NFX Schedule Delay Analysis 21DEC11.ppt [Read-Only] · Waffle Slab Schedule SAMPLE. HSE CPM...

5
2 © M+W Group M+W U.S., Inc. NFX Delay Analysis Report Critical Status: >25D Delay Overall duration affected Caution Status: >5D Delay <25D Delay Controlled Status: On Schedule LE Controll LE On Sc

Transcript of NFX Schedule Delay Analysis 21DEC11.ppt [Read-Only] · Waffle Slab Schedule SAMPLE. HSE CPM...

2 © M+W GroupM+W U.S., Inc.

NFX Delay Analysis Report

Critical Status:• >25D Delay

• Overall duration affected

Caution Status:• >5D Delay

• <25D Delay

Controlled Status:• On ScheduleSAMPLESAMPLESAMPLEControlled Status:SAMPLEControlled Status:SAMPLE•SAMPLE• On ScheduleSAMPLEOn Schedule

3 © M+W GroupM+W U.S., Inc.

Mechanical Trestle Piping

SAMPLESAMPLE

4 © M+W GroupM+W U.S., Inc.

P6 Summary – Pipe Trestle Delay Impact

SAMPLE

5 © M+W GroupM+W U.S., Inc.

P6 Summary – Pipe Trestle Delay Impact

SAMPLESAMPLE

6 © M+W GroupM+W U.S., Inc.

Waffle Slab Schedule

SAMPLE