NU Fire Lane Lease Agreement
2
NU Fire Lane Overview
• Overview of Proposed Lease Agreement Details
• Feedback from Audubon
• Tree Preservation Ordinance/ Habitat Replacement• Landscaping Plan
NU Fire Lane Path
5
Proposed Lease Agreement
• NU granted Temporary Construction Easement (0.67 acre)
• NU responsible for Construction & Ongoing Maintenance of Fire Lane Path
• Fire Lane Path Lease (0.47 acre) – Length of Fire Lane on City property is 315 ft; City
Bike Path connection to Fire Lane is 50ft long– City & NU enter into 25 year lease agreement,
optional 25 year renewal– Inspection at year 20 for maintenance & repair
Temporary Construction Easement 0.67 acre
Fire Lane Path 0.47 acre
8
Proposed Lease Agreement Payment
• Standard easement fee ($0.50/square foot) used to calculate lease rate:
• Temporary Construction Easement @ 1yr = $14,510.50• Fire Lane Path @ 25yrs = $255,012.50*
• Tree Preservation Fee (275 trees) =$173,800• NU Construction & Landscaping Costs =
$280,000• NU Ongoing Maintenance & Capital = $5,000
per year for 25 years or $125,000
9
NU Costs Breakdown
Description Estimated Costs
Temp. Const. Easement (0.67 Acre @ 1 year)
$ 14,510.50
Fire Lane Construction Costs $230,000.00
Landscaping Costs $ 50,000.00
Estimated Maintenance & Capital Outlay - $5,000/year @ 25 years
$125,000.00
Tree Preservation Fee (275 trees removed)
$173,800.00
Estimated Total Cost to NU $593,310.50
Estimated Cash Payment to City $188,310.50
10
Audubon Position
• Concerned with loss of dune grass & woods along lakefront
• Appreciate NU use of bird friendly glass• Interested in working with City & NU regarding
replacement of new bird habitat in new location
11
Tree Replacement Habitat Option
Landscape Plan