NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff...

59
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August 9, 1994 los. 50-390 APPLICANT: FACILITY: Tennessee Valley Authority (TVA) Watts Bar Units 1 SUBJECT: MEETING SUMMARY - JULY 28, 1994 MANAGEMENT MEETING (TAC M72494) REFERENCE: Meeting notice by P. S. Tam, July 19, 1994 On July 28, 1994, NRC and TVA representatives met at the Watts Bar site to discuss the problems, concerns and needed actions associated with construction and licensing of Watts Bar Nuclear Plant, Unit 1. Enclosure 1 is a list of meeting participants and observers. Enclosures 2 and 3 are TVA's handout materials. The staff stated that the ongoing action regarding assessment of the 1978 Final Environmental Assessment (NUREG-0498) and Watts Bar's Environmental Impact Statement would not be discussed in the meeting, but would be the subject of a separate, future meeting. The staff also stated that the issue concerning a recent NRC Inspector General report (regarding allegers' identities), which received media interest, would not be discussed in this meeting. TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: o Regarding Watts Bar milestones (shown on Pages 17 and 19 of Enclosure 2), the staff expressed concern that closure packages prepared by TVA for certain corrective action programs and special programs characterized as "complete" or "75% complete" did not meet the characterization. The staff (Region II) will set up a meeting within a month to discuss the results of TVA's assessment of closure status. o Regarding lessons learned from the hot functional testing (HFT), TVA stated that within two weeks, it would be ready to discuss with the staff, in a technical meeting, various problems encountered and followup actions. In particular, the staff would like to discuss the implications of the lessons for future activities, such as the HFT retests, the performance of the operators and their readiness to operate the plant safely. o The staff will meet with TVA to discuss TVA's proposal to change several tests under Preoperational Test Instructions (PTIs) to Acceptance Test Instructions (ATIs). TVA's proposal had been discussed with the staff in a technical meeting on July 6, 1994, and described in TVA submittals dated July 14 and 20, 1994. The staff is interested in understanding 9408110200 940809 PDR ADOCK 05000390 P PDR PONG u: uman wI law a a i /- U0. ort U ---

Transcript of NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff...

Page 1: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

UNITED STATESNUCLEAR REGULATORY COMMISSION

WASHINGTON, D.C. 20555-0001

August 9, 1994los. 50-390

APPLICANT:

FACILITY:

Tennessee Valley Authority (TVA)

Watts Bar Units 1

SUBJECT: MEETING SUMMARY - JULY 28, 1994 MANAGEMENT MEETING(TAC M72494)

REFERENCE: Meeting notice by P. S. Tam, July 19, 1994

On July 28, 1994, NRC and TVA representatives met at the Watts Bar site todiscuss the problems, concerns and needed actions associated with constructionand licensing of Watts Bar Nuclear Plant, Unit 1. Enclosure 1 is a list ofmeeting participants and observers. Enclosures 2 and 3 are TVA's handoutmaterials.

The staff stated that the ongoing action regarding assessment of the 1978Final Environmental Assessment (NUREG-0498) and Watts Bar's EnvironmentalImpact Statement would not be discussed in the meeting, but would be thesubject of a separate, future meeting.

The staff also stated that the issue concerning a recent NRC Inspector Generalreport (regarding allegers' identities), which received media interest, wouldnot be discussed in this meeting.

TVA's presentation followed the slides in Enclosure 2. The staff and TVA madethe following comments and commitments:

o Regarding Watts Bar milestones (shown on Pages 17 and 19 of Enclosure2), the staff expressed concern that closure packages prepared by TVAfor certain corrective action programs and special programscharacterized as "complete" or "75% complete" did not meet thecharacterization. The staff (Region II) will set up a meeting within amonth to discuss the results of TVA's assessment of closure status.

o Regarding lessons learned from the hot functional testing (HFT), TVAstated that within two weeks, it would be ready to discuss with thestaff, in a technical meeting, various problems encountered and followupactions. In particular, the staff would like to discuss theimplications of the lessons for future activities, such as the HFTretests, the performance of the operators and their readiness to operatethe plant safely.

o The staff will meet with TVA to discuss TVA's proposal to change severaltests under Preoperational Test Instructions (PTIs) to Acceptance TestInstructions (ATIs). TVA's proposal had been discussed with the staffin a technical meeting on July 6, 1994, and described in TVA submittalsdated July 14 and 20, 1994. The staff is interested in understanding9408110200 940809PDR ADOCK 05000390P PDR

PONG u: uman wIlaw

a a

i /-U0. ort ��U ---

Page 2: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

- 2 -

the nature of the changes, especially justification for any decreasedefforts from those previously approved in Watts Bar Safety EvaluationReport, Supplement 12.

o The staff will have discussions with TVA regarding updating the FSAR toinclude a description, by reference if appropriate, of the variousspecial and plant-specific processes (e.g., corrective action programs,special programs, reliefs to ASME codes) associated with Watts Barlicensing, but not specifically described in the FSAR.

o The staff stated that future management meetings should de-emphasizestatus summaries, and emphasize discussion of specific issues thatwarrant senior management attention.

Original signed by

Peter S. Tam, Senior Project ManagerProject Directorate II-4Division of Reactor Projects - I/IIOffice of Nuclear Reactor Regulation

Enclosures:1. Participants and observers list2. TVA Slides*3. Watts Bar Unit 1 - Site Integrated Schedule - Level 1*

cc w/enclosures 1:See next page

*Only enclosed with docket file and PDR copies

| OFFICE PDII-4/LA PDII-4/PM PDII-4/D

NAME BCIayto P Tam L i FHebdon 4sDATE 8/ 9/94 8/ g/94 8/ 9/94

DOCUMENT NAME: 728MTG.SUM

Page 3: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

ENCLOSURE 1

LIST OF PARTICIPANTS AND OBSERVERS

MANAGEMENT MEETING AT WATTS BAR SITE

SPRING CITY. TENNESSEE

JULY 28, 1994

Affiliation

M. BajestaniPaul R. BaronAlex BeckmanKent W. BrownTony CapozziJohn CarpenterEd ChristenburyKen ClarkClaudia CraigLinda DebbeStew EbneterWalt ElliottSteve FetchPaul FredricksonR. L. GeorgeGeorge M. GillilanMichael GlasmanRichard HardinMichael R. HardingAnn HarrisKen HarrisFrank HawkinsRoger HawkinsFrederick HebdonMike HellumsJim HooverRoger HustonKen IveyJohns JaudonJohn JenkinsonCaudle JulianBetty KauffmanOliver KingsleyJ. Bryant KinneyMike LalorJulio LaraJohn LordyBarb MartocciT. J. McGrathRobert J. Milhiser

TVA/Watts Bar Startup ManagerTVA/NAELEarth First!TVA/Corporate ElectricalTVA/Watts Bar PAC/AQHerald-News (Dayton)TVA/General CounselNRC/Region IINRC/Office of Executive DirectorTVA/LicensingNRC/Region IITVA/EngineeringLocal residentNRC/Region IITVA/Engineering & MaterialsTVANRC/Watts Bar Resident InspectorTVATVA/Concerns ResolutionTVA/Local CommunityTVA/Nuclear Advisor to the BoardLocal residentWMYVNRC/NRR/Project Directorate II-4TVA/Corporate LicensingTVA/Watts BarTVA/Corporate LicensingNRC/Watts Bar Resident InspectorNRC/Region IITVANRC/Region IIKnoxville News SentinelTVA/Generation GroupTVA/Comm.TVA/Project ManagementNRC/Watts Bar Resident InspectorTVATVA/Watts BarTVA/NSRBTVA/EBASCO

Name

Page 4: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

- 2 -

Rich MillerVictor MillerMike MobleyDon MoodyDwight NunnGeorge PannellRichard T. PurcellWilliam RussellMark Henry SallyJohn ScaliceKenneth SchausBruce SchofieldVernon J. ShanksDebra ShultsStephen SmithLarry SpiersPeter TamPat C. TrickP. Kim Van DoornE. D. VigluicciJohn VoreesGlenn Walton0. J. ZeringueRoy Zimmerman

TVA/EngineeringChattanooga Free-PressDRH, TDECTVA/Watts BarTVA/New PlantTVA/Watts BarTVA/Watts BarNRC/Office ofTVA/CorporateTVA/Watts BarTVA/NATVA/Watts BarTVA/Watts Bar

Plant ManagerCompletion

Nuclear ReactorEngineeringSite Operations

Site Licensing

Regulation

DRHTVERC/Global SustainabilityTVA/Nuclear AssuranceNRC/NRR/Project Directorate II-4Earth First!NRC/Watts Bar Senior Resident InspectorTVATVA/Watts Bar Site LicensingNRC/Watts Bar Senior Resident InspectorTVA/OperationsNRC/Office of Nuclear Reactor RequlatiotI-

Page 5: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

WATTS BAR @LEAR PLANTcc:Mr. Craven Crowell, ChairmanTennessee Valley AuthorityET 12A400 West Summit Hill DriveKnoxville, TN 37902

Mr. W. H. Kennoy, DirectorTennessee Valley AuthorityET 12A400 West Summit Hill DriveKnoxville, TN 37902

Mr. Johnny H. Hayes, DirectorTennessee Valley AuthorityET 12A-400 West Summit Hill DriveKnoxville, TN 37902

Mr. Oliver D. Kingsley, Jr.President, TVA Nuclear andChief Nuclear Officer

Tennessee Valley Authority6A Lookout Place1101 Market StreetChattanooga, Tennessee 37402-2801

Dr. Mark 0. Medford, Vice PresidentEngineering & Technical ServicesTennessee Valley Authority3B Lookout Place1101 Market StreetChattanooga, TN 37402-2801

Mr. D. E. Nunn, Vice PresidentNew Plant CompletionTennessee Valley Authority3B Lookout Place1101 Market StreetChattanooga, TN 37402-2801

Mr. J. A. Scalice, Site ViceWatts Bar Nuclear PlantTennessee Valley AuthorityP.O. Box 2000Spring City, TN 37381

General CounselTennessee Valley AuthorityET 11H400 West Summit Hill DriveKnoxville, TN 37902

President

Mr. B. S. SchofieldSite Licensing ManagerWatts Bar Nuclear PlantTennessee Valley AuthorityP.O. Box 2000Spring City, TN 37381

TVA RepresentativeTennessee Valley Authority11921 Rockville PikeSuite 402Rockville, MD 20852

Regional AdministratorU.S. Nuclear Regulatory CommissionRegion II101 Marietta Street, NW., Suite 2900Atlanta, GA 30323

Senior Resident InspectorWatts Bar Nuclear PlantU.S. Nuclear Regulatory CommissionRoute 2, Box 700Spring City, TN 37381

The Honorable Robert AikmanCounty ExecutiveRhea County CourthouseDayton, TN 37321

The Honorable Garland LanksfordCounty ExecutiveMeigs County CourthouseDecatur, TN 37322

Mr. Michael H. Mobley, DirectorDivision of Radiological Health3rd Floor, L and C Annex401 Church StreetNashville, TN 37243-1532

Ms. Danielle DroitschEnergy ProjectThe Foundation for

Global SustainabilityP.O. Box 1101Knoxville, TN 37901

Mr. Bill HarrisRoute 1, Box 26Ten Mile, TN 37880

Mr. Roger W. Huston, ManagerNuclear Licensing and Regulatory AffairsTennessee Valley Authority4G Blue Ridge1101 Market StreetChattanooga, TN 37402-2801

Page 6: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

Distribution(With Enclosure 1)W. Russell/F. MiragliaR. ZimmermanS. VargaG. LainasF. HebdonP. Tam/E. CarpenterB. ClaytonOGCE. JordanACRS(10)S. Ebneter, RIIK. Clark, RIIM. GlasmanK. IveyE. Merschoff, RIIJ. Jaudon, RIIC. Julian, RIIJ. Lara, RIIG. Walton, RIIC. Craig, EDOP. Vandoorn, RIIP. Fredrickson, RIIWBN Rdg.

(With Enclosures 1. 2 and 3)Docket FilePDR and Local PDR

Page 7: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

6.9KV SYSTELJS

2W/00/2.2/21 I37/2.1/215

MJAJOR ELECTRICAL SYSTEI8S

055 - 97*C*070708

Z93 - 980 0877 7080

203 -a989 707877E 771D7 7.00*08 PM

398 -a089 908 81070 (07o 777

2077 -TR 70877 BLDG7 (97907 T78 (97NT897

2009 - 70770BLD 8.077 OPERATED7( 9177 PA

278 -TU70770 BLDG7 9(77 78

272 -08DV S7977907708M

273 - 7E(9TO0 7707 70

219 -C09778.7 740 9(0X 788 P

275 - 02(07 99C 7.-*77L

208 - 72577 DC 079. 708

238 - 700 AC7 P87E7(77E7 708

lOAJOR NSOSS SYSTEM*S

087 -C09(97(9 AND7 907.78E C087TR97

7783 -997(TY 79970770 0757(S9E

077 - 8(40T0R (7797777

7778 - 070757 0771770

0777 -C0087.877849 97PRA7

0777 -RESID0UAL NEAT 8070967.

977 - 80577 5797099

7778 - 9(9 779777 PIT 0771.7

878 - 7977 9977777 78970899

987 -M NA70.7' 00E99 AT7(R

985 -C(970780 ROD 08799

082 -E9798- 0077708770

0670 - .90997 71705 0777770708

9779 -REACTOR8 7ROT7(T708

TURBOGENERATOR SYS~TEMS

7020 - 0(777.19887997770I. 977.

035 - 0(9009708 (771770

087 - 70908 0(N0RATOR (9787998

PROJECT MILESTONES

UAJOR SOP SY'STEIJSMI8 - 7407 57(E4

772 - CONDENSATE

003/01058 - 9978 777(0877787 A00777919

0938/068* - 97U77.78* 777(08977 A8 C0879915

NS5 -00799(770 97(7M

OGG -NEVER( 00707NS 78 0(97

777 - 7UR7781E (0799(770 7770957807777775N

072 -AU 9007IA" 8977.08

013 -FI787 0DE77(TION

079 -COD (00(9977 0(9777(9017E(

878 - 5TE9*9EN099T08 B77.0899

7728 -FI787 79077707708

927 -C(00(99(8 07I09UL977NG 9977

002 -C09787777 978

0937 -7EE(080777 977(9770A78 78(977097

0737 -OLA010 S(9 8T77

CS9EN- -9 COMNG1-It

090 RADIA7T77N 7077708770O

LOAJOR HIVAC SYSTEL8S

OM0 - 9(877L.9770

0737 - 978 (0077GS7T08770 .

SECURITY PROJECT

AREA COOPLETION

LICENSING

PLANT PROGRAMS1

FRPRTCAPT PEIOAN ROET

7517 99(9770F 7071 7 90

707779.7 77.45/77C7748T

)AR 7(7 1992 1CALE-DM9 7E7l* 1973

8 SEP I ( 79I79 E I I -77 I - I999 -78 70I7 1.87 I 78. I ).7 I S

PR(99 797 COWL7 7.8 595700 -

DES COWL7 5'S 058 0977578 T/9 (97004(77 757

0(8 (9707 SYS 203 0007 7/8 00604(9 sr 809 7.88PM 709 SY9 ... 7

DES (COWL977 SYS027 C97C7(88 N~ 7 9977977ys20

K(7(00.S7 270 S07YS 2 /2 (9767777 7757 -/77 7

DES7 (008 979 273 ((9777 T/ r 4 0060707SYS5

9(0 0908 SYS 078 0057 7/0, 079=7(7 797~ .R Y ~.

IDES COWL7 9SS 235 C08578 7/0

979 275

.................... .77 . ...

DES (9. 975 238 77O777 7 '7S776 Cr700777 C5 7IYTOS 3

7/0975237

DES (S (0707 90603

DES (9707 978 070

DES (970 SYS 977

DES (0607. 90 97

0DES 7.970 777 077 -

DE$ C970 979.

DES57 7/0 .k8 079. -DE( 7 n(9707.G 979sm8939/77*.

Io M / P 77.7.7-9

I .0070. 3(97776

5/0079890 97I7

50.07

------- 71111111

. ---- II

co.sm T/O I

729980777790708PO7PT 979 035 ,_978 7 87 __,07 79 _I~

2837 208 332 2.58 1

79*770 708 097 0C7757 T/9I0607708 TST

0077-/0. 0. 700.0 .9(7 9777--7(0-977--7-0--8. .. .. 7&=(9r 757,71U08 - 7 078*7787

7-*7777 cr .9

7798 09Cow(7C0E79O7 77T

238

I 90'

7/9 9YS 0599978.60770 SEO9(90E At

007047 7777 DI(ESEL 798 708 777

T7/O SnT.77 238

2147*I p 7. s _ _ _ _ _

C7987770 78 L(799087

7108 971 77C - -111 C~FLM SL - : -. v T7 SYS078. '-7-0I ~l ",I L, - LL I- - /O - ~ 7 - I 7--l

_(9 __ --- 78---7.-- 0 7 00*7T7776 .90977777 T/0 7,708.977

.977H'G.G7907 A80(7000PT

07*/70 771 a

-- 97- ~T/ ~ "--- -i C~ Tf TA - ~ .L - - - -I .-- - - i11 IIGS(0--878770; 0I06I077(97 797 0

(I004(8 797/71099 71-I 11- -111.-i C.45. 1/ I - - -I

, C9777 7/0-227 2

I 227 ~ ~ 2

8"I77 4077 IT

7 /0 979 0OM

-p0t 979/987189

7108 a999(7 97070 -C~.N 'ST - -- -. ~ - n I I - - . I - 77- 0S 979 970o

up 579 95

LEGENI08o _ (7" 00709/09 T578(0707

o3 - 09708609 7(77/71908NO _ 909(E7T078E TEST7 (.T)/P87E9P TEST (91/0R PROGRAM READY

M.- CRI7704AL 79(9

O - SYSTEM 99(777L.777 08 MAJOR8 *7LE(5ONEo~ -S97.TUP 708709(8l TO PLANT7

Q - 70( 797770777

99 591 275

- -- -- -I

997934I

T/0 SY N WSn063 1

OF S'S 098 0-

n -j8111-~ -.I

(0800-7-71 I5 9777 70770.97~I-- .

079 7* 777.At'18I .9C . p70 oo70h T/9 1' i 0 E(S77917087 T/0 SYS 977 W S 0770, 9770 .975 9778 VS8 0777 I I04-797 1797 .E0(77767ST 777. 7778u $0170t8 IO957T PT 99779 7

005797719707 7779 978I I - 7/0 S75 078C-T TOO~~.T'.IQ -0-" 1

09007787 ST77 I

0977578 7/9 C900(9 701779

00008.7T/8 - - I COMIT T/O c T~ - COTR(X.ROD DIVE .. I I i I 2 --- -97 -d oS' a "I(0I(970. 975 09

I( 00 9907

79*770 7007 7/ o~ow. 797

0T97790 .7.80207.70DES (001 777 028 00778 /009967(777-L /997 72

7706877~9R8 -,7O -.8.J EW 91077177.08 - -

005 (007 SS7 097

0CO005(9 797 - 0087779190 ROD7DIVE

CO77.ST* TI - i

(9797 7/0

77990~ 7.777 7/0 - 779 0078I i I ! 8777-79..

-V

-1 ~ .L ' $00009- 57 -M I

CO.79. 7/0 _71908/097097809 'EST

STATOR(00177007

(7 'IT 9079 7~0879 T/0 *__ 78771 07807_DES E~ S'S 03 - -- - .. ,I I.- 1 *7.. 09 97 707.9/( 4 I I D UTS

7757 CW0079048 7777

077*7 90097*700707777( P7.0 I

DES100. 7 779 S

0775 (C8 S70 09 -

DES COWL7 995 0727_

DES COWL8 77YS 0779

I 0(9I720507. 970S 032 - 00777 7/0 1:07978 7777 I.

MS0 00708 S'S 037 1

'-47778 9(777 'EST. 7(78

(97887 7,70 7600.7008S7* 7/0-ELE0T87091 0C70077(7 777T

097C0707 09000 77

IF 57-0770

999z

89. o07t*.7774(COMM7. 0007707

10(9. 7.9* 977 797 (01(I

7 WLLM ETS C7VL

I? ~ 7089.479 177 .7

I 777677777707(779

00660778 S77 0978777 7/9 .78-877979 7738 O- 1- -. - .- -, -- I ~ - ~ - ,~ SI S (7797 8/9 77709 (00068 7777

7795 ~ ~ TS, 0 (877977770 StE77; AT 70

71777p7 -87Kw-

7,9 779 Do75

7 0976970 7/0

D74 COWL0 SYS 07131

I9779787/&l

'977777 T/O I

CO"E7(9 707

0708.~ 7777 927

090007 r7STFL95700I-978 7.0 I I77I9(8077 0 89978

7/o 970S 797

1:0777891978PT

00657 7.7 II 06'17 0 7978(07.97 / -6I110

I - - I - -000070477 -----/-7-.-

78774 5/7( 0090778DES COWL8 SYS0 Q01

I' I TV,~~I8NOPERATION'A .I

9/007PO97E FuSLOAD 7O07

'MULL L. .. 79T 700

.77 ..... IT IKP - ------ -- -- -

13 ASTCWPO..T TS.T/. ,S000190.31 - - - - -.

By-~. fct.LIEE IE Pa7 IT/ww . '(Q TM I -- - --

- - 0979(7/9770 I9/97977 7... OQ7L - - - - -

0 -------- r*905.07.3- --

LOSO AIR 99995Sn03 072 .

C3 97 97

j(567 -- - -/- -7-0-082

D-E IIA.l99

OI A2Z.

I 997 07077707 027/070 20

30708R38 (0.30 ,

jP409A-0/777 BLDG.77897 23 PRE97 COOET T/09 031 OR9SS 037p )- - - - - - -

370 08757.97* OLMI37.*S77771 .\0077~77 70I 008*9C74T7 L II'd 37987 058 .7( 97(777 7977 30-7600-7L 7 8 /~077

097778 rCj 2 0607786 7777T 97so8/779(7718(48 957 79 / IN 085Sy a 97 85778L I77IE77s077*7178 S'V0I

VD1 I 87 32~9 M8~0l 797I 90 9 2 Too 9* TA~ 779 o.77 70277 T09 09 90890 70 7DI77' 70 990 97770 T09 07 77793 97 all C88 M993 ,079 9*23 98O7

ISSSEE 59ISSUE -EW.X A IAIC 75970 7797L OUT9

* S007 740 (7990 TE E,77 U77 0970 79-3 UE 'a7( 9877577 904P(a777.777(70 P7.9* 977\ 89 F L

70(95770 PROJ7*

NOT'UR9909/07(007 97.070LTT 5789*7777 ISSUE ISSUErE77997.LPOEf L C.S R E SC I AP ,0. 7 LC

T 0*7777 9(0777(70

-O ASESS.T c-IS'E 0 D' Q.300 ETTR - 11UE I-L/ T0(CL7(8E

897S. T.09.8*7I I~999

(0840.-. RC.6,797.C677GP. 68..

79771 97077.97.097.70

I - .- .- ---- -- - --- - - - - I - C, .S7 -. , 62 7777j-7----

C060O7(07 707..

'-1

W VS 071

0up S'S 01% -

UP SM 0796 -

99 575 08.- 3/0 979 0871

I(7EUT7O7 70777/78N77t7/70 99707 Pt

1O 6:8 7. 7075 007 97.7 --- ----- q70794I69I -

99 570 88 17/00S's0772 o99Sys 09w -

08S79078 -

7. ~~- 1 IOMRCA

Ws76 (50978 (077`97 77ON7`oOKtooo9rsvOfto o SSE. *.70*4R7T oooo 8708 oacom0*7. NO70 0RNI798778 L*--' Sp78 0787 pW oorssr C 01(908RV SE 08 9780170808 7.7p9OIW 9*N BEGIN 99(877 79L 9

0LElFEN Go .9774770(. 777777(88 766676.77..(787 78970 -=070 7009i9t87097C 778S7 79088 TE 94799L)(7778LS4780577908 * S878 '777(U77.979 998 77 (87 7070871 7797 79979EL00. SU(PRT99708977-70E777(7708 nssosIS LM'- WT~o8 E800LL9*C, TE 7909779*L ED7(7I7L FR(7 M 9ST (g. = l IF. 'r T IEV E

9.0R0SELF8'TM 908E78 ccc 797.9I7707077 4-914 R~ RWE ~WR TETO SS~ ~RSE700(94E7C07*877 8 ~E797.99 080.77977008

78978770 COI.LETE0 998(9 ES74*7.79( FOR 9W7 ~.PROTCTD98( A lASErO. TVLO(99 'C8859.7 769 7? -L99(087 77 0970TE 7E877-5S08877 SE.FOII77N90777 l. (907 I S UNITY(SNIF08 09CONI0'L8T I9710.s477E O"M O.C R, C ~ T N O -SCOITY j, DR-SCIIT770877 079781708I .T4 0 -NSl. IXII OI9.. RSS0T707908 M(O87 90C 90079 0.I 7.9ON787 7I 797 50877 002 970901 77SEEMe78704879(077 .P770S((787Y 7790(60 QUA.77970 (R R70 E77 08(53 7(9077997 82 (9089(78:7 (9((79E RE(VISION 777978770 ILW UI C~ "LC.O

04070(9I 9877777(/ T.8(FS. 77E0E FIE7977I0 AM8 7779974.977T77797677707 (007.E77 W V 9597(7 8 79 7 9L7 9 7

9977707 8--R--- V

77 7MC7 UD977

TEST09 7 8777.DI4L077 0I-ET8./N-5.9 CIE.I 8O77O7.TN EN A7Q(IT RO

97847777( 7(77 9P9 (7'E.90M'S " FT TRy 7E17. 88-77777.`0d. E-7E / 0-(877MY0887799 7879* 8::77 9 (7777088 0! 857 co"(707197 097777979'(190777 ro Py 08-9.8508870 7997* 885. (8.8(.980777ON79,

P.(77 70SS77F8780W977557GR 0OM. 87 7.R.R-7770(05 79978. (91. 088-77.T) R57770(77EE70 770878 95CE95708 7(77E07.7E.\0 FM - - 977897'007.97787/158.(107778,"O(

**99977787( 0S7E999*7999*790 (7*7) 0-eIf 9994('1 Mom79 77879.80 8(9197. 97 97 97 97.TR CLIIUIO

414 387 i 3 30 238 798 Ise De 50 257 3

*R 1994

- =17.87 091=1 797 1MAK.77

7

0

.0

01*9777

1.

9�07

----- 4 - ----------------

I SE01ME �T - .,. .-i v. 9 CD 0

---- -",- 'I-- -� ---. ...i I . 1- 1 - - - - - 4/0 S" Z's 0-cl -

. ". --- - - wmmw�I - -11- - I - - ." . �. -� �- - I I y. - .. -I i --- C>- --- O-

a's .- T/O i ST I �L .'EPA'-LIK K V, 1/0 " 019- - - -1 I .- I... -- -- -j i - 6

I . ... ...I i I 91 0 -- O-C-1. - COWO.E.T rST, i I -.- -- -�; .... .. -,- - - -

- -'. ". I I.-I

I ". -- l- . '... I -- --- --- -. ,- - 1-1- -P � i I I . I

- ...- 1 .mrj -1 1-1- II--bmm 0 i i 0 O-T- ",-, ......6----------- O.- "--' ---------- J, ........... �11 ---

Xs CO-L Sn 00, ---- - . .....- --- -- - I1-1. I- 1- 1 - I - - IL 11DE$-co�l-sn W2- -- -- -- - - I - -,. - -

I I I -. �- -. III --.- I M OOM1 -4� � --- I I F" " a v- AN F -

OES � s" w L - c 'M T/O �� Ew ST I - - - :4 IIAIII �111 11 I Ins" � - S-'ll DQI-�Sm UP 5'S-.91t - -p I I I

ml - 1.1 .1 I I I -1- 1-11 i 0

.11 I I�j -, - .,.. - -1 .. -. A- .,. I - -:0 i V.A. - ----- CT,,

-- - - -, #-. - 4 -qjo sn a'.I... : -, I CO.-NENI TST - -- - .- - - -- I DI -------- I- - -- -- - - .. -11. -?,. .-- '. , V. - .,. i

SMIC F1.19 OWI a

I-IFUISH m- . . .. , I - 5� .21I I - i 0

11 -- - - -1 I -. - .11 .1 .- p I J�O VS 0-3

DES COWPL SS 067 C�10 T/O POTI-L I- .. ". -. 1 I - 1.1 - -- SIS .67CC-O.EqE �§T/�FLU� - 73= w- r5r/rCup- -1 Q 9. 62 0.--- . - - .1 - 1-1 - - I.- - - - - - - i - 1. .1 I - - .- -- - -. .1 -'. '. ."/, �ALIUILM - i II- - 1-1. - - - I- - I.- "P.,. �. ---- - -- . -- -- -- I ... - .==:�>-g. . I . - --- I -.- .-

Xs � sn m /o Vs O!P-3- r T� . . - - 0-

---- ---- ". - --- .... .- ---. i -I.. i -I;_ .. , -_- I-so � ". I --- O "I .I

- - .....- C�.gg 'ST S-1 - -- ;- '. 14 Iz �, J. 9 I 30D-W'S-�E.T., - - . I".. -1. - 91031 .,- I.. I - &,- - I- - - -- - - 7 m - I.A! - OP SS 031 o.- 0

1- .1. I- - - - 9U�[ -- -�", - - -- - - ... - O ,i m

Xs .- - - PFAI.ETER FE�E � �. /.J� I Is, �;, .1. B.I/EGT �NT FMP E.K "S '�"T 11

I I �

I a I 1 a 0

...... .- -.. . . . I 'IV V ..- I. I I - - I-- ��7 V .1.-- - � n". j "\ . .. ....jv x 1�i

.-- ... . I.. - - 1. � - . T., 10

I�l I wlc� I I;im I

'TM Sq-2,1 -- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

-�Tm � � IT1,10 sn 213

- - IV �'s �.j-1 -4ai" 21-5

- - - - - - -i

SECI. KS PT 775-.,E�To KS IWAT LOP k COOL DOW

RE.1 ... C COW"ENT 'ST

T/O Sn 012 - -

-CD� � �>-OP 515 07-A

�1/0" 019�I Ev�f -Y m t IT51 -- - - ----

DES CO^ SYS 092 I 11IIs, _-its

�o - S� - I ... P'.1 R� I

�Tl WARr/M Ms.- ----- -- -- - _ I

WI FLKTIOML TEST1.9

-FI

-cow's T/O CQ-Q.E.l 'S'

I -- C�M-4190-0'"v ST sn cAN I - r-�_ _.FAIEM M- 11I��Ew ST

,2i=.Tllgtlll "I - - - - - - - - - - - - -

co.sm 1/0 �Mrl�

Su C, -lu

,.i(. sn- oa - '- - - - - _jiC�CNT M/FLM

F I Es.. �� � I " 'L"o �m '� I/O s!! -�r- 4

Page 8: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE
Page 9: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

2 , d .~ i t , ,: U 4 ,p =-!, At

I ,

r t EjB.,

En\ ' ' ' WA TTS BAR

JULY28, 1994

Vt' -I . '

t : t. O". - .,

u!i

Af'

NRCTVA MANAGEMVENTj.. `MEETING

c,6k4, .,AX.I~;.. ii,' -l , i -i ' ,

, : t, '

.A ,5

:k I , II \'

Page 10: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

AGENDANRC/TVA

WBN LICENSINGSTATUS MEETING

JULY 28, 1994

12:30-3:00 PMTHE WBN ENERGY CONNECTION

(TRAINING CENTER)

* OPENING REMARKS

* PLANT COMPLETION PLAN

* PLANT STATUS

* STARTUP STATUS

* OPERATIONAL READINESS

* LICENSING MILESTONES

* NUCLEAR ASSURANCE OVERVIEW

* CONCERNS RESOLUTION STATUS

* CLOSING REMARKS

TVA/NRC NUNN/RUSSELL

TVA - NUNN

TVA -

TVA -

SCALICE

BAJESTANI

TVA - MOODY

TVA - SCHOFIELD

TVA - SPIERS

TVA - HARDING

TVA/NRC - NUNN/RUSSELL

PG 2

PG 3

PG 14

PG 18

PG 21

PG 28

PG 35

PG 41

PG 47

Page 11: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

TVA/NRC

LICENSING STATUS MEETING

JULY 28,1994

1

Page 12: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

OPENING REMARK(S

D. E. NUNN

2

Page 13: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

COMPLETION PLAN

D. E. NUNN

3

Page 14: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

COMPLETION PLAN - OVERVIEW

* DEVELOPED BY MULTI-ORGANIZATION TEAM

- TEAM MEMBERSHIP: MODIFICATIONS, ENGINEERING,LICENSING, NUCLEAR ASSURANCE, SITE SUPPORT, PLANT,STARTUP AND TEST, PLANT COMPLETION

- FULLY INTEGRATED SCOPE AND SCHEDULE PLAN WITH SITEORGANIZATION BUY-IN TO COMPLETION

* BASED ON DETAILED/LOGICAL REVIEWS

- ALL REMAINING WORK TIED TO SCHEDULE MILESTONES

- IDENTIFIED SPECIFIC OWNERSHIP OF SCHEDULE MILESTONESAT MAJOR PLANT EVOLUTION

* SCHEDULE DEVELOPED FROM THE BOTTOM-UP

- SCHEDULE DEVELOPED STARTING AT THE LOWEST LEVEL OFWORK IMPLEMENTING DOCUMENT

- SCHEDULE BASED ON EXPERIENCES AND "REASONABLENESS"OF SYSTEM/AREAS TO BE COMPLETED

- SCHEDULE VALIDATED BY TEAM INTERACTION, REVIEW, ANDBUY-IN

4

Page 15: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

- - - - -M- - - -- - - - - -

WATTS BAR NUCLEAR PLANTUNIT 1 SUMMARY SCHEDULE

March Fuel Load[1992 1993 1994 1995 1996

[ 4th 1st 2nd | 3rd 4th 1st 2nd 3rd |4th 1st 2nd 3rd 4th 1 st

llot Containment Integrated Full Power COTIERCIALSecondarv Functional Leak Rate Fuel License COPERATION

lldro OpenVessel Test " Load

B B B B .'l 'B: :"" '' s>BV^5 N B : L; sss sIntee g r a t

Safeguards ,i

Major EngineerinO Design Complete Supplemental Hot

Functional Test

Construction Major Design ChangesComplete

Preoperational Test for Fuel Load Complete6.9KV Test Condenser Vacuum

Operations/Licensin ConfirmlMode 6

OVT Line Ups, llFTSupport Surveillance Test

Design

Master Fuse List Q-List QA Records Baseline Ele. Iksu s 100% ap/SP Punchlist Closure

6 ir$S IDEnd Ist SALP Period NRC -ssue Final Draft Tech. Licensing Issite Tech Spec. Certification

Tech. Spec Proof Finalized Spec ketter

mAnergency Plans Submitted NRC(;raded FSARRaseline Rsole eNRC FullStarityLockdown

Exeris Complete Comments

Security Plat Submitted Complete Security System

Page 16: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

Sp-ci.1 fon-.t R1q.9st

27-jul-94

WBN - UNIT 1

COMPLETION PLAN - SYSTEM COMPLE-

I---- -- -Revision 0 RESP: E.1 Good

AND TURNOVER SCHEDULE

TURNOYER 1994 -yy_ -: --- :-::- - -_: -: __::: W eek-Endin __::-___--

MILESTONE 04/24 05/01 5/08 .- /IS :05/22. 05/29 06/OS0 06/12 9 066 07/03-77V4Engr Compi146 Compl) _________

Mods 033 8 . 3c00 2 7 77 3f QO . 9d Qf

Release to 242 030. .. 084. ..- 0

26 03ff0PmrP§ Q7 2635200 090aoXtMAS

...~*'neelI'~ . .. ...... ... ...

(70 Cornp) I ____027:____ _____

MAintenance 033b . 0

Startup 281M Id07

(52.) .... . ..

141 Cornm p l) . D

Egerg.a030StartuP ep .. ........0..3000.08..0j00

estin 7091 09

Engineering. 035~~o8SPAEI :06

Plant........ ....

S cetartP eo .....

SPOCom03p03

rea I/ .YD I O ... .....SU Tu nove w ..............

(5 Compl)_____ _____ _____ _____ _____ _____ _____ _____ __________ _____ _____

NOTES: H = HANGER RAt (MIS tE N EINT 36) tOR H I: STS(Mt/ALPHA = SU1S(OPI: SHADED ITEMS ARE COMPLETE: SPOG = SSTEN PLANI OPERABILIIT CHECKLIST SPAt = SISItI PLANT ACCEPTANCE tYALUAIION

rcpo.Xu-- -I

Page 17: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

I nRe P..t st --- WBR-uJNII R Meyision 0 RESP c1-27-Jul-94 W COMPLETION PLAN - SYSTEM COMPLETWAN 0TURNOVER SCHEDULE -po ,.ITIIRJnVFR .194 :Week' FndingF 199441

I

NOUtS: H = HANGER RItL (KTS Rtt (tER 36) IOR HU1; SIS!ER/ALPHA = SUS(SOF[; SHADED HlEMtS ARE COMtPLElf SPOC = STS1IM rENA CFi tABilil (HEUIl151; SPAt = SSl(iM PLNI ACCEPTANCE [YALUAIION

{ S e X - @ 9 of s r r f J as f

MILESTONE 07/31 08/07 08/14 08/F2 08/28_ 09/04 09_11 09/18_ _ 09j25 10/02 I a/1 1D 9 T-1016 10/13 10/30iods - 030d 030b 031p 013 030r 227 077b 234 278 291 254 293 078

Release to 031o 031e 090g 026 246 275 279 253 298 299 233Startup 083 031n 272 250 277 282 289 257

': 031q 263 294 283 296 286

270 065 264 297 284 29021' 287

170 Com pl) 295

Maintenance 094 025 030d 031e 090g 013 030r 227 077b 234 254Release to 221 031r 031o 031m 026 246 275 253Startup 2 ..9. 049 083 031n 031p 250 299

090a 090f 031q 263090c 270 065

14Cmp)271___

Engineering 030c 082c 030i 030b 031c 013 030f 072 262 090aSPAE I 215 082d 030d 031p 031e 077a 264 090b

031m 031f 077b 090c065 077c 090d

090e090f

(66 Compl) 090gStart Preop 030k 063 261 003a 030a 067 030i 030b 031c 013 030f 024 200resting 082 b 030c 0301 082d 030d 031p 031e 077 072 262

039 031m 251 031f 264082c 065 032215 -079

(57 Compl) 090hSU Turnover 088 260 247 041 025to Ops 233 275 063

276 068221227

(54 Compl) - 236

Engineering 088SPAE 11(53 Comnpl)-Plant 244a 088 272 260 247 275Acceptance 276

SPOC2 054 038 280 005 050 044 207 200 202 206 218 020 012058 216 201 203 210 220 208 235

217 222 204 240 241 209 237

.245 205 247 225 238_ _3_ __ _ __o_ __p_ _ _ 239

(r3a T/O YD06 AB03 RB01 RB03 RB04 D8O1(5 Compl) ... ... . ..... ... . . . . . . RB02 TBOI TB06 TBO7

Page 18: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

- - - - -m- - - - -m- - - m -

WATTS BAR NUCLEAR UNIT IMODIFICATIONS WORKPLANS

COMPLETION PLAN

H

.iU'

B~IN C) U) N Cb on U) 0- Nt - N. t~ -

N) U) O I I N O . - N N^. O - N N)0O 0) 0D 00 C 0 00 00 00 0- 0- W - W Do0o0oo o o oo o o o 0o

4'JJLAn

TOTAL TO GO AS OF 5/15/94 = 1,939 WORKPLANS

ACTUAL TO GO AS OF 5/15/94 = 1,939

EMERGENT ANTICIPATED = 0

BUDGETED UNIT RATE = NOT APPUCABLE

-, , I n l I I I i I I I I I I I I I I I I L A L I I I I I I I ICo - n o0 N. N N) O - -) U) N o o - N 0

0 0 4 0 , .00 0 0 0 009 9 , ,0 I4 4 4 o o o) o o o o o o- o- o- o o

CURRENT STATUS200

160C/ILUF

z 120Da

S~ 80LUJUJ

40

0

WEEK ENODING 5-15 05-22 05-29 f0-05 OG-12 | 06-19 OG-26 07-03 07-10 07-17 07-24 07-31 08-07 08-14 11-07

VWE ACT ] 0089 104 77 119 14C 91 97 68 .90 96

WK PLAt =3 85 106 76 107 139 87 85 55 84 73 99 60 74

WK EMEnG

LCTREM4 - 2,208 2,120 2.016 1 ,9C_ 1,820 _ 1.672 1581 1,484 1.416 1,326 1,230

200

160 1-

U,

120

Dai 80

40

0

2,000

1,600

Zz

1,200 2crCOIUl

800 I-

400

0,I - ^) Un N a U n o 0 .^^,) 0 -t - ^2 U -; ^ u N CU U) N a ID W) N CU UI N

o o - - - --0 00---------- oooo---00

WEEK ENDING

WEEKLY PLAN ANTICIPATED EMERGENT REMAINING. .- ., -- - - -

2,000

1,600 azZ

1,200 >LUJccC',LUaLJ

800 ZFz

400 a

.. ; s -. .. ..

rll IIIL.I'l 111 a" 111 1 ' ' ' 'rll lli

m

1 1,385 1,312 1,213 1,153 1,079 1,1012| PLAN FEMI - - I?2.209 2,124 12-018 11.942- .

I 1, 835 I 1.9, I9 1, MO09 1,52 4 1, 1449

Page 19: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

WATTS BAR NUCLEAR UNIT 1MODIFICATIONS SCOPE STATUS

(TOTALS BASED ON PROJECT COMPLETION PLAN)

COMPLETED COMPLETED TO GO TOTAL

COMMODITY 6/3/91 THRU 3/28 THRU AS OF AT03/27/94 07/24/94 07/25/94 COMPLETION

CABLE PULLING (LF) 978,983 153,624 93,540 1,226,147

CONDUIT INSTALLATION (LF) 119,949 27,054 5,325 152,328

CABLE TERMINATIONS (EA) 69,925 11,533 4,746 86,204

CONDUIT/TRAY SUPPORTS (EA) 14,461 3,147 3,853 21,461

RAYCHEM SPLICES (EA) 18,424 859 440 19,723

LARGE BORE PIPE (LF) 2,055 403 27 2,485

SMALL BORE PIPE (LF) 8,937 346 19,147 28,430

LARGE BORE HANGERS (EA) * 2,682 468 373 3,523

SMALL BORE HANGERS (EA) * 2,325 417 69 2,811

INSTRUMENT TUBING & PIPING (LF) 22,824 3,670 549 27,043

HVAC DUCTWORK MODS (LF) 11,345 2,373 117 13,835

* INCLUDES ONLY NEW HANGERS AND HANGER MODS

9

Page 20: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

MAJOR SCHEDULE ITEMS

* FUEL LOAD SCHEDULE - MARCH 1995

* FULLY INTEGRATED LEVEL 1 SCHEDULE WHICH INCLUDES:

- PLANT

- ENGINEERING

- MODIFICATIONS

- LICENSING

° SIGNIFICANT NRC ACTIONS ARE INCLUDED

* HFT COMPLETE - SOME RETEST ACTIONS REMAIN

* SCHEDULE IS ACHIEVABLE

10

Page 21: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

COMPLETION PLAN - LICENSING ISSUES

° CAP/SP CLOSURE AND NRC 100% INSPECTIONS

° NRC OPEN ITEMS CLOSURE

* RESOLUTION OF FIRE PROTECTION ISSUES

- THERMOLAG

- FIRE PROTECTION RAIs

- NRC 90% INSPECTION

* PHYSICAL SECURITY IMPLEMENTATION

* ENVIRONMENTAL INFORMATION REVIEW

* CLOSURE OF EMPLOYEE CONCERNS

I 1

Page 22: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

ADDRESSING LESSONS LEARNED

* PROGRAM OBJECTIVE

- ENSURE PROBLEM ROOT CAUSES ARE UNDERSTOOD ANDPREVENTED FROM OCCURRING AT WBN

* PROGRAM ELEMENTS

- EVALUATE/DOCUMENT APPLICABILITY OF LESSONS LEARNEDFROM SQN, OTHER PLANTS, AND PRIOR WBN REVIEWS

- DEVELOP, DOCUMENT, AND IMPLEMENT APPROPRIATECORRECTIVE MEASURES WHERE NECESSARY

* PROGRAM FOCUS

- BALANCE OF PLANT (BOP)

- OPERATIONS

- BACKLOGS/WORK PRIORITIZATION

- PROGRAMS

- PEOPLE/ORGANIZATION/CULTURE

- CORPORATE/SITE INTERFACE

12

Page 23: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

° PROGRAM REVIEW RESULTS

DISPOSITIONED OVER 1400 ITEMS FROM SQN RESTART

PROGRAM

COMPLETED INDEPENDENT DESIGN REVIEW OF BOP SYSTEMS

COMPLETED REVIEW OF MAJOR PROGRAMS (EQ. PREDICTIVE

MAINTENANCE, VALVES, CHEMISTRY, TEMPORARY REPAIR,

EQUIPMENT TRENDING, ASME PROGRAMS,EROSION/CORROSION)

COMPLETED REVIEW OF NEARLY 400 DESIGN RELATED ITEMS

FROM SQN RESTART PROGRAM

* 89% NOT APPLICABLE/PREVIOUSLY ADDRESSED

* 4% TO BE IMPLEMENTED PRIOR TO FUEL LOAD

* 7% TO BE IMPLEMENTED AFTER FUEL LOAD

REMAINING OPEN ACTIONS

COMPLETE IMPLEMENTATION OF PERSONNEL PERFORMANCERELATED INITIATIVES

COMPLETE REVIEW OF DESIGN CHANGES TO SQN SINCEINITIAL DESIGN

IMPLEMENT REMAINING PROGRAM RECOMMENDATIONS

1 3

Page 24: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

PLANT STATUS

JOHN SCALICE

14

Page 25: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

STARTUP ACTIVITIES STATUS

HOT FUNCTIONAL TESTING (HFT)

* COMPLETED JUNE 8, 1994

* PERFORMANCE ASSESSMENT

- DEMONSTRATED EFFECTIVENESS OF THE PLANT STAFF

- OPERATORS PROVIDED AN OPPORTUNITY TO OPERATE PLANT

- OPERATIONAL LEARNING EXPERIENCE

- LESSONS LEARNED INTEGRATED INTO OPERATIONALIMPROVEMENTS

* PROBLEM AREAS

- MAIN TURBINE MECHANICAL OVERSPEED TRIP

- SAFETY INJECTION CHECK VALVE

- STEAM GENERATOR SAFETY VALVE

- POSITIVE DISPLACEMENT CHARGING PUMP

- PRESSURIZER PRESSURE CONTROLLER

- MOTOR DRIVEN AUXILIARY FEEDWATER SYSTEM

- RESIDUAL HEAT REMOVAL PUMP

- TURBINE DRIVEN AUX. FEEDWATER PUMP

1 5

Page 26: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

STARTUP ACTIVITIES STATUS

SUPPLEMENTAL HFT TESTING

* SUPPLEMENTAL HFT TO BE PERFORMED

0 SCHEDULED FOR MID JANUARY 1 995

° TDAFW

* RHR

16

Page 27: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

STARTUP ACTIVITIES STATUS

e CONTAINMENT INTEGRATED LEAK RATE TEST - COMPLETED 6/28/94

- REPORTABLE LEAKAGE WELL WITHIN TOLERANCE

* OPEN VESSEL TESTING (OVT) RETEST STARTED JULY 17 - ONGOING

0 PLANT READY FOR NEXT MAJOR MILESTONE - INTEGRATEDSAFEGUARDS TEST (IST) - SCHEDULED FOR MID OCTOBER

o FINAL COMPLETION/FUEL LOAD SCHEDULE DEVELOPED

a SCHEDULE IS ACHIEVABLE FOR MARCH FUEL LOAD

17

Page 28: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

STARTUP STATUS

M. BAJESTANI

1 8

Page 29: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

MAJOR TEST MILESTONES

ONGOING ACTIVITIES

* OVT - STATUS

* DIESEL GENERATORS - STATUS

* REACTOR PROTECTION SYSTEM (RPS) - STATUS

UPCOMING ACTIVITIES

° INTEGRATED SAFEGUARDS TEST

* SECONDARY CONTAINMENT TEST

° CONTROL ROOM PRESSURIZATION TEST

* TESTS CONTAINED IN THE COMPLETION PLAN

19

Page 30: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

STARTUP STATUS

* PREOP TESTS

- 48 OF 134 PTIs (PREOPERATIONAL TEST INSTRUCTIONS)FIELD COMPLETE

- 25 OF 39 ATIs (ACCEPTANCE TEST INSTRUCTIONS)FIELD COMPLETE

* CHALLENGES

- HVAC

- INTEGRATED SAFEGUARDS TEST

* SCHEDULE IS ACHIEVABLE

20

Page 31: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

OPERATIONAL READINESS

D. E. MOODY

21

Page 32: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

OPERATIONAL READINESS PROGRAM (ORP)

* 109 PROGRAMS DEFINED IN THE ORP

- 98 PROGRAM SELF-ASSESSMENTS PLANNED

- 83 SELF ASSESSMENTS PERFORMED AND REPORTS ISSUED

* ASSESSMENT RESULTS

- 66 OF THE 83 PROGRAMS HAVE SUCCESSFULLYCOMPLETED SELF ASSESSMENTS

- 17 PROGRAMS REQUIRE WORK AND REASSESSMENT

- 41 PROGRAMS HAVE BEEN INDEPENDENTLY REVIEWED BYNUCLEAR ASSURANCE

22

Page 33: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

OPERATIONS ACTIVITIES

* AREAS FOR CONTINUED IMPROVEMENT

- IMPLEMENTATION OF OPERATIONAL CONFIGURATIONCONTROL PROGRAM

- OWNERSHIP OF WORK CONTROL

- WORK CONTROL 12 WEEK ROLLING SCHEDULE

- TIMELY/EFFECTIVE IMPLEMENTATION OF NEW OPERATIONALPROGRAMS

- CONTINUED EMPHASIS ON OWNERSHIP

23

Page 34: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

SYSTEM ENGINEERING ACTIVITIES

OPERATIONAL SUPPORT TRANSITION

* IMPROVEMENTS

- PROVIDING SYSTEM ENGINEER ROLE MODELS IN TECH

SUPPORT

-- SRO (FORMER ASOs ON SHIFT)

- BOP SECTION MANAGER RETURNED FROM STARTUP

- STAFFED 24-HOUR ROTATION DURING HFT (CONTINUE

DURING POWER ASCENSION AND OPERATIONS)

- SYSTEM ENGINEERS ASSIGNED AS TASK MANAGERS FOR

KEY EVENTS OR RESOLUTION OF PROBLEMS

- ESTABLISHED AN OPERATIONAL READINESS SYSTEM

ENGINEERING PROGRAM SELF-ASSESSMENT

V AREAS FOR CONTINUED IMPROVEMENT

- INCREASED SYSTEM ENGINEER INVOLVEMENT IN PLANT

EVOLUTIONS

- COMPLETE PROCEDURES UPGRADE

- COMPLETE SYSTEM ENGINEERS QUALIFICATION PROGRAM

24

Page 35: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

RADCON ACTIVITIES

ALARA

* IMPROVEMENTS

- ALARA COMMITTEE MEETINGS HAVE BEEN STRENGTHENED

- SENIOR MANAGEMENT SUPPORT

- QUORUM REQUIREMENT

- MEETINGS STRUCTURED TO BE MORE EFFICIENT

- FOCUS PLACED UPON RESOLUTION OF OPEN WALKDOWNISSUES

V AREAS FOR CONTINUED IMPROVEMENT

- RESOLUTION OF REMAINING ALARA WALKDOWN ISSUES

- HEIGHTEN AWARENESS OF ALARA

25

Page 36: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

CHEMISTRY ACTIVITIES

V IMPROVEMENTS

- EFFECTIVE SYSTEM CHEMISTRY CONTROL - HFT

- ACQUISITION /SETUP OF NEW COUNT ROOM & LABORATORYEQU IPM ENT

- UPGRADE OF SECONDARY PROCESS INSTRUMENTATION

* AREAS FOR CONTINUED IMPROVEMENT

- POST ACCIDENT SAMPLING

- SECONDARY CHEMICAL ADDITION SYSTEM UPGRADES

- TRAINING

- INTERFACE WITH OPERATIONS

26

Page 37: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

MAINTENANCE PROGRAMS

° IMPROVEMENTS

- UNIT 1 OPERATIONAL PREPARATION TEAM TRAINING

- FOLLOW-UP PERFORMANCE EVALUATION PROGRAM (PEP)NOTED IMPROVEMENTS

- QUALITY FIRST THINKING AND QUESTIONING ATTITUDE OFLINE WORKERS DURING HFT

- PROMPT AND PROACTIVE RESPONSE TO HFT EMERGENTWORK

- ADVANCED RADWORKER TRAINING

* AREAS FOR CONTINUED IMPROVEMENT

- CONTROLLING BACKLOG ON PLANT OWNED EQUIPMENT

- OPERATIONAL 12-WEEK ROLLING SCHEDULE

27

Page 38: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

LICENSING MILESTONES

BRUCE SCHOFIELD

28

Page 39: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

SIGNIFICANT LICENSING ACTIONS REMAINING

* FSAR FINALIZATION

* TECHNICAL SPECIFICATION CERTIFICATION

* NRC - NRR TAC ITEMS CLOSURE

* ENVIRONMENTAL INFORMATION REVIEW

* NRC 94300 INSPECTION ITEMS

* CAPs/SPs CLOSURE

* NRC OPEN ITEMS CLOSURE

29

Page 40: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

NRC/TVA SCHEDULAR ACTIVITIES

V REVIEWED NRC 94300 LETTER DATED 6/23/94

V "INSPECTION PREPAREDNESS "SCHEDULES FOR EACH 94300ITEM ARE BEING DEVELOPED

* SCHEDULES DEVELOPED WILL ENSURE AN ORDERLY REVIEWCYCLE

* TVA WILL COORDINATE SCHEDULE ACTIVITIES WITH NRCSTAFF

30

Page 41: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

CAP/SP-COMPLETION

* 28 CAPs/SPs

* 75% COMPLETION LEVEL

- TO NRC - COMPLETE

- 23 NRC REVIEW COMPLETE

* 100% COMPLETION LEVEL

- 10 SUBMITTED TO NRC

- 9 NRC REVIEW COMPLETE

* IMPROVEMENT INITIATIVES

- 100% CLOSURE REPORT MODEL ESTABLISHED

- CAP SUBISSUES/CLOSURE TEAMS DEVELOPED

- ACCELERATED 100% CLOSURE SCHEDULE

31

Page 42: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

m - - -=- m - - -- - - - - -

WATTS BAR NUCLEAR UNIT ILICENSING

CAP/SP MILESTONES

TOTAL TO GO AS OF 5/15/94 = 18 ITEMSACTUAL TO GO AS OF 5/15/94 = 18 ITEMSEMERGENT ANTICIPATED = 0

5

4

.. ......

I I I I I I

...... .

.I

i..: i

.. -..

I I 1 I I

N CJ A N CD C 0 N O- t - N- ! Z( 1 't ID CA

' V E C N- Nf N- N- 9- N C) 9 C D 0 N 0 0CC 00 0 00000000000

N O ) 0 D (O O r 2 0 N t ~-O 'A wl 'A N O A N CD CD co N O! CD N O lo Cm) 0 N- -t - w CD 'n N 0 CD

6 6 O-NC6 -- N -N -N N - -0 - - 0- NC N N N 1 C 6 6 9 4 4°-- N 00 9-00000000000000 000000000WEEK ENDING

WEEKLY PLAN ANTICIPATED EMERGENT

li .. =

QWoCCKCx<rrc n.ArdJCQTYI)RW

BUDGETED UNIT RATE NOT APPLICABLE

................... ............ ............................... ........ ............................... ..............i..... .... ... .... ............ ............................... ............... ......... . .. . ....... .. ...... ... .. . ........ .. ........... ......... . ... ..... .. ..... .... ... .......... ...... .. . ....... .. . ......... ..... .... .. ........ ... .... ..

mnwF:z

ww.

3

2

0

20

16

ci12 z

12

wCc,

w

Fi

8<D

4

0

REMAINING

cl 0N? C?)r- r-0 0

-%I - - - -"-- -

---I - - - -

I l I .. I 1 l 1 . I I ril . I . I . .. . . . . . . . . I .I I I I I I I

Page 43: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

NRC OPEN ITEMS-CLOSURE PROGRESS

* CLOSURE ACTIVITY - JANUARY THROUGH JULY 24, 1994

- OPEN ITEMS JANUARY 94

- TVA CLOSED JANUARY TO JULY

- NRC OPENED JANUARY TO JULY

267

1 63

11 2

* CLOSURE ACTIVITY - CURRENT STATUS

- TVA OPEN ITEMS

- NRC OPEN ITEMS REVIEWING

21 6

78

* IMPROVEMENT INITIATIVES

- DEDICATED RESOURCES ASSIGNED TO CLOSUREPREPARATION

- ACCELERATED SCHEDULE ESTABLISHED

- SENIOR MANAGEMENT FOCUS

33

Page 44: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

, ---- -U - - -- - -- - W.

NRC Open Items300

250

200

150

100

50

0

Jan 94 Feb 94 Mar 94 Apr 94 iMay94 Jun94 [Jul94- |AU94 Sep94 Oct94 |Nov94 Dec94 Jan95 Feb95 Mar95 AFL

Awaiting NRC Review 65 68 60 4 40 50 78

TVA Backlog f- 256 256 263 259 253 238 216 184 146 119 91 39 23 7 4 4

. I I - -I

Page 45: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

NUCLEAR ASSURANCE-OVERVIEW

L. SPIERS

35

Page 46: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

QUALITY COMPLETION ACTIVITIES

* QUALITY INSPECTIONS

- QUALITY CONTROL INSPECTIONS

* 14,200 MANHOURS/MONTH

- QUALITY ENGINEERING DOCUMENT REVIEWS

* 750 MANHOURS/MONTH

- CAPs/SPs REVIEWS

V 1500 MANHOURS/MONTH

- INSPECTOR OF THE DAY

a 80 MANHOURS/MONTH

- QUALITY AUDIT & ASSESSMENTS

V 900 MANHOURS-/MONTH

36

Page 47: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

QUALITY COMPLETION ACTIVITIES

* RESULTS

- MODIFICATIONS INSPECTIONS (97.7%) ACCEPTABLE

- PLANT COMPLETION INSPECTIONS (99.2%) ACCEPTABLE

- OVERVIEW INSPECTIONS (99.5%) ACCEPTABLE

- WORKPLANS/WORK ORDERS (99.2%) ACCEPTABLE

* NOTABLE FINDINGS

- MODIFICATIONS MECHANICAL DOCUMENTATION

- CONFIGURATION/ STATUS CONTROL

- DCN CLOSURE PRIOR TO WORK COMPLETION

37

Page 48: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

QUALITY COMPLETION ACTIVITIES

CAPs/SPs REVIEWS

- CONTINUOUS OVERVIEW OF ALL CAPs/SPs

- FORMAL ASSESSMENTS PRIOR TO KEY MILESTONES(75% & 100%)

- RECENT SIGNIFICANT 75% REVIEWS

* INSTRUMENT LINES

* VENDOR INFORMATION

- FINDINGS ARE PROMPTLY IDENTIFIED TO RESPONSIBLEORGANIZATION

- WEEKLY REVIEWS OF DISCREPANCIES

- CORRECTIVE ACTIONS ARE REVIEWED/VERIFIEDCOMPLETE

30

Page 49: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

OPERATIONAL READINESS ACTIVITIES

* INSPECTIONS

* MAINTENANCE AND PEER 1225 MANHOURS/MONTH

- RESULTS

* MAINTENANCE (98.1 %) ACCEPTANCE

a PEER (100%) ACCEPTANCE

* QUALITY AUDITS & ASSESSMENTS 1300 MANHOURS/MONTH

- PEP (PERFORMANCE EVALUATION PROGRAM)

* OPERATIONS

• MAINTENANCE

- RESULTS

* OPs PERSONNEL PROACTIVE AND RESPONSIVE TOCOACHING

* "CONTROL ROOM OPERATIONS/DEMEANOR"IMPROVING

* MAINTENANCE PERSONNEL PROMPT, PROACTIVE,TEAMWORK IN PROBLEM SOLVING

- FINDINGS

* OFF-NORMAL CONDITIONS RESPONSE

• EXCESSIVE USE OF UNAUTHORIZED OPERATORAIDS

* MAINTENANCE MATERIAL AVAILABILITY

39

Page 50: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

QUALITY COMPLETION ACTIVITIES

CONCLUSIONS

* NRC NOTICE OF VIOLATION (NOV) 94-13

* PLANT BUILT/TESTED - ACCEPTABLE

* LINE ORGANIZATIONS - TAKING OWNERSHIP OFWEAKNESSES

* PROGRAMS/PEOPLE - OPERATIONS TRANSITIONEFFECTIVE

* ASSESSMENT RESULTS - SUBSTANTIATE ORGANIZATIONSELF-ASSESSMENT CONCLUSIONS

40

Page 51: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

CONCERNS RESOLUTION PROGRAM

M. R. HARDING

41

Page 52: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

- -- --- -m- - - - - - m - - -

WATTS BAR UNIT 1CORRECTIVE ACTION TRACKING DOCUMENT

COMPLETION SCHEDULE

300

LU 250

LiJE 200

0o 1500c) 100

u 950

0

NOTE: 425 CATDs CLOSED TO DATE

Page 53: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

q - --- m -. -m-- - m - mq -

Watts BarTVA and Contractor Issues Trend

600

500

400

300

200

100

0

71

39

1987 1988 1989 1990 1991 1992 1993 1994^

* - 1994 data through June 30

TVA F ContractorI Issues I I Issues

551

iiii

iI

itii

.4111

117 112

1986

187173

30

Page 54: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

- -mq - - --- me -- ---- mq -

DOL Complaints TrendWatts Bar Nuclear Plant

19

17

12

25

20

15

10

5

01985 1986 1987 1988 1989 1990 1991 1992 1993 1994*

* - 1994 data through June 30

43

1

78

H . .. ...7

Page 55: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

SURVEY RESULTS% POSITIVE

JULY 1993NRC

JUNE 1994OIG

WOULDSAFETY

YOU REPORT A NUCLEARCONCERN?

WOULD YOU RAISE A CONCERN TOYOUR SUPERVISOR?

ARE YOU AWARE OF CRS/ECP?

WOULDECP?

YOU RAISE ISSUES TO CRS OR

45

>99

95

88

>99

98

98

93 96

Page 56: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

PROACTIVE APPROACH BEING TAKENAT WATTS BAR

v LOOKBACK PROJECT IN PROGRESS

* COMMUNICATIONS PLAN

° SUPERVISOR TRAINING '

* EMPLOYEE CONCERNS TASK FORCE

* STRENGTHEN CRS

46

Page 57: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

CLOSING REMARK(S

D. E. NUNN

47

Page 58: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

-- I 1lak I

I

(- a -- "A ,4-, (p2) -'

f1z .- A

A

IIIIII

II

/00 � � zecl ll�

Page 59: NUCLEAR REGULATORY COMMISSION · TVA's presentation followed the slides in Enclosure 2. The staff and TVA made the following comments and commitments: ... MI8 - 7407 57(E4 772 - CONDENSATE

-- - -- - - - -

Facts AteWWatts Bar Nuclear Power Plant

OwnerTennessee Valley Authority

CapacityTwo 1,270 megawatt units (2,540 million watts total)

Site1,700 acres including the hydro station and coal plant on the Tennessee River in SpringCity, Tennessee.

FuelSlightly enriched uranium dioxide pellets in fuel rods clad with Zircaloy metal. 264 fuel rodsper fuel assembly, 193 fuel assemblies per reactor.

Reactor InformationWestinghouse pressurized water reactors fabricated of carbon steel with an internalstainless steel cladding.

Inside diameter - 14.4 feet (4.39 meters)Inside height - 43.8 feet (13.35 meters)Side thickness - 9.4 inches (23.86 centimeters)

Holds fuel assemblies. This is where heat is produced through the fission process.

Nuclear ProcessWater in the reactor is heated by uranium fuel being split or fissioned. Heat is releasedfrom the fission process. The heat is used to make the water in the reactor vessel very hot.This heated water then goes to the steam generator. The steam generators use the heatedwater to boil a secondary source of water, creating steam. The steam is used to turnturbines which spin a generator producing electricity.

Steam Generator4 per reactorHeight - 67.6 feet (20.60 meters)

Heated water from the reactor passes through tubes inside the steam generatorswhere heat is given up to a secondary source of water. This secondary watersource boils and turns to steam. A

E- - - - m - m uIurbines W1 high pressure3 low pressureTurbines rotate at 1,800 rpm (revolutions per minute)Steam inlet temperature to high pressure turbine: 541.50 F (2830 C).Steam inlet temperature to low pressure turbine: 5140 F (267.80 C).

GeneratorProduces 24,000 volts. Power leaves the generator and is directed to transformers in theswitchyard where it is stepped up to 500,000 volts.

CondenserA large box with hollow tubes running through it.

Steam from the steam generator passes through the condenser to be turned back intowater.

Water from the Tennessee River passes inside the tubes in the condenser as the steampasses around the outside of the tubes. The steam, as it is cooled, turns back into water.The water in the tubes picks up the heat from the steam. This heated water then goes tothe cooling towers to be cooled. The cooled steam, or water, is sent back to the steamgenerators to be boiled again.

Cooling TowersTwo cooling towers; one per unit.

Height - 504 feet tall (153.62 meters)Width at base - 405 feet (123.4 meters)Each tower basin holds 4,800,000 gallons of water (18,168,000 liters).The water in the condenser tubes that cooled the steam goes to the cooling towers.410,000 gallons per minute (1,551,850 liters) of water passes through the condenser andthen to the cooling towers. The towers remove heat from the water. What goes out thetop of the tower is evaporated water and warm air. The cooled water which falls to thebottom of the tower is collected in the basin and pumped back into the condenser. This isa closed loop system with no water being directed back to the river.

Pressurized Water Reactor (PWR)

1