Momentum and Thermal Slip Flow of MHD Casson Fluid over a Stretching Sheet with Viscous Dissipation
New markets for solar thermal power gain some momentum
Transcript of New markets for solar thermal power gain some momentum
34 July/August 2013 | Renewable Energy Focus
New markets for solar thermal power gain some momentum
THE SOLAR thermal power market
continued its expansion in 2012. Altogether,
712MW of additional power capacity was
connected to the grid, a substantial increase
in comparison to 2011’s 440MW. Cumulative
installed capacity by the end of 2012 grew to 2.42GW.
Once again, almost all of the newly
commissioned power capacity was in
Spain (700MW), taking the coun-
try’s cumulative capacity to 1803MW,
mainly distributed in Andalucia and
Extremadura. The Spanish market
remained driven by the feed-in tariff
regulation published in May 2007 (RD
661/2007) North America’s contribu-
tion was just 7MW in 2012, but there
are several hundred megawatts under
construction so the contribution of
the US market will be much higher in
2013.
Due to its bankability, the most
popular Concentrating Solar Power
(CSP) technology remains para-
bolic trough, with approximately 93%
market share of the power capacity
installed. By 2015 this value is expected
to decrease to 70%, with power tower
plants gaining share in the CSP mar-
ket thanks to the capability to reach
higher process temperatures. By end
2012 just 61.5MW of tower power
plants were installed, but 630MW are
under construction with scheduled
commissioning dates in 2013 and 2014.
While Fresnel technology remains
the least-implemented form of
CSP, 2012 was a great year for it. A
remarkable project was commissioned,
the Puerto Errado 2 (PE2), a 30MW
solar thermal power station built by
Novatec Solar using its proprietary
solar fi eld technology. It is the largest
CSP plant using Fresnel Technology
Worldwide so far.
Cost pressuresPressure on the CSP market per-
sists, especially from cost competitive
PV installations. An indicator for this
competition is the change of technol-
ogy in initially assigned CSP projects
that turned into PV projects. Such
projects include:
the Blythe project which changed •
from parabolic trough to PV
technology;
the Imperial Valley and Calico •
projects were changed from dish-
stirling to PV.
The change from CSP to PV tech-
nology should be seen in both the
market situation and the particular
context of these projects (eg the failed
business strategy and sunsequent
insolvency of Solar Millennium and
the failed up-scaling of the Tessera
dish technology respectively). Other
key events of the year include:
Siemens• announced it is pulling out
of the solar business in 2012. It is
now seeking for a buyer of the CSP
branch formerly known as Solel.Flagsol was a joint venture formed •
in 2007 between Solar Millennium
and Ferrostaal to design and build
solar-thermal plants; it developed
four power projects in Spain and
one in Egypt. Once Solar Millen-
nium stated its insolvency it sold its
Flagsol stake to Ferrostaal, which
is also now expected to offl oad
Flagsol, due to business strategy
changes within the company.
Flabeg• was another CSP fi rm that
fi led for bankruptcy. The German
company (which manufactured mir-
rors for CSP projects) was actually
based in Pennsylvania and received
millions of dollars in fi nancial assis-
tance from federal and state gov-
ernments for the Genesis Solar
Energy Project and the Crescent
Dunes Solar Energy Project. It is
searching now new owners as well.
Positive newsThe news for 2012 was not all bad
however. Other big players made great
steps forward though. For example,
ACWA Power from Saudi Arabia is in
a good position to move forward in the
MENA region, while Spanish compa-
nies, Abengoa, Acciona, and Sener, are
still in good standing.
2012 was also a record year for
installed capacity, while the pro-
cess of market diversifi cation contin-
ues. New markets such as Morocco,
India, South Africa and China gained
momentum and old markets like
Spain and the US stayed in place.
However, as CSP projects move in
4-5 year timeframes, the installa-
tion fi gures reached are the result of
the market conditions we saw in the
past. In this context it is highly pre-
dictable that the market in Spain will
reach a sudden stop and the market
in the USA will face new challenges
due to changing political and fi nancial
Focus on renewable power generation
Cumulated installed
capacity 2012(GW)
Installed capacity 2012
(GW)
Estimated electricity
generation 2012*(TWh/y)
Europe 1.81 0.70 3.6
North America 0.52 0.01 1.0
World Total 2.42 0.71 4.6
Largest national Market Spain: 1.81 Spain: 0.70
Table 5: Summary of the global solar thermal power market 2012
REF0413_Solar Thermal 34 30-07-2013 12:24:17
35July/August 2013 | Renewable Energy Focus
support schemes. The key highlights
for the CSP market are:
Thanks to the Moroccan Solar •
Plan with the proposed 500MW
Ouazarzate Solar Complex, Morocco
represents a very promising coun-
try in North Africa. In September
2012 the Saudi developer ACWA
won the contract for Ouazarzate
Phase 1 to build and operate the
fi rst 160MW parabolic trough CSP
plant with 3h storage. The tar-
iff delivered by the consortium led
by ACWA Power was €0.145/kWh,
28.8% lower than the one off ered by
the second nearest bidder.
The Tunisian Solar Plan consists •
of all kinds of projects from renew-
able energy sources. Currently
there is no CSP plant in the coun-
try under construction or in oper-
ation. However several projects are
under development. STEG is devel-
oping a 50MW plant at Akarit,
SITEP is developing a tower plant
at El Borma and TuNur is develop-
ing 2GW at Rjim Maatoug, certifi ed
by the Desertec Foundation. The
Desertec Industrial Intitiative (Dii)
developed further smaller reference
projects in Tunesia, but also larger
ones in Morocco and Algeria. The
most advanced of those are the ref-
erence projects in Morocco, however
all of these projects still have a long
way to go until implementation.
In Egypt, so far only one CSP plant •
is in operation, the ISCC Kuraymat
Solar Thermal Power Plant (140
MW, with 20 MW solar power). A
pure CSP plant is also under devel-
opment: the CSP Kom Ombo Proj-
ect (100 MW).
Jordan’s parliament is intend-•
ing to move to renewable energies
through a system of feed-in-tariff s
(FiTs) introduced by Jordan’s Elec-
tricity Regulatory Commissions in
April 2012 for PV and CSP, ending
when the installed capacity reaches
500MW. The prices for CSP are
fi xed at US$0.183/kWh.
China is a potential market for •
CSP – it hopes to develop its own
technology. Research facilities are
in place, such as the 1MW Yan-
qing Solar Thermal Power Sta-
tion (commissioned in 2010) or
the 1.5MW Beijing Badaling Solar
Tower, which was commissioned in
August 2012. Furthermore there
are some projects under con-
struction, such as the 50MW Del-
ingha Solar Tower Power Plant, the
100MW Golmud 100MW Parabolic
Trough Plant, the 50MW Erdos
Parabolic Trough Solar Power
Plant and the 92MW Ningxia ISCC
Plant.
The US is forecast for an 120% •
increase in its installed capac-
ity between 2013 and 2014 and
close in on Spain. In 2012 the US
had 572MW installed and fi ve
CSP plants were under construc-
tion with a combined capacity of
1319 MW. These include Solana
(280MW) with six hours of storage
and Mojave Solar Project (280MW)
located in Arizona and Califor-
nia, respectively; both promoted
by Abengoa and using parabolic
trough technology. Ivanpah is the
largest plant under construction.
At with 370MW, it is being devel-
oped by BrightSource Energy in
California, employing superheated
steam tower technology. Solar Reserve is constructing the Cres-
cent Dunes Solar Energy 110MW
molten salt tower project with ten
hours of molten salt storage.
Saudi Arabia announced a mas-•
sive construction of solar proj-
ects through King Abdullah City for Atomic and Renewable Energy (KACARE): 41GW of installed
capacity by 2032, of this 16GW of PV
and 25GW of solar thermal power.
Also on the Arabian Peninsu-•
lar, in the UAE, the three phase
Shams solar power station, located
approximately 120 kilometers
southwest of Abu Dhabi City, is
a CSP plant of note. Construc-
tion on the 100MW Shams 1 was
completed at the end of 2012, with
commissioning taking place ear-
lier this year. Shams 1 is the largest
plant in the world using parabolic
trough technology to date.
South Africa entered the solar •
thermal market in 2012 with the
construction of two plants. Both
scheduled to be fi nished in 2014,
they are Kaxu Solar One (100MW
parabolic trough with three
hour storage) and Khi Solar One
(50MW solar power tower with
two hours thermal storage). They
will be located in Northern Cape
Province near Upington and Pofad-
der, respectively. Abengoa won
the PPAs in the fi rst round of the
REFIT programme and will con-
struct, operate and maintain both
plants, owning the 51% major-
ity share; IDC holds 29% and the
Black Economic Empowerment
programme maintains the remain-
ing 20%. In the second round of
government tenders a PPA was
awarded for the Bokpoort plant
(50MW parabolic trough) to be
developed by Saudi’s ACWA.
Focus on renewable power generation
The 100MW Shams 1 CSP plant in the Western Region of Abu Dhabi was offi cially opened earlier this year. (Courtesy of Ryan Carter/Crown Prince Court – Abu Dhabi).
REF0413_Solar Thermal 35 30-07-2013 12:24:17
36 July/August 2013 | Renewable Energy Focus
Focus on renewable power generation
An initiative taken by the Govern-•
ment of India, Jawaharlal Nehru
National Solar Mission, was born
with the aim of helping solar
energy take off in this country. In
its second phase the purpose is to
achieve 10GW connected to the
network by 2017. The fi rst proj-
ects, with 50MW capacity in Raj-
asthan and Gujarat, are now under
construction.
Spanish setbackAlthough in 2012 the majority of
CSP plants in the world were con-
nected to the grid in Spain, the Span-
ish government is applying some
regulatory changes that will certainly
cut revenues for plant operators, espe-
cially when those using gas as an addi-
tional source for power generation.
The measures comprise a 7% tax to
the income of CSP plants, a new ref-
erence index to update FiTs annually
and the withdrawal of the pool + pre-
mium option whilst more cuts are to
be applied. Nevertheless, in total, there
are 2527MW under construction that
will be fi nished between 2013 and 2014.
One of the innovative projects in
2012 was the launch of the fi rst com-
mercial hybrid plant that combines
solar and biomass energy. The €153mn
Borges Solar Thermal plant, located
in Catalonia, has a power capac-
ity of 22.5MW. It was constructed in
20 months. The partners of the proj-
ect were Abantia and COMSA EMTE.
Another outstanding project was the
start of commercial operation of Puerto
Errado 2 (PE2), the largest CSP plant
using Fresnel Technology with 30MW
of power capacity. The plant was con-
structed by Novatec Solar.
In Thailand, German company
Solarlite constructed and commis-
sioned a 5MW direct steam power
plant together with the company Thai Solar Energy. The project was devel-
oped by Siasol and is eligible to the
offi cial FiT. It is a landmark in the
technological development of CSP
plants because it is the fi rst commer-
cial direct steam facility based on
parabolic trough technology.
Room for improvementThe CSP market needs to realise
signifi cant cost reductions for utility-
scale plants in order to make them
profi table and allow its deployment
in a time of low price PV modules.
With PV technology much less expen-
sive than CSP, the key selling argu-
ment for CSP remains energy storage.
Although PV plants can also store
electrical energy in batteries, this
option is disadvantageous due to high
prices and short lifetimes. The further
development of storage systems for
CSP plants is vitalthen for a perma-
nent larger share of solar technology
in the market of electricity genera-
tion. Furthermore CSP can be directly
integrated to thermal processes in the
oil, gas and chemical industry.
The key areas where CSP cost
reductions need to be achieved gen-
erally are in the solar fi eld, the heat
transfer fl uid, the storage system, the
power block and the balance of costs.
In order to reduce the production
costs of the electricity, the Thermal
Energy Storage (TES) systems need
constant improvement. The Ther-
mochemical Energy Storage has the
advantage, in comparison with the
latent and sensible systems, to store
the energy with high density and is
the most promising system under
development. Research of this kind of
storage is focused on improvements
of the chemical reaction and dealing
with storage materials issues.
Regarding the storage system new
improvements on the molten salts
were made. Norwegian company Yara International identifi ed the potassium
calcium nitrate as a promising stor-
age material. The advantages of it are
lower melting point at 91ºC and lower
grade of corrosion than the conven-
tional molten salts used in CSP appli-
cations (see page 38, Renewable Energy
Focus, January/February 2013).
Another component which plays a
key role to reduce the global cost of
the CSP plants is the mirror material.
The goal is to achieve better refl ec-
tivity and also better market prices.
SCHOTT Solar designed a receiver
with a new coating which increases
the degree of absorption to over 95.5
% and the thermal radiation has been
reduced to less than 9.5%.
Thermal applicationsApart from electricity generation,
CSP technology has a great and
nearly untapped application potential
in thermal processes, such as the min-
ing industry, cooling and the enhanced
oil recovery (EOR). The mining
industry is one of the largest energy
consumers in Chile, for example, and
presents a great market potential
for CSP covering part of the energy
demand (more than 55% of the diesel
fuel consumption) in the extraction
and production processes. The copper
production is estimated to increase
7mn tons in 2020, thus 32.7GWh
demand is expected by 2020 in com-
parison with 18.8GWh in 2009. A fi rst
installation has already been realised
by Abengoa with a 14MW solar ther-
mal plant with thermal energy stor-
age for Minera El Tesoro.
In Qatar, where air condition
use is very high, Fresnel solar ther-
mal receivers were installed at a soc-
cer stadium to produce cool air by
thermally driven absorption chillers.
Meantime, there are currently two
facilities commissioned in 2011 using
CSP for EOR, Chevron’s Coalinga (29
MWth) developed by BrightSource
with pressurised steam solar power
tower technology and Berry Petro-leum EOR plant (7 MWth) developed
by GlassPoint. The latter oil giant
Royal Dutch Shell as well as Rock-Port Capital, Nth Power, and Chrysa-lix Energy Venture Capital.
ResearchSeveral new CSP technology
research facilities were commis-
sioned in 2012. A Molten Salt Loop
Test facility was installed at the San-dia National Laboratories in Albu-
querque, New Mexico, for example.
The facility allows improvements in
the effi ciency and higher-tempera-
tures operation for linear Fresnel and
trough systems through utilisation of
molten salt Heat Transfer Fluid.
Another new research facility was
built in Almeria (Spain) by Advanced Technology Center for Renewables Energies. The objective here is to
study how a variable geometry central
receiver works and how it improves
the system effi ciency keeping the
cosine of the angle of incidence as
close to 1 as possible during the day
changing the position.
REF0413_Solar Thermal 36 30-07-2013 12:24:18