Non Disruptive Road Crossings-1 DOT

download Non Disruptive Road Crossings-1 DOT

of 117

Transcript of Non Disruptive Road Crossings-1 DOT

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    1/117

     

    NON DISRUPTIVE ROAD CROSSINGS

    MANUAL

    DRAFT DOCUMENT 

    J ANUARY 2013

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    2/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page i January 2013

    January 2013

    Draft Edition

    Abu Dhabi Department of Transport

    Al Bateen Towers

    PO Box 20

    Abu Dhabi, United Arab Emirates

    © Copyright 2012, by the Abu Dhabi Department of Transport. All Rights Reserved. This

    manual, or parts thereof, may not be reproduced in any form without written permission of

    the publisher.

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    3/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page ii January 2013

    TABLE OF CONTENTS 

    List of Figures .................................................................................................................................. v 

    List of Tables .................................................................................................................................. vi 

    1  Introduction .............................................................................................................................. 7 

    1.1  Overview ............................................................................................................................. 7 

    1.2  Purpose and scope .............................................................................................................. 7 

    1.3   Application of this manual .................................................................................................... 7 

    2  Non Disruptive Road Crossings Methods .............................................................................. 8 

    2.1  Non-steerable soil displacement methods ........................................................................... 8 

    2.2  Non-steerable soil removal methods.................................................................................... 9 

    2.3  Horizontal directional drilling (HDD) ................................................................................... 11 

    2.4  Micro tunnelling ................................................................................................................. 13 

    2.5  Pilot pipe jacking ............................................................................................................... 15 

    2.6  Manned pipe jacking methods ........................................................................................... 16 

    2.6.1  Open front pipe jacking techniques ..................... ........... ........... .................................. 16 

    2.6.2  Closed front (full face excavation) pipe jacking techniques ......................................... 17 

    2.7  New NDRC Techniques..................................................................................................... 19 

    2.7.1  Easy Pipe ................................................................................................................... 19 

    2.7.2  Direct Pipe .................................................................................................................. 20 

    3  General .................................................................................................................................... 22 

    3.1  Overview ........................................................................................................................... 22 

    3.2  Standards and Codes of Practice ...................................................................................... 22 

    3.3  Roles and responsibilities .................................................................................................. 22 

    3.3.1  Client .......................................................................................................................... 23 

    3.3.2  Consultant .................................................................................................................. 23 

    3.3.3  Contractor/Sub Contractor .......................................................................................... 23 

    3.3.4  Road Authority ............................................................................................................ 23 3.3.5   Abu Dhabi Town Planning ........... ........... ............ ........... ........... .................................. 23 

    3.3.6  Utility Agencies ........................................................................................................... 23 

    3.4  Process Map ..................................................................................................................... 23 

    3.5  Health and Safety .............................................................................................................. 26 

    3.5.1   At Concept Stage ............................ ....................................................................... .... 26 

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    4/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page iii January 2013

    3.5.2  Preliminary Design Stage ........................................................................................... 26 

    3.5.3   At Pre-Construction Stage ........... .................................................. ........... .................. 27 

    3.5.4  During Construction Stage .......................................................................................... 27 

    3.6  Environmental requirements .............................................................................................. 30 

    3.7  Site condition survey ......................................................................................................... 31 

    3.8  Geotechnical Investigation .................................................................... ............................. 32 

    3.8.1  Minimum requirements of the exploratory boreholes .................................................. 33 

    3.8.2  Borehole Positions...................................................................................................... 33 

    4  Procedures for undertaking non disruptive road crossings ............................................... 35 

    4.1  Overview ........................................................................................................................... 35 

    4.2  Concept Stage ................................................................................................................... 35 

    4.3  Preliminary Design Procedures ......................................................................................... 35 

    4.3.1  Method selection ........................................................................................................ 35 

    4.3.2  Design drawings ......................................................................................................... 58 

    4.3.3  Hand excavation ......................................................................................................... 59 

    4.4  Pre-construction stage ....................................................................................................... 59 

    4.4.1  Design calculations..................................................................................................... 59 

    4.4.2  Design drawings ......................................................................................................... 60 

    4.4.3  Ground Surface Movement ......................................................................................... 60 

    4.4.4  Groundwater Control .................................................................................................. 77 

    4.4.5  Materials and equipment ............................................................................................ 77 

    4.4.6  Method of statements ................................................................................................. 78 

    4.4.7  Risk Assessment and Risk Register ........................................................................... 80 

    4.4.8  Procedure and logistics for obtaining No Objection Certificates .................................. 81 

    4.5  During Construction ........................................................................................................... 81 

    4.5.1  Monitoring of Surface Movement ................................................................................ 81 

    4.5.2  Instrumentation Requirements .................................................................................... 83 

    4.5.3  Equipment Performance Requirements ...................................................................... 84 

    4.6   After Construction ............................. ................................................................................. 85 4.6.1  Inspection and testing ................................................................................................. 85 

    4.6.2  Site clearance and decommissioning ......................................................................... 86 

    4.6.3  Monitoring/inspection for long term (latent) defects .................................................... 86 

    4.6.4  QA/ QC Methodology ................................................................................................. 86 

    Appendix A: Checklists for submittals ........................................................................................ 88 

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    5/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page iv January 2013

    Appendix B: Forms and examples of letters for applying for NDRC works .............................. 92 

    Appendix C: Suggested minimum safe distances between utilities .................... ........... ......... 106 

    Appendix D: Checklists for monitoring during and after construction .......... ........... .............. 107 

    Cited References ......................................................................................................................... 112 

    Other References ......................................................................................................................... 113 

    Glossary ....................................................................................................................................... 114 

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    6/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page v January 2013

    LIST OF FIGURES 

    Figure 1: Impact moling/soil displacement hammer ........................................................................... 8  

    Figure 2: Pipe ramming diagram (Earth Tool Company, LLC) ................................................. ........... 8 

    Figure 3: Impact moling ..................................................................................................................... 9 

    Figure 4: Auger head ....................................................................................................................... 10 

    Figure 5: Auger boring ..................................................................................................................... 10 

    Figure 6: Process of the horizontal directional drilling (HDD) ........................................................... 12 

    Figure 7: Micro tunnelling ................................................................................................................ 13 

    Figure 8: Slurry shield micro tunnelling (Iseki Poly-Tech, Inc.-japan) ............................................... 14 

    Figure 9: Stages of pilot pipe jacking with auger soil removal .......................................................... 15  

    Figure 10: Backactor shield ............................................................................................................. 16 

    Figure 11: A cutter boom shield ....................................................................................................... 17 

    Figure 12: Open front pipe jacking ................................................................................................... 17 Figure 13: A slurry shield (full face excavation) pipe jacking machine ................... ........................... 18 

    Figure 14: Earth Pressure Balance Machine (EPBM) ...................................................................... 18 

    Figure 15: Easy pipe Method ........................................................................................................... 20 

    Figure 16: Direct Pipe Method ......................................................................................................... 21 

    Figure 17: Process map of NDRC.................................................................................................... 25 

    Figure 18: Pipe jacking worksite and shaft ....................................................................................... 26 

    Figure 19: The different cutting heads ............................................................................................. 39 

    Figure 20: Principles of a hydraulic mucking boring machine (Herrenknecht documents) ................ 40 

    Figure 21: Locating systems ............................................................................................................ 45 

    Figure 22: Basic components of rig ......................................................... ......................................... 46 

    Figure 23: Slanted face Drill Bits ...................................................................................................... 49 Figure 24: Modified Slanted face Drill Bits ....................................................................................... 49 

    Figure 25: Modified Slanted face Drill Bits ....................................................................................... 50 

    Figure 26: Rock Drill Bits ................................................................................................................. 50 

    Figure 27: Tri-Cone Rock Bits .......................................................................................................... 51 

    Figure 28: Experience guidelines for the application of different NDRC methods ............................. 55 

    Figure 29: Working shafts ................................................................................................................ 56 

    Figure 30: Stability Vs Volume Loss ................................................................................................ 66  

    Figure 31: Typical Settlement Profile for a Soft Ground Tunneling ................................................... 70 

    Figure 32: Assumptions for width of settlement trough (adapted from Peck, 1969) .......................... 71 

    Figure 33: Example of Finite Element Settlement Analysis for Twin Circular Tunnels under Pile

    Foundations ..................................................................................................................................... 72 

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    7/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page vi January 2013

    LIST OF TABLES 

    Table 1: Parameters to be considered in relation to each soil type .................................................. 34 

    Table 2: NDRC methods related to soil types .................................................................................. 37 

    Table 3: Different applications of NDRC .......................................................................................... 38 

    Table 4: NDRC methods with typical pipe size, length and accuracy .................... ........................... 42 

    Table 5: Rigs types and specification ............................................................................................... 47 

    Table 6: Drill Bit Types and Application Guidelines (Courtesy DCCA) ............................................. 48  

    Table 7: Operational risks in HDD installations (Baumert and Allouche 2003) ................................. 54 

    Table 8: Design of working shafts in Dry ground .............................................................................. 56 

    Table 9: Design of working shafts in wet ground .............................................................................. 57 

    Table 10: Shaft Dimensions ............................................................................................................. 58 

    Table 11: Shaft sizes ....................................................................................................................... 58 

    Table 12: Relationship between Volumes Loss and Construction Practice and Ground Conditions . 68 Table 13: Risk summary for typical NDRC methods ........................................................................ 80  

    Table 14: Type of records for NDRC projects .................................................................................. 83 

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    8/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page 7 January 2013

    1 INTRODUCTION

    1.1  OverviewIn 2010, the Abu Dhabi Department of Transport commenced with the “Unifying and Standardizing of

    Road Engineering Practices” Project. The objective of the project was to enhance the management,

    planning, design, construction, maintenance and operation of all roads and related infrastructures in

    the Emirate and ensure a safe and uniform operational and structural capacity throughout the road

    network.

    To achieve this objective a set of standards, specifications, guidelines and manuals were developed

    in consultation with all relevant authorities in the Abu Dhabi Emirate including the Department of

    Municipal Affairs (DMA) and Urban Planning Council (UPC). In future, all authorities or agencies

    involved in roads and road infrastructures in the Emirate shall exercise their functions and

    responsibilities in accordance with these documents. The purpose, scope and applicability of each

    document are clearly indicated in each document.

    It is recognized that there are already published documents with similar objectives and contents

    prepared by other authorities. Such related publications are mentioned in each new document and

    are being superseded by the publication of the new document, except in cases where previously

    published documents are recognized and referenced in the new document. 

    1.2  Purpose and scopeThe purpose of this Manual is to provide specific procedural guidance on Non Disruptive Road

    Crossings (NDRC) for staff of the Abu Dhabi Department of Transport and other concerned

    government highway agencies (Municipalities), designers, Contractors and utility agencies.

    However, due to the specific technical nature of this type of construction, the Manual also providesguidelines for the specialized Contractors experienced in the utilization of plant and equipment

    fabrication, in order to select the most appropriate method for such operations.

    The Manual is specifically aimed at recognizing local conditions related to the present legal

    framework, existing geotechnical conditions and practices presently employed by the local

    construction industry which perform successfully. However, global best practices are studied and

    improvements recommended as appropriate.

    The overall objective of this Manual is to provide guidelines for the construction of NDRC which do

    not result in either short term or long term surface movement, nor in road collapse due to drilling

    mistakes or obstacles.

    1.3  Application of this manualThe Manual is intended for use by the Abu Dhabi Department of Transport and other road agencies

    of the Emirate (Municipalities) in specifying the requirements and approval procedures for NDRC

    work.

    It is however also to be used by utility agencies, designers and Contractors in selection and design

    of NDRCs.

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    9/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page 8 January 2013

    2 NON DISRUPTIVE ROAD CROSSINGS METHODSIn this Chapter more detailed information is given on various methods of NDRC.

    2.1  Non-steerable soil displacement methods A number of soil displacement methods exist. Impact moling or sometimes called soil displacement

    hammer is one of the more common methods. The method involves driving a moling or hammering

    tool with a tapered head through the ground (see Figure 1). The hammering tool can either work with

    compressed air or hydraulically and it displaces the soil as it moves through the ground.

    The piping or cable material is either pushed directly behind the tool or, in stable soil conditions it

    may be pulled in afterwards through the cavity made by the tool.

    Pipe ramming with a closed pipe is another soil displacement method often used. Like impact moling

    or soil displacement hammer it uses compressed air or hydraulically activated ramming device to

    push a closed steel pipe through the soil (see Figure 2).

    Figure 1: Impact moling/soil displacement hammer

    Figure 2: Pipe ramming diagram (Earth Tool Company, LLC)

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    10/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page 9 January 2013

     Advantages and disadvantages of the non-steerable soil displacement technique are briefly set out

    below.

     Advantages 

    •  Generally very quick and easy to use and thereby also very cost effective. Moles orhammering tools are available for many soil conditions and can penetrate soft rock.

    •  The methods require relatively small entry and exit pits. When installing the pipe or cable

    directly behind the hammering tool, surface settlements are minimised.

    Disadvantages 

    •  The methods require that the soil is displaceable and surface heave may occur if sufficient

    soil cover is not available above the tunnel.

    •  A minimum cover of 10 times the outer pipe or hammer diameter is recommended.

    •  Pipelines installed in this manner are necessarily straight as there is no steering mechanism.

    •  The alignment of the tunnel can be influenced by the soil conditions, especially obstructions

    or stratifications that may alter the direction of the tool or pipe.

    •  Installation of pipelines that require a precise alignment should not be undertaken using non-

    steerable methods.

    •  The poor alignment accuracy also reduces the typical lengths for which the methods are

    appropriate, and safe distances to other structures or utilities must be maintained.

    Figure 3: Impact moling

    2.2  Non-steerable soil removal methods

    Pipe ramming can also be carried out with an open pipe end and thereby without soil displacement.Instead the soil is either removed during the driving of the pipe or afterwards. Soil removal is typically

    undertaken using water jetting, flushing, compressed air or mechanically, for example with an auger.

    These are some points to consider with this method:

    •  With the use of an auger, a cutting head can be attached to the head giving an improved

    method for application in harder soils. Examples of pipe ramming and auger boring are

    shown in Figures 8 and 9.

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    11/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page 10 January 2013

    •  The pipe material is usually a steel casing or sleeve pipe inside which the product pipe or

    cables can be pulled or pushed after soil removal.

    •  Entry and exit pits are required for this method, where the entry pit may need to be very long

    in order to accommodate the pipe and auger sections along with the ramming or jacking

    device.•  Below ground water levels the methods must be used with caution or dewatering must be

    initiated.

    •  Pipe ramming may be achieved if the pipe can be driven completely through before soil

    removal and the soil "plug" inside the pipe is sufficiently stable to withstand the ground water

    pressure while ramming. 

    When auger boring, the auger may become flooded underground water levels giving way for

    excessive soil loss and major surface settlement. Some manufacturers have designed a sluice

    system for the auger to counter this effect.

    Figure 4: Auger head

    Figure 5: Auger boring

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    12/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page 11 January 2013

     Advantages

    •  These methods, like the other non-steerable methods, are generally less expensive than

    similar sized steerable methods due to the need for fewer and simpler equipment and

    machinery.

    •  The method can be used for significantly larger pipe sizes compared to displacement

    techniques (2000 mm diameter or larger). The larger diameter pipelines are typically stiffer

    and less susceptible to altering direction during installation.

    Disadvantages

    •  In swelling or very plastic soils the methods may not be possible.

    •  Pipe ramming cannot be done in rock. However with the use of an auger, a cutting head can

    be attached to the head giving an improved method for application in harder soils.

    •  Loss of face stability when tunnelling below groundwater level can lead to construction

    difficulties and even failure to complete the tunnel. The same difficulties with directional

    control exist as for the non-steerable methods.

    2.3  Horizontal directional drilling (HDD)Horizontal direction drilling is likely to be the most widely used NDRC method, due to the extreme

    versatility in uses. The method can be conducted from the ground surface without the need of deep

    entry and exit shafts.

    •  The installation size can be anywhere from small diameter single cable crossings up to 1200

    mm diameter pipes. Drilling distances can reach as much as 1500-1800 m in a single drill -

    longer drills have been achieved using intersecting methods.

    •  The method requires a HDD rig capable of applying torque and thrust to drill a drilling pipe

    through the ground. A steerable drilling head, specially designed for the soil conditions, is

    situated at the front end of the pipes.

    •  Directly behind the drill head is a probe or transmitter sending signals through the ground.

    These signals can be tracked from the ground surface, thereby determining the position and

    depth of the drill. The direction of the drill can be altered by the asymmetrical steering face of

    the drill head.

    •  After completing the drill, the bore hole is expanded to the required size by attaching reamers

    to the drill pipe and pulling back in one or more steps. The desired pipeline is typically

    attached directly behind the final reamer.

    •  Drilling fluid (typically a bentonite suspension) is continuously pumped into the borehole in

    order to remove the spoils and support the borehole. An example of a HDD setup is shown in

    Figure 6.

    •  The reamer is generally larger than the pipeline being installed creating an overcut or annular

    space surrounding the pipeline through which the soil and drilling fluid mixture can escape.

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    13/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page 12 January 2013

    Figure 6: Process of the horizontal directional drilling (HDD)

     Advantages

    •  The wide size range and the ability to undertake HDD without large entry and exit pits and

    without groundwater lowering are very clear advantages of this method.

    •  The direction of the drill can be altered while drilling making it possible to install a curved

    pipeline. This can be a great advantage when manoeuvring around existing structures or

    other utilities.

    Disadvantages 

    •  The achievable alignment accuracy may be insufficient for pipelines that require high

    precision alignment.

    •  Maximum pipe diameters are limited to about 1200mm.

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    14/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page 13 January 2013

    •  Sudden changes in soil type from say clay to sand can lead to loss of control of fluid

    pressure which in turn can lead to collapse of the soil annulus around the pipe.

    •  In certain situations, the pipe may become stuck leading to loss of the HDD string.

    2.4  Micro tunnellingMicro tunnelling is a name generally associated to unmanned pipe jacking methods for pipes smallerthan 1000 mm diameter. However larger diameter machines and equipment are readily used and it

    would be more appropriate to use the term micro tunnelling for any unmanned pipe jacking using a

    steerable tunnelling machine.

    Figure 7: Micro tunnelling

    In micro tunnelling the pipeline is installed by pushing (jacking) the pipes forward from the starting

    shaft as the tunnelling machine excavates the soil at the front of the pipeline. The excavated soil can

    be removed through the already laid pipes by various methods. Examples of this are auger soil

    removal or slurry shield micro tunnelling as shown in Figures 7 and 8.

    In the auger method the excavated soil is removed mechanically with the continuous line of augers.

    In the slurry shield method the excavated soil is mixed with a bentonite slurry suspension and

    pumped out of the pipeline. After being pumped out the soil is settled or separated from the slurry in

    a tank or separation unit and the slurry is reused.

    When working below ground water levels the auger soil removal may pose the same problems,

    where the auger may flood and give way for excessive soil loss. The slurry shield micro tunnelling

    machine is typically designed with a pressurized bulkhead, where slurry is pumped at a sufficient

    pressure to stabilizes any loose soil and balance ground water pressure.

    The tunnelling machine can be controlled by an operator outside the pipeline. The alignment is

    usually controlled by laser or by gyroscope and water level. The line is typically straight, but using

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    15/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page 14 January 2013

    gyroscope or specialized surveying equipment and short pipe lengths, curved tunnels can be

    constructed.

    Piping materials must be designed to withstand the jacking forces acting on them under installation.

    Concrete is often used as piping material along with fibreglass or composites with concrete and

    fibreglass. Polymer materials especially polymer concretes are becoming more common due to there

    strength and corrosion resistance.

    Figure 8: Slurry shield micro tunnelling (Iseki Poly-Tech, Inc.-japan)

     Advantages 

    •  Micro tunnelling works in almost all soil conditions and cutting heads can be modified to deal

    with weak rocks.

    •  Pipes of up to 2000mm diameter can be installed and can be constructed to a high degree of

    accuracy which makes the technique suitable for pipelines that require precision in alignment

    or gradient.

    Disadvantages

    •  Obstacles (large rocks/boulders or other materials) may stop machines not designed for

    cutting through these materials. In such cases there may be no other solution, than to

    excavate from the surface to remove the obstacle. If this is not possible, the tunnel and

    machine may have to be abandoned.

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    16/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page 15 January 2013

    •  Working in mixed face conditions can be problematic, particularly where slurry support is

    used below groundwater as the slurry pressure may be difficult to control. Loss of slurry/face

    support can lead to instability and ravelling leading to large surface settlements and, in the

    extreme case, abandonment of the pipe and machine.

      Micro tunnelling is generally more expensive than many of the other NDRC methods,requiring relatively large entry and exit shafts and more advanced equipment and materials.

    2.5  Pilot pipe jackingThis method is basically a variation of the non-steerable auger boring method. In this method

    however a steerable pilot pipe is initially jacked or drilled through the soil. The alignment of the pilot

    pipe is controlled by laser and a small camera at the head of the pipe.

     After installing the pilot pipe an open steel pipe with an auger for soil removal is attached to the pilot

    pipe and pushed/jacked through. The steel pipe is usually just used as a sleeve for the product pipe

    which is pulled in afterwards.

    Variations of the method include attaching a reamer followed by a plastic pipeline and pulling thesethrough in a similar manner as HDD.

    Figure 9: Stages of pilot pipe jacking with auger soil removal

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    17/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page 16 January 2013

     Advantages 

    •  The method is very accurate (unlike the non-steerable auger boring method). The pilot pipe

    can generally be installed to an accuracy of +/- 20 mm and the steel sleeve pipe will typically

    follow this line with litt le deviation.

    •  The technique is a relatively cheap method of achieving a pipeline to a high precision in

    alignment and gradient.

    Disadvantages

    •  Large rocks or differences in soil structure surrounding the pilot pipe can give problems.

    •  Ground water may give some of the same problems described in sections on non-steerable

    auger boring and micro tunnelling.

    2.6  Manned pipe jacking methodsManned pipe jacking methods are very similar to the techniques given as micro tunnelling – the

    difference is basically that the manned methods are sufficiently large in diameter to accommodateworkers inside the pipeline.

     A wide range of tunnelling machines designed for varying types of soil and groundwater conditions

    exist. The machines can generally be divided into open or closed face machines – the selection is

    dependent on the soil conditions and the required support necessary for stability of the soil.

    2.6.1 Open front pipe jacking techniquesOpen faced pipe jacking can be done in stable soil conditions with little or no ground water inflow.

    The method consists of a tunnelling machine with an open front, where soil is excavated

    mechanically and transported with conveyor belt and/or buckets out of the pipeline. Examples of

    open front pipe jacking are shown in Figure 10 and Figure 11.

    Figure 10: Backactor shield

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    18/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page 17 January 2013

    Figure 11: A cutter boom shield

    Figure 12: Open front pipe jacking

    Working below ground water levels, pressure may be applied to the front using a chamber lock

    system as shown in Figure 12. The pressurized front allows excavation without losing soil stability

    due to ground water infiltration. This will generally only work in cohesive soils or rock - in very loose

    soils, an open front is very questionable.

    2.6.2 Closed front (full face excavation) pipe jacking techniquesIn loose soils or conditions with high ground water levels, a closed front machine may be used.

    Closed front machines can be of the slurry shield type as described in Section 4.5 on micro

    tunnelling or alternatively an earth pressure balance machine.

    The slurry shield tunnelling machine works as described previously with a bentonite slurry

    suspension that is mixed with the excavated soil and pumped out of the pipeline. An example of thistype of machine is shown in Figure 16.

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    19/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page 18 January 2013

    Figure 13: A slurry shield (full face excavation) pipe jacking machine

    Figure 14: Earth Pressure Balance Machine (EPBM)

     Advantages

    •  Manned pipe jacking methods have the general advantage that access to the driving front is

    relatively easy - making it possible to remove obstacles (larger rocks/boulders etc.) with

    manual methods.

    •  Open front machines obviously have the most direct access, where closed front machines

    may need to be designed with access gates.

    Disadvantages

    •  There are many health and safety issues associated with manned pipe jacking, not least the

    need to work in confined spaces with the dangers of face collapse and groundwater

    inundation.

    •  Detailed and robust health and safety procedures dealing specifically with the hazards

    related to this construction method need to be implemented for all manned pipe jacking

    operations.

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    20/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page 19 January 2013

    •  Tunnelling equipment is large and expensive and requires relatively large site areas for the

    launch and reception pits.

    2.7  New NDRC Techniques

    NDRC techniques continue to evolve and new techniques are constantly being trialled andimplemented to overcome some of the disadvantages of conventional techniques or provide faster,

    cheaper installations. Two such techniques are the “Easy Pipe” and the “Direct Pipe” methods

    2.7.1 Easy PipeThis technique combines conventional micro tunnelling with an innovative method of using the

     jacking pipes to help install the permanent pipe. Once the tunnel has been bored, the micro

    tunnelling machine is removed and the permanent pipe is attached to the installed jacking pipes.

    The jacking pipe segments (which are bolted together) are pulled back through the tunnel, pulling the

    permanent pipe with them. In this way, the permanent pipe is installed quickly and easily and the

     jacking pipe segments can be re-used for the next project.

    Easy Pipe installation requires a micro tunnelling unit to be prepared and assembled in the launch

    pit. The cutter head is launched and guided in the conventional micro tunnelling way along a planned

    alignment.

    The difference between the jacking pipes used by Easy Pipe and conventional ones is that the

    special design allows them to be used as jacking pipes in the forward direction while allowing them

    to be retracted from the completed bore to pull in the product pipe.

    This is because the joints between the jacking pipe sections bolt together with a design that will

    withstand thrust and pullback forces of up to 6,300 kN (630 tons).The close proximity of the jacking

    pipes' outer wall to the bore wall also avoids the potential for collapse of the bore in unstable ground

    formations.

     After the cutter head has reached the target pit, it is separated from the jacking pipe string and

    replaced by a specially designed connection pipe that also connects to the product pipe. The jacking

    pipes are then pulled back using the bi-directional jacking frame, simultaneously pulling the product

    pipe into position. In the launch pit the individual jacking pipes are successively removed along with

    all other equipment until the product pipe arrives at the launch shaft.

    The connection pipe and jacking frame are removed from the pit leaving the product pipe in place to

    be finally connected to the remainder of the pipeline on either side of the obstacle(s) crossed.

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    21/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page 20 January 2013

    Figure 15: Easy pipe Method

    2.7.2 Direct PipeThe direct pipe technique is a hybrid of the HDD and micro tunnelling methods. In this technique, the

    micro tunnelling machine is pushed in to the ground using a jacking frame that grabs directly on to

    the final production pipe and uses this to push the micro tunnel machine forward. In this way, once

    the tunnel is bored, there is no need for a secondary production pipe installation process as the

    production pipe is installed directly as part of the tunnelling operation. Installation of the pipe is

    limited by the thrust that can be applied to the pipe without causing damage and the need for

    sufficient space to lay the pipe out behind the micro tunnel machine prior to commencing boring.

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    22/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page 21 January 2013

    Figure 16: Direct Pipe Method

     Advantages 

    •  Single-step method leads to rapid installation of product piping and pipelines

    •  No time needed for coupling pipes (Micro tunneling) or drill rods (HDD)

    •  Pipeline can be installed pre-welded and already tested

    •  Costly shaft construction unnecessary - instead, only simplified surface entry and exit pits are

    required

    •  One-pass work phase of operation for excavation and pipeline installation

      Inclines and gradients as well as curved drilling profiles can be negotiated precisely•  Ideal method for sea outfalls with access from one side only

    •  Pipe Thruster enables both tunneling machine and pipeline to be withdrawn, for example for

    cutting tool retooling operations in inaccessible, low-diameter areas

    •  Cone crusher removes obstacles as they occur

     Application options

    •  Pipeline laying from construction pit to construction pit

    •  Pipeline laying from construction pit to shaft

    •  Pipeline laying from construction pit to destination point, for example water course beds

    Range of application

    •  Pipeline diameter: - 28” - 36” 38” - 44” 46” - 52” 54” - 60”

    •  Excavation diameter 805 / 990 mm 1,140 mm 1,325 mm 1,540 mm

    •  Maximum pipeline / drilling length 300 m 700 m 1,200 m 1,400 m

    •  Geology: - Clay, Silt, Sand, Gravel, Cobbles, Boulders, Rock (up to 150 Mpa = 21,750 psi)

    •  Pipe material: - Steel

    •  Coating material: - . PE, PP, GRP, FBE

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    23/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page 22 January 2013

    3 GENERAL

    3.1  OverviewThis chapter provides general information for undertaking Non Disruptive Road Crossings including

    an overview of the parties involved and their roles and responsibilities.

    The chapter further covers the general requirements for environment, health and safety along with

    requirements for site survey and geotechnical investigations.

    3.2  Standards and Codes of Practice A number of local and international Standards and Codes of Practice along with guidelines and

    specifications have been sourced during the process of creating this manual. The documents and

    information listed below were chosen as they are typically viewed as being ‘best practice’

    internationally, in the field of NDRC and trenchless technology. Particular reference can be made to

    the following existing key documents:

    •  Abu Dhabi Municipality Road Department - Requirements and Recommendations for Non -

    disruptive Road Crossings

    •  Abu Dhabi Municipality Sewerage Projects Committee - General specifications for civil works,

    Pipeline construction by Non disruptive method (2003)

    •  The Pipe Jacking Association (UK) - "An introduction to pipe jacking and micro-tunnelling

    design" (1995)

    •  Horizontal Directional Drilling Good Practices Guidelines - 2008 (3rd Edition) USA

    •  Standard DWA-A 125E Pipe Jacking and Related Techniques, German Association for

    Water, Wastewater and Waste. (2008)

      Microtunneling and Horizontal Drilling Recommendations, FSTT, French Society ofTrenchless Technology (2006)

    •  Euronorm EN 12889: Trenchless Construction and Testing of Drains and Sewers.

    •  There is a wealth of globally available documentation about 'trenchless' or 'no dig' technology

    and the list above covers some of the more important ones. Additional information on

    methods and equipment can be found in these or from technical associations such as:

    •  International Society of Trenchless Technology, ISTT - www.istt.com 

    •  Pipe Jacking Association (UK) - www.pipejacking.org 

    •  North American Society for Trenchless Technology, USA - www.nastt.org 

    3.3  Roles and responsibilities

    This section describes typical roles and responsibilities of the parties involved in undertaking NDRCworks. The specific responsibilities and authorities of the different parties involved can vary from

    project to project depending on the contract agreements between the parties.

    Road crossings and in particular NDRC works are typically contracted as part of a main project

    involving installation of utility lines in an area, along roads, etc.

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    24/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page 23 January 2013

    3.3.1 ClientThe Client is the owner of the pipeline or cable to be installed. The overall responsibility for the

    installation and operation of the pipeline or cable is that of the Client.

    The Client can delegate certain responsibilities such as design and calculations along with the

    responsibility for safeguarding of the road to others through contract agreements.

    3.3.2 ConsultantThe Consultant is typically hired by the Client to design, tender and supervise the overall project.

    The Consultant will typically undertake preliminary site and soil investigations to collect information

    on existing utilities, surface and sub-surface constructions during the design stage. The consultant

    will supervise the installation and NDRC work during construction.

    3.3.3 Contractor/Sub ContractorThe Contractor or, if delegated, the specialist Sub Contractor is responsible for the correct

    installation of the pipeline or cable in accordance with the specifications.

    The Contractor/Sub Contractor is responsible for obtaining approval from the Road Authority prior to

    commencement of the NDRC work. Approval is only given after Submitting a complete and

    acceptable method statement including all required information in accordance with this manual.

    3.3.4 Road AuthorityThe Road Authority (Abu Dhabi Department of Transport or any Municipality) is responsible for

    giving approval of any NDRC work. The Road Authority's main interest is in protecting their assets -

    the road, footpaths, structures, etc. from any harm, settlement or heave resulting from the NDRC

    work which lies within the highway Right of Way.

    3.3.5 Abu Dhabi Town Planning Abu Dhabi Town Planning will give initial approval and assign a corridor that the Client may use. Thisis done only after checking with, and obtaining NOCs from the Road Authority, other Utility Agencies

    and any other relevant authorities.

     After giving approval and assigning a corridor Abu Dhabi Town Planning will refer to the Road

     Authority for final approval of the NDRC work.

    3.3.6 Utility AgenciesOther utilities agencies may be affected by the NDRC if their pipelines or cables are located near the

    proposed NDRC. The Contractor will need to obtain No Objection Certificates (NOC's) from all the

    concerned utilities agencies. These may be accompanied with certain requirements or restrictions

    concerning the NDRC.

    3.4  Process MapWhen following the procedure below, it is imperative that the Consultant follow the guidance

    contained in this Manual, and if any of the processes are not completed to the DoT’s satisfaction,

    then the relevant stage will not be approved.

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    25/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page 24 January 2013

    The process of undertaking NDRC work involves a five part approval process. Important points for

    the Consultant to consider:

    •  The stages are illustrated in Figure 17 below showing the main activities and responsibilities

    in each stage.

    •  Detailed information and requirements of the various activities can be found the subsequent

    sections of this manual.

    •  Check lists of required submittals to the Road Authority are given in Appendix A.

    •  The estimated processing times in the approval stages are based on complete and full

    submittals. Any missing information may result in prolonged processing times.

    •  Anywhere along the process factors may arise that will require the planned NDRC to be

    revised and the process to be returned to an earlier stage.

    •  All applications for approval with the DoT must be submitted using the No Objection

    Certificate - Right of Way (NOC-ROW) online system. Please refer to the DoT website for

    the latest information on this subject.

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    26/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page 25 January 2013

    Figure 17: Process map of NDRC

    Responsible Activity Details and information to be acquired

    PHASE 1  Concept Stage

    Client/Consultant

    Map of intended NDRC Location/vicinitySize (diameter) and level

    Approval process - part 1

    Submit to Abu Dhabi Town Planning for approval of corridor and NOC Expected processing time:4-6 weeks

    PHASE 2  Preliminary design

    Client/Consultant

    Geotechnical Geotechnical Assessment (Key stage 2) according to Manual forGeotechnical Investigation and Geotechnical Design includingGround Investigation Factual and Interpretative Reports.

    Site investigation Surface and underground structures

    Other utilities Location and type

    Drawings Line, level, diameterWork area with working shaft locations and sizes

    Method selection Suggested method and equipmentRequirements for accuracy, material, etc.

    Approval process - part 2

    Submit to Road Authority for preliminary approval of designCheck list of submittals required is given in appendix A.

    Expected processing time:2-3 weeks

    PHASE 3  Pre-construction Stage

    Contractor/Sub Contractor

    Design calculations Pipe strengthWorking shaftsJacking and friction forcesSurface settlement/heave

    Design drawings Plans and profiles of the intended lineWorking area plans showing placement of equipment andmaterials.Traffic diversion plansDetails of working shaftsDe-watering system design

    Materials and equipment Lists of all in use

    Method statement Contractor nameList of personnel with qualificationsSequencing and procedure of workGround water control and dewateringSafety proceduresEnvironmental assessmentRisk assessment

    NOC From all relevant utilities and authorities

    Letters of undertaking From Client and Consultant

    Approval process - part 3

    Submit to Road Authority for approval of constructionList of submittals required is given in Appendix A

    Expected processing time:3-4 weeks

    PHASE 4  Construction

    Contractor/

    Sub Contractor

    Site condition survey Surrounding surfaces and structures

    Pre construction photosMonitoring Setup and monitoring of surface movement

    QA/QC Documentation in accordance with QC plan

    PHASE 5 After construction

    Monitoring Surface movement - monthly reports

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    27/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page 26 January 2013

    3.5  Health and Safety All parties involved in NDRC work have an important role in establishing safe working conditions.

    During planning and design all foreseeable health and safety risks likely to arise shall be identified

    and taken into consideration in the design. All health and safety information known to the Client,

    Consultant or designer must be given to the Contractor prior to undertaking the NDRC work.

    Figure 18: Pipe jacking worksite and shaft

    The Contractor must ensure that prior to commencement of any project, a Health and Safety Plan is

    prepared which covers the specific requirements of the project. This plan shall be submitted prior to

    approval of construction along with the Method Statement, and approved by the relevant Consultant

    (usually the Engineer).

    General requirements for Environment Health and Safety must comply with the EHS Manual for

    Road Projects. All issues relating to EHS must be raised and addressed along all stages of the

    project.

    3.5.1 At Concept StageDuring this phase, it is important for the design team to establish the route of the NDRC to minimise

    the risks to safety for any persons working on the construction.

    When submitting the relevant design information to Abu Dhabi Town Planning, the Consultant must

    take into account the safety impacts of the size and material used in the NDRC works, if they are

    available at this stage.

    3.5.2 Preliminary Design StageDuring this phase, the designer must take into account:

    •  The specification of materials

    •  The location of the crossing – to minimise the safety impact on pedestrians, motorists and the

    general public

    •  The diameter – to minimise the impact of construction works for construction personnel

    •  The ground conditions – to establish the risks of stability of the surrounding soils.

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    28/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page 27 January 2013

    3.5.3 At Pre-Construction StageThis is an important phase for safety considerations as it maps out the construction processes and

    methods via the Method Statement. The appointed Contractor should submit:

    •  A Method Statement which should detail all the construction methods and programme

    •  A Risk Assessment highlighting ALL risks to safety, rating each in terms of probability and

    severity

    •  A Site Emergency Plan to show evacuation procedures in an emergency

    •  A Traffic Management Plan to set out the specific requirements for the site.

    3.5.4 During Construction StageDuring this stage there are many considerations for the Contractor to consider.

    •  A daily checklist for inspection of the works is included in the Appendix and this is to be

    checked back and corroborated with the Method Statement.

    The worker should take the following general precautions:

    •  Do not take chances that may lead to injury

    •  Either use tight sheet shoring to guard against the caving in of sandy soil or loose material

    when the depth of the excavation exceeds 5 ft, or cut back the bank to the proper slope.

    Keep shoring at or near the bottom of the ditch as it is excavated and follow with bracing to

    ensure safety. Trench shields are also acceptable as a protective system. A trench shield

    does not protect the environment, only the worker.

    •  The placement of shores will depend on the type (classification) of soil encountered. Local,

    state or provincial, and federal laws man - date the distances and sizing of shoring support

    systems.

    •  Extend shoring of any type below the excavation bottom whenever possible, and brace it

    thoroughly using timbers, wedges, and cleats, or a pipe/screw-jack combination. Place all

    bracing at right angles to the sheeting or uprights and rigidly wedge, bolt, or cleat it to prevent

    movement. Hydraulic units are being used in many types of utility-trench construction

    •  Use only full-sized lumber that is assessed to be sound and straight.

    •  Install the upper braces or screw jacks first, and remove them last for best protection.

    •  Also consider excavation dimensions, soil stability, variable weather and moisture conditions,

    proximity of other structures, weight and placement of soil and equipment used on the job,

    and sources of vibration when choosing the type of shoring to use, if any. The decision must

    rest with the engineer or foreman in charge.

    •  Use hydraulic jacks temporarily only, and replace them with properly sized screw jacks or

    solid bracing.

    •  Personnel should not be required to do heavy lifting that may cause injury; use mechanical

    lifting devices to raise, lower, or suspend heavy or bulky material when working in trenches,

    manholes, or vaults.

    •  Use ladders where required. Do not jump into an excavation.

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    29/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page 28 January 2013

    •  Provide an adequate means of trench exit, such as a ladder or steps. Locate it so no more

    than 25 ft of lateral travel is required. Extend the ladder from the bottom of the excavation to

    at least 3 ft above the ground surface.

    •  Do not place excavated material closer than 2 ft from the edge of an excavation.

      Keep all tools, working materials, and loose objects orderly and away from the excavationshoulder.

    •  Keep tools, equipment, and excavated material out of open traffic lanes.

    •  Take work breaks, rests, etc. at designated locations away from the excavation.

    •  When resuming excavation after heavy rains or freezing weather, inspect all banks for

    cracks. These may indicate earth movement and the probability of cave-in.

    •  Frequently inspect the sides and rim of all open excavations to guard against cave-in.

    Operate earth-moving equipment from a position that will not imperil personnel or property by

    a cave-in due to vibration, stress, or dead weight.

    •  If it is absolutely necessary to work above an overhanging bank, use a safety belt and a

    lifeline. Have a helper nearby to assist in an emergency.

    •  To avoid striking electric or telephone conduits, gas lines, or other sub-structures, locateother utility installations before starting work.

    •  Require workers to wear adequate eye, ear, and foot protection when using a jackhammer or

    when exposed to flying particles or falling objects.

    •  Workers should always be aware of locations of running machines (back–hoes, trenching

    machines, etc.). Workers should keep clear of the sweep path and try never to turn their

    backs toward the working machine(s).

    3.5.4.1   Pipe storage•  Keep pipe yards and walkways clean and orderly.

    •  Always block pipe to prevent it from rolling or falling.

    •  Arrange and block each row of stacked pipe to prevent it from rolling from the pile.•  Store small pipe in racks according to length and size.

    •  Store pipes larger than 2inch diameter by stacking them with spacing strips placed between

    each row.

    •  Withdraw pipe from the top rows.

    3.5.4.2   Shoring and bracing

    •  Use proper shoring and bracing to prevent cave-ins while vaults or similar openings are

    under construction.

    •  Proper shoring cannot be reduced to a standard formula.

    •  Each job is an individual problem and must be considered under its own conditions.

    3.5.4.3   Posting barricades and warning signs•  Place advance warning, instructional signs, barricades, and delineators well ahead of the

    construction area to warn motorists and pedestrians of the area and safely take them through

    or past it.

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    30/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page 29 January 2013

    •  Protect the work area with barricades, barriers, or planks to provide a safe working space. If

    necessary, use flaggers to direct and slow down traffic. When used, place trucks or air

    compressors between the work and the traffic.

    •  During periods of reduced visibility, use adequate lighting on all barricades.

      When no work is in progress, place adequate barriers, barricades, flashing lights, and signsto warn and divert traffic. Use reflecting tape on all barricades.

    •  All personnel should wear protective clothing including hard hats and high visibility traffic

    vests.

    3.5.4.4   Trenching machinesThe following rules apply equally to all mechanical devices used to dig trenches and/or make

    excavations including various types of trenchers, buckets, scoops, and similar pieces of equipment:

    •  Operators should always wear hard hats.

    •  Never attempt to oil or grease a mechanism or repair or adjust any moving part of a trenching

    machine while it is in operation. Only qualified personnel should operate a trenching

    machine.

    •  Guard all moving parts. Before starting the conveyor, make sure that no person is

    endangered by it.

    •  To remove obstructions from the conveyor mechanism or buckets, stop the machines.

    •  Be alert for falling material that might roll from the conveyor.

    •  When practicable, drop dirt between the excavation and the high-way to act as a barrier.

    •  Cautiously fill gasoline or diesel tanks. Keep spout in metallic contact with the machine to

    prevent static sparks from bridging the gap and igniting the vapours. Do not smoke. Keep

    proper fire extinguishers available when refuelling construction equipment. Use only

    approved containers when storing flammables on the job site; clearly mark and define

    storage areas.

    •  Use flags by day and flashing lights or flares by night to warn the public of the trenching

    machine and its operations. Liberally use these precautions on all highway or street work.

    Plan the warning system before the work is started.

    •  Operate the machine vertically to prevent undercutting the trench wells.

    •  When loading or unloading trenching machines or other heavy equipment from truck beds,

    lowboys, or other conveyances, provide suitable skids and ample blocking to prevent

    movement of the conveyance

    •  When manually lifting or lowering pipe in an excavation, use two or more rope slings looped

    under the pipe and handle from each side of the excavation. To prevent a heavy pipe from

    pulling workers into the excavation, anchor one end of each rope sling to a massive object

    such as a truck.

    •  When aligning pipes in the excavation, either manually or mechanically, keep hands and

    fingers away from ends of pipe and other substructures that could crush.

    •  Govern crane operations only by the signals of a qualified worker.

    •  Never try to catch and hold a length of pipe that slips from a crane or hoist sling.

    •  Be alert to unsafe excavation sides when measuring, testing, or inspecting pipe in place on

    an excavation bottom.

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    31/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page 30 January 2013

    •  When cutting sections of pipe, keep feet in the clear and use adequate blocking, chocks, etc

    to prevent pipe movement.

    •  Wear safety goggles

    •  Keep tools and appliances in good condition for handling, cutting, threading, or treating pipe.

     Always use the right tool for the job.•  Do not let tools or materials become stumbling hazards where pipe is being handled.

    •  Avoid shortcuts and makeshift methods that may increase the hazards of handling pipe.

     Accidents and risks that may be particularly related to NDRC work will include, but are not limited

    to:

    •  Falling accidents (deep excavations and shafts)

    •  Materials falling from a height

    •  Collapse of excavation or shaft

    •  Road collapse or failure

    •  Flooding from broken pipelines or groundwater

    •  Striking other utilities (power, gas, oil, water, etc.)

    •  Suffocation due to inadequate fresh air supply (manned pipe jacking or micro-tunnelling)

    •  Dangerous gasses

    •  Rotating and moving machinery and equipment

    These along with any other risks must be assessed in the

    Health and Safety plan including mitigation measures.

    Employment of workers inside pipe jacking or micro tunnelling

    pipelines shall not be permitted for pipelines with an internal

    diameter smaller than 1.2 m.

    The Contractor shall develop an emergency plan that describes

    actions to be taken in the event of any sudden surface

    settlement or collapse. This plan shall be included in the

    Contractors method statement.

    3.6  Environmental requirementsGeneral environmental requirements for any construction works in connection with main roads,

    including undertaking of NDRCs, can be found in the EHS Manual for Road Projects.

    Prior to commencing any projects an environmental permit must be acquired from The Environment

     Agency - Abu Dhabi (EAD). Points that will need to be addressed for the environmental permit may

    include:

    •  Soil or spoil removal including slurry handling and disposal. 

    •  Dewatering including discharge.

    •  Waste management.

    •  Handling and storage of any hazardous materials.

    •  Activities creating dust, air pollutants or odours.

    •  Noise or vibrations.

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    32/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page 31 January 2013

    •  The Contractor is responsible for establishing, operation and decommissioning of the work

    site in an environmentally safe way and this can be controlled by using a daily checklist

    report which will be followed in line with the Method Statement. Such details will be included

    in the Contractor's Method Statement.

      All waste materials shall be collected and disposed of in an appropriate manner, and the siteshall be cleared and void of any waste matter after the construction is completed.

    •  All materials and equipment shall be stored in accordance with manufacturer's guidelines and

    in a way so that spills or emissions are avoided.

    •  Drilling fluids (slurry, bentonite, etc.) shall be recovered for

    reuse or disposal at an approved location in accordance

    with the environmental permit.

    •  The environmental issues that typically concern HDD

    include:

    -  Access restrictions due to wetlands, streams,

    endangered plant or animal life, endangered

    habitat, and potential erosion

    -  Oil and fuel spills from construction equipment

    -  Drilling-fluid surface spills that endanger animal and

    plant life

    -  Drilling fluid returns in water bodies

    -  Groundwater contamination from drilling-fluid

    additives

    -  Drilling-fluid disposal locations (The contractor must obtain approval to dispose of the

    drilling fluid at an approved disposal location. Bentonite is a good product for sealing

    drainage ditches, irrigation reservoirs, and livestock ponds.

    •  However, approval must be obtained from EAD permit received for the works.

    3.7  Site condition survey A site condition survey shall be conducted during both the preliminary design and construction

    stages of the proposed NDRC. All surface and subsurface construction within a minimum of 30 m

    from the proposed centreline and any shafts must be identified and the exact location determined.

    These will include, but are not necessarily limited to:

    •  Cables, pipelines, sewers and manholes

    •  Pavements, footpaths, etc.

    •  Buildings

    •  Foundations, retaining walls, etc.

    •  Artificial cavities

    •  Constructional systems that have remained in the area along with any other structures or

    systems that may have impact or be influenced by the intended NDRC.

     A building and structure assessment plan documenting the condition and including photographs of

    any existing damage must be included in the site condition survey. This shall be submitted for

    approval of both the preliminary design and final design. In connection with the final design the site

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    33/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page 32 January 2013

    survey must be reviewed and approved by the DoT road maintenance consultant and approved by

    the DoT.

    Immediately prior to construction the site survey shall reviewed by the Contractor and any changes

    in the condition of buildings, structures, roads, footpaths and other paved areas shall be recorded

    and photographed.

    3.8  Geotechnical InvestigationThe geotechnical investigation shall be conducted in accordance with the Manual for Geotechnical

    Investigation and Geotechnical Design including determining the projects geotechnical category and

    the procedures for managing geotechnical risk as described.

    Evaluation of soil conditions on NDRC projects is critical, but often under-emphasized. Success or

    failure is intricately tied to correctly matching equipment and methods to soil Conditions. It is the

    designer's responsibility to ensure that sufficient geotechnical information is available for the

    complete design and safe installation of the NDRC.

    For all NDRC work, a minimum requirement of a desk study shall be carried out, assessing the

    available literature, maps, aerial photographs, utility plans and existing site investigations. The aerial

    photographs must encompass as much historical information as possible, that show for example

    lowlands swamps which have since been backfilled. Existing geotechnical investigations may be

    acquired from the road department, adjacent building owners or structures and other utilities

    agencies.

    If insufficient geotechnical information is available for the area where an NDRC is proposed, then a

    thorough geotechnical investigation must be conducted.

    The soil investigation analysis is necessary for:

    •  Selecting the appropriate NDRC method, jacking technique and jacking works

    •  Selecting and designing the supports for launch and reception shafts

    •  Selecting and designing jacking pipes

    •  Planning measures for soil improvement in unstable soils

    •  Planning of soil disposal (landfill, treatment, recycling)

    •  Planning of measures for the control of groundwater

    The field exploratory techniques selected should be appropriate to the type of ground and the

    planned depth of the NDRC. The laboratory testing programme should include tests relevant to the

    ground conditions and the NDRC techniques likely to be

    employed. Table 1 below suggests parameters to be

    considered in relation to each soil type.

    The soil conditions shall be investigated and documented in

    accordance with the Manual for Geotechnical Investigation

    and Geotechnical Design. The investigation should result in

    information on reliable soil parameters which are necessary

    for the adequate design of the drives, shoring, and

    dewatering details. Analysis and design (calculations for

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    34/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page 33 January 2013

     jacking forces, stress analysis on the pipeline, ground surface settlement and heave analysis, etc.)

    should be based on such parameters.

    3.8.1 Minimum requirements of the exploratory boreholesNumber of boreholes:

    •  2 exploratory holes for crossings less than 25 m (one

    at each end)

    •  3 exploratory holes for crossings greater than 25 m

    (each end and centre)

    •  Additional holes for long crossings or in areas with

    difficult soil conditions (layered)

    Depth of boreholes:

    •  Down to 2 m below pipe invert in groundwater free

    soils•  Down to 3 m below pipe invert in groundwater bearing soils

    •  Down to the planned bottom edge of sheeting in the area of launch and reception shafts.

    3.8.2 Borehole PositionsExploratory borehole positions should be chosen to provide information on the nature of the ground

    that will be encountered by the NDRC. Under no circumstances should boreholes be sunk on the

    line of the NDRC.

     All boreholes should be properly backfilled and sealed. Piezometers should be installed where

    recommended. Boreholes should always extend sufficiently far below the invert level to identify

    changes in the strata below the NDRC that could affect both the construction and long term impact

    of the NDRC. Boreholes should be sunk adjacent to shaft locations. Additional boreholes should beconsidered, if required, to identify the location of significant changes in geology or to resolve other

    geotechnical uncertainties.

     All geotechnical investigations shall be carried out by qualified personnel and in accordance with The

    Manual for Geotechnical Investigation and Geotechnical Design.

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    35/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page 34 January 2013

    Table 1: Parameters to be considered in relation to each soil type

    TestNon-

    CohesiveSoils

    CohesiveSoils

    MixedSoils

    FillMaterial

    Rock

    Unit weight and moisturecontent X X X X X

     Angle of friction X X X

    Particle size distribution X X X X

     Abrasivity X X X X X

    Cohesion X X X

    Types and proportions ofminerals

    X X X X X

    Standard penetration tests X X X X

    Permeability and nature ofground water level andflows (seasonal/tidalchanges)

    X X X X

    Toxic/hazardous

    constituents in theground/groundwater X X X X X

    Frequency and physicalproperties of boulders,cobbles or flints

    X X X X X

    Pump down tests X X X X

    Presence of gases X

    Compressive strength X

    Rock quality designation(RQD)

    X

    Core logging (TCR, SCR,FI)

    X

    Tensile strength X

    Specific energy

    (excavatability)

    X

    Slake durability X

    Geological description X X X X

    Plasticity indices (LL, PL,PI)

    X X

    Source: An Introduction to pipejacking and microtunnelling design  

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    36/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page 35 January 2013

    4 PROCEDURES FOR UNDERTAKING NON

    DISRUPTIVE ROAD CROSSINGS

    4.1  OverviewThis chapter contains the general procedures and requirements for undertaking any NDRC works

    under DOT roads. It is divided into sections relating to the process map described in Chapter 1.

    4.2  Concept Stage At this early stage, the concept of each project will be considered by the Designer, and as per the

    stage gateway process, the options will be considered from a financial and environmental impact

    point of view before progressing to the next stage. This will be in line with the requirements of Town

    Planning as detailed in Chapter 2. 

    For NDRC, if applicable the impacts will be established and examined, and put forward into the

    report generated by the Consultant. Depending on the project, it may be the case that different

    routes for the NDRC are considered. 

    4.3  Preliminary Design Procedures

    4.3.1 Method selectionIn this section more detailed information about the guidelines requirements and criteria related to the

    two major NDRC methods are currently used in emirate of Abu Dhabi are given in order to help

    select a method appropriate for the given project. More information on the various methods can be

    found in Chapter 2.

    The Client/Consultant should, before tender, determine which methods may or may not be used for

    the NDRC works. The selection should be appropriate for the intended installation and meet the

    requirements of this Manual. Method and equipment should be selected to avoid ground loss and

    minimize settlement or heave. Also, a geotechnical section along the drive path shall be provided

    with the ground surface and groundwater elevations shown. This will assist in determining the

    method.

    The selection of route and method shall be based on the information gathered during the site

    investigation and geotechnical survey along with all other relevant information. The line and level of

    the route shall be selected so as to avoid driving through weak/strong soil boundaries, weathering

    interfaces and groundwater surfaces.

    The methods presently available are many and diverse and new techniques are continually being

    developed. Existing methods and equipment are becoming more advanced and variations or

    combinations of different methods are also being developed.

    The selection of method is also dependant on the:

    •  Cost – The cost of construction can vary dramatically depending on the method, materials,

    and route chosen.

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    37/117

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    38/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page 37 January 2013

    Table 2: NDRC methods related to soil types

    ◙ 

    ◙ 

    & ◙  ◙ 

    /

    ◙ 

    &

    ◙  ◙ 

    ◙  ◙ 

    ◙  ◙  ◙ 

    & ◙  ◙ 

    ◙  ◙ 

    / ◙  ◙  ◙  ◙ 

    ◙  ◙  ◙ 

    X – Not Suitable • - Suitable ◙ - May be Suitable (depends on specific circumstances)

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    39/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page 38 January 2013

    Table 3: Different applications of NDRC

    Micro tunnelling and Horizontal Directional are the most used methods in Emirate of Abu Dhabi, so

    more discussion will be explained.

    4.3.1.1   Micro tunnelling Method All types of Micro tunnelling boring machines have the following functions in common.

    Mechanized ground excavation and stabilization of the face

    •  The head of the machine is equipped with a cutting wheel whose tools are used to last the

    soil under the combined action of rotation and thrust. A crushing cone located behind the

    cutting wheel and intended to reduce the size of larger elements to allow their mucking, is

    present on most machines. There exist different cutting heads for various types of soil. (see

    figure below). They can be distinguished by their cutting tools.

    •  For sandy or gravely soil, the cutting wheels are equipped with teeth (figure –a). In ruggedsoil, these teeth dislodge the blocks, which are then crushed.

    Suitable at appropriate diameters and lengths ® - Small diameter only ø - Small diameter only U –Typically for Crossings only S – Siphon crossings only

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    40/117

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    41/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page 40 January 2013

    -  less than the passive earth pressure so as to avoid facing back the soil at the face

    ,leading to elevations of the surface or lateral movements likely to create disorder for

    already –existing networks(Stein et al.,1994)

    •  In the case of hydraulic mucking ,this pressure is ensured by the slurry injected into the

    chamber located at the back of the felling cone.it can be controlled more easily than the

    pressure exerted by the soil mixed in the stpe of the scew type boring machines(Bennett et al

    .1994).

    Disposal of rubble (mucking)

    There are three types: 

    •  Hydraulic mucking – Removing the earth in suspension in a freely flowing fluid to the outside.

    That fluid can be water or pressurised bentonite slurry.(See Figure 20)

    •  Mucking with a screw conveyor – The rubble is extracted from the stope using a spiral

    conveyor (see Figure 20)

    •  Pneumatic mucking – This is a system that is rarely used and consist of mucking by suction

    where the rubble is extracted from the face into an airtight vacuum container.

    Figure 20: Principles of a hydraulic mucking boring machine (Herrenknecht documents)

    Monitoring and correction of trajectory

    •  Controlling the actual trajectory of the boring machine in relation to its theoretical position ,is

    done using a laser beam with the sensor located in the start shaft whose impact on a target

    placed in the machine helps visualize the deviations in trajectory with the help of a camera on

    board the boring machine

    •  When the deviation s become excessive it is possible to correct the direction of the machine

    whose head is articulated by moving the three cylinders placed 120 c apart.

    •  4-installation of pipelines by jacking.

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    42/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page 41 January 2013

    •  This is done by successive jacking of pipes behind the boring machine ,this pipejacking is

    ensured by a thrust frame equipped with hydraulic cylinders and located in the starting shaft.

    Pipes Materials

    Many types of materials are used :-

    •  Concrete pipes represent the majority of pipelines that are currently laid .

    •  Pipes made of composite materials, known as “glass fibre reinforced plastic “offer very good

    resistance to corrosion and thus are efficient in transporting corrosive fluids or for carrying

    chemically aggressive soil, moreover they offer a high resistance at a lower weight the

    external diameters available are between 400 and 2400 mm.

    •  Steel pipes have the major advantage of offering strong resistance but they are sensitive to

    corrosion.

    •  Clay pipes available in diameters of 150 to 1200 mm offer greater resistance than the

    concrete pipes at the same thickness .when their surface is vitrified ,it is extremely resistant

    to water absorption and chemical attacks.

    In terms of corrosion resistance the jacking pipes and their joints can be subject to internal corrosioncaused by the transported substances or to external corrosion caused by the surrounding soil or

    ground water.

    If the materials used are insufficient ly resistant ,measures of corrosion protection have to be taken

    and approved by Dot.

    For steel and ductile cast iron pipes the internal protection shall not be damaged during the jacking

    process.

    The methods vary in size, length and accuracy as shown in Table 4. Due to the limitations in

    accuracy, non-steerable methods should only be used over short distances and where suThe soil

    conditions and groundwater levels are of great importance in determining the most suitable methodfor a given NDRC. In Table 2 a number of the common methods are shown with their respective

    application in various soil types.

    Some methods can be used in almost any soil conditions as long as the equipment and tools are

    appropriate for the present soil types. Horizontal directional drilling (HDD) is an example, where drills

    and reamers are available for nearly any soil type. HDD can however have limitations in coarse non-

    cohesive soils where the cavity created by the reamer can have a tendency to collapse. This is

  • 8/9/2019 Non Disruptive Road Crossings-1 DOT

    43/117

      NON DISRUPTIVE ROAD CROSSINGS M ANUAL 

    Page 42 January 2013

    especially the case in very uniform soil particle size efficient clear distance to other utilities can be

    guaranteed.

    Table 4: NDRC methods with typical pipe size, length and accuracy

    External pipediameters, De 

    Maximumlength

    Accuracy Minimumground cover

    Non-steerable:

    Impact moling/soildisplacement hammer,Pipe ramming with closed pipe

    Up to 200 mm 25 m 1-2 % of length 10 x DeMin. 3.0 m

    Pipe ramming with open pipe, Auger boring

    Up to 2000 mm 80 m 1-2 % of length 3.0 x DeMin. 3.0 m

    Steerable:

    Horizontal Directional Drilling(HDD)

    40 - 1200 mm 1800 m 2-5 % of depth

    Micro tunnelling 400-4500 mm 1000 m +/- 20 mm 3.0 x De Min. 3,0 m

    Pilot pipe with auger spoilremoval

    100 - 1200 mm 100 m +/- 20 mm 3.0 x De Min. 3.0 m

    Manned steerable:

    Pipe jacking 1500 - 4500mm

    1000 m +/- 20 mm 3.0 x De Min. 3.0 m

    Hand excavation: 

    Hand dig + Mechanicalexcavator

    Min 1500mm 125m Varies 3.0 x De Min. 3.0 m

    .

    Micro tunnelling or pipe jacking with closed front can also be applied in nearly any soil condition with

    the suitable bore heads and spoil removal systems. However, in very loose non-cohesive soils, with

    high groundwater levels, there is a risk of removing excessive soil in front of the bore head, which

    may lead to immediate or future surface settlement.

    In very loose soils or areas where soil investigations have indicated subsurface cavities, a decision

    must be made either to construct deeper in an attempt to find suitable soil conditions or to apply

    ground treatment methods prior to undertaking the NDRC.

    In Figure 2 a number of grout types are indicated for use as ground treatment methods.

    The final selection of an NDRC system should be developed using available factual and reliable soildata and surrounding constraints. The system should include the recommended route (line and

    level), boring size, NDRC method, pipeline details, equipment, and operational variables, all of

    which, in combination, will achieve the required tolerances. The proposed system should then be

    analyzed for:

    •  Jack