![Page 1: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/1.jpg)
Your Proposal is not your Plan
Why successful project
execution needs a plan
Patricia (Patty) Huntley, PMP, MBARisk Manager Loss Prevention & Client Education
![Page 2: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/2.jpg)
Workshop Learning Objectives
2© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
1. At the conclusion of this program attendees will be able to prepare a project management plan that restates and supports the architect’s role in the delivery of structural, mechanical, electrical and plumbing building systems and confirms the required integrity of these systems.
2. This program provides attendees with a tool to prepare for a design that protects the safety and welfare of the users by identifying building codes, zoning laws and regulations that apply to the project and integrating these legal considerations into drawing and specifications.
3. After completing this program attendees will have a tool to define the soundness and health impacts of the design by confirming the completion of appropriate land-use analysis, health impact assessments, programming and surveying.
4. Today’s program participants will use the Project Management Plan to analyze risks associated with construction systems, products and finishes, and to subsequently assess and plan the use of materials and construction methods to protect the life and safety of the public.
![Page 3: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/3.jpg)
3
Your Proposal is not your PlanAgenda
Risk Drivers & planning
Proposals vs. Project Management Plans
Project Management Plan as a Roadmap
1
2
3
4 Effective use of a Project Management Plan
© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
![Page 4: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/4.jpg)
YOUR INSTRUCTORPatricia (Patty) Huntley, PMP, MBA
5
+1 year, Risk Manager, XL Catlin, Design Profession Loss Prevention Education – June 2016
15 years, A/E/C Project Delivery Consultant, PSMJ Resources, Inc.and Construction Management Consultant & Trainer (2002-2016)
13 years, Senior Project Manager of design/build environmental engineering projects, The RETEC Group, Inc. (1989-2002)
� 7 years in mining industry� Certified Project Management Professional (PMI)� B.S., M.S.(abt) Colorado State University; M.B.A. University of Denver
© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO 4
![Page 5: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/5.jpg)
YOU
5© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
Project Fee Size
___ <$25,000
___ $25 - 500,000
___ >$500,000
![Page 6: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/6.jpg)
Your Proposal is not your Plan
6© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
1. My client was surprised that our project fee does
not cover unknown conditions on the project.
2. I gave everyone working on the project a copy of
the proposal but they spent time on rework
because of misunderstandings about what they are
supposed to do.
3. My client was really unhappy with me when I talked
with them about the cost of the additional work they
requested. They said it should have been included
in the original cost estimate.
Does any of this sounds familiar?
![Page 7: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/7.jpg)
7© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
Risk Drivers & PlanningSection 1
![Page 8: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/8.jpg)
8© 2018, XL Group Ltd. All rights reserved. I MAKE YOUR WORLD GO
1) TECHNICAL
2) NON-TECHNICAL
Risk Drivers
2
XL Catlin’s Design Professional Insurance
classifications of causes leading to a loss prevention file or a claim being made
![Page 9: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/9.jpg)
9© 2018, XL Group Ltd. All rights reserved. I MAKE YOUR WORLD GO
Proprietary Research
7
XL Catlin’s Design Professional Insurance
claimshave non-technical factors that contribute to technical errors
10
![Page 10: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/10.jpg)
10
TECHNICALNON-TECHNICAL
Error and/ or
omission of a
technical nature
RESULTS IN
Breakdown in
project or practice
management
processes
CONTRIBUTES TO
Loss Prevention File or Claim
© 2018, XL Group Ltd. All rights reserved. I MAKE YOUR WORLD GO
Technical vs. non-technical
![Page 11: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/11.jpg)
11
Risk Driver Interrelationship
TECHNICAL
NON-TECHNICAL
EVENT CLAIM
© 2018, XL Group Ltd. All rights reserved. I MAKE YOUR WORLD GO
contributes to, or exacerbates a claim
![Page 12: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/12.jpg)
12© 2018, XL Group Ltd. All rights reserved. I MAKE YOUR WORLD GO
Risk Drivers 2.0 by claims count
Negotiations & Contracts
6%
COMMUNICATIONS
30%
QUALITY MANAGEMENT
12%
CLIENT SELECTION
16%
CONSTRUCTION PHASE SERVICES
18%
PROJECT TEAM CAPABILITIES
14%
![Page 13: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/13.jpg)
13© 2018, XL Group Ltd. All rights reserved. I MAKE YOUR WORLD GO
55%Lack of procedures to identify conflicts, errors and omissions
Project issues/ disputes not handled well
13%
13%Scope of services not clearly explained to client
of non-technical Risk Drivers
Multiple/ Other issues19%
CommunicationsRisk Drivers (No. 1 by claims count)
![Page 14: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/14.jpg)
14
COMMUNICATIONS TAKE AWAYS
© 2018, XL Group Ltd. All rights reserved. I MAKE YOUR WORLD GO
1. Start projects correctly
• Plan then do
2. Don’t hope it will get better - manage
communication
3. Do engage XL Catlin early
CommunicationsRisk Drivers
![Page 15: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/15.jpg)
15© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
Proposal vs. Project Management Plan
Section 2
![Page 16: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/16.jpg)
�
What are you offering?
16© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
Task Delivery Product Delivery
Completed tasks Met client expectations
Detailed Scope, Schedule, Budget
Define project goals, approach, detailed scope of work
Complete all tasks within the budget & schedule
Deliver outcomes - project goals, client needs, client objectives, company needs
Completed project
![Page 17: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/17.jpg)
Proposal vs. PMPWhere would you find the following?
17© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
Proposal PMP
Project Objectives
Scope of Work
Schedule
Budget
Team Organization
Risk Management Plan
Quality Control Plan
Communication Plan
Project Closeout Checklist
![Page 18: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/18.jpg)
The devil is in the details
18© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
Your Proposal Project Execution
Present project goals
• Define Measures – monitor and forecast outcomes
• Define Metrics – quantify an outcome
Introduce project team • Manage project team
Present “amazing” project
• Execute “real” project
• Communicate & manage change
• Monitor & manage risks
• Manage & meet client expectations
![Page 19: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/19.jpg)
The devil is in the details (continued)
19© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
Your Proposal Project Execution
Present “winning” project schedule & fee
• Monitor - Budget & Schedule
• Communicate Status – Budget & Schedule
• Communicate & Manage Change
• Define Communication Plan
• Execute team and client communicationDiscuss Communication
Present Quality Process • Execute Quality Management
![Page 20: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/20.jpg)
Firms with formal project management planningSurvey of 229 Firms (PSMJ Resources, Inc.)
20© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
21% Almost Always
31% Usually to Often
30% Occasionally
18% Rarely
Prepare or generally prepare written plan
Generally do not or rarely prepare a written plan
52%
48%
Survey source: PSMJ Resources, Inc.
![Page 21: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/21.jpg)
Project planning improves budget performance& client satisfaction (PSMJ Resources, Inc.)
21© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
Average Achieved Multiplier
Average Client Satisfaction
Score
Generally donot prepare a written plan
2.5 Multiplier
Generally prepare written plan
2.8 Multiplier
4.6/5.0
4.3/5.0
Survey source: PSMJ Resources, Inc.
![Page 22: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/22.jpg)
I don’t have the time or money to do this
22© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
Can’t, Won’t, Don’t Excuse Crusher
I have a tight budget
My client will not pay for this
I manage too many projects to do this for each one
I am a project manager/doer
I keep my client happy by getting the work done
Generally 1 - 3% of budget
Include it in your budget
Let’s do the math
I like looking busy & rushed, instead of effective & efficient
Are you completing tasks or delivering a product?
![Page 23: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/23.jpg)
23© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
PMP as RoadmapSection 3
![Page 24: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/24.jpg)
What documents do you need to review while preparing your PMP?
24© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
List three documents
1.___________________________
2.___________________________
3.___________________________
![Page 25: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/25.jpg)
Bringing it all together
25© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
1. RFP – Request for proposal
2. Go-No-Go evaluation
3. Proposal - including
• Detailed WBS (Scope)
• Detailed schedule & fee
4. Negotiation notes - changes & additions
5. Contract
![Page 26: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/26.jpg)
When do you complete a Project Management Plan?
26© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
you have signed the Contract
you start billing project work
BUT . . .
![Page 27: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/27.jpg)
Right-sized PMPs
27© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
Small PMP
PMP
• Fee size
• Team size
• Project complexity
• Duration2.
![Page 28: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/28.jpg)
PMP for projects with fees less than $25,000
• Project fee <$25,000
• Single
� discipline
� sub-contractor/consultant
� client contact
• Routine projects
• 1 - 3 people work on project
• Short duration <12 weeks
28© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
Small PMP
![Page 29: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/29.jpg)
Small Project Management Plan <$25,000 fee
29© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
Small PMP Components
1. Project Information
2. Client Information
3. Scope-of-Work
4. Budget
5. Due Dates
![Page 30: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/30.jpg)
General Information
Date: Project Location:
Project Name: Signed Contract: yes no
Type of Contract: Project Manager:
Project Number: Senior Reviewer:
Client Information
Contact: Phone:
Title: Cell Phone:
Address: Email:
Task / ElementTask Lead
Due Date
Budget Hours
Budget Dollars
TOTALS
30© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
PMP for small project
![Page 31: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/31.jpg)
31© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
General Information
Date: Project Location:
Project Name: Signed Contract: yes no
Type of Contract: Project Manager:
Project Number: Senior Reviewer:
Client Information
Contact: Phone:
Title: Cell Phone:
Address: E-mail:
Small PMP – General Project Information
PROJECT
CLIENT
YES / NO?
![Page 32: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/32.jpg)
Small PMP – Scope, Schedule, Budget
32© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
Task/Element Task Lead Due DateBudget Hours
Budget Dollars
TOTALS
PROJECT
DO YOU NEED
BOTH?
![Page 33: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/33.jpg)
PMP for projects fees > (greater than) $25,000
• Project fee >$25,000
• Multiple
� disciplines
� sub-contractors/consultants
� diverse group of stakeholders
• Complex project
• Multiple people/offices work on project
• Longer duration >12 weeks
33© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
Project Management Plan
![Page 34: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/34.jpg)
Project Management Plan >$25,000 fee
34© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
PMP Components
1. Goals, Objectives 6. Document Distribution
2. Scope-of-Work 7. Project Communication
3. Budget 8. Risk Management
4. Schedule 9. Quality Management
5. Team 10. Change Management
![Page 35: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/35.jpg)
Align vision, goals, objectives
© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
Process
Product
Project
Team Performance
Quality of Design
Project Objectives
Define with Measures & Metrics
35
![Page 36: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/36.jpg)
Align process
© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
Process
• Communication
• Responsiveness
• Resource availability
• Effectiveness of meetings
• Resolution of issues
Team Performance
36
![Page 37: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/37.jpg)
Align product
© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
Product
Quality of Design
• Functionality
• Ease-of-use
• LEED Certification
• Regulatory Compliance
• Cost-effective design
37
![Page 38: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/38.jpg)
Align project
© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
Project
Project Objectives
• Well-developed SOW
• Meet deliverable deadlines
• Meet project budget
• Manage change
• Timely procurement
38
![Page 39: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/39.jpg)
Scope-of-Work & Schedule
39© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
Task
No.
Sub
Task
Task
Manager
Start
Date
Finish
Date
100
101 PM 1/15 1/22
102 PM 1/19 1/26
103 PM 1/22 6/15
104 PM 1/29 6/17
105 PM 1/15 5/31
200
201 Name 1 Date Date
202 Name 1 Date Date
203 Name 1 Date Date
300
301 Name 2 Date Date
302 Name 2 Date Date
303 Name 2 Date Date
TaskTASK 3
Task
Task
Task
Monthly Project Meeting
Subcontractor ManagementTASK 2
Task
Task
Project Task
Project Management
Project Management Plan
Project Kick-off meeting
Weekly / Monthly Project Status Report
Scope-of-Work & Schedule
Project Name: Client:
Project Number: Project Manager:
Date Prepared: PIC:
Project Start Date: Jan 15 Project Finish Date: June 15
![Page 40: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/40.jpg)
Budget
40© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
Task
No.
Sub
Task
Task
Manager
Start
Date
Finish
Date
Total Labor
Cost
Total ODC
CostTotal Cost
100
101 PM 1/15 1/22 $400 $0 $400
102 PM 1/19 1/26 $1,000 $250 $1,250
103 PM 1/22 6/15 $1,100 $0 $1,100
104 PM 1/29 6/17 $1,000 $250 $1,250
105 PM 1/15 5/31 $400 $0 $400
200 $4,400
201 Name 1 Date Date
202 Name 1 Date Date
203 Name 1 Date Date
300
301 Name 2 Date Date
302 Name 2 Date Date
303 Name 2 Date Date
Project Budget
Project Task
Client:
Project Manager:
Project Finish Date: June 15
Project Name:
Project Number:
Project Start Date: Jan 15
Date Prepared: PIC:
TASK 3
Task
Task
Task
Subtotal
Subtotal
Subcontractor Management
TASK 2
Task
Task Task
Project Management
Project Kick-off meeting
Weekly / Monthly Project Status Report
Monthly Project Meeting
Project Management Plan
![Page 41: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/41.jpg)
Schedule
41© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
Task
No.
Sub
Task
Start
Date
Finish
Date
100
101 1/15 1/22
102 1/19 1/26
103 1/22 6/15
104 Monthly Project Status Rpt 1/22 6/15
105 1/29 6/17
106 1/15 5/31
200
201 2/1 2/10
202 2/10 4/1
203 2/22 4/15
300
301 3/1 3/25
302 3/14 4/22
303 3/28 4/29
Project Name: Client:
Project Number: Project Manager:
Date Prepared: PIC:
Project Kick-off meeting
Start Date: Jan 15, Finish Date: June 15,
Project Task JAN APR MAY JUN
Project Management
Project Management Plan
FEB MAR
Weekly Project Status Rpt
Monthly Project Meeting
Subcontractor Management
TASK 2
Sub-Task
Task
Task
TASK 3
Task
Task
Task
Schedule - Bar Chart
![Page 42: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/42.jpg)
Team
42© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
Project Team
Name Assignment Organization Office E-Mail Office Ph Mobile Ph
• Internal project team
• Sub-consultant teams
• Sub-contractor teams
• Client
• Client Representative
• Significant Stakeholders
Emergency Contact Information
![Page 43: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/43.jpg)
Document Distribution
43© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
Deliverables and Schedule
Deliverable Due Date Recipients
• All deliverables
• Internal draft dates
• Internal review dates
• Final deliverables
• Confirm recipient delivery method/format
• Client review dates as a deliverable
![Page 44: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/44.jpg)
Project Communication
44© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
• Weekly meetings
• Monthly meetings
Project Communication
TypeDate/
FrequencyAttendees
• Progress reports
• Conference calls
• Invoice summaries
• Design meetings
![Page 45: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/45.jpg)
Risk Management
45© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
1. Value-added discussion
2. Proactive vs. reactive
3. IDs potential changes to the project
4. Daylights client concerns
More than Probability x Severity
![Page 46: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/46.jpg)
Common Categories of Project Risks
46© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
• Contracts & Negotiations
• Scope Management
• Financial Management
• Schedule Management
• Resource Availability
• Technical Integrity
• Quality Assurance
• Project Type
• Client Management
• Health & Safety, Regulatory
![Page 47: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/47.jpg)
Risk Management Log
47© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
Risk ManagementProject Name: __________________________ Project Number:___________________
Project Manager: ________________________ Client Name: _____________________
Date of revision: ________________________
Risk No.
Potential Risk Risk Owner Trigger DependenciesProbability
(Hi/Med/Low)Impact
(Hi/Med/Low)Management
StrategyStatus
R1
R2
• Potential risk – identify potential problems that could impact project
• Risk owner – responsible for managing risk
• Trigger – early warning sign that an event may occur
• Dependencies – contributing factors that drive a risk event
![Page 48: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/48.jpg)
Risk Management Log (continued)
48© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
Risk ManagementProject Name: __________________________ Project Number:___________________
Project Manager: ________________________ Client Name: _____________________
Date of revision: ________________________
Risk No.
Potential Risk Risk Owner Trigger DependenciesProbability
(Hi/Med/low)Severity
(Hi/Med/low)Management
StrategyStatus
R1
R2
• Probability – the likelihood a risk will occur
• Severity – the degree of harm if an event occurs
• Management Strategy – avoid, mitigate, accept & monitor, transfer
• Status – update throughout project until potential risk is gone
![Page 49: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/49.jpg)
Quality
49© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
Quality Assurance Process Quality Control Plan
• Defines expectations
• Plans project execution
• Supports active team collaboration
• Adherence to budget & schedule
• Defines checklists, techniques, methods to assure quality
• Design/Technical review
• Followed standards
• Drawings-to-Specs review
• Senior management review
• Constructability review
• CHECKING
QUALITY MANAGEMENT
![Page 50: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/50.jpg)
Quality Control Plan
50© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
QC PlanProject Name: ________________ Project Number: __________________
Project Manager: _____________ Client Name: __________________
Date of revision: ______________
Document for ReviewDocument due from
To ReviewerDate due to
reviewerDate for review
completionStatus
Standards, Procedures, SOPs, Project Documents
Title Comments
![Page 51: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/51.jpg)
Change Management
51© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
1. Discuss change process – Kick-off
2. Recognize & identify change
3. Leverage
4. Define impact of change
5. Obtain approval for change
6. Document change
Managing Change
![Page 52: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/52.jpg)
52© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
Select one: New Scope Increase in Scope Decrease in Scope
Add Services (Change Order) Form
Current Scope of Work(Describe the requirements/specifications)
(Describe in detail the reason for the change)
Cost Estimate (attach backup)
Schedule Impact (attach backup)
Project Manager: Aurthorized Client Representative:Signature:Signature:
Reason for Change
Proposed Scope of Work Change
Date:Change Order No.:Project Number:Task Number:
Project Name:Project Manager:
(Describe in detail the reason for the change)
Client Rep.:
![Page 53: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/53.jpg)
53
Section 4
Effective use of your PMP
© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
![Page 54: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/54.jpg)
PMP is consulted continuously
54© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
1) Working through a scope change
2) Completing a phase of work
3) Reviewing draft invoice
4) Prior to submitting a deliverable
When?
![Page 55: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/55.jpg)
PMP is an evergreen document
55© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
1) Change Order or Add Service
2) Scope Creep
3) Change on team
4) Change on client team
5) Change in Stakeholder requirements
6) Unexpected delays or problems
Update as change occurs
![Page 56: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/56.jpg)
56© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
Wrap up
![Page 57: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/57.jpg)
Your Proposal is not your Plan
57© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
What did we cover?
1) Risk Drivers
2) Proposal vs. Plan
3) PMP as Road Map
• Small PMP
• PMP
4) Effective use of PMP
![Page 58: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/58.jpg)
58
Questions?
© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
![Page 59: New Why successful project execution needs a plan · 2019. 5. 14. · YOUR INSTRUCTOR Patricia (Patty) Huntley, PMP, MBA 5 +1 year, Risk Manager, XL Catlin, Design Profession Loss](https://reader035.fdocuments.net/reader035/viewer/2022071215/60449fff0f4f086a9764b3aa/html5/thumbnails/59.jpg)
59© 2018, XL Group plc. All rights reserved. I MAKE YOUR WORLD GO
Patricia (Patty) Huntley
THANK YOU