NF 533 Reporting NF 533 Reporting NF 533 Reporting NF 533 Reporting NF 533 Reporting

24
NF 533 Reporting NF 533 Reporting NF 533 Reporting NF 533 Reporting NF 533 Reporting March 6, 2014

description

NF 533 Reporting NF 533 Reporting NF 533 Reporting NF 533 Reporting NF 533 Reporting March 6, 2014. Purpose of the NF 533 Series of Reports. NF 533 data is used by NASA to manage and control cost and schedule for a project/program - PowerPoint PPT Presentation

Transcript of NF 533 Reporting NF 533 Reporting NF 533 Reporting NF 533 Reporting NF 533 Reporting

Page 1: NF 533 Reporting NF 533  Reporting NF 533  Reporting NF  533  Reporting NF 533  Reporting

NF 533 ReportingNF 533 ReportingNF 533 ReportingNF 533 ReportingNF 533 Reporting

March 6, 2014

Page 2: NF 533 Reporting NF 533  Reporting NF 533  Reporting NF  533  Reporting NF 533  Reporting

Purpose of the NF 533 Series of Reports

• NF 533 data is used by NASA to manage and control cost and schedule for a project/program

• Data on the NASA 533 series of reports is used to:– Enable management to project both project/program costs

and hours to ensure dollar and labor resources realistically support the project/program schedule.

– Evaluate contractor cost performance– Plan and monitor project/program resources– Establish the basis to record cost into the NASA accounting

system (SAP) which establishes a liability for the Federal Government.

2

Page 3: NF 533 Reporting NF 533  Reporting NF 533  Reporting NF  533  Reporting NF 533  Reporting

• Other uses:– Performing PEB Analysis– Developing historical cost and trend analysis– Performing work force analysis– Developing in-house cost estimates

Purpose of the NF 533 Series of Reports

3

Page 4: NF 533 Reporting NF 533  Reporting NF 533  Reporting NF  533  Reporting NF 533  Reporting

NF 533 Series of Reports

• The NF 533 series of reports is the official set of cost reporting documents NASA requires for cost type and fixed price incentive contracts meeting specified dollar and performance-period criteria.

• NF 533 reports are completed by the contractor in a form specified by the Government

• Within the NASA Form (NF) 533 reporting system, two reports are used:– NASA Form 533M, and– NASA Form 533Q

• The requirements for NF 533 reporting are set forth in NPR 9501.2E and NPD 9501.1I

4

Page 5: NF 533 Reporting NF 533  Reporting NF 533  Reporting NF  533  Reporting NF 533  Reporting

The NF 533 Reports

5

Page 6: NF 533 Reporting NF 533  Reporting NF 533  Reporting NF  533  Reporting NF 533  Reporting

NF 533Q Overview

• The NF 533Q is a quarterly projection report which details and summarizes cost and labor hour estimates over the life of the contract

• If NF 533Q’s are required for task-order contracts, task baseline data is summarized in an initial time-phased NF 533Q

• The contractor submits the initial NF 533Q to the Government within 30 working days after contract award – Reflects the original contract value in terms of the

negotiated reporting categories• Subsequent NF 533Qs are due by the 15th of the month

prior to the first day of the quarter being reported

6

Page 7: NF 533 Reporting NF 533  Reporting NF 533  Reporting NF  533  Reporting NF 533  Reporting

NF 533Q

PAGE ______ OF ______ PAGES

Quarterly Contractor Financial Management ReportForm Approved

O.M.B. No. 2700-0003

2. REPORT FOR QUARTER BEGINNING

TO: FROM: 3. CONTRACT VALUEa. COST

4. FUND LIMITATION

b. FEE

5. BILLING

b. TOTAL PYTS

1. DESCRIPTION OF CONTRACT

a. TYPE

c. SCOPE OF WORK

b. CONTRACT NO. AND LATEST DEFINITIZED MODIFICATION NO.

d. AUTH. CONTR. REP. DATE

7. COST INCURRED/ HOURS WORKED 8. ESTIMATED COST/HOURS TO COMPLETE

CON- TRACTOR ESTIMATE

CONTRACT VALUE

11. UN- FILLED ORDERS OUT-

STANDING

9. ESTIMATED FINAL COST/HOURS

6. REPORTING CATEGORY

CUMULATIVE ACTUAL THROUGH

PRIOR MONTH

2/28/05

CURRENT MONTH ESTIMATE

3/05

CUMULATIVE ESTIMATE TO DATE

3/31/05

MONTH MONTH MONTH

FY05 1st QTRFY06

2nd QTR FY06

BALANCE OF FY06

NEXT FISCAL YEAR

FY07BALANCE

OF CONTRACT

TOTAL TO

COMPLETE

10. ESTI- MATED COM- PLETION DATE

a. b. c. d. e. f. g. h. i. j.a. b. c. a. b.

APRIL-SEPT

NASA FORM 533Q (JUL 84)

$

$ $$

(Signature)

NASA Goddard Space Flight Center Greenbelt, MD 20771

Cost-Plus-Fixed Fee

GSFC Health Unit

XYZ Corporation

4/1/05 - 6/30/05

7,422,005

1,200,000

445,320

a. INVOICE AMTS. $ 982,837 Inv #427 743,321

NAS5-33333 Mod. #12

3/15/05

Direct Labor Hours (Reg & OT) -Prime -WFF Physician -EAP Counselor Total Direct Labor Hours

Direct Labor Cost (Reg & OT) - Overhead @ 32.48% Subtotal Costs Other Direct Costs (ODCs): Government-Directed ODCs Off-Site Physicals Recruiting Malpractice Insurance Subcontract/Consultants Answ. Service/Beeper Other Support Services Total ODCs Subtotal Costs G&A Expenses @3.00% Subtotal Costs Fixed Fee @6.00% Total CPFF

25,807 511 655

26,973

3,630 65 83

3,778

29,437 576 738

30,751

4,250 77

618 4,945

4,250 77

618 4,945

4,453 81

648 5,182

10,694 195 250

11,139

10,694 195 250

11,139

10,694 195 250

11,139

10,694 195 250

11,139

42,776 780

1,000 44,556

85,552 1,560 2,000

89,112

184,057 3,355 5,884

193,296

213,494 3,931 6,622

224,047

213,880 3,900 5,000

222,780

$550,192

178,703

$728,895

$62,971

20,453

$83,424

$613,163

199,156

$812,319

$77,782

25,264

$103,046

$77,782

25,264

$103,046

$81,486

26,467

$107,953

$203,792

66,192

$269,984

$203,792

66,192

$269,984

$203,792

66,192

$269,984

$203,792

66,192

$269,984

$843,784

274,061

$1,117,845

$1,777,073

577,194

$2,354,267

$3,673,076

1,193,018

$4,866,093

$4,286,239

1,392,174

$5,678,412

$4,227,674

1,373,150

$5,600,824

59,894

2,800

1,191

14,152

51,842

0

11,032

$140,910

7,608

1,329

292

1,183

10,578

0

1,613

$22,593

67,502

4,129

1,483

15,325

62,419

0

12,645

$163,503

5,000

686

350

1,360

6,148

0

1,300

$14,844

5,000

686

350

1,360

6,148

0

1,300

$14,844

5,200

785

450

1,360

7,400

0

1,566

$16,761

28,969

4,303

919

3,695

15,152

0

7,854

$60,892

28,969

4,303

919

3,695

15,152

0

7,854

$60,892

28,969

4,303

919

3,695

15,152

0

7,854

$60,892

28,969

4,303

919

3,695

15,152

0

7,854

$60,892

121,129

18,010

3,875

15,520

63,740

735

32,830

$255,739

258,988

38,570

8,300

33,400

136,976

1,591

70,155

$547,980

511,193

75,986

17,251

67,780

280,920

2,326

138,517

$1,093,973

578,695

80,115

18,734

83,105

343,339

2,326

151,162

$1,257,476

608,158

89,740

19,350

77,777

318,942

3,686

153,750

$1,271,403

$869,805

60,477

$930,282

54,960

$985,242

$106,017

8,481

$114,498

6,870

$121,368

$975,822

68,958

$1,044,780

61,830

$1,106,610

$117,890

9,431

$127,321

6,870

$134,191

$118,127

9,450

$127,577

6,870

$134,447

$124,714

9,977

$134,691

6,870

$141,561

$330,876

26,484

$357,360

21,452

$378,812

$330,876

26,484

$357,360

21,452

$378,812

$330,876

26,484

$357,360

21,452

$378,812

$330,876

26,484

$357,360

21,452

$378,812

$1,373,584

109,887

$1,483,471

89,008

$1,572,479

$2,902,247

232,180

$3,134,427

188,066

$3,322,493

$5,960,066

476,861

$6,436,927

383,492

$6,820,419

$6,935,888

545,819

7,481,707

445,322

$7,927,029

$6,872,227

549,778

$7,422,005

445,320

$7,867,325

APRIL MAY JUNEJULY-SEPT

OCT-DEC

JAN-MARCH

4th QTR

7

Mod #23

Page 8: NF 533 Reporting NF 533  Reporting NF 533  Reporting NF  533  Reporting NF 533  Reporting

NF 533M Overview

• The NF 533M is a monthly report which provides data on planned and actual costs and labor hours, short-term cost projections, estimates to complete, and contract values.

• Documentation of analyses is done using Form 210-49, 533 Analysis and Record of Actions Taken

8

Page 9: NF 533 Reporting NF 533  Reporting NF 533  Reporting NF  533  Reporting NF 533  Reporting

49

9

Page 10: NF 533 Reporting NF 533  Reporting NF 533  Reporting NF  533  Reporting NF 533  Reporting

• 533M reports are due from the contractor no later than 10 operating days after the closing of the contractor’s accounting period.

533M Reporting Requirements

FEBRUARY

Su M T W Th F Sa

MARCH

Su M T W Th F Sa

Last day of contractor’s

accounting period

533M due to Government

10

Page 11: NF 533 Reporting NF 533  Reporting NF 533  Reporting NF  533  Reporting NF 533  Reporting

NF 533M

NASA FORM 533M (JUL 84)

Baseline Plan Identification (Col. 7b & 7d): Revision No. ___12_____________, Dated _________________.

PAGE _______ OF _______ PAGES

ACTUAL PLANNEDACTUAL PLANNED

a. b. c. d. a. b.

Monthly Contractor Financial Management Report Form ApprovedO.M.B. No. 2700-00003

2. REPORT FOR MONTH ENDING AND NUMBER OF OPERATING

DAYS

TO: FROM:3. CONTRACT VALUE

a. TYPE

c. SCOPE OF WORK

b. CONTRACT NO. AND LATEST DEFINITIZED MODIFICATION NO.

d. AUTH. CONTR. REP. (Signature) DATE

7. COST INCURRED/HOURS WORKED

DURING MONTH DETAIL

8. ESTIMATED COST/HOURS TO COMPLETE

CUM. TO DATE

6. REPORTING CATEGORYa. b.

a. COSTS

5. BILLING

9. ESTIMATED FINALCOST/HOURS

$

b. FEE

$

a. INVOICE AMTS. BILLED

$ 982,837 Inv # 427

B. TOTAL PYTS REC'D.

$

4. FUND LIMITATION

$$

CONTRACTOR ESTIMATE

10. UNFILLED ORDERS

OUTSTANDING

Direct Labor Hours (Reg & OT) -Prime -WFF Physician -EAP Counselor Total Direct Labor Hours

Direct Labor Cost (Reg & OT ) - Overhead @ 32.48%

Subtotal Costs Other Direct Costs (ODCs): Government-Directed ODCs Off-Site Physicals

Recruiting Malpractice Insurance Subcontract/Consultants Answ. Service/Beeper Other Support Services Total ODCs

Subtotal Costs

G&A Expenses @3.00% Subtotal Costs Fixed Fee @6.00% Total CPFF

1. DESCRIPTION OF CONTRACT

CONTRACT VALUE

c.

BALANCE OF CONTRACT

NASA GODDARD SPACE FLIGHT CENTER Greenbelt, MD 20771

Cost Plus Fixed Fee

GSFC Health Unit

XYZ CORP.

NAS5-33333 Mod. #12

4/12/05

1,200,000

7,422,005 445,320

743,321

March 31, 2005 20 days

4,717

68 80

4,865

85,939 27,913

$113,852

5,032 700

915 1,360 6,148

0 1,214

$15,369

$129,221

10,338 $139,559

6,870 $146,429

3,630

65 83

3,778

62,971 20,453

$83,424

64,926 3,500

2,106 15,512 57,989

0 12,246

$156,279

$999,026

70,815 $1,069,841

61,830 $1,131,671

30,524

594

720

31,098

636,131 206,616

842,747

7,608 1,329

292 1,173

10,578 0

1,613 $22,593

$106,017

8,481 $114,498

6,870 $121,368

68,496 11,961

2,628 10,557 95,202

0 14,517

$203,361

$964,177

76,337 $1,030,614

61,830 $1,092,344

29,762

585 747

31,094

566,739 184,077

$769,816

4,250

77

618 4,945

77,782 25,264

$103,046

5,000 686

350 1,360 6,148

0 1,300

$14,844

$117,890 9,431

$127,321 6,870

$134,191

4,250

77

618 4,945

77,782 25,264

$103,046

5,000 723

600 1,360 6,148

0 1,250

$15,081

$118,127 9,450

$127,577 6,870

$134,447

174,470

3,183 4,666

183,059

3,494,544 1,135,030 $ 4,629,573

503,769 75,206

14,678 64,873 273,054 2,326136,366

$ 1,071,272

$ 5,700,845

456,123 $ 6,156,968

369,750$ 6,526,720

213,494

3,931

6,622

224,047

4,286,239 1,392,174 $ 5,678,412

578,695 80,115

17,734 83,105 343,339 2,326

151,162$ 1,257,476

$ 6,935,888

545,819 $ 7,481,707

445,320 $ 7,927,029

April ‘05 May ‘05

4,227,674

1,373,150

$ 5,600,824

March ‘05 March ‘05

213,880

3,900

5,000

222,780

608,158 89,740

19,350 77,777

318,942 3,686

153,750 $ 1,271,403

$ 6,872,227

549,778$ 7,422,005

445,320 $ 7,867,325

11

Page 12: NF 533 Reporting NF 533  Reporting NF 533  Reporting NF  533  Reporting NF 533  Reporting

12

NF 533M Analysis – Cost over Obligations

• What is it?– Actual or estimated cost exceeds obligation

• Why do we do it?– May constitute a violation of appropriation law

• How we do it?– Calculations within the CCR (Contractor Cost

Reporting) Accrual Worksheet show cost over obligation for actual and estimated costs

• Those without access to the CCR may view the CCR Accrual Worksheet by generating Business Warehouse report CMRPT01

Page 13: NF 533 Reporting NF 533  Reporting NF 533  Reporting NF  533  Reporting NF 533  Reporting

NUMBER OF OP DAYS 24FINANCIAL MONTH ENDING : December 31, 2010 FUND LIMITATION: 9,112,397$ MODIFICATION NO. 2 19.17120521000 BROOKPARK ROADCLEVELAND, OHIO 44135 FROM: TYPE OF CONTRACT: COST PLUS AWARD FEESCOPE OF WORK: AUTH REP:

PROGRAM MANAGER

CONTRACT VALUE - COST: 18,224,889$ CONTRACT VALUE - FEE: 1,336,180$ INVOICE AMOUNTS : 8,508,149$ TOTAL VALUE: 19,561,069$ AMOUNTS RECEIVED: 7,695,931$

8. ESTIMATED COST/HOURS TO COMPLETEDecember 2010 December 2010 CUM TO DATE CUM TO DATE J anuary 2011 February 2011 c. BAL OF a. CONTRACTOR b. CONTRACT

a. ACTUAL b. PLANNED c. ACTUAL d. PLANNED a. ESTIMATE b. ESTIMATE CONTRACT ESTIMATE VALUELABOR HOURSDIRECT LABOR-P RODUCTIVE 17,329.50 17,108.00 183,613.20 179,314.00 17,157.00 14,172.00 195,127.45 410,069.65 410,069.65 DIRECT LABOR-NONP RODUCTIVE 3,030.20 - 24,101.95 - - - - - - DIRECT OVERTIME 33.00 78.00 467.00 594.00 73.00 61.00 982.00 1,583.00 1,583.00 P ROGRAM SUP P ORT 948.50 - 8,535.70 - - - - - - TOTAL LABOR HOURS 21,341.20 17,186.00 216,717.85 179,908.00 17,230.00 14,233.00 196,109.45 411,652.65 411,652.65

COST - DIRECT LABORDIRECT LABOR-P RODUCTIVE 467,877.76 469,553.00 4,795,707.15 4,622,319.65 449,988.00 371,729.00 5,096,099.84 10,713,523.99 10,713,523.65 DIRECT OVERTIME 1,352.50 2,901.00 18,375.46 22,114.00 2,780.00 2,297.00 35,892.54 59,345.00 59,345.00 P ROGRAM SUP P ORT 41,051.66 41,720.00 357,302.23 506,351.00 39,981.00 33,028.00 611,430.49 1,041,741.72 1,041,741.00 TOTAL LABOR COSTS 510,281.92 514,174.00 5,171,384.84 5,150,784.65 492,749.00 407,054.00 5,743,422.87 11,814,610.71 11,814,609.65

LABOR OVERHEAD 202,110.22 199,184.00 2,063,398.54 2,008,002.00 190,885.00 157,687.00 2,178,082.91 4,590,053.45 4,590,053.00 TOTAL LABOR RELATED COSTS 712,392.14 713,358.00 7,234,783.38 7,158,786.65 683,634.00 564,741.00 7,921,505.78 16,404,664.16 16,404,662.65

TASK-DIRECT COSTSTRAVEL - 682.00 3,904.64 7,585.00 654.00 539.00 11,237.36 16,335.00 16,335.00 TRAINING 3,190.00 3,290.00 6,215.00 15,403.00 3,153.00 2,605.00 45,648.00 57,621.00 57,621.00 EQUIP MENT - 820.00 - 7,715.00 785.00 647.00 16,791.00 18,223.00 18,223.00 MATERIALS/TOOLS 568.15 2,128.00 17,487.80 18,584.00 2,040.00 1,683.00 24,696.20 45,907.00 45,907.00 OTHER 19,922.04 26,314.00 341,283.11 276,906.00 25,219.00 20,833.00 227,270.43 614,605.54 614,606.00 TOTAL TASK-DIRECT COSTS 23,680.19 33,234.00 368,890.55 326,193.00 31,851.00 26,307.00 325,642.99 752,691.54 752,692.00

G &A 41,262.26 46,326.00 428,623.39 467,613.00 44,394.00 36,674.00 557,842.91 1,067,534.30 1,067,534.00

TOTAL COST 777,334.59 792,918.00 8,032,297.32 7,952,592.65 759,879.00 627,722.00 8,804,991.68 18,224,890.00 18,224,888.65

AWARD FEE 27,941.00 58,139.00 552,604.00 582,802.00 55,718.00 46,028.00 681,287.00 1,335,637.00 1,336,180.00

TOTAL COST AND FEE 805,275.59 851,057.00 8,584,901.32 8,535,394.65 815,597.00 673,750.00 9,486,278.68 19,560,527.00 19,561,068.65

7. COSTS INCURRED/HOURS WORKED 9 EST. FINAL COST/HOURS

13

In this case when actual costs are added to the Jan. estimate, there will not be sufficient funding.

To-Date: $8,584,901 + Jan Est. 815,597= Needed $9,400,498Available $9,112,397

Cost Over ObligationsBox 4 Fund LimitationIs this value correct? Does it include all mods/incremental funding actions?Value = obligations

Page 14: NF 533 Reporting NF 533  Reporting NF 533  Reporting NF  533  Reporting NF 533  Reporting

14

NF 533M Analysis – Available Funding

• What is it?– Adequate funding to cover estimated cost

• Why do we do it?– To ensure adequate funding is available to cover

second month estimated cost– To be proactive in limiting Cost in Excess of

Obligations• How we do it?

– Compare Net Uncosted Fund Limit after posting the current month’s estimate (8a) with the amount reported in column 8b of the NF 533M report

Page 15: NF 533 Reporting NF 533  Reporting NF 533  Reporting NF  533  Reporting NF 533  Reporting

15

NUMBER OF OP DAYS 24FINANCIAL MONTH ENDING : December 31, 2010 FUND LIMITATION: 9,112,397$ MODIFICATION NO. 2 19.17120521000 BROOKPARK ROADCLEVELAND, OHIO 44135 FROM: TYPE OF CONTRACT: COST PLUS AWARD FEESCOPE OF WORK: AUTH REP:

PROGRAM MANAGER

CONTRACT VALUE - C OST: 18,224,889$ CONTRACT VALUE - FEE: 1,336,180$ INVOICE AMOUNTS : 8,508,149$ TOTAL VALUE: 19,561,069$ AMOUNTS RECEIVED: 7,695,931$

8. ESTIMATED COST/HOURS TO COMP LETEDecember 2010 December 2010 CUM TO DATE CUM TO DATE J anuary 2011 February 2011 c. BAL OF a. CONTRACTOR b. CONTRACT

a. ACTUAL b. PLANNED c. ACTUAL d. PLANNED a. ESTIMATE b. ESTIMATE CONTRACT ESTIMATE VALUELABOR HOURSDIRECT LABOR-P RODUCTIVE 17,329.50 17,108.00 183,613.20 179,314.00 17,157.00 14,172.00 195,127.45 410,069.65 410,069.65 DIRECT LABOR-NONP RODUCTIVE 3,030.20 - 24,101.95 - - - - - - DIRECT OVERTIME 33.00 78.00 467.00 594.00 73.00 61.00 982.00 1,583.00 1,583.00 P ROGRAM SUP P ORT 948.50 - 8,535.70 - - - - - - TOTAL LABOR HOURS 21,341.20 17,186.00 216,717.85 179,908.00 17,230.00 14,233.00 196,109.45 411,652.65 411,652.65

COST - DIRECT LABORDIRECT LABOR-P RODUCTIVE 467,877.76 469,553.00 4,795,707.15 4,622,319.65 449,988.00 371,729.00 5,096,099.84 10,713,523.99 10,713,523.65 DIRECT OVERTIME 1,352.50 2,901.00 18,375.46 22,114.00 2,780.00 2,297.00 35,892.54 59,345.00 59,345.00 P ROGRAM SUP P ORT 41,051.66 41,720.00 357,302.23 506,351.00 39,981.00 33,028.00 611,430.49 1,041,741.72 1,041,741.00 TOTAL LABOR COSTS 510,281.92 514,174.00 5,171,384.84 5,150,784.65 492,749.00 407,054.00 5,743,422.87 11,814,610.71 11,814,609.65

LABOR OVERHEAD 202,110.22 199,184.00 2,063,398.54 2,008,002.00 190,885.00 157,687.00 2,178,082.91 4,590,053.45 4,590,053.00 TOTAL LABOR RELATED COSTS 712,392.14 713,358.00 7,234,783.38 7,158,786.65 683,634.00 564,741.00 7,921,505.78 16,404,664.16 16,404,662.65

TASK-DIRECT COSTSTRAVEL - 682.00 3,904.64 7,585.00 654.00 539.00 11,237.36 16,335.00 16,335.00 TRAINING 3,190.00 3,290.00 6,215.00 15,403.00 3,153.00 2,605.00 45,648.00 57,621.00 57,621.00 EQUIP MENT - 820.00 - 7,715.00 785.00 647.00 16,791.00 18,223.00 18,223.00 MATERIALS/TOOLS 568.15 2,128.00 17,487.80 18,584.00 2,040.00 1,683.00 24,696.20 45,907.00 45,907.00 OTHER 19,922.04 26,314.00 341,283.11 276,906.00 25,219.00 20,833.00 227,270.43 614,605.54 614,606.00 TOTAL TASK-DIRECT C OSTS 23,680.19 33,234.00 368,890.55 326,193.00 31,851.00 26,307.00 325,642.99 752,691.54 752,692.00

G &A 41,262.26 46,326.00 428,623.39 467,613.00 44,394.00 36,674.00 557,842.91 1,067,534.30 1,067,534.00

TOTAL COST 777,334.59 792,918.00 8,032,297.32 7,952,592.65 759,879.00 627,722.00 8,804,991.68 18,224,890.00 18,224,888.65

AWARD FEE 27,941.00 58,139.00 552,604.00 582,802.00 55,718.00 46,028.00 681,287.00 1,335,637.00 1,336,180.00

TOTAL COST AND FEE 805,275.59 851,057.00 8,584,901.32 8,535,394.65 815,597.00 673,750.00 9,486,278.68 19,560,527.00 19,561,068.65

7. COSTS INCURRED/HOURS WORKED 9 EST. FINAL COST/HOURS

Fund Limitation: $9,112,397Estimated Costs: $ 10,074,248

($961,851)

Available Funding

Insufficient funds obligated to cover the cost of next month’s work; action must be taken to fund the planned work

Columns 7c (actual cumulative cost to date), $8,584,901 + 8a (current estimate) $815,597 + 8b (next month’s estimate) $673,750 equals $10,074,248; compare to Box 4 (fund limitation)

Box 4 Fund LimitationIs this value correct?

Page 16: NF 533 Reporting NF 533  Reporting NF 533  Reporting NF  533  Reporting NF 533  Reporting

SAMPLE NF 533M’s

16

Page 17: NF 533 Reporting NF 533  Reporting NF 533  Reporting NF  533  Reporting NF 533  Reporting

17

Page 18: NF 533 Reporting NF 533  Reporting NF 533  Reporting NF  533  Reporting NF 533  Reporting

18

Page 19: NF 533 Reporting NF 533  Reporting NF 533  Reporting NF  533  Reporting NF 533  Reporting

19

Page 20: NF 533 Reporting NF 533  Reporting NF 533  Reporting NF  533  Reporting NF 533  Reporting

20

Summarized Samples of Analytics for NF 533 Forms

Page 21: NF 533 Reporting NF 533  Reporting NF 533  Reporting NF  533  Reporting NF 533  Reporting

NF 533 Analyses• Review baseline values – To ensure changes to baseline budget values are

documented by contract modifications– Compare current baseline cost & labor values to values in previous month’s

NF 533– Compare contract cost & labor values (cols. 7b & 9b) to accepted baseline

budget – Ensure contract value on NF 533M = awarded contract value

• Review contract reporting structure – To ensure contractor is reporting by reporting categories negotiated into the contract, as modified – Compare NF 533M reporting categories to categories stipulated in the contract

• Check math accuracy - To ensure accurate data is used in management reporting, financial statements and decision-making– Verify NF 533M calculations

• Compare estimated vs. planned cost – To determine whether the contractor is properly reporting current month estimates– Compare current month estimate to current month planned (on next NF 533M)

Page 22: NF 533 Reporting NF 533  Reporting NF 533  Reporting NF  533  Reporting NF 533  Reporting

NF 533 Analyses• Compare estimated vs. actual cost – To ensure reasonableness and accuracy of

estimates to maximize accuracy of cost recorded in NASA’s accounting system and used in project management decision-making– Difference between 8a (estimate) from prior month’s NF 533 and 7a (actual) from

current month’s NF 533 divided by 7a (actual) from current month• Check cost over obligations –To ensure no violations of appropriation law

– Review calculations within the CCR Accrual Worksheet or CMRPT01 BW report which show cost over obligations for actual and estimated costs

• Check available funding – To ensure adequate funding is available to cover second month estimated cost; be proactive in limiting Cost in Excess of Obligations– Compare Net Uncosted Fund Limit after posting the current month’s estimate (8a) with

the amount reported in column 8b of the NF 533M report• Compare cumulative invoice vs. cumulative NF 533M cost – To reconcile contractor’s

cost reported on NF 533M with cost reported on invoices to support payment of invoices– Compare cumulative billed amount on invoice to cumulative recorded actual costs on

NF 533M for same reporting period

Page 23: NF 533 Reporting NF 533  Reporting NF 533  Reporting NF  533  Reporting NF 533  Reporting

NF 533 Analyses• Cost Over and Underruns – To determine if Estimated Final Cost is

higher or lower than Contract Value – Compare Estimated Final Cost/Hours, Column 9.a., Contractor

Estimate, to Column 9.b., Contract Value– Use “burn rate” analysis to estimate final cost independent from the

contractor’s reported estimate (average actual monthly costs) x (months left on contract) plus cumulative actual cost

• Actual vs. Planned Current Month - To identify prospective project control issues; may be the first indicator of a potential problem– Examine variances between the values reported in columns 7a and 7b

in the same row• Cost Over and Underruns – To determine if Estimated Final Cost is

higher or lower than Contract Value – Compare Estimated Final Cost/Hours, Column 9.a., Contractor

Estimate, to Column 9.b., Contract Value– Use “burn rate” analysis to estimate final cost independent from the

contractor’s reported estimate (average actual monthly costs) x (months left on contract) plus cumulative actual cost

Page 24: NF 533 Reporting NF 533  Reporting NF 533  Reporting NF  533  Reporting NF 533  Reporting

NF 533 Analyses• Cumulative Actual vs. Planned – To assess the financial position of the

contract; variances may be an indication of technical, financial, or management issues– Examine variances between the values reported in columns 7c and 7d in

the same row• Average Labor Rates – To provide essential data about contract

performance related to baseline budget labor cost; an indicator of overruns/savings on the contract– Compare average labor rates reported in the NF 533M with the planned

rates of the baseline budget• Labor Overhead Rates - To indicate overruns/savings on the contract;

provides data about contract performance related to baseline budget planned labor overhead rates– Compare planned vs. actual labor overhead rates

• G&A Rates - To indicate overruns/savings on the contract; provides data about contract performance related to baseline budget planned G&A rates– Compare plan vs. actual General and Administrative (G&A) overhead rates