    Enhancing and Preserving

    Newman Golf Course

    A PRESENTATION FOR THE PEORIA PARK DISTRICT

    Todd Quitno

    Lohmann Golf DesignsBob Lohmann

    Lohmann Golf Designs

  • 8/9/2019 Newman Golf Course - Plan Presentation to Board

    2/27

    2015 (and beyond) Enhancement Project :• General Purpose for the Master Plan

    • Greens• Bunkers

    •Fairways

    • Tees

    • Timing / CostsBOB LOHMANN, ASGCA

    Founded firm in 1984

    Involved in every project since

    Currently basking in the sun in Arizona

    TODD QUITNO, ASGCA18+ years of project management with LGD

    100+ new/renovation projects, 6 national awards

    Lead architect for Kellogg Renovation

    Concept studies for Madison, Newman

  • 8/9/2019 Newman Golf Course - Plan Presentation to Board

    3/27

    • Make more beginner friendly by adding more variety in the forward yardagesand improving overall playability (attract Donovan golfers)

    • Restore to championship caliber by enhancing strategy and length, reinstall asa host or co-host of the City Championship

    • Rectify agronomic issues with the greens , specifically the perennial decline inturf quality during hot summer months (City Championship time)

    • Resolve major drainage issues that occur across several holes (3-7) causingclosures and subsequent revenue loss (rounds, carts, maintenance delays)

    • Conserve water, labor and fuel costs by reducing areas of maintained turfthrough use of “no-mow” areas

    • Keep course open during construction

    General Purpose

  • 8/9/2019 Newman Golf Course - Plan Presentation to Board

    4/27

    Objective

    Improve health of greens, providing more consistency throughout the 18 holes in terms ofplayability, tolerance to heat stress and watering requirements.

    Opportunities / Constraints :

    • Consider possibility of re-surfacing greens

    • Methyl bromide no longer available

    • Regrassing requires closing of course

    Priority #1 - Greens

    Fumigation

  • 8/9/2019 Newman Golf Course - Plan Presentation to Board

    5/27

    Objective

    Improve health of greens, providing more consistency throughout the 18 holes in terms ofplayability, tolerance to heat stress and watering requirements.

    Opportunities / Constraints :

    • Consider possibility of re-surfacing (like at Kellogg)

    • Installation of internal drainage system

    Priority #1 - Greens

  • 8/9/2019 Newman Golf Course - Plan Presentation to Board

    6/27

    Poor Drainage / Turf Stress

  • 8/9/2019 Newman Golf Course - Plan Presentation to Board

    7/27

    Slit Drainage

  • 8/9/2019 Newman Golf Course - Plan Presentation to Board

    8/27

    Objective

    Improve health of greens, providing more consistency throughout the 18 holes in terms ofplayability, tolerance to heat stress and watering requirements.

    Opportunities / Constraints :

    • Consider possibility of re-surfacing (like at Kellogg)

    • Installation of internal drainage system

    • Reconstruction or coring of problem greens (e.g. 18)

    Priority #1 - Greens

  • 8/9/2019 Newman Golf Course - Plan Presentation to Board

    9/27

    Greens Coring

  • 8/9/2019 Newman Golf Course - Plan Presentation to Board

    10/27

    Objective

    Improve health of greens, providing more consistency throughout the 18 holes in terms ofplayability, tolerance to heat stress and watering requirements.

    Opportunities / Constraints :

    • Consider possibility of re-surfacing (like at Kellogg)

    • Installation of internal drainage system

    • Reconstruction or coring of problem greens (e.g. 18)

    • Green expansions

    Priority #1 - Greens

  • 8/9/2019 Newman Golf Course - Plan Presentation to Board

    11/27

    • Slight adjustments in perimeter shapes for varied look• Additional pin positions / spread wear• Greens look, play bigger without reconstruction• Room exists within current irrigation spacing• Use of Donovan sod for material consistency / playabilityWORK CAN BE COMPLETED WITHIN 2 TO 3 WEEKS, TWO HOLES AT A TIME,KEEPING COURSE OPEN DURING CONSTRUCTION

    Green Expansion

  • 8/9/2019 Newman Golf Course - Plan Presentation to Board

    12/27

    Objective

    Improve drainage through swale that crosses holes 3,4,5,7,11 and 17 to provide optimal (dry)conditions for playability and maintenance

    Opportunities / Constraints :• Install sub-surface mainline drainagesystem to capture and direct stormwater, dispensing in swale by Hole 12

    • Provide laterals to collect isolatedpockets of water

    • Tie new features into mainline

    • Add full or partial path system toallow quicker opening after storms

    Priority #2 - Drainage

    Fumigation

  • 8/9/2019 Newman Golf Course - Plan Presentation to Board

    13/27

  • 8/9/2019 Newman Golf Course - Plan Presentation to Board

    14/27

    Objective

    Provide distinct teeing areas to accommodate a true 4-marker system with adequate size andyardage variety

    Opportunities / Constraints :

    • Add forward teeing areas to accommodate women, seniors and beginners and relieve stresson existing tee surfaces (by moving marker)

    • Separate the red and gold tees so that each has a distinct identity and yardage.• Works well with drainage project (source of dirt)

    Priority #3 - Tees

    Fumigation

  • 8/9/2019 Newman Golf Course - Plan Presentation to Board

    15/27

    EXISTING: 6838 6467 5571Existing tee layout…where to put the

    Gold?110 yd discrepancy

  • 8/9/2019 Newman Golf Course - Plan Presentation to Board

    16/27

    Objective

    Provide distinct teeing areas to accommodate a true 4-marker system with adequate size andyardage variety

    Opportunities / Constraints :

    • Add forward teeing areas to accommodate women, seniors and beginners and relieve stresson existing tee surfaces (by moving marker)

    • Separate the red and gold tees so that each has a distinct identity and yardage.• Rebuild several back tees making them longer front to back for more yardage variety

    Fumigation

    Priority #3 - Tees

  • 8/9/2019 Newman Golf Course - Plan Presentation to Board

    17/27

    Extend Hole 17 to par 5

    • Par 72

    • Safety with #3 green

    • More interesting hole

  • 8/9/2019 Newman Golf Course - Plan Presentation to Board

    18/27

    Objective

    Rebuild bunkers, providing• More consistent sand conditions throughout course• More resistance to erosion / storm damage (and subsequent clean-up)• Better strategic positioning and overall aesthetic appeal

    Opportunities :

    • Increase number of bunkers to around 31 (from the existing 27) while decreasing theoverall area of sand

    Priority #4 - Bunkers

  • 8/9/2019 Newman Golf Course - Plan Presentation to Board

    19/27

    Existing bunkers:

    27 @ 30,000 total sf

    Proposed bunkers:31 @ 25,000 total sf

  • 8/9/2019 Newman Golf Course - Plan Presentation to Board

    20/27

    Use of Grass Hollows

  • 8/9/2019 Newman Golf Course - Plan Presentation to Board

    21/27

    ObjectiveRebuild bunkers, providing

    • More consistent sand conditions throughout course• More resistance to erosion / storm damage (and subsequent clean-up)• Better strategic positioning and overall aesthetic appeal

    Opportunities :

    • Increase number of bunkers to around 31 (from the existing 27) while decreasing theoverall area of sand

    • Maximize visual and strategic appeal while minimizing maintenance

    Priority #4 - Bunkers

  • 8/9/2019 Newman Golf Course - Plan Presentation to Board

    22/27

    Example: BEFORE

  • 8/9/2019 Newman Golf Course - Plan Presentation to Board

    23/27

    Example: AFTER

    Anticipated Cost-Benefit:

    • Reduced sand area

    • Proper sub-surface drainage removes water instantly

    • Flatness of sand allows for minimal repair after storms

    • Visually striking, especially with morning/evening sun

    • Improve strategic value and playing appeal

  • 8/9/2019 Newman Golf Course - Plan Presentation to Board

    24/27

    ObjectiveRebuild bunkers, providing

    • More consistent sand conditions throughout course• More resistance to erosion / storm damage (and subsequent clean-up)• Better strategic positioning and overall aesthetic appeal

    Opportunities :

    • Increase number of bunkers to around 31 (from the existing 27) while decreasing theoverall area of sand

    • Maximize visual and strategic appeal while minimizing maintenance

    • Build on priority basis

    1st priority: Rebuild existing bunkers, mostly greenside

    2nd priority: New bunker locations, mostly fairway (best completed with back tees)

    Priority #4 - Bunkers

  • 8/9/2019 Newman Golf Course - Plan Presentation to Board

    25/27

  • 8/9/2019 Newman Golf Course - Plan Presentation to Board

    26/27

    Proposed Project Phasing and Costs

  • 8/9/2019 Newman Golf Course - Plan Presentation to Board

    27/27

    GREENS EXPANSION AND DRAINAGE PROJECT

    Why now (Spring)?• Take immediate action on green health (protect against summer heat)• Use Donovan sod while still available

    Scope: 1 – 6, 8 – 12, 14 – 17 (Excl. 7, 13, 18)

    Proposed Schedule:2/11 Approval by Park Board for Lohmann to do design work2/18 Special meeting2/25 Plans to Park District Planning Dept.3/3 Out to bid3/10 Pre-bid meeting3/17 Bid opening3/25 Park Board approval3/26 Notification to contractor and material blender

    5/1 Start construction• Two holes at a time (1 to 2 days down time)• Reopen main part of greens right away (temp. rope off sod expansions)

    5/22 Completion

    Schedule