New England 04 2016

20
By Irwin rapoport CEG CORRESPONDENT The Connecticut Department of Transportation’s (CTDOT) $34.8 million project to replace the Route 8/25 bridges in Bridgeport has exceeded the half-way point as crews from Manafort Brothers Incorporated are working hard to meet the September delivery date. The four bridges being rehabilitated carry an average of 88,000 cars over Capital Avenue, Lindley Street and a large parking lot. The Lindley Street Bridge consists of seven, 82 ft. (25 m) long spans with four 12-ft. (3.6 m) lanes and two shoulders in each direction. The project will reduce the bridge to two spans while keeping the same lane and shoul- der capacity. The Capital Avenue Bridge, consisting of a single span with four 12-ft. lanes and two shoulders in each direction will be replaced with a similar structure. The work also includes the construction of a large retaining wall to support 425 ft. (130 m) of new highway, the rehabilitation of the metal bin-wall retaining wall which is currently supporting Route 8 southbound, south of Capital Avenue and capacity improvements to two intersections on Lindley Street adja- cent to Route 8 northbound. The bridges will be demolished and rebuilt in a different configuration using accelerated bridge construction tech- niques. The new superstructures will consist of prefabricated bridge units (PBUs), which consists of two steel beams fab- ricated with an integral concrete deck to form a double tee section. The PBUs will be connected in the field with narrow longitudinal closure pours. CTDOT’s $34.8M Bridgeport Route 8/25 Project Reaches Important Milestone THE NEW ENGLAND EDITION A Supplement to: Your New England States Connection • Amanda Hogeboom-merritt 1-800-988-1203 “The Nation’s Best Read Construction Newspaper… Founded in 1957.” 1 1 1 11 2 16 201 3 9 1 95 95 495 95 9 16 3 26 2 202 89 93 93 95 2 7 4 7 2 89 89 91 91 3 7 2 2 6 90 90 495 95 93 195 95 6 95 7 6 395 95 84 91 91 84 95 E q u I P m E N t g u I d E Formerly February 24 2016 Vol. XlIX • No. 4 ® Manafort Brothers Incorporated photo The Connecticut Department of Transportation’s (CTDOT) $34.8 million project to replace the Route 8/25 bridges in Bridgeport has exceeded the half-way point as crews from Manafort Brothers Incorporated are working hard to meet the September delivery date. see CtdOt page 8 Specializing in: Demolition, Portable Crushing, Material Sales, C & D Recycling, Land Clearing & 30-115 Yd. Trailers 2208 Plainfield Pike • Johnston, RI 02919 401-943-7100 • Fax: 401-647-5041 www.jrvinagrocorp.com Call for Pricing LEED Accredited in Waste Management GIVE US YOUR HAMMER! GIVE US YOUR HAMMER! 61 Silva Lane • Dracut, MA 01826 30% off same class Ramfos hammer with competitor’s trade in Call Today (978) 454-3320 • Repairs • Rebuilds • Replacement Parts in Stock www.foleyengines.com M.G. Equipment Call Phil Guerard (413) 427-7171 SNOW CONTRACT? RENT with us! HIGH QUALITY FAST SHIPPING GUARANTEED TO FIT UNDERCARRIAGE PARTS FLATPROOF SKIDSTEER TIRES RUBBER PADS FOR STEEL TRACKS 888-888-1248 NJ, TX, WA WAREHOUSES WE STOCK RUBBER TRACKS for Over 6,000 Models! Some Used Tracks Available. 5% discount in February CALL 888-81-GORILLA(46745) *Some restrictions apply New Hydraulic Hammers. Remanufactured Hammers. Hammer repairs/rebuilding with free area pickup. Hammer toolbits delivered to your site! YOUR ONE-STOP HYDRAULIC HAMMER SHOP™ Other Screeners Available ArguS INduStrIAl CO. www.ez-screen.com 866-745-5828 6’x5’ Screenbox Works with 1/2 to 1 3/4 Yd. Loaders, 25 H.P. Kohler Diesel Engine, 24” Conveyor Dumps Screened Product 9’ High $41,900 plus freight. 2016 EZ-Screen 1200XLS New Option Separate 3 Products

description

New England 04 2016

Transcript of New England 04 2016

Page 1: New England 04 2016

By Irwin rapoportCEG CORRESPONDENT

The Connecticut Department of Transportation’s(CTDOT) $34.8 million project to replace the Route 8/25bridges in Bridgeport has exceeded the half-way point ascrews from Manafort Brothers Incorporated are workinghard to meet the September delivery date.

The four bridges being rehabilitated carry an average of88,000 cars over Capital Avenue, Lindley Street and a largeparking lot. The Lindley Street Bridge consists of seven, 82ft. (25 m) long spans with four 12-ft. (3.6 m) lanes and twoshoulders in each direction. The project will reduce thebridge to two spans while keeping the same lane and shoul-der capacity.

The Capital Avenue Bridge, consisting of a single span

with four 12-ft. lanes and two shoulders in each directionwill be replaced with a similar structure. The work alsoincludes the construction of a large retaining wall to support425 ft. (130 m) of new highway, the rehabilitation of themetal bin-wall retaining wall which is currently supportingRoute 8 southbound, south of Capital Avenue and capacityimprovements to two intersections on Lindley Street adja-cent to Route 8 northbound.

The bridges will be demolished and rebuilt in a differentconfiguration using accelerated bridge construction tech-niques. The new superstructures will consist of prefabricatedbridge units (PBUs), which consists of two steel beams fab-ricated with an integral concrete deck to form a double teesection. The PBUs will be connected in the field with narrowlongitudinal closure pours.

CTDOT’s $34.8M Bridgeport Route 8/25 Project Reaches Important Milestone

THE NEW ENGLAND EDITION A Supplement to:

Your New England States Connection •  Amanda Hogeboom-merritt 1-800-988-1203

“The Nation’s Best Read Construction Newspaper… Founded in 1957.”

1

1

1

11

2

16

201

3

9

1

95

95

495

95

9

16

3

26

2

202

89

93

93 95

2

7

4

7

2

89

89

91

91

37

22

6

90

90

495

9593

195

95

6

95

7

6395

95

8491

91

84

95

E q u I P m E N t g u I d E

F o r m e r l y

February 242016

Vol. XlIX • No.4

®

Manafort Brothers Incorporated photoThe Connecticut Department of Transportation’s (CTDOT) $34.8 million project to replace the Route 8/25 bridgesin Bridgeport has exceeded the half-way point as crews from Manafort Brothers Incorporated are workinghard to meet the September delivery date.

see CtdOt page 8

Specializing in:

Demolition, Portable Crushing, Material Sales, C & D Recycling,

Land Clearing & 30-115 Yd. Trailers2208 Plainfield Pike • Johnston, RI 02919401-943-7100 • Fax: 401-647-5041

www.jrvinagrocorp.comCall for Pricing

LEED Accredited in Waste Management

GIVE USYOUR

HAMMER!

GIVE USYOUR

HAMMER!

61 Silva Lane • Dracut, MA 01826

30% off same class Ramfos hammer with competitor’s trade in

Call Today (978) 454-3320

• Repairs

• Rebuilds

• ReplacementParts in

Stock

www.foleyengines.com

w

M.G. EquipmentCall Phil Guerard (413) 427-7171

SNOW CONTRACT?RENT with us!

• HIGH QUALITY• FAST SHIPPING• GUARANTEED TO FIT• UNDERCARRIAGE PARTS• FLATPROOF SKIDSTEER TIRES• RUBBER PADS FOR STEEL TRACKS

888-888-1248

NJ, TX, WA

WAREHOUSES

WE STOCK RUBBER TRACKSfor Over 6,000 Models!

Some Used TracksAvailable.

5% discount in February

CALL 888-81-GORILLA(46745)*Some restrictions apply

New Hydraulic Hammers.Remanufactured Hammers.Hammer repairs/rebuilding

with free area pickup.Hammer toolbits delivered

to your site!

YOUR ONE-STOP HYDRAULIC HAMMER SHOP™

Other Screeners AvailableArguS INduStrIAl CO.www.ez-screen.com866-745-5828

6’x5’ ScreenboxWorks with 1/2 to 1 3/4Yd. Loaders, 25 H.P.

Kohler Diesel Engine, 24”Conveyor Dumps

Screened Product 9’ High

$41,900 plus freight.

2016 EZ-Screen1200XLS

New Option Separate3 Products

Page 2: New England 04 2016

Page 2 • February 24, 2016 • www.constructionequipmentguide.com • New England States Supplement • Construction Equipment Guide

THE W.I. CLARK COMPANYBrookfield, CT • Wallingford, CT • Plainfield, CT

Call Mark Doty @ 203-823-2316

See Our Complete Inventory at www.wiclark.com

c/Air, 4x4, Ext. Hoe, Front & Rear Couplers,12 & 24” Buckets, Wobble Sticks, GreatCondition, stk#22910 ..........................$42,500

2002 John Deere 310SG 2011 Deere 310SJ

Tier 4 Cummins Power, Dealer Maintained,Excellent Condition, stk#23023 ..........$69,000

2012 Ingersoll Rand XP825WCU

Cummins Power, Dealer Maintained SinceNew, Great Condition, stk#20097 ......$109,000

2008 Ingersoll Rand HP1600WCU

c/Heat, 4x4, Ext. Hoe with 24” Bucket, GoodRubber, stk#22767 ..............................$18,500

Deere 410C

Hydraulic Hammer with Jumper Hoses, 90%Bit, 725 ft lb unit, stk#22386 ..................$4,000

Allied Construction 725

2010 John Deere 410J

7 Hrs, 4x4, Loader and Backhoe, NewCondition, stk#22911 ..........................$16,500

2015 Kubota BX25DLB

410 Hrs, 4x4, c/Heat, Full Light Package,Loader w/Front Coupler, Rear Backhoe,Excellent Condition, stk#22912 ..........$46,500

2012 Kubota R420S

1861 Hrs, c/Air, Pilots, Ext Hoe, Front & RearHyds, Great Rubber, stk#22596 ..........$80,000

c/Air, 1890 Hrs, 4x4, Ext. Hoe, Front & RearHyds, 4-1 Bkt, stk#22846 ....................$79,500

Page 3: New England 04 2016

Construction Equipment Guide • New England States Supplement • www.constructionequipmentguide.com • February 24, 2016 • Page 3

Track DENSITY IN REAL TIME.

DENSITY: 94.2%PASS: 4 TEMPERATURE: 250°

DENSITY: 95.1%PASS: 5 TEMPERATURE: 220°

PASS: 2 DENSITY: 92.6%TEMPERATURE: 270°

DEALER LOGO

Contact your localdealer:

dealer:

Dealer Name

T, SCity123.456.7890

T, SCity123.456.7890

T, SCity123.456.7890

T, SCity123.456.7890

T, SCity123.456.7890

T, SCity123.456.7890

T, SCity123.456.7890

123.456.7890

T, SCity123.456.7890

T, SCity123.456.7890

oVVolv

oVVolv

o Intelligent Compaction (IC) with Density Dirolv

o has changed the game. Density Dirolv

ect.o Intelligent Compaction (IC) with Density Dir

ovides actual density calculations in rect pro has changed the game. Density Dir

ealovides actual density calculations in r

ALERDELOGO

time — eliminating guessless time, get your bonus, and win mor

e at Learn mor olvv

work and rtime — eliminating guessacts with Ve contrless time, get your bonus, and win mor

ectyDirom/Densite.cocolv .

e sampling. Imeducing cor re sampling. Impr and r reducing corect.o Density Dirolvcts with V Volv

, do it ine mat qualityov mpr o

www.tylerequipment.com

251 Shaker RoadEast Longmeadow, MA 01028800.292.6351

1980 Berlin TurnpikeBerlin, CT 06037800.352.4473

Contact your local dealer:

Page 4: New England 04 2016

Page 4 • February 24, 2016 • www.constructionequipmentguide.com • New England States Supplement • Construction Equipment Guide

The Rhode Island Department of Transportation receivedbids for transportation-related improvement projects.

Following is a list of some of the projects let.

R.I. Contract No.: 2015-CH-061Project: 2015 Statewide resurfacing program, Contract-1.Contractors and Bid Amounts:

• J.H. Lynch & Sons — $4,129,266• Cardi Corporation — $4,259,705• D’ambra Construction Company Inc. — $4,277,854

R.I. Contract No.: 2015-CH-066Project: 1R improvements to Route 116 Knotty OakRoad.Contractors and Bid Amounts:

• Cardi Corporation — $1,437,414• D’ambra Construction Company Inc. — $1,553,335• J.H. Lynch & Sons — $1,691,071

R.I. Contract No.: 2015-CB-004Project: Repairs to Coles Bridge No. 134.Contractors and Bid Amounts:

• Manafort Bros Inc. — $463,722• J.H. Lynch & Sons — $488,512• Cardi Corporation — $540,437• Aetna Bridge Company — $547,444• D’ambra Construction Company Inc. — $553,736• Northern Construction Service LLC — $675,248

R.I. Contract No.: 2015-CH-022Project: 1R improvements to Woonasquatucket Avenue.Contractors and Bid Amounts:

• D’ambra Construction Company Inc. — $3,365,318• J.H. Lynch & Sons — $3,828,030• Cardi Corporation — $3,933,250

R.I. Contract No.: 2015-CT-069Project: State Traffic Commission Contract 5 — North.Contractors and Bid Amounts:

• Cardi Corporation — $1,244,462• J.H. Lynch & Sons — $1,308,154• D’ambra Construction Company Inc. — $1,333,333

R.I. Contract No.: 2015-CB-030Project: Clarence L. Hussey Memorial Bridge No. 11.Contractors and Bid Amounts:

• Aetna Bridge Company — $1,677,016• Cardi Corporation — $1,836,752• John Rocchio Corporation — $2,208,858• Northern Construction Service LLC — $2,350,978• D’ambra Construction Company Inc. — $3,510,739• New England Building & Bridge Company Inc. —

$3,605,073

R.I. Contract No.: 2015-CB-082Project: High priority repairs to Pawtuxet River North

Bridge No. 062901.Contractors and Bid Amounts:

• New England Building & Bridge Company Inc. —$581,439

• Aetna Bridge Company — $585,744• Cardi Corporation — $684,196

R.I. Contract No.: 2015-CH-065Project: 1R improvements to Rt. 107.Contractors and Bid Amounts:

• J.H. Lynch & Sons — $2,397,701• Cardi Corporation — $2,495,060• D’ambra Construction Company Inc. — $2,673,379

R.I. Contract No.: 2015-CT-020Project: Traffic signal optimization 2015 Contract 2.Contractors and Bid Amounts:

• Arden Engineering — $964,765• J.H. Lynch & Sons — $1,068,360

R.I. Contract No.: 2015-CT-086Project: Emergency signal repairs — Hartford Avenue atBrown Avenue, Johnston.Contractors and Bid Amounts:

• Rossi Electric Company — $84,340• Arden Engineering — $89,220

R.I. Contract No.: 2015-CB-021Project: I-95 Corridor bridge preservation and resurfacing.Contractors and Bid Amounts:

• Cardi Corporation — $10,391,810• J.H. Lynch & Sons — $11,490,921• Aetna Bridge Company — $11,912,985

R.I. Contract No.: 2015-CH-013Project: Improvements to Dexter Street and repairs toBridge #935.Contractors and Bid Amounts:

• D’ambra Construction Company Inc. — $3,853,271• Cardi Corporation — $4,274,871• J.H. Lynch & Sons — $4,359,429

R.I. Contract No.: 2015-CH-050Project: Improvements to New River Road and VictoryHighway.Contractors and Bid Amounts:

• J.H. Lynch & Sons — $1,281,947• Narragansett Improvement Company — $1,294,883• D’ambra Construction Company Inc. — $1,333,333

R.I. Contract No.: 2015-CR-052Project: 2015 paver placed elastomeric surface treatment.Contractors and Bid Amounts:

• T. Miozzi Inc. — $1,683,408• J.H. Lynch & Sons — $1,832,545• Cardi Corporation — $1,860,383• D’ambra Construction Company Inc. — $1,921,559

R.I. Contract No.: 2015-CH-047Project: Improvements to U.S. Rte. 1 in South Kingstown.Contractors and Bid Amounts:

• D’ambra Construction Company Inc. — $1,879,417• Cardi Corporation — $1,892,369• J.H. Lynch & Sons — $2,308,722

Newport • Providence • Washington • Bristol • Kent • Carolina • Newport • Providence • Washington • Bristol • Kent • Carolina • Newport •Providence • Washington • Bristol • Kent • Carolina • Newport • Providence • Washington • Bristol • Kent • Carolina • Newport • Providence• Washington • Bristol • Kent • Carolina • Newport • Providence • Washington • Bristol • Kent • Carolina • Newport • Providence • Washington• Bristol • Kent • Carolina • Newport • Providence • Washington • Bristol • Kent • Carolina • Newport • Providence • Washington • Bristol •Kent • Carolina • Newport • Providence • Washington • Bristol • Kent • Carolina • Newport • Providence • Washington • Bristol • Kent •

Rhode Island...

“The Ocean State” Highway Projects

For advertising rates: Contact Edwin M. McKeon Jr.

215/885-2900Toll Free 800/523-2200

Fax 215/885-2910e-mail [email protected]

Contact Amanda Hogeboom-Merritt• New England 518/396-7659

Toll Free 800/988-1203Fax 315/866-1379

e-mail [email protected]

Contact Kent Hogeboom• New York • New England 315/866-1379

Toll Free 800/988-1203Fax 315/823-4136

e-mail [email protected]

Construction Equipment Guide NortheastEdition (ISSN 1081-7034) is published bi-weekly by Construction Equipment GuideLtd. Advertising and Editorial Offices arelocated at 470 Maryland Dr., Ft. Washington, PA 19034. Toll Free800/523-2200 or Fax 215/885-2910.Annual Subscription Rate $65.00. Call forCanadian and foreign rates.

Periodicals postage paid at Ft. Washington,PA and at additional mailing offices. POSTMASTER: Send address changes toConstruction Equipment Guide NortheastEdition, 470 Maryland Dr, Ft. Washington, PA19034.

Contents Copyrighted ©2016, byConstruction Equipment Guide, which is aRegistered Trademark, registered in the U.S.Patent Office. Registration number 0957323.All rights reserved, nothing may be reprintedor reproduced(including framing) in whole or part without writtenpermission from the publisher. All editorialmaterial, photographs, drawings, letters, and other material will be treated as unconditionally assigned for publication andcopyright purposes and are subject toConstruction Equipment Guide's unrestrictedright to edit and comment editorially.Contributor articles do not necessarily reflectthe policy or opinions of this publication.

Call or write for advertising rates, publicationschedule and media kit. The ConstructionEquipment Guide is not responsible for cleri-cal or printer's errors, every care is taken toavoid mistakes. Photographs of equipmentused in advertisements are not necessarilyactual photographs of the specific machine.Similar photographs are used occasionallyand every effort is taken to depict the actualequipment advertised. The right is reservedto reject any advertising.

Founder, Publisher & CEO Edwin M. McKeon Sr. Northeast Publisher Edwin M. McKeon Jr.

Editor In Chief Craig Mongeau Associate Editor Christine Allen

Editorial Consultant Pete Sigmund Production Mgr. John Pinkerton

Controller Judith NixonCirculation Mgr. Cathy Printz

Main office 470 Maryland Drive Fort Washington, PA 19034

215/885-2900 Toll Free 800/523-2200

Fax 215/885-2910

Web site www.constructionequipmentguide.comEditorial e-mail [email protected]

Advertising e-mail [email protected]

NEW ENGLAND EDitioN

Page 5: New England 04 2016

Construction Equipment Guide • New England States Supplement • www.constructionequipmentguide.com • February 24, 2016 • Page 5

160 Elm St. Unit 1 • Walpole, MA 02081(508) 660-7600

Fax: (508) 660-7614

www.lhequip.com

Page 6: New England 04 2016

Page 6 • February 24, 2016 • www.constructionequipmentguide.com • New England States Supplement • Construction Equipment Guide

Harvard Museum AwardsRenovation Project to SCI

South Coast Improvement Company(SCI), a design-build general contractorserving New England and the Mid-Atlanticstates, was recently awarded renovationprojects at the Harvard Museum of NaturalHistory at 26 Oxford St. on the campus ofHarvard University in Cambridge, Mass.

The projects will feature the creation ofstudent suites within the open space in theComparative Zoology section of the muse-um. Each suite will include desk/workstationwith data links and updated furniture.

The other renovation will involve con-verting open space in Suite B23 into officespace for museum staff.

South Coast Improvement Company willbegin these renovations on Feb. 1, with acompletion date anticipated in the spring.The two renovation projects cost a total ofapproximately $600,000.

“The goal of renovations at educationaland institutional facilities like the NaturalHistory Museum is to create an exception-al final product and cause minimal disrup-tion to staff and students in the process,”said Tom Quinlan, president of SouthCoast Improvement Company.“Fortunately, we have a lot of experiencewith these kinds of projects and we can’twait to get going.”

Some recent South Coast Improvement

projects at schools and universities includework at Milton Academy, Boston Collegeand MIT.

Based in Marion, Mass., and with anoffice in Reading, Pa., South CoastImprovement Co is a recognized leader inproviding building and renovation servicesto a client base of institutional, senior living,healthcare and retail clients.

About South Coast ImprovementCompany

South Coast Improvement offers a rangeof design, construction and managementservices across a variety of sectors — interi-ors as well as exteriors — including officebuildings, health care facilities, educationalinstitutions, commercial properties, assistedliving facilities and residential communities.South Coast Improvement’s servicesinclude: preconstruction analysis; construc-tion management; general contracting;design/build services; capital improvement;building envelope improvements; and interi-or renovations.

For more information, call 508/748-6545or visit www.southcoastimprovement.com.

(This story also can be found onConstruction Equipment Guide’s Website at www.constructionequipment-guide.com.)

South Coast ImprovementCompany (SCI), a design-build general contractorserving New England andthe Mid-Atlantic states,was recently awardedrenovation projects atthe Harvard Museum ofNatural History at 26Oxford St. on the campusof Harvard University inCambridge, Mass.

THE N.I.C.E. COMPANY9 Rosenfeld Drive, Hopedale, MAToll Free# 888-717-8096 • www.theniceco.com

We sell NICE machines!

WE R

EN

T •

WE R

EN

T •

WE R

EN

T •

WE R

EN

T •

WE R

EN

T •

WE R

EN

T •

WE R

EN

T •

WE R

EN

T •

WE R

EN

T •

WE R

EN

T •

WE R

EN

T •

WE R

EN

T •

WE R

EN

T •

WE R

EN

T •

WE R

EN

T •

WE R

EN

T •

WE R

EN

T •

WE R

EN

T •

WE R

EN

T

WE R

EN

T • W

E R

EN

T • W

E R

EN

T • W

E R

EN

T • W

E R

EN

T • W

E R

EN

T • W

E R

EN

T • W

E R

EN

T • W

E R

EN

T • W

E R

EN

T • W

E R

EN

T • W

E R

EN

T • W

E R

EN

T • W

E R

EN

T • W

E R

EN

T • W

E R

EN

T • W

E R

EN

T • W

E R

EN

T • W

E R

EN

T

NEW 2014 Hyundai RobexR140LC-9A EXCAVATOR: Brand

New, Equipped w/Factory Plumbing,AC, Bucket w/Teeth, Quick Coupler

$115,000 $109,000

2011 Doosan DX255LC: QC, tilt-ing, digging buckets, 6K hours. Marked Down! Only $69,000

NEW DOOSAN 225LC:with Factory Plumbing.

Only $149,000 $139,000

2008 Terex TA35: 4,200 hours,very nice. $139,000 $119,000or rent for $9,000 per month

1986 LIDDELL 35 TONDETACH TRAILER:

$11,000

2007 KOMATSU PC158:4200 Hrs, Plumbed, QuickCoupler, Hard to Find These

Machines with Fairly Low Hours!$79,000

2014 KOMATSU PC138: AS NEW, only 340 hours, JRB coupler, plumbed

$144,500 ONLY $129,000

2011 CAT 307D:1700 hours, steel tracks, plumbed

$63,500

RENT ME!!

RENT ME!!

RENT ME!!

RENT ME!!

NEW 2014 JCB 3CX: 14’ backhoe, E stick, 4x4, plumbed to front $79,000

2008 CAT 324D: 5200 hours $99,000

Page 7: New England 04 2016

Construction Equipment Guide • New England States Supplement • www.constructionequipmentguide.com • February 24, 2016 • Page 7

Doosan wheel loaders are packed with comfort features you can see, hear and feel. A wide-open view of the work area. Low noise levels. Air suspension seat and ergonomic controls in line with your natural movements. Still, performance and productivity are key, and your Doosan loader delivers power and torque to penetrate hard materials. Superior li� height and li� capacity increase e�ciency. Operators can see and feel the di�erence.

Get a closer look. Stop by and visit us today.

Doosan and the Doosan logo are registered trademarks of Doosan Corp. in the United States and various other countries around the world. 16-D012

Equipment East61 Silva Lane • Dracut, MA 01826978-454-3320 • www.equipmenteast.com

Authorized Doosan Dealer

The best in heavy equipment.

l leehn wasDooeed fnr aaeee, hs

psur si. Aslevelol marutar nuoyuod yn, ayee kra

d mrae htartenep

h ctied wkcae prs aredaol lf tw oein vepo-edi. A wleemonogrd ent aaen soisneamrofre, pllit. Sstnemevos previler dedaon lasr Dooue� hir loirepu. Sslairetad m

nau cos yerutaet f erofomoh cesiow noa. Lerk aroe whf t

htie wnin ls ilortnoc cimytivitcudord pne acnoe tuqrod tnr aewos pyticapa� cid lnt ahgie

pmeuiqEreal Deanoso DdzeirohtAu

tsa Etn

atatpeic�e esaercni

oor lesolt a ceG

on lasooe Dhd tnn aasooDors aeirtnuor cehts ouoirav

� hopu. Ssatanee an sas crotarep. Oycn

s tt uisid vny ap bot. Skoo

on Casoof Ds okramedard teretsigee rro ag210D-6. 1dlroe whd tnuo

ytapa� ct ag.ecnere�eie dhl teed f en

.yy.aods t

d ns aetatd Setine Uhn t. ipro

pmeuiqEe naa Lvli1 S6 •

0233-454-879

tsa Etn6281A 0, Mtucar D

• .tsatenempiuqe.ww w

mco.

Page 8: New England 04 2016

Page 8 • February 24, 2016 • www.constructionequipmentguide.com • New England States Supplement • Construction Equipment Guide

The Lindley Street Bridges will be reduced to two spanseach by filling in five of the seven spans on each bridge. Thepier to the north of the second span will be converted to anabutment by constructing a retaining wall behind the exist-ing pier. The substructures to the north of the final two spanstructures will be left in place and buried. The area under thespans to be removed will be filled. The fill will be retainedby concrete retaining walls built outboard of the existingbridge limits.

Federal highway funds cover 85 percent of the cost, withthe remaining 15 percent from the state. The existingbridges, nearly 2 mi. (3.2 km) north of Interstate 95, werebuilt in 1973 and according to CTDOT, have reached the“excessive deterioration” point and cannot be repaired.

“The bridges are part of CTDOT’s bridge program whichprioritizes work based on a continuous assessment of theremaining useful life of bridges and their need to be replacedor rehabilitated,” stated the project Web site. “CTDOT hasdetermined that the bridges involved are reaching the end oftheir useful life and warrant rehabilitation.”

“The existing precast concrete beams supporting the road-way are experiencing what is called an Alkali-SilicaReaction, where, due to a chemical reaction within the con-crete, the concrete literally self-destructs,” said Scott Adkins,project engineer of CTDOT. “While the bridges are current-ly structurally safe, there is no way to repair the beams, andtherefore the entire superstructure must be replaced. In the1970s, ASR was a common problem. Fortunately, advancesin concrete construction have significantly reduced theoccurrence of ASR.

“Lane closure and stage construction peri-ods that would impact the travel lanes onRoute 8/25 have been reduced from twoyears to two periods of approximately 14days each,” said Adkins. “The ability toreduce the impact on the traveling public isvery important to the department and playeda central role in the design of the project andis part of the ‘get in and get out’ policy putforward by CTDOT.”

Commenting on additional constructionmethods, which will reduce the long-termmaintenance costs, Adkins said, “The newbridges, which have been designed to have alifespan of nearly 75 years, are being builtwith what is referred to as ‘weathering steel’beams. Weathering steel has been used formore than 50 years and is a great alternative,as it does not require painting. In addition,five of the seven Lindley Street spans will beeliminated. The anticipated maintenancesavings during the lifetime of the bridge is inexcess of a million dollars.”

According to the Web site, “When theLindley Street Bridge was built, the landadjacent to the Lindley Street Bridge was aparking lot for the Bridgeport MachineCompany. Closure of the parking lot would have left the sitewith virtually no parking. The state decided at that time tobuild over the parking lot instead of displacing the companythat was a significant part of the Bridgeport industrial com-munity. Unfortunately the company no longer exists on thesite so the state was able to work to secure the land beneath

the bridge to allow the elimination of the spans.”The bridges were designed by WSP/Parsons

Brinckerhoff.“The biggest challenge during the design of the project

was finding a way to reduce the impact to the traveling pub-lic,” said Adkins. “We knew that a project that did not

employ accelerated bridge constructionmethods would create long term impacts onthe public. A great example of the success ofABC is the I-84 bridge replacement projectin Southington, where the contactor replacedthe superstructures over the course of aweekend.”

The construction schedule is based on twophases — two bridges per-phase. Duringtwo short term construction windows, oneside of Route 8/25 will be closed for approx-imately two weeks. Traffic will be detouredacross the median to the opposite side of thehighway. Opposing traffic will be separatedby concrete barriers for safety. There will beminor closures of Lindley Street and CapitalAvenue during these periods to allow for therapid construction. Minor local road detourswill be used to accommodate local traffic.

The footprint of Route 8/25 will remainunchanged in the final configuration of the

new highway infrastructure.“The expressway has ample room for current traffic and

future traffic increases,” stated the Web page. “There are alsono safety concerns with the current alignment of the road-ways, so re-alignments are not required. Minor changes are

CTDOT’s Program Results in Bridge Replacement Project

Manafort Brothers Incorporated photoCTDOT noted that work will continue on the construction of PBUs in the construction area along Route 8 NB at

Exit 5 and that in early summer, thesePBUs will be transported to the LindleyStreet and Capital Avenue sites to be setin place once the existing structureshave been removed.

Manafort Brothers Incorporated photoThe Lindley Street Bridges will be reduced to two spans each by filling in five of theseven spans on each bridge.

CTDOT from page 1

see CTDOT page 14

Page 9: New England 04 2016

Construction Equipment Guide • New England States Supplement • www.constructionequipmentguide.com • February 24, 2016 • Page 9

EW Sleeper Co., Inc.391 Loudon Rd.

Concord, NH 03302391 Loudon Rd.

Concord, NH 03802603.225.3361800.358.6007

www.ewsleeper.com

391 Loudon Rd.

Concord, NH 03302

603.225.3361

800.358.6007

www.ewsleeper.com

Page 10: New England 04 2016

Page 10 • February 24, 2016 • www.constructionequipmentguide.com • New England States Supplement • Construction Equipment Guide

Go to www.acecrushers.comfor a complete listing and description of our new and used equipment.

Ace Equipment Sales, Inc. and Milroy and Company LLC171 Tolland Turnpike (Route 74) • PO Box 535 • Willington, CT 06279

(860) 429-2793 • Fax: (860) 429-0542

John Patton • (860) 614-3426

WE HAVE ALL THE PARTS YOU NEED:Manganese, Conveyor Belts, Idlers, Head Pulleys, Tail Pulleys and Much More!

Quality Service Guaranteed!

CRUSHING EQUIPMENT, PARTS & SERVICE

• Largest Screen Deck in its Class• Longer Conveyors at 16’8” Stockpile Height• Standard 14’ Wide 12 CY Hopper

ENGINE 129-horsepower CAT® C4.4 (Tier 3)HOPPER CAPACITY 12-cubic yardsSTOCKPILE HEIGHT 16-feet 8-inches

TOP DECK 22-feet by 5-feetMIDDLE DECK 22-feet by 5-feetBOTTOM DECK 20-feet by 5-feet

TS-522 TD

Page 11: New England 04 2016

Construction Equipment Guide • New England States Supplement • www.constructionequipmentguide.com • February 24, 2016 • Page 11

A P PALionville,

(

(610) 363-9200

.

(908) Frenchtown,

NJFrenchtown,

�����$�&",��*�!��-.��*)#("�!*1��

� ������������������

������",'%)��/,)+%&"�",'%)�������������������

�����",,2��*�!��)#*,���������������������

������%)��.,"".��,%�*/��������

����������

����$""+���0%-��!��*) *,!����������

���������

� � �� �

���$/)��%&"�*$)-.*)�����������

������������

������'"-� 0")/" 0*)��� ����������������

����*,.$���+'"��.,"".�*�/,)��� �������

���������

� �� � �

www.tylerequipment.com

444 d,

444 NY d,

� �� �

� �

� �� �

� �� � �

� �� � �

� � �� � �

� �� �

� �� � �

� �� � �

� � �� � �

�����,-$�''� 0"��%''%-.*)�����������

����������

Page 12: New England 04 2016

Page 12 • February 24, 2016 • www.constructionequipmentguide.com • New England States Supplement • Construction Equipment Guide

MassHighway received bids for transportation-relatedimprovement projects.

Following is a list of some of the projects let.

District: District 6Proposal Number: 001 - 605883-86121Project: Bridge replacement.Location: Bridge No. D-05-003 (precast concrete NEBTBeams) Needham Street over Great Ditch. (Dedham). Contractors and Bid Amounts:

• Northern Construction Services LLC — $2,819,836• E T & L Corporation — $2,857,658• John Rocchio Corporation — $3,025,594• SPS New England Inc. — $3,052,029• Construction Dynamics Inc. — $3,187,730• J H Lynch & Sons Inc. — $3,341,640.• Wes Construction Corporation — $3,501,173• S&R Corporation — $3,515,000• New England Infrastructure — $3,570,746

District: District 5Proposal Number: 002 - 607930-87530Project: Scheduled and emergency drainage repairs andimprovements. Location: Various locations (including Martha’sVineyard).

Contractors and Bid Amounts:• P.G. Construction Inc. — $872,469• Lal Construction Company Inc. — $1,375,825• N E L Corporation — $1,452,650

District: District 4Proposal Number: 004 - 607709-86123Project: Resurfacing and related work.Location: Along a section of Route 28 (Broadway Street).(Methuen). Contractors and Bid Amounts:

• Newport Construction Corporation — $671,451• D&R General Contracting — $687,805• J Tropeano Inc. — $771,005• Aggregate Industries NE Region Inc. — $798,364

District: District 3Proposal Number: 005 - 607660-86983Project: Painting, cleaning, structural repairs and relatedwork.Location: Seven bridges along Interstate 90. (Weston).Contractors and Bid Amounts:

• Atsalis Brothers Painting Company — $1,610,360• Prime Coatings Inc. — $1,939,525.• The Aulson Company LLC — $2,073,319• Allied Painting Inc. — $2,270,470• Southern Road & Bridge LLC — $2,272,980

District: District 4Proposal Number: 002 - 607174-86986Project: Resurfacing and related work (including 9bridges).Location: Along a Section of Route 1. (Chelsea, Malden,Revere and Saugus).Contractors and Bid Amounts:

• Aggregate Industries NE Region Inc. — $13,574,185• Newport Construction Corporation — $13,577,181• SPS New England Inc. — $13,678,562

Essex • Bristol • Franklin • Plymouth • Worcester • Middlesex • Norfolk • Dukes • Barnstable • Suffolk • Hampshire • Chilmark • Amherst •Monterey • Nantucket • Hampden • North Adams • Essex • Bristol • Franklin • Plymouth • Worcester • Middlesex • Norfolk • Dukes •Barnstable • Suffolk • Hampshire • Chilmark • Amherst • West • Monterey • Nantucket • Hampden • North Adams • Essex • Bristol • Franklin• Plymouth • Worcester • Middlesex • Norfolk • Dukes • Barnstable • Suffolk • Hampshire • Chilmark • Amherst • West • Monterey •Nantucket • Hampden • North Adams • Essex • Bristol • Franklin • Plymouth • Bristol • Franklin • Plymouth • Worcester • Middlesex

Massachusetts...

‘Bay State’ Highway Projects Let

see DOT page 16

Place Your Business Card for...

3 months $300* only $50 an issue6 months $585* only $45 an issue1212 months $1040* only $40 an issue

Call now to reserve your space! 800-225-8448* pre-payment required

200 Codman Hill Rd., Boxborough, MA 01719978-429-8666

Hydraulic Cranes 8 to 600 Ton

Daily & HourlyServices

Fully Insuredwww.astrocrane.com

EQUIPMENT DECALS

REPLACEMENT

DECAL SETS

for Construction, Forestry,

and

Industrial Equipment.

Safety Decals.

Prompt, Knowledgeable

Service. Great Prices.

We are The Heavy

Equipment Decal Experts.

Call

215-536-5339

Email: info@CustomServices

Company.com

www.QuipCal.com

LANDSCAPE EQUIPMENT

Bush Hog Z60, 60’’ Rough CutMower, s/n 22198, Good condi-tion ..................................$950.

Harter Equipment Inc.732-446-7600

Classified Rates: 30 Words or Less for $30.00. EachAdditional Word is $1.16. For just an additional $20 your adcan be posted on our online searchable database for 30 days.Ad runs for 2 (two) insertions - no changes in second insertion.

PLEASE ENCLOSE PAYMENT WITH ORDER and mail to:470 Maryland Drive• Fort Washington, PA 19034

215/885-2900 • Fax 215/885-2910Toll Free 1-800/523-2200

DISPLAY ADS/CLASSIFIEDS

DAILY AND WEEKLYEQUIPMENT RENTALS

CLOSE TO YOUR JOB SITE

CATERPILLAR®

GENIE®

CHALLENGER®

SCREEN MACHINE®

RENTMACHINES.COM

Page 13: New England 04 2016

Construction Equipment Guide • New England States Supplement • www.constructionequipmentguide.com • February 24, 2016 • Page 13

A Company

CARIBOU, ME314 Main Street

Caribou, ME 04736

CHELMSFORD, MA15 Katrina Road

Chelmsford, MA 01824

BANGOR, ME188 Perry Road

Bangor, ME 04401

WESTBROOK, ME160 Warren Avenue

Westbrook, ME 04092

CONCORD, NH237 Sheep Davis Road

Concord, NH 03301

WE PROUDLY REPRESENT THE TEREX FINLAY LINE OF AGGREGATE EQUIP-

MENT THROUGHOUT NEW ENGLAND.

PLEASE FEEL FREE TO CONTACT US FOR YOUR SALES, RENTAL, PARTS AND SERVICE (NEW AND USED) NEEDS!

CALL TODAY!

978-987-2793

Page 14: New England 04 2016

Page 14 • February 24, 2016 • www.constructionequipmentguide.com • New England States Supplement • Construction Equipment Guide

proposed for the northbound exit ramp at Lindley Street. Anadditional lane will be added to the end of the ramp to makemore room for turning vehicles onto Lindley Street. Theintersection at the Lindley Street ramp will be upgradedalong with the intersection of Lindley Street and Route 1(North Avenue).”CTDOT noted that work will continue on the construction

of PBUs in the construction area along Route 8 NB at Exit 5and that in early summer, these PBUs will be transported tothe Lindley Street and Capital Avenue sites to be set in placeonce the existing structures have been removed.Justin Gill, Manafort’s heavy highway department man-

ager, takes nothing for granted in terms of working condi-tions.“With last winter still fresh in our minds,” he said, “we

planned for the additional effort required to place PBU con-crete during the cold weather months. Fortunately, the real-ity was unseasonably warm weather for late fall and earlywinter. This allowed us to place most of the concrete in quitefavorable temps. All of the PBU concrete was placed priorto the first large snow storm of the season.”This also is CTDOT’s first design-build project and Gill is

confident that Manafort has a thorough knowledge of thework, especially the upcoming bridge reconstruction.“Construction of each stage will be limited to 14 consec-

utive calendar days for each stage,” he said. “During each14-day period, one side of the expressway will be complet-ed, including construction of two bridges and the final fillingof the spans under the Lindley Street Bridge. “Offline improvements consist of rehabilitation of an

approximately 600 foot long metalbin retaining wall and intersectionimprovements in the vicinity of theLindley Street Route 8 northboundexit ramp,” he added. “This metal binretaining wall will be rehabilitatedwith precast concrete panels and soilnails extending under Route 8 south-bound. The intersection workinvolves the widening of LindleyStreet and the Route 8/25 northboundexit ramp at Lindley Street andreplacement of the traffic control sig-nal. This work also includes opera-tional improvements at the NorthAvenue and Lindley Street intersec-tion to the east. Offline work shall becompleted prior to the construction ofthe Route 8/25 bridges in order tofacilitate maintenance of traffic.”The final construction stage

involves a full width of asphalt over-lay for the entire length of the project— approximately 1,600 ft. (487.68m). The work will see the removal of

15,000 cu. yds. (11,468 cu m) ofexcavation; 60,000 cu. yds. (45,873cu m) of material fill, structural back-fill and road base; and 4,000 cu. yds. (3,058 cu m) of light-weight fill. This is bolstered by 6,000 cu. yds. (4,587 cu m)of structural concrete, 950,000 lbs. (430,912 kg) of rebar,150,000 lbs. (68,039 kg) of miscellaneous metals, 1 million

lbs. (453,592 kg) of structural steel and 14,000 tons (12,700t) of asphalt.On a daily basis there are between 35 to 45 people on site

doing regular extended shifts and second shifts, and with

two-week closure period this sum-mer, crews will be working round-the-clock. The key subcontractors areHartland Building and Restoration;Santoro, Inc.; A&J Paving; DucciElectrical Contractors; andUnderground Builders.Equipment being used includes

Volvo 360, Volvo 480, JD 450, JD750 excavators with demolitionattachments; Cat D4, Cat D6, JD 550bulldozers; Schwing 42M, Schwing32M concrete pump trucks; GroveRT600 hydraulic cranes; and earthmoving equipment such as Bobcat550 skid steers and Ingersoll RandSD50 and SD100 small rollers thatwere required to place fill under theexisting bridge structures. Manafort will rent self-propelled

modular transporters (SPMTs) tomove the PBUs on site. Thesemachines will be rented from MarinoCrane of Middletown, Mass. Largehydraulic cranes will be rented tohoist and set the heavy PBU sections.For these picks Manafort also will

rent the cranes from Marino Crane.(This story also can be found on Construction

Equipment Guide’s Web site at www.constructionequip-mentguide.com.) CEG

CTDOT’s Route 8/25 Project Reaches Half-Way Point

Manafort Brothers Incorporated photoThe four bridges being rehabilitated carry an average of 88,000 cars over Capital Avenue, Lindley Street and a

large parking lot.

Manafort Brothers Incorporated photoThe bridges will be demolished and rebuilt in a different configuration using accelerated bridgeconstruction techniques.

CTDOT from page 8

Page 15: New England 04 2016

Construction Equipment Guide • New England States Supplement • www.constructionequipmentguide.com • February 24, 2016 • Page 15

CHADWICK-BAROSS15 Katrina Road

Chelmsford, Massachusetts

Call Dan Rott1-978-479-5192

www.chadwick-baross.com

www.cbused.com

A STRONGCO Company

1-800-53-CRUSH

Call for Instock Parts

284 North StreetWindsor Locks, CT 06096

51 Veterans DriveLoudon, NH 03307

1-800-53-CRUSH or 860-627-6596www.powerscreen-ne.com

Page 16: New England 04 2016

Page 16 • February 24, 2016 • www.constructionequipmentguide.com • New England States Supplement • Construction Equipment Guide

By Wilson RingASSoCIATED PRESS

GREENSBoRo, Vt. (AP) In thesnowy woods of northern NewEngland and other forested parts of thecountry, the lumberjack is an endan-gered species.

As markets for forest productschange and high-tech machineryreplaces chain saws, which themselvesreplaced the ax, a generations-old wayof life is disappearing, one that histori-cally saw fathers pass on to their sonstheir love and knowledge of the woodsand the independence that came fromworking for oneself.

Ken Davis feels this keenly as hereaches retirement age after a half-cen-tury career with no one to pass thetorch to.

Davis once employed 19 peoplefull-time to cut the wood, haul it andthen truck it, sometimes to his log yard,other times directly to the now-disap-pearing mills across Vermont, New

Hampshire, Maine and upstate NewYork that would turn it into lumber orprocess it into paper. He now employsseven, and has no sons. His daughterand son-in-law tried it for a while, butthey didn’t keep at it.

“I’ve got the sawdust in my veins,and they don’t make a dialysismachine to get it out, so I’m still here,”Davis said recently at his log yard inthe town of Hardwick, in an especiallyrural region Vermonters call theNortheast Kingdom.

None of Davis’ employees areshowing interest in taking over hisbusiness. It’s the same story across theregion, said Michael Snyder, commis-sioner of the Vermont Department ofForest, Parks and Recreation.

“It’s dangerous, it’s hard to make aliving and everybody hates you,”Snyder said of logging. “Who’s sign-ing up for that?”

The arguments for not becoming alogger are solid.

For one, there’s just not as much

demand for paper and other woodproducts because of low commodityprices and international competition,making it less secure than it once was.It’s physically and — yes — intellectu-ally demanding work that increasinglyrequires special skills to run hugelyexpensive, high-tech machinery. Andbecause of that machinery, capitalinvestment needed to get started can beprohibitive.

The renaissance that farming hasundergone in recent years, with anemphasis on food systems and sustain-able agriculture, hasn’t brought thesame energy to logging. In many quar-ters, loggers are still seen as despoilersof the land. But Snyder noted thatwhile forests can do just fine on theirown, logging can support their healthby weeding out infestations and inva-sive species.

Logging entails a number of jobs,including fallers, who cut down treesby hand — essentially, lumberjacks;

High-Tech Machinery, Less Demand PutLumberjacks on Endangered Species List

see LOGGING page 18

District: District 6

Proposal Number: 003 - 606773-88277Project: Clean, paint and concrete- joint and steel repairs.Location: Everett and Market Street Bridges — BridgeNos. (B-16-058 and B-16-059) both over Interstate 90-MBTA Railroad and adjacent streets. (Boston).

Contractors and Bid Amounts:

• N E L Corporation — $2,949,853• Prime Coatings Inc. — $5,412,203

District: District 4

Proposal Number: 004 - 607964-88711Project: Scheduled and emergency guardrail repairs andimprovements.Location: Various locations.

Contractors and Bid Amounts:

• Delucca Fence Company Inc. — $729,340• Premier Fence LLC — $729,849

District: District 2

Proposal Number: 001 - 607001-88111Project: Storm water improvements.

Location: At four locations along a section of Interstate 91and Routes 2 to 5 and 20. (Longmeadow, Springfield,Templeton and Westfield).

Contractors and Bid Amounts:

• A Pereira Construction Company Inc. — $798,195• Ludlow Construction Company Inc. — $809,470• JBL Construction Company Inc. — $873,485• Northern Construction Services LLC — $897,852• UEL Contractors Inc. — $963,080• Caracas Construction Corporation — $1,110,510• C & A Construction Company — $1,183,927

District: District 6

Proposal Number: 002 - 606997-88523Project: Storm water improvements.Location: Various locations along sections of Interstate 93and Routes 3 and 18. (Boston, Braintree, Milton andWeymouth).

Contractors and Bid Amounts:

• Newport Construction Corporation — $1,125,939• McCourt Construction Company Inc. — $1,374,745• MDR Construction Company Inc. — $1,399,427• A A Will Corporation — $1,488,407

District: District 5

Proposal Number: 002 - 607896-88793Project: Scheduled and emergency bridge shielding.Location: Various locations (excluding Martha’s Vineyardand Nantucket).

Contractors and Bid Amounts:

• N E L Corporation — $753,600• Aetna Bridge Company — $845,548.• SPS New England Inc. — $964,650

District: District 5

Proposal Number: 005 - 607934-88632Project: Scheduled and emergency bridge structuralrepairs.Location: Various locations.

Contractors and Bid Amounts:

• SPS New England Inc. — $4,960,474• N E L Corporation — $5,406,330• Aetna Bridge Company — $5,876,215• Mig Corporation — $6,557,961• S&R Corporation — $7,201,575

Essex • Bristol • Franklin • Plymouth • Worcester • Middlesex • Norfolk • Dukes • Barnstable • Suffolk • Hampshire • Chilmark • Amherst •Monterey • Nantucket • Hampden • North Adams • Essex • Bristol • Franklin • Plymouth • Worcester • Middlesex • Norfolk • Dukes •Barnstable • Suffolk • Hampshire • Chilmark • Amherst • West • Monterey • Nantucket • Hampden • North Adams • Essex • Bristol • Franklin• Plymouth • Worcester • Middlesex • Norfolk • Dukes • Barnstable • Suffolk • Hampshire • Chilmark • Amherst • West • Monterey •Nantucket • Hampden • North Adams • Essex • Bristol • Franklin • Plymouth • Bristol • Franklin • Plymouth • Worcester • Middlesex

Massachusetts...

‘Bay State’ Highway Projects LetDOT from page 12

2012 CAT 980K, 3800hrs, GP Bucket (7.8 yd), 90% L-5 Tires, LightPackage, Power/Heated Mirrors, Axle Cooler Option, Auto-Shift, RideControl ........................................................................................CALL2012 CAT 966K, 3780 hrs, GP Bucket w/Edge, Ride Control, Light Package, New L-3 Radial Tires....................................$255,0002003 CAT 966G II, GP Bucket w/ Teeth, 70% Tires, New Paint, 3rd Valve option, Ride Control....................................................SOLD2008 CAT D8T Waste Handler, Factory Spec, New CAT U/C ..........................................................................................................$255,000

208 Holland RoadBrimfield, MA 01010

Sales Contact: R.J. [email protected]

413-245-3882Fax: 413-245-3522

www.rjpoirier.com

Repair Services:Complete Machine Rebuilding, Engine,

Transmission, Undercarriage, Bucket Rebuilding,Computer Diagnostics, Software Enhancements,Hydraulic Cylinder Repair, Custom Products.

2011 CAT 972K,3300 Hrs, GP Bucketw/Edge, RideControl, LightPackage, 85% Tires..........................CALL

Page 17: New England 04 2016

Construction Equipment Guide • New England States Supplement • www.constructionequipmentguide.com • February 24, 2016 • Page 17

Chappell Tractor Sales, Inc.

454 Route 13 SouthMilford, NH 03055800/698-2640

www.chappelltractor.com

Chappell Tractor East, LLC

251 Route 125Brentwood, NH 03833

800/616-5666www.chappelltractor.com

Kahn Tractor & Equipment, Inc.

520 Pond RoadNorth Franklin, CT 06254

860/642-7596www.kahntractor.com

Lorusso Heavy Equipment, LLC160 Elm StreetP.O. Box 857

Walpole, MA 02801508/660-7600

www.lhequip.com

Page 18: New England 04 2016

Page 18 • February 24, 2016 • www.constructionequipmentguide.com • New England States Supplement • Construction Equipment Guide

operators of machinery used to fell trees;and graders and scalers, who check theamount and quality of the wood. The num-ber of all logging workers is expected to fallonly 4 percent from 2014 to 2024, from53,700 to 51,700, according to Bureau ofLabor projections.

Nationwide, the number of fallers is pro-jected to decline 17 percent over the sameperiod, from 8,200 in 2014 to 6,800 in 2024.

With the industry becoming more mecha-nized, the number of equipment operators isexpected to stay about the same, withgraders and scalers declining 2 percent andall other logging workers falling 7 percent.

“Today you are running a half-million,$600,000 machine, and not only do youneed to operate it, you’ve got to read GPSand computer-based technology equipment,you’ve got to be able to service and maintainthat equipment, you have to know forestry,environmental law, best management prac-tices, tree identification,” said Dana Doran,executive director of the ProfessionalLogging Contractors of Maine.

Across the region, efforts are under wayto bring along young loggers. The VermontTechnical College in Randolph helps trainforest technicians. In Maine, the industry isbacking a plan to train logging technicians incommunity colleges.

In the Northeast Kingdom, one of Davis’workers, 31-year-old Aaron Martin, said helikes the freedom of working outside in dif-ferent places. He has been logging for 10years, but few of his friends have beendrawn to the life, he said: “They don’t likebeing out in the cold.”

But as much as he likes his work, he hasno interest in being the boss.

“With that comes its own headaches,” hesaid. “It’s nice to be able to work for some-body else and not deal with all the stress thatcomes with paying all the bills and every-thing that goes with it, finding the next job.

“I just go to work and do what I’m told.It’s a lot simpler that way.”

(This story also can be found onConstruction Equipment Guide’s Website at www.constructionequipment-guide.com.)

Waving Goodbye to a Piece ofAmericana: The Lumberjack

AP/Wilson Ring photoIn this Jan. 20, 2016, photo, logs destined for a mill are unloaded at a satellite woodyard in Harwick, Vt. The owner of the yard, Ken Davis, said he isn’t sure what he’lldo with his business when he retires because none of his employees want to take itover. Experts said it’s a problem across the Northeast as loggers age and feweryoung people take it up.

LOGGING from page 16

NEW ENGLAND SUPPLEMENTADVERTISER INDEX

The Advertisers Index is printed as a free editorial service to ouradvertisers and readership. Construction Equipment Guide is not

responsible for errors or omissions.

ACE EQUIPMENT SALES INC ......................................10

ARGUS INDUSTRIAL COMPANY ....................................1

ASTRO CRANE ..............................................................12

BULLETIN BOARD..........................................................12

CHADWICK BAROSS MA ........................................13,15

CLASSIFIED....................................................................12

E W SLEEPER CO............................................................9

EQUIPMENT EAST........................................................1,7

FOLEY MARINE & INDUSTRIAL ENGINE ......................1

GORILLA HAMMERS........................................................1

HYUNDAI CONSTRUCTION EQUIPMENT....................17

J R VINAGRO CORPORATION........................................1

LORUSSO HEAVY EQUIPMENT LLC..............................5

M G EQUIPMENT ............................................................1

MILTON CAT....................................................................12

NORTHLAND JCB ..........................................................13

POWERSCREEN NEW ENGLAND................................15

R J POIRIER HEAVY EQUIPMENT REP ......................16

ROGERS BROTHERS ....................................................19

SDLG DEALER GROUP ................................................11

SUMMIT SUPPLY LLC/MULTI MACHINE ........................1

THE N.I.C.E. COMPANY ..................................................6

THE W I CLARK CO ........................................................2

TYLER EQUIPMENT CO ..................................................3

WOODCO MACHINERY ................................................20

Page 19: New England 04 2016

Construction Equipment Guide • New England States Supplement • www.constructionequipmentguide.com • February 24, 2016 • Page 19

Tyler Equipment251 Shaker Road

East Longmeadow, MA 01028(413) 525-6351(800) 292-6351

Parts: (877) 255-6351

1980 Berlin TurnpikeBerlin, CT 06037(860) 356-0840(800) 352-4473

Parts: (860) 356-0848

www.tylerequipment.com

C.N. Wood Co., Inc.200 Merrimac St.

Woburn, MA 01801(781) 935-1919

Avon, MA (508) 584-8484

Johnston, RI(401) 942-9191

www.cn-wood.com

Page 20: New England 04 2016

Page 20 • February 24, 2016 • www.constructionequipmentguide.com • New England States Supplement • Construction Equipment Guide

Some companies have you choose power or fuel efficiency. You chose both.

DEALER LOGO

Contact your localdealer:

Dealer Name

T, SCity123.456.7890

T, SCity123.456.7890

T, SCity123.456.7890

T, SCity123.456.7890

T, SCity123.456.7890

T, SCity123.456.7890

T, SCity123.456.7890

T, SCity123.456.7890

T, SCity123.456.7890

eloped the industrvo deolvVVolv

st fuel efficiency guary’s fireloped the industr

ever ha avvantee so you nest fuel efficiency guar

e

ALERDELOGO

omise on perto comprmonitoring, you can f

owing your business. Get the details at gr

And with Car. oductivitye or prormancfomise on pere imporocus your attention on mormonitoring, you can f

owing your business. Get the details at ocolvv

ack machinereTTrAnd with Caretant things — like impor

tfuelom/smare.coc .

Contact your local dealer:

WoodCo MaChinery

140 Wales AvenueAvon, MA 02322508.584.8484

22 North Maple StreetWoburn, MA 01801781.935.3377

60 Shun PikeJohnson, RI 02919401.942.9191

www.woodcomachinery.com