(n)QPS
description
Transcript of (n)QPS
(n)QPS
LHC status
LHC: past, present and futureMike Lamontfor the LHC team
121-3-2011
Clear priority to lay the foundations for 2011 and the delivery of 1 fb-1. Peak luminosity target 1x1032 cm-2s-1
Gain solid operational experience of injecting, ramping, squeezing and establishing stable beams
Steady running at or around 1 MJ for an extended period
Perform a safe, phased increase in intensity with validation and a running period at each step
2010 – main aims
LHC status 221-3-2011
Luminosity: 3 running periods
3
Bunch trains
Nominal bunch commissioning
Initial luminosity
run
Nominal bunch
operation(up to 48)
Performance ramp-up
(368 bunches)
Perform
ance
ramp-u
p mad
e pos
sible
by a
safe,
stag
ed co
mmission
ing.
Meticu
lous p
repara
tion f
or un
safe
beam
s!
21-3-2011 LHC status
2010 parameters
LHC status
2010 Nominal
Energy [TeV] 3.5 7
beta* [m] 3.5, 3.5, 3.5, 3.5 m 0.55, 10, 0.55, 10
Emittance [microns] 2.0 – 3.5 start of fill 3.75
Transverse beam size at IP [microns] around 60 16.7
Bunch current 1.2e11 1.15e11
Number of bunches 368348 collisions/IP 2808
Stored energy [MJ] 28 360
Peak luminosity[cm-2s-1] 2e32 1e34
421-3-2011
Overall LHC efficiency in 2010
5
W. Venturini
65%availability!
Great a
chiev
emen
t for th
e firs
t
year
of op
eratio
n!
21-3-2011 LHC status
Physics operations
~30%Stable beams!
W. Venturini
21-3-2011 LHC status 6
2010 - records
Peak stable luminosity delivered 2.07 x 1032 cm-2s-1
Maximum luminosity delivered in one fill 6.3 pb-1
Maximum luminosity delivered in one day 5.98 pb-1
Maximum luminosity delivered in 7 days 24.6 pb-1
Maximum colliding bunches 348Maximum average events per bunch crossing
3.78
Longest time in Stable Beams for one fill 30.3 hoursLongest time in Stable Beams for one day 22.8 hours (94.9%)Longest time in Stable Beams for 7 days 69.9 hours (41.6%)Fastest turnaround to Stable Beams 3.66 hours (protons)
Courtesy AtlasLHC status 721-3-2011
Status LHC Stored Energy
80 kg TNT
Stored energy reached at 3.5 TeV: 28.0 MJ
8LHC status Ralph Assmann21-3-2011
Ions
LHC status
Protonsagain
50 & 75 ns
921-3-2011
Excellent single beam before collisions ~200 - 300 hours
Luminosity lifetime ~15 - 20 hours Reasonably well given by emittance growth and intensity decay Minimal drifts in overlap – beams very stable
Intensity lifetime ~90 hours Luminosity burn, losses on collimators
Emittance growth (hor. ~ 30 hours, vert. ~ 20 to 40 hours) Intra Beam Scattering and something else – at least sometimes “the hump”
Lifetimes
1021-3-2011 LHC status
Aperture
LHC status 1121-3-2011
Optics & magnetic machine Optics stunningly stable
Machine magnetically and optically well understood Excellent agreement with model and machine
Magnetically reproducible Important because set-up remains valid from fill to fill
LHC status 1221-3-2011
Measured Cleaning at 3.5 TeV
IR8IR1
IR2
IR5
Mom
entu
m
Cle
anin
g
Dum
p P
rote
ctio
n C
ol.
(beam1, vertical beam loss, intermediate settings)
LHC status
Making sure the hierarchy is respected
1321-3-2011
Excellent single beam lifetime Ramp & squeeze essentially without loss
No quenches with beam above 450 GeV Excellent performance of Machine Protection
Optics close to model (and correctable) Excellent reproducibility Aperture as expected Better than nominal from injectors
Emittances, bunch intensity Beam-beam: can collide nominal bunch currents
With smaller that nominal emittances
LHC 2010 - summary
14
And surprisingly good availability… 21-3-2011 LHC status
PROBLEMS – TWO OF THEM
LHC status 1521-3-2011
Many sudden local losses have been recorded. No quench, but preventive dumps Rise time around of the order 1 ms. Potential explanation: dust particles falling into beam
creating scatter losses and showers propagating downstream
Distributed around the ring – arcs, inner triplets, IRs
UFOs – unidentified falling objects
LHC status 1621-3-2011
● Revision of thresholds on superconducting magnets could make the UFO effects acceptable
● More detailed analysis needed to understand discrepancies with current simulations + additional quench tests to benchmark
UFOs – a possible solution?
● More events at higher intensities● Only 1? event observed at 450GeV● Signal shortens, i.e. the losses are faster with intensity● Signal amplitude does not increase with intensity
B.Dehning, E. Holzer, A.Nordt, M.Sapinski 21-3-2011 LHC status 17
Electron cloud
LHC status
Schematic of electron cloud build up in LHC arc beam pipe due to photoemission and secondary emission [F. Ruggiero] Reflection
Secondary emission yield [SEY]
18
Very much dependent on bunch spacing: - 150 ns. – local signs in common beam pipe- 75 ns. – some first signs- 50 ns. – vacuum valves in
21-3-2011
Vacuum pressure rise (background in experiments) Single-bunch instability Multi-bunch instability Incoherent emittance growth Heat load in cold arcs (quenches in the limit) Perturbation of beam diagnostics
Electron cloud effects
LHC status
Electron cloud effects occur both in the warm and cold regions.
19
Well understood, very well studied (other machines, simulations…)
21-3-2011
Vacuum activity started off in regions with common beam pipe at 450 GeV as we pushed up the number of bunches with 150 ns spacing Test solenoids cured problem – electron cloud
Tried 50 ns bunch spacing Things really kicked off High vacuum activity in warm regions (single beam pipe) Significant heat load in cold regions Instabilities and beam size growth observed Surface conditioning (‘scrubbing’) observed
Gas desorption rates and SEY drop Time constant < 1 day
Situation a lot cleaner with 75 ns incoherent effects seen – emittance blow-up 800+ bunches injected into both beams
Experience in 2010
LHC status 2021-3-2011
2010 observations are certainly due to ~ 2 < SEY < 2.5, whereas 1.7 was usually the max value studied in the past
Expect to be able to reach 200-300 b with 75 ns without scrubbing
Scrubbing with large emittance (>3.5 mm), high intensity (>1.2e11), 4x36b of 50 ns beam
Time 2-3 days needed to setup 50 ns at injection 7 days of scrubbing 1 day for validation and scrubbing result evaluation
Lots of wire wrapped around warm bits during the technical stop (solenoids)
Scrubbing strategy for 2011
21LHC status21-3-2011
Solenoids between DFBX and D1 in IR1R
LHC status 2221-3-2011
2011
LHC status 23
Energy – stick at 3.5 TeV – we still worry about the splices
21-3-2011
Motivation is clear!
1 fb-1 delivered to each of IP1, IP5 and IP8 at 3.5 TeV Can probably do better for IP1 and IP5
It will be a challenge to deliver 1 fb-1 to IP8 Maximum luminosity : from 2e32 to 3e32 cm-2 s-1
Luminosity leveling via separation required to get close Alice
pp run: 5e29 < L < 5e30 cm-2 s-1, µ < 0.05
2011: main goals
2421-3-2011 LHC status
fast, secure and far-reaching
Decided on beta* = 1.5 m in Atlas, CMS; 3 m in LHCb; 10 m in Alice
Beam commissioning: 3 weeks Exit - stable beams with low number of bunches
Ramp-up to ~200 bunches (75 ns): 2 weeks Multi-bunch injection commissioning continued Stable beams
Technical Stop: 4+1 days Scrubbing run: 10 days including 50 ns injection comm. [Intermediate energy run – 5 days] Resume 75 ns operation and increase no. bunches: 3
weeks 300 – 400 – 600 – 800 – 930 - MPS and OP qualification
Physics operation 75 ns: ~930 bunches (50 ns. remains an option if things look good)
Baseline scenario
2521-3-2011 LHC status
2011 LHC schedule Q1/Q2
26LHC status21-3-2011
2011 Q3/Q4
LHC status 2721-3-2011
Estimated Peak and Integrated Luminosity
LHC status 2821-3-2011
Energy 3.5 TeVBeta* 1.5 mBunch spacing 75 nsBunch intensity 1.2 x 1011
Stored beam energy 75 MJDays at peak luminosity 135Hübner factor 0.2
Emittance[mm.mrad]
Beam-beam parameter
Peak Luminosity
[cm-2 s-1]
Integrated Luminosity
[fb-1]
2.5 0.006 1.3 x 1033 ~2.72.0 0.007 1.6 x 1033 ~3.3
2011 – progress so far
LHC status 29
19th February First beam, circulating beams established.
3rd March First collisions at 3.5 TeV, beta*=1.5 m. with pilot beams
5th March Nominal bunches at 3.5 TeV, start collimator set-up, injection and beam dump set-up & validation
13th March First stable beams, 3 bunches per beam, initial luminosity 1.6e30 cm-2s-1
18th March 32 bunches per beam, initial luminosity ~3e31 cm-2s-1
19th March 64 bunches per beam, initial luminosity ~6e31 cm-2s-1
20th March 75ns_136b+4small_138_102_105_24bpi11inj 1.45e32 cm-2s-1
Impressive re-commissioning, improvements across the board.
Operation cycle now well optimized: faster ramp & squeeze, much fewer manual actions required by shift crews
21-3-2011
LHC status 3021-3-2011
Machine still beautiful
LHC status 3121-3-2011
Injection, ramp and squeeze fully operational LHC magnetic model & optics excellent Beam instrumentation in good shape. Beam cleaning and collimation works reliably
with predicted efficiency. Machine protection excellent performance Machine aperture looks good Performance with beam (losses, lifetimes,
luminosity, emittance growth etc.) is very encouraging
Conclusions 1/2
LHC status 32
We have a beautiful machine on our hands!21-3-2011
Machine availability is excellent – the hard work of numerous teams
There are problems UFOs somewhat worrying Electron cloud well understood – measures prepared
2011 – another long year ahead… 75 ns. bunch spacing – up to 930 bunches Nominal intensities, beta* 1.5 m in Atlas and CMS Should be good for 5 to 10 x 1032 cm-2s-1 and 1 to 3 fb-1
Progress so far is good…
Will run in 2012 Attempt to measure splice resistance in 2011/2012 might open
the way to 4 TeV or higher
Conclusions 2/2
LHC status 3321-3-2011
LHC status 3421-3-2011