Northwest Florida Transportation Corridor Authority.

13
Northwest Florida Transportation Corridor Authority

Transcript of Northwest Florida Transportation Corridor Authority.

Page 1: Northwest Florida Transportation Corridor Authority.

Northwest Florida Transportation Corridor

Authority

Northwest Florida Transportation Corridor

Authority

Page 2: Northwest Florida Transportation Corridor Authority.

NFTCA WebsiteNFTCA Website

• www.nwftca.com• www.nwftca.com

Page 3: Northwest Florida Transportation Corridor Authority.

NFTCA OverviewNFTCA Overview

• Created by the 2005 Florida LegislatureCreated by the 2005 Florida Legislature• Florida Statute Section 343.80Florida Statute Section 343.80• One of several transportation authorities in One of several transportation authorities in

FloridaFlorida• Includes 8 Counties (Escambia, Santa Rosa, Includes 8 Counties (Escambia, Santa Rosa,

Okaloosa, Walton, Bay, Gulf, Franklin, & Wakulla)Okaloosa, Walton, Bay, Gulf, Franklin, & Wakulla)• Eight Voting Board Members (FDOT non-voting)Eight Voting Board Members (FDOT non-voting)

• Created by the 2005 Florida LegislatureCreated by the 2005 Florida Legislature• Florida Statute Section 343.80Florida Statute Section 343.80• One of several transportation authorities in One of several transportation authorities in

FloridaFlorida• Includes 8 Counties (Escambia, Santa Rosa, Includes 8 Counties (Escambia, Santa Rosa,

Okaloosa, Walton, Bay, Gulf, Franklin, & Wakulla)Okaloosa, Walton, Bay, Gulf, Franklin, & Wakulla)• Eight Voting Board Members (FDOT non-voting)Eight Voting Board Members (FDOT non-voting)

Page 4: Northwest Florida Transportation Corridor Authority.

PurposePurpose

The primary purpose of the authority is to improve mobility on the U.S. 98 corridor in Northwest Florida to enhance traveler safety, identify and develop hurricane evacuation routes, promote economic development along the corridor, and implement transportation projects to alleviate current or anticipated traffic congestion.

The primary purpose of the authority is to improve mobility on the U.S. 98 corridor in Northwest Florida to enhance traveler safety, identify and develop hurricane evacuation routes, promote economic development along the corridor, and implement transportation projects to alleviate current or anticipated traffic congestion.

Page 5: Northwest Florida Transportation Corridor Authority.

Authorized ActionsAuthorized Actions

• Construct any feeder roads, reliever roads, connector roads, bypasses, or appurtenant facilities that are intended to improve mobility along the U.S. 98 corridor.

• Plan, design, finance, and construct transportation improvement projects

• Acquire and hold title to property that will accommodate the development of transportation facilities

• Seek financial assistance from local, State and the Federal government as well as private entities

• Implement toll facilities to aid in funding projects

• Construct any feeder roads, reliever roads, connector roads, bypasses, or appurtenant facilities that are intended to improve mobility along the U.S. 98 corridor.

• Plan, design, finance, and construct transportation improvement projects

• Acquire and hold title to property that will accommodate the development of transportation facilities

• Seek financial assistance from local, State and the Federal government as well as private entities

• Implement toll facilities to aid in funding projects

Page 6: Northwest Florida Transportation Corridor Authority.

Develop Master PlanDevelop Master Plan

“The authority shall develop and adopt a corridor master plan no later than July 1, 2007. The goals and objectives of the master plan are to identify areas of the corridor where mobility, traffic safety, and efficient hurricane evacuation need to be improved; evaluate the economic development potential of the corridor and consider strategies to develop that potential; develop methods of building partnerships with local governments, other state and federal entities, the private-sector business community, and the public in support of corridor improvements; and to identify projects that will accomplish these goals and objectives.”

“The authority shall develop and adopt a corridor master plan no later than July 1, 2007. The goals and objectives of the master plan are to identify areas of the corridor where mobility, traffic safety, and efficient hurricane evacuation need to be improved; evaluate the economic development potential of the corridor and consider strategies to develop that potential; develop methods of building partnerships with local governments, other state and federal entities, the private-sector business community, and the public in support of corridor improvements; and to identify projects that will accomplish these goals and objectives.”

Page 7: Northwest Florida Transportation Corridor Authority.

Master Plan Phase IMaster Plan Phase I

Page 8: Northwest Florida Transportation Corridor Authority.

Master Plan Phase IMaster Plan Phase I

• Completed by FDOT in April 2006• Documents existing conditions and identifies

transportation projects recently completed or currently under study, design, right-of-way acquisition or construction

• Serves as the baseline condition for the NFTCA Master Plan

• Completed by FDOT in April 2006• Documents existing conditions and identifies

transportation projects recently completed or currently under study, design, right-of-way acquisition or construction

• Serves as the baseline condition for the NFTCA Master Plan

Page 9: Northwest Florida Transportation Corridor Authority.

Master Plan Phase IIMaster Plan Phase II

– Develop Overall Vision (Goals & Objectives)– Assess Existing Conditions (No-build/Do Nothing)– Identify Improvement Opportunities– Determine What Needs To Be Done– Identify Projects & Constraints– Develop Preliminary Costs– Identify Finance Options/Availability– Prioritize Projects

– Develop Overall Vision (Goals & Objectives)– Assess Existing Conditions (No-build/Do Nothing)– Identify Improvement Opportunities– Determine What Needs To Be Done– Identify Projects & Constraints– Develop Preliminary Costs– Identify Finance Options/Availability– Prioritize Projects

Page 10: Northwest Florida Transportation Corridor Authority.

Goals & ObjectivesGoals & Objectives

• GOAL A: Improve the mobility of people and goods throughout the US 98 corridor area

• GOAL B: Enhance traffic safety along the US 98 corridor for all modes of travel

• GOAL C: Reduce hurricane evacuation clearance times on US 98 and designated routes connecting with US 98

• GOAL D: Identify transportation strategies that enhance the region’s economic development potential

• GOAL A: Improve the mobility of people and goods throughout the US 98 corridor area

• GOAL B: Enhance traffic safety along the US 98 corridor for all modes of travel

• GOAL C: Reduce hurricane evacuation clearance times on US 98 and designated routes connecting with US 98

• GOAL D: Identify transportation strategies that enhance the region’s economic development potential

Page 11: Northwest Florida Transportation Corridor Authority.

Goals & ObjectivesGoals & Objectives

• GOAL E: Build partnerships with key stakeholders throughout the region in formulating transportation alternatives for the US 98 corridor

• GOAL F: Identify projects along with finance strategies for implementation

• GOAL E: Build partnerships with key stakeholders throughout the region in formulating transportation alternatives for the US 98 corridor

• GOAL F: Identify projects along with finance strategies for implementation

Page 12: Northwest Florida Transportation Corridor Authority.

Where Are We?Where Are We?

• December 2006 – Complete Draft Alternative December 2006 – Complete Draft Alternative AnalysisAnalysis

• January 2007 – Develop Draft Master PlanJanuary 2007 – Develop Draft Master Plan• February 2007 – Conduct Public MeetingsFebruary 2007 – Conduct Public Meetings• March 2007 – Adopt Master PlanMarch 2007 – Adopt Master Plan

• December 2006 – Complete Draft Alternative December 2006 – Complete Draft Alternative AnalysisAnalysis

• January 2007 – Develop Draft Master PlanJanuary 2007 – Develop Draft Master Plan• February 2007 – Conduct Public MeetingsFebruary 2007 – Conduct Public Meetings• March 2007 – Adopt Master PlanMarch 2007 – Adopt Master Plan

Page 13: Northwest Florida Transportation Corridor Authority.

Thank YouThank You