OF THIS TABLE! 

Page 2: Nyngan Solar Farm Submissions Report Final v1

 

1/216 carp st  (po box 470)  bega  nsw  2550  australia  t 61 2 6492 8333  f 61 2 6494 7773 

www.nghenvironmental.com.au   e [email protected] 

unit 9/65 tennant st  (po box 1037) fyshwick  act  2609  australia 

t 61 2 6280 5053  f 61 2 6280 9387 

18/21 mary stsurry hills  nsw  2010  australia 

t 61 2 8202 8333  f 61 2 6494 7773 

po box 8323perth bc  68849  australia 

t 61 8 9759 1985  f 61 2 6494 7773 

  102/63‐65 johnston st  (po box 5464)wagga wagga  nsw  2650  australia t 61 2 6971 9696  f 61 2 6971 9693 

suite 6/234 naturaliste tce  (po box 1037)dunsborough wa  6281  australia 

t 61 8 9759 1985 f 61 2 6494 7773   

 

Document Verification

 

Project Title: Nyngan Solar Farm Submissions Report

Project Number:  1585 

Project File Name:  Nyngan Solar Farm Submissions Report 031210 .docxRevision  Date  Prepared by (name)  Checked by (name)  Approved by (name) 

Draft V1  6/12/10  Amy Webb Brooke Marshall 

Brooke Marshall  Brooke Marshall 

Final V1  8/12/10  Amy Webb Brooke Marshall 

Brooke Marshall  Brooke Marshall 

  

       

  

       

  

       

nghenvironmental prints all documents on environmentally sustainable paper including paper made from 100% bagasse (a bi‐product of sugar production) or recycled paper. 

 

 

Page 3: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1   i   

CONTENTS 

1  INTRODUCTION .......................................................................................................................... 1 

1.1  BACKGROUND ......................................................................................................................................1 

1.2  PURPOSE OF THIS REPORT ...................................................................................................................2 

2  THE PROPOSAL ........................................................................................................................... 3 

2.1  SUMMARY OF THE PROPOSAL .............................................................................................................3 

2.1.1  Photovoltaic array .................................................................................................................................. 3 

2.1.2  Connection to the existing Nyngan substation ...................................................................................... 3 

2.1.3  Access tracks .......................................................................................................................................... 3 

2.1.4  Buildings ................................................................................................................................................ 4 

2.1.5  Project timing and staging ..................................................................................................................... 4 

2.1.6  Operational management...................................................................................................................... 4 

2.1.7  Decommissioning ................................................................................................................................... 4 

2.2  PROJECT BENEFITS ...............................................................................................................................8 

3  CONSIDERATION OF SUBMISSIONS ............................................................................................. 9 

3.1  EXHIBITION PERIOD AND LOCATION ....................................................................................................9 

3.2  RESPONSES RECEIVED ..........................................................................................................................9 

4  PROPONENT’S RESPONSE TO COMMUNITY SUBMISSIONS ........................................................ 10 

5  PROPONENT’S RESPONSE TO GOVERNMENT AGENCY SUBMISSIONS ........................................ 11 

5.1  DEPARTMENT OF ENVIRONMENT, CLIMATE CHANGE AND WATER..................................................11 

5.2  NSW OFFICE OF WATER .....................................................................................................................13 

6  MODIFICATIONS TO THE PROPOSAL: SUMMARY ....................................................................... 15 

6.1  DELETED SOCS ....................................................................................................................................15 

6.2  NEW SOCS ..........................................................................................................................................15 

6.3  MODIFIED SOCS .................................................................................................................................15 

7  CONCLUSION ............................................................................................................................ 16 

 

 

Page 4: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1   ii   

Appendix A: Revised Statements of Commitment  

Appendix B: Additional investigations 

B.1 Flora Addendum 

B.2 Archaeology and Aboriginal Heritage Addendum 

 

 

Page 5: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  1   

1 INTRODUCTION 

1.1 BACKGROUND 

The Nyngan  Solar  Farm  is  proposed  in  the  Central West  on  cleared  farmland  off  East Nyngan  Road, 

Nyngan  (the  proposal  site).  The  proposal  encompasses  the  construction  and  operation  of  a  solar 

photovoltaic  array over  an  area of  approximately 200 hectares of  a 450 hectare  site, with  associated 

electrical infrastructure, maintenance facilities, access tracks and minor upgrades to adjacent roads. 

The proposal is a Part 3A Major Project under the NSW Environmental Planning and Assessment Act 1979

and therefore the consent authority is the Minister for Planning. The proposal is also consistent with the 

criteria of Critical  Infrastructure as  it  is  a power  generator with  the  capacity  to  generate  in  excess of 

30MW. 

The proponent for the Nyngan Solar Farm proposal is Infigen Suntech Australia Pty Ltd (Infigen Suntech). 

Infigen Suntech  is a  joint venture  formed between  Infigen Energy Limited  (Infigen Energy) and Suntech 

Power Australia Pty Ltd  (Suntech) to deliver utility scale photovoltaic solar projects  in Australia.  Infigen 

Energy  is  a  specialist  renewable energy business  that develops, owns  and operates  renewable energy 

generation  facilities  across  Australia,  the  United  States  and  Germany.  Suntech  is  the world’s  largest 

producer of silicon solar modules, with offices in 13 countries. 

An  Environmental  Assessment  (EA),  prepared  by  nghenvironmental,  was  submitted  to  the  NSW 

Department  of  Planning  and  placed  on  public  exhibition  from  the  4th  of  November  to  the  6th  of 

December 2010. During  this period1,  submissions were  sought  from  the  local  community, government 

agencies, interested parties and other stakeholders.  

Key  issues  were  formalised  in  the  Director  General’s  Requirements  for  the  preparation  of  the 

Environmental Assessment.  Investigation of  these  issues  formed  the major part of  the  Environmental 

Assessment. These issues were investigated via specialist reports and by desktop assessment. 

Specialist investigations were carried out in the key areas of: 

  Biodiversity impacts  Visual impacts 

  Aboriginal archaeological impacts  Flooding impacts 

  Noise impacts   

These investigations were appended to the EA in full and are summarised in the body of the EA.  

Additionally, since the submission of the EA to the Department of Planning: 

Flora  investigations were undertaken, specific to threatened species  impacts, to validate 

the assumptions made in the Biodiversity Assessment 

Further  Archaeological  investigation was  carried  out  in  the  eastern  section  of  the  site, 

which had not previously been surveyed.  

                                                              

   

Page 6: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  2   

These  investigations are appended  to  this Submissions Report and are summarised under  the  relevant 

agency response headings in this report.  

1.2 PURPOSE OF THIS REPORT 

This Submissions Report has been prepared by Infigen Suntech and nghenvironmental. It: 

Considers and responds to the issues raised in the public and agency submissions for the 

Nyngan Solar Farm  

Includes  the  results  of  the  additional  studies  undertaken  to  assess  the  impact  of  the 

proposal 

Describes  any  changes  to  the  proposal,  including  a  revised  set  of  Statements  of 

Commitments 

Page 7: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  3   

2 THE PROPOSAL 

2.1 SUMMARY OF THE PROPOSAL 

The proposal remains as described in the Environmental Assessment (nghenvironmental 2010). That is: 

Infigen Suntech proposes to construct a 100 megawatt (MW) capacity solar farm on cleared farmland off 

East Nyngan Road, Nyngan  (the proposal  site). The  solar panel array would occupy approximately 200 

hectares on a site 450 hectares in size. The solar farm would have an expected operating life of up to 50 

years. The decommissioning phase would remove all above ground infrastructure from the site. 

The key infrastructure elements for the project would include: 

A PV array incorporating rows of panels and a series of central inverters and kiosk transformers 

Cabling between the PV array and central inverters (underground or frame secured) 

Cable connection to the existing 132kV Nyngan substation (underground) 

Internal access tracks and upgrades to existing roads 

Site office, operations  and maintenance buildings  incorporating  a  control  room  and  switching 

equipment 

Temporary construction facilities such as a site compound and equipment laydown area 

2.1.1 Photovoltaic array 

The PV array being considered consists of Suntech poly‐crystalline solar panels mounted on a fixed steel 

support frame. The maximum height of the array would be 3.5 metres.  

The proposed Suntech panels are efficient modules suitable for utility scale solar power generation. Each 

panel would be approximately 2 metres long x 1 metre wide. The PV panels would be arranged in rows, 

with  sufficient  spacing  between  rows  to  allow maintenance  activities  such  as weed  control  or  panel 

washing as required.  

The PV panel mounting structures would be supported by steel posts driven into the ground.  

2.1.2 Connection to the existing Nyngan substation 

The  cable  connection  between  the  solar  farm  and  existing  substation would  be  via  an  underground 

transmission line.  

2.1.3 Access tracks 

On site access tracks required for construction and operation would be gravel formations up to 8 metres 

in width and may be reduced to 5 metres after the construction phase. Tracks would be maintained for 

the lifetime of the solar farm. 

Page 8: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  4   

2.1.4 Buildings 

Temporary  construction  buildings would  be  installed within  a  fenced  facilities  area.  Additionally,  the 

following  permanent  buildings  may  be  constructed  at  the  site:  a  site  office,  an  operations  and 

maintenance building incorporating a control room with monitoring and workshop facilities. 

2.1.5 Project timing and staging 

The  construction  timeline  for  the  project  would  be  dependent  on  the  timing  of  approval,  funding 

arrangements and  the supply of key components. However,  it  is  likely  that  the 10 month construction 

period  would  commence  in  September  2012.  Construction  works  would  be  confined  to  standard 

construction hours (Monday‐Friday 7am‐6pm, Saturday 8am‐1pm).  

2.1.6 Operational management 

A  site manager would  be  employed  to manage  the  facility.  Security  staff  or  services would  also  be 

engaged. The PV array and other equipment would be inspected and maintained on an ‘as needs’ basis. A 

supervisory control and data acquisition (SCADA) system would monitor the operational solar farm and 

identify any electrical faults.  

Periodic weed control would be undertaken as required. Groundcover vegetation around the panel rows 

would be either slashed or grazed by sheep. Regular washing of the solar panels  is not expected to be 

required.  If  required,  water  would  be  sourced  from  the  Bogan  Shire  Council  or  commercial  water 

suppliers to remove dust or bird excrement. Detergent would not be used. 

2.1.7 Decommissioning 

The  life  span  of  the  PV  infrastructure  is  30  to  50  years.  At  the  end  of  the  project  all  above‐ground 

infrastructure would be removed. 

 

 

Page 9: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  5   

 

Figure 2‐1 Location of the proposal 

Prepared by:

°

Site boundary

Development envelope

TOPOGRAPHIC CONTEXT: NYNGAN SOLAR FARM SITEPrepared for:

    @ A3Reference: 1337‐17

Coordinate system: GDA 94

1:40000

www.nghenvironmental.com.au

0 0.5 10.25 Kilometers

Notes:

1.0 Layers prepared by nghenvironmental

Page 10: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  6   

 

Figure 2‐2: Nyngan Solar Farm layout, View 1: Panel modules, buildings and roads 

Existing substation

[_ Public road access

Site boundary

Existing track (proposed construction access)

Laydown area

Temporary laydown area

Proposed roads

Modules and inverters

Site office

Development envelope

°

0 250 500125 Metres

    @ A4 Reference: 1337 ‐ 1

1:27000

Coordinate System:      GDA94 Zone 55

www.nghenvironmental.com.au

Page 11: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  7   

 

Figure 2‐3: Nyngan Solar Farm layout, View 2: Cabling layout 

Site boundary

Development envelope

Boundary fence

Existing substation

[_ Public road access

Lot boundaries

Cable trench circuit 1

Cable trench circuit 2

Cable trench circuit 3

Cable trench circuit 4

Transformers

Site office

°

0 250 500125 Metres

    @ A4 Reference: 1337 ‐ 2

1:27000

Coordinate System:      GDA94 Zone 55

www.nghenvironmental.com.au

Page 12: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  8   

2.2 PROJECT BENEFITS 

The Nyngan  Solar  Farm would be  clean,  renewable  and  sustainable  and would  emit  zero  greenhouse 

gases  (Infigen  Energy  2010b).  The  100MW  solar  farm  would  generate  approximately  200GWh  of 

electricity per year, enough renewable energy to power up to 20,000 homes and would be the equivalent 

of removing approximately 30,000 cars from Australian roads each year (Infigen Energy 2010b).  

Building  a  solar  farm  of  this  scale  in Nyngan would  be  a major  boost  to  the  Australian  solar  energy 

industry.  It would provide  local employment opportunities both throughout the construction phase and 

once the site becomes operational, and would also help to develop local and regional capabilities in solar 

photovoltaic plant construction.  

The  solar  farm  would  contribute  to  Australia’s  Renewable  Energy  Target  (RET)  of  sourcing  20%  of 

electricity from renewable sources by 2020. 

The Nyngan Solar Farm would: 

Provide reliable energy in a market where demand will soon exceed supply 

Reduce green house gas emissions that contribute to climate change 

Assist  in meeting  Federal  and  State  policy  objectives  to  enhance  the  contribution made  by 

renewable energy sources to meeting demand 

Contribute to the development of the utility scale renewable energy industry in NSW 

Assist  in the experience and  learning required  in Australia  industry to  further proliferate utility 

scale solar in Australia 

Provide a local and regional economic stimulus through jobs and training 

 

Page 13: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  9   

3 CONSIDERATION OF SUBMISSIONS 

3.1 EXHIBITION PERIOD AND LOCATION 

The  Nyngan  Solar  Farm  Environmental  Assessment  was  on  public  exhibition  from  Thursday  4th  of 

November to Monday 6th of December 2010 at: 

Department of Planning, Information Centre, 23‐33 Bridge Street, Sydney 

Nature Conservation Council of NSW, Level 2/5 Wilson Street Newtown NSW 2042 

Bogan Shire Council, 81 Cobar Street, Nyngan 

Local residents were notified of the exhibition period through newspaper advertisements placed  in the 

local papers by the Department of Planning. A media release was issued by Infigen Suntech.  

3.2 RESPONSES RECEIVED  

The Department of Planning received a total of two submissions; both were from government agencies. 

No submissions were received from individual members of the public or representative groups.  

Table 3‐1 Responses received 

Category  Number of submissions 

   

Individual members of the public  0 

Interest groups  0 

Government agency submissions  2 

Total  2 

 

 

Page 14: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  10   

4 PROPONENT’S RESPONSE TO COMMUNITY SUBMISSIONS 

Not applicable. No community submissions were received in relation to the Nyngan Solar Farm proposal.  

Page 15: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  11   

5 PROPONENT’S RESPONSE TO GOVERNMENT AGENCY SUBMISSIONS 

5.1 DEPARTMENT OF ENVIRONMENT, CLIMATE CHANGE AND WATER 

Issue  Response 

Additional studies: Flora  Additional flora investigations were conducted (included in Appendix B) in fulfilment of SoC 1 of the EA. As a result of these investigations, the original SoC has been deleted.  

See also flora and fauna survey issue below.  

Additional studies: Archaeology and 

Aboriginal heritage 

Additional Archaeology and Aboriginal heritage investigation was conduected (included in Appendix B) in fulfilment of SoC 31 of the EA. As a result of this investigation, the original SoC has been deleted.  

Flora and fauna surveys  DECCW proposed to amend SOC 1 so as to read: 

“A supplementary flora and fauna survey during spring is required to identify us threatened flora and fauna species inhabit the area encompassed by the site and to properly assess the impact of the proposal on threatened species. This will include targeted surveys for the Red Darling‐pea and Slender Darling‐pea”. 

Supplementary flora surveys were conducted during early November (spring) specifically targeting the Red‐darling pea and Slender‐darling pea. These species were not detected on  the site. An addendum to  the original Biodiversity Assessment (Appendix B)  concluded  that  impacts  to  threatened  species are unlikely.  Flora  surveys were  also  conducted  to  confirm vegetation types and condition. 

A follow up fauna survey was not considered to be warranted as the fauna survey results and assessments documented in the original Biodiversity Assessment (BA) were not affected by seasonality.  Statements of Commitment (SOC) that ensure biodiversity  values  are  maintained  or  improved  are  included  in  the  Environmental  Assessment,  developed  from  the mitigation measures detailed in the BA.  

One additional SoC is proposed, as a precautionary measure, to provide additional assurance that the proposal is unlikely to have a significant impact on hollow dependant threatened fauna species: 

 

Page 16: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  12   

Issue  Response 

EXISTING SOC 5:

If the removal of any hollow bearing trees is required, this activity would be preceded by a pre‐clearance check by a qualified ecologist including anabat survey and stag watching. 

The  approach of pre‐clearance  surveys has been  adopted  as  a precautionary measure  as  it  is  considered unlikely  that threatened  species occur within  the hollow onsite. This approach enables  the detection of hollow usage by  threatened species that may move onto the site between the project approval and works commencing and  is designed to minimise harm  to  resident  fauna. An additional SoC  is now proposed however,  to address  the unlikely situation  that a tree  to be removed provides important habitat for a threatened species, and provide guidance in this case: 

NEW SOC  

If pre‐clearance surveys identify hollow‐bearing trees that are significant to the viability of local threatened species populations (for example a threatened microbat roost tree) these trees would be retained and infrastructure would be redesigned to accommodate them.  

Offset plan  DECCW sought to amend SOC 2 regarding offsetting so as to include: 

A requirement for the offset plan to be submitted for approval prior to the commencement of works 

A  statement  that  the plan would offset  the  impact of  the development  for  the period  that  the  impact occurs  in 

accordance with DECCW’s ‘Principles for the Use of Biodiversity Offsets in NSW’ 

It is proposed to adopt DECCWs amendments and modify SOC 2 as set out below:  

SOC 2 MODIFICATION 

An Offset Plan will be prepared by an ecologist  consistent with  ‘maintain or  improve’ principles  for biodiversity 

outcomes, as  set out  in  the Biodiversity Assessment and  submitted  for approval prior  to  the  commencement of 

works.  The  plan would  be  developed  in  consultation with  the  landowner  and would  offset  the  impact  of  the 

development  for  the  period  that  the  impact  occurs  in  accordance  with  DECCW’s  ‘Principles  for  the  Use  of 

Biodiversity Offsets in NSW’ 

   

Page 17: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  13   

5.2 NSW OFFICE OF WATER 

Issue  Response 

Groundwater  interception  or  use requires licensing 

Section  6.1.1  states  that  “No  groundwater  extraction  at  the  proposal  site  is  planned  as  part  of  the  proposal”.  The 

installation of  the  solar array and  infrastructure would not affect  the net amount of water  reaching  the  surface of  the 

ground during rain or flooding events nor its ability to infiltrate and replenish groundwater systems. In the event water is 

required for panel washing, it would be sourced through commercial supplies.  Therefore, it is not considered that a license 

is required. 

No new SOC is considered warranted. 

Water Management Plan  NOW incorrectly notes that a “water management plan” would be included in the CEMP and OEMP.  

The  CEMP  and  OEMP  would  incorporate  surface  water  quality management  of  construction  impacts,  including  road 

construction works. SOC 48 of  the EA  includes provision  for monitoring of surface water quality  following heavy  rainfall 

events  in  the Erosion and Sediment Control  sub‐plan of  the CEMP, which addresses NOW’s  concerns  regarding  surface 

water quality monitoring. 

No new or modified SOC is considered warranted. 

Preparation  of  a  flood  management plan 

NOW incorrectly notes that a flood management plan would be included in the CEMP and OEMP. 

The Nyngan  area  is  prone  to  flooding  and  therefore  a  flood  consultant was  engaged  to  undertaken  an  assessment  of 

potential flood impacts. This has been provided as Appendix H in the EA. The flood study included: 

A review of available flood levels from the Nyngan April 1990 Flood Investigation (DWR 1990) 

Interpretation of the reported flood levels in order to determine potential flood levels for the Nyngan site 

Creation of flood inundation extent contours  

A further flood study or flood management plan is not considered warranted. 

No new or modified SOC is considered warranted. 

Page 18: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  14   

Issue  Response 

Provision of CEMP and OEMP to NOW for  review  prior  to  project commencement 

NOW indicates it requires the CEMP and OEMP to be provided to NOW for review prior to project commencement. 

SOC 49 of the EA states “The site CEMP and OEMP could be provided to the New South Wales Office of Water for review of 

soil and water management measures for construction and operation, if required”. 

It is now recommended that SOC 49 is modified as follows: 

SOC MODIFICATION 

The  site  CEMP  and OEMP would  be  provided  to  the New  South Wales Office  of Water  for  review  of  soil  and water 

management measures for construction and operation, prior to project commencement. 

Page 19: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  15

6 MODIFICATIONS TO THE PROPOSAL: SUMMARY 

As a result of the submissions from Government agencies, a number of changes have been made to the 

Statement of Commitments as follows: 

6.1 DELETED SOCS 

The surveys referred to in these SoCs have now been undertaken. They are documented in Appendix B.  

SOC 1 DELETED 

A supplementary flora survey during spring (early November) would be required to confirm if threatened flora 

species  including  Slender  Darling‐pea  and  Red  Darling‐pea  inhabit  the  higher  quality  derived  grass  and 

shrubland on the site. 

SOC 31 DELETED 

An additional  field survey would be undertaken  in  the eastern area of  the site  to confirm  the archaeological 

status of that area. The additional field survey would be undertaken in consultation with Registered Aboriginal 

Parties. 

6.2 NEW SOCS 

The following additional SoCs now accompany the proposal: 

SOC NEW  

If pre‐clearance  surveys  identify hollow‐bearing  trees  that are  significant  to  the viability of  local  threatened 

species  populations  (for  example  a  threatened  microbat  roost  tree)  these  trees  would  be  retained  and 

infrastructure would be redesigned to accommodate them. 

6.3 MODIFIED SOCS  

The following SoCs have had points removed, added or clarified. The number refers to the numbering in 

the publically exhibited EA. The revised SoCs are now presented in Appendix A (renumbered). 

SOC 2 MODIFICATION 

An  Offset  Plan  will  be  prepared  by  an  ecologist  consistent  with  ‘maintain  or  improve’  principles  for 

biodiversity outcomes, as set out  in the Biodiversity Assessment and submitted for approval prior to the 

commencement of works. The plan would be developed  in consultation with  the  landowner and would 

offset the  impact of the development for the period that the  impact occurs  in accordance with DECCW’s 

‘Principles for the Use of Biodiversity Offsets in NSW’ 

SOC 49 MODIFICATION 

The site CEMP and OEMP would be provided to the New South Wales Office of Water for review of soil 

and water management measures for construction and operation, prior to project commencement. 

 

Page 20: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  16   

7 CONCLUSION 

This Submissions Report responds to the comments and issues raised in submissions from the community 

and Government agencies following the public exhibition of the Nyngan Solar Farm EA. Specialist advice 

has been sought from the consultants  involved  in the original assessment  in preparing these responses. 

The  Submissions  Report  fulfils  the  requirements  of  Section  75H  of  the  Environmental  Planning  and 

Assessment Act 1979.  

In response to the submissions and on the basis of additional investigations: 

2 Statements of Commitment have been deleted  

1 new Statement of Commitment has been created 

2 Statements of Commitment have been modified 

In consideration of the assessment of the impacts from the project contained in the EA and the proposed 

mitigation measures committed to in the revised Statement of Commitments (included as Appendix A of 

this report and supported by additional studies included in Appendix B of this report), it is believed that 

all  relevant  issues  and  concerns  have  been  addressed  and  that  the  project  should  now  proceed  for 

approval by the Minister. 

 

 

Page 21: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  A‐I   

APPENDIX A REVISED STATEMENTS OF COMMITMENT The following tables constitute the revised Statements of Commitment to which the proponent commits, pending project approval, to manage the environmental 

impacts of the project. Bold entries are new or modified SoCs. Superseded SoCs have been deleted from this list. SoC numbering has been revised. 

 

Biodiversity 

SoC  Impact  Objective  Mitigation tasks  Project phase  Auditing 

1  Infrastructure  related 

biodiversity impacts 

Minimise  biodiversity 

impacts  

An Offset Plan will be prepared by an ecologist consistent with ‘maintain or improve’ principles 

for  biodiversity  outcomes,  as  set  out  in  the  Biodiversity  Assessment  and  submitted  for 

approval prior to the commencement of works. The plan would be developed  in consultation 

with the  landowner and would offset the  impact of the development for the period that the 

impact occurs  in  accordance with DECCW’s  ‘Principles  for  the Use of Biodiversity Offsets  in 

NSW’. 

Pre‐construction  CEMP 

2  Infrastructure  related 

biodiversity impacts 

Minimise  biodiversity 

impacts  

The  PV  array,  site  access  tracks  and  other  infrastructure  should  be  microsited  to  avoid 

constraints identified within the Biodiversity Assessment constraints mapping. These include: 

Stands of Woodland across the site 

Hollow bearing trees 

Isolated trees, where possible 

Areas of Myall Woodland EEC would be avoided. If infrastructure was to be placed within these 

areas  it  would  be  microsited  to  avoid  and  retain  Myall  individuals  particularly  in  areas  of 

regeneration. 

The denser patches of Coolibah‐Black Box Woodland EEC in the central section of the site would 

be avoided and  retained.  Infrastructure would be microsited  to avoid  the need  for  clearing  in 

this community. No development  that would  reduce  the  functionality of  these areas as  fauna 

movement corridors should be undertaken.  

Design phase  CEMP 

3  Infrastructure  related  Minimise  biodiversity  Biologically sensitive areas (listed above and displayed on the constraints map, Figure 6‐13 of the 

EA)  would  be  clearly  identified  throughout  construction  and  protected  from  the  direct  and 

Design phase  CEMP 

Page 22: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  A‐II   

SoC  Impact  Objective  Mitigation tasks  Project phase  Auditing 

biodiversity impacts  impacts  indirect  impacts of  the Proposal. Contractors and  staff will be made aware of  the  significance 

and sensitivity of these areas. 

4  Infrastructure  related 

biodiversity impacts 

Minimise  biodiversity 

impacts  

If the removal of any hollow bearing trees was required this activity would be proceeded by a 

pre clearance check by a qualified ecologist including anabat survey and stag watching. 

Design phase  CEMP 

5  Infrastructure  related 

biodiversity impacts 

Minimise  biodiversity 

impacts  

If  pre‐clearance  surveys  identify hollow‐bearing  trees  that  are  significant  to  the  viability of 

local  threatened  species  populations  (for  example  a  threatened microbat  roost  tree)  these 

trees would be retained and infrastructure would be redesigned to accommodate them. 

Pre‐construction 

Construction 

CEMP 

6  Infrastructure  related 

biodiversity impacts 

Minimise  biodiversity 

impacts  

Works will  avoid  impacts  to mature  eucalypts wherever  possible.  Tree  protection  standards 

should comply with Australian standard AS4970‐2009 Protection of trees on development sites 

(Standards  Australia,  2009).  Wherever  practicable,  excavations  and  vehicle/machinery 

movements will occur outside the canopy dripline of large eucalypts. 

Design phase  CEMP 

7  Construction impacts  Minimise  biodiversity 

impacts  

Where practical, timber from cleared trees should be relocated into areas of adjacent woodland 

to provide  foraging habitat  for Brown Tree  creepers, Grey‐crowned Babblers and Bush Stone‐

curlews, rather than removed or burnt. 

Construction  CEMP 

8  Construction impacts  Minimise  biodiversity 

impacts  

Existing farm tracks should be used wherever possible to minimise the number of new roads.  Construction  CEMP 

9  Construction impacts  Minimise  biodiversity 

impacts  

Perimeter fences should not contain barbed wire, particularly the top strands. If a cyclone mesh 

fence is to be used efforts should be made to increase the visibility to fast flying parrots. 

Construction  CEMP 

10  Construction impacts  Minimise  biodiversity 

impacts  

Works  should  be  planned  to  avoid  sensitive  times  for  threatened  species  Late  July  to  early 

December  for  Gray‐crowned  Babblers  (Counsilman  1979),  June  to  December  for  Brown 

Treecreepers  (Schodde  and  Tidemann,  2007),  May  to  December  for  Pink  cockatoos  and 

September to December for Superb Parrots. 

Construction  CEMP 

11  Construction impacts  Minimise  biodiversity  Activity would be minimised in the area adjacent to the Brown Treecreeper roost/nest site (refer 

to  Figure 6‐12 of  the EA) at all  times. No works would  take place within 100m of  the Brown 

Construction  CEMP 

Page 23: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  A‐III   

SoC  Impact  Objective  Mitigation tasks  Project phase  Auditing 

impacts  Treecreeper roost/nest site (refer to Figure 6‐12 of the EA).

12  Construction impacts  Minimise  biodiversity 

impacts  

Where cement is included in cable trench backfill, at least 20 centimetres of cement‐free topsoil 

will be replaced as the top layer in the backfill. 

Construction  CEMP 

13  Construction impacts  Minimise  biodiversity 

impacts  

Where practicable, whole sods will be removed with an excavator where these areas are well‐

vegetated with dense root systems. Sods will be stored in moist, shaded conditions and replaced 

following the works. Sod storage time will be minimised and sods will be replaced  in a manner 

that maximises the chances of re‐establishment. 

Construction  CEMP 

14  Construction impacts  Minimise  biodiversity 

impacts  

Excavated topsoil, subsoil will be stored separately and replaced in a manner that replicates the 

original profile as closely as possible.  

Construction  CEMP 

15  Construction impacts  Minimise  biodiversity 

impacts  

Where practicable, grass surfaces and shrubs will be retained or restored on  infrequently used 

vehicle routes. 

Construction  CEMP 

16  Construction impacts  Minimise  biodiversity 

impacts  

Site stabilisation, rehabilitation and revegetation will be undertaken without delay.  Construction  CEMP 

17  Construction impacts  Minimise  biodiversity 

impacts  

Works will  avoid  impacts  to mature  eucalypts wherever  possible.  Tree  protection  standards 

should comply with Australian standard AS4970‐2009 Protection of trees on development sites 

(Standards  Australia,  2009).  Wherever  practicable,  excavations  and  vehicle/machinery 

movements will occur outside the canopy dripline of large eucalypts. 

Construction  CEMP 

18  Construction impacts  Minimise  biodiversity 

impacts  

As a general rule, disturbed areas will be used preferentially for vehicle and machinery access, 

materials  laydown,  stockpiling of  cleared  vegetation  and  the deposition  and  retrieval of  spoil 

whenever practicable.  

Construction  CEMP 

19  Operational impacts  Minimise  biodiversity 

impacts  

Efforts should be made to minimise disturbance to the existing groundcover during construction. 

Construction and maintenance vehicles  should not access  the  site when  soils are very wet  to 

minimise soil compaction and disturbance.  

Operation  OEMP 

Page 24: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  A‐IV   

SoC  Impact  Objective  Mitigation tasks  Project phase  Auditing 

20  Construction impacts  Minimise  biodiversity 

impacts  

Works will be avoided during, and  immediately  following heavy  rainfall events  to protect soils 

and vegetation at the site. 

Construction  CEMP 

21  Construction impacts  Minimise  biodiversity 

impacts  

A weed management  plan would  be  developed  for  the  site  including  but  not  limited  to  the 

following outcomes; 

The control of noxious weeds recorded on the site 

Preventative measures for the spread or introduction of weeds 

Monitoring of control and preventative measures and ongoing adaptive management 

Construction  CEMP 

22  Construction impacts  Minimise  biodiversity 

impacts  

Laydown sites  for excavated spoil, equipment and construction materials will be weed‐free or 

treated for weeds wherever practicable. Sediment control materials should be weed free such as 

certified weed free hay bales or geotextiles. Imported materials such as sand and gravel will be 

sourced from sites which do not show evidence of noxious weeds or Phytophthora infection. 

Construction  CEMP 

23  Construction impacts  Minimise  biodiversity 

impacts  

If  dams  are  removed  during  site  development works,  alternative watering  points  should  be 

established to compensate for their loss and maintain similar habitat resources for native fauna. 

Construction  CEMP 

24  Construction impacts  Minimise  biodiversity 

impacts  

If used,  and where practicable, power poles  and overhead powerlines will be bird‐safe using 

flags or marker balls, large wire size and wire and conductor spacing. 

Construction  CEMP 

25  Construction impacts  Minimise  biodiversity 

impacts  

Log habitat removed during the construction phase will be reinstated following the works.  Construction  CEMP 

26  Construction impacts  Minimise  biodiversity 

impacts  

Trenches  should be  left open  for  the  least  time practical and would be  inspected  for  trapped 

fauna prior to back filling. Any trench sections  left open overnight would be  inspected early  in 

the morning and any trapped fauna removed. The use of ramps or ladders to facilitate trapped 

fauna escape is recommended if trenches are to be left open overnight. 

Construction  CEMP 

27  Operational impacts  Minimise  biodiversity  A groundcover management plan would be developed that would include regular monitoring of  Operation  OEMP 

Page 25: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  A‐V   

SoC  Impact  Objective  Mitigation tasks  Project phase  Auditing 

impacts  vegetation cover and composition and allow for adaptive management. This would include:

Advice  from an agronomist  in  relation  to preferred  species/varieties, establishment 

methods of alternative pastures and best practice management.  

Where information is lacking, trials may be required onsite. 

The  establishment  of  shade  tolerant  perennial  groundcover  across  the  cropping  and  exotic 

dominated grazing paddocks prior to the installation of the PV arrays. 

28  Operational impacts  Minimise  biodiversity 

impacts  

If  localised erosion  is detected, effective  treatments would be applied without delay,  such as 

hardening  with  mulch,  reseeding  and  covering  with  an  open  weave  jute  matting,  gypsum 

application  to  improve  structure and  infiltration, protection with geotextile  fabric or  localised 

flow dispersal and diversion structures. 

Operation  OEMP 

29  Operational impacts  Minimise  biodiversity 

impacts  

The space between the PV array rows should be maintained and kept clear to enable access by 

vehicles for ongoing weed control, and pasture renovation if required. 

Operation  OEMP 

30  Operational impacts  Minimise  biodiversity 

impacts  

Monitoring of  fauna  site habitat usage pre and post  construction  is  recommended 

but not considered essential. Operation  OEMP 

 

Indigenous Heritage 

SoC  Impact  Objective  Mitigation tasks  Project phase  Auditing 

31  Impact  on  local  Aboriginal 

community 

Minimise impact  Ongoing consultation would be undertaken with Registered Aboriginal Parties  All  CEMP 

OEMP 

 

Page 26: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  A‐VI   

Visual Amenity 

SoC  Impact  Objective  Mitigation tasks  Project phase  Auditing 

32  Deterioration  of  visual  amenity 

during construction 

Mitigate impacts  Measures  to  reduce  visual  impacts  during  construction,  including  but  not  limited  to  the 

following: 

Dust reduction throughout the construction process 

Prompt restoration of any earthworks required for the construction 

Clearing of existing vegetation would be kept to a minimum 

Construction  CEMP 

33  Deterioration  of  visual  amenity 

by  solar  panels  and  associated 

infrastructure 

Mitigate impacts  Measures include but are not limited to the following: 

Colour of above ground infrastructure to be sympathetic to the landscape character 

Underground cabling to be utilised if practical 

The design and location of ancillary works are to incorporate measures which would 

reduce the visual impact 

Construction 

Operation 

CEMP  

OEMP 

34  Deterioration  of  visual  amenity 

at surrounding residences 

Mitigate impacts  Visual screen planting  is to be undertaken  in the  form of boundary planting around 

the  solar  farm,  foreground  planting  at  affected  viewpoints  and  residential  tree 

planting 

Tree  planting  would  be  undertaken  in  consultation  with  relevant  landowners  to 

achieve  screening  for  homesteads with  a  high  visual  impact  to  strategically  block 

parts of the development 

Species typical of the area (mallee scrub) would be selected to enhance the existing 

landscape character 

Post construction  OEMP 

35  Creation of a visual attraction  Maximise  visual 

opportunities 

A designated viewing area may be provided where visitors would be able to safely view the solar 

farm and surrounding landscape. 

Construction 

Operation 

CEMP  

OEMP 

 

Page 27: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  A‐VII   

Noise 

SoC  Impact  Objective  Mitigation tasks  Project phase  Auditing 

36  Noise  impacts  to  sensitive 

receivers 

Compliance  Construction would be undertaken during standard working hours of: 

Monday – Friday: 7am to 6pm 

Saturday: 8am to 1pm 

Sunday and public holidays: No work 

All  CEMP  

OEMP 

37  Noise  impacts  to  sensitive 

receivers 

Compliance  Construction staff would be made aware of noise sensitive receivers and would be made aware 

of noise reduction options.  

All  CEMP  

OEMP 

38  Noise  impacts  to  sensitive 

receivers 

Compliance  Periods of respite would be provided in the case of unavoidable maximum noise level events.  All  CEMP  

OEMP 

39  Noise  impacts  to  sensitive 

receivers 

Compliance  Reasonable  and  feasible measures  to  reduce  noise would  be  implemented  and  could  include 

reducing the throttle setting and turning off equipment when not being used. 

All  CEMP  

OEMP 

40  Noise  impacts  to  sensitive 

receivers 

Compliance  Equipment and plant would be maintained to reduce noise emissions.  All  CEMP  

OEMP 

41  Noise  impacts  to  sensitive 

receivers 

Compliance  Mobile plant clustering near residences would be avoided.  All  CEMP  

OEMP 

42  Noise  impacts  to  sensitive 

receivers 

Compliance  A 24 hour toll‐free contact phone number for enquiries during the works would be provided.  All  CEMP  

OEMP 

Page 28: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  A‐VIII   

SoC  Impact  Objective  Mitigation tasks  Project phase  Auditing 

43  Noise  impacts  to  sensitive 

receivers 

Compliance  A  documented  complaints  process  would  be  implemented  and  would  include  an  escalation 

procedure so that if a complainant is not satisfied there is a clear path to follow. 

All  CEMP  

OEMP 

44  Noise  impacts  to  sensitive 

receivers 

Compliance  Where complaints occur safeguards would be  reviewed  to determine  if  further safeguards are 

required or possible.  

All  CEMP  

OEMP 

45  Noise  impacts  to  sensitive 

receivers 

Consultation  Consultation with neighbours within 1 kilometre of  the  site would occur prior  to  construction 

commencing and would focus on identifying particular times of inconvenience. 

Pre‐construction  CEMP 

 

Hydrology and Water Quality 

SoC  Impact  Objective  Mitigation tasks  Project phase  Auditing 

46  Deterioration  of  water  quality 

(Surface Water) 

Minimise risk  Infrastructure  placement,  including  tracks,  substations,  control  buildings,  stockpiles,  and  site 

compounds and turnaround areas, would not be sited within 40 metres of a major drainage line 

or water course. 

Detailed design  CEMP 

47  Deterioration  of  water  quality 

(Surface Water) 

Achieve  neutral  or 

beneficial  water  quality 

impact 

The proponent would prepare an Erosion and Sediment Control Plan (ESCP) as a sub plan of the 

Construction Environmental Management Plan. This plan would include the following provisions: 

Sediment traps would be installed wherever there is potential for sediment to collect 

and enter waterways 

Stockpiles generated as a result of construction activities would be bunded with silt 

fencing, (mulch bunds or similar) to reduce the potential for runoff from these areas 

On  the  steeper  slopes  check  banks  would  be  installed  across  the  trenchline,  as 

appropriate, following closure of the trench. These would discharge runoff to areas of 

stable vegetation 

Construction  CEMP 

Page 29: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  A‐IX   

SoC  Impact  Objective  Mitigation tasks  Project phase  Auditing 

Stabilisation  and  site  remediation  would  be  undertaken  as  soon  as  practicable 

throughout and post construction 

Soil  and water management  practices would  be  developed  as  set  out  in  Soils  and 

Construction Vol. 1 (Landcom 2004) 

Monitoring  of  surface water  quality would  be  undertaken  following  heavy  rainfall 

events 

48  Deterioration  of water  quality 

(Surface Water) 

Achieve  neutral  or 

beneficial  water  quality 

impact 

The  site  CEMP  and OEMP would  be  provided  to  the New  South Wales Office  of Water  for 

review  of  soil  and  water  management  measures  for  construction  and  operation,  prior  to 

project commencement. 

Construction 

Operation 

CEMP 

OEMP 

49  Flooding  Minimise impact  Low‐lying areas of the site would be avoided for stockpiling and storage of plant, equipment and 

infrastructure.  

Construction  CEMP 

50  Flooding  Minimise impact  Disturbed areas of the site would be rehabilitated as soon as possible as works progress.   Construction  CEMP 

51  Water supply   Minimise risk  Undertake  liaison with representatives of Bogan Shire Council regarding the potential supply of 

construction water. 

Construction  CEMP 

52  Deterioration  of  water  quality 

(Surface Water) 

Minimise risk  All vehicles onsite would follow established trails and minimise onsite movements.  Construction 

Operation 

CEMP 

OEMP 

53  Deterioration  of  water  quality 

(Surface and Ground Water) 

Minimise risk  Maintenance or re‐fuelling of machinery would be carried out on hard‐stand in accordance with 

industry standards for fuel transfer. 

Construction  CEMP 

54  Deterioration  of  water  quality 

(Surface and Ground Water) 

Minimise risk  Carry  out  dust  suppression  as  required  through  either  watering  or  chemical  means 

(environmentally friendly polymer based additives to water).  

Construction 

Decommissioning 

CEMP 

Page 30: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  A‐X   

SoC  Impact  Objective  Mitigation tasks  Project phase  Auditing 

55  Deterioration  of  water  quality 

(Surface Water) 

Achieve  neutral  or 

beneficial  water  quality 

impact 

A  Site  Restoration  Plan  (SRP) would  be  prepared  as  part  of  the  Construction  Environmental 

Management Plan. This would set out protocols for rehabilitation of disturbed areas as soon as 

possible after soil disturbance. It would include: 

Site preparation 

Stabilisation 

Revegetation  

Monitoring 

Construction 

Decommissioning 

CEMP 

56  Deterioration  of  water  quality  

(Surface and Ground Water) 

Minimise risk  A Spill Response Plan  would be prepared as part of the  CEMP and OEMP including: 

Identify persons  responsible  for  implementing  the plan  if a  spill of a dangerous or 

hazardous chemical/waste would occur 

Identify all chemicals required for the proposal, including physio‐chemical properties, 

risks posed to water quality objectives and appropriate methods of storage of these 

chemicals 

Locate Material Safety Data Sheets (MSDS) for all chemical inventories at on site and 

readily available 

Comply with manufacturers recommendations in relation to application and disposal 

where chemicals are used 

Report any spill that occurs to the Construction Manager regardless of the size of the 

spill 

Establish clearly defined works and refuelling areas 

Spill protocols in this plan would dictate when the EPA would be notified 

Chemical / fuel storage areas would be  identified, and be bunded to prevent  loss of 

any pollutants 

Hydrocarbon spill kits would be stored at  the site. A number of site staff are  to be 

trained in the use of the spill kits 

Notification to the NSW DECCW EPA in the event of any spill that had the potential to 

Construction 

Operation 

Decommissioning 

CEMP 

OEMP 

Page 31: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  A‐XI   

SoC  Impact  Objective  Mitigation tasks  Project phase  Auditing 

pollute waters 

57  Deterioration  of  water  quality  

(Surface and Ground Water) 

Minimise risk  Monitor bunded infrastructure to ensure that volume of oil could be fully contained in the event 

of leak. 

Operation  OEMP 

58  Deterioration  of  water  quality  

(Surface and Ground Water) 

Minimise risk  Maintain septic systems, if installed, to meet appropriate Australian standards.  Construction 

Operation 

Decommissioning 

CEMP 

OEMP 

59  Flooding  Minimise impact  Kiosk  transformers  and  central  inverters  would  be  raised  by  0.5  metre  subject  to  final 

engineering designs to prevent impacts in the event of a 1:250 year flood. 

Construction  CEMP 

 

Traffic and Access 

SoC  Impact  Objective  Mitigation tasks  Project phase  Auditing 

60  Safety and asset protection  Minimise risk  The proponent would develop and implement a Traffic Management Plan (TMP) in consultation 

with  roads  authorities  to  facilitate  appropriate management  of  potential  traffic  impacts.  The 

TMP would include provisions for: 

 Scheduling of deliveries and managing timing of transport  

Limiting the number of trips per day  

Undertaking community consultation before and during all haulage activities 

Designing  and  implementing  temporary  modifications  to  intersections,  roadside 

furniture, stock grids and gates  

Managing  the  haulage  process,  including  the  erection  of warning  and/or  advisory 

speed  signage  prior  to  isolated  curves,  crests,  narrow  bridges  and  change  of  road 

Construction  CEMP 

Page 32: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  A‐XII   

SoC  Impact  Objective  Mitigation tasks  Project phase  Auditing 

conditions 

Designation of a speed limit would be placed on all of the roads that would be used 

primarily by construction traffic  

Preparation of a Transport Code of Conduct  to be made available to all contractors 

and staff  

Identification of a procedure to monitor the traffic  impacts during construction and 

work methods modified (where required) to reduce the impacts 

Provide  a  contact  phone  number  to  enable  any  issues  or  concerns  to  be  rapidly 

identified and addressed through appropriate procedures 

Reinstatement of pre‐existing conditions after temporary modifications to the roads 

and pavement along the route 

61  Community  safety  and 

convenience 

Minimise impact  The proponent would use a  licensed haulage contractor with experience  in transporting similar 

loads,  responsible  for obtaining all  required approvals and permits  from  the RTA and Councils 

and for complying with conditions specified in those approvals. 

Construction  CEMP 

62  Safety and asset protection  Minimise impact  The  proponent  would  prepare  road  dilapidation  reports  covering  pavement  and  drainage 

structures  in  consultation with  roads authorities  for  the  route prior  to  the  commencement of 

construction and after construction is complete.  

Construction  CEMP 

63  Safety and asset protection  Minimise impact  The  proponent would   repair  any  damage  resulting  from  the  construction  traffic  (except  that 

resulting from normal wear and tear) as required during and after completion of construction at 

the proponent’s cost or, alternately, negotiate an alternative for road damage with the relevant 

roads authority. 

Construction  CEMP 

64  Noise impacts  Minimise impact  Route  specific mitigation measures,  which   will  be   investigated  and  detailed  further  in  the  

Traffic Management Plan, include potential for utilising access routes diverted around the town 

via Cemetery Road or Tottenham Road  in  the event of  several  complaints occurring  regarding 

additional traffic noise as a result of vehicle deliveries. 

Construction  CEMP 

Page 33: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  A‐XIII   

SoC  Impact  Objective  Mitigation tasks  Project phase  Auditing 

65  Noise impacts  Minimise impact  The Community Consultation Plan would  include consultation with potential affected  residents 

on Hoskins Street, Pangee Street and other local roads as a result of additional traffic noise. 

Construction  CEMP 

66  Air quality  Minimise impact  Water carts would be used on unsealed  roads  in  the event  that dust becomes a problem as a 

result of construction vehicle movements. 

Construction  

Operation 

CEMP  

OEMP 

67  Soils  Minimise impact  Erosion  and  sediment  controls would  be  implemented  at  unsealed  roads  frequently  used  for 

vehicle access e.g. East Nyngan Road. 

Construction 

Operation 

CEMP  

OEMP 

 

Soils and Landforms 

SoC  Impact  Objective  Mitigation tasks  Project phase  Auditing 

68  Erosion  Minimise impact  Progressive  Erosion  and  Sediment  Control  Plans  would  be  prepared  for  the  site,  including 

controls at drainage lines and slopes. 

Construction  CEMP 

69  Erosion  Minimise risk  Erosion and sediment control plans would include measures from controlling erosion at unsealed 

roads where impacts could occur from excessive vehicle use. 

Construction 

Operation 

CEMP  

OEMP 

70  Erosion  Minimise impact  Cable trenches would be dug beneath or beside internal access roads to minimise disturbance.  Construction  CEMP 

71  Soil quality  Minimise risks  Subsoil would  be  separated  from  topsoil  for  rehabilitation  purposes.  Topsoil  from  excavation 

would  be  stockpiled  and  replaced.  On  steep  slopes,  topsoil  would  be  stabilised.  Any  excess 

subsoil would be removed from the site and disposed of at an appropriate fill storage site. 

Construction  CEMP 

Page 34: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  A‐XIV   

SoC  Impact  Objective  Mitigation tasks  Project phase  Auditing 

72  Soil quality  Minimise impact  Avoid compaction of soil resulting from vehicle access and laying of materials particularly during 

saturated soil conditions, and remediate as necessary. 

Construction  CEMP 

73  Soil loss or stability of landform 

loss 

Minimise risks  Concrete wash would be deposited in an excavated area, below the level of the topsoil, or in an 

approved landfill site. Where possible, waste water and solids would be reused onsite. 

Construction  CEMP 

74  Soil loss or stability of landform 

loss 

Minimise risks  Access  routes  and  tracks  would  be  confined  to  already  disturbed  areas,  where  possible.  All 

contractors would be advised to keep to established tracks. 

Construction  CEMP 

75  Soil quality  Minimise risks  A spill response plan would be developed for all phases of the project. This would include trigger 

points of when to notify the DECCW. 

Construction 

Decommissioning  

Operation 

CEMP  

OEMP 

76  Soil loss or stability of landform 

loss Minimise impact 

If runoff below panels result in localised erosion, the affected soils at the site should be treated 

and protected without delay.  Operation  OEMP 

77  Soil loss or stability of landform 

loss Minimise risk 

The proponent would routinely monitor soil condition and vegetation cover below the array and 

liaise with the landowner regarding stock and vegetation management issues as required. Operation  OEMP 

78  Soil quality  Minimise risk  Site restoration plan would be  implemented to  include deep rooted species to prevent dryland 

salinity. 

Construction 

Operation 

CEMP 

OEMP 

79  Soil quality  Minimise risks  The  substation  augmentation would  include provision of  a bunded  container  to  a  capacity of 

110% and regularly inspected and maintained to ensure leaks are not present. 

Construction 

Operation 

CEMP 

OEMP 

 

Page 35: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  A‐XV   

Historic Heritage 

SoC  Impact  Objective  Mitigation tasks  Project phase  Auditing 

80  Disturbance  to  a  potential 

heritage item or relic 

Minimise disturbance  In the event of an item of heritage significance being uncovered at the proposal site after works 

commence,  the NSW Heritage Branch  (Department of  Planning)  should be  contacted  prior  to 

further work being undertaken at the site. 

Construction 

Decommissioning 

CEMP 

 

Air Quality and Climate 

SoC  Impact  Objective  Mitigation tasks  Project phase  Auditing 

81  Air quality  Minimise risks  Dust  levels  at  stockpile  sites  would  be  visually  monitored.  Dust  suppression  would  be 

implemented if required (through either watering or chemical means ‐ environmentally friendly 

polymer based additives to water). Stockpiles would be stabilised (covered or seeded). 

Construction  CEMP 

82  Air quality  Minimise risks  Water carts would be used on unsealed access roads regularly during all phases of the project to 

prevent dust impacts. This safeguard would be applied to access roads in use only. 

All  CEMP 

OEMP 

83  Air quality  Minimise risks  Should  a  complaint  relating  to  dust  by  a  resident  be  received,  it  would  be  managed  in 

accordance with a complaints handling process. Response to the compliant could  include dust 

monitoring, assessment of dust gauges and identification of any additional mitigation measures, 

where required. 

Construction  CEMP 

 

Waste Management and Resource Use 

SoC  Impact  Objective  Mitigation tasks  Project phase  Auditing 

84  Waste generation  Minimise  waste  and 

maximise  recycling  of 

materials 

The proponent would prepare a Waste Management Plan to be included within the Construction 

Environmental Management Plan. It would include but not be limited to the following:  

The scope for reuse and recycling would be evaluated 

Construction 

Operation 

CEMP 

OEMP 

Page 36: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  A‐XVI   

SoC  Impact  Objective  Mitigation tasks  Project phase  Auditing 

Provision for recycling would be made onsite 

Wastes would be disposed of at appropriate facilities 

Toilet  facilities  would  be  provided  for  onsite  workers  and  sullage  from  the 

contractor’s  pump  out  toilet  facilities  would  be  disposed  at  the  local  sewage 

treatment plants or other suitable facility agreed to by Council 

Excavated material would be used in road base construction where possible. Surplus 

material would be disposed of  in appropriate  locations on  site  (on agreement with 

the landowner), finished with topsoil, and revegetated 

85  Waste generation  Maximise  recycling  of 

materials 

PV modules would be recycled, where possible.  Decommissioning   

 

Socioeconomic and Community 

SoC  Impact  Objective  Mitigation tasks  Project phase  Auditing 

86  Impact on current land use  Minimise impact  Develop,  implement and monitor the effects of a Site Restoration Plan. The plan would aim to 

stabilise disturbed areas. The Plan would consider: 

Appropriate stabilisation techniques across the precincts 

Suitable  species  for  re‐seeding  (native,  locally  occurring  species  would  be  given 

preference in areas dominated by native cover) 

Monitoring for weed and erosion issues 

Construction  

Decommissioning 

CEMP 

87  Impact on current land use  Minimise disruption  Liaison would be undertaken with neighbouring  landowners  to provide  information about  the 

timing  and  routes  to be used during  construction  and decommissioning.  This  could be  in  the 

form of advertising and provision of a contact point  for  further  inquiries. The aim would be to 

reduce the risk of interference with agricultural activities on affected roads and road verges. 

Construction  CEMP 

Page 37: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  A‐XVII   

SoC  Impact  Objective  Mitigation tasks  Project phase  Auditing 

88  Affect on local community  Maximise  positive 

impact of proposal 

Liaise  with  local  industry  representatives  to  maximise  the  use  of  local  contractors  and 

manufacturing facilities in the construction and decommissioning phases of the project. 

Construction  CEMP 

89  Affect on local community  Maximise  positive 

impact of proposal 

Liaise with the local visitor information centres to ensure that construction and decommissioning 

timing  and  haulage  routes  are  known  well  in  advance  of  works  and  to  the  extent  practical 

coordinated with local events, such as the Nyngan Ag Expo. 

Construction  CEMP 

90  Affect on local community  Maximise  positive 

impact of proposal 

Make available employment opportunities and  training  for  the ongoing operation of  the  solar 

farm to local residents where reasonable. 

Operation  OEMP 

 

Mineral Resources and Land Use Impacts 

SoC  Impact  Objective  Mitigation tasks  Project phase  Auditing 

91  Conflict  with  mineral 

exploration 

Minimise conflict  Consultation  with  St.  Barbara  Limited  (mineral  lease  holder)  would  occur  prior  to 

commencement of construction.  

Pre‐construction  CEMP 

92  Impact on current land use  Minimise impacts  A Site Restoration Plan would be developed to ensure stabilisation of disturbed areas as quickly 

as possible. The Plan would consider: 

Appropriate stabilisation techniques across the precincts 

Suitable  species  for  re‐seeding  (native,  locally  occurring    species  would  be  given 

preference) in areas dominated by native cover 

Monitoring for weed and erosion issues 

Construction  

Decommissioning 

CEMP 

93  Impact on current land use  Minimise disruption  Liaison would be  undertaken with  neighbouring  landowners  and  landowners  adjoining  access 

roads,  to provide  information about  the  timing and  routes  to be used during construction and 

decommissioning. This could be  in  the  form of advertising and provision of a contact point  for 

further inquiries. The aim would be to reduce the risk of interference with agricultural activities 

Construction  CEMP 

Page 38: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  A‐XVIII   

SoC  Impact  Objective  Mitigation tasks  Project phase  Auditing 

on affected roads and road verges.

94  Impact on current land use  Minimise impact  Consideration would be given to the grazing of sheep beneath the panels.   Operation  OEMP 

 

Health and Safety 

SoC  Impact  Objective  Mitigation tasks  Project phase  Auditing 

95  Radiation exposure from EMFs  Minimise exposure  Adhere to standard industry approaches and policies with respect to EMF through maintenance 

of adequate easements around transmission lines. 

Operation  OEMP 

96  Radiation exposure from EMFs  Minimise exposure  The  substation  upgrade  and  transmission  lines  would  be  located  as  far  as  practical  from 

residences,  farm  sheds, and yards  in order  to  reduce  the potential  for both chronic and acute 

exposure. 

Operation  OEMP 

 

Fire and Bushfire Issues and Impacts 

SoC  Impact  Objective  Mitigation tasks  Project phase  Auditing 

97  Bushfire risk  Minimise risk The  proponent  would  prepare  a  Bushfire  Management  Plan  as  part  of  the  Construction 

Environmental Management  Plan  and Operation  Environmental Management  Plan.  The Rural 

Fire  Service  and NSW  Fire  Brigade would  be  consulted  in  regard  to  its  adequacy  to manage 

bushfire  risks  during  construction,  operation  and  decommissioning.  The  plan  would  as  a 

minimum include: 

Hot‐work procedures, asset protection zones, safety, communication, site access and 

response protocols  in the event of a fire originating  in the solar farm  infrastructure, 

or in the event of an external wildfire threatening the solar farm or nearby persons or 

property 

Fire response planning would address any potential for dangerous gas emissions from 

Construction 

 Operation  

Decommissioning 

CEMP 

OEMP 

Page 39: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  A‐XIX   

SoC  Impact  Objective  Mitigation tasks  Project phase  Auditing 

the solar farm during a fire event to affect firefighters and neighbouring residents 

Flammable  materials  and  ignition  sources  brought  onto  the  site,  such  as 

hydrocarbons, would be handled and stored as per manufacturer’s instructions 

During  the  construction  phase,  appropriate  fire  fighting  equipment would  be  held 

onsite when the fire danger is very high to extreme, and a minimum of one person on 

site  would  be  trained  in  its  use.  The  equipment  and  level  of  training  would  be 

determined in consultation with the local RFS 

Asset  protection  zones  (APZs),  based  on  the  RFS  Planning  for  Bushfire  Protection, 

would be maintained around the site buildings and in the transmission line corridor. 

Workplace health and  safety protocols would be developed  to minimise  the  risk of 

fire for workers during construction and during maintenance in the control room and 

amenities 

Fire extinguishers would be stored onsite in each of the site buildings 

98  Bushfire risk  Minimise risk If  sowing of pasture  grasses  in  the  PV  array  area  is  required,  low  growing  species  should be 

selected. 

Construction 

Operation  

CEMP 

OEMP 

99  Bushfire risk  Minimise risk Pasture would be maintained at a low height (<100mm) below the PV array using sheep grazing 

or slashing. Operation   OEMP 

100  Bushfire risk  Minimise risk Appropriate firefighting equipment would be maintained on the site during the operation of the 

solar farm, including protective clothing. Staff would be trained in its use. Operation   OEMP 

101  Bushfire risk  Minimise risk A formal response procedure would be developed for operation staff at the solar farm, including 

notification of neighbouring and downwind landholders if required. Operation   OEMP 

102  Bushfire risk  Minimise risk 

The  transformers  would  be  bunded  to  a  capacity  of  110%  and  regularly  inspected  and 

maintained to ensure leaks do not present a fire hazard, and to ensure the bunded area is clear 

(including removing any rainwater). 

Operation   OEMP 

Page 40: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  B‐I   

APPENDIX B ADDITIONAL INVESTIGATIONS    

Page 41: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  B‐II   

B.1 FLORA ADDENDUM    

Page 42: Nyngan Solar Farm Submissions Report Final v1

Biodiversity Assessment

Addendum

NYNGAN SOLAR FARM

DECEMBER 2010

Page 43: Nyngan Solar Farm Submissions Report Final v1

Nyngan Solar Farm Biodiversity Assessment Addendum

1/216 carp st (po box470) bega nsw 2550 australia t 61 2 6492 8333 f 61 2 6494 7773

web: www.nghenvironmental.com.au email: [email protected]

206/410 elizabeth st

surry hills nsw 2010 australia

t 61 2 8202 8333 f 61 2 9211 1374

102/63-65 johnston st (po box 5464)

wagga wagga nsw 2650 australia

t 61 2 6971 9696 f 61 2 6971 9693

unit 9/65 tennant st (po box 1037)

fyshwick act 2609 australia

t 61 2 6280 5053 f 61 2 6280 9387

suite 6/234 naturaliste tce

dunsborough wa 6281 australia

t 61 8 9759 1985 f 61 2 6494 7773

Document Verification

Job title: Nyngan Solar Farm Biodiversity Assessment

Addendum

Project File

Name

\\10.0.11.1\Active\Projects\2010\Infigen Energy\Nyngan BA Targeted Survey -

1550\Report\Draft\Nyngan BA addendum v1.0.docx

Revision Date Prepared by Checked by Approved by

V1.0 01/12/10 Dave

Maynard

Brooke

Marshall

Brooke

Marshall

nghenvironmental prints all documents on sugar cane paper made from 100% bagasse (a by-product of sugar production).

Page 44: Nyngan Solar Farm Submissions Report Final v1

Nyngan Solar Farm Biodiversity Assessment Addendum

Nyngan BA addendum v1.0.docx

i

TABLE OF CONTENTS

1 INTRODUCTION ...................................................................................................... 1

2 METHODS ............................................................................................................... 2

3 RESULTS ............................................................................................................... 4

3.1 TARGETED SURVEYS ...................................................................................................................... 4

3.2 ADDITIONAL AREAS SURVEYED ..................................................................................................... 5

3.3 VEGETATION CONDITION AT THE TIME OF THE SURVEY ............................................................... 6

4 CONCLUSIONS AND RECOMMENDATIONS ............................................................. 9

5 REFERENCES ......................................................................................................... 11

APPENDIX A REVISED FLORA SPECIES LISTS ............................................................. A-1

Tables

Table 1-1 Threatened flora species with potential to occur on site ............................................................. 1

Table 3-1 Additional survey sites and corresponding vegetation types and condition ................................ 6

Figures

Figure 2-1 Locations of targeted threatened species searches and additional survey points at the Nyngan

Solar Farm site ............................................................................................................................................ 3

Figure 3-1 Broughton Pea (Swainsona procumbens) in flower at the subject site ....................................... 4

Figure 3-2 Grazed Myall regeneration in the eastern paddock at the proposal site. ................................... 5

Figure 3-3 An area dominated by *Lepidium spp. In the northern area of the central section of the site ... 7

Figure 3-4 Good condition native pasture in the north of the eastern paddock. ......................................... 7

Figure 3-5 Area of high fdiversity grassland in the north of the eastern paddock ....................................... 8

Page 45: Nyngan Solar Farm Submissions Report Final v1

Nyngan Solar Farm Biodiversity Assessment Addendum

Nyngan BA addendum v1.0.docx

1

1 INTRODUCTION

A Biodiversity Assessment was completed in October 2010 as part of an environmental assessment for

the proposed Nyngan Solar Farm located in central western New South Wales (nghenvironmental

2010). The Department of Planning issued Director Generals Requirements on 01 September 2010

indicating that the EA must specifically consider threatened flora species and Endangered Ecological

Communities that have potential to occur on the site. The seasonal timing of the fieldwork for the

Biodiversity Assessment (winter 2010) was not suitable for the detection of the following two

threatened species with potential to occur on the site:

Table 1-1 Threatened flora species with potential to occur on site

Species Status

Red Darling-pea (Swainsona plagiotropis) Vulnerable (TSC, EPBC)

Slender Darling-pea (Swainsona murrayana) Vulnerable (TSC, EPBC)

To determine if these threatened species were at risk from the proposed development, the following

recommendation was made within the original Biodiversity Assessment:

“Supplementary surveys, prior to finalisation of infrastructure layout, are required to confirm the

assumptions of this assessment as follows:

o A supplementary flora survey during spring (early November) would be required to

confirm if threatened flora species including Slender Darling-pea and Red Darling-pea

inhabit the higher quality derived grass and shrubland on the site. This survey would

be undertaken prior to finalisation of infrastructure layout and prior to project

determination. The probability of these species occurring is considered low and the

surveys would be undertaken to verify the assumptions made in the Assessment of

Significance.”

This supplementary survey report addresses this recommendation and presents:

The methods and results of targeted searches for identified subject species, and other State-

and Commonwealth-listed threatened species potentially present at the subject site

Updated information regarding seasonal variation in species composition and vegetation

condition and distribution at the site

Further recommendations required to manage biodiversity impacts of the proposal

Page 46: Nyngan Solar Farm Submissions Report Final v1

Nyngan Solar Farm Biodiversity Assessment Addendum

Nyngan BA addendum v1.0.docx

2

2 METHODS

The supplementary survey was undertaken by two botanists (Dave Maynard and Kelly Simpson) on 3rd

November, 2010.

The targeted searches involved searches on foot through all areas of suitable habitat within the

development envelope. Areas of marginal habitat were also included as a precautionary measure and

searched from a slow moving vehicle. Searches were conducted in pairs, employing linear transects

spaced 10m apart. A total of 19 person hours was spent on the targeted search transects and vehicle-

based surveys covering approximately 144 hectares. A search at the location of a known record of the

Red Darling-pea approximately 35 kilometres north-west of the site was also undertaken to confirm

flowering time.

During targeted searches, particular attention was paid to native species composition and diversity to

confirm condition assumptions made during the original survey for the Biodiversity Assessment. Other

areas not inspected during the original survey which were later included within the development

envelope were surveyed to ascertain vegetation types and conditions. The locations of these surveys

are indicated on (Figure 2-1).

Page 47: Nyngan Solar Farm Submissions Report Final v1

Nyngan Solar Farm Biodiversity Assessment Addendum

Nyngan BA addendum v1.0.docx 3

Figure 2-1 Locations of targeted threatened species searches and additional survey points at the Nyngan Solar Farm site

Page 48: Nyngan Solar Farm Submissions Report Final v1

Nyngan Solar Farm Biodiversity Assessment Addendum

Nyngan BA addendum v1.0.docx

4

3 RESULTS

3.1 TARGETED SURVEYS

None of the threatened species targeted during the survey were recorded at the subject site however,

the more common Broughton Pea (Swainsona procumbens) was detected on the site in numerous

locations in full flower and fruit (Figure 3-1). A search was conducted at a known location for the Red

Darling-pea (Swainsona plagiotropis) to confirm flowering times but it was not located. However, two

individuals of Swainsona campylantha were detected during the search.

Climatic conditions had been favourable prior to the survey with good rains in the preceding weeks

and numerous native wild flowers were in flower at the site, including species of Swainsona. This

suggests that it is likely that if the threatened species targeted at the site were present they would

have been detectable.

Figure 3-1 Broughton Pea (Swainsona procumbens) in flower at the subject site

During the targeted surveys two small areas of Myall regeneration were identified in the eastern

paddock that was not detected during the original survey (Figure 3-2). These areas are within the

development envelope and are likely to be impacted by the proposal. Individuals within these areas

exhibited evidence of being grazed relatively heavily by stock. Given the small size of the patches, the

levels of disturbance and the occurrence of more extensive areas of Myall Woodland within the site

boundary (including regeneration) the clearing of these small patches is not considered to alter the

assumptions made in the original Biodiversity Assessment. Extensive areas of Myall Woodland were

Page 49: Nyngan Solar Farm Submissions Report Final v1

Nyngan Solar Farm Biodiversity Assessment Addendum

Nyngan BA addendum v1.0.docx

5

also detected in the locality and at the regional scale when travelling to the location of the known

record of the Red Darling-pea.

The declared noxious weed, Mexican Poppy (*Argemone ochroleuca subsp. ochroleuca) was detected

on a disturbed embankment adjacent to the dam in the south of the central areas of Black Box

Woodland. This is listed as a Class 5 noxious weed within the Bogan local control area and the

requirements in the Noxious Weeds Act 1993 for a notifiable weed must be complied with.

Figure 3-2 Grazed Myall regeneration in the eastern paddock at the proposal site.

3.2 ADDITIONAL AREAS SURVEYED

Due to refinements to the site boundary and development envelope (DE) following the original surveys

in July 2010, several areas within the revised DE had not been completely surveyed. These areas were

included in the current survey (Figure 2-1). Vegetation types and condition are summarized in Table

3-1. Generally these areas were found to be similar in composition and condition to adjacent areas

included in the original survey. Site 3 (south of the piggery) was located in a paddock that showed

evidence of past tilling. At the time of the survey this area had been colonised predominately by native

Sclerolaena and Atriplex species and exotic grasses however, given current land management practices

it is likely that it will be tilled in the future and planted with exotic pasture species. Due to the high

levels of disturbance, the area is not considered to be representative of a derived grassland or

shrubland and is not considered to comprise Black Box Woodland EEC.

Page 50: Nyngan Solar Farm Submissions Report Final v1

Nyngan Solar Farm Biodiversity Assessment Addendum

Nyngan BA addendum v1.0.docx

6

Vegetation condition was rated according to the following four-point scale, focusing on floristic

integrity in the groundcover and shrub layers:

Exotic Groundlayer dominated by exotics, native shrubs and trees sparse or absent

Poor Understorey dominated by one or two native grass or shrub species, <5 native forbs

Moderate Understorey dominated by native grasses or shrubs, 5-11 native forb species present

Good Understorey dominated by native grasses or shrubs with a diversity of forbs (at least 12

native forb species).

These classes are considered most relevant for vegetation types with a naturally diverse grassy

groundcover and shrub layer, such as the woodland and natural grassland observed on the site.

An updated species list with additional species recorded during the survey is included as Appendix A.

Table 3-1 Additional survey sites and corresponding vegetation types and condition

Site Community and location Dominant species Condition Significance

1 Black Box Woodland/Myall Woodland derived grass/shrubland

- alluvial clays

MGA 521426 6505455

Chloris truncata, Austrodanthonia spp., Austrostipa spp., Rhodanthe corymbiflora

Moderate-good

Moderate

2 Derived grass/shrubland

- alluvial clays

MGA 520497 6505756

Chloris truncata, Enteropogon acicularis, Sclerolaena tricuspis, Sclerolaena birchii

Poor-moderate

Low-moderate

3 Native shrubland

- disturbed area previously tilled

MGA 519453 6504841

Sclerolaena diacantha, Sclerolaena tricuspis, Atriplex sp., *Hordeum leporinum

Poor Low

4 Exotic pasture

- alluvial clays, dry area

MGA 519706 6505846

*Hordeum leporinum, *Trifolium spp., Sclerolaena spp.

Exotic Low

3.3 VEGETATION CONDITION AT THE TIME OF THE SURVEY

Favourable rains in the weeks preceding the survey had lead to vigorous vegetation growth across the

site. In general, the condition classes assigned in the original Biodiversity Assessment were confirmed

during the recent survey. Areas of the western paddocks were heavily infested with exotic annual

grasses but these were interspersed with predominately native vegetation. Areas to the north of the

Black box Woodland remnants in the centre of the site were dominated by exotic forbs such as

*Lepidium spp. (Figure 3-3).

Species diversity had increased dramatically in the northern section of the eastern paddock (Figure 3-4

& Figure 3-5). In general, the area north of the existing transmission line within the DE was dominated

by native grasses with a high diversity of native forb species. Additional species recorded are included

in the revised species list provided in Appendix A. It is difficult to determine from which vegetation

community the native pasture in this area is derived. Scattered Myall occurs in the southern section

and remnant Black Box Woodland occurs to the north of the site. The bulk of the pasture is likely to be

derived from Myall Woodland and many of the species recorded are common to this community.

Page 51: Nyngan Solar Farm Submissions Report Final v1

Nyngan Solar Farm Biodiversity Assessment Addendum

Nyngan BA addendum v1.0.docx

7

Native grassland derived from this community does not form part of the Myall Woodland EEC as

defined by the Scientific Committees determination for this community (DECCW 2010). However,

being in good condition and given the general lack of vegetation in this condition on the site, it is still

considered to be of high value. It is possible that the species diversity in this area may persist under

the proposed solar array but no information regarding its ability to persist in shaded conditions was

able to be referenced.

Figure 3-3 An area dominated by *Lepidium spp. In the northern area of the central section of the

site

Figure 3-4 Good condition native pasture in the north of the eastern paddock.

Page 52: Nyngan Solar Farm Submissions Report Final v1

Nyngan Solar Farm Biodiversity Assessment Addendum 

 

 

Nyngan BA addendum v1.0.docx             8 

 

Figure 3‐5 Area of high diversity grassland in the north of the eastern paddock 

Site boundary

Vegetation (type, condition)

Black Box Woodland (EEC TSC), Moderate to good

Black Box Woodland (EEC TSC),Moderate

Black Box Woodland (EEC TSC), Poor to moderate

Derived grassland (BBW) (EEC TSC), Poor to moderate

Myall Woodland (EEC TSC), Moderate

Myall Woodland (EEC TSC), Poor to moderate

Native pasture, Poor to moderate

Exotic pasture or crop

Native pasture, good

°

0 0.5 10.25 Kilometers

    @ A4 Reference: 1550‐1

1:27000

Coordinate System:      GDA94 Zone 55

www.nghenvironmental.com.au

Page 53: Nyngan Solar Farm Submissions Report Final v1

Nyngan Solar Farm Biodiversity Assessment Addendum

Nyngan BA addendum v1.0.docx

9

4 CONCLUSIONS AND RECOMMENDATIONS

The Nyngan Solar Farm Biodiversity Assessment concluded that the impacts to flora values at the

subject site resulting from the proposal would not be significant in light of the general low condition of

the native vegetation within the development envelope, the low habitat values and the local

abundance of similar vegetation in the locality. The findings of the supplementary survey support

these conclusions. An area of good condition native pasture in the north-east of the site was detected

during the supplementary survey however, it is not considered to comprise a threatened entity.

The declared noxious weed, Mexican Poppy (*Argemone ochroleuca subsp. ochroleuca) was detected

on a disturbed embankment adjacent to the dam in the south of the central areas of Black Box

Woodland. This is listed as a Class 5 noxious weed within the Bogan Local Control Area and the

requirements in the Noxious Weeds Act 1993 for a notifiable weed must be complied with.

None of the threatened subject species were recorded at the subject site and, on the basis of observed

condition and low integrity of the majority of the potential habitat at the site, their occurrence is

considered unlikely. The timing of the survey was considered suitable for detecting these species and

targeted searches would likely have detected these species if present.

Although there are no legislative requirements associated with the area of high diversity grassland in

the north-east of the site, this area is considered to have value in that higher diversity grassland is

poorly represented on the site. Ideally, this area would be avoided by the proposal however, if this is

not possible it is recommended that further consultation with a qualified agronomist be undertaken to

investigate appropriate management techniques for maintaining the biodiversity values of this area

under the photovoltaic array. An additional Statement of Commitment (SoC) and the rewording of

draft SoC 27 in the Environmental Assessment are required to achieve this outcome and are presented

below.

SoC Impact Objective Mitigation tasks Project

phase

Auditing

New Construction

impacts

Minimise

biodiversity

impacts

The area of good condition high diversity native

grassland in the north of the eastern paddock would

preferentially be avoided by the proposal. If avoidance

is not possible appropriate management procedures

would be included in the ground cover management

plan to maintain biodiversity values in this area.

Construction CEMP

Page 54: Nyngan Solar Farm Submissions Report Final v1

Nyngan Solar Farm Biodiversity Assessment Addendum

Nyngan BA addendum v1.0.docx

10

SoC Impact Objective Mitigation tasks Project

phase

Auditing

27

modified

Operational

impacts

Minimise

biodiversity

impacts

A groundcover management plan would be developed

that would include regular monitoring of vegetation

cover and composition and allow for adaptive

management. The aim would be to establish shade

tolerant perennial groundcover across the cropping

and exotic dominated grazing paddocks under the

panel array and maintain biodiversity values in better

quality areas.This would include:

Advice from an agronomist in relation to

preferred species/varieties, establishment

methods of alternative pastures and best

practice management.

Advice from an agronomist in relation to

maintaining biodiversity values in the high

diversity grassland area in the north of the

eastern paddock (if it is unable to be

avoided by the proposal).

Where information is lacking, trials may be

required onsite.

Operation OEMP

Page 55: Nyngan Solar Farm Submissions Report Final v1

Nyngan Solar Farm Biodiversity Assessment Addendum

Nyngan BA addendum v1.0.docx

11

5 REFERENCES

Department of Environment, Climate Change and Water (DECCW) (2010) Threatened species,

populations and ecological communities of NSW, Department of Environment and Climate

Change NSW accessed at http://www.threatenedspecies.environment.nsw.gov.au/index.aspx.

Harden, G.J. (ed.), (1990-2002) Flora of New South Wales. Volumes 1-4, Royal Botanic Gardens

Sydney, University of New South Wales Press, Kensington, New South Wales.

nghenvironmental (2010) Biodiversity Assessment - Nyngan Solar Farm, prepared for Infigen Suntech,

October 2010

Page 56: Nyngan Solar Farm Submissions Report Final v1

Nyngan Solar Farm Biodiversity Assessment Addendum

Nyngan BA addendum v1.0.docx A-1

Appendix A REVISED FLORA SPECIES LISTS

Page 57: Nyngan Solar Farm Submissions Report Final v1

Nyngan Solar Farm Biodiversity Assessment Addendum

Nyngan BA addendum v1.0.docx A-2

The survey area was stratified into 5 relatively homogeneous survey zones based on Proposal

elements, vegetation structure and topography:

WP Native pasture and Chenopod shrubland (western area): sites 2, 6

CA Cropped areas/Improved pasture (central area and far south east): site 7, 9

BBW Black Box woodland (central area and scattered in western area): sites 1, 5, 6, 7, 8, 10, 11

MW Myall woodland and grassland (eastern area): sites 12, 13, 14

SS Disturbed and planted area (around existing sub station): site 3

Cover/abundance assessments are based on visual estimates of foliage cover (after Carnahan 1997),

scored using a modified Braun-Blanquet 6-point scale:

1 1 to a few individuals present, less than 5% cover

2 many individuals present, but still less than 5% cover

3 5 - <20% cover

4 20 - <50% cover

5 50 - <75% cover

6 75 - 100% cover.

Where the cover/abundance of a particular species varies markedly over the random meander survey

area, a range of values is provided. In these cases, abundance is based on a standard 20 metre x 20

metre quadrat scale.

Species of conservation significance are bolded. Introduced species are denoted by an asterisk.

Noxious weeds declared for the Bogan Shire Council control area under the Noxious Weeds Act 1993

are indicated with a ‘Δ’ symbol. Where uncertainty exists due to the unavailability of mature

reproductive material, the taxon is preceded by a question mark, or plants are identified to genus level

only. Botanical nomenclature follows G.J. Harden (ed) (1990-2002) Flora of New South Wales, UNSW

Press, except where recent changes have occurred.

Additions from the recent November 2010 survey are highlighted

Page 58: Nyngan Solar Farm Submissions Report Final v1

Nyngan Solar Farm Biodiversity Assessment Addendum

Nyngan BA addendum v1.0.docx A-3

Scientific name Common name Family

Abundance

WP CA BBW MW SS

TREES

Acacia harpophylla Brigalow Fabaceae 0-1

Acacia pendula Weeping Myall Fabaceae 0-2 0-2

Apophyllum anomalum Warrior Bush Capparaceae 0-1

Callitris glaucophylla White Cypress Cupressaceae 0-1

Capparis lasiantha Nepine Capparaceae 0-1 0-1

Casuarina cristata Belah Casuarinaceae 0-1

Eremophila ?mitchellii Budda Myoporaceae 0-1 0-2

Eucalyptus campaspe Silver Gimlet Myrtaceae 0-1

Eucalyptus largiflorens Black Box Myrtaceae 0-3 2-4 0-1

Eucalyptus sideroxylon Mugga Ironbark Myrtaceae 0-1

Eucalyptus populnea subsp. bimbil

Bimble Box Myrtaceae 0-1 0-2 0-1

Eucalyptus urna Merrit Myrtaceae 0-1

Flindersia maculosa Leopardwood Rutaceae 0-1 0-1

Geijera parviflora Wilga Rutaceae 0-2 2 0-1 0-1

Schinus areira Pepper Tree Anacardiaceae 0-1

SHRUBS, SUB-SHRUBS

Abutilon oxycarpum Flannel weed Malvaceae 0-1

Amyema quandang Mistletoe Loranthaceae 0-1

Atriplex semibaccata Creeping Saltbush Chenopodiaceae 0-2 0-2 0-2 0-2

Capparis mitchellii Wild Orange Capparaceae 0-1

Dodonaea viscosa Sticky Hop-bush Sapindaceae 0-1

Eremophila maculata Spotted Fuchsia-bush Myoporaceae 0-3

Δ*Lycium ferocissimum African Boxthorn Solanaceae 0-1 0-1 0-2

Maireana aphylla Cotton Bush Chenopodiaceae 0-1

Maireana appressa Chenopodiaceae 0-1 0-1

Maireana brevifolia Small-leaf Bluebush Chenopodiaceae 0-2 0-2

Maireana ?decalvans Black Cotton Bush Chenopodiaceae 0-1

Myoporum montanum Western Boobialla Myoporaceae 0-1

Rhagodia spinescens Spiny Saltbush Chenopodiaceae 0-1 0-1

Salsola tragus subsp. tragus Chenopodiaceae 0-2

Sclerolaena birchii Galvanised Burr Chenopodiaceae 2 2 2

Sclerolaena bicornis Goathead Burr Chenopodiaceae 1-2 1-2 0-2

Page 59: Nyngan Solar Farm Submissions Report Final v1

Nyngan Solar Farm Biodiversity Assessment Addendum

Nyngan BA addendum v1.0.docx A-4

Scientific name Common name Family

Abundance

WP CA BBW MW SS

Sclerolaena diacantha Grey Copperburr Chenopodiaceae 2 2 1 2

Sclerolaena tricuspis Giant Redburr Chenopodiaceae 2 2 2 2

Senna artemisioides Fabaceae 0-1

Solanum esuriale Quena Solanaceae 0-1

Solanum ferrocissimum Spiny Potato Bush Solanaceae 0-1

*Solanum nigrum Black-berry Nightshade

Solanaceae 0-1

Δ*Xanthium spinosum Bathurst Burr Asteraceae 0-1 0-1

FORBS

*Anagallis arvensis Scarlet Pimpernel Myrsinaceae 0-1

Δ*Argemone ochroleuca subsp. ochroleuca

Mexican Poppy Papaveraceae 0-2

Brachyscome ciliaris var. subintegrifolia

Variable Daisy Asteraceae 0-2 1 0-2

Brachyscome dentata Asteraceae 0-1

Crassula sieberiana Australian Stonecrop Crassulaceae 0-2

Bulbine bulbosa Bulbine Lily Asphodelaceae 0-2

Calotis hispidula Bogan Flea Asteraceae 0-1 0-1 0-1

Calotis scabiosifolia var. scabiosifolia

Rough Burr-daisy Asteraceae 1 0-1

*Capsella bursa-pastoris Shepherd’s Purse Brassicaceae 0-2

*Carthamus lanatus Saffron Thistle Asteraceae 0-1

Chamaesyce drummondii Caustic Weed Chenopodiaceae 0-2

Chenopodium curvispicatum Chenopodiaceae 0-2

*Chenopodium murale Nettle-leaf Goosefoot

Chenopodiaceae 0-1 0-1 0-1

Cotula australis Carrot Weed Asteraceae 0-2

Daucus glochidiatus Native Carrot Apiaceae 1

Dichondra repens Kidney Weed Convolvulaceae 0-2

*Echium plantagineum Paterson’s Curse Boraginaceae 0-2 1-5 0-3

Einadia nutans subsp. nutans

Climbing Saltbush Chenopodiaceae 0-1 0-1 0-1

Einadia polygonoides Chenopodiaceae 0-1 0-1

*Erodium cicutarium Common Storksbill Geraniaceae 0-1 0-1 1 0-1

Erodium crinitum Blue Storksbill Geraniaceae 0-1

Eryngium paludosum Long Eryngium Apiaceae 0-1

Page 60: Nyngan Solar Farm Submissions Report Final v1

Nyngan Solar Farm Biodiversity Assessment Addendum

Nyngan BA addendum v1.0.docx A-5

Scientific name Common name Family

Abundance

WP CA BBW MW SS

Goodenia fascicularis Mallee Goodenia Goodeniaceae 0-1

Harmsiodoxa blennodioides Brassicaceae 0-1 0-1

*Hypochaeris radicata Cat’s Ear, Flatweed Asteraceae 0-1

?Leiocarpa tomentosa Woolly Plover-daisy Asteraceae 0-1

*Lepidium africanum Peppercress Brassicaceae 0-2 0-4

*Lepidium bonariense Peppercress Brassicaceae 0-3

Leptorhyncus squamatus Scaly Buttons Asteraceae 0-1

*Malva parviflora Small-flowered Mallow

Malvaceae 0-2 0-4

*Malvastrum americanum Spiked Malvastrum Malvaceae 0-2

*Marrubium vulgare Horehound Lamiaceae 0-1 0-1

*Medicago ?arabica Spotted Burr-medic Fabaceae 2 0-2 1 1-2

Mimulus gracilis Slender Monkey-flower

Scrophulariaceae 0-1

Minuria integerrima Smooth Minuria Asteraceae 0-1

Oxalis ?perennans Oxalis Oxalidaceae 0-1 0-1 0-1

Plantago cunninghamii Plantaginaceae 0-1

Ptilotus sessilifolius Amaranthaceae 1

*Rapistrum rugosum Turnip Weed Brassicaceae 0-1 0-1

Rhodanthe corymbiflora Small White Sunray Asteraceae 2

Rhodanthe moschata Asteraceae 1

?Rostellularia adscendens Acanthaceae 0-1 0-1 0-2

Rumex brownii Native Dock Polygonaceae 0-1

Senecio cunninghamii var. cunninghamii

Asteraceae 0-1

Senecio glossanthus Streaked Poverty Bush

Asteraceae 0-1 1

Sida fibulifera Pin Sida Malvaceae 1 1

Sida trichopoda High Sida Malvaceae 0-1

*Silybum marianum Variegated Thistle Asteraceae 0-1 0-2

*Sonchus oleraceus Common Sowthistle Asteraceae 0-1

*Sisymbrium orientale Indian Hedge Mustard

Brassicaceae 0-2 0-2

Swainsona procumbens Broughton Pea Fabaceae 1

Tetragonia tetragonoides Native Spinach Aizoaceae 0-1

*Trifolium spp. Clover Fabaceae 0-3 0-3 0-3

Page 61: Nyngan Solar Farm Submissions Report Final v1

Nyngan Solar Farm Biodiversity Assessment Addendum

Nyngan BA addendum v1.0.docx A-6

Scientific name Common name Family

Abundance

WP CA BBW MW SS

Triptilodiscus pygmaeus Common Sunray Asteraceae 1-2

*Urtica repens Small Nettle Urticaceae 0-2

Vittadinia ?cuneata Fuzzweed Asteraceae 0-1 0-1

Wahlenbergia communis Tufted Bluebell Campanulaceae 0-1 0-2

Wahlenbergia stricta Tall Bluebell Campanulaceae 1

Xerochrysum bracteatum Golden Everlasting Asteraceae 1

GRASSES

Austrodanthonia caespitosa Ringed Wallaby Grass Poaceae 0-2

Austrodanthonia setacea Small-flowered Wallaby Grass

Poaceae 0-2

Austrodanthonia sp. Poaceae 0-2

Austrostipa scabra subsp. scabra

Rough Speargrass Poaceae 0-2

Chloris truncata Windmill Grass Poaceae 2 2 2-4

Cymbopogon refractus Barbed-wire Grass Poaceae 0-1

*Cynodon dactylon Couch Poaceae 0-3

Enteropogon acicularis Curly Windmill Grass Poaceae 1-3 1-3 1-3 2

Eragrostis brownii Browns Lovegrass Poaceae 0-2 1-3 1-2

*Eragrostis cilianensis Stinking Lovegrass Poaceae 2 0-2 0-2

Eragrostis parviflora Weeping Lovegrass Poaceae 0-3 0-3 0-3 0-2

Eragrostis setifolia Neverfail Poaceae 0-2

*Hordeum leporinum Barley Grass Poaceae 0-4 2-6

Lachnagrostis filiformis Blown Grass Poaceae 2 2 2 2

Panicum decompositum var. tenuis

Poaceae 2 2 2-3 2

Sporobolus caroli Fairy Grass Poaceae 0-1 0-1 0-2 0-1

GRAMINOIDS

Carex inversa Knob Sedge Cyperaceae 0-1 0-2

Cyperus difformis Dirty Dora Cyperaceae 0-1

Juncus sp Rush Juncaceae 0.1 0-1

FERNS

Marsilea drumondii Common Nardoo Marsileaceae 0-1 0-2

Page 62: Nyngan Solar Farm Submissions Report Final v1

Submissions Report Nyngan Solar Farm 

1585 Final V1  B‐III   

B.2 ARCHAEOLOGY AND ABORIGINAL HERITAGE ADDENDUM 

Page 63: Nyngan Solar Farm Submissions Report Final v1

Addendum Proposed Nyngan Photovoltaic Solar Farm

Indigenous Archaeological and Cultural Heritage Assessment

A report to Infigen

November 2010

New South Wales Archaeology Pty Limited PO Box 2135

Central Tilba NSW 2546 www.nswarchaeology.com

Page 64: Nyngan Solar Farm Submissions Report Final v1

TABLE OF CONTENTS

1. SUMMARY ....................................................................................................................................................... 1

1.1 INTRODUCTION ................................................................................................................................................. 1

1.2 PARTNERSHIP WITH ABORIGINAL COMMUNITIES ............................................................................................. 1

1.3 OBJECTIVES ...................................................................................................................................................... 1

1.4 RESULTS AND IMPACT ASSESSMENT ................................................................................................................ 1

2. SURVEY RESULTS .......................................................................................................................................... 3

2.1 SURVEY COVERAGE ......................................................................................................................................... 3

2.2 ABORIGINAL OBJECT RECORDINGS .................................................................................................................. 5

2.3 IMPACT ASSESSMENT ....................................................................................................................................... 6

3. RECOMMENDATIONS ................................................................................................................................ 8

4. REFERENCES .................................................................................................................................................. 9

Page 65: Nyngan Solar Farm Submissions Report Final v1

Proposed Nyngan Photovoltaic Solar Farm - Addendum

New South Wales Archaeology Pty Ltd November 2010 page 1

1. SUMMARY

1.1 Introduction

New South Wales Archaeology Pty Ltd has been commissioned to undertake an Indigenous archaeological and cultural heritage assessment of the proposed Nyngan Solar Farm. The proposed Nyngan Solar Farm is defined as a Major Project (Critical Infrastructure) under Part 3A of the Environmental Planning and Assessment Act 1979. An initial field survey in relation to this proposal was conducted in August 2010. Subsequently the proposal envelope was expanded to encompass additional areas to the east and south (Figure 1). In an assessment of adequacy in relation to the Indigenous Archaeological and Cultural Heritage Assessment regarding this project the NSW Department of Planning required that these further areas also be subject to field survey and assessment prior to determination. This report details the results of the subsequent field survey of the additional area and forms an addendum to the earlier report (New South Wales Archaeology Pty Limited 2010). 1.2 Partnership with Aboriginal Communities

This assessment has been conducted in accordance with consultation process as outlined in the NSW Department of Environment, Climate Change and Water’s (NSW DECCW) Aboriginal Cultural Heritage Consultation Requirements for Proponents 2010 (ACHCRP) (NSW DECCW 2010). The field survey of the additional proposed impact areas has been undertaken with the assistance of Tommy Ryan of the Nyngan Local Aboriginal Land Council (NLALC). 1.3 Objectives

This additional assessment has sought to identify and record Aboriginal objects, to assess the archaeological potential of the landscape and to formulate appropriate management and mitigation strategies. The investigation has included a field survey of the expanded proposal area as well as the proposed access road which extends from the north-western boundary of the site to the southern edge of the Nyngan township, and an analysis of results. The additional field work was undertaken in November 2010. 1.4 Results and Impact Assessment

The additional portion of the proposal area surveyed during this assessment measures approximately 123 hectares in area. It is estimated that approximately 43 hectares of that area was subject to survey inspection. Ground exposures inspected are estimated to have measured approximately 3.87 hectares in area. Of that ground exposure area archaeological visibility (the potential artefact bearing soil profile) is estimated to have been 1.55 hectares. Effective Survey Coverage is therefore relatively low and is calculated to have been 1.26 % of the area. Two additional Aboriginal object locales were recorded during the field survey, each comprised of a single stone artefact. The Effective Survey Coverage achieved during the survey in combination with the nature of the ground exposures present is considered to have been sufficient and of a quality so as to effectively characterise the nature of artefact distribution. The results of this survey are therefore assessed to be a relatively accurate reflection of the artefact density within the additional proposed impact area. Accordingly, based on the relevant predictive model of site distribution for the area, and the results of the field survey, artefact density in the study area is assessed to be very low. The area is assessed to be of low archaeological potential and significance.

Page 66: Nyngan Solar Farm Submissions Report Final v1

Proposed Nyngan Photovoltaic Solar Farm - Addendum

New South Wales Archaeology Pty Ltd November 2010 page 2

Figure 1. Location of the additional surveyed areas, indicated with black outline, in relation to that which was originally surveyed in August 2010 (fainter outline to west).

Page 67: Nyngan Solar Farm Submissions Report Final v1

Proposed Nyngan Photovoltaic Solar Farm - Addendum

New South Wales Archaeology Pty Ltd November 2010 page 3

2. SURVEY RESULTS

2.1 Survey Coverage

The study area is located immediately to the south of the township of Nyngan. It is situated within the Darling Riverine Plains bioregion on the Bogan River floodplain. The landform which comprises the study area is continuous with the prior area surveyed, being a flat with level gradient and open aspect that forms part of the alluvial floodplain associated with the Bogan River. The western extent of the subject study area is located ca. 3.2 kilometres east of the Bogan River while the eastern extent is ca. 5.4 kilometres to the east of that river. The area has undergone relatively high levels of prior disturbance associated with agriculture. Following the original clearance of vegetation, subsequent farming practices have impacted the entire proposal area. These impacts include fencing, the creation of mechanically graded roads and unformed internal tracks, the excavation of dams and associated shallow drainage channels as well as ongoing grazing. In addition, almost the entire area has a long history of impacts associated with ploughing (Tommy Ryan 2010 pers. comm.) which has resulted in some deflation of the soil profile as the result of aeolian action (Plates 1 and 2). This is particularly evident in the southern section of the surveyed area. These previous farming practices and their effects are assessed to have caused high levels of impact to ground surfaces and to any Aboriginal objects which may once have been present. Plate 1. Area showing evidence of ploughing in the north western section of the proposal area; looking east. There are few trees present within the subject surveyed area. All trees within areas of proposed impacts are assessed to be regrowth and estimated to be around 50 years old, but were nevertheless inspected during the survey and exhibited no evidence of Aboriginal scarring. At the time of field survey several paddocks had relatively recently been ploughed, cultivated and harvested, while some other areas possessed a reasonably consistent coverage of vegetation, predominantly in the form of weed species (Plate 3).

Page 68: Nyngan Solar Farm Submissions Report Final v1

Proposed Nyngan Photovoltaic Solar Farm - Addendum

New South Wales Archaeology Pty Ltd November 2010 page 4

The survey was focused on areas of ground exposure which were found to be present along most fence lines, in areas of unformed vehicle tracks, and in numerous bare earth patches which were distributed reasonably consistently throughout the area. Archaeological visibility within many areas of ground exposure was moderate to good as the result of the ground surface being penetrated by ploughing, vehicle traffic, weathering and stock treadage. The area of the proposed access road is highly disturbed, having been repeatedly graded over time and now thickly laid with imported gravel (Tommy Ryan 2010 pers. comm.). Plate 2. Large area of bare earth associated with ploughing and stock grazing, southern section looking west. Plate 3. Area of weed growth, central section looking south.

Page 69: Nyngan Solar Farm Submissions Report Final v1

Proposed Nyngan Photovoltaic Solar Farm - Addendum

New South Wales Archaeology Pty Ltd November 2010 page 5

The study area measures c. 123 hectares in size. It is estimated that approximately 43 hectares of that area was subject to survey inspection. Ground exposures inspected are estimated to have been 3.87 hectares in area. Of that ground exposure area archaeological visibility (the potential artefact bearing soil profile) is estimated to have been 1.54 hectares. Effective Survey Coverage is therefore calculated to have been 1.26% of the proposal area. 2.2 Aboriginal Object Recordings

The following Aboriginal object locales were recorded during the subject survey; their location is shown in Figure 2 (note locale numbering is sequential and continues from those originally recorded in August (NSW Archaeology 2010): Survey Unit 1/Locale 3 519623e 6504561n GDA One stone artefact was recorded in an area of exposure adjacent to a fence line (Plate 4). The broad area measures 60 x 40 m, of which 60% was ground exposure, possessing 60% archaeological visibility. The effective survey coverage is relatively high and given that one artefact only was recorded artefact density is assessed to be very low. The recorded artefact is a white quartzite proximal flake portion; size class 3 (less than 3 cm in overall dimensions). The site is likely to contain additional artefacts in a subsurface context in very low densities. The area is eroding due to water, wind, ploughing, vehicle traffic and animal treadage. Plate 4. SU1/L3 looking west.

Page 70: Nyngan Solar Farm Submissions Report Final v1

Proposed Nyngan Photovoltaic Solar Farm - Addendum

New South Wales Archaeology Pty Ltd November 2010 page 6

Survey Unit 1/Locale 4 519471e 6504618n GDA One stone artefact was recorded in an area of bare earth exposure (Plate 5). The area where the artefact is located measures 120 x 50 m, of which 80% was ground exposure, possessing 60% archaeological visibility. The effective survey coverage is relatively high and given that one artefact only was recorded artefact density is assessed to be very low. The recorded artefact is a grey chert core, with 8 negative flake scars and 20% terrestrial cortex; size class 5. The site is likely to contain additional artefacts in a subsurface context in very low densities. The site area has been cultivated and eroding due to water, wind and animal agents. Plate 5. SU1/L4 looking east. 2.3 Impact Assessment

Two Aboriginal object locales were recorded during the subject field survey (SU1/L3 and SU1/L4), each comprised of a single stone artefact (Figure 2). While the Effective Survey Coverage for the surveyed area is calculated to have been relatively low at the time of survey, many extensive areas of good ground exposure possessing reasonable archaeological visibility were distributed throughout the study area. These exposures enabled a reasonable characterisation of artefact distribution within the proposal area. The subject area surveyed is located to the east and south of the original proposal envelope. The western extent of the is located c 3.2 kilometres east of the Bogan River while the eastern extent is situated c. 5.4 kilometres to the east of that river. The predictive model of site distribution for the region indicates that in such an environmental setting, distanced from access to reliable water and situated on an amorphous floodplain, artefact density would be very low. As indicated by Nyngan Local Aboriginal Land Council representative Tommy Ryan (2010 pers. comm.) such an area would have been used for hunting and transitory movement, but that the focus of Aboriginal activity in the region and associated higher densities of artefact distribution would have been nearer to the river.

Page 71: Nyngan Solar Farm Submissions Report Final v1

Proposed Nyngan Photovoltaic Solar Farm - Addendum

New South Wales Archaeology Pty Ltd November 2010 page 7

As noted above, the Aboriginal object locales recorded in the additional proposed impact area are two single and isolated stone artefacts. These are both assessed to be of low archaeological significance. Undetected or subsurface stone artefacts are assessed to be present in very low density. The Effective Survey Coverage achieved during the survey is considered to have been sufficient to characterise the nature of artefact distribution in the study area. The survey results are therefore assessed to be a relatively accurate reflection of the artefact density in the proposal area. Accordingly, based on the relevant predictive model of site distribution for the area, and the results of the field survey, artefact density in the study area is assessed to be very low. The proposal area is assessed to be low archaeological potential and significance. Given that both the two recorded Aboriginal objects and the predicted undetected and subsurface artefacts are assessed to be of low significance, the impacts can be viewed as being of correspondingly low significance. This assessment forms the basis for the formulation of recommendations relating to the proposal. Figure 2. Location of Aboriginal object locales SU1/L3 and SU1/L4 recorded during the subject survey.

Page 72: Nyngan Solar Farm Submissions Report Final v1

Proposed Nyngan Photovoltaic Solar Farm - Addendum

New South Wales Archaeology Pty Ltd November 2010 page 8

3. RECOMMENDATIONS

The following recommendations are made on the basis of: � A consideration of the Part 3A amendment to the Environmental Planning and Assessment

Act. � The results of the investigation as documented in this report. � Consideration of the type of development proposed and the nature of proposed impacts.

� Advice provided from Nyngan Local Aboriginal Land Council. The following recommendations are provided:

o The two recorded Aboriginal object locales and the predicted very low density subsurface artefact distribution in the subject survey area does not surpass archaeological significance thresholds which would act to preclude the proposed impacts.

o The two recorded Aboriginal object locales SU1/L3 and SU1/L4 are assessed to be representative of a very low density distribution of stone artefacts. The archaeological significance of these locales is assessed to be low. Accordingly unmitigated impact is considered to be appropriate.

o There are no identified Indigenous archaeological and heritage constraints relating to the proposal in the additional area.

Page 73: Nyngan Solar Farm Submissions Report Final v1

Proposed Nyngan Photovoltaic Solar Farm - Addendum

New South Wales Archaeology Pty Ltd November 2010 page 9

4. REFERENCES

New South Wales Archaeology Pty Limited 2010 Proposed Nyngan Photovoltaic Solar Farm Indigenous Archaeological and Cultural Heritage Assessment. A report to nghenvironmental.

Tommy Ryan November 2010 personal communication.