Neutrino target station at JPARC Contents Introduction Radiation (detail: talked by Oyama) Support...
-
Upload
bennett-jacob-park -
Category
Documents
-
view
222 -
download
1
Transcript of Neutrino target station at JPARC Contents Introduction Radiation (detail: talked by Oyama) Support...
Neutrino target station at JPARC
Contents•Introduction •Radiation (detail: talked by Oyama)•Support system & maintenance •Cooling system•Schedule
Yoshikazu Yamada (KEK)Y.Hayato, E.Hirose, A.K.Ichikawa, T.Iwashita,
T.Kobayashi, S.Koike, T.Miura, H.Nakano, Y.Oyama, N.Sato, T.Suzuki, Y.Yamanoi
4th International Workshop on the Neutrino Beams and Instrumentation
November 11, 2003
1st Horn 2nd Horn 3rd Horn
Fast-extracted proton beam line
Neutrino beam line and target
Target Station
Decay volume
Beamdump
50GeV PS
Target•Carbon target: 30mm-,900mm-L•beam size: σr ~6mm
beam to SK
0.75MW beam
Neutrino target station22m
Iron shield
Helium container
Machine room
Service pit
Storage for radioactive material
11m
33m
Iron shield
Concrete blocks
40 ton crane
Target & 1st horn
Beam window
2nd horn 3rd horn
Final focus
Decay volume
Concrete shield
Beam window
Ground level
Baffle
22m
Iron:2.2m
concrete wall : 20cm-t
Iron:1.5mIron
:1.5
m
Concrete:4.4m
Concrete:1m
< 12.5Sv/h@floor of surface building
< 0.25
Sv/h
@ou
t of the con
trol areafence
Concrete: 4.5m
Con
crete:3.6m
Shielding and radiation level
< 5mSv/h@boundary of concrete
0.75MW operation
detail Oyama’s talk
confirmed by MARS
Residual dose
Aluminum wall ~0.65(0.17) Sv/h
Upper iron shieldOuter : 22(16) Sv/hInner : 0.56(0.42) Sv/h
Floor of service pit~0.1(0.07) μSv/h Service pit
Machine room
One (seven) day cooling after one year operation
(by MARS)
detail Oyama’s talk
Side view of target area
Baffle
Target+1st horn 2nd horn
3rd horn
Iron shield
Concrete shield
Iron shield
Concreteshield
Service pitBus bar
Aluminum wall
Bus bar Bus bar
Win
dow
Helium container
Support of hornCollimator
for DV
15m
2.2m
1m
Front view of target area
1st horn
Iron shield
Concrete shield
Iron shield
Concrete shield block
Service pit
Transformer
Aluminum wall
Bus bar
Helium container
Support of horn
Concrete shield block
Area for ad
dition
al sh
ields for 4M
W
storage for radioactive
material
Underground machine room
3m6m
1st horn
Iron shield
Iron shield
Bus bar
Helium container
Concrete shield block
Helium container•3m(W)6m(H)15m(L), 5cm-thick iron wall •Filled by Helium gas (1-atm, 130m3, ~99%) •Reduce Tritium production : ~1/25?
• ~30mb for Air, ~1.2mb for He
•Tritium production after 200 days operation:
Air:800Bq/cm3, He:30Bq/cm3
•Ventilation time after 200 days operation
Air:110days, He:5days
(ventilation: 8000m3/hour, regulation:5mBq/cm3)
•Reduce corrosion by NOx : ~1/100?•20cm thick Aluminum wall in target area
reduce surface dose by ~1/10 at maintenance
Support system of horn
Support of horn
Iron shield
Concrete shield
support alignment
support hear
Exchange of the target/ horn
storage of radioactive materials
top view
Cross-sectional view
•Upper Iron and concrete shields are removed.
•Highly radioactivated target/horn are moved under ground-level and kept in the storage of radioactive materials for several years.•New target/horn are installed and shields are installed.•All works should be done remotely.
Ground level
Exchange of the target
A) If horn is broken, scrap target and horn.B) If target is broken;
1) Scrap target and horn. or2) Replace broken target with new one in the horn
i) at the storage for radioactive material. orii) at the beam line.
All works should
be done remotely.
Heat load : ~170 kW on Aluminum, 40kW on Iron
Heat load on Al-wall/Fe-shield
En
ergy
dep
osit
(W
/m)
Aluminum
Fe(1st 20cm)
Fe(2nd 20cm)
Iron shield
Iron shield
Concrete shieldMARS
Water pipe for Aluminum wall
(option for 4MW)
Cooling for Aluminum wall
Temperature rise in Al wall QAl=17/8(kW/m),L= 3/2(m),
A l =240(W/mK), A=0.2(m2)
)(332/
KA
LQT
Al
Al
Iron shield
Iron shield
Concrete shield
Water flow =170(kJ/s)/4.2(J/g/K)/10(K)/8
=30(Litter/min.)(8)
1-inch tubeRe=32000, k=4860(W/m2K),
T=3.7(K) 、 P=0.11(kg/cm2)
Radio activity of water Oyama’s talk
Air cooling surface for iron shieldOuter surface (Default)Middle surface (Option for 4MW)Inner surface (Option for 4MW)
Cooling for Iron shieldWater pipe for upper iron shield
Iron(1m-t)
heat at rI
cooled at rO
)(27)(2.21)(5.5
2ln
2
KKK
kr
Q
r
rQT
OO
Fe
I
O
Fe
FeO
Temperature rise in iron shield QFe=4(kW/m), Fe=80(W/mK),
rI =1.5(m),rO =3.0(m), kO=10(W/m2K)
Iron shield (Duratec?)
Iron shield
Concrete shield
Concrete shield
Air flow: 40000(J/s)/1.0(J/g/K)/10(K) =200(m3/min)Radio activity of air Oyama’s talk
Cooling system for Al wall
150kW
1.15m3
170kW 0.06m3
32C360 litter/min
Buffer tank
32C
Chiller
50kW
Chiller
50kW
Spare chiller50kW
Underground machine room
(TP+2.7m)
Underground machine room for beam dump
(TP?m)Final focus Section(TP-1.7m)
Machine building for beam dump
(TP?m)Primary cooling systemfor Decay volume(Target side)
Primary cooling systemfor Decay volume(Dump side)
Buffer tank
Pump
Pump
Decay volume
Primary cooling water linefor magnet(FF section)
Magnet DP tank
Disposalline
Water
Disposal line
800m3/20days
30C540 litter/min
35C
30C3000 litter/min
80C
30C
32C360 litter/min
35C
35C
32C
23C120 litter/min
30C480 litter/min
Primary cooling systemfor Aluminum wall andupper/collimator ironshield
35C
45C 240 litter/min
for target
for 1st horn
20kW0.1m3
30 litter/min
10kW0.2m3
30litter/min
10kW0.2m3
30litter/min
10kW0.2m3
30litter/min
30 litter/min
30 litter/min
30 litter/min
60 litter/min
150 litter/min
Buffer tank
240 litter/min
Pump
Chiller
50kW
Chiller
50kW
Spare chiller50kW
Underground machine room
(TP+2.7m)Surface building of target station(TP+10.8m)
2nd machine building
(TP+9.3m)
cooling system for target/horn
Third water cooling system Primary water cooling system
Secondary water cooling system
for 2nd horn
for 3rd horn
water line
Secondary
Disposal to buffer
tank for DV
Pumps
Filters for radioactivity
Degassing system
Water
Buffer tank
Underground machine pit
(TP+2.7m)
Service pit
(TP+2.7m)
Target area
(TP-1.7m)
Target20kw1 litter
Primary cooling system for target
30litter/min.
in experiment
in maintenance
Circulation in experiment
Always ventilating
Ventilation inmaintenance
StackHEPAfilter
Filter for salt
Cooling unit
Fresh air
Air circulation/ventilation system
Circulation in experiment
Building
Underground machine room
Iron shieldcooling
Inside double-door
FY2003 FY2004 FY2005 FY2006 FY2007 FY2008
Support for target and horns
Conceptual design
Basic prototype
Design Prototype Production Installation
Helium container Conceptual design
Basic prototype
Design Prototype Production Installation
Mockup
Remote maintenance
Conceptual design
Basic prototype
Design Prototype Production Installation
Cooling Conceptual design
Prototype Design Production Installation
Shield Conceptual design
Prototype Design Production Installation
Building Conceptual design
Design Construction
ScheduleBudget for TS(our hope)
Summary
•Conceptual design of Target Station finish soon.•Building•Shielding•Cooling•Support •Maintenance
•Realistic design, R&D work and prototyping will start.•Construction will start in 2006 and end in 2008
if budget is approved.
Backup
10-410-310-210-1100 101 102 103 104 10510-3
10-2
10-1
100
101
102
103
104
AL
Fe
After one year irradiation
Time (Hour)
Eff
ecti
ve
Do
se (
mS
v/h
)
Na-24
Na-22
Effect of Aluminum wall
Aluminum wall reduces surface dose by ~1/10 at maintenance.Cost vs Performance should be studied.
After one year irradiation
1day 100 days
Time after irradiation (hour)
~100mSv/h
Dos
e at
tar
get
area
(m
Sv/
h)
Aluminum
Iron
Secondary cooling water system
Third cooling water system
Primary cooling water system
Heat exchange
To 2nd machine building
Cooling system for Target/Horn
water line
Secondary
Disposal to buffer
tank for DV
Pumps
Filters for radioactivity
Degassing system
Water
Buffer tank
Underground machine pit
(TP+2.7m)
Service pit
(TP+2.7m)
Target area
(TP-1.7m)
1st horn10kw200 litter
Primary cooling system for horn
30litter/min.
in experiment
in maintenance
Very rough cost estimation
•Building: ~4.3M$(Underground) + ~0.8M$(Surface)•Crane: ~0.5M$•Concrete shield blocks: 1600m3~300$/m3 = ~0.5M$•Iron shield blocks: 4000ton(200~300)$/ton = 0.8~1.2M$•Helium container: 160ton~1000$/ton~2? = 0.3M$?•Aluminum wall: 120ton~3000$/ton~2? = 0.7M$?•Support system of horn: ~0.1M$?4 = ~0.4M$?•Air cooling & ventilating system: ?•Water cooling system: ?
•1M$ ~ 1108 Yen•Excluding horns and target
Service pit(230m3)Machine room(140m3)Keep out in experiment•In experiment:circulation•In maintenance:ventilation
Control of airBuilding (8300m3):•Ventilation through stack
Helium container:Keep out forever•Circulation of Helium
Stock room for radioactive partsKeep out forever•In experiment :circulation•In maintenance:ventilation
Area for rem
oved
shield
s
Area for entrance control
Operation room for maintenance
Area for spare horns
Storage for radioactive material
Traile
r
Underground machine room
33m
22m
Top view of target station
beam
Underground machine room
•ターゲット一次冷却水( 0.01m3,28kBq/cc )のポンプ+タンク、熱交換器 (~30kW) 、二次冷却水のポンプ+タンク
•ホーン一次冷却水( 0.6m3,5kBq/cc )のポンプ+タンク、熱交換器 (~30kW) 、二次冷却水のポンプ+タンク
•鉄シールド+アルミヘリウム箱一次冷却水(数 m3?, 数 kBq/cc? )のポンプ+タンク、熱交換器 (~200kW)(二次系は FF 部と共通)
•ディケイボリューム一次冷却水( 3m3, 数 kBq/cc )のポンプ+タンク、熱交換器 (~200kW)(二次系は FF 部と共通)
排水は地下機械室よりディケイボリュームを通って下流の DP タンクへ
放射化物保管庫
地下機械室
FF 部DV
空気・ヘリウムの放射化
場所Neutron fluence
(/p/cm2)
放射化(Bq/cc)
容量(m3)
トリチウム (Bq)
排気時間(h)
上屋 110-19 410-14 8000 0.3 1
サービスピット 510-12 210-6 230 5105 0.03
地下機械室 510-12 210-6 330 7105 0.04
放射化物保管庫 510-12 210-6 780 1.6106 0.1
鉄シールド外面 110-10 410-5 38 1.5106 0.005
鉄シールド中間 110-8 410-3 33 1.3108 0.004
鉄シールド内面 210-5 8 28 2.21011 5.6
TS ヘリウム 210-4 80? 135 1.11013? 270?
DV ヘリウム 510-5 20? 1600 3.11013? 800?
0.75MW20 日運転後(反応断面積 30mb )排気基準: 5mBq/cc 以下
ヘリウムの断面積は 1.2mb ?( 1/25 ?)
Neutrino target
Graphite rod•diameter:30mm, Length:900mm (80% interaction)•beam size: σr ~6mm
•fixed inside 1st horn•20kw heat load: cooled by water
Hayato’s talk tomorrow
1st Horn 2nd Horn3rd HornTarget
0.75MW beam
鉄シールドブロック
2mX1.5mX1m (23 トン) 36 個= 810 トン
3mX1.5mX1m (34 トン) 72 個= 2430 トン
2.2mX2.2mX1m (36 トン) 18 個= 650 トン
合計3900トン平成 18 年度製造、 19 年度据付
冷却面(水冷又は空冷、250k W )
水冷の場合、冷却管取付けIron shield