New MRI Facility, Extension & Refurbishment to Tullamore Mid Regional Hospital
The Midland Regional Hospital in Tullamore is a modern live acute hospital campus. After a suc-
cessful prequalifying and tender process we were selected as the preferred tenderer for the pro-
ject based on both our experience and also commercial offering. The project consisted of a new
MRI scanner, control room, Tech room, plant room, coms room, five bay recovery area, Anaes-
thetic prep area, three ultrasound rooms, consultants offices, waiting areas, changing areas and
reception area.
The MRI & Ultrasound Department is attached to the side of the existing X-Ray & CT department
and below the operating theatres. The project consisted of five different tie in points and also
remodelling of the existing hospital corridors. All M&E services also had to be tied into the exist-
ing hospital services. The chilled water had to be brought from the existing roof plant room to the
MRI plant room in order to serve the new MRI scanner. Significant existing services had to be
diverted prior to any construction works commencing on site. All hospital interfaces were agreed
thought a strict method statement procedure. A method statement tracker was issued at each
progress meeting to track the status of submitted method statement and also one that were
pending.
Once the diversions of the existing services and the aspergillus prevention measures were com-
pleted the construction works could commence. The frame consisted of concrete pad founda-
tions, foundation columns, rising walls, ground bearing slab (Strengthened under the MRI scan-
ner), concrete columns, beams, roof slab and screed. The entire building frame was designed to
allow for vertical expansion of three more floors.
Key Data: Value: €2,368,000 Building Type: Acute Healthcare Programme Duration: 11 Months Contracting Authority
HSE
Page 2 ELLIOTTGROUP ©
HE
AL
TH
CA
RE
New MRI Facility, Extension & Refurbishment to Tullamore Mid Regional Hospital
The external facades consisted of self coloured rendered block work, Zinc wall panelling, Aluminium windows and
Louvred walls. Access panels were incorporated into the louvered wall which would make it easy for future MRI
replacement. This louvered wall also allows for Air circulation into the plant rooms and tech room. The roof consist-
ed of mastic asphalt, roof lights and aluminium capping's. A small amount of plant was placed on the roof and an
exclusion zone was formed around the quench pipe from the MRI unit.
We appointed Imedco to supply and installed the RF cage and internal walls panelling within the scanner room. GE
Supplied and installed the MRI scanner. We arranged numerous coordination meeting with all parties to ensure that
the RF cage and the scanner was coordinated and installed in strict accordance with the manufacturers instruc-
tions. The scanner was brought in when the project was 75% completed. A panel of RF cage and wall panelling
was left off in order to accommodate the scanner deliver. Once the scanner was in a protected we completed the
RF cage and wall panelling. The scan room, tech room and control room were handed over to GE once we had the
RF
Internal finishes consisted of a mix of 30min and 60min fire rated walls. Prior to walls and ceilings being closed we
carried out a wall/ceiling closure hold point, where all installations and tests were formally recorded and witnessed
by all stakeholders. These construction check sheets formed part of the O&M Manual. We also recorded all fire
proofing using a special app which generated an id number, photo and location on a drawing of all fire proofing
carried out on the project. All fire dampers where also recorded and a sample was signed off by safeguard prior to
bulk installation of same. Once M&E was 1st fixed the wall closures commenced and the design team was given
notice in order to inspect same. Walls where then closed and skimmed. All walls received full height timber grounds
in order to future proof for any fixing of fixtures and fittings. Once the walls were skimmed we gave all of the walls
their 1st coat of decoration. We also commenced with the 1st fix of joinery and fixtures and fittings. Focus also
turned on the M&E to get out of the ceilings so that we could install the grid and the radiant panels. The SAS metal
ceiling grid system incorporated radiant panels, barasol lighting, and LED lighting. Once the 1st Fix was completed
Page 3 ELLIOTTGROUP ©
HE
AL
TH
CA
RE
New MRI Facility, Extension & Refurbishment to Tullamore Mid Regional Hospital
Site Location: Mid Regional Hospital Tullamore Proportion of Project Undertaken: All
Scale: 10,000 Sqft
Procurement: Public Government Form Status: Completed Tender entity: Elliott Building & Civil Engineering
Start Date: May 2016 End Date: April 2017 Handover Date: April 2017
Date of Defects Cert: April 2018
Role of Company in delivery of Project:
PSCS & Main Contractor
Name & Address of Contracting Authority
HSE Midlands
Architect: MRL & Van Dijk
Civil Engineer: Hayes Higgins
M&E Engineer: FLN
Quantity Surveyor: O’Reilly Hyland Tierney Contracting Authority Contact Name
Anne Daly
Phone Number
On Request
on the joinery we commenced with the DPM and floor levelling compound to the vinyl flooring. This allowed us to
dress up the skirting under the IPS and furniture. Once the following was completed it was protected immediately.
The M&E in the ceilings was then completed and ceiling tiles were laid in. Around the same time the 2nd fix joinery
was occurring along with 2nd coat decoration. All wall protection was then completed. The final fix of all trades was
then completed and the automatic doors & screens.
Once the works were completed we commenced the commissioning of all systems. All certificates were complied
and put into the O&M. All BCAR information was also complied and ready prior to substantial completion. Once the
systems had been verified we requested the Design Team to inspect same and the certs. Demonstrations were
then arranged for the Maintenance and End user teams.
This project consisted of all of the issues associated with working on a live acute medical campus. Our Team and
company management systems ensured that the project was delivered on time and achieved all BCAR require-
ments.