NEW INTERNATIONAL TECHNOLOGY COMPANY - … · new international technology company w.l.l. ... major...
Transcript of NEW INTERNATIONAL TECHNOLOGY COMPANY - … · new international technology company w.l.l. ... major...
Operation and Maintenance
Waste Management Services
Technical Assistance
Industrial Cleaning Services
Landscaping & Irrigation
Spare Parts Management
NEW INTERNATIONAL TECHNOLOGY COMPANY W.L.L.
ISO 9001;2015 QUALITY MANAGEMENT SYSTEM
ISO 14001:2015 ENVIRONMENTAL MANAGEMENT SYSTEM
BS OHSAS 18001:2007 OCCUPATIONAL HEALTH & SAFETY MANAGEMENT SYSTEM
2
New International Technology Company W.L.L. (NITCO) PO Box: 22498, Doha – State of Qatar
E mail: [email protected]
Main Office
Office No. 209, 2nd Floor, Al Mana Plaza
Building 56, Street 850, Zone 23 Qatari Bin Al Fujaah Street
Doha, Qatar
Telephone +974 4437 6130 / 4437 6131
Fax +974 4437 6129
Partners: Al Jabor Group Holdings
P.O Box 24024 DOHA QATAR
Tel. +974 44445501
Fax +974 44449411
E-mail: [email protected]
Europower S.p.A
Piazza F.Buffoni, 3
21013 Gallarate (VA) Italy
Tel. ++39 0331 71621
Fax ++39 0331 770786
Email: [email protected]
Date of Registration in Qatar: August 12, 1999
Commercial Registration No.: 8299
Qatar Chamber of Commerce Registration No.: 01/00700
Municipal License: 26219
General Information / 1
3
Bankers in Qatar: The Commercial Bank of Qatar
Main Corporate Branch
PO Box 3232 DOHA
Tel. +974 4449 0000
Fax +974 4449 0070
Al Ahli Bank
Al Mansoura Branch
PO Box 2309 DOHA
Tel. +974 44439144
Fax +974 44444652
Arab Bank
Main Branch
PO Box 172 DOHA
Tel. +974 44387777
Fax +974 4487677
Auditors in Qatar: Hussain Al-Obaidly & Partner
Accounting and Auditing PO Box 9866 DOHA
Tel. +974 44416333 / 44416816
Fax +974 44416334
Insurance Company in Qatar: Qatar Insurance Company
PO Box 666 DOHA
Tel. +974 44490468
Fax +974 44831569
Libano Suisse Insurance Co.
PO Box 441 DOHA
Tel. +974 44664406
Fax +974 44664409
AIG MEA Ltd (QFC Branch)
PO Box 23043 DOHA
Tel. +974 44967428
Fax +974 44967411
Contact in Qatar: Michele POLAME
Executive Director
Tel. +974 44376130-1
Fax +974 44376129
E-mail: [email protected]
General Information / 2
4
EUROPOWER S.p.A is part of , a protagonist in the international energy
market, providing plants and parts for the production of steam for industrial use and of power,
for waste and water treatment, operating worldwide also through owned reputed Companies
such as ANSALDO CALDAIE S.p.A. and its own division MACCHI.
Profile
ITALY – QATAR - GCC
EUROPOWER S.p.A., founded in
1979, formerly Commissioning Italia
S.p.A. until 2006, is a company active in
engineering and global services, designs
and supplies turn-key plants and
systems, technical assistance and global
services for plants producing electricity
and thermal energy, waste to energy
plants, water treatment and renewable
energy plants.
EUROPOWER operates through it’s
EPC division dedicated to design and
supply of “turn-key” plants”, Operation
and Maintenance division, dedicated to supply start-up, operation and
maintenance of plants and Technical
Assistance division, dedicated to Pre-Commissioning, Commissioning and
Personnel training. The company is
also active in the field of gasification
technology.
NITCO is active in the Middle East as
Global Environmental Service
Company involved in the waste water
treatment & desalination,
environmental services and technical
consultancy, utilizing dedicated
Companies based in UAE and QATAR.
NITCO Group Headquarters in Genova (Italy)
5
SWS
Saline Water Specialist (SWS) is specialized in plants for industrial water treatment solutions and
seawater desalination. SWS designs and supply, with its proprietary know-how, custom designed package
units for the primary water treatment and the production of pure water for industrial use. SWA is a division
of Sofinter S.p.a
EUROPOWER S.p.A
Europower is a leader in engineering, construction, start- up, operation and maintenance of industrial plants
producing electricity and thermal energy, waste to energy plants, biomass plants, water treatment and
industrial utilities.
AC BOILERS S.p.A
With over 150 years’ experience in Steam Generation and Burner Technology and a track record of 1000
units exceeding 80,000 MW installed worldwide, AC BOILERS SpA, formerly Ansaldo Cadaie, is the largest
Italian original technology Boiler Manufacturer, providing the full range of Steam Generator Technologies.
MACCHI S.p.A
A Division of Sofinter, MACCHI is highly experienced and active in the supply of industrial and heat recovery
boilers for Oil & Gas and Petrochemical sectors.
ITEA S.p.A
ITEA is providing high technology energy- recovery solutions. As part of Sofinter Group, ITEA spa is dedicated
to the development and business of plants based in ISOTHERM Pwer ®” Flameless” Oxy Combustion
Technology.
The Group
The experience and knowhow of the above,
constantly contributes to the reinforcement and
updating of the Technical Knowledge of all the
Group.
6
NITCO in Qatar
In QATAR, NITCO is operating through New International Technology Company
(NEWINT) having permanent specialized manpower (approx 200 people) and
equipment in the sectors of:
Operation and Maintenance of sewerage systems (sewage treatment plants, networks, pumping stations and auxiliary equipment);
Solid waste (domestic and industrial) collection, transportation and
disposal, community road sweeping;
Landfills construction and management;
Environmental services, such as waste water collection and disposal;
Electro-mechanical refurbishment of industrial plants;
Landscaping activities, from design to global maintenance of green
areas, nurseries and greenhouses, public parks, sports facilities.
Techical Assistance worldwide in the industrial sector (power and steel making)
SINCE 1997
10
Advantages of GPS Tracking System
Use GPS data as a time clock feature to capture job site arrive/leave times.
Reduce unnecessary stress on dispatch personnel with real-time commercial fleet tracking
information.
Improve vehicle utilization by eliminating unnecessary idle time and operating misuse.
Increase productivity and efficiency by eliminating wait/down time, dispatch inaccuracies and
tardiness.
Capitalize on accurate fleet and asset data for profit/loss analysis, accountability and budget
preparation.
Develop strategic transportation planning schedules along with advanced vehicle maintenance
routines.
GPS VEHICLE TRACKING SYSTEM
NITCO has implemented a vehicle GPS Tracking System to manage the vehicle fleet of
the company with ADVANCE TECHNOLOGIES AND SOLUTION – QATAR
11
Provide safety and security to personnel with direct assistance and support.
Major Projects in Qatar
12
Major Projects in Qatar
TECHNICAL ASSISTANCE IN DAILY OPERATION AND MAINTENANCE
SERVICES AT DOHA NORTH SEWAGE TREATMENT WORKS, QATAR
Contract No. : 0230003_P_03_001_001
Client:
KEPPEL SEGHERS
Services:
TA IN Operation and
Maintenance
Period:
2012 – 2022
(10 YEARS)
The landmark project is the largest Greenfield wastewater treatment, water
reuse and sludge treatment plant in Qatar
With a peak design capacity to treat wastewater of up to 439,000m3 per
day, the Doha North Sewage Treatment Works will serve a projected
population of over 900,000 when completed.
As a Design-Build-Operate project, Keppel Seghers will design and build
Doha North Sewage Treatment Works and subsequently operate it for a
period of 10 years.
This modern facility will feature advanced biological treatment processes as
well as membrane and ultra-violet technologies to produce high quality
reclaimed water for reuse in agriculture. The facility will also be equipped
with thermal drying processes to treat wastewater sludge. The dried and
pelletised sludge will be used as soil conditioners or refuse-derived fuel.
Services carried out by NITCO:
Technical assistance in DAILY
complete operation and maintenance
of the plant.
13
Services include:
Provision and Coordination of specialized team to carry out O&M
Services
Routine and Preventive Maintenance
(STP and collecting system, pumping
stations) and daily Operation
Carry out Operation & Maintenance
of irrigation pumping stations
Overhauling of equipment
Carry out of non-routine and
emergency services
Carry out of sewage analysis
Collection, transportation and
disposal of wastewater from
different locations
Electromechanical refurbishment
Major Projects in Qatar
OPERATION AND MAINTENANCE OF SEWERAGE SYSTEM AND
TREATMENT FACILITIES AT MESAIEED INDUSTRIAL CITY
Contract GC16107200
Client:
QATAR
PETROLEUM
Services:
Operation and
Maintenance
Period:
2017 - 2022
Operation and Maintenance of 16 nos. pumping stations, 83.5 km
of sewerage network and 1298 manholes, 18 km of rising mains,
sewage treatment plant and treated sewage effluent (TSE) network
(103 km, 108 nos. valve chambers, 266 nos. distribution chamber,
APPROX. 600 nos. valves) at Mesaieed (pop. 60,000)
Sewage Treatment Plant (STP) treats the wastewater by an aerobic
biological oxidation process; dry weather flow: 11,000 m3/day.
14
Major Projects in Qatar
OPERATION AND MAINTENANCE OF SEWERAGE SYSTEM AND
TREATMENT FACILITIES AT MESAIEED INDUSTRIAL CITY
Existing DWTP and New DWTP Contract GC11111200
Client:
QATAR
PETROLEUM
Services:
Operation and
Maintenance
Period:
2012 – 2017
Operation and Maintenance of 18 nos. pumping stations, 103.20 km
of sewerage network (size/type 150-500mm AC/VC, size/type – 150-
650 (HDPE) and 1483 manholes), 18 km of rising mains (size/type
100-300 mm AC/DI, 500 mm (HDPE)), sewage treatment plant and
treated sewage effluent (TSE) network (130 km, 108 nos. valve
chambers, 366 nos. distribution chamber, 551 nos valves) at
Mesaieed (pop. 50,000)
Sewage Treatment Plant (STP) treats the wastewater by an aerobic
biological oxidation process; dry weather flow: 10,000 m3/day.
The plant includes nos. 04 aeration tanks, 04 nos.
settlement tanks, 03 nos. screw pumps, sludge
drying beds and tertiary treatment plant (sand
filter system), chlorination system; a pre-aeration
tank of 400 m3 is operating, collecting raw sewage
(coming by tankers) from locations not connected
to sewage network.
The final effluent pumping station at STP pumps
the TSE to an elevated tower of 2,000 m3; TSE is
used for irrigation.
Services carried out by NITCO include:
Provision and Coordination of
specialized team to carry out O&M
Services
Routine and Preventive Maintenance (STP and collecting system, pumping
stations) and daily Operation
Overhauling of equipment
Carry out of non-routine and
emergency services
Carry out of sewage analysis
Collection, transportation and disposal
of wastewater from different locations
Electromechanical refurbishment
15
Major Projects in Qatar
OPERATION AND MAINTENANCE OF SEWERAGE SYSTEM AND
TREATMENT FACILITIES AT MESAIEED INDUSTRIAL CITY
Contract GTC 05 107 MIC (New Extended Contract)
Client:
QATAR
PETROLEUM
Services:
Operation and
Maintenance
Period:
1998 – 2012
Operation and Maintenance of 14 nos. pumping stations, 36 km of
sewerage network (size/type 150-500mm AC/VC and 710
manholes), 12 km of rising mains (size/type 100-300 mm AC/DI),
sewage treatment plant and treated sewage effluent (TSE) network
(45 km, 41 nos. valve chambers, 132 nos. distribution chamber, 513
nos valves) at Mesaieed (pop. 20,000)
Sewage Treatment Plant (STP) treats the wastewater by an aerobic
biological oxidation process; dry weather flow: 4,361 m3/day.
The plant includes nos. 02 aeration tanks, 02 nos.
settlement tanks, 03 nos. screw pumps, sludge
drying beds and tertiary treatment plant (sand
filter system), chlorination system; a pre-aeration
tank of 400 m3 is operating, collecting raw sewage
(coming by tankers) from locations not connected
to sewage network.
The final effluent pumping station at STP pumps
the TSE to an elevated tower of 2,000 m3; TSE is
used for irrigation.
Services carried out by NITCO include:
Provision and Coordination of
specialized team to carry out O&M Services
Routine and Preventive
Maintenance (STP and collecting
system, pumping stations) and daily
Operation
Overhauling of equipments
Carry out of non-routine and emergency services
Carry out of sewage analysis
Collection, transportation and
disposal of wastewater from
different locations
Electromechanical refurbishment
16
Major Projects in Qatar
GARBAGE COLLECTION AND ROAD SWEEPING AT
MESAIEED INDUSTRIAL CITY
Contract GTC 05 136 MIC (Extended Contract)
Client:
QATAR
PETROLEUM
Services:
Solid waste
management
Period:
2005 –2011
Collection and disposal of all refuse and garbage together with road
sweeping within Mesaieed Industrial City (pop. 20,000), including
Mesaieed Industrial Area and Mesaieed Community Area.
Contract includes the construction of 02 nos. Landfill Areas,
Mesaieed New Sanitary Landfill and Mesaieed Non-hazardous
Industrial Landfill and relevant access road.
Activities are executed daily to guarantee the
continuous cleaning of roads, community and
service areas, walk ways.
Road sweepers and tractor brushes are deployed
along with a complete range of supporting vehicles.
Collection of garbage usually disposed in plastic bins
is executed by Rear End Loading vehicles of
different capacity ; steel skips are operated by Skip
Loaders.
The Landfills are daily managed by means of
Bulldozers and Shovels (Wheel Loaders)
Services carried out by NITCO include:
Daily garbage collection and disposal
by dedicated equipment, cleaning and
maintenance of approx 1500 garbage
containers;
Sweeping of all roads, main street and
other major areas including sidewalks
and gabbro areas;
Operation and maintenance of the
above Landfills; access and disposal
management, garbage sorting,
arrangement of the garbage levels in
site, safety and general monitoring of
the disposal, administrative
management
Supply and install of garbage
containers
17
Major Projects in Qatar
OPERATION ASSISTANCE AND MAINTENANCE OF SEWAGE
TREATMENT SYSTEM IN DUKHAN FIELDS
Contract GTC 05 211 FSD
Client:
QATAR
PETROLEUM
Services:
Operation and
Maintenance
Period:
2005 – 2008
Operation and Maintenance of Sewage Treatment Plant (STP), 03
nos. pumping stations, 14,5 km of sewerage network (size/type 200-
400mm VC, 85 nos. manholes, 98 nos. inspection chambers), 06 km
of rising mains (size/type 200 mm VC/DI), Sewage Treatment plant
at Dukhan (pop. 13,000)
Sewage Treatment Plant (STP) treats the wastewater by Sequence
Batch Reactors (SBR) equipped with aeration system; dry weather
flow: 3,240 m3/day (max)
It includes 01 no. 200 m3 toxic holding tank, pre-
aeration and equalization tanks, sand filters, UV
disinfection system, sludge digester, sludge drying
beds. TSE (approx 2,000 m3/day) is transported, for
irrigation purposes, to designated areas by tankers
Services carried out by NITCO include:
Provision and Coordination of
specialized team to carry out O&M Services
Routine and Preventive
Maintenance (STP and collecting
system, pumping stations) and
Operation;
Overhauling of equipments;
Carry out of non-routine and emergency services
Carry out of sewage analysis;
Collection, transportation and disposal of wastewater from
different locations
Transportation and disposal
(irrigation) of TSE and wet/dry
solids to different locations
18
Major Projects in Qatar
REMOVAL OF WASTE WATER AND ASSOCIATED SERVICES
Contracts DGC EM 003, 008, 009, 011, 014 (Extended Contracts)
Client:
DOHA GOLF CLUB
Services:
Liquid waste
collection and
network cleaning
Period:
2007 – 2013
Daily waste water collection and disposal from Doha Golf Club
course and premises and cleaning of sewer network
Services carried out by NITCO include:
Daily collection and disposal from
cesspits by vacuum tankers;
Maintenance of the sewer line:
cleaning of cesspits, blockage
removal, sludge/grease removal
Inspection of the network
19
Major Projects in Qatar
AMC FOR SEWAGE AND WASTE DISPOSAL, SITE CLEANING &
MANPOWER SUPPLY
Contracts PO 2013400730 & PO 2016401167/0
Client:
QATAR VINYL CO.
Services:
Waste Management
Period:
2013 – 2016 &
2016 - 2021
Daily collection and disposal of sewage waste and domestic and
industrial waste from QVC site in Mesaieed
Services carried out by NITCO include:
Daily removal and disposal of sewage waste (fluid and sludge) by vacuum
tankers from the cesspits of the plant;
Removal and disposal of industrial waste: oil and other industrial
chemical waste;
Daily Collection and disposal of
domestic solid waste from plant
premises;
Daily general site cleaning of all the
outdoor areas: garbage collection
from street bins, litter picking,
mechanical sweeping by dedicated
equipment, removal of materials of different nature
20
Major Projects in Qatar
OPERATION AND MAINTENANCE OF WASTE WATER TREATMENT
PLANTS AT RAS LAFFAN INDUSTRIAL CITY
Contract GTC 05 107 MIC VARIATION Nr. 02,03,05 (Extended Contract)
Client:
QATAR
PETROLEUM
Services:
Operation and
Maintenance
Period:
2005 – 2011
Comprehensive Operation and Maintenance Services of 10
nos. waste water treatment plants in different locations inside
Ras Laffan Industrial City, total capacity 40,000 m3/day
Services carried out by NITCO include:
Providing and Coordination of
specialized team to carry out O&M
Services
Routine operation and maintenance of waste water treatment plants;
Scheduled Preventive Maintenance
and overhauling of equipment;
Non routine and emergency services;
Laboratory analysis
Sludge disposal
Spare parts and consumables (chemicals) supply and management
21
Major Projects in Qatar
WASTE MANAGEMENT SERVICES
Contracts TDR/003/02/2005 and TDR/009/02/2006
Client:
QATAR STEEL
Services:
Waste Management
Period:
2005 – 2008
Collection and disposal of waste water and sludge removal
from Qatar Steel Plant in Mesaieed
Services carried out by NITCO include:
Daily collection and disposal of approx 135 m3/day from 30 nos.
pits (50 to 81 m3) of the plant by
vacuum tankers;
Daily cleaning of the pits
Maintenance of the drainage line to the pits, removing of blockage by
pressure pumps
Removal of sludge and solid waste
from cesspits , sewage holding
tanks and grease traps
Daily collection of refuse and garbage from different locations
Daily sweeping and cleaning of all
plant roads and road shoulders,
slag and scrap yards, parking areas
Removal and disposal of
accumulated solid waste and debris
from family accommodation compounds and buildings
(Mesaieed Community Area)
22
Major Projects in Qatar
UPGRADING OF SEWERAGE NETWORK AND MECHANICAL AND
ELECTRICAL WORKS AT MESAIEED (PHASE 3)
Contract GTC 06 127 MIC
Client:
QATAR
PETROLEUM
Services:
Civil Works
(Drainage)
Period:
2005 – 2008
Refurbishment of the existing sewerage network, pumping
stations, treated sewage effluent (TSE) network and sewage
treatment plant (STP) in Mesaieed: excavation of all the areas,
materials supply and installation, roads reinstatement. Testing
and commissioning
Works carried out by NITCO include:
Replacement and construction of V.C.
sewers of various diameters (approx
15 km), associated manholes (nos.
225) and chambers at pumping
stations PSU1, PSU2, PSU3 and PSU5;
Replacement and construction of property connections with V.C. pipes
(approx 07 km) including inspection
chambers (181 nos.) at various
locations;
Replacement of the existing rising
main (approx 02 km)
Replacement, Installation and commissioning of screw pump,
lubricating system and spare parts in
STP
Replacement, Installation and
commissioning of high and low flow
pumps, gate and check valves,
electromagnetic flow meter in
pumping stations
Miscellaneous civil works in TSE
23
Major Projects in Qatar
OPERATION AND MAINTENANCE OF SEWAGE PUMPING STATIONS,
TREATMENT PLANTS AND THEIR RELATED SEWERAGE NETWORKS
IN THE STATE OF QATAR
Contract C99 - 2007
Client:
PUBLIC WORKS
AUTHORITY
Services:
Operation and
Maintenance
Period:
2008 – 2009
Comprehensive Operation and Maintenance Services of 48
nos pumping stations, 13 nos Package treatment plants and 01
sewage treatment plant and related network
Works carried out by NITCO include:
Providing and Coordination of specialized team to carry out O&M
Services
Routine operation and maintenance
of waste water treatment plant,
package treatment plants, pumping
stations, sewage network;
Scheduled Preventive Maintenance and overhauling of equipment;
Non routine and emergency
services;
Laboratory analysis;
Sludge disposal;
Design and implementation of
dedicated OMCMS (O&M
computerized management system)
24
Major Projects in Qatar
MECHANICAL AND ELECTRICAL WORKS TO PUMPING STATIONS
Contract QR 709 SC 01
Client:
GULF
CONSOLIDATED
CONTRACTORS
Services:
Electromechanical
refurbishment
Period:
2007 – 2008
Procurement, installation and commissioning, including
supervision and handing over of mechanical and electrical
installations for the modification/upgrading of pumping
stations in Mesaieed
Works carried out by NITCO include:
Procurement and installation of D.I. pipes and valves, submersible
pumps, pumping station control
cabinet, 200mm penstocks, surge
vessel chamber, lifting equipment
Electrical connections and
modifications
Testing and commissioning of the equipment
25
Major Projects in Qatar
SEWAGE AND WASTE DISPOSAL SERVICES
Contract LTC-008/12
Client:
SEEF LIMITED
Services:
Sewage, Domestic
Waste and Industrial
Waste Disposal
Period:
2014 – 2017
Daily removal and disposal of sewage water and domestic and
industrial waste from SEEF site in Mesaieed.
Services carried out by NITCO include:
Daily removal and disposal of sewage
waste (fluid and sludge) by vacuum
tankers from the cesspits of the plant;
Removal and disposal of industrial Wast;
Rental of steel skips;
Daily Collection and disposal of
domestic solid waste from plant premises.
26
Major Projects in Qatar
REFURBISHMENT OF BOILER IN NODCO PLANT AT MESAIEED
INDUSTRIAL CITY
Contract 6998/04/741
Client:
MACCHI S.p.A.
Services:
Mechanical Erection
and Supervision
Period:
2004
Refurbishment of a MACCHI Boiler installed in NODCO
Refinery at Mesaieed Industrial City, consisting in cutting and
removal of existing super heater, replacing the
interconnecting pipe spools, cutting and welding of stream
drums, installation and painting of flue gas stream generator
Services carried out by NITCO include:
Engineering supervision for the
erection
Provision and coordination of
specialized Team and equipment
PWHT, ND tests
Hydro testing of the boiler and
piping system
27
Services carried out by NITCO include:
Clean all outdoor and underground grease traps or grease interceptors in
Katara including all necessary service,
materials, labor and transportation as
per the schedule.
Conduct quarterly inspection and
cleaning service for blockages or
potential blockages on the upstream
and downstream pipes connected to
the grease traps.
Provide all manpower, materials and equipment to clear any blockage
found in grease trap or pipes.
PROVISION OF THREE YEARS GREASE TRAP CLEANING SERVICE AT
KATARA
Contract CVF/TC/FM/006/2013
Client:
KATARA
(CULTURAL
VILLAGE
FOUNDATION)
Services:
Grease traps Cleaning
Period:
2014 - 2017
Comprehensive preventive and breakdown maintenance
service specialized in cleaning services for outdoor and
underground grease traps installed in Katara.
Major Projects in Qatar
28
CALL-OFF CONTRACT FOR INDUSTRIAL CLEANING SERVICES
Contracts QAL-TNL-0147
Client:
Qatar Aluminium
Limited
Services: Industrial Cleaning
services
Period:
2012- 2015
Services carried out by NITCO include:
Provision of plant cleaners services
and Garbage collectors services
Refuse / garbage collection at the skips
Street/Road sweeping services
throughout the plant premises on
daily basis
Provision of cleaning materials,
equipment and machineries
SUPPLY and operation of an Industrial Vacuum truck (Super
Sucker) capable of cleaning coke and
alumina spills at a height exceed 70
meters.
Major Projects in Qatar
The scope of work is consisting two parts.
Plant area cleaning services and provision of multi skilled
labour crew
Industrial vacuum truck for ship unloading process
changeover and spill clean-up port & utilities
29
INDUSTRIAL CLEANING SERVICES
Contract 4600000880
Client:
Qatar Aluminium
Limited
Services: Industrial Cleaning
services
Period:
2015- 2018
Services carrying out by NITCO include:
Provision of plant cleaners services
and Garbage collectors services
Refuse / garbage collection at the skips and channels cleaning
Street/Road sweeping services
throughout the plant premises on
daily basis
Provision of cleaning materials,
equipment and machineries
SUPPLY and operation of an
Industrial Vacuum truck (Super
Sucker) capable of cleaning coke and alumina spills at a height exceed 70
meters.
Major Projects in Qatar
The scope of work consists of:
Qatalum Plant area and premises cleaning and provision
of multi skilled manpower
Provision of Industrial vacuum truck, Super sucker and
relevant equipment
30
SEWAGE SYSTEM CLEANING AND SEWAGE DISPOSAL
Contract 601355
Client:
Qatar Fertiliser
Company (QAFCO)
Services:
Sewer network
cleaning and removal
of sewage water
Period:
2017- 2019
Provision of 5000 gallon vacuum suction tanker for
removal and disposal of sewage from Qafco Wakrah 2
buildings regularly (on daily basis) . The work also
includes cleaning of sludge chambers, septic tanks, drain
lines etc. to keep the sewage system clean.
Services carried out by NITCO include:
Provision of 5000 gallon Vacuum
tankers including high pressure jetting
pump, operators, helpers and necessary
equipment and accessories to carry out
the work.
Cleaning of chambers and pipelines with high pressure water jetting.
Removal of all deposits accumulated in
the sewage system to prevent any
blockage or overflow.
Transportation and dumping of sludge
and residual at an approved dumping
site.
Cleaning of pit wall, floor and piping
with jetting machine and vacuum tanker
Washing and cleaning of surface area around the pit.
Major Projects in Qatar
31
WASTE MANAGEMENT AND ASSOCIATED SERVICES
Contract 255/9000/2014
Client:
Banana Island Resort
by Anantara
Services:
Solid and liquid waste
management and
associated services
Period:
2014- 2016
Provision of dedicated manpower and equipment
suitable to carry out waste management and associated
activities at Banana Island Resort and it’s facilities
located in Al Shuyoukh port and Al Wakra port
Services carried out by NITCO include:
Domestic waste segregation at the Island, transportation and disposal of
waste at an authorized facility in
mainland.
Grease traps cleaning at the Banana
Island Resort main facility
Removal and disposal of sewage and domestic garbage from Al Shuyoukh
Port
Removal and disposal of garbage from
Stores facility at Al Wakra
Major Projects in Qatar
32
Major Projects in Qatar
LANDSCAPING WORKS WITHIN DUKHAN FIELDS
Contract CG 09100400
Client:
QATAR
PETROLEUM
Services:
Landscaping Works
(EPIC Contract)
Period:
2009 – 2013
Engineering, Procurement, Installation and Commissioning
(EPIC) works of LANDSCAPING and BEAUTIFICATION
from Bridge no. 4 to Interchange no. 3 and from Khatiyah
under pass to STP main entrance, along the Zekreet to Umm
Bab Highway (Route 3) in Dukhan (Qatar).
Works carried out by NITCO include:
Landscaping of 03 nos roundabouts
Landscaping of central median
Construction of 02 nos. picnic/park areas
Landscaping of verges within the
construction limits
Landscaping of Khatiyah underpass
and surrounding areas
Landscaping of STP main entrance and its access roads
Landscaping around road bridge
Construction of six nos. underground pump houses and
storage tanks
Construction of new SMB
enclosure for irrigation power
supply distribution
Demolition of existing paved areas, interlock tiles walkways etc.
33
LANDSCAPING , IRRIGATION AND INDOOR PLANTS MAINTENANCE
Contracts TC-CN-194-11-GS & TC-CN-023-15-GS
Client:
Oryx GTL Limited.
Services:
Landscaping, Irrigation
and Indoor plants
Maintenance.
Doha & RLIC
Period:
2012-2016 &
2016-2019
Carrying out new landscaping works, maintenance of existing
landscapes, irrigation maintenance of irrigation equipments
/systems, up keeping of interior decoration with live plants and
its watering, replanting, maintenance of water features, at
ORYX GTL offices and plant premises in Ras Laffan and in Doha.
Services carried out by NITCO include:
Landscaping, Irrigation and Indoor
plants Maintenance
Development of new areas
Soil testing services
Weed removal and cleaning services
Pest control and disease control
Scarifying / Aerating
Grass maintenance
Water feature maintenance
Indoor plant maintenance
Major Projects in Qatar
34
SUPPLY AND MAINTENANCE SERVICES OF INDOOR PLANTS AND
POTS AT RASGAS FACILITIES
Contract CT/GR11/S078/11
Client:
RasGas Company
Limited.
Services:
Supply of Pots and
Indoor plants
including
Maintenance.
Period:
2012-2014
Supply, Delivery, Installation and Maintenance of indoor plants
and pots at the RasGas headquarters, west bay- Doha and other
RasGas facilities in Ras Laffan.
Services carried out by NITCO include:
Supply, delivery and installation of
indoor pots of different sizes and design
with materials that add more value to
the surrounding environment.
Supply and installation of different plants of high quality, planted in the best
quality soil and soil coverage with
pebbles or any other decorative
element.
Daily maintenance of the indoor plants.
Provision of multi-skilled workforce.
Regular watering of the plants at the
facility.
Major Projects in Qatar
35
NITCO WASTE SERVICES DIVISION capitalizes the technical know how acquired during years of
activity in favor of Major Clients to provide Services for the execution of minor/short time Projects
and/or on-call activities.
The intention is to provide Quality and Effective Services to satisfy in limited time the
requirements of the increased number of Clients
To this purpose, NITCO addresses to:
Industrial sites and workshops
Construction sites
Residential compounds
Commercial complexes
Camp and accommodation facilities
Hotels
Sports facilities
and provides this range of Services:
Operation and Maintenance of major domestic sewage systems:
Our specialized team daily operates and maintains all the electromechanical equipment and facilities
and performs the supporting activities:
Removal of blockages in sewer network
Cleaning and sewage/grease removal from the above
Periodical and on-call removal, transportation and disposal of sewage
Dewatering and over pumping
Potable Water transportation
Solid waste management Services
We serve important Community, Commercial and Industrial areas for:
Periodical and on-call removal, transportation and disposal of domestic and industrial solid waste
Roads sweeping and industrial cleaning
Landfills management
Garbage containers rental and supply (plastic and steel, all sizes)
Waste Services Division
All the Services are
executed also on
emergency basis.
36
Solid Waste Management Services
Removal and collection of solid waste (approximately 2,000 m3/month)
YEAR: 2010 - 2017
Waste Services Division
Clients
ALCAT
ALFRED TALKE LOGISTICS
AL HUDA
AL JABER ENGINEERING
AL RAIS GROUP
AL SADAF
ARCHIRODON
ASAS REALESTATE CO.
BANANA ISLAND RESORT DOHA
COMMERCIAL BANK OF QATAR
COMMODORE QATAR CONTRACTING CO.
CROWNE PLAZA HOTEL
DANEM ENGINEERING
GRAND HERITAGE HOTEL
GULF CONSOLIDATED CONTRACTORS (GCC)
ITALIAN STYLE – QATAR
KG INTERIORS
MARBU ASPHALT FACTORY
MAERSK OIL QATAR
MERWEB HOTEL
OXYGEN INTERNATIONAL
PEMCO INSPECTION COMPANY
QATAR ALUMINUIM LIMITED (QATALUM)
QATAR CATERERS AND CONTRACTORS
QATAR FIRST INVESTMENT BANK
QATAR MUSEUMS AUTHORITY
QATAR PRIMARY MATERIALS CO.
QATAR QUERIES AND BUILDING
QATAR REAL ESTATE (AL AQARIA)
Q- RELIANCE INTERNATIONAL
QATAR FERTILISER COMPANY
RUMAILLAH FACILITIES MANAGEMENT CO.
SEEF LIMITED
SINO HYDRO CORPORATION
SWISSBEL HOTEL, DOHA
TEKNOTES
TYESEER SERVICES
UNITED PRECAST CONCRETE
UNION PRECAST FACTORY
ZUBLIN INTERNATIONAL
37
Operation and Maintenance of major domestic sewerage systems
Removal and collection of waste water (approximately 60,000 m3/month) and associated
services
YEAR: 2010 – 2017
Clients
AL HUDA
AL JABER
ALFRED TALKE LOGISTICS
AL GHAITH TRADING & INDUSTRIAL SERVICES
AL RAIS GROUP
ARCHIRODON
BANANA ISLAND RESORT
BIN THANI ELECTRO MECHANICAL CONT.
CORAL HOTEL DOHA
DOHA GOLF CLUB
DANEM ENGINEERING WORKS
DOOSAN INDUSTRIES
DOUBLE TREE BY HILTON
ETA STAR INTERNATIONAL
GALFAR ALMISNAD ENGG.
GULF CONSOLIDATED CONTRACTORS
GULF CONTRACTING CO.
GRAND HERITAGE HOTEL, DOHA
GRAND REGAL HOTEL, DOHA
IBIN AJAYAN TRADING CO.
INTERCONTINENTAL HOTEL, DOHA
INTEGRAL FOOD SERVICES
H.H. THE EMIR’S PRIVATE AFFAIRS
HYOSUNG EBARA
KATARA – CULTURAL VILLAGE FOUNDATION
KEMCO MAINTENANCE & SERVICE
LANDMARK COMMERCIAL CENTER
LINC FACILITIES MENA (DOHA LAND)
Clients
MAWASHI
MESAIEED POWER COMPANY (M-POWER)
MAINTENANCE MANAGEMENT GROUP (MMG)
MARRIOTT MARQUIS DOHA CITY CENTER HOTEL
NATIONAL CLEANING COMPANY.
ORYX ROTANA HOTEL, DOHA
PETROSERV LIMITED
QATAR ALUMINUIM LIMITED (QATALUM)
QATAR CATERERS AND CONTRACTORS
QATAR FERTILISER COMPANY
QATAR FIRST INVESTMENT BANK
QATAR PRIMARY MATERIALS CO.
QATAR MUSEUM AUTHORITY
QATAR NAVIGATION Q.S.C (MILAHA)
QATAR REAL ESTATE (ALAQARIA)
QATAR TRADING AND CONTRACTING GROUP
QATAR VINYL COMPANY
QROM POWDER COATING FACTORY
RITZ CARLTON HOTEL
ROTANA HOTEL DOHA
SEALINE BEACH RESORT
SEEF LIMITED
TECHNIP CHIYODA JOINT VENTURE (TCJV)
TEKNOTES
TYESEER SERVICES
UNITED DEVELOPMENT COMPANY (UDC) THE PEARL
VEOLIA WATER
VORTEX INTERNATIONAL
Waste Services Division
38
Landscaping, Irrigation and indoor plants Maintenance
Landscaping Services
We serve important Community, Commercial and Industrial areas for:
Maintenance of Landscaping and Irrigation system
Maintenance of Indoor Plants
Development of New Landscape Area
(Landscaping and maintenance associated services)
YEAR: 2009 – PRESENT
LIST OF CLIENTS:
ORYX GTL LIMITED
RASGAS COMPANY LIMITED
MESAIEED POWER COMPANY
QATAR VINYL COMPANY
QATAR MUSEUM AUTHORITY
QATAR PETROLEUM
CORAL HOTEL
LINC GROUP
Landscaping Division
39
Currently for two major Clients (COMMISSIONING S.r.l. Italy and EUROPOWER S.p.A. Italy),
NITCO Qatar is providing through specialized Consultancy the following Services in Qatar and
worldwide:
- Technical Assistance to preparation of major Tenders and proposals, Market research
and business intelligence in Qatar;
- Technical assistance in site and supervision for:
Mechanical and electrical erection
Production and site management
Materials coordination
Commissioning, start-up and operation
We operate in Europe, North Africa (Algeria, Egypt, Libya), Asia (China, Vietnam, Korea,
India, Turkey, Kurdistan, Russia), South America (Brazil, Venezuela, Ecuador,
Argentina) and Middle East (Kuwait, Iran, KSA, UAE ) in the Power and Steel making
sectors with specialized teams in site on medium-long term basis.
Technical Assistance
41
CLIENT YEAR AND DESCRIPTION
NITCO S.p.A / AKMERCAN 2009 Technical evaluation for “Project
of solid waste collection and removal and
cleaning works in third and fourth sector of
Abu Dhabi”.
ABU DHABI MUNICIPALITY 2003-2008 O&M of irrigation pumping station and
reservoirs of Abu Dhabi Island.
ABU DHABI MUNICIPALITY 2003-2010 O&M of sewage pumping stations and
treatment plants at Delma, Baaya Sila, Ghuwaifat, and
Ghayathi – Western Region Abu Dhabi (total 8,225
m3/day).
ABU DHABI MUNICIPALITY 2002-2007 O&M of sewage treatment plants of
Ghantoot and Al Khatim (total 2,000 m3/day) and
Medinat Zayed, Marfa, Bainuna, Liwa, Abu Al Abyad,
Sir Baniyas (total capacity 18,900 m3/day).
ABU DHABI WATER AND 2000-2002 O&M of distillers of the desalination
station of Umm al Nar.
ELECTRICITY AUTHORITY
ACTCO/ANSALDO 2003 Erection of Electrical Substations in Saniya
and Al Wagon.
FISIA ITALIMPIANTI 1999-2001Technical Assistance for erection and
commissioning of desalination plants for Dubai
Electricity and Water Authority at Jewel Ali.
ABU DHABI WATER AND 1999-2001 Maintenance of auxiliaries in the
desalination stations of Umm Al Nar, Al Tawellah.
ELECTRICITY AUTHORITY Baniyas, Mina Zayed (Abu Dhabi).
Major Projects in UAE
43
CLIENT YEAR AND DESCRIPTION
ACCAM SpA 2001-2021 Full management of operation and
Maintenance of Waste to Energy Plant
ELETTRA Srl PRODUCTION 2003-2015 Turn-key with total guarantee of
Operation (GTF) of Combined Cycle Plant
EUROPEN COMMISSION 2005-2013 Operation & Maintenance -CCR Plant Tri-
CHP Exercise and Maintaining
LUCCHINI SIDERURGICA 2004-2014 Global Maintenance Service (LTSA) for
11.5 Mw Power Plant in Blast Furnace.
FISIA ITALIMPIANTI 2004-2008 Elaboration of Operation and
Maintenance Manuals for desalination Plants abroad.
ENELPOWER 2004-2008 Elaboration of Operation and
Maintenance Manuals for desalination and energy
plants abroad.
ABB 2002-2003 Incinerator Commissioning and
Operation (Milano).
MULTISERVICE 2002-2008 Waste collection and disposal
(Industrial Plant).
FISIA ITALIMPIANTI 2002-2010 Technical Assistance Services abroad in
the Industrial sector.
FISIA ITALIMPIANTI 2001-2002 Commissioning and spare part
Management of Energy Plant from Waste in Campania
Region (7000 tons/day).
ABB SADELMI 1998 - 2000 Commissioning of Combined Cycle
Power Plant of API Refinery.
Major Projects in Italy