Nigeria: Environmental and Social Management...

69
E1965 v4 THE WORLD BANK GROUP Nigeria: Environmental and Social Management Plan-ILE-IFE P095003 NG: Rural Access and Mobility Project- Phase 2 - 7/6/2012 [Type the abstract of the document here. The abstract is typically a short summary of the contents of the document. Type the abstract of the document here. The abstract is typically a short summary of the contents of the document.]

Transcript of Nigeria: Environmental and Social Management...

Page 1: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

E1965 v4

The World Bank Group

Nigeria: Environmental and Social Management Plan-ILE-IFE

P095003 NG: Rural Access and Mobility Project- Phase 2

-

7/6/2012

[Type the abstract of the document here. The abstract is typically a short summary of the contents of the document. Type the abstract of the document here. The abstract is typically a short summary of the contents of the document.]

Page 2: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

SECL, Nigeria in JV with VSPL, Indiain JV with

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

TABLE OF CONTENTChapter 1 : ENVIRONMENT MANAGEMENT PLAN................................................................................2

1.1 SPECIFIC ACTIVITIES BY SPIU................................................................................................21.2 SPECIFIC ACTIVITIES BY CONTRACTOR.................................................................................21.3 SITE SPECIFIC MANAGEMENT PLAN-CLUSTER-(ILESA Region).............................................2

1.3.1 Cultural Properties................................................................................................21.3.2 Sensitive Features.................................................................................................21.3.3 Community properties..........................................................................................21.3.4 Farm Lands, Bushes and Tree cutting:...................................................................2

1.4 IMPLEMENTATION OF ESMP...............................................................................................21.5 ENVIRONMENTAL MONITORING PROGRAMME..................................................................2

1.5.1 Monitoring of Earthworks Activities......................................................................21.5.2 Monitoring of Concessionaire / Contractor's Facilities, Plant and Equipment......2

1.6 BUDGET...............................................................................................................................2

Chapter 2 IMPLEMENTATION & MONITORING SCHEDULE.................................................................2

2.1 ENVIRONMENTAL CELL, SPIU...............................................................................................22.2 IMPLEMENTATION ARRANGEMENTS..................................................................................2

2.2.1 Independent Engineer (IE)....................................................................................22.2.2 Contractor.............................................................................................................22.2.3 Contractor.............................................................................................................2

2.3 REPORTING SYSTEM............................................................................................................22.4 ENVIRONMENTAL CAPACITY BUILDING...............................................................................2

Chapter 3 ENVIRONMENTAL MONITORING PROGRAM.......................................................................2

3.1 PERFORMANCE INDICATORS (PI) OF MONITORING............................................................23.2 MONITORING OF PERFORMANCE INDICATORS...................................................................2

3.2.1 Ambient Air Quality (AAQ) Monitoring.................................................................23.2.2 Ambient Noise Monitoring....................................................................................23.2.3 Water Quality........................................................................................................23.2.4 Soil Quality............................................................................................................23.2.5 Plantation and Survival Rate.................................................................................2

3.3 ENVIRONMENTAL MONITORING COST................................................................................2

| Page (ii)

Page 3: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

SECL, Nigeria in JV with VSPL, Indiain JV with

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

LIST OF TABLESTable 1-1: Environmental Management Plan...............................................................................................2Table 1-2: Environmental Budget................................................................................................................2Table 2-1: Summary of Reporting of Environmental components and Responsibilities...............................2Table 2-2: Modules for Training................................................................................................................... 2Table 3-1: Environmental Monitoring Plan...................................................................................................2

LIST OF BOXES

Box 2-1: Qualification and Responsibilities of Environmental Officer of Independent Engineer..................2Box 2-2: Qualification and Responsibilities of Environmental Officer of Contractor.....................................2

| Page (iii)

Page 4: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

SECL, Nigeria in JV with VSPL, Indiain JV with

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

ACRONYMS

APHA American Public Health AssociationARAP Abbreviated Resettlement Action PlanESIA Environmental and Social Impact AssessmentESMP Environment and Social Management PlanFMEnv Federal Ministry of EnvironmentHSE Health, Safety & EnvironmentICB International Competitive BiddingIE Independent EngineerNOC No Objection CertificateOP Operational Policy (World Bank)ROW Right of WayR&R Resettlement & RehabilitationSPIU State Project Implementation UnitWB World BankWHO World Health Organization

| Page (iv)

Page 5: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

SECL, Nigeria in JV with VSPL, Indiain JV with

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

Chapter 1 : ENVIRONMENT MANAGEMENT PLAN

| Page (1)

Page 6: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

SECL, Nigeria in JV with VSPL, Indiain JV with

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)The Environmental and Social Management Action Plan (ESMP) is required to ensure sustainable development of the road during construction and operational phases. ESMP is site and time specific. For the proposed construction packages of the project road, ESMP has been designed for each cluster. The ESMP has two main component (i) Generic ESMP and (ii) Specific ESMP. The generic ESMP is applicable for all the road clusters, but the specific ESMPs are applicable only to the specific clusters. The generic and Specific ESMPs are being developed considering the operation policies of World Bank as well as the National Policies on Environment.

The implementation of ESMP is important. For this an institutional framework has been developed and roles and responsibilities of the various line departments are made. Some capacity development program are also identified as part of the ESMP as sub-project. The essence of the project is its proper maintenance during and post rainy season. This is also to be considered and need of community based implementation program suggested.

In general, SPIU of Osun state, Nigeria (with assistance from Contractor and Independent Engineer/Supervision Consultant) is the responsible entity for ensuring that the mitigation measures are carried out. Mitigation measures for generic impacts are listed in Table 1.1. The list provides reference implementing organisation and responsible entity.

1.1 SPECIFIC ACTIVITIES BY SPIU

The role of SPIU in the implementation of ESMP involves the following activities:

ESIA clearance from Federal Ministry of Environment, if required; Clearance of ESIA from World Bank;Disclosure of ESIA document in Nigeria as well as in the info shop of World Bank and Permission from Forest Department for felling of trees, wherever applicable.

1.2 SPECIFIC ACTIVITIES BY CONTRACTOR

The activities to be performed by the contractor to implement the ESMP shall comprise the following:

Confirm the Tree Cutting Schedule based on the final design and provide modified schedule to SPIU.

Fell the trees after SPIU secures Forest Department permission, wherever applicable;Fell the trees in farm land after SPIU provides necessary compensation to the farm land owners;Finalizing the selection of material sources (quarry and borrow material, water, sand etc);( refer

Annexure 1.1, 1.2, 1.3 and 1.4).Selection, design and layout of construction areas, abour camps etc. (Refer Annexure 1.6)

1.3 SITE SPECIFIC MANAGEMENT PLAN-CLUSTER-(ILESA Region)1.3.1 Cultural Properties

In this project there is no impact on cultural property (e.g. church, mosque etc.). Impact on cultural properties during the road construction phase in the Corridor of Impact will be avoided through adequate scheduling of vehicles and construction machineries. Care shall be taken for the chance found cultural properties. It is the prime responsibility of the contractor to inform the SPIU’s Environment and Social safeguard specialist regarding the chance found cultural property so that necessary safeguard measure can be taken up.

1.3.2 Sensitive Features

Some section of the project road is passing through Sasha forest areas, which is a protected area. Tree felling at this section may require for the project road widening. The road within the Sasha forest section is however having sufficient RoW (around 6m) to accommodate the project. However, some tree cutting may be required not only for the project construction but also for the movement of construction vehicles, storage areas for construction materials etc. A compensatory afforestation of 2 trees per tree cutting shall be made at this section of project road.

1.3.3 Community properties

| Page (2)

Page 7: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

SECL, Nigeria in JV with VSPL, Indiain JV with

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)As such in this section no such community property is going to get affected due to the proposed construction of project road. There is no impact on ground water resources, school, water tank, palm oil production unit. However, one bus stop is going to get affected as part of the project. A new bus shelter to be provided for this section.

1.3.4 Farm Lands, Bushes and Tree cutting:

As such in this section no such farm land is adjacent to project has been identified. The farm land is at least 2-3m apart from the road sections and there are naturally grown bushes along the project roads. Private farm land owners shall be compensated if their land is going to be taken for this project for the loss of livelihood, if any.

1.4 IMPLEMENTATION OF ESMP

The Environmental Officer of the contractor should be available for the entire duration of the project and shall be primarily responsible for compliance of ESMP. The Environmental Specialist from the Independent Engineer/ Supervision Consultant shall monitor the compliance of the ESMP and all the design drawings of various civil structures shall be implemented after his approval. The proposed organogram for the implementation and monitoring of ESMP is presented in figure 1.1. The details of the implementation and monitoring schedule of ESMP are described in Chaper-2. The key issues that require special attention along with the mitigations to be implemented have been detailed in Table 1.1.

Project Coordinator

Infrastructure

Procurement

Env. & Social Safeguard

Monitoring and evaluation

Internal Audit

Communication

Accounts

TEAM-SPIU-OSUN

Chief Project Manager(Contractor)

Environmental Officer (Contractor)

Team Leader(Independent Engineer /

Consultant)

Environmental Expert (Independent Engineer /

Consultant)

State Ministry of Environment

Figure: 1.1: Organization Structure for Implementation of ESMP

| Page (3)

Page 8: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

Table 1-1: Environmental Management Plan

Environmental Impact / Aspect

Mitigation Measures1 Location2 Time Frame3Responsibility Cross

referenceImplementation Supervision

DESIGN STAGE

Geometric Design

The proposed alignment is selected / adjusted to minimise farm land disturbance to avoid culturally & environmentally sensitive areas – cultural properties, water bodies etc.

During alignment

DesignContractor SPIU Design Report

Issues from stakeholder Consultations

Various issues raised were examined & suitably incorporated based on merit & other road safety measures.

During Design Contractor SPIU ESIA report

Orientation of Implementation Agency

A comprehensive training / orientation schedule has been prepared at different stages of SPIU. During Design SPIU SPIU Chapter 2,

ESMP.

PRE-CONSTRUCTION STAGE

Farm Land Acquisition

Land requirement details to be sent to the Govt. and permission to be taken for the same.

Affected farm land owners to be compensated for their livelihood as per OP: 4.12 (Involuntary Resettlement)

Right of Way (ROW)

Before construction

startsSPIU. SPIU

Tree cutting in forest areas Compensatory afforestation shall be made Right of Way

(ROW)

Before construction

startsSPIU. SPIU Forest Law of

Nigeria

Mobilisation & Site Clearance

Removal of Vegetation

Vegetation will be removed from the ROW before the commencement of Construction. ROW

Before construction

Starts Contractor IE, SPIU

Feasibility report and

design drawings

Procurement of plants and machineries

Specifications of plant and machinery to be procured need to comply to the relevant international standard norms and with the requirements of emission control

Prior to mobilisation at

site

Contractor IE, SPIU International standard

specifications

1 Some of the mitigation measures are preventive in nature while some others include additional measures in terms of environmental conservation and involve physical and construction work. 2 Unless otherwise stated, the Project Site covers area beyond ROW, such as borrow areas, and equipment storage sites.3 Time frame refers to the duration or instant of time when the mitigation measures will be taken.

Page 9: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

Environmental Impact / Aspect

Mitigation Measures Location Time FrameResponsibility Cross

referenceImplementation Supervision

legislations in Nigeriaand Air & Noise

Standards of FMEnv

Page 10: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

Environmental Impact / Aspect

Mitigation Measures Location Time FrameResponsibility Cross

referenceImplementation Supervision

Setting up of construction camps

The construction camps will be located at least 500m away from habitations and there must be necessary (temporary) living accommodation and ancillary facilities as approved by the IE/SC.

construction campsite

During Establishment

, Operation and

Dismantling of Such Camps.

Contractor IE, SPIU Annexure 1.6

Setting up of construction plant and machinery sites

Construction plant and machinery site to be located at least 1000m away from the nearest habitation.

At plant location

During erection, testing,

operation and dismantling of such plants

Contractor IE, SPIU

CONSTRUCTION STAGELand

Loss of farm land due to heavy movement of construction vehicles

Temporary impact on farm land is envisaged due to movement of construction vehicles. Proper scheduling of vehicles to be made to bring and dispose of construction materials. Since the road lengths are smaller, hence the storage of material can be made at one end of the road.

Temporary acquisition of farm land due to vehicle movement shall be compensated as per OP:4.12.

RoW During Construction Contractor IE, SPIU

Soil Erosion and Sedimentation control

Main reason of soil erosion is rains. Contractor should plan the activities so that proper surface pitching is done to avoid loose soil. Following preventive measures to be taken such as: Embankment slopes to be covered, soon after completion. Vegetation growth along the project roads to be maintained for soil stability; Proper road side drainage will be given to minimize erosion. Top soil from borrow area, construction site to be protected / covered for soil erosion. Along sections abutting water bodies, stone pitching needs to be carried out. Community based maintenance of road be made

Throughout Project

Corridor,and equipment storage sites,

etc.

Upon completion of construction activities at these sites.

During construction

Contractor SPIU Standard engineering practices,

community based

maintenance program

Page 11: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

Environmental Impact / Aspect

Mitigation Measures Location Time FrameResponsibility Cross

referenceImplementation Supervision

during and after rainy season

Page 12: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

Environmental Impact / Aspect

Mitigation Measures Location Time FrameResponsibility Cross

referenceImplementation Supervision

Loss of farm land top soil

The top soil will be covered; Top soil to be stripped to a specified depth of 150mm Top soil to be stored in stockpiles and shall be

covered. Stockpiles to be designed in such a way that slope do

not exceed 1:2 (vertical to horizontal). Silt fencing to protect the edges of the pile and height

of stockpiles to be restricted to 2m.

All along Project

Corridor, where productive land

is acquired

During construction Contractor IE, SPIU

Standard practice, WB

safeguard documents

Compaction of Soil and Damage to Vegetation

Construction vehicles should operate within the Corridor of Impact avoiding damage to soil and vegetation.Diversions, access road used during construction period will be redeveloped by Contractor, to the satisfaction of the owner / villagers.Construction vehicle, machinery and equipment shall move or be stationed in the ROW only. While operating on temporarily acquired agricultural land for any construction activities, top soil will be preserved in stockpiles.

Throughout Project

Corridor and all areas

temporary acquired.

During construction Contractor IE, SPIU

Contamination of soil

Oil & fuel spills from construction equipment shall be controlled by good O&M practices;

Contaminated soil shall be disposed of as per guidelines of FMEnv;

Vehicle maintenance and refueling in construction camps should be confined to areas with traps oil / grease to prevent wastewater from entering into rivers and streams

At fuel storage areas –

usually at construction

camps, temporarily

acquired site.

During Construction. Contractor IE, SPIU

Guidelines of FMEnv and World Bank

Quarrying

Material sources

Quarry material shall be sourced from approved and licensed aggregate and sand quarries. Copy of licenses to be submitted to the IE. For operating new quarries, the Contractor shall obtain materials from quarries only after consent of concerned authorities and only after development of a comprehensive quarry’ redevelopment plan. Adequate safety precautions shall be ensured during

During construction

Contractor IE, SPIU

Page 13: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

Environmental Impact / Aspect

Mitigation Measures Location Time FrameResponsibility Cross

referenceImplementation Supervision

transportation of quarry material from quarries to the construction site. Vehicles transporting the material shall be covered to prevent spillage. Operations to be undertaken by the Contractor as per the direction and satisfaction of the IE.

Page 14: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

Environmental Impact / Aspect

Mitigation Measures Location Time FrameResponsibility Cross

referenceImplementation Supervision

Generation of Debris

Debris generated due to the dismantling of the existing culverts and other concrete structures and cutting materials shall be suitably reused in the proposed construction as fill materials for embankments

Throughout Project

Corridor.

During Construction Contractor SPIU

Air

Dust Generation

Vehicles covering construction materials shall be covered;

Plant and machinery to be at least 1 km away in the downwind direction from nearest human settlements;

Regular water sprinkling at morning and evening hours at the construction yards.

Throughout Project

Corridor, all access roads,

temporarily acquired sites.

Beginning with &

throughout construction

until side slopes are covered.

Contractor SPIU

Equipment Selection, Maintenance and Operation

Regular pollution under check for construction vehicles shall be made; Further, idling of vehicles to be stopped during construction period; Automatic diesel logger may be installed in vehicles to minimise idling

Throughout Project

Corridor, all access roads,

sites temporarily

acquired and all borrow

areas.

During Construction. Contractor IE, SPIU

Water

Alteration of drainage due to construction /replacement of culverts

Diversions will be constructed during dry season, with adequate drainage facility, and will be completely removed before the onset of wet season. Debris generated due to the excavation of foundation or due to the dismantling of existing structure will be removed from the water course. Temporary Silt fencing to be provided on the mouth of discharge into natural streams.

Throughout Project

Corridor, all access roads,

temporarily acquired sites.

Whenever encountered

during construction

Contractor IE, SPIU

Runoff and drainage

Throughout continuous drain is provided. Throughout Project Corridor

During Construction Contractor IE, SPIU

Water requirement for project

Contractor will provide a list of sources (surface / ground) for approval from IE. Prior to use of source Contractor will take written

Throughout Project

Corridor, all

During Construction

Contractor IE, SPIU

Page 15: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

Environmental Impact / Aspect

Mitigation Measures Location Time FrameResponsibility Cross

referenceImplementation Supervision

permission from authority, to use the water in construction activity, and submit a copy to IE

access roads, temporarily

acquired sites.

Page 16: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

Environmental Impact / Aspect

Mitigation Measures Location Time FrameResponsibility Cross

referenceImplementation Supervision

Silting / sedimentation

Measures suggested under “Soil Erosion and Sedimentation control” will be enforced. Silt fencing is provided around water bodies. Construction activities will be done carefully near water bodies during wet season. Soil trap are suggested / will be provided in all ancillary sites and camps.

Throughout construction

periodContractor IE, SPIU

Contamination of water

Measures suggested under “Contamination of soil” will be enforced. Construction work close to water bodies will be carried out intermittently during wet season with adequate monitoring. Labour camps will be located away from water bodies. Car washing / workshops near water bodies will be avoided.

All areas in immediate vicinity of

construction campsite

chosen by the Concessionaire / Contractor.

Throughout construction

period, During Establishment

, Operation and

Dismantling of Labour Camps.

Contractor SPIU

Noise

Noise from Vehicles, Plants and Equipment

Construction activities near habitation areas shall be prohibited between 9 p.m to 6 a.m.

Maintenance of vehicles, equipments and machinery shall be made.

All plants and equipments to confirm to the noise standards of FMEnv.

Provision of ear-plugs to contractors exposed to high noise levels.

Noise barriers to be given at sensitive location

Throughout Project

Corridor, all access roads,

sites temporarily

acquired and all borrow

areas.

Throughout construction Contractor IE, SPIU

Flora & Fauna

Loss of trees and Avenue Planting

Plant a minimum of 2 times of trees as compensatory afforestation for the number of tree cutting along the ROW. Cost of plantation included in the ESMP Budget. Concessionaire / Contractor has to make sure that no trees / branches to be fell by labourer for fuel, warmth during winter. Enough provision of fuel to be ensured.

After completion of construction

activities

Contractor IE, SPIU

Fauna Construction workers must protect natural resources and wild animals.

During construction

Contractor IE, SPIU

Page 17: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

Environmental Impact / Aspect

Mitigation Measures Location Time FrameResponsibility Cross

referenceImplementation Supervision

Hunting will be prohibited. Nesting grounds & migratory paths, if any are protected.

Page 18: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

Environmental Impact / Aspect

Mitigation Measures Location Time FrameResponsibility Cross

referenceImplementation Supervision

Socio – Economic Environment

AccidentsThe Concessionaire / Contractor will provide, erect and maintain barricades, including signs marking flats, lights and flagmen as required by the Independent Engineer.

During Construction Contractor IE, SPIU

Resettlement Action of People

Affected population will be compensated as per WB policy and entitlement framework.

During Construction

Contractor, SPIU IE, SPIU

Temporary Loss of Access

The works shall not interfere with or cause inconvenience to public or restrict the access to use and occupation of public or private roads, and any other access footpaths to or of properties whether public or private.

All along the Project corridor

DuringConstruction Contractor IE, SPIU

Road Safety And Construction Safety

Risk from Electrical Equipment

Adequate precautions will be taken to prevent danger from electrical equipment. No material or any of the sites will be so stacked or placed as to cause danger or inconvenience to any person or the public. All necessary fencing and lights will be provided to protect the public. All machines to be used in the construction will conform to the relevant Nigerian Standard , will be free from defect, will be kept in good working order, will be regularly inspected and properly maintained as per IS provisions and to the satisfaction of the Independent Engineer.

Entire Project site.

During Construction Contractor IE, SPIU

Risk caused by Force’ Majure

All reasonable precaution will be taken to prevent danger of the workers and the public from fire, flood, drowning, etc. All necessary steps will be taken for prompt first aid treatment of all injuries likely to be sustained during the course of work.

Entire Project site

DuringConstruction Contractor IE, SPIU

Safety Measures During Construction

To ensure safety of the temporary accesses during construction, safety devices shall be installed.

Traffic rules and regulation shall be strictly adhered to local laws.

Workers undertaking various operations during

All construction sites

During construction

Contractor IE, SPIU

Page 19: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

Environmental Impact / Aspect

Mitigation Measures Location Time FrameResponsibility Cross

referenceImplementation Supervision

construction shall be protected by providing helmets, masks, safety goggles, hand gloves and rubber boots etc.

First aid kits shall be provided at construction site for workers to meet minor accidents during construction

Page 20: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

Environmental Impact / Aspect

Mitigation Measures Location Time FrameResponsibility Cross

referenceImplementation Supervision

Hygiene

At every workplace, good and sufficient water supply shall be maintained to avoid waterborne / water-related / water-based diseases to ensure the health and hygiene of workers.

Adequate drainage, septic tanks, soak pits and wastewater disposal shall be provided at workplace.

Preventive Medical care shall be provided to workers.

An action plan shall be prepared and implemented

All Worker’s Camps

During construction Contractor IE, SPIU Annexure 1.4

HIV/AIDS from construction crews

Camps will be located at least 500-1km away from habitation;

The entry and exit from the camps will required to strictly monitored with details of visitors;

Arranging HIV/AIDs awareness campaign in villages at regular intervals;

Crews need to be rotated in the project and they need to be allowed to meet their partner (back home) at regular intervals.

Contractor through the IE need to inform the location of such camps to SPIU in advance.

Construction Camps and Surrounding

Villages

During pre-construction

and construction

stage

Contractor IE/SPIUThe EHS policy of World Bank

and its partners

OPERATION STAGE

Water quality degradation due to road run-off

Silt fencing, Oil & Grease traps, etc. shall be provided at sensitive water bodies to ensure that the water quality is not impaired due to contaminants from road run-off and sediment load. Monitoring shall be carried out as specified in the Monitoring plan

At sensitive water bodies identified.As specified in the monitoring plan

During Operational

StageSPIU SPIU

As per Monitoring

plan in chapter6.

Contamination of Soil and Water Resources from Spills Accidents

Contingency plans to be in place for cleaning up of spills of oil, fuel and toxic chemicals. Spill of oil, fuel and automobile servicing units without adequate disposal systems in place to be discouraged. Accidental spills are potentially disastrous, but its probability is quite low as one of the objectives of this

Entire Project corridor.

During Operational

Stage

SPIU SPIU

Page 21: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

Environmental Impact / Aspect

Mitigation Measures Location Time FrameResponsibility Cross

referenceImplementation Supervision

project is to enhance road safety. The Public will be informed about the regulations on land pollution. Land pollution monitoring program has been devised for checking pollution level and suggesting remedial measures.

Traffic and Accident Safety

Depending on the level of congestion and traffic hazards, traffic management plans will be prepared. Traffic control measures including speed limits to be enforced strictly. Road control width to be enforced. Local government bodies and development authorities will be encouraged to control building development along the highway.

All along the Project corridor

and surrounding

areas.

During Operational

StageSPIU SPIU

Through Operation

Stage.

Road side tree plantation

Trees planted along the corridor shall be maintained for a period of three years. Maintenance works include, watering of the saplings, and all necessary measures for survival of the sapling. The avenue plantation should be completed, maintained and casualties to be replaced. Discouraging local peoples from cutting tree / branches for fuel, cattle food etc. Educating people about the usefulness of trees.

All along the corridor

Immediately from the

planting of sapling

During Operational

StageSPIU SPIU

Monitoring at critical locations

The monitoring of Air, land, water and Noise to be carried out identified critical locations besides locations identified by IE along the project corridor.

SPIU SPIU ESMP Budget.

Noise

HORN PROHIBITED sign post will be enforced Maintenance of noise barriers Discouraging local people from establishing sensitive receptor near the road. The public will be informed about the regulations on noise pollution.

After completion of construction

Throughout and after project development

period

During Operational

Stage

State Police, State

Transport Dept., SPIU

SPIU

Page 22: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

1.5 ENVIRONMENTAL MONITORING PROGRAMME

The Environmental Monitoring Programme has been detailed out in chapter 3. Successful implementation of the Environmental Monitoring Program is contingent on the following:

The Independent Engineer is to request the Contractor to commence all the initial tests for monitoring (i.e. for Air, Water Quality and Noise Levels) early in the Contract to establish 'base' readings (i.e. to assess the existing conditions prior to effects from the Construction activities being felt).

The Independent Engineer is to request the Concessionaire / Contractor to submit for approval a proposed schedule of subsequent periodic tests to be carried out.

Monitoring by the Independent Engineer’s Officer of all the environmental monitoring tests, and subsequent analysis of results.

Where indicated by testing results, and any other relevant on-site conditions, IE to instruct the Concessionaire / Contractor to:

o Modify the testing schedule (dates, frequency)o Modify (add to or delete) testing locationso Verify testing results with additional testing as/if requiredo Require recalibration of equipment, etc., as necessary

o Request the Concessionaire to stop, modify or defer specific construction equipment, processes, etc., as necessary, that are deemed to have contributed significantly to monitoring readings in excess of permissible environmental "safe" levels.

1.5.1 Monitoring of Earthworks Activities

Most of the environmental problems related to the construction works are anticipated to be associated with the earthworks, particularly for the Quarries and Borrow Areas. Details regarding the guidelines and procedures adopted to minimise the environmental impacts of opening, operating and closing of Quarries and Borrow Areas are presented in Annexure 1.1 to 1.4. Other environmental effects associated with the earthworks including the development of adequate temporary drainage to minimise detrimental effects (e.g. erosion) due to run-off, and safety aspects related to Works implementation.

1.5.2 Monitoring of Concessionaire / Contractor's Facilities, Plant and EquipmentAll issues related to negative environmental impacts of the Contractor's Facilities, Plant and

equipment are to be controlled through:The Contractor's self-imposed quality assurance planRegular / periodic inspection of the Concessionaire / Contractor’s plant and equipmentMonthly appraisal of the Contractor.

Other environmental impacts are to be regularly identified and noted on the monthly appraisal inspection made to review all aspects of the Contractor's operation. The officer is to review all monthly appraisal reports, and through the team leader is to instruct the Contractor to rectify all significant negative environmental impacts.

1.6 BUDGET

The environmental budget for the various environmental management measures proposed in the ESMP is detailed in Table 1-2. There are several other environmental issues that have been addressed as part of good engineering practices, the costs for which have been accounted for in the Engineering Cost. The rates adopted for the budget has been worked out on the basis of market rates and the Schedule of rates. Various environmental aspects covered/will be covered under engineering costs are listed below:

Turfing and Pitching of slopesConstruction of slope protection works as retaining walls; breast walls toe walls, drains, and

gabions.Construction of roadside amenities as bus stops etc.

Page 23: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

Table 1-2: Environmental Budget

Item No. Component Description Unit Quantit

yUnit cost

(Naira)

Total cost (Naira)Detailed

Cost Cost

(Million)1 MITIGATION / ENHANCEMENT COST 

1.1Horticulture

Compensatory Re-plantation of trees for timber grade trees @30 trees per km and compensation for 2 tree to be cut in Sash forest area and timber grade trees @5 trees in other sections of project road.

No. 3900 2000.00 78,00,000.00 7.8

1.2 Bamboo tree guard as per design provided by the engineer No. 4000 1000.00 40,00,000.00 4.0

1.3 Compensation for Economic Trees COVERED IN ARAP

1.4 SoilProviding Oil Interceptors as per design and drawing at vehicle parking areas and as per directions of the Environmental Specialist / Environmental Engineer of the Engineer.

Nos. 5 1,00,000.00 5,00,000.00 0.5

1.5 Soil Erosion Protection Measures for Soil Erosion like retaining wall, breast wall, turfing , vegetative cover etc. To be Covered in Engineering Cost

1.6 Water Quality Silt Fencing around soil stockpiled near water bodies and at areas identified by the engineer. m 150 4000.00 6,00,000.00 0.6

1.7 Noise Barrier Provision of Noise barriers in the form of compound walls m 50 6000 3,00,000.00 0.3TOTAL MITIGATION / ENHANCEMENT COST 13.2

2 MONITORING COST2.1 Construction Stage 

2.1.1 Air

Sampling of Ambient Air Quality for PM2.5, PM10, at 6 locations including the plant and machinery site , once in a season for both dry and wet season for a period of 20 months

No. of Samples 18 10,000.00 1,80,000.00 0.18

2.1.2 Water Quality

Grab sampling, once in a month for culverts culvert location in dry season and twice in a month for wet season and analysis of locations near the cross drainage site for 1.5 years as per the Monitoring Plan. The location of monitoring shall be 10 at major culvert locations for a period of 20 months (12 months dry and 8 months wet)Dry Season: 10x12=120Wet Season: 10x2x8=160Total= 280The parameters to be monitored are TSS and TDS, BOD, COD, E.Coli, Phosphate and Nitrate

No. of Samples 280 10,000.00 28,0

0,000.00 2.8

Page 24: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

Item No. Component Description Unit Quantit

yUnit cost

(Naira)

Total cost (Naira)Detailed

Cost Cost

(Million)

2.1.3 Noise

Monitoring of noise level – weekly at 2 construction camp and once in a season for the other 5 baseline monitoring locations for the 20 months construction period. Camp site samples: 1x4x2x20=160Other areas: 1x5x2x1.5=15Total: 175

Nos. 175 5,000.00 8,75,000 0.875

2.1.4 Soil

Sampling and analysis of soil quality - once in season (dry, wet ) at 10 locations for 20 months of construction periodSamples: 2x10x1.5=30

Nos. 30 20,000.00 6,00,000.00 0.6

2.1.5

Transportation Cost

Transportation cost for monitoring of noise, air and water during construction period for 20 months L.S. - -  3,00,000.00 0.3

Monitoring Cost during Construction Stage 4.7552.2 Operation Stage 

2.2.1 Air

Sampling of Ambient Air Quality and gaseous pollutants (PM10, PM2.5, CO, SOx, NO2) once in a season for 2 seasons (dry and wet) at 6 locations for first 5 years as per the Monitoring Plan

No. of Samples 60 20,000.00 12,0

0,000.00 1.2

2.2.2 Water Quality

Grab sampling, once in a season for 2 seasons at 15 locations (10 Surface and 5 Ground) for every year for the first 3 years as per monitoring plan and parameters as per APHA standard.

No. of Samples 90 20,000.00 18,0

0,000.00 1.8

2.2.3 Noise

Monitoring of noise level - once in a season for 2 seasons in a year for the first 5 years (at baseline monitoring locations) at 5 locations. The monitoring to be carried out for 60 seconds interval for every hour, Day time and Night time

Nos. 50 5,000.00 2,50,000.00 0.25

2.2.4 Soil

Sampling and analysis of soil quality - once in a season for two season (dry and wet) for first 3 years as per the Monitoring Plan at 3 locations

Nos. 18 20,000.00 3,60,000.00 0.36

2.2.5

Transportation Cost

Transportation cost for monitoring of noise, air and water during operation period for first 5 years L.S. -   300,000.00 0.3

Monitoring Cost during Operation Stage for first 5 years 3.91TOTAL MONITORING COST 8.665

3 MISCELLANEOUS COST

3.1 Training Training L.S. -   20,00,000.00 2.0

3.2 Advocacy and Holding meetings for policy planning and subsequent review meetings Year 2 50,000.00 1,00,000.00 0.1

Page 25: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

Item No. Component Description Unit Quantit

yUnit cost

(Naira)

Total cost (Naira)Detailed

Cost Cost

(Million)

Policy Making with Revenue Department, Forest Department, local representatives, NGOs, etc. regarding development controls.

3.3

Administrative Charges including logistics

Maintenance of vehicle with the Environment Cell, Data processing, administrative support, stationery etc. Months 24 1,00,000.0

024,00,000.0

0 2.4

3.4Miscellaneous

Items

Digital Camera for the Environment Cell No. 1 50,000.00 50,000.00 0.05

3.5 Portable sound level meter No. 1 4,00,000.00 4,00,000.00 0.4

TOTAL MISCELLANEOUS COST 4.95TOTAL COST 26.815

Contingency @ 5% on Total Environmental Cost 1.34

GRAND TOTAL28.2

(approx.)

Page 26: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

Chapter 2 IMPLEMENTATION & MONITORING SCHEDULE

This chapter provides an assessment of the existing institutional arrangement within SPIU and, reflects on capacity building / training issues that need to be addressed to ensure timely implementation of ESMP. The institutional arrangement proposed for this project has been presented here with newly defined roles and responsibilities. The responsibility of implementing the mitigation measures lies with the SPIU, Osun State. All construction activities being taken up by the contractor through International Competitive Bidding. The Independent Engineer shall monitor the implementation of the work on behalf of SPIU. The contractor will be responsible for planning all Environmental and Social Management Plan (ESMP) activities. In the pre-construction phase of the project the concessionaire shall study the ESMP to identify environmental issues and arrive at a suitable strategy for implementation.

2.1 ENVIRONMENTAL CELL, SPIU

SPIU already has an organizational and institutional capacity at the headquarters created to meet the requirements for implementation of the environmental mitigation measures in the ESMP. As part of the project it is envisaged that they will continue to:

Monitor progress of the implementation of the ESMP measures in consonance with the timeline for the project within the allotted budget;

Maintain interaction with the various other statutory bodies like Federal Ministry of Environment and Forest Department and Land Revenue Department;

Interact with the Environmental Expert of the Independent Engineer on the state of the environment and mitigation and enhancement measures adopted;

Occasionally inspect the environmental measures being implemented by the Contractor;Report progress of works, both in terms of physical progress and quality for transmission to

statutory authorities such as the Ministry of Environment and Forests;Document and disseminate good practices, bottlenecks and their resolution during the

implementation of environmental measures.

2.2 IMPLEMENTATION ARRANGEMENTS

The SPIU is responsible for the implementation of the provisions made within the ESMP through its site offices. The services of Independent Engineer will be procured to assist the site offices for monitoring the environmental aspects of the project during implementation. The organization chart for implementation arrangements is shown in Figure 1-1.

2.2.1 Independent Engineer (IE)

The Independent Engineers (IE), to be procured through International Competitive Bidding (ICB) shall assist the SPIU with the implementation of project, once the project documents are ready. The Environmental Expert of the IE shall be the key personnel to ensure the successful implementation of ESMP provisions. Since ICB procurement is envisaged, the selected consultants are expected to have the necessary professional(s) to tackle the issues that the project is likely to bring up. The Environmental Specialist of the Independent Engineer will be a key position, which can be leveraged to ensure that the contractor complies with the various ESMP requirements.

In case it is not feasible the field engineers supervising construction can be trained on environmental aspects, who then shall perform additional duty of apprising the Team Leader and the Environmental Specialist of any significant development on environment.

2.2.2 Contractor

Page 27: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)For effective implementation and management of the ESMP, The BOT / Annuity concessionaire shall contrive to establish a Safety, Health and Environment (SHE) Cell headed by an Environment Officer to deal with the environmental issues of the project. This officer shall interact with the contractor, SPIU, IE and other line departments to ensure that the mitigation and enhancement measures mentioned in the ESMP are adhered. The Environmental officer of the concessionaire shall be the interface between the Environmental Specialist of IE and the Environmental Officer of the contractor. His prime responsibility shall be to apprise the Environmental Specialist of the IE about the ground conditions. He shall also procure the requisite clearances and the NOCs for the project and shall also strictly supervise that the contractor adheres to the ESMP. The environmental officer can also look after the additional charges of safety and health.

Box 2-1: Qualification and Responsibilities of Environmental Officer of Independent Engineer

Qualifications & Experience Postgraduate in Environmental Science / Environmental Management / Zoology / Botany /

Ecology / Environmental Planning / degree in Civil Engineering with specialisation in environment.

5 years of total experience with a minimum of 3 years in the implementation of ESMP of highway projects and an understanding of environmental, health and safety issues.

Prior practical experience in State and National Highways would be an advantage.

Roles & Responsibilities He / She shall be reporting directly to the Chief Project Manager of the Concessionaire. Primarily responsible for implementation of the ESMP on site and ensuing that the

environmental quality is meeting the standards laid down by Federal ministry of Environment and other related authority.

The EO shall implement the ESMP by assigning the necessary resources (manpower, money and machinery) and attend such meetings as are required for the effective implementation of the ESMP on site.

He shall maintain a “Complain Register” to record any grievances from members of public. He shall maintain a register of all road side trees planted and present within ROW. The EO shall be the interface of the concessionaire with the client and the IC.

2.2.3 Contractor

Execution of works will be the responsibility of the contractor. The contractor shall employ an Environmental Officer whose qualification and responsibilities shall be as per Box 2.2. The contractor shall be responsible for both the jobs done by the petty contactor (if Sublet) as well by him. In both the cases the concessionaire will implement the environmental measures (either through the contractors or themselves). This has been done with a view to ensure that road construction and environmental management go together.

Box 2-2: Qualification and Responsibilities of Environmental Officer of Contractor

Qualifications & Experience Postgraduate in Environmental Science / Environmental Management / Zoology / Botany /

Ecology / Environmental Planning / Environmental Engineering. 3 years of experience with a minimum of 2 years in the implementation of ESMP of highway

projects and an understanding of environmental, health and safety issues. Prior practical experience in State and National Highways would be an advantage.Roles & Responsibilities The Environmental Officer shall report directly to the Resident Construction Manager / Project

Manager so that the pertinent environmental issues that he raises are promptly dealt with. He shall also have a direct interaction with the Environmental Expert and the Environmental

Officer of the IC and the concessionaire respectively. Monitor / implement measures laid out in the ESMP and or as directed by the IE for the work

executed both by petty contractors and the contractor.

Page 28: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region) Provide key inputs in the development of the Contractors’ implementation plan for all

construction activities, including haulage of material to site, adhering to the requirements of the ESMP and getting approval of concessionaire and the IC on the same before start of works.

Ensure that the regulatory permissions required for the construction equipment, vehicles and machinery (given in the ESMP) have been obtained and are valid at all times during the execution of the project.

Prepare / fill up the environmental and safety related forms given in the ESMP Prepare Safety Plans, Emergency Response Plans and Quarry Management and other safety,

health and environment related Plans for approval of the IC and the concessionaire. Identify locations for siting construction camps and other plants, machinery, vehicles and

equipment, as well as locations for storage and disposal of wastes, both from the construction camps and from the site and obtain approval for the same from the concessionaire and the IC.

Detail out site-specific environmental mitigation and enhancement measures and obtain approval of concessionaire and the IC for the same

Carry out the measurements of environmental mitigation and / or enhancement works and prepares bills for the same for approval and payment through the Concessionaire’s Environmental Officer

Ensure that the safety of the workers and other site users is not compromised during construction

Ensure that adequate monitoring facilities are available for collecting samples of all discharges from the Contractor’s plants, equipment and camps

Verify the extent of environmental compliance at sites from where the Contractor is procuring the material – quarries, sand and suggest appropriate mitigation measures, if required

Responsible for implementation of safety and health regulations if also acting as safety officer

The environmental officer shall have a small environmental, health and safety team to help him in implementing the ESMP. These team members may / may not report to him / her directly but shall apprise him of all the incidents and mark a formal report of any incident having an impact on the Health, Environment and Safety issues.

Duty Officers (DO)

The Duty Officers shall, on day to day basis, monitor the Project Facilities and report to the EO on activities that adversely affect the environment in the vicinity.

Supervisors

They shall take the necessary mitigation measures.

Plant Engineer

The Plant Engineer has the responsibility of managing and controlling plant and machinery and fleet of vehicles shall ensure that the environment is not degraded at his plant site. Even though the Environmental Officer shall routinely monitor to detect any negative issues due to operations and bring it to the knowledge of Plant manager for taking rectification works. In case of emergency the Plant Engineer shall immediately notify the Environmental officer for necessary actions.

2.3 REPORTING SYSTEM

Reporting system provides necessary feedback for project management to ensure quality of the works and that the program is on schedule. The rationale for a reporting system is based on accountability to ensure that the measures proposed as part of the Environmental Management Plan get implemented in the project. Reporting system for the suggested monitoring program operates at two levels as:

Reporting for environmental condition indicators and environmental management indicators Reporting for operational performance indicators at the SPIU site level.

Page 29: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)The reporting system will operate linearly – contractor who is at the lowest rung of the implementation system reporting to the Concessionaire, who in turn shall report to IE and the SPIU as per figure 1-1. All reporting by the concessionaire shall be on a quarterly basis, while the reporting time of the contractor shall be decided upon by the concessionaire. The SPIU Site Office will be responsible for setting the targets for the various activities anticipated during construction phase in consultation with the IE/SC and obtaining agreement from the Contractor after mobilisation but before beginning of works on site. The contractor will report from then on regarding the status on each of these. The SPIU Site Office will monitor the activities through its own staff or the consultant’s Environmental Specialist after it has obtained the Contractor’s report with the Consultant’s remarks on it during the construction phase. During the operation phase, the supervision as well as reporting responsibilities will lie with the SPIU Site Office.

Table 2-3: Summary of Reporting of Environmental components and Responsibilities

Format No. Item Timing

Independent Engineer SPIU PIU / Site office

Supervision Reporting Overseeing / Compliance

CONTRACTOR MOBILIZATION AND SITE CLEARANCE

M1

Reporting by contractor to IC for dumping locations &

construction and labour camp site

Before start of construction As required Quarterly As required

M2Reporting by contractor to

IC for construction and labour camp site

Before start of construction As required Quarterly As required

M3 Target sheet for Tree cutting

Before start of work As required After

cutting As required

M4 Reporting for borrow areas

Before start of construction As required Quarterly As required

CONSTRUCTION PHASE

C1 Target sheet for Pollution Monitoring

As per Monitoring Plan As required After

Monitoring As required

C2 Top soil Conservation Before start of work As required Quarterly As required

OPERATION PHASE

O1 Target sheet for Pollution Monitoring During Operation As required After

Monitoring As required

O2 Redevelopment of Borrow Areas

After completion of usage of

Borrow AreaAs required After

Monitoring As required

O3 Survival Rate of Trees During Operation As required After Monitoring As required

2.4 ENVIRONMENTAL CAPACITY BUILDING

Training of staff will be done at a number of levels. Some short-term training is required for the Environment Manager, other staff members of the Environment Unit and the contractor staff to raise their levels of environmental awareness. The training can be conducted by either some external agency or through the help of in-house expertise of the SPIU and the consultants and help of Federal Ministry of Environment and World Bank. In the long-term training, special environmental issues will be examined and likely solutions provided to the Environment Unit.

The main focus of future training programmes has to be on implementation with special ESMP basis. Since project preparation is drawing to a close, the officials can concentrate on the progress of the project. The following modules can be taken up:

Page 30: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

Table 2-4: Modules for Training

Sl. No.

Timing Target Group Mode of training Short Description Responsibilit

y

1

After finalization of Contracts for Civil Works

Members of the Osun-SPIU site office, Environmental Specialist of the IE, Concessionaire and the Environmental staff of the Civil Contractor

Lectures, Presentations, Discussions

Overview of responsibilities The roles and

responsibilities of the IE and the Contractor

Reporting arrangements

Contractual obligations, Environmental Protection and Social Development

External Agency or

SPIU

2.During

implementation

Members of the SPIU site office, Counterpart staff from other departments such as Revenue, Forests, etc.

Lectures, Discussions,Presentations

,Role Play

Inter-Departmental Co-ordination

Clearance requirements and prescribed procedures

Expectations of other departments – documentation and follow-up

Developing formats for ease of reporting

External Agency,

Consultants, SPIU

Page 31: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

Chapter 3 ENVIRONMENTAL MONITORING PROGRAM

Environmental monitoring is an effective tool in making necessary recommendations and adopt suitable control strategies so that menace of rising environmental pollution could be minimized and a relief be extended to the people including labours in case of any damage caused under occupational health hazards. The monitoring is necessary for the following reasons:

To assess what impacts have occurred; To evaluate the performance of mitigation measures proposed in the ESMP. To ensure that the conditions of necessary consent and approvals are adhered to. To suggest improvements in management plan, if required To see that benefits expected from the EA are achieved as the project proceeds. To meet legal and community obligations.

3.1 PERFORMANCE INDICATORS (PI) OF MONITORING

The physical, biological and social components, which are significant in affecting the environment at critical locations, have been suggested as Performance Indicators. The following specific environmental parameters can be qualitatively measured and compared over a period of time and therefore selected as Performance Indicators for monitoring due to their regulatory importance and the availability of standardized procedures and relevant expertise.

Ambient Air Quality Noise Levels Water Quality Soil Quality Plantation and Survival Rate

3.2 MONITORING OF PERFORMANCE INDICATORS3.2.1 Ambient Air Quality (AAQ) Monitoring

The baseline air quality in these project sections do not show any significant pollution as the areas is still in a virgin condition. However, with the construction of roads there is estimation of movement of heavy vehicles during the construction phase as well chance of increase in induced traffic during the operation phase.

The major increase of pollution in the region during the construction phase would be dust as the existing roads are earthen in nature. Hence constant monitoring of PM10 and PM2.5 may be required. These parameters are to be monitored at selected locations such as plant and machinery sites, concrete mixer site excavation works, etc. starting from the commencement of construction activity. The chance of increase in other pollutants like SO2, NOx and CO but are estimated to be negligible and will be intermittent in nature during the construction stage.

However, during the operation stage monitoring is required to be done for all the parameters like Particulate Matter (Size less than 10micron or PM10), Particulate Matter (Size less than 2.5 or PM2.5), Sulphur Dioxide (SO2), Oxides of Nitrogen (NOx) and Carbon Monoxide (CO). These parameters need to be monitored at the first 5 years of the operation stage to establish a data bank to ensure that the project has not made any significant impact to the nearby settlements and vegetation. The monitored results are to be checked with the standards of FMEnv/State Ministry of Environment.

3.2.2 Ambient Noise Monitoring

The measurement for monitoring the noise levels to be carried out at sensitive locations and at construction sites along the project road in accordance to the Ambient Noise Standards of FMEnv/State Ministry of Environment. Sound pressure level would be monitored on twenty-four hour basis.

Page 32: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)3.2.3 Water Quality

Water quality of local water resources that is used by local community shall be monitored.

The water quality during the construction phase shall be monitored at the major culvert construction site at the downstream mainly for pH, total solids, total suspended solids, total dissolved solids. In addition, the parameters like BOD, COD, Phosphate, Nitrate as well as E.Coli be monitored during the construction stage.

During the operation stage in order to capture information on impact on surface and ground water quality at least a trend shall be set for the first 3 years of the operation stage for 2 seasons in the year for the parameters as suggested in American Public Health Association (APHA)/State Ministry of Environment (Osun).

3.2.4 Soil Quality

The soil quality of the surround fields close to the construction site and plant site will be monitored to understand the impact of soil quality. The physic-chemical parameters recommended for analysis are physical Parameter: Texture, Grain Size, Gravel, Sand, Silt, Clay; Chemical Parameter: pH, Conductivity, Calcium, Magnesium, Sodium, Nitrogen, Absorption Ratio.

3.2.5 Plantation and Survival Rate

The widening and up gradation of the project requires felling of roadside trees. This loss will be compensated by compensatory afforestation. The compensatory avenue plantation shall be made as per the guidelines of forest department. Two times of the tree cutting will be compensatory afforested (cost of the plantation budgeted in ESMP).

3.3 ENVIRONMENTAL MONITORING COST

A separate budgetary provision has been made for implementation of Environmental Monitoring Plan. The environmental monitoring cost is estimated based upon the environmental monitoring program being considered in Table 3.1. A budgetary provision of Naira 4.755 million has been kept for environmental monitoring during construction stages. For operation stage Naira 3.91 Million has been considered for first 5 years.

Page 33: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)Table 3-5: Environmental Monitoring Plan

Environment

Component Pr

ojec

t st

age Institutional Responsibilities

Parameters Standards Locations Frequency Implementation Supervision

Air

Con

str

uctio

n PM10 μg /m3, PM2.5 μg/m3, SO2,

NOX, CO FMEnv/State Ministry of

Environment

Plant site, and at locations of baseline

monitoring

Once in a season for 2 seasons (dry, wet ) for

20 months

Contractor through approved monitoring agency/Lab IE & SPIU

Ope

ratio

n

PM10 μg /m3, PM2.5 μg/m3, SO2,

NOX, CO

At locations of baseline monitoring

Once in a season for 2 season in a year for the

first 5 years.

Contractor through approved monitoring agency/Lab IE & SPIU

Surf

ace

Wat

er Q

ualit

y

Con

stru

ctio

n pH, temperature, DO, BOD, COD, Total Suspended Solid, turbidity, Total Hardness, Coliform/E.Coli

Standard parameters for Surface

water quality as per APHA

and State Ministry of

Environment

At locations of baseline monitoring

Grab sampling, once in a month during dry

season and twice in a month for wet season

for the entire construction period i.e

20 month at 10 locations

Contractor through approved monitoring agency/Lab IE & SPIU

Ope

ratio

n

pH, temperature, Oil &

Grease, Total Suspended

Solid, turbidity, Chlorine, Iron,

sulphate, nitrate

Standard parameters for Surface

water quality as per APHA

and State Ministry of

Environment

At locations of baseline monitoring

Grab sampling, once in a season for 2 seasons at 10 selected locations every year for the first 3 years.

Contractor through approved monitoring agency/Lab IE & SPIU

Gro

und

Wat

er

Qua

lity

Ope

ratio

n

pH, Temperature,

TSS, Total hardness,

Suspended Solid, Chlorine, Iron, Sulphate,

Nitrate

Ground Water Quality Standard as per APHA

At identified location in the settlement

areas

Grab sampling, once in a season for 2 seasons at 10 selected locations every year for the first 3 years.

Contractor through approved monitoring agency/Lab IE & SPIU

Page 34: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)Environ

ment Compon

entPr

oje

ct

stag

e Institutional Responsibilities

Parameters Standards Locations Frequency Implementation SupervisionN

oise

Lev

els

Con

stru

ctio

n Leq dB (A) (Day and Night)

Average and Peak values Ambient

NoiseStandardFMEnv

At equipment yards and at locations of baseline monitoring

Once in a week for the entire construction

period at the construction yard.

Once in a season for the entire construction

period at the baseline locations.

Contractor through approved monitoring agency/Lab IE & SPIU

Ope

ratio

n Leq dB (A) (Day and Night)

Average and Peak values

At locations of baseline monitoring

Once in a season for all the season in every

alternate year for first 5 years,– 60 Seconds

interval for every hour, Day time and Night time

SPIU through approved monitoring agency/Lab IE & SPIU

Soil

Con

stru

ctio

n

Physical Parameter:

Texture, Grain Size, Gravel,

Sand, Silt, Clay; Chemical

Parameter: pH,Conductivity,

Calcium, Magnesium,

Sodium, Nitrogen,

Absorption Ratio

Near Constructionsites along the roadand at locations of baseline monitoring

Once in every season for the construction

period

Contractor through approved monitoring agency/Lab

IE & SPIU

Page 35: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)Environ

ment Compon

Pr oj ec t Institutional ResponsibilitiesParameters Standards Locations Frequency Implementation Supervision

Ope

ratio

n

Physical : Texture, Grain Size, Gravel,

Sand, Silt, Clay; Chemical

Parameter: pH,Conductivity,

Calcium, Magnesium,

Sodium, Nitrogen,

Absorption Ratio

At the baseline monitoring locations

Once in every year for the two season for the

first 3 years.

Contractor through approved monitoring agency/Lab IE & SPIU

Tree

pla

ntat

ion/

gr

een

belt

deve

lopm

ent

Con

str

uctio

n Tree Survival rate

90% TreeSurvival Rate

Throughout theProject in

substantiallycompleted section

Once in a monthContractor through approved monitoring horticulture agency IE & SPIU

Ope

ratio

n

Tree Survival rate

90% TreeSurvival Rate

Throughout theProject stretch Once in three month

Contractor through approved monitoring horticulture agency IE & SPIU

Wat

er B

odie

s

Con

stru

ctio

n

Turbidity in Storm

Water bodies load in receiving

water bodies

As specified by

the engineerWater quality

standards

At the drains,and tanks

construction site/ along the ROW

Dry and wet season Contractor IE & SPIU

Ope

ratio

n

Turbidity in Stormwater

Silt load in receiving water

bodies

As specified by

the engineer /Water quality

standards

At the drains,and tanks

construction site/ along the ROW

Dry and wet season Contractor IE & SPIU

Page 36: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

ANNEXURES

Page 37: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

Annexure 1-1: Guidelines for New Quarry Management

1. Management Plan for New QuarryThe contractor shall prepare a quarry management plan for operation of new quarries and submit it to the IE for approval and necessary actions. The plan shall consist of the following:

1.1 Selection Details1.1.1 Location and Layout

Sketch plans and photographs to be provided along with adequate details: A map and sketch plan of the area showing the location of the proposed quarry site with

respect to the project road, nearby villages, worker accommodation locations along with indicative distances of the different sites from each other and from the road.

A detailed sketch plan of the quarry area showing approach and haulage roads, location of the rock outcrops to be quarried, indicating which sites will be quarried in which year or phase, location of stock piles, location of guard house, perimeter fence, location of water sources, amenities, and any further details.

Photographs of the site

1.1.2 Selection Criteria A brief statement as to how the site was chosen. Alternative sites that were considered to be mentioned. Record any public consultations involved while choosing and what the public concerns

were, if any.

1.1.3 Agreement with landownersStatement of ownership of the land along with lease / purchase agreements.

1.1.4 Licenses and permitsContractor to state the licences and permits that are necessary for operation, and attach them as appropriate.

1.2 Operation1.2.1 Method of extraction

A brief method statement of extraction indicating the techniques to be used, use of explosives if any, if so how are the charges laid, how often the blasting shall be done, etc.

Appropriate reference should be made to the contractor’s safety manual. A copy of the operator’s licence to handle explosives should be submitted to the IC.

1.2.2 Loading and haulageContractor to describe the process in a few sentences of loading of rocks fragments; means of transportation to site.

1.2.3 Crusher PlantPer say there is no such crusher plant is expected in the project, hence the chances of fugitive emission is less. Concrete mixers will however be used in the project.

1.2.4 Storage of explosivesContractor to state where these are to be procured from, where they will be stored and how the supply of explosives will be kept secure (if they are to be kept off site, state what precautions will be given for transportation).

1.2.5 ProductsA list of aggregate sizes and any other products from the quarry. Make sure the sketch map states where these will be stock piled.

Page 38: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

1.2.6 Testing and quality assurance Refer quality assurance plan of contractor if any. If not, contractor to provide details of sampling frequency, who takes the does the testing,

which standards are to be complied with, and any further pertinent details.

1.2.7 Water sourcingContractor to indicate the operations that shall need water, and its source (an indication on the sketch map will suffice).

1.2.8 Safety Contractor to divulge safety measures to the IE. Ensure that workers at the quarry sites are aware of the appropriate sections of the safety

plan.

1.2.9 Workers AccommodationContractor to provide details of how many workers will be accommodated on site and what the accommodation arrangements and standard will be.

2. Environmental Management 2.1 Environmental Management during Operation2.1.1 Removal of trees and plants

Contractor to describe briefly the floral species that have had to be removed (it will be helpful give local names if English or scientific names are not known), and roughly how many.

2.1.2 OverburdenContractor to state where this will be deposited (indicate on the sketch map), and what methods will be taken to contain it, if any.

2.1.3 Silt managementContractor to state how silt arising from quarry operations will be managed, e.g. provision of a silt retention pond, and show where this is on the sketch map. Say how the silt retention pond will be managed (i.e. how often it will be dredged).

2.1.4 Surface water drainageIf it will be necessary to provide drainage channels, contractor to show on the sketch map where these are and confirm that they will be kept free of blockages.

2.1.5 Soil and water contaminationContractor to list sources of possible contaminants to the soil (fuel stores, etc) and what will be done to control it (minimise spillages, control leaks from plant, etc).

2.1.6 Air pollution What are the sources of air pollution? Details of air pollution control measures in each case. Details of worker protection equipment along with appropriate reference to the safety

plan.

2.1.7 NoiseSources of noise, distance from settlement, labour camp and proposed mitigation to the population / workers exposed.

2.1.8 TrafficImpact of quarry operations on traffic and how this may be controlled.

2.1.9 Approach roadContractor to state whether this will be maintained, and if so in what condition.

Page 39: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

2.2 Environmental Management at Closure of the site2.2.1 Dismantling and removal of machinery

Contractor to state whether and when this shall be done.

2.2.2 Slope stabilisation and / or protectionMeasures taken to protect the slope and to guard against any possible serious rock fall, or any measures to safeguard against hazards like this.

2.2.3 Rehabilitation Rehabilitation plan of the quarry. The contractor shall be responsible for the Redevelopment Plan prior to completion after

five years, during the defect liability period. The IC and the APRDC shall be responsible for reviewing this case of redevelopment prior to the issuing the defect liability certificate.

2.2.4 Hand-overTerms of hand-over of the quarry site to the owner/authority at the end of its use.

2.2.5 Removal of debris and solid wasteConfirmation of Contractor in removal of debris and solid wastes and disposal at a suitable site.

For each aggregate-cum-quarry sand source, the plan should be the same. The table below gives the format:SI. No. Item Unit Detail

sRemarks by

IE, if any1. Name / identity of the location2. Nearest project road Chainage.3. Name of the owner4. Area involved m2

5. Existing land use (verification from land records with revenue department)

6. Land use of the area surrounding the proposed site including a map

7. Access roads – existing conditions, proposed development and maintenance

8. Tree cutting and vegetation clearance if any, along with compensation measures

Nos.

9. Arrangement with the owner (agreement with land owner should be attached as an Annexure)

10. Quantity of material to be withdrawn vis-a-vis the material available

Cum

11. Particular areas to be quarried should be clearly identified12. Machinery & equipment to be used13. Drainage plans 14. Top soil management 15. Description of the operating practices to be adopted.16. Health facilities

17. Safety provisions made including fire protection systems and the availability of different personal protective equipment

18. Monitoring plans for air, noise and water quality

19. Copy of the license from Mining & Geology, Police & Fire dept.

20. Conditions laid down in the clearances / licenses and plans to ensure compliance

21. Information on whether or not the quarry will be closed under this project. If yes, the proposed closure & restoration plan.

Page 40: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

SI. No. Item Unit Detail

sRemarks by

IE, if any

22. Concerns of the local people living in the immediate / near vicinity should be identified and appropriates measures should be reflected

23. Photograph of the quarry prior to commencing operations.24. Sketch of the layout of the quarryAttach Photograph of Proposed Site, Location Map, Consents, licenses, safety plan, tree compensation plan, restoration plan, drainage plan, monitoring plan, Agreement with land owner etc. as annexure

Submitted Checked & Approved

Signature SignatureName NameDesignation DesignationContractor Independent Engineer

Page 41: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

Annexure 1.2: Guideline for Rehabilitation of Quarries and Borrow Areas

Quarries and Borrow Areas

The contractor shall use materials from the existing and licensed quarry areas only. In case any new quarries are opened by the contractor, he shall secure permissions for the same and shall follow the rehabilitation plan.

The objective of the rehabilitation programme is to return the borrow pit sites to a safe and secure area, which the general public should be able to safely enter and enjoy. Securing borrow pits /quarry sites in a stable condition should be a fundamental requirement of the rehabilitation process. This could be achieved by filling the quarry / borrow pit floor to approximately the access road level.

It is important to plan restoration from the outset and coordinate restoration with quarrying activities. In addition to the bio-diversity issues, land planning considerations are also taken into account when defining a rehabilitation project in order both to preserve the environment and to generate income for the local communities. In this framework quarry rehabilitation often leads to the creation of wetlands and natural reserves or recreation areas.

Special quarry / borrow pit rehabilitation plan should be specified according to the location and shaping of the mining slopes after exploitation and overburdened dump, with different subsequent uses e.g. forest, meadow, water body etc., the re-greening and replanting methods..

Other criteria which should be followed for rehabilitation of quarry/ borrow pits are as given below:

Quarries and borrow pits will be backfilled with rejected construction wastes and will be given a vegetative cover. If this is not possible, then slopes will be smoothed and depression will be filled in such a way that it looks more or less like the original ground surface.

During works execution, the contractor shall ensure preservation of trees during piling of materials; spreading of stripping material to facilitate water percolation and allow natural vegetation growth; reestablishment of previous natural drainage flows; improvement of site appearance; digging of ditches to collect runoff; and maintenance of roadways where a pit or quarry is declared useable water source for livestock or people nearby. Once the works are completed, and at own expense the contractor and contractor shall restore the environment around the work site to its original splits.

To create a safe environment, the faces of borrow pit excavation sites have to be reduced to a naturally stable slope or be adequately fenced to prevent access to the top and bottom of the faces. Such a fence must be of a height as prescribed under local mine act with a barbed wire top strand designed to exclude the public from the quarry area. Depending on the location of the site presence of a permanent lake is considered to be a satisfactory alternative to a fence.

Appropriate plant species for the planting programme have to be selected in consultation with ecological consultant and local forest department and farm land owners for the loss of economic trees made during the quarry and borrow operations.

Page 42: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

Annexure 1.3: Guidelines for Existing Quarry Management

The Contractor will finalise the locations from the list given by Consultant's for procuring materials. The Contractor shall establish a new quarry only with the prior consent of the Independent Engineer (IE) only in cases when: (i) Lead from existing quarries is uneconomical and (ii) Alternative material sources are not available. The Contractor shall prepare a Redevelopment Plan for the quarry site and get it approved by the IE. The construction schedule and operations plans to be submitted to the IC prior to commencement of work shall contain a detailed work plan for procuring materials that includes procurement, transportation and storage of quarry materials.

CONSTRUCTION STAGE Development of site: To minimise the adverse impact during excavation of material following measures are need to be undertaken:

i) Adequate drainage system shall be provided to prevent the flooding of the excavated area ii) At the stockpiling locations, the Contractor shall construct sediment barriers to prevent the

erosion of excavated material due to runoff iii) Construction of offices, laboratory, workshop and rest places shall be done in the up-wind of

the plant to minimize the adverse impact due to dust and noise. i) The access road to the plant shall be constructed taking into consideration location of units

and also slope of the ground to regulate the vehicle movement within the plant. iv) In case of storage of blasting material, all precautions shall be taken as per The Explosive

Rules, 1983.

QUARRY OPERATIONS INCLUDING SAFETY

SI. No.

Item Unit Details

Remarks by IE, if

any1. Name / identity of the location2. Nearest project road Chainage.3. Name of the owner4. Area involved

5.

Arrangement with the owner (agreement with the third party / contractor should be attached as an Annexure and should necessarily require the adaptation of good quarry management practices - a description of the requirements should be included)

Cum

6. Quantity of material to be withdrawn vis-à-vis the material available

8. Machinery & equipment to be used Cum

9. Drainage plans10. Top soil management 11. Description of the operating practices 12. Health facilities

13. Safety provisions made including fire protection systems and the availability of different personal protective equipment

14. Conditions laid down in the clearances / licenses and plans to ensure compliance

15. Monitoring plans for air quality 16. Information on whether or not the quarry will be closed under

this project. If yes, the proposed closure & restoration plan.17. Photograph of the quarry prior to commencing operations.

19. Sketch of the layout of the quarry

Page 43: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

SI. No.

Item Unit Details

Remarks by IE, if

any

i) During excavation, slopes shall be flatter than 20 degrees to prevent their sliding. In cases where quarry strata are good and where chances of sliding are less this restriction can be ignored.

ii) In case of blasting, procedure and safety measures shall be taken as per The Explosive Rules, 1983

iii) The contractor shall ensure that all workers related safety measures shall be dune as per guidelines for Workers and Safety.

Topsoil will be excavated and preserved during transportation of the material measures shall be taken to minimize the generation of dust and prevent accidents. The IC shall review the quarry site for the management measures during quarry operation, including the compliance to pollution norms.

POST CONSTRUCTION STAGE

The Contractor shall restore all haul roads constructed for transporting the material from the quarries to construction site to their original state.

The IE shall be entrusted the responsibility of reviewing the quarry site for the progress of implementation of Redevelopment Plan.

The redevelopment of exhaust quarry shall be the responsibility of the agency providing the permit to ensure the implementation of Redevelopment Plan.

For existing quarry managed directly by a third party / contractor from whom the contractor is sourcing the materials, the plan should contain the following:Attach Photograph of Proposed Site, Location Map, consents, licenses and Agreement with land owner

REMARKS

Submitted Checked Approved

Signature Signature SignatureName Name NameDesignation Designation DesignationContractor Contractor Independent Engineer

Page 44: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

Annexure 1.4: Guidelines for Siting, Operation & Redevelopment of Borrow Areas

(A) SitingSpecific locations of borrow areas to be used will be identified by contractor based on the recommendations of the ESIA report. In case the contractor or the contractor wants to open any new borrow areas other than mentioned in this report, and then the selection and recommendations for borrow areas will be based on environmental as well as civil engineering considerations.Certain precautions have to be taken to restrict unauthorised borrowing by the contractor and the contractor. No borrow area shall be opened without permission of the Engineer.

Table 1: Probable Borrow Area along the Project Corridor

Sam

ple

no.

Nam

e of

Vill

age

Mat

eria

l typ

e

Site identification Approximate Quantity (Cum)

Ava

ilabl

eLa

nd /

Terr

ain

Surr

ound

ing

Land

/Te

rrai

n

Rem

arks

Nea

rest

Cha

inag

e (K

m.)

Left

/ Rig

ht

Offs

et fr

om

near

est

Cha

inag

e (m

)

Leng

th (m

)

Bre

adth

(m)

Dep

th (m

)

Tota

l (C

um)

(B) Criteria for Evaluation of Borrow Areasi. Existing land use (Agricultural / Barren / Scrub / grazing / any other type)ii. Vegetation / trees to be removediii. Erosion/degradation potential iv. Distance and name of the nearest settlementv. Distance from the nearest surface water bodyvi. Drainage pattern of the areavii. Distance of the nearest Reserve Forest (if any)viii. Distance of the nearest Sacred Tree (if any)ix. Distance from the nearest school / hospital / primary health centrex. Daily / Occasional use of borrow area by the communityxi. Any schemes or avenues for generation of income for adjoining community

(C) Documentation of Borrow PitThe contractor must ensure that following data based must be documented for each identified borrow areas that provide the basis of the redevelopment plan. Chainage along with offset distance Area (in Sq m) Type of Access/width from carriageway Soil Type Slope / Drainage Characteristics Water Table of the area or identify from nearest well etc/ask people Existing Land-use such as barren/agricultural/grazing land Location/Name/Population of Nearest Settlement/Community & distance from Borrow Area/Type

and characteristics of settlement Daily / occasional use of the Borrow Area by the community, if any Identification of any other community facility in the vicinity of the borrow pit

(D) Guidelines for Stripping, Stocking, Preservation of Top Soil

Page 45: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

During the excavation of the borrowing material contractor must ensure that the topsoil from all areas of cutting and all areas to be permanently covered shall be stripped to a specified depth of 150mm and stored in stockpiles. At least 10% of the temporarily acquired area shall be earmarked for storing topsoil. The stockpile shall be designed such that the slope does not exceed 1:2 (vertical to horizontal), and the height of the pile is restricted to 2m..

(E) Guidelines for Enhancement

As far as possible borrow area selected for enhancement shall be on government / community land in the vicinity of settlement. The contractor must ensure that any enhancement design proposed should be workable, maintenance free and preferably worked out in consultation with the community and proposed enhancement materials should be locally available. The borrow area can be developed either of the following:Vegetative Cover:

Vegetative cover must be established on all affected land. Topsoil must be placed, seeded, and mulched within 30 days of final grading if it is within a

current growing season or within 30 days of the start of the next growing season. Vegetative material used in reclamation must consist of grasses, legumes, herbaceous, or

woody plants or a mixture thereof. Plant material must be planted during the first growing season following the reclamation

phase. Selection and use of vegetative cover must take into account soil and site characteristics

such as drainage, pH, nutrient availability, and climate to ensure permanent growth. The vegetative cover is acceptable if within one growing season of seeding: The planting of trees and shrubs results in a permanent stand, or regeneration and

succession rate, sufficient to assure a 75% survival rate; The planting results in 90% ground coverage. The site shall be inspected when the planting is completed and again at one year to ensure

compliance with the reclamation plan.Certificate of Completion of Reclamation Contractors have to obtained certificate of satisfaction from the landowner and submit it to

the Engineer before final payment is to done.

(F) Drawings to be Prepared The contractor have to prepared the drawings showing both cross-section as well as plan of

the identified borrow areas incorporating following inputs: Contours if any, depth if any Location of trees, height, foliage spread and afternoon shaded area on ground Any other existing details at the road / property interface such as signage/railing/etc. Details of immediate surrounding for at least 5m on either sides

(G) Photographs to be IncludeThe contractor must ensure that photographs are to be taken before and after the excavation of borrow materials and also after the implementation of redevelopment plan, incorporating the following: Overall View from access side Any other community resource in the vicinity All spots to be detailed such as access to borrow pit /cluster of existing trees etc.

(H) OUTPUTSThe contractor must ensure based on the above-mentioned guidelines following outcomes must be evolved:

Page 46: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

Working plan Cross Section Longitudinal Section/Elevation of Site Details of all proposed Enhancements including signage etc. BoQ

Page 47: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

Annexure 1.5: Guidelines for Sediment Control

Prior to the start of the relevant construction, the Contractor shall submit to the Engineer for approval, his schedules for carrying out temporary and permanent erosion / sedimentation control works as are applicable for the items of clearing and grubbing, roadway and drainage excavation, embankment / sub-grade construction, culverts and other structures across water courses, pavement courses and shoulders. He shall also submit for approval his proposed method of erosion / sedimentation control on service road and borrow pits and his plan for disposal of waste materials. Work shall not be started until the erosion / sedimentation control schedules and methods of operations for the applicable ' construction have been approved by the Engineer.

The surface area of erodible earth material exposed by clearing and grubbing, excavation, borrow and fill operations shall be limited to the extent practicable. The Contractor may be directed to provide immediate control measures to prevent soil erosion and sedimentation that will adversely affect construction operations, damage adjacent properties, or cause contamination of nearby streams or other watercourses. Such work may involve the construction of temporary berms, dikes, sediment basins, slope drains and use of temporary mulches, fabrics, mats, seeding, or other control devices or methods as necessary to control erosion and sedimentation.

The Contractor shall be required to incorporate all permanent erosion and sedimentation control features into the project at the earliest practicable time as outlined in his accepted schedule to minimize the need for temporary erosion and sedimentation control measures.

Temporary erosion, sedimentation and pollution control measures will be used to control the phenomenon of erosion, sedimentation and pollution that may develop during normal construction practices, but may neither be foreseen daring design stage nor associated with permanent control features on the Project.

Silt Fencing:

Silt fencing may be provided to prevent sediments from the construction site entering into the nearby watercourses. The silt fencing consists of geo textile with extremely small size supported by a wire mesh mounted on a panel made up of angle / wooden frame and post. It is expected a single person will be able to drive the angles by pressing from the top. The frame will be installed at the edge of the water body along which construction is in progress. Silt fencing is proposed for a length of 150m. This is based on the primary survey data inventory of cross drainage structures to be developed/replaced in the project. Depending on the length of the individual water body, the number of units of silt fencing to be installed is decided by the Independent Engineer. A typical drawing of silt fencing is given below:

Page 48: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

Annexure 1.6: Guidelines for Siting & Layout of Construction Camp

(A) SITING

The contractor based on the following guidelines shall identify the location of the construction site. The construction site shall be located:

The construction camps will be located at least 500 m away from habitations at identified sites. The living accommodation and ancillary facilities for labour shall be erected and maintained to standards and scales approved by the resident engineer.

On non-agricultural lands, as far as possible

Not within 1000m of either side of locations of Forest areas.

All sites used for camps must be adequately drained. They must not be subject to periodic flooding, nor located within 300 feet of pools, sink holes or other surface collections of water unless such water surface can be subjected to mosquito control measures.

The camps must be located such that the drainage from and through the camps will not endanger any domestic or public water supply.

All sites must be graded, ditched and rendered free from depressions such that water may get stagnant and become a nuisance.

(B) LAYOUT

A conceptual layout of a typical construction site has been presented in Figure A. The Contractor during the progress of work will provide, erect and maintain necessary (temporary) living accommodation and ancillary facilities for labour to standards and scales approved by the engineer. All temporary accommodation must be constructed and maintained in such a fashion that uncontaminated water is available for drinking, cooking and washing. Safe drinking water should be provided to the dwellers of the construction camps. Adequate washing and bathing places shall be provided, and kept in clean and drained condition. Construction camps are to be sited away from vulnerable people and adequate health care is to be provided for the work force.

Sanitation Facilities: Construction camps shall be provided sanitary latrines and urinals. Sewerage drains should be provided for the flow of used water outside the camp. Drains and ditches should be treated with bleaching powder on a regular basis. The sewage system for the camp must be properly designed, built and operated so that no health hazard occurs and no pollution to the air, ground or adjacent watercourses takes place. Compliance with the relevant legislation must be strictly adhered to. Garbage bins must be provided in the camp and regularly emptied and the garbage disposed off in a hygienic manner

Shelter at Workplace: At every workplace, there shall be provided free of cost, four suitable shelters, two for meals and two others for rest, separately for use of men and women labourers. The height of shelter shall not be less than 3m from floor level to lowest part of the roof. Sheds shall be kept clean and the space provided shall be on the basis of at least 0.5m2 per head.

Canteen Facilities: A cooked food canteen on a moderate scale shall be provided for the benefit of workers wherever it is considered necessary. The contractor shall conform generally to sanitary requirements of local medical, health and municipal authorities and at all times adopt such precautions as may be necessary to prevent soil pollution of the site.

First aid facilities: At every workplace, a readily available first-aid unit including an adequate supply of sterilized dressing materials and appliances will be provided as per the Factory Rules. Workplaces

Page 49: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)

remote and far away from regular hospitals will have indoor health units with one bed for every 250 workers. Suitable transport will be provided to facilitate taking injured and ill persons to the nearest hospital. At every workplace an ambulance room containing the prescribed equipment and nursing staff will be provided.

Health Care Facilities: Health problems of the workers should be taken care of by providing basic health care facilities through health centres temporarily set up for the construction camp. The health centre should have at least a doctor, nurses, duty staff, medicines and minimum medical facilities to tackle first-aid requirements or minor accidental cases, linkage with nearest higher order hospital to refer patients of major illnesses or critical cases.

The health centre should have MCW (Mother and Child Welfare) units for treating mothers and children in the camp. Apart from this, the health centre should provide with regular vaccinations required for children.

Page 50: Nigeria: Environmental and Social Management …documents.worldbank.org/.../E19650v40EA0P0070063B0… · Web viewGrab sampling, once in a month for culverts culvert location in dry

Federal Ministry of Agriculture and Rural Development

Detailed engineering design, safeguards studies and Preparationof bidding documents for prioritized 222.83km rural roads in osun state of Nigeria

ESMP (ILE-IFE Region)FIGURE A: TYPICAL LAYOUT OF CONSTRUCTION CAMP