North Terminal Development Projects - IEMA€¦ · Of these 34 mppa, 18.7 mppa used the South...
Transcript of North Terminal Development Projects - IEMA€¦ · Of these 34 mppa, 18.7 mppa used the South...
North Terminal Development Projects
EnvironmEntal StatEmEnt Non-Technical Summary
July 2009 BAA GatwickLondon
|
Gatwick Airport North Terminal Development Projects
Non-Technical Summary
Date: July 2009
2
Contents 1 Introduction 1
2 The Existing Site 3
3 Background and Need 5
4 Consideration of Alternatives 7
5 Project Description 9
6 Construction 15
7 Approach to the Environmental Impact Assessment 17
8 Air Noise 21
9 Air Quality 23
10 Ecology 25
11 Economics 27
12 Employment 29
13 Ground Noise 31
14 Landscape and Visual 33
15 Transport 35
16 Waste 37
17 Water 39
18 Where to find a copy of the Environmental Statement 43
Tables Table 1: Summary of Headline Forecasts 12 Table 2: Key Assessment Terms 19 Table 3: Basis of Assessment 19
Figures Figure 1: Overview of the North Terminal Development Projects 1 Figure 2: Location of Proposed Development Sites 3 Figure 3: Illustration of the North Terminal Extension 9 Figure 4: Illustration of Multi-storey Car Park 6 9 Figure 5: Construction Programme 15
1
1 Introduction 1.1.1 Gatwick Airport is a major international airport primarily serving London, the South East and Southern
England. In 2008 over 34 million passengers per annum (mppa) used the Airport, travelling on some
256,400 flights. Of these 34 mppa, 18.7 mppa used the South Terminal and 15.4 mppa used the North
Terminal.
1.1.2 This document is the Non-Technical Summary of the Environmental Statement that has been prepared to
accompany two planning applications submitted by Gatwick Airport Limited. The first is for extensions to the
eastern and southern sides of the North Terminal building (the ‘North Terminal extension’) and the second is
for the provision of a new multi-storey car park adjacent to the North Terminal (‘multi-storey car park 6’).
1.1.3 These developments would support an increase in passenger throughput at Gatwick Airport overall to 40
million passengers per annum (with 276,000 air transport movements per year). This level of capacity is
expected to be reached in 2019. The North Terminal extension and multi-storey car park 6 would enable the
predicted growth in passenger traffic to be accommodated at the passenger service levels that the Airport
and the airlines aspiresto.
1.1.4 While not being applied for at this stage, the environmental impact assessment also takes account of two
other developments that are expected to come forward at the Airport (in accordance with the Gatwick Airport
Interim Master Plan1 and Car Parking Strategy
2) over the period up to 2019. These comprise airfield and pier
works and the provision of additional long-stay parking at ‘Flying Pan’ and ‘Summer Special’ car parks, to
meet the increased demand arising from passenger growth. Considering these additional developments
allows the environmental impact assessment to provide a complete picture of the likely significant effects of
the Airport’s growth to 40 million passengers per annum.
1.1.5 Collectively, the above developments being assessed within the EIA are known as the ‘North Terminal
Development Projects’. Figure 1 provides a diagram showing the make-up of the North Terminal
Development Projects and their status with regard to whether or not planning permission is being sought at
this time.
Figure 1: Overview of the North Terminal Development Projects
1 Gatwick Airport Limited (2006) Gatwick Airport Interim Master Plan, October 2006. 2 Entec UK Limited (2009) Gatwick Airport Car Parking Strategy, February 2009.
North Terminal Development
Projects
(1) Airfield and pier works
(2) Additional long-stay car parking
Planning permission not sought – EIA assumptions
Multi-storey car park 6
Planning permission sought
North Terminal extension
Planning permission sought
2
1.1.6 The preparation of the environmental impact assessment has been managed by Ove Arup & Partners Ltd on
behalf of Gatwick Airport Limited. Ove Arup & Partners Ltd and other environmental consultancies have
carried out the assessments for each environmental topic. The Environmental Statement comprises the
following sections:
1 Introduction and Composition of the Environmental Statement
2 The North Terminal Development Projects Sites
3 Project Description
4 Construction Methodology
5 Approach to the Environmental Impact Assessment
6 Policy Context
7 Consideration of Alternatives
8 Air Noise
9 Air Quality
10 Ecology
11 Economics
12 Employment
13 Ground Noise
14 Landscape and Visual
15 Transport
16 Waste
17 Water
1.1.7 The Environmental Statement comprises three volumes: Volume 1 Main Text, Volume 2 Figures and Volume
3 Appendices, as well as this Non-Technical Summary.
1.1.8 Information on obtaining copies or viewing the full Environmental Statement is given at the end of this
document.
3
2 The Existing Site
2.1 Gatwick Airport 2.1.1 Gatwick Airport is approximately 40 kilometres (25 miles) from central London, within the local authority
administrative district of Crawley and the county of West Sussex. The Airport is also close to the boundaries
of Reigate and Banstead, Mole Valley and Tandridge districts to the north, north-west and north-east of
Gatwick Airport respectively.
2.1.2 The nearest towns to Gatwick Airport are Horley and Crawley, the centres of which are located
approximately two kilometres to the north-east and 5.5 kilometres to the south of the Airport respectively with
suburbs of these towns bordering the Airport Site. Two kilometres to the west and one kilometre to the north-
west of the Airport boundary respectively are the villages of Charlwood and Hookwood.
2.1.3 The London to South Coast (Eastbourne, Brighton, Portsmouth, Southampton and Bognor Regis) railway line
passes through the Airport. The Airport has a railway station (at the South Terminal) which is served by
regular through trains and the Gatwick Express service running directly between Gatwick Airport and London
Victoria.
2.1.4 The M23 motorway runs to the east of Gatwick Airport with a motorway spur leading from Junction 9 of the
M23 to Junction 9a at Gatwick Airport. Road access to the Airport is provided from this junction as well as
from the A23 and A217.
2.2 The Proposed Development Sites 2.2.1 The total area of the proposed development sites is 29.7 hectares, although the actual development area for
which planning permission is currently being sought (ie without the airfield and pier works and the additional
long-stay car parking) is significantly less at 1.8 hectares.
Figure 2: Location of Proposed Development Sites
2.2.2 There are no statutorily designated ecological sites within or adjacent to the proposed development sites.
Brockley Wood, listed on the Forestry Commission’s Inventory of Woodland and Trees (a non-statutory
listing), is situated approximately 400 metres south-west of the existing ‘Summer Special’ car park.
2.2.3 The River Mole flows adjacent to the northern boundary of the Airport in a north-easterly direction and there
are three further watercourses within 2km, namely Mans Brook, Gatwick Stream and Crawters Brook.
2.2.4 The proposed development sites are described individually below.
4
North Terminal Extension Site
2.2.5 The North Terminal extension would be developed along the eastern and part of the southern edges of the
existing North Terminal building.
2.2.6 The southern extension area is currently an area of level and vacant tarmac that is used for empty baggage
storage, following the removal a temporary building. The eastern extension area currently partly comprises
an existing glass atrium which sits on the front of the Terminal building and is used as circulation space and
is partly built out over the existing elevated roadway that currently functions as the departures forecourt.
2.2.7 The North Terminal extension necessitates the demolition and re-routing of the domestic passenger route
from the existing Terminal to the domestic baggage reclaim hall.
Multi-Storey Car Park 6 Site
2.2.8 The new multi-storey car park would be provided to the east of the North Terminal and north of existing multi-
storey car park 5 and the Transit station. This land is an existing ground-level car park, currently occupied by
the North Terminal car rental operation as well as providing parking for high-sided vehicles.
Additional Long-Stay Parking Sites
2.2.9 The ‘Flying Pan’ and ‘Summer Special’ car parks are situated to the north and west of the cargo facility at
North Terminal respectively.
2.2.10 Both car parks currently provide long-stay block parking, where a higher density of cars can be parked than
in a conventional car park. Dog Kennel Pond (a balancing pond) is immediately to the north of the ‘Flying
Pan’ car park, whilst new stands will soon be constructed west of ‘Summer ‘Special’ car park as part of the
North West Zone Stands Project, which recently received planning permission.
Airfield and Pier Works
2.2.11 The airfield and pier works would take place within the existing airfield in the locations shown in Figure 2.
This comprises works to Pier 1, Pier 2, Pier 6, remote parking for small aircraft and the remote parking area /
new Pier 7 on the Tower Stands site.
5
3 Background and Need 3.1.1 Gatwick Airport Limited is predicting growth in passenger numbers at the Airport to 40 million passengers per
annum in the year 2019. It is proposed to accommodate this growth mainly within the North Terminal which
currently serves about 15 mppa by increasing the passenger throughput capacity to 20 mppa.
3.1.2 The need for the North Terminal Development Projects can be put simply as to ensure that the predicted
growth in passenger traffic planned for North Terminal can be accommodated at the passenger service
levels the Airport and its airlines aspires to.
3.1.3 Internal improvements are currently being made to facilities in North Terminal such as the departures lounge.
However, further improvements to the landside departures and check-in concourse and the international and
domestic arrivals concourse and baggage reclaim halls, are required if service standards are to be met.
3.1.4 Additionally, to ensure the proper and efficient functioning of the Airport as passenger throughput grows,
further short-stay car parking would be required to meet anticipated demands that would arise. A planning
application is therefore also made for multi-storey car park 6, to meet these future demands for short-stay car
parking adjacent to the Terminal.
3.1.5 It is also anticipated that over time, the demand for passenger long-stay parking would increase as the
number of passengers increases. Included in the assessment (but not being applied for within the current
planning application) therefore, are anticipated proposals for further long-stay car parking developments (a
single level of decked parking on the ‘Flying Pan’ and ‘Summer Special’ sites). Whether the scale of
additional demand for long-stay passenger parking as assessed materialises will only become clear in future
years.
3.1.6 In addition, in accordance with the Interim Master Plan, development of the airfield is likely to continue over
the period to 2019, to meet increased demand arising from passenger growth. These developments include
a new Pier 7 to serve North Terminal, reconfiguration of a number of remote and pier served stands and the
redevelopment of Pier 1.
7
4 Consideration of Alternatives 4.1.1 With regard to the North Terminal Development Projects, the only element for which alternatives has been
considered in detail is the North Terminal extension. Only one site was considered for the multi-storey car
park 6, this being the obvious location and as identified in the Interim Master Plan.
4.1.2 In relation to the additional long-stay parking and airfield works, these elements are not being applied for as
part of the current planning application and therefore have not yet been subject to full optioneering studies
and detailed design. The schemes considered within this environmental impact assessment reflect the most
likely options being considered by Gatwick Airport Limited at the present time.
4.2 North Terminal Extension Alternatives 4.2.1 At the start of the
optioneering process four
possible designs for the
North Terminal building
extension were produced,
essentially considering
internal reconfiguration only,
south extension, north
extension and east
extension. To investigate
these four initial design
options, the design team
engaged in a process of
testing each of the options
against Gatwick Airport
Limited’s key business objectives that include the maintaining good service levels throughout the
development and ability to provide future flexibility.
4.2.2 Using these criteria, it was identified that there was no single directional extension (south, north or east) that
could provide a suitable solution but that a combination would need to be provided.
4.2.3 From this it was determined that the preferred options to be investigated further were a combination of an
eastern extension with a south reclaim hall expansion. Following the design of a number of sub-options and
further analysis, the southern and eastern extension was selected which is presented and assessed in this
Environmental Statement.
9
5 Project Description
5.1 North Terminal Building Extension 5.1.1 The North Terminal extension would partially infill the vacant area to the south of the existing
Terminal (at all four levels: Arrivals, Avenue, Departures and plant room) and also extend to the
east at Departures Level, over the former forecourt road. This would create an additional floor
area of 14,555 square metres over four floors. This additional area is required for the increases in
baggage reclaim halls, both domestic and international (at Arrivals Level) and Departures Level
check-in facilities, to accommodate predicted future passenger numbers.
5.1.2 The North Terminal extension and multi-storey car park 6 are shown in Figure 3 and Figure 4.
Figure 3: Illustration of the North Terminal Extension
Figure 4: Illustration of Multi-storey Car Park 6
10
5.1.3 At Arrivals Level to the south, the new domestic baggage reclaim hall would add an additional
baggage belt. The increase in area of the international baggage reclaim hall would also add an
additional longer baggage belt suitable for new large aircraft. The new extension to the south at
this level also encompasses a new domestic passenger route from the Terminal to the reclaim hall.
The route consists of an elevated corridor located in the double height space crossing through the
international reclaim hall and down into the domestic reclaim hall.
5.1.4 Above the double height baggage reclaim halls is the south extension to the Departures Level
check-in hall. The check-in hall would increase by an additional bay, adding extra check-in desks.
Additional check-in desks are also to be added to the north of the check-in hall, at the end of the
existing row of desks. At Departures Level, additional space would be created for circulation and
check-in facilities with a new roof with skylights, allowing natural light into the Terminal.
5.1.5 To the east, the extension takes over half of the elevated roadway, formerly the departures
forecourt, creating a new area for customer service desks and ticket desks and passenger
circulation and wayfinding. Internally, the departures concourse would be rationalised and
upgraded to reflect the quality of the new extension and create a more light filled space. A new
roof and canopy extend over this area providing a new front to the Terminal bringing it up-to-date
both internally and externally.
5.1.6 The extension would add a new bomb blast resistant glazed façade to the Terminal which would
also enhance the presence and appearance of the Airport as passengers approach.
5.2 Multi-Storey Car Park 6 5.2.1 Multi-storey car park 6 (Figure 4) is intended to provide additional car parking to meet anticipated
short-term demand at North Terminal as its passenger throughput increases. This land is
currently occupied by the North Terminal car rental operation as well as providing parking for high-
sided vehicles.
5.2.2 The new car park comprises a ground-level plus six storeys of parking with access to the Terminal
at Avenue and Departures Levels. The car park would provide approximately 900 self park, short-
stay spaces. There would also be car rental and spaces in a pick-up zone.
5.2.3 Vehicular access to the upper floors would be via externally located circular ramps which would
provide independent up and down vertical circulation. Passenger access would be via lifts and
access stairs and dedicated fire escape stairs would also be provided. Vehicular access and
egress would be via the outer forecourt road.
5.3 Additional Long-Stay Parking 5.3.1 It is assumed that 2,600 new car parking spaces would be provided by constructing elevated
decks at the existing ground-level ‘Flying Pan’ and ‘Summer Special’ car parks, to accommodate
the forecast increase in passenger numbers associated with increasing the capacity of the Airport
to 40 million passengers per annum.
5.3.2 The elevated decks at the ‘Flying Pan’ and ‘Summer Special’ car parks would be of simple steel
framed construction with treated steel decks. The car park frames and decks are pre-assembled
in units off site and then transported to site for assembly. Once on site, the steel frames and
decks are bolted together and lifted into place consecutively in units using cranes.
11
5.4 Airfield and Pier Works 5.4.1 The environmental impact
assessment also takes
account of the changes to
the airfield that are expected
to come forward at the
Airport over the period to
2019. These airfield works
comprise the following
elements.
5.4.2 Gatwick Airport Limited
intends to develop a new
pier (Pier 7) on the airfield to
provide an improved,
covered pier service to a
greater number of aircraft
stands. Based on work completed to date a likely location for this new pier is on the Tower
Stands site which is a largely paved area currently used for aircraft parking.
5.4.3 The following airfield works are assumed for the purposes of the environmental impact
assessment:
• A new pier (‘Pier 7’) comprising a two-level structure with an internal third suspended level
forming the Arrivals corridor, and adjacent aircraft stands. The dimensions of the structure
would be 30 metres by 250 metres with a maximum height of 13.8 metres. The pier would be
connected to the existing Terminals using electric buses.
• Redevelopment of Pier 1 – this involves the demolition of the existing Pier 1 facility, together
with the adjacent Southgate warehouse units and Old Customs House offices, to enable the
construction of a new pier (two levels) with the opportunity for a further two ‘push and hold’
stands to the west. The new Pier 1 would have a smaller footprint than the existing Pier 1
facility with an area of approximately 1,500 square metres, dimensions of 25 metres by 60
metres and a building height of 9 metres. Connectivity to the Terminal would be provided by
new link corridors.
• Reconfiguration of Pier 2 – this involves reconfiguring the stands to replace the existing nine
stands with 13 smaller stands. The footprint of the pier would remain unchanged with the
reconfiguration works taking place within the existing footprint.
• Reconfiguration of Pier 6 – this involves reconfiguring the stands to replace the existing six
stands with four stands to accommodate wider aircraft.
• Reconfiguration of remote stand parking for small aircraft to the south of Pier 6 – this involves
moving the remote stand parking for small aircraft southwards slightly and reconfiguring the
stands to provide stands for three larger aircraft.
5.5 Forecasts 5.5.1 As a result of the North Terminal Development Projects, passenger throughput at the Airport is
expected to increase to 40 mppa (from a current level of 34.2 mppa). It is predicted that this level
of throughput would be reached in 2019.
5.5.2 For the purposes of the EIA, forecasts have been provided by Gatwick Airport Limited for the 40
mppa ‘development case’ scenario. Forecasts have also been prepared for the ‘base case’
scenario in 2019 which represents the Airport operational situation in 2019 without the North
Terminal Development Projects.
5.5.3 Table 1 summarises the headline forecasts associated with each of the assessment cases that
have been used in the EIA.
12
Table 1: Summary of Headline Forecasts
2007
2008
2019
Base Case
2019
Development
Case
Passenger throughput (mppa) 35 34 36 40
South Terminal 21.1 18.7 20.0 20.2
North Terminal 14.1 15.4 16.0 19.8
Passenger Air Transport Movements (000s) 258.63 256.05 265.43 275.79
Cargo Air Transport Movements (000s) 0.17 0.32 0.13 0.25
Total Air Transport Movements (000s) 258.8 256.4 265.6 276.0
Other Aircraft Movements (000s) 7.8 7.4 8.0 9.7
Total Aircraft Movements (000s) 266.6 263.7 273.6 285.7
Cargo tonnage 171,200 107,700 91,400 116,200
5.6 Wider Context 5.6.1 The environmental impact assessment assesses the environmental effects of the four
developments described above. However, it is important to put the projects within the wider
context of other already permitted development projects at Gatwick North Terminal. These
projects are the:
• North Terminal Forecourt;
• North Terminal Interchange;
• Inter-Terminal Transit System upgrade; and
• North West Zone Stands Project.
5.6.2 The North Terminal Forecourt and North Terminal Interchange Projects are being undertaken in
response to the regulations being imposed on Gatwick Airport Limited by the Department for
Transport under Aviation Security in Airport Development, the purpose of which is to mitigate
terrorist threat. Compliance with Aviation Security in Airport Development requires that
uncontrolled vehicles cannot come within 30 metres of the Terminal building. This means
introducing a controlled zone to the front of the Terminal restricting access for uncontrolled
vehicles.
5.6.3 Previously, uncontrolled vehicles have been able to drop off directly outside the Terminal at
ground level and at second floor level via the raised roadway. Given that uncontrolled vehicles
will no longer be able to use this raised roadway, a new forecourt area needs to be developed
which is to be provided along Northways and Furlong Way – this is the North Terminal Forecourt
Project.
5.6.4 This new forecourt proposal has instigated a review of pedestrian access to the Terminal (due to
the shifting arrival point for many passengers) which has led to the development of a new
interchange (the North Terminal Interchange Project) through which passengers arriving at North
Terminal by varying modes of transport will enter and leave the Terminal.
5.6.5 The Inter-Terminal Transit System that currently runs between the North and South Terminals at
Gatwick Airport is coming to the end of its design life and is due to be upgraded. This will involve
a full closure of the Inter-Terminal Transit System to upgrade the system and install new trains.
5.6.6 The North Terminal Forecourt, North Terminal Interchange and Inter-Terminal Transit System
upgrade are separate projects that are going ahead independently of the North Terminal
Development Projects. The cumulative effects of these projects, in conjunction with the North
Terminal Development Projects, have been considered as part of the environmental assessment.
13
5.6.7 Additionally, the cumulative effects of the North Terminal Development Projects with the North
West Zone Stands Project (granted planning permission in January 2009) are also considered.
The North West Zone Stands Project comprises the development of six fully serviced remote
stands and an associated taxi lane in the North West Zone area of the Airport, with associated
earth screening bund, surface water attenuation pond and other infrastructure.
15
6 Construction
6.1 Phasing 6.1.1 Construction of the North Terminal extension and multi-storey car park 6 would follow a sequential
process planned to commence in Autumn 2009, with overall completion planned for 2011. The
construction programme for the North Terminal Development Projects is provided in Figure 5. This
figure also shows the anticipated construction programmes for the other projects in the wider
North Terminal context, described in Section 5 of this NTS.
Figure 5: Construction Programme
6.1.2 The construction of the assumed additional long-stay car parking would take place over the ten
year period of growth of the Airport to 2019, with the intention of providing car parking to meet
demand as it arises.
6.2 Working Hours 6.2.1 Site working hours would be
07.00 to 18.00 hours
Monday to Friday inclusive.
No Saturday, Sunday or
night-time work is planned,
however there may be
occasions when this would
require adjustment to
accommodate specific
activities. These could
include variations to
construction working hours
to cope with loss of
programme due to poor
weather.
6.2.2 It is envisaged that deliveries of aggregates and materials would probably be spread across the
11 hour day.
6.3 Community Liaison Strategy 6.3.1 A community liaison strategy would be introduced for the projects, led by Gatwick Airport Limited
staff. The precise form of this liaison would be agreed with the local stakeholders based upon
what is required, but may include flyers or consultation meetings.
6.4 Construction Environmental Management Plan 6.4.1 A Construction Environmental Management Plan would be prepared by the appointed contractor,
and construction would need to comply with measures detailed within the Plan.
16
6.4.2 The Construction Environmental Management Plan would set out the environmental management
measures that would be adopted during the construction of the projects in order to prevent or
reduce potential environmental effects associated with demolition and construction activities. It
would also identify who is responsible for the implementation of each measure and what evidence
will be required to demonstrate compliance.
6.4.3 All the necessary permits, licences and consents would be obtained, for example for handling any
hazardous waste found or discharges to water.
6.4.4 Measures set out in the Construction Environmental Management Plan are assumed to be
adopted for the purposes of assessing likely environmental effects of construction as detailed in
the Environmental Statement.
17
7 Approach to the Environmental Impact Assessment
7.1 Overview 7.1.1 The Environmental Statement has been prepared in accordance with the Environmental Impact
Assessment Regulations3.
7.1.2 The Environmental Impact Assessment Regulations enact in UK legislation, the European
Community requirements for the environmental impact assessment of major projects, set out in
Directive 85/337/EEC, as amended by Directive 97/11/EC, as part of the planning consent
procedures.
7.1.3 The North Terminal Development Projects fall within Schedule 2 of the Environmental Impact
Assessment Regulations, meaning that an environmental impact assessment may be required,
depending on the likelihood of significant environmental effects. In this case, taking account of the
possibility that there may be environmental effects which could potentially be significant, it was
agreed with Crawley Borough Council that an environmental impact assessment would be carried
out.
7.1.4 The purpose of undertaking an environmental impact assessment is to assess how the
environment is likely to be affected by a proposal so that measures can be taken, if necessary,
that would prevent or reduce the adverse environmental effects. The main stages in the
preparation of the Environmental Statement were:
• scoping and consultation;
• baseline data gathering;
• impact assessment;
• consideration of measures to prevent, reduce or offset effects, where appropriate; and
• preparation of an Environmental Statement and Non-Technical Summary.
7.1.5 Each of these is described in turn below.
7.2 Scoping and Consultation 7.2.1 A Scoping Paper
4 guided by Regulation 10(2) of the Environmental Impact Assessment
Regulations was produced and circulated by Gatwick Airport Limited in January 2009. The
purpose of this Paper was to engage with the local planning authority and other consultees in
seeking agreement on the scope of the environmental impact assessment and the approach to be
adopted for the assessment of those topics which had been ‘scoped in’ to the environmental
impact assessment.
7.2.2 The Scoping Paper was distributed to a range of consultees, providing information about the
proposed Project and giving an overview of existing conditions on the Sites and in the area. On a
topic by topic basis, the approach to identifying baseline information and potential environmental
effects was described and the scope of the assessment and the methodology for assessing both
construction and operational effects was set out.
7.2.3 Following distribution of the Scoping Paper, two Scoping Workshops were held to facilitate
discussions with statutory and non-statutory consultees on the proposed scope and
methodologies for the environmental impact assessment. As a result of the scoping exercise the
following assessment topics were ‘scoped in’ to the environmental impact assessment:
• Air Noise;
• Air Quality;
• Ecology;
• Economics;
• Employment;
3 The Town and Country Planning (Environmental Impact Assessment)(England and Wales) Regulations1999 (SI No. 293) as amended by the Town & Country Planning (Environmental Impact Assessment)(Amendment) Regulations 2006 (SI 2006 No. 3295) and the Town & Country (Environmental Impact Assessment)(Amendment)(England) Regulations 2008 (SI 2008 No. 2093). 4 Gatwick Airport Limited (2009) Environmental Scoping Paper, January 2009
18
• Ground Noise;
• Landscape and Visual;
• Transport;
• Waste; and
• Water.
7.2.4 The following topics were ‘scoped out’ of the Environmental Statement:
• Third Party Risk;
• Cultural Heritage; and
• Ground Resources and Contaminated Land.
7.3 Baseline Data Gathering 7.3.1 Information about existing conditions at and in the area around the Sites has been obtained for
each of the environmental topics ‘scoped in’ from the following sources:
• documentary information from a wide variety of sources including information held by Gatwick
Airport Limited, and historical and contemporary records;
• field survey information including background noise levels, ecological features, landscape
character and traffic levels on the road network;
• maps of both historical and contemporary features; and
• data from statutory and non-statutory consultees.
7.4 Impact Assessment 7.4.1 The likelihood of significant environmental effects arising from the North Terminal Development
Projects has been assessed by reference to construction, existence and operational
characteristics of the developments. A cumulative assessment was also undertaken. These are
described in turn below.
Construction Effects
7.4.2 Construction effects are defined in the Environmental Statement as those temporary effects that
arise during demolition, enabling works and construction which cease after the completion of
construction. Examples would include construction noise, vibration and dust.
Existence and Operational Effects
7.4.3 The operational assessment identifies effects arising from both the existence and operation of the
North Terminal Development Projects:
• Existence effects arise from the physical presence of the development and are generally
unchanging over time (eg effects from land take for the development such as loss of ecological
resources).
• Operational effects may vary from hour to hour, day to day and year to year. These include
operational ground noise, emissions to air and water and visual effects from new floodlighting
associated with the additional long-stay car parking.
Cumulative Effects
7.4.4 Cumulative effects are those effects that arise (during both construction and operation) from the
combination of the North Terminal Development Projects and other existing or reasonably
foreseeable proposed developments.
7.4.5 If development projects are considered individually, the environmental effects may appear not
likely to be significant. However the combination of effects from the proposed development and
those caused by other permitted developments (existing, not yet constructed or currently under
construction), acting together, may generate elevated levels of environmental effect and these are
referred to as cumulative effects.
7.4.6 These types of effects have been assessed in the environmental impact assessment process and
are reported in the topic sections of the Environmental Statement.
19
Assessment Years
7.4.7 The environmental assessment work reported in the Environmental Statement has adopted the
following assessment years.
• Construction: the construction effects assessment considers the construction effects of the
North Terminal Development Projects at the peak construction period which is identified as
November 2009 to January 2010;
• Operation: the core assessment year for the environmental impact assessment of operational
effects is 2019, which is the year at which the expanded Airport is expected to reach 40 million
passengers per annum;
• For the transport assessment, an additional year of 2026 has been assessed, for consistency
with the South East Plan5 housing forecasts.
Assessment Cases
7.4.8 For the purposes of predicting and assessing the likely significant environmental effects of the
North Terminal Development Projects, a series of scenarios have been developed which have
been used to formulate assessments.
7.4.9 A series of terms are used for this purpose, which are defined in the table below.
Table 2: Key Assessment Terms
Term used Explanation
Baseline The Sites (and surrounding area) as they currently exist.
Base case This is the predicted future scenario representing the situation at the Airport without the
North Terminal Development Projects, either during the construction period or at 2019.
Development
case
The construction development case represents the situation at the Airport during
construction and assumes that the Projects are implemented in accordance with a
Construction Environmental Management Plan.
The operational development case represents the situation at the Airport with the North
Terminal Development Projects in operation at 2019. This case assumes that planning
permission and other consents have been granted for all elements Project.
Mitigation
measures
Measures proposed as part of the North Terminal Development Projects that would
prevent or reduce significant adverse environmental effects.
7.4.10 The construction effects assessment of the North Terminal Development Projects considers the
effects of construction by comparison to the no development base case for the relevant
assessment year and where appropriate, by comparison to absolute criteria.
7.4.11 The operational assessment for each topic considers the existence and operational effects of the
North Terminal Development Projects by comparison to the no development base case for the
relevant assessment year and, where appropriate, by comparison to absolute criteria. This is
summarised in Table 3 below, which applies to both construction and operational assessments.
Table 3: Basis of Assessment
Base case = Baseline projected forward to the relevant assessment year
Development
case
= Base case + North Terminal Development Projects at the relevant
assessment year
Assessment = Effect of the development case by comparison to the base case
5 The South East Plan (2009) Regional Spatial Strategy for the South East of England, May 2009, Government Office for the South East.
20
Consideration of Mitigation Measures
7.4.12 In general a ‘hierarchy’ of mitigation has been adopted for the environmental impact assessment,
such that potentially significant adverse environmental effects have been firstly prevented or
avoided (eg through environmental design). Where this is not possible, they have been reduced or
ameliorated as far as practicable. Where effects cannot be entirely avoided or reduced, then
offsetting measures have been adopted, where this is practicable. All types of mitigation
measures are described within the individual topic sections in the Environmental Statement.
21
8 Air Noise
8.1 Introduction 8.1.1 The air noise assessment identifies the effects that may occur from the North Terminal
Development Projects due to noise generated by aircraft whilst on the runway, during take-off, in
flight, on approach and landing. Noise due to aircraft during taxiing or from other operations on the
ground is considered within the ground noise assessment (Section 13).
8.1.2 The effects of the North Terminal Development Projects which have the potential to result in
changes in air noise are the increase in total aircraft numbers using the Airport (around 4%), and
the changes in the numbers of certain types of aircraft using the Airport. Therefore only the
operational phase of the development is relevant to air noise and so the construction phase is not
considered further.
8.2 Methodology 8.2.1 Noise from airports is
typically represented by
‘noise contours’ that show
areas around an airport
which experience similar
noise levels. The air noise
contours used in this
assessment have been
calculated by the
Environmental Consultancy
and Research Department
of the Civil Aviation Authority
using an air noise model,
which has been developed
over the last 30 years and
brings together a range of international best practice. The model makes use of airport
characteristics such as flight paths and routes and aircraft noise data derived from measurements
taken at London airports including Gatwick. The model and its database are updated each
summer.
8.2.2 The model allows air noise levels to be calculated at a grid of locations surrounding the Airport.
The noise levels are calculated by considering, for each aircraft, its track and noise characteristics
which are then used to generate noise contours.
8.2.3 The noise contours are overlaid onto Ordnance Survey mapping to show locations that are
affected by aircraft noise. This allows the number of dwellings and people exposed to certain
noise levels to be calculated. The computer models used to generate the noise contours also
allow noise levels at specific points to be identified. The assessment has considered sensitive
receptors such as residential dwellings, schools and hospitals, and assigned appropriate
assessment criteria based on Government policy and other guidelines. Effects on Areas of
Outstanding Natural Beauty in the surrounding area are also considered.
8.2.4 Two models have been developed for the assessment; one that models the number of aircraft
movements which would occur in 2019 without the North Terminal Development Projects and a
second that models the number of aircraft movements which would occur with the in 2019 with the
Projects. By comparing models, the change due to the North Terminal Development Projects can
be examined.
8.2.5 The assessment methodology has been discussed with a number of consultees, including
representatives from the relevant local authorities and at a Scoping Workshop held in January
2009. Further consultation has also been undertaken with other consultees by the project team.
22
8.3 Baseline 8.3.1 The level of air noise experienced by sensitive receptors depends primarily on their proximity to
the runway and flight paths. The noise contours for the current number of aircraft movements at
Gatwick Airport show that some (but not all) parts of Lowfield Heath, Burstow, Charlwood and
Fernhill Road, experience what the Government considers to be a ‘medium’ level of noise. A
small number of properties off Ilfield Road and some areas of Fernhill experience a ‘high’ level of
noise. Communities in some areas in the southern parts of Lingfield, Charlwood and Chorley
would experience lower levels of noise, but may still be annoyed by aircraft noise. A number of
flight paths overfly the various Areas of Outstanding Natural Beauty surrounding the Airport.
8.4 Assessment 8.4.1 The assessment compares the situation which would occur in 2019 without the North Terminal
Development Projects to the situation in 2019 when the North Terminal Development Projects is
assumed to be operational.
8.4.2 The air noise levels in 2019 without the North Terminal Development Projects are very similar to
those described above for the current conditions, described under ‘Baseline’ above. Compared
with the base case and the baseline, the North Terminal Development Projects result in only minor
changes to the location and extent of the noise contours. There are no clear changes in the areas
exposed to medium or high noise levels. However, the noise contour area where communities
may be described as experiencing ‘significant annoyance’ includes slightly more of south Lingfield.
There is no change proposed to the flight paths in the future, either with or without the North
Terminal Development Projects.
8.4.3 All of the receptors considered by the assessment, including Areas of Outstanding Natural Beauty,
are likely to experience increases in air noise of less than 1 decibel, with most experiencing
changes of less than half a decibel. An increase of this level of noise is unlikely to be noticeable.
8.4.4 The air noise effects are not considered significant.
8.5 Mitigation 8.5.1 Gatwick Airport already has a number of measures in place to manage and reduce air noise levels.
These include departure noise limits, specified arrival and departure routes, night noise limits, and
a noise action plan is currently being developed. No additional measures are considered
necessary, since the air noise effects due to the North Terminal Development Projects are not
considered significant.
8.6 Residual Assessment 8.6.1 People living and working in the area around Gatwick Airport and its flight paths are likely to
experience very small air noise level increases (of much less than 1 decibel) due to the North
Terminal Development Projects, which are unlikely to be noticeable.
23
9 Air Quality
9.1 Introduction 9.1.1 The assessment evaluates the likely significant effects of the North Terminal Development
Projects on air quality arising from emissions of polluting gases and fine particles from:
• aircraft main engines in the landing and take-off flight phases on the ground and up to 1000
metres height;
• aircraft auxiliary power units;
• airside support vehicles and plant;
• road vehicles on Airport landside roads and on a specified road network around the Airport;
• vehicles in car parks and car rental pounds; and
• Airport heating plant and the fire training ground.
9.1.2 The key pollutants that have been assessed are nitrogen oxide which comprises nitric oxide and
nitrogen dioxide, and particulate matter less than 10 micrometers and 2.5 micrometers in diameter.
9.1.3 Effects have been assessed in 2019, when the North Terminal Development Projects would reach
full use.
9.1.4 Potential effects on air quality during construction were considered during scoping. It was
concluded that the increase in exhaust emissions associated with additional road traffic
movements, over what would be a relatively short period of time, with no overlap between the
peak construction periods for each element of the North Terminal Development Projects, would be
small and insignificant in relation to the emissions from the baseline traffic flows on the local road
network. The distance between source and receptor is also sufficient for effects of construction
dust to be not significant and, as with all construction phase emissions, these are short-term and
temporary in nature. Construction effects from air quality were therefore scoped out of the ES.
9.2 Methodology 9.2.1 The methodology involved
the quantification of
emissions of nitrogen oxide,
particulate matter less than
10 micrometers and less
than 2.5 micrometers in
diameter arising without and
with the North Terminal
Development Projects in
2019. This enabled the
absolute values and
incremental change in
ground-level concentrations
of these pollutants as well as
levels of nitrogen deposition
to be determined. The methodology enables the environmental effects on air quality from the
operation of the North Terminal Development Projects to be assessed.
9.2.2 Calculated emissions are input to a dispersion model, which uses actual meteorological data for
one year to simulate the way the emitted pollutants are diluted and dispersed in the atmosphere.
ADMS-Airport version 2.3 computer software was used for the modelling assessment to determine
concentrations and deposition rates of airborne pollutants emitted from the sources described
above at specified locations within the assessment area, termed sensitive receptors. These
concentrations and deposition rates were then compared with UK and EU Air Quality Standards,
and other relevant guideline values for each pollutant, and the magnitude and significance of the
changes brought about by the North Terminal Development Projects were assessed.
24
9.3 Baseline 9.3.1 The baseline air quality conditions have been established from air quality monitoring data
collected in the assessment area by local authorities (Crawley Borough Council, Reigate and
Banstead Borough Council and Mole Valley District Council), from data collected by Gatwick
Airport Limited in the vicinity of the Airport and from background pollutant concentration data
published on behalf of the Department for Environment, Food and Rural Affairs.
9.3.2 To provide some context for the calculated nitrogen deposition, rates from Airport sources have
been presented alongside the total nitrogen deposition from all sources, at the selected ecological
receptor locations, calculated using the UK Air Pollution Information Service6 website.
9.3.3 Baseline air quality in the area close to the Airport is generally good, although Reigate and
Banstead Borough Council has declared an Air Quality Management Area in the south-west of
Horley near to Gatwick Airport (to the north-east of the Airport and west of the M23 motorway), on
the basis of a potential exceedence of the annual mean nitrogen dioxide Air Quality Objective. A
further nitrogen dioxide Air Quality Management Area has also been declared for a section of the
M23 motorway near Horley (extending 30 metres either side of the carriageway) between
Junctions 8 and 9, where the motorway lies within the administrative boundary of Reigate and
Banstead. At all other locations around the boundary of Gatwick Airport, the Air Quality Objectives
are comfortably achieved.
9.4 Assessment 9.4.1 The assessment focused on quantifying the change in concentrations of nitrogen dioxide,
particulate matter less than 10 micrometers and less than 2.5 micrometers in diameter at sensitive
receptor locations around the Airport, and at locations of existing air quality monitoring stations.
Concentrations of nitrogen oxide and rates of nitrogen deposition at sensitive ecological receptors
around the Airport, including Sites of Special Scientific Interest, Special Protection Areas and
Special Areas of Conservation have been determined. During operation of the North Terminal
Development Projects the changes in ambient concentrations of nitrogen oxide, nitrogen dioxide,
particulate matter less than 10 micrometers and 2.5 micrometers in diameter were shown by the
dispersion modelling to be very small and were therefore considered as not significant. Air quality
in 2019 is also forecast to improve beyond the current baseline, to the extent that the Air Quality
Objective for nitrogen dioxide is anticipated to be met at locations where there are currently Air
Quality Management Areas. At ecological receptor locations the assessment has shown that
changes in nitrogen oxide concentrations and nitrogen deposition rates are very small and not
significant.
9.5 Mitigation 9.5.1 In air quality terms, the operational effects of the North Terminal Development Projects have been
shown to be very small and no further measures to prevent or reduce air quality effects are
required.
9.6 Residual Assessment 9.6.1 The residual air quality effects of the operation of the North Terminal Development Projects are
considered not significant.
6 Air Pollution Information Service (2007) www.apis.ac.uk
25
10 Ecology
10.1 Introduction and Methodology 10.1.1 The assessment of likely significant ecological effects has involved desk based data gathering and
field surveys of the sites of all elements of the development, to identify the presence of species
and semi-natural habitats protected by law or considered to be of nature conservation value.
10.1.2 Significant ecological effects can be defined as changes in the status of species, or the habitats
that support them. Effects on status generally relate to changes in the presence or absence of
species or habitats through direct loss or as a result of disturbance due to either the construction
or the operation and existence of the development. The assessment has been carried out in
accordance with national recognised best practice guidance set out by, amongst others, the
Institute of Ecology and Environmental Management7.
10.2 Baseline 10.2.1 All the elements of the Project would be undertaken within areas of existing built structure or
hardstanding within the curtilage of Gatwick Airport. The potential for the built structures to support
species or habitats of ecological value was examined by survey. All structures were inspected for
their potential to support bats. In addition, data held by the Sussex and Surrey Biological Records
Centres was sought and reviewed to identify whether there were any historic records for species
and habitats within, or in association with, the proposed development sites.
10.2.2 There are historic records of bats dispersing along the River Mole corridor and foraging in areas of
semi-natural habitat to the north and west of the ‘Summer Special’ and ‘Flying Pan’ car parks,
outside the extent of the currently developed land. No other species or habitats of nature
conservation value were recorded in any part of the proposed development sites and therefore
effects on bats was the only element scoped into the ecological assessment for the North
Terminal Development Projects.
10.3 Assessment 10.3.1 Proposed works would be
restricted to existing areas
of developed land.
Moreover, indirect effects
associated with dust,
uncontrolled surface water
run-off, noise, vibration and
traffic movements would
also be restricted within the
existing extent of developed
land. The construction of all
the elements of the
proposed development
would therefore not result in
any significant ecological
effects.
10.3.2 The provision of elevated decks for the ‘Summer Special’ and ‘Flying Pan’ would require additional
lighting as part of the operation of the these car parks. Whilst the car parks are already lit, it was
assessed that the provision of additional lighting would increase overall lighting intensity and result
in a greater degree of light spillage into the surrounding areas of semi-natural habitat along the
River Mole corridor and the boundary of the North West Zone area. Light spillage can disrupt bats’
ability to navigate and forage and it was therefore considered that the provision of additional
lighting in relation to these car parks would have a minor adverse effect on a bat assemblage,
assessed as being of local importance.
7 Institute of Ecology and Environmental Management (2006) Guidelines for Ecological Impact Assessment in the United Kingdom.
26
10.4 Mitigation 10.4.1 Lighting design including the arrangement of the light columns, the use of flat glass, internal
louvres, hoods and deflectors, have been identified as providing mitigation to significantly reduce
additional light spillage resulting from the operation of the decked car parks. Measures would be
designed to ensure that as much of the light as possible is focused directly onto the car park deck
to significantly reduce light spillage.
10.5 Residual Assessment 10.5.1 The implementation of the proposed measures to mitigate effects would result in a negligible
effect on the bats ability to disperse and forage.
10.5.2 No other potentially significant ecological effects were identified.
27
11 Economics
11.1 Introduction and Methodology 11.1.1 The assessment of the likely significant effects of the North Terminal Development Projects on
economics considers:
• the benefits to people using the Airport (direct user benefits); and
• the benefits to the economy as a result of the Airport enabling other types of activity to take
place (wider economic benefits).
11.1.2 These effects arise as a result of the operation of the Airport. There are no economic effects
associated with construction of the North Terminal Development Projects beyond the employment
created which is covered in Section 12, Employment.
Direct Benefits
11.1.3 The proposed development would generate direct user benefits from the additional capacity.
While it is not possible to value the benefits (due to insufficient data), such benefits include
benefits to existing users of the Airport, new passengers who were previously unable to fly, freight
users, the Airport operator and government revenue.
Wider Economic Benefits
11.1.4 The assessment area covers the South East and Greater London regions. The analysis considers
the importance of Gatwick Airport to the following activities and assesses the contribution of the
North Terminal Development Projects to the different activities:
• where companies choose to invest including investment from overseas companies (inward
investment);
• international trade;
• international tourism; and
• benefits to business through increased productivity.
11.1.5 The baseline has been assembled from published data. Forecasts of future passenger and cargo
levels at the Airport have been provided by Gatwick Airport Limited.
11.2 Baseline 11.2.1 With 34.2 million passengers per annum in 2008, Gatwick is the second largest airport in the UK
and the principal airport in the South East region. Heathrow is the largest airport. In 2008
Gatwick was served by approximately 80 airlines carrying passengers to almost 200 destinations.
11.2.2 Some 17% of Gatwick’s passengers are making business trips which make Gatwick the second
largest airport in the UK for business passengers. Of its 34.2 million passengers, approximately
12 million come from or go to a destination in Greater London and approximately 12 million come
from or go to a destination in the South East.
11.2.3 The assessment area of the South East and London is very important to the success of the UK
economy and as competition from overseas increases, it is important that the assessment area
can respond to these changing circumstances.
11.3 Assessment
Business Location Decisions and Inward Investment
11.3.1 Access to air services influences where certain businesses choose to locate, particularly
businesses who deal with customers and suppliers who are located overseas. Gatwick has an
important role to play in attracting and retaining investment in the assessment area. The North
Terminal Development Projects would provide additional capacity which would help the
assessment area to remain competitive relative to overseas locations. A target for the South East
Regional Economic Strategy8 is to increase the proportion of businesses operating internationally
8 South East England Development Agency, The Regional Economic Strategy 2006-2016.
28
and to encourage inward investment. On this basis, the effect of the North Terminal Development
Projects on location decisions and inward investment is assessed as beneficial.
International Trade
11.3.2 International trade is important to the growth and development of the economy and aviation allows
international trade in goods and services to take place. Aviation plays a part in the movement of
traded goods and it provides businesses which trade internationally with easy contact to overseas
customers and suppliers for face-to-face meetings. The network of services provided by Gatwick
helps businesses in the assessment area to trade and operate on an international basis. The
effect of the North Terminal Development Projects on international trade is therefore assessed as
beneficial.
International Tourism
11.3.3 International tourism is an
important industry throughout
the world and the UK is one of
the top destinations. Gatwick is
the third most important airport
in the UK for international
visitors coming to the UK and is
the second most important
airport for UK residents wanting
to make overseas trips. The
North Terminal Development
Projects would enable more
trips to and from the UK to be
made. International tourism is a
very competitive industry and it is important that overseas visitors find it ‘easy’ to access the UK.
The effect of the North Terminal Development Projects on international tourism is therefore
assessed as beneficial.
Productivity Gains
11.3.4 Economic analysis has found that there is a relationship between business air use and
productivity. Applying this relationship shows that gross value added in the UK would be £0.8
billion higher in 2019 with the North Terminal Development Projects than would otherwise be the
case. On this basis the North Terminal Development Projects are assessed as having a beneficial
effect on productivity.
Overall Conclusion
11.3.5 The North Terminal Development Projects are assessed as having a beneficial effect on the
assessment area economy as they contribute to specific policies and objectives for the
development of the economy.
11.4 Mitigation 11.4.1 As the effects on economics of the North Terminal Development Projects have been assessed as
beneficial, there are no measures required to prevent or reduce effects.
11.5 Residual Assessment 11.5.1 As there are no measures required to prevent or reduce effects, the residual effect remains
beneficial.
29
12 Employment
12.1 Introduction and Methodology 12.1.1 The assessment of the likely significant effects of the North Terminal Development Projects on
employment considers the employment created during its construction and operation.
12.1.2 The construction employment assessment area covers the South East and Greater London
regions. The operational employment assessment area covers 13 local authorities around the
Airport from Croydon in the north to Brighton and Hove in the south, Worthing in the west and
Wealdon in the East.
12.1.3 The baseline has been assembled from published data and surveys of companies and employees
at Gatwick. Forecasts of future employment at the Airport have been made using information on
future passenger numbers and the relationship between passengers and employment.
12.2 Baseline 12.2.1 In 2008 there were 33,200 people in employment related to Gatwick Airport in the assessment
area. These employees earned wages and salaries of nearly £770 million.
12.2.2 Most of the employees (22,700) were employed within the boundary of Gatwick Airport while the
rest were employed throughout the assessment area in activities related to the operation of the
Airport.
12.2.3 The assessment area lies
within the South East region
which has been one of the
fastest growing regions in
the UK. The assessment
area has a high proportion
of the working age
population in work or
looking for work and
employment has been
growing in recent years.
Average earnings of people
living in the assessment
area are high and reflect the
effect of commuting
patterns on earnings in the assessment area.
12.2.4 The assessment area as a whole has a relatively low rate of unemployment, but for some groups
of the unemployed (eg lower skilled people) and some individual local authorities the
unemployment rate is much higher. This shows that there is a need for job opportunities in the
assessment area which could be done by people with lower skills.
12.3 Assessment
Construction
12.3.1 At the peak of activity, there would be 705 people employed at the Airport on the construction of
the North Terminal Development Projects which represents less than 0.5% of construction
employment in the assessment area.
12.3.2 There would also be some employment created elsewhere in the South East and London as a
result of the development. This is estimated to be 635 which also represents a very small
percentage of total employment in the assessment area.
12.3.3 The construction of the North Terminal Development Projects on employment is assessed as
minor beneficial.
30
Operation
12.3.4 In 2019 the North Terminal Development Projects would increase Gatwick related employment by
3,200 in the assessment area. The wages and salaries of the additional 3,200 employees would
be almost £74 million and the majority of these jobs (2,200) would be on the Airport site.
12.3.5 These additional jobs would contribute to the jobs target in the South East Plan5. Hence, when
the North Terminal Development Projects are operational, the employment effect is assessed as
moderate beneficial.
12.4 Mitigation 12.4.1 As the effects on employment during construction and operation of the North Terminal
Development Projects have been assessed as minor and moderate beneficial respectively, there
are no measures required to prevent or reduce effects.
12.5 Residual Assessment 12.5.1 As there are no measures to prevent or reduce effects, the residual effect during construction and
operation remains minor and moderate beneficial respectively.
12.5.2 Additionally, the Gatwick Skills Centre is an initiative which could support the employment growth
at the Airport with the North Terminal Development Projects which would ensure that people living
in the assessment area could make the most of the job opportunities at the Airport.
31
13 Ground Noise
13.1 Introduction 13.1.1 Ground noise is defined as any airport or airport related noise other than that generated by aircraft
in flight or taking-off or landing (which is defined as air noise). The North Terminal Development
Projects are required to support planned increases in passenger capacity at the Airport which
would in turn lead to small increases in the total amount of aircraft taxiing and Auxiliary Power Unit
operation and airport related road traffic as well as some re-distribution of aircraft ground
operations around the Airport.
13.1.2 The North Terminal Development Projects do not in themselves generate any significant ground
noise, but the changes in aircraft ground operations and road traffic would lead to small changes
in ground noise sound levels at different receiver locations around the Airport which are therefore
assessed in this Environmental Statement. It is not expected that the North Terminal Development
Projects would lead to any changes in rail traffic in the area and it is not therefore expected that
there would be any changes in rail traffic noise.
13.2 Methodology 13.2.1 Baseline background noise sound level surveys have been carried out in representative
residential areas around the Airport at three yearly intervals since 1999. The data are used to
show any changes in background noise sound levels since 1999 and to set a context against
which modelled aircraft taxiing and Auxiliary Power Unit noise sound levels can be compared.
13.2.2 Aircraft taxiing and Auxiliary Power Unit noise is assessed by modelling future sound levels from
these sources and then comparing the modelled sound levels against adopted criteria. The
method for calculating aircraft taxiing and Auxiliary Power Unit sound levels is based on accepted
methods used for previous large-scale airport development projects, as are the adopted criteria.
13.2.3 Road traffic noise is assessed by investigating proportional differences in predicted road traffic
flows between the base and development cases, as predicted by the LGW CONTRAM 2019 road
traffic model which was prepared as part of the Transport Assessment9, to determine the need, or
otherwise, for detailed quantitative noise modelling.
13.3 Baseline 13.3.1 The baseline background noise sound level survey data show small differences, both up and
down, in the lowest hourly average background sound levels between the different sets of survey
data. Some of these differences are simply due to statistical variation. The differences may also
reflect small changes in road traffic or to some extent aircraft ground operations in particular areas
around the Airport where the infrastructure has changed since 1999. However, there is no
consistent pattern overall, suggesting that there has not been any systematic or overall change in
background noise sound levels when looking at the area as a whole since 1999.
13.4 Assessment 13.4.1 None of the North Terminal Development Projects require any major earthworks, and as all of the
general building works would be carried out at considerable distances from the nearest noise
sensitive receivers outside the Airport boundary, it is not expected that there would be any
significant construction noise effects. Contractors would be required to produce and comply with
a Construction Environmental Management Plan for the day-to-day limitation and management of
any minor construction noise problems arising.
13.4.2 The assessment of aircraft taxiing and Auxiliary Power Unit noise sound levels during operation
shows small and mostly negligible differences in those receptors experiencing minor, moderate,
and major adverse effects (as calculated according to the adopted criteria) between the base and
development cases in 2019. These differences are attributable to small differences in the forecast
total numbers of arrivals and departures at both the North and South Terminals at different times
9 Included in the planning application documents.
32
of the day and night, which in turn leads to small differences in the total numbers of aircraft ground
operations on different parts of the Airport.
13.4.3 The assessment of road traffic noise shows that the proportional differences in road traffic flows
between the base and development cases in 2019 are not large enough to produce any significant
difference in road traffic noise effects between the two cases.
13.5 Mitigation 13.5.1 Any construction noise effects arising
during the course of the works would
be managed under the provisions of
the Construction Environmental
Management Plans which all
contractors would be required to
produce.
13.5.2 Aircraft ground noise is managed
under Managing Director's
Instructions which impose specific
restrictions on aircraft operators to
minimise unecessary running of
aircraft engines and Auxiliary Power
Units while on the ground. The
taxiway layout is designed to minimise
taxiway delays as much as possible, and this helps to keep taxiing noise down. Fixed Electrical
Ground Power is provided on all aircraft parking stands to substitute for aircraft mounted Auxiliary
Power Units or mobile Ground Power Units whenever possible.
13.5.3 A new Gatwick Airport Noise Insulation Scheme has just opened offering a range of noise
insulation options to 1,183 eligible households in different directions around the Airport.
13.6 Residual Assessment 13.6.1 For ground noise, the residual effects remain as identified in the Assessment section.
33
14 Landscape and Visual
14.1 Introduction and Methodology 14.1.1 The assessment of likely
significant landscape and visual
effects has involved a study of
existing landscape character,
identification of key viewpoints
for the proposed development
and an assessment of the
sensitivity of such views.
Landscape effects may be
defined as changes to landscape
elements, characteristics,
character, and qualities of the
landscape as a result of
development. Visual effects
relate to the changes that arise in the composition of views as a result of changes to the
landscape, to people’s responses to the changes, and to the overall effects with respect to visual
amenity.
14.1.2 The assessment has been carried out in accordance with best practice guidance recommended,
amongst others, by the Landscape Institute and Institute of Environmental Assessment10.
14.2 Baseline 14.2.1 The baseline study considered the quality, value and sensitivity of the existing landscape, the
nature and sensitivity of existing views, and the existing visual amenity of local residents and other
sensitive receptors, both at night and during the day.
14.2.2 Gatwick Airport comprises an intensively developed area of flat, open, low-lying land within a
broad river valley. It is located within the undulating countryside of the Low Weald, which is
interrupted by the extensive built-up areas of Horley to the north and Crawley to the south.
Existing views of the Airport may be obtained by walkers, horse-riders, motorists and residents.
Open, far-distance views of the Airport may be obtained from elevated land to the west and north-
west. The Airport is seen as a slither of built development in these views, seen against a
backdrop of distant hills (refer to the photograph above showing an elevated view of the Airport
from Norwood Hill Road).
14.2.3 Near-distance views of Airport structures are filtered and enclosed, in many cases, by tree and
shrub belts and/or earth bunds along the peripheries of the Airport. Near-distance unobstructed
views of the Airport are rare, and have been identified only in the vicinity of the Airport access
road/roundabout to the north-east of the Terminal. In a small number of cases where views are
unobstructed, their character is already dominated, or at least strongly influenced, by Airport
buildings, lighting and traffic/aircraft movements.
14.3 Assessment 14.3.1 Existing vegetation and earth bunding along the Airport periphery would substantially enclose
most external ground-level views of the construction works, including views from the rural
landscapes to the west and north-west. The construction works would not result in any significant
adverse effects on external views, including distant elevated views, or on the character of the
landscapes beyond the boundary of the Airport.
14.3.2 Open views of the North Terminal extension and multi-storey car park 6 would be obtained from
the Airport access road/roundabout to the north-east of the Terminal. The proposed development
would not alter the character of these views, or their amenity value, to a fundamental degree. The
development is also unlikely to result in any real change to the amenity of other existing views.
10 The Institute of Environmental Assessment and Landscape Institute (2002) Guidelines for Landscape and Visual Impact
Assessment, 2nd Edition; Spon Press; London.
34
Where available from low-lying ground around the Airport, these views would be mostly limited to
highly filtered winter views, seen through existing tree and shrub planting along the periphery of
the Airport, with only very occasional glimpsed views of the upper parts of the additional long-stay
decked car parks and associated lighting columns. Lighting emanating from the columns on the
proposed additional long-stay car parking would be seen in the context of sky-glow from existing
Airport lighting sources and the occasional, highly filtered direct views of existing lighting sources,
which may be seen through peripheral Airport tree and shrub vegetation. The proposed
development, including new artificial lighting would not have any significant effect on these
existing views.
14.3.3 The completed development would represent an expansion of features which are already
characteristic of the Gatwick Airport landscape. The proposed buildings would be confined to the
existing built footprint of the Airport and would not exceed the prevailing height of existing
structures. The North Terminal extension and multi-storey car park 6 would reinforce the existing
cluster of relatively large-scale buildings around the North Terminal. The reconfigured piers and
the additional long-stay car parking would be seen in the context of the existing airfield structures
and the already permitted North West Zone development. Additionally, the completed
development would not change the fundamental character of the existing settings of the
Charlwood Conservation Area and listed buildings.
14.4 Mitigation 14.4.1 A series of measures to reduce significant adverse construction effects are set out in the
Construction Environmental Management Plan and include topsoil storage, and use of directional
lighting to control spillage from security lighting.
14.4.2 In order to mitigate operational effects of light spillage on existing views from the ‘dark skies’ rural
landscape to the west and north-west, lighting at the two additional long-stay car parking areas
would have back-shields fitted to the inside of each light to prevent up-lighting, and would be
positioned in the centre of the car park, rather than the outside edges. These measures would be
sufficient to prevent any additional light spillage into the adjacent ‘dark skies’ landscape, above
and beyond the current levels.
14.5 Residual Assessment 14.5.1 The implementation of measures to control spillage from artificial light would further reduce the
level of effects, which would not be significant, with or without this mitigation.
35
15 Transport
15.1 Introduction 15.1.1 The likely surface access transport effects have been assessed for the construction and operation
of the North Terminal Development Projects, that is, the changes in the levels of road congestion,
delays and public transport travel conditions.
15.2 Methodology 15.2.1 The methodology for the assessment of surface transport effects has been guided by relevant
transport policies and guidance.
15.2.2 To assess the transport effects during construction, the traffic predicted to be generated by the
construction of the North Terminal Development Projects is compared to forecast base case traffic
flows across the local road network. Guidance published by the Institute of Environmental
Assessment11 has been used to assess the significance of the calculated traffic changes on
individual road links.
15.2.3 Transport effects during the operation of the North Terminal Development Projects have been
determined by comparing modelled scenarios with and without the Projects in 2019. In addition,
effects have been identified in 2026 in line with the South East Plan housing forecasts.
15.2.4 A suite of traffic models have been developed as the basis for forecasting future growth in general
traffic, and traffic directly associated with the Airport. Forecasts of demand drivers such as future
levels of households, population and employment in the region (and in the rest of the country) and
of future Airport passengers and employees have been used to develop forecasts of future travel
demand and the effects on the public transport and highway networks.
15.2.5 It is noted that the future year base case scenarios include junction improvements at the North
Terminal Roundabout, M23 Junction 9A and the Beehive Roundabout to increase capacity at
these junctions that are currently suffering congestion due background traffic volumes. These
junction improvement schemes are assumed to be operational in both the base and development
case scenarios as they are schemes that are being brought forward regardless of the North
Terminal Development Projects.
15.2.6 The effect of the North Terminal Development Projects on public transport has also been
assessed to determine whether any effects can be accommodated within the existing services.
15.3 Baseline 15.3.1 There are three main points of access to the Airport from the strategic road network; the North
Terminal Roundabout and the two roundabouts off the M23 link, which provide access to both the
South and North Terminals. The M23 is managed by the Highways Agency and North Terminal
Roundabout is managed by West Sussex County Council as the local highway authority.
15.3.2 Gatwick Airport is served by a railway station situated at South Terminal. The station concourse
and platforms are owned and operated by Network Rail. Six train operators run services from
Gatwick Airport, providing links to destinations across the UK. The Gatwick Airport Surface
Access Strategy (2007) states that there are 950 trains serving Gatwick Airport every day.
15.3.3 Daily coach services connect Gatwick to more than 400 UK towns and cities. Direct services run
to destinations including Heathrow, central London, Bristol, Brighton, Birmingham,
Oxford, Cambridge and Norwich.
15.3.4 The principal pedestrian and cycle access to the Airport is via National Cycle Route 21, which
passes through the Airport site on a north–south axis and which links into local networks in
Crawley and Horley. Povey Cross Bridge provides additional access to the Airport and is
convenient for staff living in and around Charlwood and Hookwood, and from the Balcombe Road
for residential areas to the east of the Airport.
11 Institute of Environmental Assessment (1993) Guidelines for the Environmental Assessment of Road Traffic.
36
15.4 Assessment 15.4.1 Transport modelling results suggest that all junctions operate within capacity in 2019 and 2026,
with the exception of Junction 9 where the background traffic causes the junction to slightly
exceed capacity in the AM peak period. When comparing the 2019 base case and development
cases for all junctions the results shows that the North Terminal Development Projects only
increase traffic levels slightly on the existing local network.
15.4.2 The main construction traffic effects are the increase in HGV traffic during the PM peak. This is
due to the low numbers of existing HGVs traffic on the network at this time. Therefore although
the actual numbers of construction HGVs are relatively low, this results in a higher percentage on
some road links. Despite the higher percentage of HGVs there would not be a significant effect in
terms of traffic congestion, queue lengths and journey times due to the low numbers.
15.4.3 With regard to the analysis of the capacity of the public transport services operating at the Airport,
this showed that the public transport services are capable of absorbing an increase in patronage
on existing services, as well as being able provide additional services.
15.5 Mitigation 15.5.1 With the junction improvements in place at the North Terminal Roundabout, M23 Junction 9A and
Beehive Roundabout, no additional highways mitigation is required as a result of the North
Terminal Development
Projects.
15.5.2 To reduce the effects of
construction traffic, a
number of measures would
be built into the
Construction Environmental
Management Plan which
would be used to define the
methodology during the
construction period. This
would include controlling
site deliveries to avoid peak traffic periods, night working and other standard practices.
15.6 Residual Assessment 15.6.1 The modelling results show that all scenarios operate within capacity in the 2019 and 2026
scenarios with the exception of Junction 9 which slightly exceeds capacity during the AM peak
period in 2019 and 2026. However, this is as a result of background growth and not the North
Terminal Development Projects.
15.6.2 No significant residual effects are identified for the construction.
37
16 Waste
16.1 Introduction 16.1.1 The principles of the waste hierarchy and circular product life-cycle (illustrated below) have been
considered during the design process of the North Terminal Development Projects to prevent
waste generation and to find opportunities for re-use of materials on-site.
16.1.2 The principles of the waste hierarchy have also been addressed as part of the existing operational
waste management at Gatwick Airport, which has an on-site composting facility to manage green
waste generated around the Airport complex. Waste that cannot be prevented or re-used on-site
would require off-site treatment or disposal to enable the waste to be managed in such a way that
would not cause harm to the environment, human health or amenity.
16.1.3 Whilst all forms of waste management have the potential to adversely affect the environment,
those associated with landfill are considered to be of greater significance than those associated
with other forms of waste management such as recycling and composting.
16.1.4 The purpose of the waste assessment, therefore, is to establish the likely significant
environmental effects of the disposal by landfill of solid waste that would be generated by the
construction and operation of the North Terminal Development Projects.
16.2 Methodology 16.2.1 The amount of solid waste requiring off-site management has been quantified using empirical
waste generation rates and information provided by Gatwick Airport Limited. The proportion of the
waste that would require landfill disposal has been determined on the basis that 85% of
construction waste and 70% of operational waste would be diverted from landfill by recycling and
composting in line with BAA’s corporate waste management targets.
16.2.2 The criteria used to determine the significance of the predicted landfill disposal requirement is
based on professional judgement, taking into account the amount of waste that would require
landfill disposal and the capacity of landfill predicted to be available in West Sussex and the South
East of England during:
• the period 2009 to 2011 for the assessment of construction waste, in line with the proposed
construction programme; and
• in 2019 for the assessment of operational waste, the year in which an additional four million
passengers is expected to pass through Gatwick Airport as a result of the new facilities
provided by the North Terminal Development Projects.
16.2.3 The assessment has also considered the effect of varying rates of recycling and composting for
operational waste and the effect of the cumulative quantity of waste that would be generated by
construction of the North Terminal Development Projects and other major development projects
planned for Gatwick Airport.
38
16.3 Baseline 16.3.1 In 2008, Gatwick Airport generated an estimated
16,319 tonnes of operational waste, managed by
BAA’s waste management contractor (Grundon) and
other independent waste contractors, of which 24%
was recycled and composted. This is likely to
increase to 18,207 tonnes in 2019, based on an
average 1% increase per year in the quantity of
waste generated by businesses and industry in West
Sussex.
16.3.2 The quantity of waste generated by on-site
construction activities at Gatwick Airport varies each
year due to the different types and numbers of
construction activities that are undertaken.
16.3.3 Future waste arisings and landfill disposal capacity
has been identified through a desk-based review of
publicly available sources of information. This
information shows that:
• Construction waste arisings in West Sussex and
the South East of England are projected to be
4,017,000 tonnes and 36,402,000 tonnes
respectively during the period 2009 to 2011. Whilst there is likely to be a deficit of landfill
capacity West Sussex, sufficient capacity would be available in the South East of England.
• In 2019, waste from businesses in West Sussex and the South East of England is likely to
amount to 859,000 tonnes and 10,614,000 tonnes respectively but there is a projected deficit
of landfill capacity in both West Sussex and the South East of England for this year.
16.4 Assessment 16.4.1 Waste generated by the construction and operation of the North Terminal Development Projects
would have an adverse impact in terms of further increasing the quantity of waste to be managed
using landfill disposal in West Sussex and the South East of England during the period 2009 to
2011 and in 2019.
16.4.2 In 2009 to 2011, it has been estimated that the North Terminal Development Projects would
generate 72,746 tonnes of construction waste, of which 10,912 tonnes (15%) would require landfill
disposal. The likely significant environmental effects would be minor adverse due to a predicted
deficit of space in West Sussex and further depletion of available space in the South East of
England.
16.4.3 In 2019, an additional 2,040 tonnes of waste would be generated as a result of the operation of
the North Terminal Development Projects, of which 612 tonnes (30%) would require landfill
disposal. The likely significant environmental effects would be minor adverse due to a deficit of
landfill space in both West Sussex and the South East of England.
16.5 Mitigation and Residual Assessment 16.5.1 No additional mitigation or offsetting measures have been proposed at this stage although the use
of construction waste resource efficiency tools may help to identify further opportunities for on-site
re-use of construction waste materials, thereby reducing the quantity of waste requiring off-site
treatment and disposal. As such, the residual environmental effects would be as identified for the
initial assessment, which has already considered environmental design and waste management
measures agreed during the design phase.
16.5.2 Enhancement opportunities are suggested including the use of construction waste resource
efficiency tools and on-site composting of food waste generated at Gatwick Airport.
39
17 Water
17.1 Introduction 17.1.1 The assessment of the likely significant effects of the North Terminal Development Projects on the
water environment encompasses the ‘natural waters’ such as surface water (channels, flow, flood
risk and quality) and groundwater (its availability and water quality); and ‘Airport waters’, that is,
the man made aspects of drainage, water supply, use and discharge.
17.2 Methodology 17.2.1 The existing (baseline) conditions have been established using a combination of desk based
studies and site visits. The assessment used a combination of recognised good practice,
established standards, and professional judgement to determine the importance of the water
environment at Gatwick Airport and the changes that would be brought about by the construction
of the North Terminal Development Projects. The project team held consultation meetings
seeking advice and feedback from the Environment Agency and other interest groups.
Consultation was also held with a wide range of interested parties during a Scoping Workshop in
January 2009.
17.2.2 Results of previous hydrologic modelling have been used as part of the Flood Risk Assessment
prepared for the development. The Flood Risk Assessment included the existing flood risk and
the projected future flood risk with the North Terminal Development Projects in place.
17.2.3 An assessment of cumulative effects has been made, as well as the identification of appropriate
mitigation measures to minimise potential effects.
17.3 Baseline 17.3.1 The North Terminal Development Projects cover various locations within Gatwick Airport. Surface
drainage from the area surrounding the North Terminal drains to Balancing Pond D (shown in the
below photograph). Clean water from Pond D discharges to the River Mole to the north of the
Airport. In addition, the Gatwick Stream borders the eastern edge of the Airport. The River Mole
has good flow and water quality and supports a wide range of fish; such as carp, roach and
gudgeon. The Gatwick Stream skirts the town of Crawley, and flows northwards from its source on
the Tunbridge Wells Sands, meeting the River Mole south of Horley (just downstream of the
Airport).
17.3.2 Hydraulic modelling of
baseline conditions
shows that the area
around North Terminal is
within Flood Zone 3. This
means that it has a 1%,
or 1 in 100 year, risk of
flooding each year,
caused by the Gatwick
Stream overflowing its
banks. In addition, all of
the sites for the North
Terminal Development
Projects are a risk of
flooding from surface
run-off.
17.3.3 The area around Gatwick Airport is underlain by Weald Clay and is classified as unproductive for
groundwater abstraction. The nearest aquifers are five kilometres to the south-east and nine
kilometres north of the site. There are no groundwater or surface water abstractions within two
kilometres of the site. The management of the River Mole catchment has been integrated within
40
the Thames Corridor Abstraction Management Strategy12 and has been categorised as ‘no water
available’.
17.3.4 Potable water is supplied by Sutton and East Surrey Water Ltd and the current potable water
consumption at Gatwick Airport is approximately 1,000 mega litres per year. Foul water is treated
by Thames Water Utilities Limited at Crawley Wastewater Treatment Works. The existing surface
water drainage system at Gatwick Airport comprises ten drainage areas. Three of these areas
drain directly into the River Mole and other nearby watercourses. The run-off from the other
seven drainage areas is diverted to existing balancing ponds before discharge to surface
watercourses. The Pond D drainage area and balancing pond has a water quality monitoring
device to allow clean discharge to the River Mole or discharge of contaminated water to Crawley
Wastewater Treatment Works. This is because the drainage from this area covers most of
Gatwick Airport’s runway, taxi and stand areas and as a result contains higher levels of
contaminated run-off.
17.4 Assessment 17.4.1 The design of the North Terminal Development Projects has aimed to avoid or reduce effects on
the water environment. During construction (2009-2011), a range of pollution prevention
measures would be applied to protect the water environment.
17.4.2 Assuming it is water tight, the North Terminal extension has the potential to cause minor
displacement of fluvial flood water during flood events. The North Terminal Development Projects
would result in minimal increases in areas of hardstanding, and are therefore not anticipated to
significantly affect surface run-off volumes.
17.4.3 Following the application of such measures, the main effects that may occur during construction
are minor adverse effects upon the function of the surface drainage system due to additional
sediment and pollution sources arising from the works. There are not anticipated to be any
significant effects upon the water environment during operation of the projects.
17.4.4 The assessment considered cumulative effects on the water environment which could arise
through a combination of other developments in the area as well as interactive effects of the North
Terminal Development Projects upon other aspects of the environment. No changes to the
assessment presented above were identified in relation to cumulative effects.
17.5 Mitigation 17.5.1 Measures to avoid or reduce
effects have been included
within the design, and an
Construction Environmental
Management Plan has been
produced for use during
construction. Additional
measures have also been
identified to further reduce any
remaining effects.
17.5.2 As displacement for any
displacement of fluvial flood
waters, the ground levels in
multi-storey car park 6 would be levelled to their lowest point (on average by 300mm) to provide
like for like compensation for displacement of flood waters from the North Terminal extension and
ensure no increase in flood risks. Gatwick Airport Limited is also contributing to the Upper Mole
Flood Alleviation Scheme, which will result in a significant reduction in flood risk across the Airport.
17.5.3 To reduce rates of surface run-off, oversized drainage pipes with flow restriction would be used to
store run-off and release it at controlled rates into the existing drainage system.
12 Environment Agency (2004) Thames Corridor Abstraction Management Strategy, http://publications.environment-
agency.gov.uk/pdf/GETH0604BHZE-e-e.pdf?lang=_e , accessed April 2009.
41
17.5.4 During operation, river water quality would be regularly monitored at set points to ensure the
surrounding watercourses are not being subjected to adverse pollution.
17.6 Residual Assessment 17.6.1 Most of the effects described above can be avoided by design and mitigation measures.
Nevertheless, during construction there is potential for minor adverse effects on the drainage
function of Balancing Pond D due to additional sediment and pollution sources. Once operational,
it is anticipated that the North Terminal Development Projects would have negligible or no effect
upon the water environment.
43
18 Where to find a copy of the Environmental Statement 18.1.1 All of the planning submission material including the Environmental Statement for the North Terminal
Development Projects is available for inspection at the following location:
Crawley Borough Council
Town Hall
The Boulevard
Crawley
West Sussex
RH10 1UZ
Telephone: 01293 438 000
18.1.2 Copies of the Environmental Statement and other documents are available by contacting the Gatwick Airport
Strategy and Planning department at Gatwick Airport on [email protected]. A
reasonable charge will be made to cover the costs of printing and distribution.
18.1.3 Electronic copies of the Environmental Statement on a CD are available free of charge.
For further information contact:
Amanda Kuffel T +44 (0)20 7755 4466 E [email protected]
www.arup.com BAA GatwickLondon