NORTHAM PLATINUM LIMITED 15 MVA ELKEN SIX …...The Southern African Institute of Mining and...
Transcript of NORTHAM PLATINUM LIMITED 15 MVA ELKEN SIX …...The Southern African Institute of Mining and...
The Southern African Institute of Mining and Metallurgy
Refractories 2010 Conference
T Dickinson
________________________________________________________________________
Page 23
NORTHAM PLATINUM LIMITED 15 MVA ELKEN SIX-IN-LINE
SMELTING FURNACE COMPLETE REBUILD 2008
T Dickinson
Dickinson Group
Introduction:
Northam Platinum is situated in Limpopo Province ± 30 km south of Thabazimbi. The
Dickinson Group was successful in securing the project which we started in September
2008 and completed in December 2008.The shutdown was planned for a total of 70 days
from the last matte tap to the first slag tap. We have successfully completed the project in
the planned shutdown duration.
Scope of Work:
The scope consisted of the following disciplines:
1. Engineering / Third Party Inspection:
1.1. Refractory drawings.
1.2. Structural and ancillary steelwork drawings.
1.3. Furnace shutdown procedure.
1.4. Furnace start-up & loading of pre-charge material procedure.
2. Quality Assurance and Quality Control Support.
3. Project Management.
4. Surveying Works.
5. Medical and Training.
6. Demolition Works.
7. Civil Works.
8. Structural Steel Works.
9. Steel Plate Works.
10. Steel / Flexible Piping Works.
11. Refractory Installation.
12. Electrical.
13. Instrumentation.
14. Loading of pre-charge materials.
15. Supply and Installation of Scaffolding.
16. Structural Painting.
The Southern African Institute of Mining and Metallurgy
Refractories 2010 Conference
T Dickinson
________________________________________________________________________
Page 24
1.1 Refractory Drawings
RHI Refractories was responsible for the design and supply of all the refractory
drawings:
• Refractory course drawings.
• Refractory general arrangement drawings.
• Refractory cross section drawings.
• Refractory longitudinal drawings.
• Refractory BOM including the expansion materials.
1.2 Structural and ancillary steelwork drawings:
• Our Company has employed the services of Pöyry to conduct a laser point
scan upon completion of the furnace.
• The laser point scan was then converted into a 3-D model, which can be used
to generate 2-D drawings from any part of the furnace.
• We have also re-designed the matte tapping platform to ease the lancing
operation during normal operation of the furnace
1.3 Furnace shutdown procedure:
• Northam Platinum and The Dickinson Group were responsible to compile a
safe and practical furnace shutdown procedure.
• We have conducted a hazard identification workshop in order to identify all
the possible risks associated with the furnace shutdown.
• Northam Platinum derived a method to minimize the remaining product inside
the furnace after the final matte tap.
1.4 Furnace start-up and loading of pre-charge material:
• Northam Platinum compiled a heat-up / start-up procedure which included the
method to load the pre-charge material.
• Northam Platinum also provided a crew that was responsible to supervise the
furnace start-up on a 24 hours basis.
2. Quality Assurance and Quality Control Support:
• We have appointed a QA/QC officer at the manufacturing workshop to ensure the
correct quality and rectification of defects prior to the delivery of the steel
structure onto site.
The Southern African Institute of Mining and Metallurgy
Refractories 2010 Conference
T Dickinson
________________________________________________________________________
Page 25
• RHI was responsible to oversee the refractory installation and to ensure that the
installation was according to the correct quality and standard.
• Northam Platinum was responsible to oversee the furnace heat-up electrical start-
up.
3. Project Management:
The Dickinson Group was responsible for the management of the complete project
which included the following:
• The manufacturing and delivery of all the steel related items.
• Manufacturing of miscellaneous refractory materials.
• Civil work repairs.
• Removal and installation of instrumentation in and around the furnace.
• Removal and installation of the earth ring and control system of the furnace.
4. Surveying Works:
We have appointed Young, Stuart & Associates Inc. to conduct the following surveys for
us during the installation project:
• Inside steel dimensions of the completed furnace box steelwork as well as the
buckstay positions.
• Matte & slag tap-hole elevations and positions was surveyed and punched onto
the existing steelwork.
• The hearth profile as per Northam Platinum requirements.
• Upper hearth skewback brick level.
• Inside of the furnace refractory dimensions.
5. Medical and Training:
All our Employees were trained on all skill levels which included the following courses:
• KBC and Site Induction.
• Valid occupational medical certificates.
• Mine Health and Safety Act.
• Hazard identification and Risk Assessment.
• Lock out procedure.
• Safety Induction.
• Occupational Hygiene.
• PPE (Personal Protective Equipment)
• Valid driver’s license and/or Forklift license.
The Southern African Institute of Mining and Metallurgy
Refractories 2010 Conference
T Dickinson
________________________________________________________________________
Page 26
• Hoist Operation course.
• First Aid course.
• Accredited Certification in all Refractory Installation disciplines.
6. Refractory Demolition:
During the initial 24 hour cooling down period of the furnace, we used the
opportunity to demolish the slag & matte tapping platforms, as well as the slag return
launder support structure. We utilized lancing equipment, telescopic forklifts fitted
with grabs, mobile cranes and the overhead crane.
We also demolished the two civil support plinths for both tapping platforms. This
was necessary to enable us to construct temporary ramps which were used to gain
access into the furnace during the demolishing period. After the initial 24 hours of
natural cooling, we forced cooled the furnace by spraying water into the furnace.
When the top layer of the material inside the furnace was solid we flooded the
furnace utilizing fire hoses. The flooding continued for 36 hours. Once the furnace
was cooled down sufficiently the furnace roof IPE beams were cut off using wire
packed lancing equipment. This caused the roof to drop down into the furnace.
Lancing Operator busy cutting out the old floor plates and Grillage beams
The Southern African Institute of Mining and Metallurgy
Refractories 2010 Conference
T Dickinson
________________________________________________________________________
Page 27
The end wall refractories were removed next, utilizing large excavators. The end
wall buckstays were removed afterwards with telescopic forklifts fitted with grabs
and the overhead crane.
Large Excavator removing rubble from the inside of the furnace
After the end walls were completely demolished, we used waste rubble and rock
material to construct the two ramps at the slag and matte ends. The rest of the furnace
was demolished utilizing four large excavators, two fitted with demolition hammers
and two with buckets.
All the buckstays were lanced into two halves which eased their removal. When all
the refractory material was demolished and carted away, the rest of the steel structure
was lanced off and removed with large excavators.
Care was taken not to damage the civil plinths underneath the furnace floor.
All the rubble and scrap steel was sorted and transported to an area away from the
furnace.
The Southern African Institute of Mining and Metallurgy
Refractories 2010 Conference
T Dickinson
________________________________________________________________________
Page 28
Front-end Loader clearing the rubble inside the furnace
7. Civil Works:
We have constructed new plinths under the matte and slag tapping platforms.
The plinths under the matte tapping platform was re-designed in order to suit the new
design of the matte tapping platform. All damaged plinths under and/or next to the
furnace were repaired with a high early strength concrete (Sika Crete). The concrete
slope under the furnace was repaired to its original condition.
Damaged plinth boxed and ready to be casted
The Southern African Institute of Mining and Metallurgy
Refractories 2010 Conference
T Dickinson
________________________________________________________________________
Page 29
8. Structural Steel Works:
Both the matte and slag tapping platforms were replaced with newly fabricated steel
work. The slag return launder platform and support structure were supplied and
erected by the Dickinson Group.
Installation of Grillage Beams
We supplied and installed the buckstay grillage beams, the side and end wall
buckstays, the whaler beams as well as the furnace inspection door frames complete
with door and handle.
Installation of side wall buckstays
The Southern African Institute of Mining and Metallurgy
Refractories 2010 Conference
T Dickinson
________________________________________________________________________
Page 30
Installation of matte end buckstays and shell plates
We completed the mechanical installation of the roof which consisted of the furnace
roof main support structural beams, roof yoke end connections, all the primary
support structural beams and support castings.
The Southern African Institute of Mining and Metallurgy
Refractories 2010 Conference
T Dickinson
________________________________________________________________________
Page 31
Roof main support beams between the electrodes
We removed the hearth cooling ducting and we were able to salvage 50% of the total
ducting. The additional 50% required was fabricated and installed with the salvaged
ducting.
9. Steel Plate Work:
The scope of work for the aforementioned works consisted of the supply and
installation of miscellaneous sizes of steel packer plates for the leveling of the
grillage beams, mild steel plate to cover both tapping platforms (as per the design),
furnace bottom, side and end walls shell plates as per the existing design.
The Southern African Institute of Mining and Metallurgy
Refractories 2010 Conference
T Dickinson
________________________________________________________________________
Page 32
Installation of steel side walls
10. Steel / Flexible Piping works:
• We have removed all large bore piping at the slag end to provide access for the
large excavators during the demolition phase. All the piping was re-installed after
the refractory installation period. All the piping was salvaged and re-used.
• New small bore piping was supplied and installed at the matte and slag tap holes.
• We have covered these pipes with heat resistant glass fiber coating to give
additional protection and to extend their useful life.
11. Refractory Installation:
The refractory installation consisted of the installation of the bottom-in fill, infill
screed, lower hearth, upper hearth, both side and end walls and the roof refractory
material.
The Southern African Institute of Mining and Metallurgy
Refractories 2010 Conference
T Dickinson
________________________________________________________________________
Page 33
Refractory installation of the bottom infill brick
The Southern African Institute of Mining and Metallurgy
Refractories 2010 Conference
T Dickinson
________________________________________________________________________
Page 34
Refractory installation of lower hearth bricks
Completed refractory installation
The Southern African Institute of Mining and Metallurgy
Refractories 2010 Conference
T Dickinson
________________________________________________________________________
Page 35
Hanging roof structure
We also supplied and installed stainless steel anchors and guniting material required
for the fire protection of the structural steel work on the matte and slag end as well as
the furnace buckstays, whaler beams etc. We installed ceramic sleeves around the tie
rods to protect the tie rods from heat.
12. Electrical:
The Dickinson Group was responsible for the removal of the existing ring earth
around the furnace and we replaced the existing system with a similar system widely
used in the typical installation of six-in-line furnaces.
13. Instrumentation:
• Drilling of the thermocouple holes was done as per the original design.
• We supplied and installed new cable racking, cables and thermocouples as per the
original design.
The Southern African Institute of Mining and Metallurgy
Refractories 2010 Conference
T Dickinson
________________________________________________________________________
Page 36
14. Loading of pre-charge materials:
• Our Company was responsible to load all pre-charge material as per Northam
Platinum’s specification and procedure.
• The dry slag was loaded into trucks that are equipped with pumps that can pump
the dry slag from the truck into the furnace.
• We loaded scrap railway lines and scrap steel under the electrodes.
• We constructed a steel basket under each electrode and filled each basket with
coke.
• All the pre-charge material was supplied by Northam Platinum Mine.
15. Supply and Installation of Scaffolding:
We employed Kaefer as our scaffolding sub contractor. They supplied and erected all the
scaffolding that was required during the complete shutdown period. Their personnel and
material were based on site which made the logistics and management of them practical.
16. Structural Painting:
• All structural steel that we supplied was painted as per the required specification.
• The hold down boxes were removed by us, sent out for sandblasting and painted
as per specification.
• All the surrounding steel work, including handrails, kick plates and building
columns were cleaned by wire brushes and painted as per specification.
• The hearth cooling ducting that was salvaged was cleaned and painted as per
specification.
• All hard steel piping was painted as per specification.
The Dickinson Group successfully completed this turnkey project in the planned
shutdown period. The key to our success in every project that we undertake is the
commitment of top management and our workforce, proper planning, knowledge and
experience in our work field, financially strong to back a project of this size and leaders
in turnkey refractory services.