Nuclear in the Energy Mix - Light Water Reactor ... Meetings/09-30 IAEA/10-2/CHAUS… · •Nuclear...
Transcript of Nuclear in the Energy Mix - Light Water Reactor ... Meetings/09-30 IAEA/10-2/CHAUS… · •Nuclear...
Anton ChaushevskiFaculty of Electrical Eng.& IT,
Sts Cyril and Methodius University - Skopje
Workshop on Cost Estimation and Cost Analysis of Nuclear Projects and Programmes
Idaho National Laboratory, USA
Nuclear in the Energy Mix Perspective of North Macedonia
INL, September 30 – October 03, 2019
•Existing Power System (PS)
•New production capacities candidates
•Long term scenarios for Power System
•Activities in energy planning Model for hourly operation of power plants
Environmental impacts from fossil fuels technologies
•Nuclear option for future development
Content
•Import is 30% of electricity needs (2000-3000 GWh/year)
• Base load from TPP on lignite (over 30 years old units in operation)
• Domestic lignite with limited reserves (next 20 years)
•Base load in critical status after 2030
•Needs for new base load production capacities
•Small grid with Max. power needs 1500-2000 MW
•Yearly energy needs 9000 GWh
•The largest single generation unit is 220MW (thermal unit)
Current situation in Electric Power System
•Challenges in new technology which is environmentally acceptable (REN in first period next 5-10 years)
•Nuclear power is an energy option after 2030
•SMR as reasonable and acceptable investments for small country as a new nuclear beginner
•ELEM - power plants and private producers
•MEPSO – national TSO
•EVN and other distributions
Existing power system and main companies Map of the grid
Бугарија
Грција
АлбанијаЛерин
Червена Могила
Солун
Вруток
Шпиље
Глобочица
Охрид2
Ресен
Битола4
Битола1
Битола3 СуводолБ.Гнеотино
Сопотница
Битола
Осломеј
Кичево
Битола 2
Прилеп1
Прилеп3Прилеп2
Самоков
КозјакСв.Петка
ТиквешФени
Неготино
Гевгелија
Струмица2
Струмица1 Сушица
Радовиш
БеровоБучим
ДубровоНеготино
Градска
Кавадарци
ЗгрополциЦентрална
Велес2
Велес
ТопилницаШтип2
Штип1
О.Поле КочаниДелчево
М.Каменица
К.Паланка
Пробиштип
Кратово
Куманово 1
Куманово 2Рафинерија
Бунарџик
Скопје 4
Скопје2
Скопје3
Ѓ.Петров
Гостивар
Југохром
Теарце ТЕ ТО
Вaландово
Косово
Урошевац
Скакавица
Петрич
Србија
Штип
Скопје 5
Струга
Тетово 1
Тетово 2
Полог
Скопје1
Бошков мост
Железара
Петровец
Богданци
Охрид1
Охрид
ТИРЗ Тетово
Ново КосовоВрање
ХЕЦ
ВЕЦ
ТЕЦ
ТЕТО
400 kV ДВ
110 kV ДВТС 400/110 kV
ТС 110/x kV
Состојба 2020
Елбасан
Куманово
ИЗ Неокази
рудникИловица
The structure of the Power system
TSO
MEPSO
Regulated consumeELEM with TPPs & HPPs
GENERATION SYSTEM
Independent Power ProducersCHP, CC,....
CONSUMERS
Large Ind. consumersIMPORT from Market
Connection Export to Market
Distribution Companies,
EVN
PVSmall HPP
Wind Farms
2014 2015 2016TPP 3507 3092 2699
Bitola 3317 2986 2672Oslomej 190 106 27
CHP Energetika 0 0 1.3HPP 958 1528 1490
Mavrovo 398 439 553Crn Drim 326 529 586
Tikves 116 313 145Treska 118 247 206
Wind Park 70 121 110ELEM Total 4535 4741 4299
CHP TETO+Kogel 192 179 554IMPORT 3072 2656 2191
REN (Substitice) 256 350 449Small HPP 242 308 389
PV 14 22 24Biomass 0 20 36
DEMAND 8055 7926 7493
Supply structure in GWh for last yearsRegulating consumers and customers (7500-8000 GWh)
Industrial consumers for 110 kV are not included (free on the market) (1000-1500 GWh)
Typical yearly and daily demand
0
200
400
600
800
1000
1200
1400
1600
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
P (MW)
30 December 201620 October 201606 August 201616 May 2016
Existing iInstalled capacitiesInstalled Power
P (MW)Yearly Available Generation
W (GWh)TPP coal 825 4800TPP oil 210 1000CHP gas 287 2000HPP (Large&Small) 675 1545Wind farm 37 120PV 17 22Biomass 6 18TOTAL 2057 9470
Emission factors and environmental impactsfrom fossil fuel thermal power plants
LIGNITE CO2 SO2 H2O N2 O2 TotalNm3/kg-Fuel 0.435 0.004 0.723 2.384 0.146 3.693kg / kg Fuel 0.855 0.012 0.581 2.981 0.209 4.637kg/Nm3 Gasses 0.231 0.003 0.157 0.807 0.057 1.256g/kJ 0.111 0.002 0.075 0.387 0.027 0.602g/kWh 1249.0 16.9 848.6 4354.7 305.3 6774.5
OIL CO2 SO2 H2O N2 O2 TotalNm3/kg-Fuel 1.587 0.014 0.336 8.634 0.530 11.101kg / kg Fuel 3.117 0.040 0.270 10.793 0.757 14.976kg/Nm3 Gasses 0.281 0.004 0.024 0.972 0.068 1.349g/kJ 0.078 0.001 0.007 0.269 0.019 0.373g/kWh 821.2 10.5 71.1 2843.1 199.3 3945.3
NATURAL GAS CO2 SO2 H2O N2 O2 TotalNm3/kg-Fuel 0.999 0.000 1.999 9.842 0.604 13.444kg / kg Fuel 1.962 0.000 1.606 12.303 0.863 16.734kg/Nm3 Gasses 0.146 0.000 0.119 0.915 0.064 1.245g/kJ 0.051 0.000 0.041 0.317 0.022 0.431g/kWh 331.1 0.0 271.0 2075.4 145.5 2823.0
0
200
400
600
800
1000
1200
1400
Lignite Oil Natural. Gas
CO2 (gr/kWh)
0
2
4
6
8
10
12
14
16
18
Lignite Oil Natural. Gas
SO2 (gr/kWh)
Generation prices of electricity Thermal PP (coal), 55 Euro/MWh CC thermal PP (gas), 65 Euro/MWh Hydro Power (Run off, Storage), 20 Euro/MWh
REN Small Hydro 45-120 Euro/MWh (Feed in tariff) Wind Power, 89 Euro/MWh (Feed in tariff) PV Solar, Market price + Add. Biomass 180 Euro/MWh (Feed in tariff)
Small HPP (80MW) 389 GWh Wind power (37MW) 110 GWh PV (18MW) 24 GWh Biomass (7MW) 36 GWh
REN in 2016
Operation Planning of Power Generation in the Power System
MODELS for Planning of Power System • Long – term planning (year, few years, decades)New investments in power plants, National Strategy planning,...• Short term planning (in a day, week, …, year)Operation of existing power plants…
k –Thermal power plant contracts (TPP & NPP) with Pter (t), m - Hydropower plants, each with power Phyd (t) n - Additional systems or interconnectionsREN – Renewable (Wind farms, PV and others)
)()()()()( tPtPtPtPtP loadN
sysR
RENM
hydK
ther =+++ ∑∑∑∑
Other Constraints: • Water balance for HPP, • Energy production balance for TPP• Contracts for import/export• Planned outages
min))(())((1 11 1
⇒∆⋅+∆⋅ ∑∑∑∑= == =
ttPKttPKN
n
T
tsysn
K
k
T
tterk
Power balance between generation and consumption in each time interval according to the relation
Model for hourly operation of power plants in PS Optimization function -Total Operation Costs -minimum
Modelling thermal units
Thermal Power Plants (TPP &NPP)Production costs depend on power output (CAP+Fuel+O&M)
32)( PCPBPAPK ⋅+⋅+⋅=
)()()( 2,,,,,, tkktkkktktkktktkk PCPBAPPqPPK ⋅+⋅+⋅=⋅=
Modelling Hydro Power units
Hydro Power Plants Specific spent water per energy depend on turbine discharge and storage level
⋅+⋅+⋅=
2
,
,
,
,
,
,
,
,neto
tm
tmmneto
tm
tmmmneto
tm
tmneto
tm
tm
H
PC
H
PBA
H
P
H
PQ
P(t)
...
maxP
minP
1t 3t2t 4t nt
varP
totP
)( 1tP
)( 2tP
)( 3tP
)( 4tP
)( ntP
t∆
t
ttP
t
tWP
n
i
n
i
t
tii
t
ti
tot ∆
⋅=
∆=
∑
∑=
=
1
1
)()(
minvar PPP tot −=
Electricity load representative
In order to reduce the dimension of the problem , the number of time interval (T) can be smaller with different duration (appropriate to the demand)
Wide options of Generation planning ( long & short terms) Operating regime of HPP’s & TPP’s Flexible opportunity for interval’s dividing: months, weeks. days, hours (few,...,2,1) Balance of total & variable load Water balance for HPP’s reservoirs Electricity exchange (import, export)
Model possibilities
Existing power system of Macedonia
Lignite TPP – 820 MW, 4500 GWhBitola, OslomejGas TPP – 280 MW, 2000 GWhTE TO, Kogel, Energetika ELEM Oil TPP – 210 MW, 1200 GWhNegotinoHYDRO – 580 MW, 1450 GWh
Basin Wannual [GWh] Wshare [%]1 Mavrovo HPPs 488 33.662 Crn Drim HPPs 513 35.383 Treska HPPs 190 13.104 Crna HPPs 184 12.695 Small HPPs 75 5.17
Total 1450 100.00
DEMAND near 9000 GWhDomestic production around 6500 GWhImport (Gap) of 2500 GWh
Future projection of new power plants
Basin Pinst. Wyear InvestmentMW GWh mil €
Boskov Most Radika 68.2 117 70Lukovo pole and HPP Crn Kamen Mavrovo 5 163 45Galiste Crna river 193.5 264 200Cebren Crna river 333 340 319Spilje 2 Crn Drim 72 33 35Gradec Vardar 54.6 252 157Veles Vardar 93.0 300 25110 HPPs in the Vardar valley Vardar 176.8 784 486TOTAL 1032 2343 1563
Lignite TPP – 300 MW, 2000 GWh1 units x 300 MWGas TPP – 500MW, 3000 GWh2 units Nuclear – up to 1000 MW, 8000 GWh
HYDRO – near 1000 MW, 2300 GWhRenewable (up to 400 GWh) Small HPP 60 MW Wind 150 MW PV 20 MW
Simulation of Scenario in hourly optimization Case with NPP
0
500
1000
1500
2000
2500
1 6 11 16 21 26 31 36 41 46 51 56 61 66 71 76 81 86 91 96 101
106
111
116
121
126
131
136
141
146
151
156
161
166
P(MW)
Hydro
Import PUMP
Gas
NUCLEAR
0
500
1000
1500
2000
2500
1 6 11 16 21 26 31 36 41 46 51 56 61 66 71 76 81 86 91 96 101
106
111
116
121
126
131
136
141
146
151
156
161
166
P(MW)
Hydro
Import PUMP
Gas
NUCLEAR
Winter Week
Summer Week
0
100
200
300
400
500
600
700
800
900
1000
1 7 13 19 25 31 37 43 49 55 61 67 73 79 85 91 97 103
109
115
121
127
133
139
145
151
157
163
P (MW) Treska
Mavrovo
CRNA
Crn Drim
Gradec
0
100
200
300
400
500
600
700
800
900
1000
1 7 13 19 25 31 37 43 49 55 61 67 73 79 85 91 97 103
109
115
121
127
133
139
145
151
157
163
P (MW) Treska
Mavrovo
CRNA
Crn Drim
Gradec
Conventional HPPConventional+ Reversible HPPCovering the peak demand
Comparison of covering the base load No Nuclear and large NPP option
Coal + Import6400 GWh
Nuclear NPP 6800 GWh
0
200
400
600
800
1000
1200
117
033
950
867
784
610
1511
8413
5315
2216
9118
6020
2921
9823
6725
3627
0528
7430
4332
1233
8135
5037
1938
8840
5742
2643
9545
6447
3349
0250
7152
4054
0955
7857
4759
1660
8562
5464
2365
9267
6169
3070
9972
6874
3776
0677
7579
4481
1382
8284
5186
20
P (MW)
0
200
400
600
800
1000
1200
117
735
352
970
588
110
5712
3314
0915
8517
6119
3721
1322
8924
6526
4128
1729
9331
6933
4535
2136
9738
7340
4942
2544
0145
7747
5349
2951
0552
8154
5756
3358
0959
8561
6163
3765
1366
8968
6570
4172
1773
9375
6977
4579
2180
9782
7384
4986
25
P(MW)
CASE OF OPERATION OF THE POWER SYSTEM WITH WIND FARMS PLANNING IN A YEAR FOR 8760 HOURS
Simulation of power generation units operation:• TPPs of: Pmin=870MW < P(t) < Pmax=1270MW• HPPs for average hydrology of: Pinst=628MW• Wind power plants of 150 MW with an annual production of 300 GWh. • Annual demand of 10,000 GWh.
ТPPPmin(MW)
Pinst (MW)
Annual generationW (GWh)
Lignite (Bitola1,2,3, & Oslomej) 550 800 5000Gas (TE-TO, Kogel, Energetika) 160 260 2000Oil (Negotino) 160 210 1000Total 870 1270 8000
HPPPinst(MW)
Annual generation for average inflow W (GWh)
ELEM –storage HPP 550 1500EVN 38 110Small HPP 40 120Total 628 1730
Power system operation in the selected winter week
TPP operation for both cases, with and without wind power
Covering the demand and wind power for selected winter week
HPP operation for both cases, with and without wind power
Power system operation in the selected summer week
TPP operation for both cases, with and without wind power
Covering the demand and wind power for selected summer week
HPP operation for both cases, with and without wind power
Suppressed (pished) power in the system for each hour of the year(case with wind farm of 600MW total installed power)
The power pushed into the system as theresult of wind power injection can bereduced if the technical minimum power ofthe thermal units can be decreased in orderto accept the power from wind farms.Otherwise, can be reduced with additionalhydro power units (storage or reversible), orflexible gas power turbines.
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
2033
2034
2035
2036
2037
2038
2039
2040
Wyear (GWh)
ImportRenewableHydroNew GasGasNew coalLignite
Covering the electricity needs up to 2040•Reduced fossil fuel scenario•Annual growth rate of 2,5%•Gap of electricity needs - IMPORT or NUCLEAR•After 2035 - over 6000 GWh
Security rules for grid N-1 security rule
– is fulfilled if all technical criteria are respected when contingency event occurs in the network
Extreme contingencies– busbar outage– complete power plant outage
N-2 security rule– double circuits outage – simultaneous outage
of two different lines
Cascade outages Loading Voltage profile Max outage of load/production Voltage stability Dynamic stability
Technical criteria
MK grid long-term visions & NPP integration
27
Bitola
Dubrovo
Skopje
Kosovo B
Nis
Sofija
Chervena Mogila
Blagoevgrad
Thessaloniki
Amyndeo
Florina
Ag. Dimitrios
Filippi
Kardia
Zemlak
Elbasan
Fierze
Prizren
Vau Dejes
Podgorica
Ribarevina
PlevljaTrebinje
Arachtos
N
Stip
Tirana
New interconnection projects
28
Some facts Big gap in covering the power needs in Macedonia, for the last
10 years which is 30% of the total demand. Fossil option (coal and gas) for long term supply is uncertainty
and insecure (depend on transportation limitations and global energy policy with gas pipe lines).
Environmental consequences from fossil fuel option as an additional challenge.
Nuclear option as a real long term power supply security. Small and medium size reactors (SMR) are preferable, or
sharing large scale NPP as regional project Stakeholders for NEP are ELEM, MEPSO, DRS-Directorate for
Radiation Safety, Universities with academia
•Low investments for small country
•Modularity of the technology and relatively easier for implementation for new beginner country in nuclear power (HR needs, nuclear regulatory authorities,…)
•Transport problem for large and heavy equipments (no sea port or any water transport, only roads and railway)
•Implementation the environmental friendly technologies
SMR as Energy option after 2030
Sharing Large NPP as regional project •Possibility to start of new beginner in nuclear technology
•HR needs and nuclear regulation
•Letter of interest for NPP Belene send to Bulgarian authorities
•Long way to negotiations for until decision