NEW TOWN HEIGHTS DLF – KAKKANADWORK PROGRESS REPORT FOR THE MONTH OF MAY 2011
Click to proceed……..
![Page 2: NEW TOWN HEIGHTS DLF – KAKKANAD WORK PROGRESS REPORT FOR THE MONTH OF MAY 2011 Click to proceed……..](https://reader030.fdocuments.net/reader030/viewer/2022020219/56649c895503460f94941e55/html5/thumbnails/2.jpg)
Dear Sir,
We are glad to inform you that the construction activities are in full swing at New Town Heights DLF – Kakkanad, in all the launched towers. Please find below the Tower wise progress report.
Tower 6 / Block N• 17th floor slab shuttering work in Progress.• Block work progressing on the 10th floor.• Ceiling plastering progressing on the 5th floor.
Tower 6 / Block P • 17th to 18th floor slab column raising in progress.• Block work in progress on the 11th floor.• Ceiling plastering progressing on the 3rd floor
Tower 6 / Block Q • 18th floor slab casting in progress.• Block work in progress on the 11th floor.• Ceiling plastering progressing on the 5th floor.
Tower 5 / Block K• 16th floor slab shuttering in progress.• Block work in progress on the 6th floor.• Ceiling plastering progressing on the 9th floor.
Tower 5 / Block L • 15th floor slab casting in progress.• Block work in progress on the 7th floor.• Ceiling plastering in progress on the 9th floor.
Tower 5 / Block M • 15th floor slab shuttering in progress.• Block work in progress on the 7th floor.• Ceiling plastering progressing on the 8th floor.
![Page 3: NEW TOWN HEIGHTS DLF – KAKKANAD WORK PROGRESS REPORT FOR THE MONTH OF MAY 2011 Click to proceed……..](https://reader030.fdocuments.net/reader030/viewer/2022020219/56649c895503460f94941e55/html5/thumbnails/3.jpg)
Tower 4 / Block H•Ground to 1st floor column raising in progress.
Tower 4 / Block J• 2nd floor slab shuttering work in progress.
Tower 3 / Block G• 16th floor slab shuttering work in progress.• Block work progressing on the 3rd floor.• Ceiling Plastering in progress on the 3rd floor.
Tower 2a / Block D • 9th to 10th floor column raising in progress.• Block work in progress on the 3rd floor.• Ceiling plastering work in progress on the ground floor.
Tower 2b / Block E • 6th to 7th floor column raising in progress.• Block work in progress on the ground floor.• Ceiling plastering in progress on the 2nd level podium floor.
Tower 2b / Block F• 7th floor slab shuttering in progress.• Block work in progress on the 2nd floor.• Ceiling plastering in progress on the 1st floor.
![Page 4: NEW TOWN HEIGHTS DLF – KAKKANAD WORK PROGRESS REPORT FOR THE MONTH OF MAY 2011 Click to proceed……..](https://reader030.fdocuments.net/reader030/viewer/2022020219/56649c895503460f94941e55/html5/thumbnails/4.jpg)
Tower 1 / Block A • 16th floor slab casting completed.• Block work progressing on the 8th floor.• Ceiling Plastering in progress on the 7th floor.
Tower 1 / Block B• 18th floor slab casting completed.• Block work progressing on the 10th floor.• Ceiling plastering work in progress on the 8th floor.
Tower 1 / Block C• 12th to 13th floor column raising in progress.• Block work progressing on the 5th floor.
We are also attaching the site progress photographs along with this.
![Page 5: NEW TOWN HEIGHTS DLF – KAKKANAD WORK PROGRESS REPORT FOR THE MONTH OF MAY 2011 Click to proceed……..](https://reader030.fdocuments.net/reader030/viewer/2022020219/56649c895503460f94941e55/html5/thumbnails/5.jpg)
TOWER 6
Block work 10th floor in Progress. Ceiling Plastering 5th Floor
in Progress.
Block work 11th floor in Progress. Ceiling Plastering
3rd floor in Progress
Block work 11th floor in Progress. Ceiling Plastering
5th floor in Progress
Block –Q 18th Floor Slab Reinforcement work in Progress
Block –P 17th to 18th floor Column Raising in Progress
Block –N17th Floor Slab Shuttering in Progress
![Page 6: NEW TOWN HEIGHTS DLF – KAKKANAD WORK PROGRESS REPORT FOR THE MONTH OF MAY 2011 Click to proceed……..](https://reader030.fdocuments.net/reader030/viewer/2022020219/56649c895503460f94941e55/html5/thumbnails/6.jpg)
Tower 5Block –K, 16th floor slab Shuttering & Reinforcement work in Progress
Block –L,15th Floor slab reinforcement work is in Progress
Block work 7th floor in Progress. Ceiling
Plastering 9th floor in Progress
Block work 6th floor in Progress. Ceiling Plastering 9th floor
in Progress
Block work 7th floor in Progress. Ceiling Plastering 8th floor in
Progress
Block –M 15th Floor Slab Shuttering work in Progress
![Page 7: NEW TOWN HEIGHTS DLF – KAKKANAD WORK PROGRESS REPORT FOR THE MONTH OF MAY 2011 Click to proceed……..](https://reader030.fdocuments.net/reader030/viewer/2022020219/56649c895503460f94941e55/html5/thumbnails/7.jpg)
TOWER -4 (Block H)
Block –HGround floor to 4th floor Column Raising in Progress
![Page 8: NEW TOWN HEIGHTS DLF – KAKKANAD WORK PROGRESS REPORT FOR THE MONTH OF MAY 2011 Click to proceed……..](https://reader030.fdocuments.net/reader030/viewer/2022020219/56649c895503460f94941e55/html5/thumbnails/8.jpg)
TOWER 4-(Block J)Block –J2nd floor Slab Shuttering work in Progress
![Page 9: NEW TOWN HEIGHTS DLF – KAKKANAD WORK PROGRESS REPORT FOR THE MONTH OF MAY 2011 Click to proceed……..](https://reader030.fdocuments.net/reader030/viewer/2022020219/56649c895503460f94941e55/html5/thumbnails/9.jpg)
TOWER-3 (Block G)
Block work 3rd floor is in Progress & Ceiling Plastering 3rd Floor in Progress
Block G16th floor slab shuttering work in Progress
![Page 10: NEW TOWN HEIGHTS DLF – KAKKANAD WORK PROGRESS REPORT FOR THE MONTH OF MAY 2011 Click to proceed……..](https://reader030.fdocuments.net/reader030/viewer/2022020219/56649c895503460f94941e55/html5/thumbnails/10.jpg)
Tower -2a(Block D)
Block work 3rd floor is in Progress & Ceiling Plastering Ground Floor in Progress
Block –D9th to 10th floor Column Raising in Progress
![Page 11: NEW TOWN HEIGHTS DLF – KAKKANAD WORK PROGRESS REPORT FOR THE MONTH OF MAY 2011 Click to proceed……..](https://reader030.fdocuments.net/reader030/viewer/2022020219/56649c895503460f94941e55/html5/thumbnails/11.jpg)
Tower -2b(Block E)Block –E6th to 7th floor Column Raising in Progress.
Block work Ground floor is in Progress & Ceiling Plastering 2nd level podium Floor in Progress
![Page 12: NEW TOWN HEIGHTS DLF – KAKKANAD WORK PROGRESS REPORT FOR THE MONTH OF MAY 2011 Click to proceed……..](https://reader030.fdocuments.net/reader030/viewer/2022020219/56649c895503460f94941e55/html5/thumbnails/12.jpg)
Tower -2b(Block F)Block –F7th Floor Slab Shuttering work in Progress
Block work 2nd floor is in Progress & Ceiling Plastering 1st Floor in Progress
![Page 13: NEW TOWN HEIGHTS DLF – KAKKANAD WORK PROGRESS REPORT FOR THE MONTH OF MAY 2011 Click to proceed……..](https://reader030.fdocuments.net/reader030/viewer/2022020219/56649c895503460f94941e55/html5/thumbnails/13.jpg)
TOWER 1Block –C12th to 13th Floor column raising in progress
Block –B18th Floor Slab casting completed.
Block –A16th floor slab casting completed
Block work 8th floor in Progress. Ceiling
Plastering 7th Floor In Progress
Block work 10th floor in Progress. Ceiling Plastering
8th Floor In Progress
Block work 5th Floor in
Progress
![Page 14: NEW TOWN HEIGHTS DLF – KAKKANAD WORK PROGRESS REPORT FOR THE MONTH OF MAY 2011 Click to proceed……..](https://reader030.fdocuments.net/reader030/viewer/2022020219/56649c895503460f94941e55/html5/thumbnails/14.jpg)
Block –Q 1st level podium Slab Completed
Block –E & FPodium Pile cap work completed & column raising is in Progress
![Page 15: NEW TOWN HEIGHTS DLF – KAKKANAD WORK PROGRESS REPORT FOR THE MONTH OF MAY 2011 Click to proceed……..](https://reader030.fdocuments.net/reader030/viewer/2022020219/56649c895503460f94941e55/html5/thumbnails/15.jpg)
MARKETING OFFICE -MODEL FLAT
Signature Tower Model Flat Partition Wall & False Ceiling Work in Progress
Tower 2 Model Flat Partition Wall & False ceiling Work in Progress