NGCP Tdp Vol3 Part1 SO (Final)

download NGCP Tdp Vol3 Part1 SO (Final)

of 258

Transcript of NGCP Tdp Vol3 Part1 SO (Final)

  • One G r i d .

  • 1

    Table of Contents

    Disclaimer. pages 2 Foreword.. pages 3 Preliminaries.. pages 4 Telecommunication pages 6 - 58 SCADA . pages 59 - 158 Protection.... pages 159 - 187 Infrastructure... page 188 - 244

    SOME... pages 246 - 267

    September2009Volume3

  • 2

    Disclaimer

    The Transmission Development Plan (TDP): Volume III: Part 1 (System Operations) was prepared and published solely for information purposes. While System Operations (SO)/NGCP, to the best of its

    knowledge, has used the most accurate data available, and has used utmost prudence in the use of this information, nothing in this document can be or should be taken as a recommendation in respect of any

    possible investment or business decision. This document does not claim to contain all the information that a prospective investor, grid user or potential participant to the electricity market, or any other person or interested parties may require for making decisions. In preparing this document it is not possible nor is it

    intended for SO/NGCP to have considered the investment objectives, financial situation and particular needs of each person who uses this document.

    In all cases, anyone proposing to rely on or use the information in this document should independently verify and check the accuracy, completeness, reliability and suitability of that information and the reports and other information relied on by SO/NGCP in preparing this document, and should obtain independent and specific

    advice from appropriate experts.

    In the same manner, SO/NGCP does not make representations or warranty as to the accuracy, reliability, completeness or suitability for particular purposes of the information in this document. Persons reading or

    using this document acknowledge that SO/NGCP and/or its employees shall have no liability (including liability to any person by reason of negligence or negligent misstatement) for any statements, opinions, information or

    matter (expressed or implied) arising out of, contained in or derived from, or for any omissions from, the information in this document, except insofar as liability under any statute of the Republic of the Philippines

    cannot be excluded.

  • 3

    Foreword

    This plan is System Operations (SO) roadmap in participation to transmission development of NGCP required to meet the objectives of its task: to operate and maintain the power transmission grid of the

    country. This plan was envisioned in order to support the sustenance of the existing infrastructures, facilities, systems and equipment which are under the responsibility of SO. As a commitment for ensuring a reliable, efficient, economical and quality operation of the transmission Grid, NGCP will be investing to upgrade,

    expand and replace existing infrastructures, facilities, systems and equipment. These upgrading, expansion and replacement initiatives are expected to enhance system and equipment performance and ensure the reliability,

    security and quality of transmission service in the country.

    This edition of the TDP Volume III will be released by System Operations (SO) and Metering Services Group. Part 1 will cover planned and developed capital expenditures relating to System Operations. Part 2 will cover

    capital expenditures relating to Metering Services.

  • 4

    Chapter.01 Preliminaries

    About System Operations System Operations (SO) functions, as the System Operator of NGCPs power transmission grid involve the management and operation of various power sources and transmission facilities. To carry out this function, SO is responsible in dispatching the proper loading of generating plants and dispatching transmission lines in order to achieve a secure and reliable power system. It also determines the appropriate configuration of the existing transmission network and other related transmission facilities at all times. This function covers the three major regions of the Philippines, namely Luzon, Visayas and Mindanao. In order to undertake the above services, SO operates and manages various facilities, infrastructure, systems and equipment strategically located in Luzon, Visayas and Mindanao which include among others:

    1. National Control Center, Regional Control Centers and Area Control Centers. 2. Telecommunication network infrastructure. 3. Supervisory Control and Data Acquisition (SCADA) systems and equipment. 4. Information and Communication Technology (ICT) infrastructure. 5. Network Protection systems and equipment. For business management purposes, SOs obligations can be grouped into several key service areas described as follows:

    1. System operations dispatching generation and managing the transmission system. 2. Power quality - providing the appropriate and acceptable level of quality electricity service in accordance

    with the requirements set forth in Grid Code. 3. Grid reliability - ensure a secured and reliable transmission network, reliable infrastructure and efficient

    system and equipment. 4. Market operations support - providing data, information and other support required by Wholesale

    Electricity Spot Market (WESM) operations. 5. Maintenance and technical support - providing corrective and preventive maintenance services, operations

    planning and technical services.

    Structure of the TDP Volume III The 2010 TDP Volume III consists of two (2) parts. Part 1 contains the capital expenditure of System Operations while Part 2 contains capital expenditure related to Metering Services. Volume III: Part 1 is consists of development plan of System Operations as explains by several functional disciplines of System Operations, as follows: A. Telecommunication B. SCADA C. Protection D. Infrastructure E. SO Managed Equipment (SOME)

    Each of these disciplines provides explanation of the development plans related to its respective capital expenditures:

  • 5

    a. Preface - describes the objectives and credible basis of the development plan. b. System Profile - describes the existing system profile by discussing and assessing the inventory, status

    and conditions of systems and equipment. It also presents the current problems and issues. c. Requirement Analysis - discusses the additional requirements from various aspects that affect the

    systems and equipment. d. Planning Criteria - explains the capital expenditures drivers on developing these program plans. e. Project Development - provides the discussions on how the capital expenditures were developed and

    established. The capital expenditures describes in Volume III: Part 1 are totally independent from Volume I and II. These CAPEX projects covers the NGCP's proposed upgrading, rehabilitation, replacement, repair and/or maintenance of SCADA, Telecommunication systems, Infrastructure and System Operations (SO) Management Equipment used in the management of the national transmission and dispatching generation, including support to market operations and arrangement for ancillary services. It covers the plan for the upgrade, rehabilitation and replacement of secondary equipment/system for the planning horizon. It excludes those projects already integrated into the project package contained in Volume I and II for repair and maintenance including budgeting and procurement process of secondary protection system.

  • 6

  • 7

    A. PREFACE Most significant among the System Operations (S.O.) assets is the NGCP telecom networkrepresenting over 80% of S.O.s present value (which also includes the SCADA/EMS system, network protection supervisory and test facilities, Grid operations tools and civil infrastructure). NGCPs private telecom network exists to meet operational needs mainly in the absence of responsive public infrastructure around its areas of operation and has proven to be the most secureyet most economicalmeans of servicing various mission-critical applications throughout the lives of its transmission line assets. Among other services, the NGCP telecom network provides communication facilities for line protection, SCADA/EMS, telephony, MIS/office automation and metering and billing applications. Because the pace of development vis--vis geographic peculiarities of the electricity Grids in Luzon, Visayas and Mindanao varied significantly, the characteristics of the respective telecom systems and facilities differ appreciably among each other. While Luzons attention is more on establishing and maintaining security of existing links, Mindanao is more concerned on yet putting up almost-the-most-basic communication access among it substations. Visayas, on the other hand, is midwayaiming to interconnect non-contiguous optical segments to build a more reliable backbone. As the open market integrates, the respective characteristics of the telecom networks in Luzon, Visayas and Mindanao become more similar as common performance parameters are adopted and the same operating philosophies are shared. The 2010-2019 CAPEX projects identified in this volume reflect this trend as an integrated NGCP telecom network develops over the course of the study period. A.1 Objective

    Plan telecom network development within the next 10 years to support continuity of Grid operations and associated businesses;

    Program addition, replacement, reconfiguration and retirement of telecom facilities in line with said network plan but excluding those telecom facilities programmed as complement for new T/L projects outlined in Volume 1.

    A.2 Credible Basis

    Power demand forecast and corporate thrusts defined in Volume 1, consistent with ERC references and guidelines;

    Philippine Grid Code; ERC-defined asset lives of telecom network elements and pertinent qualifications by NGCP on

    current applications.

  • 8

    B. SYSTEM PROFILE B.1 Statistical data

    B.1.1 Luzon Existing Telecom Facilities

    In Luzon, the telecom backbone has a general bandwidth of 155 Mb/s (STM1) with a fair number of segments operating at the higher capacity of 622 Mb/s (STM4). A combination of optical paths (embedded along the transmission lines) and microwave radio hops forms the said backbone, which also connects Luzon to Visayas and Mindanao via two (2) routesthrough Mindoro in the West and via Bicol in the East. Substations and offices which are not located along the backbone route are connected through spur links. Existing microwave radio spur links range in capacity from 8 Mb/s (4E1) to 155 Mb/s (STM1). There are also substation-to-substation narrow-band power line carriers (PLC) mainly to carry line protection signaling but which also provide low speed data or voice communication when there are no other cost-effective means to deliver such basic services (e.g., when the substation or power plant is located in difficult terrain). Bandwidth is optimized through the use of traffic managers such as the circuit-switched PABX systems (for legacy telephony and modem connections) and routers (for the modern IP-based applications). Operations and maintenance are organized through the use of network management systems and other remote sensing and supervision facilities; performance monitors ensure that the right quality of service is delivered. As an ultimate backup system, S.O. operates and maintains a UHF radio network in Luzon which also serves as mobile dispatch system for O&M in its transmission line maintenance activities.

    NGCP also maintains telecom infrastructure in the form of the outside plant for the (transmission-line-embedded) optical links and PLCs, telecom antenna towers and radio repeater buildings. Table B.1.1 lists the major elements in the Luzon Grid telecom network indicating their respective conditions against current issues of concern.

  • 9

  • 10

    Figure B.1.1a Luzon Telecom Network Table B.1.1.a Existing Telecom Facilities, Luzon (Part 1 of 3)

    NETWORK ELEMENT

    ECO. LIFE CLASS E.L. OUTLOOK

    SDH 18 hops

    0

    M/W RADIO 15 yrs (ERC)

    PDH 51

    hops 12

    hops

    While the SDH radios deployed in the backbone are below the ERC economic life of 15 years, 33% no longer have spare-parts support. Redundancy (1+1) protection is no longer available for some links due to lack of spares. Part of the installed base thus needs to be retired yearly to provide source of spares for the rest. As for the PDH, 47% of those within the ERC 15-year life are without spares support and forced retirement needs to be resorted to produce spares. Some PDH spur links are also filled to capacity and must be upgraded to accommodate additional applications through the service access points.

    >24 cores

    1560 kms 0

    OPGW 50 yrs (ERC)

  • 11

    Table B.1.1.b Existing Telecom Facilities, Luzon (Part 2 of 3)

    NETWORK ELEMENT

    ECO. LIFE CLASS E.L. OUTLOOK

    ACCESS MUX 10 yrs 117 nodes

    103 nodes

    The access multiplexers serve as the service access points to the telecom backbone. Application interfaces should therefore be compatible with current subscriber demand. The 47% of installed base which are beyond economic life cannot meet present IP-application needs and other data-com requirements. Such are beyond upgrade and must be replaced to be responsive to demand up to 2019.

    ROUTER 8 yrs 24

    nodes 19

    nodes

    Routers are the traffic management nodes for IP traffic. 49% of the router base are beyond economic life and no longer has the benefit of manufacturer support. The present use of CISCO proprietary routing protocol also limits the usefulness of other telecom network elements with built-in routing functions.

    MOBILE NETWORK UHF

    REPEATERS 12 yrs 19 12

    Over 38% of UHF radios in mobile network repeater systems have exceeded economic life. Not all spare parts are now available in the market and equipment have to be progressively retired to provide source of spare parts for remaining installed base.

    MOBILE NET-

    WORK 0 10

    UHF SUBSCRIBER

    RADIO STATIONS

    8 yrs

    POINT-TO-

    POINT 4 4

    The UHF radio network is our backup communication facility for gird supervision and control in case the backbone fails; it also serves as the dispatch facility for O&M T/L maintenance activities. Over 77% of the radio equipment have exceeded economic life, necessitating us to program staggered replacement to guard against run-to-failures without spares on hand

    PABX 8 yrs 34 14

    Around 30% of PABX equipment have exceeded their economic lives; while obsolescence may be addressed by retiring part of the installed base (to source spares), replacements of telephony equipment will be in line with our IP migration program.

    48VDC POWER SUPPLY/

    CHARGER 12 yrs 113 37

    Telecom equipment depends on reliable DC systems. The 25% of chargers which are beyond the effective service lives should be addressed by a timely replenishment program to avoid traffic downtimes resulting from interrupted power supply systems.

    Access Mux, Routers, UHF radio, PABX and DC supplies are not included in the ERC asset lives assessment--calculated economic service lives are based on NGCP assessment.

  • 12

    Table B.1.1.c Existing Telecom Facilities, Luzon (Part 3 of 3)

    NETWORK ELEMENT

    ECO. LIFE

    CLASS E.L. OUTLOOK

    48VDC BATTERY BANK

    8 yrs 110 41

    Replacements for battery banks which have exceeded their respective design lives should be on hand at the instant that measured capacity have degraded below efficiency thresholds. There is an estimated 27% of installed base that should be addressed under this category.

    GENERATOR SET 6 yrs 15 28

    Generators are necessary as AC backup systems where there is no substation service backup power as in repeater stations. The 65% over their natural service lives are programmed to be replaced or rehabilitated, depending on the extent of effect of depreciation.

    ANTENNA

    TOWER 63 0

    Retrofitting works are conducted on existing telecom towers when additional load (i.e., antenna systems) will be installed.

    INFRA-STRUCTURE

    50 yrs (ERC)

    REPEAT-ER BLDG. 36 0

    Expansion work is required in cases where additional equipment has to be housed on account of network reconfigurations or extensions.

    INTEG-RATED 0 1

    NETBOSS is an integrated telecom network management system coordinating the different element managers into a single MMI. Hardware upgrade is necessary to cope with software maintenance and applications development chores.

    ELEMENT MANAG-

    ERS 3 3

    Fault management is done remotely through proprietary element managers which are dependent on manufacturer support for the respective network elements involved.

    QUALITY MANAG-

    ERS 1 0

    Performance/quality management systems measure and control network conditions that affect quality of service. Our bandwidth manager checks traffic congestion.

    NETWORK MANAGEMENT

    SYSTEM 5 yrs*

    REMOTE SENSING 2 1

    Online optical fiber monitoring systems are presently installed to determine location of fiber breaks as soon as they occur so that corrective and security measures may be implemented as soon as possible.

    Generators are not included in the ERC asset lives assessment--calculated economic service lives are based on NGCP's. Battery life is based on average design lives of installed battery banks. * Network Management Systems 5-year economic life pertains to that of hardware/electronics only.

  • 13

    B.1.2 Visayas Existing Telecom Facilities

    Visayas telecom backbone operates at a bandwidth of 155 Mb/s (STM1). A combination of optical paths (embedded along the transmission lines) and microwave radio hops forms the said backbone, interconnecting the island sub-grids of Leyte, Cebu, Negros, Panay and Bohol. The backbone links Luzon via Panay in the West and via Leyte in the East; Mindanao is connected from Negros through the island of Siquijor at the Southernmost tip of Visayas. Substations and offices which are not located along the backbone route are connected through spur links. Existing microwave radio spur links in Visayas range in capacity from 8 Mb/s (4E1) to 32 Mb/s (E3). There are also substation-to-substation narrow-band power line carriers (PLC) mainly to carry line protection signaling but which also provide low speed data or voice communication when there are no other cost-effective means to deliver such basic services (e.g., when the substation or power plant is located in difficult terrain). Bandwidth is optimized through the use of traffic managers such as the circuit-switched PABX systems (for legacy telephony and modem connections) and routers (for the modern IP-based applications, which now include VOIP and SCADA/EMS communications). Operations and maintenance are organized through the use of network management systems and other remote sensing and supervision facilities; performance monitors ensure that the right quality of service is delivered. NGCP also maintains telecom infrastructure in the form of the outside plant for the (transmission-line-embedded) optical links and PLCs, telecom antenna towers and radio repeater buildings. Table B.1.2 lists the major elements in the Visayas Grid telecom network indicating their respective conditions against current issues of concern.

  • 14

    Figure B.1.1b Visayas Telecom Network

  • 15

    Table B.1.2.a Existing Telecom Facilities, Visayas (Part 1 of 3)

    NETWORK ELEMENT

    ECO. LIFE CLASS E.L. OUTLOOK

    SDH 9 hops 0

    M/W RADIO 15 yrs (ERC)

    PDH 18

    hops 7 hops

    While SDH radios deployed in the backbone are below the ERC economic life of 15 years, these have no longer spare-parts support. Redundancy (1+1) protection is not available for some links due to lack of spares. Part of the installed base thus needs to be retired yearly to provide source of spares for the rest. As for the PDH, most of the links are obsolete and under-capacity and need to be replaced.

    >24 cores

    280 kms 0

    OPGW 50 yrs (ERC)

  • 16

    Table B.1.2.b Existing Telecom Facilities, Visayas (Part 2 of 3)

    NETWORK ELEMENT

    ECO. LIFE

    CLASS E.L. OUTLOOK

    PRIMARY 10

    nodes 15

    nodes

    ACCESS MUX 10 yrs

    TRANS-PORT LEVEL

    52 nodes 0

    The access multiplexers serve as the service access points to the telecom backbone. Some have transport capability and may be configured as SDH (backbone) nodes in the future. Of the primary or access-level multiplexers, about 6% are of the T1 (non-regional) standard, are beyond economic life and considered obsolete; the rest are flexible enough to cater to future requirements. Existing transport-level multiplexers are flexible and can even be upgraded to integrate into the network as optical backbone add-drop terminals (OLTE).

    ROUTER 8 yrs 19

    nodes 0

    Presently, there are 19 CISCO routers in support of Corporate MIS, line protection transient recorders, VoIP and video-con services. The number and size of router equipment shall be dimensioned to support physical separation among the SCADA, network protection and Corporate MIS WAN networks. "Open Systems" routing protocol shall be implemented to optimize functionality of telecom complement and a replenishment program to address obsolescence shall be observed.

    CIRCUIT-SWITCHED

    26 nodes 1 node

    PABX 8 yrs

    IP-BASED 2 nodes 0

    Circuit-switched (i.e., legacy) PABX systems shall be retained to optimize service lives. Necessary replacements to cover obsolescence and under-capacity shall, as much as possible, be of the IP technology. IP phones will gradually replace analog ones as the necessary (LAN/WAN) distribution infrastructure is put in place. By 2019, legacy PABX equipment still serviceable shall serve as backup.

    48VDC POWER SUPPLY/CHARGER 10 yrs 31 22

    Presently, DC systems are generally configured with only one battery charger and one battery bank. 41.5% of the battery chargers are beyond their economic livesno longer supported by the manufacturer. Because spare parts are no longer available, gradual replacement of these obsolete chargers is necessary to sustain availability. Also, upgrading to redundant (1+1) systems in key stations must be done to improve reliability, especially where security of fault clearance systems is paramount.

    Multiplexer, router, PABX and power supply equipment are not included in the ERC asset lives assessmentcalculated economic service lives are based on NGCP's.

  • 17

    Table B.1.2.c Existing Telecom Facilities, Visayas (Part 3 of 3)

    NETWORK ELEMENT

    ECO. LIFE CLASS E.L. OUTLOOK

    48VDC BATTERY BANK

    5 yrs 23 21

    47.72% of the battery banks are beyond their respective economic lives. Batteries whose capacities are below 80% should be replaced because they are no longer reliable. Monitoring and periodic replacement of battery banks is necessary to maintain continuity of telecom service during commercial AC power interruption.

    GENERATOR SET 6 yrs 1 16

    Gen sets provide backup AC during commercial power failures. 95% of these gen sets are beyond service lives and 23% may no longer be repaired in case of breakdown due to off-production of spares. Replacement of these gen sets is necessary to ensure continuous and reliable power supply. Additional gen sets are also required for redundancy at remote repeater sites to improve availability of the radio stations.

    ANTENNA TOWER 33 0

    Periodic repainting of the tower and retightening of bolts is being done to prolong the life span of these structures. Some towers will be retrofitted to accommodate additional load when necessary.

    INFRASTRUCTURE 50 yrs (ERC)

    REPEATER BLDG. 22 0

    Periodic rehab is being done to ensure the security of telecom equipment and to prolong usage of these shelters. Repainting, waterproofing and rehab of dilapidated building structures should be done to maintain the functionality of the buildings.

    ELEMENT MANAG-

    ERS 4 7

    Fault management is done remotely through proprietary element managers which are dependent on manufacturer support for the respective network elements involved. There are element managers for the radios, OLTE, multiplexers and SNMP elements.

    QUALITY MANAG-

    ERS 1 0

    Performance/quality management systems measure and control network conditions that affect quality of service. The E1 performance monitoring system is one of these.

    REMOTE SENSING/

    SUPER-VISION

    0 1

    The battery monitoring systems which reports temperature and humidity conditions is aimed at prolonging service lives of expensive stationary battery systems.

    NETWORK MANAGEMENT

    SYSTEM 5 yrs*

    SURVEIL-LANCE 10 0

    Surveillance cameras are installed at various microwave radio repeater stations as part of security measures.

    Generators are not included in the ERC asset lives assessment--calculated economic service lives are based on NGCP's. Battery life is based on average design lives of installed battery banks. * Network Management Systems 5-year economic life pertains to that of hardware/electronics only.

  • 18

    B.1.3 Mindanao Existing Telecom Facilities

    Mindanaos telecom backbone operates at a capacity of 32 Mb/s (E3). The microwave-radio-only backbone connects to Luzon and Visayas via a radio hop between Iligan and the Visayas island of Siquijor. Substations and offices which are not located along the backbone route are connected through spur links. Existing microwave radio spur links range in capacity from 4 Mb/s (2E1) to 32 Mb/s (E3). There are also substation-to-substation narrow-band power line carriers (PLC) meant to carry line protection signaling but which also provide low speed data and voice communication in the absence of microwave radio spur links. Bandwidth is optimized through the use of traffic managers such as the circuit-switched PABX systems (for legacy telephony and modem connections) and routers (for the modern IP-based applications). Operations and maintenance are organized through the use of a network management system; performance monitors like the LAN/WAN bandwidth manager ensure that the right quality of service is delivered. As an ultimate backup system, S.O. operates and maintains a VHF radio network in Mindanao which also serves as mobile dispatch system for O&M in its transmission line maintenance activities.

    NGCP also maintains telecom infrastructure in the form of the outside plant for the (transmission-line-embedded) optical links and PLCs, telecom antenna towers and radio repeater buildings. Table B.1.3 lists the major elements in the Mindanao Grid telecom network indicating their respective conditions against current issues of concern.

  • 19

    FigureB.1.1cMindanaoTelecomNetwork

  • 20

    Table B.1.3a Existing Telecom Facilities, Mindanao (Part 1 of 2)

    NETWORK ELEMENT

    ECO. LIFE CLASS E.L. OUTLOOK

    SDH 0 0

    M/W RADIO 15 yrs (ERC)

    PDH 26

    hops 31

    hops

    While the some of the PDH radios deployed in the backbone are below the ERC economic life of 15 years, 54% no longer have spare-parts support. Redundancy (1+1) protection is no longer available for some links due to lack of spares. Part of the installed base thus needs to be retired yearly to provide source of spares for the rest. PDH spur links are also filled to capacity and must be upgraded to accommodate additional applications through the service access points. Some links which still operate within the government-reallocated 2GHz frequency (for CMTS) must be replaced to avoid interference.

    PLC 8 links 34 links

    PLC/PSE 20 yrs*

    PSE 31

    links 41

    links

    With the exception of a few voice and SCADA channels, PLC's with their associated PSE's are now mainly used for T/L protection. (PSE's are also used independently for interfacing protection relays with other media such as optical fiber and radio.) While ERC lists PLC economic life as 35 years, we understand that the assessment pertains mainly to outside plant, i.e., wave traps, T/L coupling capacitors, line matching units and cable; further, the practical service life depends on reliability and security of operationsperformance measures which are significantly affected by degradation of electronics over time. Thus, to sustain performance targets and ensure grid security, service lives of PLC/PSE's are limited to within their peak operating condition.

    ACCESS MUX 10 yrs 0 51 nodes

    The access multiplexers serve as the service access points to the telecom backbone. The entire portion of the installed base which are beyond economic life cannot meet present IP-application needs and other data-com requirements. Such are beyond upgrade and must be replaced to be responsive to demand up to 2019.

    ROUTER 8 yrs 7

    nodes 0

    The routers are the traffic management nodes for IP traffic. Although most of the routers are still within the economic life, 71% of the router base model is already obsolete. The present use of CISCO proprietary routing protocol also limits the usefulness of other telecom network elements with built-in routing functions.

    OLTE, Access Mux and Routers are not included in the ERC asset lives assessment--calculated economic service lives are based on NGCP assessment. * PLC/PSE 20-year economic life pertains to that of terminal equipment only.

  • 21

    TableB.1.3bExistingTelecomFacilities,Mindanao(Part2of2)

    NETWORKELEMENT

    ECO.LIFE CLASS E.L. OUTLOOK

    VHFRADIOS 7yrs 0 16

    Fordispatch:themostreliableandfastestmeansofcommunicationintheregion.However,themodeofcommunicationisbroadcasted;hence,thereisnoprivacy.Thisismosteffectiveintimesofemergencysuchasgridblackout,powerrestoration&coordinationpurposes.5%ofVHFbase/mobileradioarestillof1974technologywhiletheremainingareof1994.Mostoftherepeaterradiosareinstalledin1995butstilloperatingasofthistime.Mostoftheseradiosareoperatingbelowperformancelevelduetodegradationofelectronicparts.Sparesarenolongeravailableinthemarket/outofproduction.

    PABX 8yrs 032

    nodes

    AmajorcomponentinMindanao'stelecomsystemisthetelephonyorvoicecommunicationnetwork.WiththeexpansionofthenationwideIPnetworkandthemovetowardsanIPbasedtelephonysystem,these"legacy"equipmentwouldbegraduallyupgradedorreplacedtotakeadvantageofamoreoptimizedbandwidthutilizationrealizedfromIPtransportsystems.

    GENERATORSET 6yrs 0 22

    GensetsprovidebackupACpowersupplyduringACcommercialpowerfailure.Alloftheinstalledgensetsarebeyonditsservicelifeandsparesarealreadyoutofproduction.

    ANTENNATOWER

    53

    Tobeabletorealizethefulleconomiclivesofantennatowers,constantrepaintingofthetowerisnecessary;thiswillalsomaintainthedistinguishinginternationalorangeandwhitewarningcolorsspecifiedbytheAirTransportationOfficeauthorities.

    INFRASTRUCTURE50yrs(ERC)

    REPEATERBLDG.

    33

    Repeaterbuildingsaremainlymadeofconcretebutstilldeterioratewithtime.Sincetheyaremostlyinstalledinelevatedlocations,thebuildingsdeterioratefasterduetoconstantexposuretoextremesinweatherconditions.Insectinfestationsalsocauseaccelerateddeteriorationofwoodenstructures.Regularmaintenanceisnecessarytosustainsatisfactorybuildingcondition,ensuringsufficientprotectionforthetelecomequipmenthousedtherein.

    NETWORKMANAGEMENT

    SYSTEM5yrs* 0 1

    LoneNMSisusedtomanageproprietaryPDHradiosandmultiplexers.Althoughthesystemisstilloperational,thehardwareisalreadypronetooccasionalshutdownsandthesoftwareneedstobeupgradedtoaddresscompatibilityissueswithnewerversionsofnetworkelements.

    VHF, PABX, power supply, and generators are not included in the ERC asset lives assessment--calculated economic service lives are based on NGCP's. * Network Management Systems 5-year economic life pertains to that of hardware/electronics only.

  • 22

    C. REQUIREMENTS ANALYSIS

    Grid expansion, current business demand, technology direction and the need to replenish equipment to sustain operations are the bases for which we have determined our requirements within the course of the study period 2010-2019. C.1 Transmission Grid Extension

    Telecom requirements as a result of transmission grid extension are addressed through the telecom components of transmission line projects defined in Volume 1.

    There are, however, deficiencies in existing telecom facilities which were a result of

    under-programming of the necessary telecom complements in previous or current transmission line expansion projectsthe appropriate adjustments to reverse such deficiencies shall be included as among the requirements in this program.

    This volume does not include provisions for interconnections of new customers

    anticipated or notgiven that the program for such customer-specific facilities are governed by a separate mechanics.

    C.2 Corporate Business Needs

    Current business requirements vis--vis the state of pertinent telecom facilities are assessed in the following tables. The telecom elements are further analyzed according to four (4) basic parameters of the service: capacity (or bandwidth), route protection (or security), network reach and traffic management. Table C.2.1a Network Protection Needs versus Telecom System

    RESPONSIVENESS OF EXISTING TELECOM SYSTEM

    BANDWIDTH/ CAPACITY

    ROUTE PROTECTION

    NETWORK REACH

    TRAFFIC MANAGEMENT

    64 kb/s station-to-station links require minimum bandwidth and occupy the least backbone space; but use of PLC-only to connect some stations preclude of differential protection

    Multiple routes and media are requiredto comply with Protection Philosophy

    Tele-protection links are generally put in place as requisite to Grid extension or connection; but there is need for direct optical links for differential relays in line with Protection Philosophy

    No traffic management is required since point-to-point connection is sensitive to dynamic rerouting

    INADEQUATE INADEQUATE INADEQUATE GOOD TILL 2019

  • 23

    Table C.2.1b SCADA/EMS Needs versus Telecom System especially in Mindanaoneed

    Table C.2.1c Telephony Needs versus Telecom System

    RESPONSIVENESS OF EXISTING TELECOM SYSTEM

    BANDWIDTH/ CAPACITY

    ROUTE PROTECTION

    NETWORK REACH

    TRAFFIC MANAGEMENT

    Growth in bandwidth requirements is expected to flatten as use of IP telephony makes more efficient use of backbone capacity

    Because some of the nodesincluding major substations and regulating plantsare connected only to the network by radio spur links or radial optical (flat-ring) connections, path redundancy is not complete

    As with teleprotection and SCADA, telephony links are standard facilities put in place upon Grid connection

    Need to shift to IP-based traffic management systems (versus circuit-switched PABX systems)to complement migration to IP telephony

    GOOD TILL 2019 INADEQUATE GOOD TILL 2019 INADEQUATE Table C.2.1d MIS, Office Automation, Billing and Metering Needs versus Telecom System

    RESPONSIVENESS OF EXISTING TELECOM SYSTEM

    BANDWIDTH/ CAPACITY

    ROUTE PROTECTION

    NETWORK REACH

    TRAFFIC MANAGEMENT

    Need to increase spur link capacity to ease bottlenecks at service access points (4E1s and 8E1s are not enough)

    Alternate WAN routes are requiredto optimize backbone utilization for high bandwidth but less-priority applications

    Need to extend IP connectivity for business and automation applications to all stations

    Traffic management functionality is built into transport and access facilities; only lookout is need to replenish end-of-life network elements

    INADEQUATE INADEQUATE INADEQUATE GOOD TILL 2019

    Table C.2.1e O&M Mobile Dispatch Needs versus Telecom System

    RESPONSIVENESS OF EXISTING TELECOM SYSTEM

    BANDWIDTH/ CAPACITY

    ROUTE PROTECTION

    NETWORK REACH

    TRAFFIC MANAGEMENT

    Some RTU links still use PLC routes, to set up more backbone links to address bandwidth requirements

    Need to implement mesh connectivity to increase datacom accessibility and thus ensure data sufficiency

    SCADA extensions are provisioned in programmed Grid expansions as well as in iterconnection of new customers

    Need to shift to IP-based traffic management systemshand-in-hand with more pervasive use of IP datacoms

    INADEQUATE INADEQUATEn GOOD TILL 2019 INADEQUATE

  • 24

    RESPONSIVENESS OF EXISTING TELECOM SYSTEM

    BANDWIDTH/ CAPACITY

    ROUTE PROTECTION NETWORK REACH

    TRAFFIC MANAGEMENT

    O&M dispatch requirements are voice only and use minimal backbone bandwidth as mobile traffic is mostly local

    Duplex traffic are RF broadcast and does not involve multiple routes for protection

    There are still significant blind spots in network coverage

    Subscriber base per operation area is low-density class only and does not require special traffic managers or multiplexers

    GOOD TILL 2019 GOOD TILL 2019 INADEQUATE GOOD TILL 2019

    Following is the applications-versus-requirements responsiveness matrix, summarizing the above assessments. Table C.2.2 Summary: Business Application Needs versus Telecom System

    From the above table, our present assessment of the NGCP telecom network is that: (a) bandwidth of the transmission system is insufficient to carry all telecom traffic, (b) path protectioni.e., network securityis significantly inadequate, (c) there is need to extend service access points to some key applications and (d) the shift in the nature transport mechanism (i.e., from TDM to IP) necessitate new

    traffic management systems to optimize backbone bandwidth. We may assume from the following graph that the capacity of the existing backbone is just enough to meet NGCP applications demand without the need to expand within the next 10 years. (That is: there is no over-capacity in NGCPs backbone.)

  • 25

    Figure C.2.1 Telecom Demand Analysis, 2010-2019

    However, as we have discussed above, bottlenecks in the existing service access pointsi.e., network connections to the plants/substationsprevent remote nodes from optimizing use of the backbone bandwidth. Thus, in ensuring adequacy of capacity of the network to carry applications demand, continuity of the desired bandwidth should be established by providing the appropriately-sized spur links. As much as the need to provide sufficient bandwidth, the need for alternate (1+1) physical paths for important network nodes should also be addressed in establishing a resilient-enough telecom transmission system. In NGCPs SDH network, a general deficiency in this area is manifested in the absence of physical ring protectionmainly because of the need to still retrofit OPGW in old transmission linesintended to prevent traffic loss in case of single-point failures (e.g., cut OPGW, power supply outage in a common node). Following is an illustration of a non-protected versus ring or 1+1 protected optical network connection.

  • 26

    Fig. C.2.2 Non-protected versus Protected Telecom Paths

    C.3 Technology Evolution

    Consideration of the effects of technology trends in programming facilities to meet applications demand is important in our effort to optimize returns by availing of the most efficient technology which will deliver the required services, avoiding early obsolescence, selecting which standards and policies to adopt and determining how to adapt existing processes with the anticipated changes in the business environment. Table C.3 Technology Direction versus Telecom Developmental Plan

    C.4 Equipment Replacement

    Determining the optimum point to replace a facility or equipment should be given due consideration in programming plant acquisitions in order to maximize asset service lives. Diligence in regularly assessing the responsiveness of existing facilities against service requirementsvis--vis industry standards as well as market and manufacturing trendsis

    TECHNOLOGY DIRECTION TELECOM REQUIREMENTS 2010-2019

    1. USE OF IP FOR BANDWIDTH EFFICIENCY AND TRAFFIC MANAGEMENT CONVENIENCE

    MIGRATION TO IP BASED TELEPHONY USE OF IP-BASED SCADA (RTU) DATACOMS

    2. DECREASING MANUFACTURING COSTS, THUS CHEAPER COSTS OF REPLACEMENTSTENDENCY FOR FUNCTIONS TO BE OPTIMIZED ACCORDING TO NEAR-TERM NEEDS

    DECENTRALIZATION OF PROCESSING AND CONTROL FUNCTIONSUSE OF DISTRIBUTED ARCHITECTURE.

    MODULARIZATION

    3. CONVERGENCE THROUGH STANDARDIZATION

    INTEGRATION OF ROUTING FUNCTIONS IN TELECOM EQUIPMENT.

    INCORPORATION OF ACCESS PORTS AND MUX FUNCTIONS INTO SDH NODES

    4. CHEAPER COST OF EMPLOYING HYBRID POWER SUPPLY SYSTEMS

    DESIGN OF POWER SUPPLY SYSTEMS LESS DEPENDENT ON COMMERCIAL POWER SERVICE

  • 27

    necessary to ensure that future acquisitions are optimized (service lives are maximized and values of features are realized).

    Table C.4 Equipment Replacement in Telecom Developmental Plan

    CAUSE FOR REPLACEMENT TELECOM REQUIREMENTS 2010-2019

    1. ECONOMICSCOST OF CONTINUED OWNERSHIP HAS EXCEEDED COST OF REPLACEMENT

    RETIREMENT OF OBSOLETE MUX AND RADIO EQUIPMENT WHOSE COST OF SPARE PARTS AND/OR UPGRADES ARE TOO EXPENSIVE

    2. NO SPARE PARTS SUPPORT

    PHASED REPLACEMENTS OF RADIOS, OLTES AND MUX EQPT. TO PROVIDE SOURCE OF SPARES FOR REMAINING INSTALLED BASE

    3. SIGNIFICANT DEGRADATION OF PERFORMANCE

    REPLACEMENTS OF PLC/PSES AND POWER SUPPLY COMPONENTS EXCEEDING PROGRAMMED EFFECTIVE (PEAK-PERFORMANCE) SERVICE LIFE

    4. UNDER-CAPACITY

    REPLACEMENTS/UPGRADES OF M/W RADIO SPUR LINKS THAT ARE BOTTLENECKS IN THE DELIVERY OF BANDWIDTH TO ACCESS POINTS

    5. NO CAPABILITY TO ADDRESS STANDARD/PREVALENT PROTOCOLS (TECHNOLOGY OBSOLESCENCE)

    REPLACEMENTS OF ACCESS MUX EQPT. WITHOUT IP APPLICATION PORTS UPDATE OF TEST EQPT. SUPPORT TO ADDRESS NEW PERVASIVE DATACOM PROTOCOLS AND DIAGNOSTIC/ MEASUREMENT METHODS

  • 28

    1

    4

    SWD

    D. PLANNING CRITERIA

    The facilities program meant to meet needs identified in our requirements analysis above shall be governed by the following philosophies and policies consistent with corporate mandate.

    D.1 Technology Philosophy

    Decision to adapt to technology directions should be weighed against impact on core

    business vis--vis economics. Reliability and security precedes functionality.

    Adopt open-systems standards in management, traffic processing and interfacing to

    increase flexibility to technology shifts and changes in organizational models as well as to optimize access to best of breed.

    Prefer green technology as part of corporate social commitment.

    D.2 Technology Development Route

    Network infra shall continue to accommodate and prioritize real-time channels

    allocated for grid protection signaling. To optimize bandwidth, IP-based traffic management facilities shall be established and

    switched-circuit traffic managers shall be gradually retired.

    IP telephony shall be implemented hand-in-hand with the shift in traffic management paradigm to optimize infra utilization.

    Routing protocol shall be migrated from proprietary to open systems to take

    advantage of the increasing prevalence of routing functionality in modern telecom facilities.

    The energy-efficient (and generally cheaper) split-type radio technology shall be

    adopted where feasible (e.g., for up-to-STM1 radio links) to optimize radio transmitter power, eliminate waveguide-caused problems and minimize dependence on air-conditioning requirements (and reduce failure rates resulting from lack thereof).

    ADM (add-drop-multiplexing) and terminal functionalityas well as application access

    capabilityshall be incorporated in new SDH nodes to limit failure points and maximize manageability.

    D.3 Policies

    Philippine Grid Code Protection Philosophy

    Spare Parts Management Policy

    Government regulatory policies on use of radio frequency spectrum

  • 29

    Network security policy: physical separation of SCADA and protection networks from admin/MIS network

    E. PROJECT DEVELOPMENT

    Implementation of the facilities plan requires that the most efficient mode and scale of asset acquisition be established as basis for the CAPEX program. Both new projects and replenishments involve planning for service lives of assets according to anticipated optimum generated values from depreciation, with due consideration to established factors of safety.

    E.1 Guidelines

    Infrastructure components shall be dimensioned to meet expected growth in requirements up to the end of expected economic lives.

    Facilities shall be dimensioned according to an 85% fill of expected maximum capacity for contingency.

    Replacements of operational network components shall be phased such that there is

    minimum traffic interruption.

    Turnkey implementation (i.e., through Work Orders) shall be employed where:

    (1) Projects cannot be carried out using existing resources, or (2) There is a need for technology transfer.

    Replenishments/ upgrades of network components that have exceeded economic lives

    shall be implemented using in-house engineering resources (i.e., shall be procured as GPE) to minimize implementation time and synchronize construction with operational priorities.

    For purposes of depreciation programming, CAPEX projects shall be classified as:

    (1) Expansion : New Asset (2) Upgrade/Rehab : Add Value to Existing Asset (3) Replacement/Replenishment : Replace (Depreciated) Asset

    E.2 Economic Analysis

    Purpose: since telecom projects of NGCP are indirectly productive (i.e., with no definitive marketable outputs), economic analysis aims to establish the least-cost option in delivering the required services.

    Alternatives from which to determine optimum allocation of resources are defined according to the following aspects:

  • 30

    (1) Method of project implementationi.e., turnkey or in-house; (2) Means of establishing and sustaining facilitiesi.e., lease or own; (3) Distribution of benefits; e.g., which technology offers the flexibility to

    accommodate the most applications and satisfy the most operational objectives using shared infrastructure.

    E.3 Safety and Security Concerns

    For maximum security, physically separate networks shall be provided for both teleprotection and SCADA applications.

    Repeater station security systems shall be reinforced to protect telecom backbone integrity.

    Long-haul optical links shall preferably employ the use of the more physically-secure

    transmission line-embedded fibers, such as in OPGW and OPPC, over ADSS (given current experience in ADSS maintenance).

    Telecom towers shall be constructed with utmost consideration in the safety of

    maintenance personnel; retrofitting of safety facilities shall be addressed where necessary among existing towers.

    E.4 Specifications Program (General Principles)

  • 31

    Table E.4.1 Specifications of Major Network Elements, 2010-2019

    ELEMENT 2010 2019 RATIONALE 1. Backbone

    Capacity STM1 (155Mb/s)

    STM1 (155Mb/s)

    Forecasted demand by 2019 is about 120Mb/s only; (expensive) higher capacity implementation in M/W radio segmentswhich comprise significant portions of the backbonewould be premature (i.e., not cost-justified)

    2. OPGW 24 Cores 48 Cores Only about 4 cores max allotted for dedicated relay communication but rapidly decreasing difference in installed cost of higher-density OPGW warrants increase in fiber cores; mechanical and electrical parameters limit size variance, though

    3. M/W Radio Spur Links

    4E1~E3 E3~STM1 Primarily because of the need for separate SCADA, admin and protection IP networks, higher capacity tributaries are needed

    4. SDH Topology

    Flat Ring Physical Ring Physically redundant (1+1) paths would provide required telecom backbone security

    5. Sync System GPS GPS GPS was the original choice for synchronization because of its relatively cheap cost of implementation and maintenance vis--vis the proven reliability

    6. WAN Topology

    Partial Mesh Full Mesh IP Path redundancy would optimize access to SCADA, protection and MIS nodes by avoiding single points of failure

    7. IP Bandwidth Management

    Shared Network

    Physically separate networks

    SCADA, Protection and Admin/MIS shall have physically distinct networks for optimum security

    8. PABX/ Telephony

    Circuit-switched

    IP Legacy telephony switches will be gradually replaced by IP-based systems to maximize bandwidth efficiency and simplify traffic management

    9. Protection Signaling Equipment

    Priority-coded

    Simultaneous independent commands

    To ensure integrity of discrete protection signals and simplify analysis of events, new PSE shall be specified with independent signal processing per port

    10. IP Routing Proprietary (CISCO)

    Open Systems Migration from EIGRP to OSPF would optimize utility of telecom facilities (equipped with routing function), simplify (hierarchical) network management and reduce costs of ownership

  • 32

  • 33

    Fig. C.4.1a NGCP Telecom Network, December 2009

    Fig. C.4.1b NGCP Telecom Network, December 2010

  • 34

  • 35

    Fig. C.4.1c NGCP Telecom Network, December 2011

  • 36

    Fig. C.4.1d NGCP Telecom Network, December 2012

  • 37

    Fig. C.4.1e NGCP Telecom Network, December 2013

    Fig. C.4.1f NGCP Telecom Network, December 2014

  • 38

  • 39

    Fig. C.4.1g NGCP Telecom Network, December 2015

    Fig. C.4.1h NGCP Telecom Network, December 2016

  • 40

  • 41

    Fig. C.4.1i NGCP Telecom Network, December 2017

    Fig. C.4.1j NGCP Telecom Network, December 2018

  • 42

    Fig. C.4.1k NGCP Telecom Network, December 2019

  • E.5 Project Description Table Table E.5.1 Luzon Telecom Projects

    REPLACEMENTS AND REPLENISHMENTS 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 TOTAL

    1. Microwave Radios and Antenna Systems

    1.1 SDH MW Radio System 18.9 12.0 12.0 12.0 12.0 12.0 78.9 1.2 PDH MW Radio System 7.0 12.0 20.0 10.0 12.0 12.0 12.0 12.0 7.0 104.0 1.3 Spare Antenna & Radome 4.2 3.4 4.5 5.0 5.0 22.1

    1.4 Spare Parts for Microwave Radio 15.4 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 60.4 2. OLTE 2.1 Nortel TN4XE OLTE (STM-4) 9.0 9.0 9.0 12.0 12.0 51.0 2.2 Nortel TN1X OLTE (STM-1) 7.0 7.0 5.0 19.0 2.3 Siemens SMA OLTE (STM-1) 7.0 7.0 7.0 21.0 2.4 Spare Parts for OLTE 3.0 3.0 3.0 3.0 3.0 5.0 5.0 5.0 5.0 35.0 3. PLC/PSE Systems 3.1 BBC ETI-22 25.2 15.0 10.0 5.0 55.2 3.2 ABB ETL-42 10.0 15.0 15.0 15.0 10.0 20.0 20.0 105.0 3.3 Siemens ESB2000i 5.0 5.0 5.0 5.0 5.0 25.0 3.4 Protection Signaling Eqpt. 6.0 6.0 6.0 18.0 3.5 Spare Parts for PLC/PSE 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 54.0 4. MUX and Accessories 4.1 Telco Access60 MUX 2.0 4.0 3.0 3.0 3.0 3.0 18.0 4.2 ABB FOX515/512 MUX 2.0 2.0 2.0 2.0 2.0 2.0 3.0 3.0 3.0 21.0 4.3 Terminal blocks & MDF 0.7 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 5.2 4.4 IP/E1 Wireless Extender 1.0 1.0 1.0 1.0 1.0 5.0

  • 4.5 Spare Parts for MUX Eqpt. 4.6 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 58.6 5. Routers and Bridges

    5.1 Replacement of CISCO 2600 & 2500 Series 1.4 1.4 1.4 1.4 1.4 2.0 2.0 2.0 13.0

    5.2 Spare Parts for Routers & Bridges 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 13.5 6. OPGW and Accessories 6.1 Spare OPGW & Accessories 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 90.0 7. PABX 7.1. Spare Parts for legacy PABX 2.4 3.0 3.0 8.4 7.2. Spare Parts for IP Telephony 3.0 3.0 3.0 5.0 5.0 5.0 5.0 29.0 8. UHF Radio Equipment

    8.1. Replacement of UHF antenna system, coaxial cable and its ancillaries 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 4.5

    8.2. Replacement of point to point UHF communication equipment 1.0 1.0 1.0 3.0

    8.3. Replenishment of UHF radio spare parts 1.6 2.0 2.0 2.0 3.0 3.0 3.0 3.0 3.0 3.0 25.6 9. Test Equipment

    9.1 Replacement of degraded test instruments for Fiber Optic Systems 1.3 0.1 3.0 3.0 3.0 10.4

    9.2 Replacement of degraded test instruments for MW/UHF Radio Systems 3.0 3.0 0.5 3.0 3.0 3.0 0.5 3.0 3.0 22.0

    9.3 Replacement of degraded test instruments for PLC/PSE Systems 2.4 1.4 1.5 0.7 1.5 0.8 1.5 9.8

    9.3 Replacement of degraded test instruments for Datacom & IP 2.0 2.2 3.0 2.0 2.0 2.2 3.0 2.0 2.2 20.6

  • 9.3 Replacement of degraded test instruments for Electrical Installations 1.0 1.0 1.0 1.0 4.0 10. Power Supply System 10.1. 48VDC Rectifier/Charger 13.9 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 121.9

    10.2. Spare Parts for Rectifier/ Charger 3.4 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 48.4 10.3. Battery Banks 14.2 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 86.2 TOTAL 111.6 128.4 135.5 147.9 122.4 120.2 125.2 107.8 127.5 140.2 1,266.7

    REHABS AND UPGRADES 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 TOTAL 1. MIGRATION TO IP TELEPHONY 5.6 5.0 5.0 5.0 5.0 25.6 2. UPGRADE OF SYNCHRONIZATION SYSTEM 6.0

    6

    3. WAN RECONFIGURATION & MIGRATION TO OSPF 5.0

    5

    4. UPGRADE OF NETWORK MANAGEMENT SYSTEM 4.6 25.2 10.2 12.0 4.6 15.0 10.0

    81.6

    6. HYBRID POWER SUPPLY SYSTEM 7.8 8.0 8.0 8.0 8.0 8.0 8.0 8.0 63.8 7. UHF/VHF NETWORK a. Upgrade of UHF repeater radio 17.5 17.5

    b. Acquisition of transportable UHF repeater for selected North & South Luzon O&M 9.3 12.4

    21.7

    c. Acquisition of UHF subscriber mobile radio 1.2 1.3 1.5 1.6 1.8

    7.4

  • 8. GROUNDING SYSTEM 4.2 2.0 2.0 2.0 2.0 12.2 46.9 44.5 10.0 32.5 23.5 6.2 34.4 8.0 21.8 13.0 240.8

    EXPANSIONS 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 TOTAL

    1. OPTICAL GROUND WIRE (OPGW)

    a. BACNOTAN TAP-IN (7Km) 5.5 5.5 b. SAN JOSE-TAYABAS (120Km) 84.0 84.0

    c. TAYABAS-DASMARIAS (105Km) 74.0

    74.0

    d. SAN MANUEL-BINGA (30Km) 25.0 25.0

    e. SANTIAGO-TUGUEGARAO (118Km) 84.0

    84.0

    2. OLTE COMPLEMENT FOR OPGW 1.5 3.0 3.0 3.0 5.0

    15.5

    3. SDH MW RADIO BACKBONE EXTENSION

    WESTERN LUZON : 4 LINKS (HERMOSA-BOTOLAN) 28.0

    28.0

    4. EXPANSION OF WIDE AREA NETWORK

    MIS/BUSINESS 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 18.0

    SCADA (NCC, 4-ACC, 59 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 27.0

    PROTECTION (NCC, 4-EHV, 59-HV) 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 27.0

    BW Management System 2.0 2.0 2.0 6.0 5. FACILITIES MNGMT. SYSTEM TWENTY TWO (22) SITES

  • a. Maunong, Cuyapo, Tamayo R/S 6.0

    6.0

    b. Ampucao, Cabuyao, San Isidro,Dela Paz, Calapan R/S 10.0

    10.0

    c. Mataba, Kalayaan EHV, Lucban, Guinayangan, Pasacao R/S 10.0

    10.0

    d. Pinamalayan, San Aquilino, Looc R/S 6.0

    6.0

    e. Camalig, New Bacman, Matnog R/S 6.0

    6.0

    f. Pantabangan, Palauig, Dasol R/S 6.0

    6.0

    g. Mexico, Binan, La Trinidad, Naga S/s 8.0

    8.0

    h. San Jose, Hermosa, Concepcion,San Manuel S/s, Kadampat S/s 10.0

    10.0

    i. Dasmarinas, Tayabas, Batangas, Cabanatuan, Gumaca, Labo 12.0

    12.0 6. SYNCHRONIZATION SYSTEM 6.0 6.0

    12.0

    7. NEW STRUCTURES & AUX SUPPORT SYSTEMS

    a. Remote monitoring system for 48VDC Battery System 5.0 6.0 6.0 6.0 6.0 29.0

    c. Acquisition of surge arresters for Repeater Stations 2.5 2.5 2.5 1.5 1.5 1.5 1.5 1.5 1.5 16.5 TOTAL 15.0 114.5 56.5 99.5 15.5 21.5 51.5 114.5 21.5 15.5 525.5

  • Table E.5.2 Visayas Telecom Projects

    REPLACEMENTS AND REPLENISHMENTS 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 TOTAL

    1. PABX/ IP TELEPHONY a. PBX equipment 4.0 2.0 2.0 0.5 8.5 b. PABX Spares 0.5 0.5 0.5 0.5 0.5 0.5 0.5 3.5 c. VOIP 0.2 0.5 0.5 0.5 0.5 0.5 0.2 0.2 0.2 0.2 3.5

    2. MW RADIO (SDH/PDH) 0.0 0.0 a. Banilad-Canlandog (3 links) 17.0 0.0 17.0 b. Loon Tagbilaran 5.0 0.6 5.6 c. Palompon Tongonan 5.0 0.6 5.6 d. Talisay Tabango 5.0 0.9 5.9 e. Amlan Suba 5.0 0.6 5.6 f. Sta. Barbara - Canlandog 5.0 0.6 5.6 g. Isabel Palompon 5.0 0.6 5.6 h. Camotes Maasin 5.0 0.6 5.6 i. Mauagao Isabel 5.0 0.6 5.6 j.SDH RADIO spares 2.9 2.9 2.9 2.9 2.9 2.9 2.9 2.9 2.9 2.9 29.0 k.PDH RADIO spares 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 9.0 l. ETHERNET RADIO spares 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 2.0 3. MUX 0.0 0.0 a. Multiplex Equipment 5.0 12.5 10.0 25.0 2.5 10.0 25.0 90.0 b. MUX Spares 1.5 1.1 1.1 0.8 1.8 1.1 1.0 1.7 1.1 11.2 4. PLC/PSE SYSTEMS 0.0 0.0 a. PLC Equipment 16.0 16.0 16.0 16.0 8.0 8.0 4.0 4.0 88.0 b. PSE Equipment 3.0 2.2 2.2 1.1 0.7 9.2 c. PLC/PSE Spares 0.7 0.7 0.6 0.5 1.0 0.5 0.7 0.5 0.7 0.6 6.5

  • 5. POWER SUPPLY SYSTEM 0.0 0.0 a. 48V Power Supply 4.0 8.0 8.0 8.0 8.0 8.0 8.0 2.0 2.0 4.0 60.0 b. POWER SUPPLY spares 1.3 0.5 0.5 0.2 0.5 0.2 1.9 0.4 5.5

    7. TEST AND MEASURING EQUIPMENTS

    0.0 0.0

    a. PORTABLE SPECTRUM ANALYZER (28Ghz) 2.5 2.0 2.0

    0.5 4.5

    b. Portable E1 tester 1.5 1.5 1.5 0.4 4.9 c. Portable SDH tester 1.5 1.5 1.5 0.4 4.9 d. Safety Climbing Gadgets 0.1 0.1 0.1 0.0 0.3 e. GPS 0.0 0.0 0.0 0.0

    f. LEVEL METER and SIGNAL GENERATOR SET 1.2 1.2

    0.3 2.7

    g. BER and DATACOM Tester 0.9 0.9 0.2 2.0

    h. MK-11 TRIP BOX AND TRANSMISSION TIME TESTER 1.1

    0.1 1.2

    8. AUXILIARY EQUIPMENTS 0.0 0.0 b. PORTABLE GENSET, 5.5KVA 0.3 0.3 0.3 0.1 1.0

    d. BATTERY MONITORING SYSTEM (BMS) 1.5 1.7 1.7 1.7 1.7

    0.8 9.1

    i. DIGITAL MULTIMETER 0.1 0.1 0.1 0.1 0.0 0.4 j. PORTABLE UPS 0.1 0.1 0.1 0.1 0.0 0.4

    k. 48VDC - 220AC POWER SUPPLY INVERTER 0.1 0.1 0.1 0.1 0.1

    0.1 0.6

    l. ETHERNET RS232 MEDIA CONVERTER 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1

    0.1 1.0

    m. FIBER OPTIC MEDIA 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 1.0 o. WAN/ LAN 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 10.0 p. SERVER 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 2.0

  • q. PROTOCOL CONVERTER 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 1.0 r. SYNCHRONIZATION

    SYSTEM 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5

    5.0 s. SURVEILLANCE SYSTEM 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 2.0

    TOTAL 45.2 71.4 61.5 52.1 62.3 30.8 27.1 27.7 42.7 21.2 442.0

    REHABS AND UPGRADES 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 TOTAL 1. PABX/ IP TELEPHONY 2.0 2.0 2.0 4.0 4.0 4.0 4.0 2.8 24.8 2. MW RADIO (SDH/PDH) a. Camotes Ormoc 7.0 7.0

    b. Canlandog Dingle, Ivisan - Panit-an, Banilad - Buenavista 19.0

    19.0

    c. Sta. Barbara Iloilo, Bacolod Canlandog, Buenavista - Ubay 15.0

    15.0

    d. Caniapasan Canlandog Caniapasan Ivisan, Ormoc Palompon 17.0

    17.0

    e. Camotes Ubay, Ivisan Jawili, Pio Corpus Tabango, Amlan Siquijor 26.0

    26.0

    f. Compostela Mauagao, Maugao Talisay 10.0

    10.0

    3. MUX 15.0 2.5 0.3 17.8 4. MUX MANAGEMENT SYSTEM 8.0 2.0 2.0

    12.0

    5.GROUNDING SYSTEM 2.0 2.0 2.0 2.0 2.0 10.0

    6. SDH MICROWAVE RADIO NETWORK MANAGEMENT SYSTEM 3.0 3.0 3.0 3.0 3.0

    15.0

  • 7.PDH MICROWAVE RADIOS NETWORK MANAGEMENT SYSTEM 3.0 3.0 3.0 3.0

    12.0

    8. TELECOM DATA MANAGEMENT SYSTEM 3.0 3.0

    0.4

    6.4

    9. SNMP NETWORK MANAGEMENT SYSTEM 2.0 2.0

    0.5 4.5

    10. NETWORK PERFORMANCE MANAGEMENT SYSTEM 4.0 4.0

    1.0

    9.0

    11. WAN NETWORK MANAGEMENT SYSTEM 3.0 3.0

    0.8 6.8

    12. SMS 0.5 0.5 0.1 1.1

    13. AUXILIARY EQUIPMENT NETWORK MANAGEMENT SYSTEM 2.0

    0.3

    2.3 14. NMS CONTROL ROOM 2.6 2.6 0.3 5.5 15. SYNCHRONIZATION SYSTEM 5.0 5.0

    0.6 10.6

    TOTAL 35.6 7.5 14.5 19.0 28.0 30.0 30.6 40.5 19.0 7.1 231.8

    EXPANSIONS 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 TOTAL

    1. PABX/ IP TELEPHONY 2.0 2.0 2.0 2.0 8.0 2. OPGW a. Compostela-Talisay 90.9 90.9 b. Malitbog-Tabango 42.8 42.8 c. Naga-Sigpit 11.0 11.0 d. Sigpit-Talavera 6.0 6.0 e. Ormoc-Isabel 48.0 48.0

  • f. Bacolod-Cadiz 34.0 34.0 g. Sta. Barabara - Dingle 18.0 18.0 h. Tongonan-Isabel 48.0 48.0 3. MW RADIO (SDH/PDH) 0.0

    a. Banilad-Mandaue via Camotes (2 links) 10.0

    10.0

    b. Bacolod- Sta. Barbara via Guimaras (2 links) 10.0

    10.0

    c. Majic - Loon 5.0 5.0

    d. Buenavista-Camiguin via Jagna (2 links) 5.0 7.0

    12.0

    4. ETHERNET RADIO 1.4 1.4 0.7 0.7 0.7 0.7 0.7 0.7 7.0 5. MUX 20.0 10.0 5.0 35.0 6. 48VDC POWER SUPPLY 2.2 6.2 8.4 7. RENEWABLE POWER SUPPLY 3.5 3.6 3.6 3.6 3.6 3.6

    21.5

    10. LIGHTNING PROTECTION 2.7 3.6 0.9

    7.2

    11. WIDE AREA NETWORK 3.0 6.5 2.5 7.5 2.5 5.0 5.0 5.0 10.0 47.0 12. VOICE RECORDING SYSTEM 0.6 0.6 0.6 0.9 0.6 0.6 1.2

    5.1

    13. TELECOM SURVEILANCE 0.3 0.5 0.3 0.3 0.5 0.5 0.5 0.5 1.0 4.4 14.SYNCHRONIZATION SYSTEM 0.8 0.8

    1.6

    15. MIGRATION OF WAN PROTOCOL TO OPEN SYSTEM 1.0 1.0

    2.0 16. IP PHONE 0.4 0.4 0.4 0.4 0.2 0.2 0.2 0.2 0.4 2.8 TOTAL 37.1 164.7 54.0 35.4 68.3 46.0 10.6 8.3 60.6 0.7 485.7

  • Table E.5.3 Mindanao Telecom Projects

    REPLACEMENTS AND REPLENISHMENTS 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 TOTAL

    1. PABX/VOIP SYSTEM 0.0 a. PABX System 7.5 7.5 7.5 7.5 7.5 7.5 7.5 6.6 59.1 b. PABX Spares 6.7 6.7 6.7 6.7 6.7 6.7 6.7 6.7 6.7 6.7 67.0

    2. PLC/PSE SYSTEM 0.0 0.0 a. PLC/PSE Equipment 42.0 42.0 42.0 42.0 42.0 35.0 21.0 28.0 294.0 b. PLC/PSE Spares 31.4 31.4 31.4 31.4 31.4 31.4 31.4 31.4 27.5 278.9 3. MW RADIO SYSTEM 0.0 0.0 a. PDH Radio Links 28.0 28.0 28.0 28.0 28.0 14.0 154.0 b. PDH Radio Spares 30.3 30.3 30.3 30.3 30.3 30.3 30.3 30.3 30.3 30.3 303.0 C. SDH Radio Spares 7.0 7.0 1.8 15.8 4. MULTIPLEXERS 7.5 7.5 7.5 7.5 7.5 4.7 42.2 5. VHF Land Mobile Radio 4.0 6.0 6.0 6.0 2.3 24.3 6. 48VDC POWER SUPPLY 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 45.0 7. WIDE AREA NETWORK 2.0 5.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.4 23.4 9. TEST AND MEASURING EQUIPMENTS

    0.0 0.0

    a. NETWORK ANALYZER 1.0 1.0 0.8 0.2 3.0 b. Portable 64/2Mbit BER

    tester 0.7 0.7 0.1

    1.5 c. GPS 0.2 0.0 0.2 d. LEVEL METER and SIGNAL

    GENERATOR SET 1.6 1.6 0.2

    3.4 e. SPECTRUM ANALYZER 2.0 2.0 0.3 4.3 f. SWR/RF POWER METER 1.0 1.0 0.1 2.1 g. FUNCTION GENERATOR 1.0 0.0 1.0 h. TRANSMISSION TEST SET 1.6 0.0 1.6

  • i. OPTICAL CABLE TRACER 1.0 1.0 0.1 2.1 j. OPTICAL FIBER SPLICING

    EQUIPMENT 1.0 1.0 0.1

    2.1 k. HIGH PRECISION OPTICAL

    FIBER FUSION SPLICER 0.2 0.0

    0.2 l. HAND POLISHING PUCK 1.6 1.6 0.2 3.4

    11. AUXILIARY EQUIPMENTS 0.0 0.0 c. POWER AUDIO AMPLIFIER 0.1 0.0 0.1 d. AUDIO MIXER 0.1 0.0 0.1 e. SPEAKER SET/SOUND

    SYSTEM/PAGING SYSTEM 0.5 0.0

    0.5 f. NMS 3.0 0.0 3.0 g. ETHERNET IF UNIT W/

    INTEGRATED HUB 0.8 0.8 0.8 0.8 0.8 0.8 0.5

    5.2 m. PROTOCOL CONVERTER 0.9 0.4 0.0 1.3

    TOTAL 167.2 166.1 167.1 160.7 167.7 132.5 103.4 82.4 64.0 130.5 1,341.6

    REHABS AND UPGRADES 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 TOTAL 1. PABX 4.0 0.0 4.0 2. SDH Radio 49.0 35.0 21.0 42.0 14.0 28.0 0.0 189.0 3. MULTIPLEXERS 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 6.0 5.1 51.1 4. VHF RADIO 5.2 0.0 5.2 5.GROUNDING SYSTEM 2.0 2.0 2.0 2.0 2.0 1.0 11.0 TOTAL 16.2 54.0 42.0 26.0 49.0 19.0 35.0 5.0 8.0 6.1 260.3

  • EXPANSIONS 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 TOTAL 1. Power Line Carrier (PSE) 50.0 50.0 6.3 106.3 2. Protection Signalling Eqpt. 12.6 12.6 1.6 26.8 3. FACILITIES MANAGEMENT SYSTEM 10.0 10.0 10.0 10.0 10.0 10.0 6.0

    7.0 73.0

    4. Network Mngmt. System 9.4 9.0 3.0 1.5 22.9 5. WIDE AREA NETWORK 24.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 96.0

    6. REMOTE BATTERY MONITORING SYSTEM

    (33 sites) 2.5 2.5 2.5 2.5 2.5 2.5 1.5

    1.8

    18.3 7. OPGW 0.0 0.0 0.0 a. Abaga-Agus 2 191.2 191.2 b. Bunawan-Maco-Tindalo-Bislig 134.0 134.0 c. Sangali-Sta.Clara-Aurora 231.0 231.0 d. Bislig-Butuan (Phase 1) 134.0 134.0 e. Aplaya-Nasipit-Butuan; Bislig-Butuan (Phase 2) 136.0

    136.0

    f. Loon-Matanaw; Kibawe-Maramag 88.0

    88.0

    g. Matanaw-Klinan 78.0 78.0 h. Kibawe-Agus 2 91.0 91.0 8. OLTE FOR OPGW 10.0 10.0 8.0 6.0 6.0 2.0 4.0 2.0 2.0 0.0 50.0 9. SYNCHRONIZATION SYSTEM 5.0 5.0 5.0

    15.0

    10.OLTE FOR SDH 16.0 8.0 8.0 10.0 5.3 47.3 11. LIGHTNING PROTECTION (33 SITES) 10.0 10.0 10.0 10.0 10.0 10.0 6.0

    7.0 73.0

    TOTAL 319.7 267.1 280.5 178.5 187.5 120.5 103.5 15.0 101.0 38.3 1,611.6

  • Table E.5.4 Summary of Cost of CAPEX Projects, 2010-2019

    TELECOMPROJECTS LUZON VISAYAS MINDANAO TOTAL

    REPLENISHMENTS/REPLACEMENTS

    1,267 442 1,342 3,050

    REHABS/UPGRADES 241 232 260 733

    EXPANSIONS 526 486 1,612 2,623

    TOTAL 2,033 1,160 3,214 6,406

  • P R E F A C E

    SCADA systems have been employed as indispensable tools for safely and securely operating the Philippine grid. Data acquisition equipment installed in power plants and substations not only continuously feed data to the control centers, but provide remote control capabilities to devices installed in the field.

    Real-time information from the remote stations as presented by SCADA provide instantaneous picture of the ever-changing conditions of the power system thus enabling the system operators to make timely decisions and actions.

    B.1.1 OBJECTIVES

    The TDP programs have been developed with the following objectives:

    1. to sustain the performance and reliability of installed data acquisition and control center systems, including the updating of system software,

    2. to expand the functionality and capability of the SCADA system and equipment in order to meet new requirements of the grid and electricity market system,

    3. to enhance installed system to support increasing stringent corporate performance targets.

    These programs identified in this TDP are geared towards the continuing effort to maintain performance levels of existing SCADA systems and facilities through regular maintenance, planned replacement of failed, obsolete and unsuitable facilities, and acquisition of new facilities to support requirements for operations and address performance deficiencies and new functionalities.

    B.1.2 CREDIBLE BASIS

    Regulatory and Statutory Requirements

    NGCPs commitment towards complying with the following applicable regulatory requirements is one of the major drivers for the SCADA CAPEX programs:

    Philippine Grid Code (PGC), Open Access Transmission Service (OATS), Wholesale Electricity Spot Market Rules (WESM Rules) and, Directives from the Department of Energy (DOE) , Energy Regulatory Commission

    (ERC) and other government agencies.

    NGCP Transmission Master Plan (2009-2030) and 2010-2019 TDP Volume 1

    Anticipated additions to power plants and substations as outlined in NGCPs short, medium and long term plans provide inputs to SCADA requirements in the upcoming period. Although associated data acquisition equipment are usually included in theprojectsfornewplants and substations, these additions also impose requirements on the master stations and affect other existing equipment and systems.

  • ERC Economic Life of Major High Voltage Electrical Equipment

    The Sinclair Knight Merz (SKM) study in 2006 on the economic life of electrical equipment provides the general basis for the replacement plans of SCADA equipment.

    While ERC has adopted a fifteen-year economic life for SCADA based on the above study, this should be considered as referring to the entire SCADA system. Individual components have various applicable economic lives depending of the type of equipment and the environment in which it is operating:

    SCADA computer hardware - IT-type equipment which have an industry-accepted service life of five (5) years. For hardware used continuously in a harsh environment, service life deteriorates fast.

    SCADA software - software do not suffer physical degradation, however its life is shortened with technological development which make it incompatible to new hardware and the subsequent withdrawal of support from the software developer.

    Data Acquisition Equipment being designed for the substation environment, these follows the standard economic life of fifteen (15) years, except for IEDs where active components last only for ten (10) years.

    Auxiliary Equipment similarly, power equipment generally have about fifteen (15) years service live. Sealed maintenance-free batteries are replaced every three (3) years, their service life severely affected by discharged duty and operating temperature.

    SCADA systems are designed according to specific system requirements to match the existing power system. Power system expansions require corresponding SCADA expansions. Accumulated expansions may require accelerated replacement even if the SCADA is still operating within the service life.

  • B.2 S C A D A S Y S T E M S P R O F I L E

    B.2.1 SCADA Systems Profile

    NGCP SCADA systems consist of SCADA and EMS installed at control centers and substations automation systems at the substations. These are of varying ages and are in various conditions ranging from obsolete to newly installed systems.

    SCADA/EMS equipment consists of master station hardware and software, and data acquisition equipment installed at power plants and substations in the entire country.

    Systems/Equipment Luzon Visayas Mindanao Total

    SCADA/EMS 2 2 1 6

    ACC SCADA Systems 0 4 5 9

    Substations Automation Systems

    18 8 2 28

    Remote Terminal Units 101 45 38 184

    Gateway 8 0 0 8

    Transducers/IEDs 603 477 165 1,245

    Synchro-check Relays 140 31 25 196

    OLTC Tap Position Indicators 20 7 5 32

    AGC Controllers 12 8 0 20

    UPS Systems 7 11 9 27

    48V DC Systems 0 11 38 49

    Emergency Generators 0 1 5 6

    Several Substation Automation Systems, referred to as Microcomputer-based Substation Control (MBSC) systems are currently set-up in substations all over the Philippine grid. These are supplied by different manufacturers and of varying ages.

    MBSC Systems Status

    Installed Qty

    Economic Life

    > EL

    < EL Remarks

    Operational 11 5 10 10 Luzon

    On Restoration 7 5 7 0

    Operational 6 5 0 6 Visayas

    Under Engg 2 5 2 0

    Operational 2 5 0 2 Mindanao

    Under Engg 0 5 3 0 3 uninstalled

    The master station systems installed at different control centers of NGCP are from different manufacturer and installed at different periods.

  • SCADA Systems Luzon Visayas Mindanao Total

    Control Centers 6 6 6 18

    Power Plants 30 19 15 64

    Substations 47 30 29 106

    Total 83 55 52 188

    NGCP Control Center Hierarchy

    NGCP maintains a hierarchy of control centers to support operations of the nation-wide transmission system with the dispatch of all generation facilities connected to the Philippine grid. This hierarchy consists of three (3) levels:

    1. National Control Center. The National Control Center (NCC) in Diliman, Quezon City coordinates all high-voltage transmission operations (300 kV HVDC, 500 kV, critical 230 kV and 138 kV circuits) and dispatch all generation. A Backup National Control Center (BNCC) has been established at Cebu City.

    2. Regional Control Centers. The RCCs are responsible for monitoring and control of non-

    critical 230 kV and 138 kV transmission systems in each of the three power grids: Luzon, Visayas and Mindanao. The Luzon RCC is co-located with the NCC, and the Visayas RCC with the BNCC. The Mindanao RCC is responsible for the operation of the Mindanao grid.

    3. Area Control Centers. To supervise other parts of the transmission network not

    managed by the RCCs and coordinate directly with the customers, Area Control Centers are established all-over Luzon, Visayas and Mindanao.

  • Control Centers Location

    Control Level Control Centers Location System

    National & Luzon Region NCC and LRCC Diliman, Quezon City

    XA/21

    Back-up Emergency Backup NCC Araneta, Quezon City Realflex

    Luzon ACCs South Tagalog ACC Binan, Laguna

    Central Luzon ACC Mexico, Pampanga

    Northern Luzon ACC La Trinidad, Benguet

    Southern Luzon ACC Naga, Bicol

    Remote consoles of

    XA/21

    Visayas Region Visayas RCC Cebu City XA/21

    Visayas Back-up Back-up RCC Mandaue City Realflex

    Visayas ACCs Leyte-Samar ACC Ormoc City, Leyte

    Realflex SCADA Bohol ACC Tagbilaran, Bohol Realflex SCADA Negros ACC Bacolod ACC Realflex SCADA Panay ACC Sta. Barbara Realflex SCADA Mindanao Region Mindanao RCC Iligan PowerCC

    Mindanao ACCs Cagayan ACC Cagayan de Oro PowerCC

    Butuan ACC Butuan PowerCC

    Davao ACC Davao PowerCC

    Gen. Santos ACC Gen. Santos PowerCC

    Zamboanga ACC Zamboanga PowerCC

    B.2.1.1 Luzon SCADA

    Luzon EMS Profile

    After eight year in operations, the existing GE XA/21 EMS at the National Control Center (NCC) is being upgraded to address deficiencies in performance and reliability, to support expanded database requirements and to include new functionalities required by Market Operations. The upgrade will be completed by 2011.

    A back-up control center with limited functionality is currently operating at the Araneta S/s using Realflex SCADA software.

    Luzon ACC SCADA systems Profile

    The four (4) ACCs in Luzon use remote consoles that connects to the NCC EMS. The availability of these ACCs is dependent on the EMS and the communication links between NCC and these ACCs.

    Under the NCC EMS upgrade, a back-up EMS will be installed at the Central Luzon ACC in Mexico, Pampanga. The ACC remote consoles will also be upgraded.

  • As part of this TDP, Luzon ACCs will be provided with stand-alone SCADA systems for independent and more reliable SCADA operations.

    Luzon MBSC Systems Profile

    Eleven (11) MBSC systems in Luzon are operating as originally designed and seven (7) are now due for upgrading/replacement. These systems are supplied by different manufacturers making maintenance difficult. Of the seven systems that are due for upgrading/replacement, four are being implemented by SO, two are handled by P&E group and one is being handled by O&M group.

    New MBSC system for Dolores (Taytay) Substations is in the process of acquisition by the O&M group for the year 2010.

    Luzon Data Acquisition Equipment Profile

    Almost all remote terminal units in Luzon use GE D20 RTUs. Most of these RTUs have been upgraded in 2006 to support new protocols. Communications capability for these RTUs is limited to direct serial connection. A few RTUs still use analog communications link with bandwidth as low as 1200 baud. Most RTUs reports to the master stations using Harris H5000 protocol. Only few RTUs use DNP V3.0 protocol.

    With the development pointed towards IP-based communication systems, programs to upgrade the existing RTUs to support IP-based connections have been included in the 2010-2019 TDP.

    Category Equipment Installed Qty Economic

    Life >

    EL <

    EL Remarks

    Servers 7 5 7 0

    Workstations 14 3 14 0

    Routers 7 5 7 0

    Switches 9 5 9 0

    EMS Master Station Equipment

    Software 7 5 7 0 No HW Support Servers 18 5 6 12 4 defective

    Workstations 28 3 15 13

    Gateway 9 5 3 6 1 defective

    Routers 3 5 2 1

    Switches 19 5 4 15

    Bay Control Units 182 15 0 182 99 no longer available, 23 defective

    Substation Automation Equipment

    Software 19 5 9 10

    RTUs 101 15 16 85

    Transducers 312 15 0 312

    Data Acquisition Equipment

    IEDs 509 10 0 509

  • Synchrocheck 140 15 0 140

    AGC Controller 12 15 0 12

    OLTC 20 10 0 20

    UPS 7 15 0 7

    48VDC Chargers 0 15 0 0

    Batteries 7 3 0 7

    Auxillary Equipment

    Generator sets 0 20 0 0

    Transd. Calibrator 2 10 1 1

    Protocol Analyzer 4 10 2 2

    Fiber Optic Test Set

    1 10 0 1

    Multi testers 10 10 2 8

    DC standards 2 10 1 2

    Oscilloscope 2 10 0 2

    Battery Tester 1 10 0 1

    Test Equipment

    Power Analyzer (PQM)

    1 10 0 1

    Office Furniture 0 5 0 0 Others

    Installation Tools 0 5 0 0

  • B.2.1.2 Visayas SCADA

    Visayas EMS Profile

    The EMS used at the Visayas RCC is identical to the NCC EMS and is intended to be the back-up for NCC in case of NCC unavailability. Together with NCC, this EMS is undergoing upgrade to improve system performance and reliability.

    A back-up control center is operating at the Mandaue S/s using Realflex SCADA software.

    Visayas ACC SCADA systems Profile

    The four Visayas ACCs use Realflex SCADA system software which have been installed in the nineties have undergone series of upgrades for software versions and hardware. Upgrade for the replacement of obsolete hardware is still on-going and will be completed by the end of 2010.

    After having been in operations for a long period, the ACC SCADA Systems are scheduled to be replaced in 2013.

    Visayas MBSC Systems Profile

    Visayas have MBSC systems supplied by ABB, Siemens and Areva. Two systems are based on the D20 RTUs and DAPservers and use Realflex SCADA as the HMI software. The MBSC at Sta. Barbara SS is currently undergoing upgrading.

    Most MBSCs in the VIsayas have been programmed to undergo upgrading involving mostly hardware and minor software upgrades every five (5) years.

    Visayas Data Acquisition Equipment Profile

    Almost all RTUs in the Visayas are GE D20 RTUs, mostly installed during the early nineties. The main board and some peripheral boards were upgraded in 2006 for higher performance and support to more protocols. The RTUs are programmed for upgrading to support communications through TCP/IP networks in the future.

    Visayas Auxillary Equipment Profile

    Operations of SCADA equipment are dependent on auxillary equipment like UPS, DC power supply, batteries and emergency generators. These equipment typically have longer life spans. Some equipment are programmed for replacement in this TDP.

  • Category EquipmentInstalled

    QtyEconomic

    Life>EL

  • B.2.1.3 Mindanao SCADA

    Mindanao EMS Profile

    The Mindanao SCADA/EMS is presently under upgrading after a fire in 2009 destroyed their previous EMS.

    A temporary Siemens Spectrum WinCC SCADA system with limited capability was hastily set-up and presently used to support dispatch engineers in operating the Mindanao grid. This system cannot fully support the needs for operations since it is only capable of basic SCADA functions and do not have advanced applications like Automatic Generation Control (AGC) and network applications.

    Mindanao ACC SCADA systems Profile

    Mindanaos five ACCs have stand-alone Siemens Spectrum WinCC SCADA systems installed in the past three years. These systems are non-redundant units with the SCADA applications and HMI running under a single hardware. Like the temporary system used at the MRCC, these SCADA systems only have basic SCADA functions and do not support advanced functionalities.

    Mindanao MBSC Systems Profile

    There is still no MBSC being used for operations in Mindanao. Although the Pitogo system has already been tested and commissioned, it is not actually used because there are still no transmission lines going into the substation. The other MBSCs are still under P&E construction. However, two systems are already of deteriorated conditions because they have been delivered many years but and have not been installed. MBSCs in Mindanao are supplied by Siemens, ABB and Areva.

    Mindanao Data Acquisition Equipment Profile

    Telegyr Station Manager RTUs are used mostly in Mindanao. These RTUs have been upgraded in 2008 for additional communication ports to new master stations and support DNP V3.0 protocol. A few GE D20 have been installed in some power plants. These RTUs only support serial connections to the master stations.

    Originally transducers were installed in the nineties for providing power system information to the RTUs. Since 2004, transducers are being replaced with Intelligent Electronic Devices (IEDs).

  • Category EquipmentInstalled

    QtyEconomic

    Life>EL

  • B.2.2 Problems and Issues

    In the operations of NGCPs SCADA systems, the following problems and issues are frequently encountered that limits the performance of the systems:

    Limited operating life of hardware:

    Although IT equipment typically have service lives of five (5) years, in the environment where these equipment are used in SCADA systems, actual operating life is usually shortened to about three (3) years due to continuous and heavy demand on the processing power of these equipment, and the harsh operating environment specially for computers used in substation automation.

    This usually results in high maintenance costs for replacement hardware.

    Fast Obsolescence of Computer Hardware and Limited Support for Legacy Systems due to Rapid Technology Development

    After a few years, replacement parts or even equipment are no longer available because these hardware are already not manufactured. To make matters worse, new hardware models are usually not compatible with other old equipment.

    When new models and system versions are introduced in the market, the manufacturer usually withdraws support for these systems a few years there-after.

    Insufficient capacity to support rapid power system expansion:

    The rapid construction of power plants and substations and the fast expansion of the power grid through the introduction of additional transmission lines and equipment have put a tremendous strain on the performance requirements of existing SCADA systems and data acquisition equipment.

    Proprietary Requirements for Multi-vendor systems

    NGCP has employed SCADA systems and equipment supplied by different vendors. The proliferation of different systems complicates the requirements for NGCP in terms of spare parts and technical proficiency in maintaining, expanding and upgrading the systems.

    In addition to these operational issues, planning for SCADA requirements are hampered by unresolved policies on compliance to certain PGC requirements:

    SCADA Monitoring Requirements at Customer Connection Points: SCADA Monitoring for Embedded Generators

  • B.3 R E Q U I R E M E N T A N A L Y S I S

    B.3.1 TRANSMISSION GRID EXTENSION

    Additional SCADA/EMS requirements usually result from transmission grid extensions and power plant additions. Transmission expansion activities are identified in the Volume 1 of this Transmission Development Plan as developed by NGCPs P&E group.

    Major SCADA requirements for new stations are usually incorporated in the design of these new stations and are provided under the P&E projects. This however only addresses the SCADA requirements for remote sites. Corresponding equipment additions and capability expansions also required at the master stations are usually not included in the scope of these projects.

    On an individual station basis, these requirements may be addressed by the addition of expansion modules and reconfiguration of the existing system. The corresponding requirements at the master stations will only be incremental for a few individual stations.

    Overtime, accumulated expansion requirements may reach the point where the capacity may no longer be supported by the existing master station system. This results in accelerated need for system replacement programs.

    Small scale substation expansions are implemented by NGPs O&M group, like additional circuit breakers, etc. These expansions require only additional RTU boards for new I/O