TOWN OF SURFSIDE BEACH
BUDGET FY 2012 - 2013
2
TABLE OF CONTENTS1. Title Page
2. Table of Contents
3. Organizational Charts
4. Town of Surfside Beach Organizational Chart
5. Administration Chart
6. Court Chart
7. Finance Chart
8. Fire Chart
9. Planning, Building & Zoning Chart
10. Police Chart
11. Public Works Chart
12. Recreation & Special Events Chart
13. Budget
14. Accounting Language Changes
15. Summary of All Activities Chart
16. Summary of All Activities Table
17. Total Fund Balances by Year (General Fund only) Chart
18. Total Fund Balances by Year (General Fund only) Table
19. Unassigned Fund Balance by Year (General Fund only) Chart
20. Unassigned Fund Balance by Year (General Fund only) Table
21. Unassigned Fund Balance as a Percentage of Expenditures Chart
22. Unassigned Fund Balance as a Percentage of Revenue Chart
23. FY 2012-2013 Proposed Revenues Chart
24. FY 2012-2013 Proposed Revenues Table
25. Intergovernmental and Other Revenues Detail
26. Millage Assignment Chart
27. Total General Fund Expenditures by Fiscal Year Chart
28. Total General Fund Expenditures by Fiscal Year Table
29. Total Operating Expenditures by Fiscal Year Chart
30. Total Operating Expenditures by Fiscal Year Table
31. FY 2012-2013 Proposed Expenditures by Department Table
32. FY 2012-2013 Proposed Expenditures by Department Chart
33. Net Revenue (Expenditures) before Debt Service and Capital Expenditures Chart
34. Net Revenue (Expenditures) before Debt Service and Capital Expenditures Table
35. Capital Expenditures
36. Capital Expenditures – Police
37. Capital Expenditures – Police
38. Capital Expenditures – Grounds
39. Capital Expenditures – Court
40. Capital Expenditures – Public Works
41. Capital Expenditures – Non-Departmental
42. General Fund Capital Expenditures Chart
43. General Fund Capital Expenditures Table
44. Debt Service
45. Debt Service General Obligation Bonds Chart
46. Debt Service General Obligation Bonds Table
47. Debt Service – Ladder Truck Chart
48. Debt Service – Ladder Truck Table
49. Capital Projects Fund Storm Water Header Page
50. Capital Projects Fund Storm Water Chart
51. Capital Projects Fund Storm Water Table
52. Hospitality Fund
53. Hospitality Revenues Chart
54. Hospitality Revenues Table
55. Hospitality Expenditures Chart
56. Hospitality Expenditures Table
57. Accommodations Tax
58. Accommodations Tax Revenues Chart
59. Accommodations Tax Revenues Table
60. Accommodations Tax Expenditures Chart
61. Accommodations Tax Expenditures Table
62. Enterprise Funds
63. Sanitation Fund Chart
64. Sanitation Fund Table
65. Pier Enterprise Fund Chart
66. Pier Enterprise Fund Table
ORGANIZATIONAL CHARTSBY DEPARTMENT
3
TownCouncil
Administration Finance Building & Zoning Court Public Works Recreation Police
DepartmentFire
Department
Deputy Administrator
Town of Surfside Beach, SCOrganizational Chart 6/30/13
TownAdministrator
Town Clerk
4
Surfside Beach AdministrationFY 2012‐2013 Organizational Chart
Town Council
Town Administrator
Deputy Administrator
Part‐time Receptionist
Part‐time Receptionist
Website & Marketing Intern
Town Clerk
5
Surfside Beach CourtFY 2012‐2013 Organizational Chart
Surfside Beach CourtFY 2012‐2013 Organizational Chart
JudgeJudge
Associate Judge and Clerk of
Court
Associate Judge and Clerk of
Court
Assistant Clerk of Court
Assistant Clerk of Court
6
Surfside Beach Finance DepartmentFY 2012‐2013 Organizational ChartSurfside Beach Finance DepartmentFY 2012‐2013 Organizational Chart
Treasurer Treasurer
Payroll & BenefitsPayroll & BenefitsBusiness License Official
Business License Official
Business License Inspector
Business License Inspector
Senior Accountant, Financial Reporting, Accounts Payable
Senior Accountant, Financial Reporting, Accounts Payable
7
8
Surfside Beach Fire DepartmentFY 2012‐2013 Organizational ChartSurfside Beach Fire Department
FY 2012‐2013 Organizational Chart
Fire Chief Fire Chief
A/C Operations (EOC) (Volunteer)A/C Operations
(EOC) (Volunteer)
LieutenantA‐Shift
LieutenantA‐Shift
EngineerA‐ShiftEngineerA‐Shift
LieutenantB‐Shift
LieutenantB‐Shift
EngineerB‐ShiftEngineerB‐Shift
Volunteers24
Volunteers24
LieutenantC‐Shift
LieutenantC‐Shift
EngineerC‐ShiftEngineerC‐Shift
A/C Admin Support
(Volunteer)
A/C Admin Support
(Volunteer)
Surfside Beach Planning, Building & Zoning Department FY 2012‐2013 Organizational Chart
Surfside Beach Planning, Building & Zoning Department FY 2012‐2013 Organizational Chart
DirectorDirector
Building Inspector &
Code Enforcement
Building Inspector &
Code Enforcement
Construction Services
Coordinator
Construction Services
Coordinator
9
Surfside Beach Police DepartmentFY 2012‐2013 Organizational Chart
Chief of PoliceChief of Police
CaptainCaptain
Comm. Supv. Comm. Supv.
Senior DispatcherSenior
Dispatcher
DispatcherDispatcher
DispatcherDispatcher
DispatcherDispatcher
DispatcherDispatcher
P/T Dispatcher
P/T Dispatcher
P/T Dispatcher
P/T Dispatcher
P/T Dispatcher
P/T Dispatcher
Evidence & Transport Evidence & Transport
Rotation SergeantRotation Sergeant
Patrol CorporalPatrol
Corporal
Patrol OfficerPatrol Officer
Patrol OfficerPatrol Officer
Patrol CorporalPatrol
Corporal
Patrol OfficerPatrol Officer
Patrol OfficerPatrol Officer
P/T Patrol Officer
P/T Patrol Officer
P/T Patrol Officer
P/T Patrol Officer
P/T Patrol Officer
P/T Patrol Officer
Rotation SergeantRotation Sergeant
Patrol CorporalPatrol
Corporal
Patrol OfficerPatrol Officer
Patrol OfficerPatrol Officer
Patrol CorporalPatrol
Corporal
Patrol OfficerPatrol Officer
Patrol OfficerPatrol Officer
Criminal DetectiveCriminal Detective
Narc Dectective
Narc Dectective
Bike Patrol FunctionBike Patrol Function
PT Victim's AdvocatePT Victim's Advocate
LieutenantLieutenant
10
Surfside Beach Public WorksFY 2012‐2013 Organizational Chart
Surfside Beach Public WorksFY 2012‐2013 Organizational Chart
Public Works Director
Public Works Director
Executive AssistantExecutive Assistant
Fleet ForemanFleet
Foreman
MechanicMechanic
StreetSupervisorStreet
Supervisor
Street ForemanStreet
Foreman
Heavy Eq. Op
Heavy Eq. Op
Light Eq. Op
Light Eq. Op
Light Eq. Op
Light Eq. Op
Light Eq. Op w/CDLLight Eq. Op w/CDL
Light Eq. Op
Light Eq. Op
Light Eq. Op
Light Eq. Op
Grounds ForemanGrounds Foreman
Light Eq. Op
Light Eq. Op
LaborerLaborer
SanitationSupervisorSanitationSupervisor
CDL Foreman(CDL‐3 Driver)CDL Foreman(CDL‐3 Driver)
CDL‐3 DriverCDL‐3 Driver
CDL‐3 DriverCDL‐3 Driver
CDL‐2 DriverCDL‐2 Driver
CDL‐1 DriverCDL‐1 Driver
LaborerLaborer LaborerLaborer
CDL‐3 Driver CDL‐3 Driver
GroundsSupervisorGroundsSupervisor
FacilitiesPart Time
Facilities
11
Surfside Beach Recreation and Special Events Department FY 2012‐2013 Organizational ChartSurfside Beach Recreation and Special Events Department FY 2012‐2013 Organizational Chart
Special Events/ Recreation Supervisor
Special Events/ Recreation Supervisor
Athletics CoordinatorAthletics
Coordinator
Part‐TimeAthletic AidePart‐Time
Athletic Aide
12
BUDGETJULY 1 , 2012 - JUNE 30 , 2013
13
ACCOUNTING LANGUAGE CHANGES
• Unassigned• Assigned• Committed (Reserve was old term)• Restricted (Designated was old term)
• Victims’ Advocate Program• Street Improvements
• Non-Spendable (Reserve was old term)• Inventory (diesel and postage)• Prepaids (Insurance)• Advances (Pier)
14
SUMMARY OF ALL ACTIVITIES
$(1,000,000)
$-
$1,000,000
$2,000,000
$3,000,000
$4,000,000
$5,000,000
$6,000,000
$7,000,000
$8,000,000
$9,000,000
$10,000,000
AdoptedRevenues
ProposedRevenues
AdoptedExpenditures
ProposedExpenditures
AdoptedImpact onFund Balance
ProposedImpact onFund Balance
15
SUMMARY OF ALL ACTIVITIES
FundAdopted
RevenuesProposed Revenues
Adopted Impact on
Fund Balance
Proposed Expenditures
Adopted Expenditures
Proposed Impact on
Fund Balance
General Fund $ 5,332,140 $ 5,611,012 $ (438,912) $ 6,099,810 $ 5,771,052 $ (488,798)
Capital Projects Fund $ 320,000 $ 268,750 $ (4,000) $ 437,375 $ 324,000 $ (168,625)
Hospitality Fund $ 810,000 $ 795,000 $ 366,396 $ 780,000 $ 443,604 $ 15,000 Accommodations Tax Fund $ 495,000 $ 450,000 $ 13,653 $ 477,508 $ 481,347 $ (27,508)Local Accommodations $ 140,000 $ 140,000 $ - $ 140,000 $ 140,000 $ -
Sanitation Fund $ 1,136,200 $ 1,094,000 $ 521 $ 1,195,023 $ 1,135,679 $ (101,023)Pier Enterprise Fund $ 280,000 $ 304,773 $ 150,604 $ 135,193 $ 129,396 $ 169,580 Governmental Activities Total $ 8,513,340 $ 8,663,535 $ 88,262 $ 9,264,909 $ 8,425,078 $ (601,374)
16
TOTAL FUND BALANCES BY YEAR (GENERAL FUND ONLY)
$- $500,000
$1,000,000 $1,500,000 $2,000,000 $2,500,000 $3,000,000 $3,500,000 $4,000,000 $4,500,000 $5,000,000
Totals
Actual EndingBalance3/31/2009
Actual EndingBalance6/30/2010
Actual EndingBalance6/30/2011
AdoptedEnding Balance6/30/2012
ProposedEnding Balance6/30/2013
17
TOTAL FUND BALANCES BY YEAR (GENERAL FUND ONLY)
Fund Balances
Actual Ending
Balance 3/31/2009
Actual Ending
Balance 6/30/2010
Actual Ending
Balance 6/30/2011
Adopted Ending
Balance 6/30/2012
Proposed Ending
Balance 6/30/2013
Totals $ 4,339,154 $ 4,563,328 $ 3,929,995 $ 3,491,083 $ 3,002,285
18
UNASSIGNED FUND BALANCE BY YEAR (GENERAL FUND ONLY)
19
$0
$200,000
$400,000
$600,000
$800,000
$1,000,000
$1,200,000
$1,400,000
$1,600,000
$1,800,000
Actual EndingBalance3/31/2009
Actual EndingBalance6/30/2010
Actual EndingBalance6/30/2011
AdoptedEndingBalance6/30/2012ProposedEndingBalance6/30/2013
UNASSIGNED FUND BALANCE BY YEAR (GENERAL FUND ONLY)
Fund Balance
Actual Ending
Balance 3/31/2009
Actual Ending
Balance 6/30/2010
Actual Ending
Balance 6/30/2011
Adopted Ending
Balance 6/30/2012
Proposed Ending
Balance 6/30/2013
General Fund $ 1,142,666 $ 1,572,656 $1,672,042 $1,306,582 $ 1,104,284
20
UNASSIGNED FUND BALANCE AS A PERCENTAGE OF EXPENDITURES
0.00%
5.00%
10.00%
15.00%
20.00%
25.00%
Actual EndingBalance3/31/2009
Actual EndingBalance6/30/2010
Actual EndingBalance6/30/2011
BudgetedEnding Balance6/30/2012
ProposedEnding Balance6/30/2013
21
UNASSIGNED FUND BALANCE AS A PERCENTAGE OF REVENUE
Unassigned$1,104,284
19.68%
General Fund Revenue
$5,611,012
Calculation: $1,104,284 ÷ $5,611,012 = 19.68%22
FY 2012-2013 PROPOSED REVENUES
Property Taxes$2,184,000
39%
Licenses and Permits
$1,493,000 27%
Franchise Fees$584,600
10%
Other Financing Sources$786,192
9%
Intergovernmental Revenues$281,720
6%
Fines and Forfeits$195,000
4%
Other Revenue$76,500
1%Interest$10,000
0%
23
FY 2012 – 2013 PROPOSED REVENUES
Revenues FY 2013 Proposed Property Taxes $ 2,184,000
Licenses and Permits $ 1,493,000
Franchise Fees $ 584,600
Other Financing Sources $ 786,192
Intergovernmental Revenues $ 281,720
Fines and Forfeits $ 195,000
Other Revenue $ 76,500
Interest $ 10,000
Total $ 5,611,012 24
INTERGOVERNMENTAL AND OTHER REVENUESIntergovernmental Revenues FY11-12 Budget FY12-13 ProposedLocal Government Fund(State ) $ 90,000 $ 65,000 Alcohol Permits $ 41,500 $ 41,500 Homestead Exemption $ 40,000 $ 40,000 Merchants Inventory $ 11,120 $ 11,120 Grants - DOT & CTC - -Grants (Gov, Police, Insurance) $ 7,500 $ 7,500 H.C. Recreation Dept. $ 16,600 $ 16,600 H.C. Vehicle Tax (Road Fees) $ 100,000 $ 100,000 Subtotal $ 306,720 $ 281,720
Other Revenue Rec. Fees, Athletics & Sp. Events $ 55,000 $ 51,500 Miscellaneous (False Alarms, Prisoner Housing, Donations, etc.) $ 25,000 $ 25,000 Subtotal $ 80,000 $ 76,500
Other Financing Sources Accommodations Tax Fund (First $25,000 plus 5% of Receipts) $ 45,000 $ 46,250 Sanitation Fund (% of Income) $ 58,500 $ 109,250 Hospitality Fund $ 150,000 $ 441,880 Local Accommodations (100%) $ 140,000 $ 140,000 Pier Enterprise (% of Income) $ 17,500 $ 30,477 Pier Enterprise (Interest per payment schedule) $ 22,820 $ 18,335 Sale of Fixed Assets $ 25,000 -Subtotal $ 458,820 $ 786,192 Total $ 845,540 $ 1,144,412
25
MILLAGE ASSIGNMENT
26
FY2013-2014
General Fund55%
Debt Service24%
StormWater13%
Capital Replacements
8%
FY2012-2013
General Fund66%
Debt Service12%
StormWater14%
Capital Replacements
8%
40 Mils• 22.4 to General Fund• 9.6 to Debt Service• 5 to Storm Water• 3 to Capital Replacements
TOTAL GENERAL FUNDEXPENDITURES BY FISCAL YEAR
FY 2009 Actual FY 2010 Actual FY 2011 Actual FY 2012Adopted
FY 2013Proposed
$5,457,413 $6,874,719 $6,826,907 $5,771,052 $6,099,810
$1,386,21015 Month Year
$1,105,414Fire Truck
$7,000,000
$6,000,000
$5,000,000
$4,000,000
$3,000,000
$2,000,000
$1,000,000
$ 0
27
TOTAL GENERAL FUNDEXPENDITURES BY FISCAL YEAR
Fiscal Year Total Expenditure
FY 2009 Actual $ 5,457,413
FY 2010 Actual $ 6,874,719
FY 2011 Actual $ 6,826,907
FY 2012 Adopted $ 5,771,052
FY 2013 Proposed $ 6,099,810
28
TOTAL OPERATING EXPENDITURESBY FISCAL YEAR (EXCLUDES SALARIES AND BENEFITS)
FY 2009 Actual FY 2010 Actual FY 2011 Actual FY 2012Adopted
FY 2013Proposed
$-
$200,000
$400,000
$600,000
$800,000
$1,000,000
$1,200,000
$1,400,000
$1,600,000
$1,359,943
$1,210,675
$1,130,695 $1,204,332
$1,281,878 $265,354
$1,476,029
(Last 12 months)
29
TOTAL OPERATING EXPENDITURESBY FISCAL YEAR (EXCLUDES SALARIES AND BENEFITS)
Fiscal Year Operating Expenditures
FY 2009 Actual $ 1,359,943
FY 2010 Actual $ 1,476,029
FY 2011 Actual $ 1,130,695
FY 2012 Adopted $ 1,204,332
FY 2013 Proposed $ 1,281,878
30
FY 2013 PROPOSED EXPENDITURESBY DEPARTMENT
Salaries$2,876,353
55%
Benefits$1,125,536
21%
Police$266,426
5%
Public Works$196,830
4%
Administration$144,634
3%
Recreation & Events$124,761
2%
Fire$127,115
2%
Non-Departmental$119,305
2%
P,B & Z$72,631
1%
Grounds$66,054
1%
Finance$70,117
1%
Court$36,675
1%
Facilities$27,791
1% Fleet Maintenance$29,539
1%
31
Salaries & Benefits $4,001,889
FY 2013 PROPOSED EXPENDITURESBY DEPARTMENT
Expenditures FY 2013 ProposedSalaries $ 2,876,353Benefits $ 1,125,536Police $ 266,426Public Works $ 196,830Administration $ 144,634Recreation & Events $ 124,761Fire $ 127,115Non-Departmental $ 119,305P,B & Z $ 72,631Grounds $ 66,054Finance $ 70,117Court $ 36,675Facilities $ 27,791Fleet Maintenance $ 29,539Total $ 5,283,76732
NET REVENUE (EXPENDITURES) BEFORE DEBT AND CAPITAL EXPENDITURES
$0
$500,000
$1,000,000
$1,500,000
$2,000,000
$2,500,000
$3,000,000
$3,500,000
$4,000,000
$4,500,000
Total Revenue = $ 5,611,012
$4,001,889
$1,281,878
$327,245
Personnel Costs
Operating Expenditures
Net Revenue before Debtand Capital Expenditures
33
NET REVENUE (EXPENDITURES) BEFORE DEBT AND CAPITAL EXPENDITURES
Revenues Personnel Costs Operating Expenditures
Net Revenue Expenditures
before Debt and Capital
Expenditures$ 5,611,012 $ 4,001,889 $ 1,281,878 $ 327,245
34
35
CAPITAL EXPENDITURES
CAPITAL EXPENDITURES - POLICENew Police Interceptor
36
$27,000
CAPITAL EXPENDITURES - POLICE
Unmarked VehicleState Contract
37
$17,000
Unmarked VehiclePre-owned
$10,000
Total Expenditure for 3 Police Vehicles = $54,000
CAPITAL EXPENDITURES - GROUNDS2013 Ford F-150 4x2
38
Total = $20,000
CAPITAL EXPENDITURES - COURT
Prisoner at J. Reuben Long Workstation in Surfside Beach
39
Total Equipment and Configuration = $14,000
CAPITAL EXPENDITURESPUBLIC WORKS
2012 JD Tractor 2013 Mack 10-Wheel Dump
40
$25,000 $125,000
Total = $150,000
CAPITAL EXPENDITURESNON-DEPARTMENTAL
HVAC
41
$8,000
Downstairs Carpet Town Hall
$6,500Total = $14,500
GENERAL FUNDCAPITAL EXPENDITURES
$-
$20,000
$40,000
$60,000
$80,000
$100,000
$120,000
$140,000
$160,000
$27,000 $20,000 $14,000
$125,000
$6,500
$17,000 $10,000
$25,000
$8,000
42
$54,000
$20,000 $14,000
$150,000
$14,500
GENERAL FUNDCAPITAL EXPENDITURES
Department Cost Description
Police $ 54,000 3 Vehicles
Grounds $ 20,000 Truck
Court $ 14,000 Video Equipment/Configurationfor remote bonding
Public Works $ 125,000 2013 Mack 10-Wheel Dump Truck
$ 25,000 2012 John Deere Tractor
Non-Departmental $ 8,000 HVAC
$ 6,500 Downstairs Carpeting Town Hall
Total $ 252,500 43
44
DEBT SERVICE
DEBT SERVICEGENERAL OBLIGATION BONDS
$390,000
$420,000
$450,000
Total Expenditures
FY 2010Actual
FY 2011Actual
FY 2012Actual
FY 2013Actual
45
DEBT SERVICEGENERAL OBLIGATION BONDS
ExpendituresFY 2010 Actual
FY 2011 Actual
FY 2012Actual
FY 2013 Actual
Principal General Obligation Bonds $370,000 $375,000 $400,000 $ -
Total Principal $370,000 $375,000 $400,000 $ 415,000
Interest General Obligation Bonds $ 45,875 $ 35,700 $ 24,450 $ -
Total Interest $ 45,875 $ 35,700 $ 24,450 $ 12,450
Agent Fees $ 1,310 $ 827 $ 1,080 $ 1,080
Total Expenditures $417,185 $411,527 $425,530 $ 428,530
46
DEBT SERVICE – LADDER TRUCK
$0$10,000$20,000$30,000$40,000$50,000$60,000$70,000$80,000$90,000
$100,000$7
3,14
7
$73,
147
$73,
147
$73,
147
$73,
147
$73,
147
$73,
147
$73,
147
$73,
147
$73,
147
InterestRequirements
PrincipalRequirements
47
DEBT SERVICE – LADDER TRUCK
Fiscal Year Principal Requirements Interest Requirements
2011-2012 73,147 18,689 2012-2013 73,147 16,866 2013-2014 73,147 14,951 2014-2015 73,147 13,082 2015-2016 73,147 11,213 2016-2017 73,147 9,370 2017-2018 73,147 7,476 2018-2019 73,147 5,607 2019-2020 73,147 3,738 2020-2021 73,147 1,874
Totals $ 731,469 $ 102,866
48
49
CAPITAL PROJECTS FUNDSTORM WATER
CAPITAL PROJECTS FUNDSTORM WATER
$-
$100,000
$200,000
$300,000
$400,000
$500,000
$600,000
$700,000
$800,000
$900,000
Total Storm Water Expenditures
FY 2009Actual
FY 2010Actual
FY 2011Actual
FY 2012Adopted
FY 2013Proposed
50
CAPITAL PROJECTS FUNDSTORM WATER
Capital Projects
FY 2009 Actual
FY 2010 Actual
FY 2011 Actual
FY 2012 Adopted
FY 2013 Proposed
Total Storm Water Expenditures $ 871,444 $ 274,209 $ 170,488 $ 324,000 $ 437,375
51
52
HOSPITALITY FUND
HOSPITALITY REVENUES
$-
$200,000
$400,000
$600,000
$800,000
$1,000,000
$1,200,000
Total Revenues
FY 2009Actual
FY 2010Actual
FY 2011Actual
FY 2012Adopted
FY 2013Proposed
53
HOSPITALITY REVENUES
REVENUES FY 2009 Actual
FY 2010 Actual
FY 2011 Actual
FY 2012 Adopted
FY 2013 Proposed
Hospitality Revenue $ 669,304 $ 804,000 $ 575,000 $ 600,000 $ 625,000
Parking Meter $ 124,622 $ 158,138 $ 125,000 $ 125,000 $ 125,000
Grants $ 15,919 $ 37,988 $ 45,708 $ -
Vets Memorial $ 200 $ - $ - $ -Misc. Incl./
Donations $ 25 $ 200 $ 40 $ -
Interest Earned $ 25,252 $ 5,671 $ 1,000 $ -
Sale of Fixed Asset $ 4,258 $ - $ - $ -Transfer - Parking
Tickets $ 87,007 $ 82,663 $ 93,693 $ 85,000 $ 45,000
Total Revenues $ 926,587 $ 1,088,660 $ 887,324 $ 810,000 $ 795,000
54
HOSPITALITY EXPENDITURES
$-
$500,000
$1,000,000
$1,500,000
$2,000,000
$2,500,000
$3,000,000
Total Expenditures
FY 2009Actual
FY 2010Actual
FY 2011Actual
FY 2012Adopted
FY 2013Proposed
Cost of New Firehouse≈ 2.5 Million
55
HOSPITALITY EXPENDITURES
Expenditures FY 2009 Actual
FY 2010 Actual
FY 2011 Actual
FY 2012 Adopted
FY 2013 Proposed
Parking Collection - Admin $ 25,571 $ 59,090 $ 5,405 $ 3,526 $ -
Police$ 96,922 $ 112,334 $ 112,449 $ 196,478 $ 65,409
Fire$ 193,729 $ 2,326,032 $ - $ 27,000 $ 16,380
Public Works$ - $ - $ - $ - $ 135,231
Recreation$ 37,626 $ 97,255 $ 132,759 $ 26,600 $ 23,600
Non-Departmental/GROUNDS $ 73,870 $ 116,822 $ 335,000 $ 40,000 $ 97,500 Transfers to General Fund $ - $ - $ 60,000 $ 150,000 $ 441,880
Total Expenditures$ 427,718 $ 2,711,533 $ 577,132 $ 443,604 $ 780,000
56
57
ACCOMODATIONS TAX FUND
ACCOMMODATIONS TAXREVENUES
$-
$100,000
$200,000
$300,000
$400,000
$500,000
$600,000
Total Revenues
FY 2009Actual
FY 2010Actual
FY 2011Actual
FY 2012Adopted
FY 2013Proposed
58
ACCOMMODATIONS TAXREVENUES
Revenue Sources FY 2009 Actual
FY 2010 Actual
FY 2011 Actual
FY 2012 Adopted
FY 2013 Proposed
Accommodations Revenue $525,835 $ 545,348 $ 410,000 $ 450,000 $ 450,000
Interest Earned $ 9,103 $ 75 $ - $ - $ -
Special Events/Sponsorships $ 4,109 $ 9,958 $ 20,000 $ 20,000 $ -
Other Financing Sources/Sale of F/A $ - $ 2,081 $ 25,000 $ 25,000 $ -
Total Revenues $539,047 $ 557,462 $ 455,000 $ 495,000 $ 450,000
59
ACCOMMODATIONS TAX EXPENDITURES
$0
$100,000
$200,000
$300,000
$400,000
$500,000
$600,000FY 2010Actual
FY 2011Actual
FY 2012Adopted
FY 2013Proposed
60
ACCOMMODATIONS TAX EXPENDITURES
EXPENDITURESFY 2009 Actual
FY 2010 Actual
FY 2011 Actual
FY 2012 Adopted
FY 2013 Proposed
Public Safety $ 148,424 $ 183,859 $ 87,792 $ 93,234 $ 96,221
Public Works/Sanitation $ 123,377 $ 90,563 $ 66,808 $ 107,760 $ 75,125
Recreation & Special Events
$ 39,127 $ 59,390 $ 41,934 $ 70,227 $ 72,479
Grounds Department $ - $ 15,496 $ 11,639 $ 13,876 $ 12,413
Total Departmental $ 310,928 $ 349,308 $ 208,173 $ 285,097 $ 256,238
Non Departmental $ 160,638 $ 160,002 $ 161,630 $ 152,000 $ 175,020
Transfer to General Fund
$ 50,042 $ 51,017 $ 46,218 $ 44,250 $ 46,250
Total Expenditures $ 521,608 $ 560,327 $ 416,021 $ 481,347 $ 477,508
61
62
ENTERPRISE FUNDSSANITAT ION AND P IER
SANITATION FUND
($150,000)
($100,000)
($50,000)
$0
$50,000
$100,000
$150,000
$200,000
Net Income/(Loss)
FY 2009Actual
FY 2010Actual
FY 2011Actual
FY 2012Adopted
FY 2013Proposed
63
SANITATION FUND
FY 2009 Actual
FY 2010 Actual
FY 2011 Actual
FY 2012 Adopted
FY 2013 Proposed
Total Revenue $1,149,744 $1,410,025 $1,115,513 $1,136,200 $1,094,000
Total Expenses $1,002,937 $1,244,195 $1,026,792 $1,135,679 $1,195,023
Net Income/(Loss) $146,807 $165,830 $88,721 $521 ($101,023)
64
PIER FUND
($50,000)
$0
$50,000
$100,000
$150,000
$200,000
$250,000
$300,000
FY 2009Actual
FY 2010Actual
FY 2011Actual
FY 2012Adopted
FY 2013ProposedIncome/(Loss)
65
PIER FUND
Pier FundFY 2009 Actual
FY 2010 Actual
FY 2011 Actual
FY 2012 Adopted
FY 2013 Proposed
Total Revenue $85,341 $447,800 $323,408 $280,000 $304,773
Total Expenses $107,370 $183,658 $168,956 $129,396 $135,193
Income/(Loss) ($22,029) $264,142 $154,452 $150,604 $169,580
66