NETA_ATS-1999

220
Acceptance Testing Specifications for Electric Power Distribution Equipment and Systems These specifications have been developed These specifications have been developed by the InterNational Electrical Testing Association for use by

description

INTERNATIONAL ELECTRICALE TESTING ASS.

Transcript of NETA_ATS-1999

Page 1: NETA_ATS-1999

Acceptance Testing Specifications for

Electric Power Distribution Equipment and Systems

�These specifications have been developed

These specifications have been developed by the

InterNational Electrical Testing Association for use by

Page 2: NETA_ATS-1999

electrical power distribution system engineers.

�©Copyright 1999 InterNational Electrical Testing Association

PO Box 687 • 106 Stone Street • Morrison, CO 80465 303.697.8441 • Fax: 303.697.8431

E-mail: [email protected] • Web site: www.netaworld.org

Page 3: NETA_ATS-1999

NETA Standards Review Council

These specifications were submitted for public comment and reviewed by the NETA Standards Review Council.

Charles K. Blizard Roderic L. Hageman

Diane W. Johnson Mary R. Jordan

Mark Lautenschlager Alan D. Peterson

NOTICE

In no event shall the InterNational Electrical Testing Association be liable to anyone for special, collateral, incidental, or consequential damages in connection with or arising out of the use of these materials.

This document is subject to periodic review, and users are cautioned to obtain the latest edition. Comments and suggestions are invited from all users for consideration by the Association in connection with such review. Any such suggestions will be fully reviewed by the Association after giving the commenter, upon request, a reasonable opportunity to be heard.

This document should not be confused with federal, state, or municipal specifications or regulations, insurance requirements, or national safety codes. While the Association recommends reference to or use of this document by government agencies and others, use of this document is purely voluntary and not binding.

InterNational Electrical Testing Association PO Box 687 • 106 Stone Street • Morrison, CO 80465

303.697.8441 FAX:303.697.8431 E-mail: [email protected] • Web Site: www.netaworld.org

Mary R. Jordan, EdD - Executive Director

Page 4: NETA_ATS-1999

PREFACE

The purpose of these specifications is to assure that all tested electrical equipment and systems supplied by either contractor or owner are operational and within applicable standards and manufacturer’s tolerances and that equipment and systems are installed in accordance with design specifications.

The need for acceptance testing of electrical power systems is very clear to those with extensive startup and/or operating experience. Shipping and installation damage, field and factory wiring errors, manufacturing defects, and systems and components not in accordance with drawings and specifications are some of the many problems that can be detected by appropriate testing. When these defects are found before startup they can be corrected under warranty and without the safety hazards and possible equipment and consequential damages of loss of use/production that can occur if discovered after startup or energizing. In addition, test results obtained during acceptance testing are invaluable as base reference data for the periodic testing that is an essential element of an effective maintenance program.

It is the intent of this document to list a majority of the field tests available for assessing the suitability for service and reliability of the power distribution system. Certain tests have been assigned an “optional” classification. The following considerations were used in determining the use of the “optional” classification:

1. Did another test listed provide similar information?

2. How did the cost of the test compare to the cost of other tests providing similar information?

3. How commonplace was the test procedure? Is it new technology?

While acknowledging the above, it is still necessary to make an informed judgment for each particular system regarding how extensive the testing should be. The approach taken in these specifications is to present a comprehensive series of tests that is applicable to most industrial and larger commercial systems. The guidance of an experienced testing professional should be sought when making decisions such as how extensive testing should be. In smaller systems some of the tests can be deleted. In other cases, a number of the tests indicated as optional should be performed.

As a further note, it is important to follow the recommendations contained in the manufacturer’s instruction manuals. Many of the details of a complete and effective acceptance testing procedure can only be obtained from that source.

The Association encourages comment from users of this document. Please contact the NETA office at 303.697.8441 or your local NETA member firm.

Alan D. Peterson NETA Technical Chair

ATS – 1999

Page 5: NETA_ATS-1999

CONTENTS

ELECTRICAL ACCEPTANCE TESTS 1. GENERAL SCOPE, ACCEPTANCE TESTING SPECIFICATIONS .......................................1 2. APPLICABLE REFERENCES ................................................................................................2 3. QUALIFICATIONS OF TESTING ORGANIZATION AND PERSONNEL................................7 4. DIVISION OF RESPONSIBILITY ...........................................................................................8 5. GENERAL ..............................................................................................................................9

5.1 Safety and Precautions ...................................................................................................9 5.2 Suitability of Test Equipment...........................................................................................9 5.3 Test Instrument Calibration ...........................................................................................10 5.4 Test Report ...................................................................................................................11

6. POWER SYSTEM STUDIES................................................................................................12 6.1 Short-Circuit and Coordination Studies .........................................................................12 6.2 Load Flow Studies - Reserved ......................................................................................14 6.3 Stability Studies - Reserved ..........................................................................................14 6.4 Switching Transients Studies - Reserved......................................................................14 6.5 Motor Starting Studies - Reserved ................................................................................14 6.6 Harmonic Analysis - Reserved......................................................................................14 6.7 Ground Mat Studies - Reserved....................................................................................14 6.8 Cable Ampacity Studies - Reserved..............................................................................14 6.9 Reliability Studies – Reserved.......................................................................................14

7. INSPECTION AND TEST PROCEDURES...........................................................................15 7.1 Switchgear and Switchboard Assemblies .....................................................................15 7.2 Transformers.................................................................................................................20

1. Dry-Type................................................................................................................20 1. Air-Cooled, 600 Volt and Below - Small (167 kVA Single-Phase, 500 kVA Three-Phase, and Smaller).......................20 2. Air-Cooled, All Above 600 Volt and 600 Volt and Below - Large (Greater than 167 kVA Single-Phase and 500 kVA Three-Phase).................23

2. Liquid-Filled ...........................................................................................................27 7.3 Cables...........................................................................................................................32

1. Low-Voltage, Low-Energy - Reserved ...................................................................32 2. Low-Voltage, 600 Volt Maximum ...........................................................................32 3. Medium-Voltage, 69 kV Maximum.........................................................................34 4. High-Voltage..........................................................................................................38

7.4 Metal-Enclosed Busways ..............................................................................................42 7.5 Switches........................................................................................................................44

1. Air Switches...........................................................................................................44 1. Low-Voltage ...................................................................................................44 2. Medium-Voltage, Metal-Enclosed ..................................................................47 3. High- and Medium-Voltage, Open..................................................................50

2. Oil Switches: Medium-Voltage...............................................................................52 3. Vacuum Switches: Medium Voltage ......................................................................55

ATS – 1999

Page 6: NETA_ATS-1999

4. SF6 Switches: Medium-Voltage - Reserved...........................................................57 5. Cutouts - Reserved ........................................................................................57

7.6 Circuit Breakers.............................................................................................................58 1. Low-Voltage...........................................................................................................58

1. Insulated Case/Molded Case .........................................................................58 2. Power.............................................................................................................61

2. Medium-Voltage ....................................................................................................64 1. Air...................................................................................................................64 2. Oil...................................................................................................................67 3. Vacuum..........................................................................................................71 4. SF6 .................................................................................................................75

3. High-Voltage..........................................................................................................79 1. Oil...................................................................................................................79 2. SF6 .................................................................................................................83

4. Extra-High-Voltage ................................................................................................87 1. SF6 .................................................................................................................87

7.7 Circuit Switchers ...........................................................................................................91 7.8 Network Protectors, 600 Volt Class...............................................................................93 7.9 Protective Relays ..........................................................................................................96 7.10 Instrument Transformers.............................................................................................104 7.11 Metering ......................................................................................................................107 7.12 Regulating Apparatus..................................................................................................108

1. Voltage ................................................................................................................108 1. Step-Voltage Regulators ..............................................................................108 2. Induction Regulators ....................................................................................113

2. Current - Reserved ..............................................................................................116 3. Load-Tap Changers.............................................................................................117

7.13 Grounding Systems.....................................................................................................120 7.14 Ground-Fault Protection Systems ...............................................................................121 7.15 Rotating Machinery .....................................................................................................124

1. Motors..................................................................................................................124 1. AC Motors ....................................................................................................124 2. DC Motors....................................................................................................130

2. Generators...........................................................................................................133 1. AC Generators .............................................................................................133 2. DC Generators .............................................................................................138

7.16 Motor Control ..............................................................................................................141 1. Motor Starters......................................................................................................141

1. Low-Voltage .................................................................................................141 2. Medium-Voltage ...........................................................................................144

2. Motor Control Centers .........................................................................................148 1. Low-Voltage .................................................................................................148 2. Medium-Voltage ...........................................................................................148

7.17 Adjustable Speed Drive Systems................................................................................149 7.18 Direct-Current Systems...............................................................................................152

1. Batteries ..............................................................................................................152 2. Battery Chargers .................................................................................................156

ATS – 1999

Page 7: NETA_ATS-1999

3. Rectifiers - Reserved ...........................................................................................157 7.19 Surge Arresters ...........................................................................................................158

1. Low-Voltage Surge Protection Devices ...............................................................158 2. Medium- and High-Voltage Surge Protection Devices.........................................160

7.20 Capacitors and Reactors.............................................................................................162 1. Capacitors ...........................................................................................................162 2. Capacitor Control Devices - Reserved.................................................................163 3. Reactors (Shunt and Current Limiting) ................................................................164

1. Dry-Type ......................................................................................................164 2. Liquid-Filled..................................................................................................166

7.21 Outdoor Bus Structures...............................................................................................170 7.22 Emergency Systems ...................................................................................................172

1. Engine Generator ................................................................................................172 2. Uninterruptible Power Systems ...........................................................................174 3. Automatic Transfer Switches ...............................................................................177

7.23 Telemetry/Pilot Wire/Scada - Reserved ......................................................................179 7.24 Automatic Circuit Reclosers and Line Sectionalizers ..................................................180

1. Automatic Circuit Reclosers, Oil/Vacuum ............................................................180 2. Automatic Line Sectionalizers, Oil .......................................................................183

7.25 Fiber-Optic Cables ......................................................................................................186 7.26 Electrostatic/Electromagnetic Field Testing - Reserved ..............................................186 7.27 Special Systems - Reserved .......................................................................................186

8. SYSTEM FUNCTION TESTS.............................................................................................187 9. THERMOGRAPHIC SURVEY ............................................................................................188

ATS – 1999

Page 8: NETA_ATS-1999
Page 9: NETA_ATS-1999

10. TABLES 10.1 Insulation Resistance Tests, Electrical Apparatus and Systems..............................190 10.2 Switchgear Withstand Test Voltages .......................................................................191 10.3 Recommended Dissipation Factor/Power Factor

of Liquid-Filled Transformers, Regulators, and Reactors.........................................192 10.4 Suggested Limits for New Insulating Liquids Test Limits for New Insulating Oil Received in New Equipment.......................193 Test Limits for Silicone Insulating Liquid in New Transformers........................193 Typical Values for Less-Flammable Hydrocarbon Insulating Liquid.................194 10.5 Transformer Insulation-Resistance, Acceptance Test Voltage and

Minimum Results .....................................................................................................192 10.6 Medium-Voltage Cables, Maximum Field Acceptance Test Voltages (kV, dc).........196 10.7 Molded-Case Circuit Breakers, Inverse Time Trip Test ...........................................197 10.8 Instantaneous Trip Tolerances for Field Testing of Circuit Breakers........................198 10.9 Instrument Transformer Dielectric Tests, Acceptance .............................................199 10.10 Maximum Allowable Vibration Amplitude .................................................................200 10.11 Overpotential Test Voltages for Electrical Apparatus

Other than Inductive Equipment ..............................................................................201 10.12 Bolt Torques for Bus Connections ...........................................................................202 US Standard, Heat-Treated Steel - Cadmium or Zinc Plated...........................202 Silicon Bronze Fasteners, Torque (Foot Pounds) ............................................203 Aluminum Alloy Fasteners, Torque (Foot Pounds) .........................................203 Stainless Steel Fasteners, Torque (Foot Pounds) ...........................................204 10.13 Reserved .................................................................................................................205 10.14 Insulation Resistance Conversion Factors

for Conversion of Test Temperature to 20ºC ...........................................................206 10.15 AC High-Potential Test Voltage for Automatic Circuit Reclosers .............................207 10.16 AC High-Potential Test Voltage for Automatic Line Sectionalizers ..........................207 10.17 Metal Enclosed Bus Dielectric Withstand Test Voltages..........................................208 10.18 Thermographic Survey, Suggested Actions Based on Temperature Rise ...............209

ATS – 1999

Page 10: NETA_ATS-1999
Page 11: NETA_ATS-1999

STANDARD SPECIFICATION FORM

Electrical Acceptance Tests

1. GENERAL SCOPE, ACCEPTANCE TESTING SPECIFICATIONS

1.1 This standard covers the suggested field tests and inspections that are available to assess the suitability for initial energization of electrical power distribution equipment and systems.

1.2 The purpose of these specifications is to assure that all tested electrical equipment and systems are operational and within applicable standards and manufacturer’s tolerances and that the equipment and systems are installed in accordance with design specifications.

1.3 The work specified in these specifications may involve hazardous voltages, materials, operations, and equipment. These specifications do not purport to address all of the safety problems associated with their use. It is the responsibility of the user to review all applicable regulatory limitations prior to the use of these specifications.

ATS – 1999 1

Page 12: NETA_ATS-1999

2. APPLICABLE REFERENCES

2.1 All inspections and field tests shall be in accordance with the latest edition of the following codes, standards, and specifications except as provided otherwise herein.

1. American National Standards Institute - ANSI

2. American Society for Testing and Materials - ASTM

ASTM D 92-90. Test Method for Flash and Fire Points by Cleveland Open Cup

ASTM D 445-88. Test Method for Kinematic Viscosity of Transparent and Opaque Liquids

ASTM D 664-95 Test Method for Acid Number of Petroleum Products by Potentiometric Titration

ASTM D 877-87. Test Method for Dielectric Breakdown Voltage of Insulating Liquids using Disk Electrodes

ASTM D 923-91. Test Method for Sampling Electrical Insulating Liquids

ASTM D 924-98 (1990). Test Method for A-C Loss Characteristics and Relative Permittivity (Dielectric Constant) of Electrical Insulating Liquids

ASTM D 971-91. Test Method for Interfacial Tension of Oil against Water by the Ring Method

ASTM D 974-95. Test Method for Acid and Base Number by Color-Indicator Titration

ASTM D 1298-85 (1990). Test Method for Density, Relative Density (Specific Gravity), or API Gravity of Crude Petroleum and Liquid Petroleum Products by Hydrometer Method

ASTM D 1500-91. Test Method for ASTM Color of Petroleum Products (ASTM Color Scale)

ASTM D 1524-94 (1990). Test Method for Visual Examination of Used Electrical Insulating Oils of Petroleum Origin in the Field

ASTM D 1533-88. Test Methods for Water in Insulating Liquids (Karl Fischer Reaction Method)

2 ATS – 1999

Page 13: NETA_ATS-1999

2. APPLICABLE REFERENCES (cont.)

ASTM D 1816-84a (1990). Test Method for Dielectric Breakdown Voltage of Insulating Oils of Petroleum Origin Using VDE Electrodes

ASTM D 2029-92. Test Methods for Water Vapor Content of Electrical Insulating cases by Measurement of Dew Point

ASTM D 2129-90. Test Method for Color of Chlorinated Aromatic Hydrocarbons (Askarels)

ASTM D 2284-95. Test Method of Acidity of Sulfur Hexafluoride

ASTM D 2285-85 (R1990). Test Method for Interfacial Tension of Electrical Insulating Oils of Petroleum Origin Against Water by the Drop-Weight Method

ASTM D 2477-84 (R1990). Test Method for Dielectric Breakdown Voltage and Dielectric Strength of Insulating Gases at Commercial Power Frequencies

ASTM D 2685-95. Test Method for Air and Carbon Tetrafluoride in Sulfur Hexafluoride by Gas Chromatography

ASTM D 2759-94. Method for Sampling Gas from a Transformer under Positive Pressure

ASTM D 3284-90a (R1994). Test Method for combustible Gases in Electrical Apparatus in the Field

ASTM D 3612-95. Test Method of Analysis of Gases Dissolved in Electrical Insulating Oil by Gas Chromatography

ASTM D 3613-92. Methods of Sampling Electrical Insulating Oils for Gas Analysis and Determination of Water Content

3. Association of Edison Illuminating Companies - AEIC

4. Canadian Standards Association - CSA

5. Institute of Electrical and Electronic Engineers - IEEE

ANSI/IEEE C2-1997, National Electrical Safety Code

ANSI/IEEE C37-1995, Guides and Standards for Circuit Breakers, Switchgear, Relays, Substations, and Fuses

ANSI/IEEE C57-1995, Distribution, Power, and Regulating Transformers

ATS – 1999 3

Page 14: NETA_ATS-1999

2. APPLICABLE REFERENCES (cont.)

ANSI/IEEE C62-1995, Surge Protection

ANSI/IEEE Std. 43-1974 (R1991). IEEE Recommended Practice for Testing Insulation Resistance of Rotating Machinery

ANSI/IEEE Std. 48-1996. Standard Test Procedures and Requirements for Alternating-Current Cable Terminations 2.5 kV through 765 kV

IEEE Std. 81-1983. IEEE Guide for Measuring Earth Resistivity, Ground Impedance, and Earth Surface Potentials of a Ground System (Part I)

ANSI/IEEE Std. 81.2-1991. IEEE Guide for Measurement of Impedance and Safety Characteristics of Large, Extended or Interconnected Grounding Systems (Part 2)

ANSI/IEEE Std. 95-1977 (R1991). IEEE Recommended Practice for Insulation Testing of Large AC Rotating Machinery with High Direct Voltage

IEEE Std. 100-1996. The IEEE Standard Dictionary of Electrical and Electronics Terms

ANSI/IEEE Std. 141-1993. IEEE Recommended Practice for Electrical Power Distribution for Industrial Plants (IEEE Red Book.)

ANSI/IEEE Std. 142-1991. IEEE Recommended Practice for Grounding of Industrial and Commercial Power Systems (IEEE Green Book)

ANSI/IEEE Std. 241-1990 (R1997). IEEE Recommended Practice for Electric Power Systems in Commercial Buildings (Gray Book)

ANSI/IEEE Std. 242-1986 (R1991). IEEE Recommended Practice for Protection and Coordination of Industrial and Commercial Power Systems (Buff Book)

IEEE 386-1995. IEEE Standard for Separable Insulated Connectors System for Power Distribution Systems above 600 V.

ANSI/IEEE Std. 399-1990. IEEE Recommended Practice for Industrial and Commercial Power Systems Analysis (Brown Book)

ANSI/IEEE Std. 400-1991. IEEE Guide for Making High-Direct-Voltage Tests on Power Cable Systems in the Field

ANSI/IEEE Std. 421B-1979. IEEE Standard for High-Potential-Test Requirements for Excitation Systems for Synchronous Machines

4 ATS – 1999

Page 15: NETA_ATS-1999

2. APPLICABLE REFERENCES (cont.)

ANSI/IEEE Std. 446-1995. IEEE Recommended Practice for Emergency and Standby Power Systems for Industrial and Commercial Applications (Orange Book)

ANSI/IEEE Std. 450-1995 IEEE Recommended Practice for Maintenance, Testing, and Replacement of Vented Lead-Acid Batteries for Stationary Applications

ANSI/IEEE Std. 493-1990. IEEE Recommended Practice for the Design of Reliable Industrial and Commercial Power Systems (Gold Book)

ANSI/IEEE Std. 602-1996. IEEE Recommended Practice for Electric Systems in Health Care Facilities (White Book)

ANSI/IEEE Std. 637-1985 (R1992). IEEE Guide for the Reclamation of Insulating Oil and Criteria for Its Use

ANSI/IEEE Std. 739-1995. IEEE Recommended Practice for Energy Management in Commercial and Industrial Facilities (Bronze Book)

ANSI/IEEE Std. 1100-1992. IEEE Recommended Practice for Powering and Grounding Sensitive Electronic Equipment (Emerald Book)

ANSI/IEEE Std. 1106-1995. IEEE Recommended Practice for Maintenance, Testing, and Replacement of Nickel-Cadmium Storage Batteries for Generating Stations and Substations

ANSI/IEEE Std. 1159-1995 – Recommended Practice for Monitoring Electric Power Quality

ANSI/IEEE Std. 1188-1996. Recommended Practice for Maintenance, Testing, and Replacement of Valve-Regulated Lead-Acid (VRLA) Batteries for Stationary Applications

6. Insulated Cable Engineers Association - ICEA

7. InterNational Electrical Testing Association - NETA NETA MTS-97. NETA Maintenance Testing Specifications for Electrical Power Distribution Equipment and Systems

8. National Electrical Manufacturer’s Association - NEMA

NEMA Standard for Publication No. AB4-1991. Guidelines for Inspection and Preventive Maintenance of Molded-Case Circuit Breakers Used in Commercial and Industrial Applications

NEMA Publication MG1-1993. Motors and Generators

ATS – 1999 5

Page 16: NETA_ATS-1999

2. APPLICABLE REFERENCES (cont.)

9. National Fire Protection Association - NFPA ANSI/NFPA 70-1996. National Electrical Code

ANSI/NFPA 70B-1994. Recommended Practice for Electric Equipment Maintenance

ANSI/NFPA 70E-1995. Electrical Safety Requirements for Employee Workplaces

ANSI/NFPA 99-1993. Standard for Healthcare Facilities

ANSI/NFPA 101-1994. Life Safety Code

ANSI/NFPA 110-1993. Emergency and Standby Power Systems

ANSI/NFPA 780-1995. Installation of Lightning Protection Systems

10. Occupational Safety and Health Administration - OSHA

11. Scaffold Industry Association - SIA

ANSI/SIA A92.2-1990. Vehicle Mounted Elevating and Rotating Aerial Devices

12. State and local codes and ordinances

13. Underwriters Laboratories, Inc. - UL

2.2 Other Publications Paul Gill, Electrical Power Equipment Maintenance and Testing, New York: Marcel Dekker, Inc., 1998

6 ATS – 1999

Page 17: NETA_ATS-1999

3. QUALIFICATIONS OF TESTING ORGANIZATION AND PERSONNEL

3.1 The testing organization shall submit appropriate documentation to demonstrate that it satisfactorily complies with the following. An organization having a “Full Membership” classification issued by the InterNational Electrical Testing Association meets this criteria.

1. The testing organization shall be an independent, third party, testing organization which can function as an unbiased testing authority, professionally independent of the manufacturers, suppliers, and installers of equipment or systems evaluated by the testing organization.

2. The testing organization shall be regularly engaged in the testing of electrical equipment devices, installations, and systems.

3.2 The testing organization shall utilize technicians who are regularly employed for testing services.

3.3 Each on-site crew leader shall hold a current registered certification in electrical testing applicable to each type of apparatus to be inspected or tested. The certification in electrical testing shall be issued by an independent, nationally-recognized, technician certification agency. The following entities shall qualify as independent, nationally-recognized, technician certification agencies:

1. InterNational Electrical Testing Association (NETA) Accepted certifications:

Certified Technician/Level III Certified Senior Technician/Level IV

2. National Institute of Certification in Engineering Technologies (NICET) Accepted certifications specifically in Electrical Testing Engineering Technology:

Engineering Technician/Level III Senior Engineering Technician/Level IV

ATS – 1999 7

Page 18: NETA_ATS-1999

4. DIVISION OF RESPONSIBILITY

4.1 The owner’s representative shall provide the testing organization with the following:

1. A short-circuit analysis and coordination study and a protective device setting sheet as described in Section 6.

2. A complete set of electrical plans and specifications along with any pertinent change orders.

3. An itemized description of equipment to be inspected and tested.

4. A determination of who shall provide a suitable and stable source of electrical power to each test site.

5. Notification of when equipment becomes available for acceptance tests. Work shall be coordinated to expedite project scheduling.

4.2 The installing contractor or testing firm shall perform certain preliminary low-voltage insulation-resistance, continuity, and/or rotation tests prior to and in addition to tests specified herein.

4.3 The testing organization shall provide the following:

1. All field technical services, tooling, equipment, instrumentation, and technical supervision to perform such tests and inspections.

2. Specific power requirements for test equipment.

3. Notification to the owner’s representative prior to commencement of any testing.

4. A timely notification of any system, material, or workmanship which is found deficient on the basis of acceptance tests.

5. A written record of all tests and a final report.

8 ATS – 1999

Page 19: NETA_ATS-1999

5. GENERAL

5.1 Safety and Precautions

This document does not include any procedures, including specific safety procedures. It is recognized that an overwhelming majority of the tests and inspections recommended in these specifications are potentially hazardous. Inherent in this determination is the prerequisite that individuals performing these tests be capable of conducting the tests in a safe manner and with complete knowledge of the hazards involved.

1. Safety practices shall include, but are not limited to, the following requirements:

1. Occupational Safety and Health Act.

2. Accident Prevention Manual for Industrial Operations, National Safety Council.

3. Applicable state and local safety operating procedures.

4. Owner’s safety practices.

5. ANSI/NFPA 70E, Electrical Safety Requirements for Employee Workplaces.

2. All tests shall be performed with apparatus de-energized except where otherwise specifically required.

3. The testing organization shall have a designated safety representative on the project to supervise operations with respect to safety.

5.2 Suitability of Test Equipment

1. All test equipment shall be in good mechanical and electrical condition.

2. Split-core current transformers and clamp-on or tong-type ammeters require consideration of the following in regard to accuracy:

1. Position of the conductor within the core

2. Clean, tight fit of the core pole faces

ATS – 1999 9

Page 20: NETA_ATS-1999

5. GENERAL (cont.)

3. Presence of external magnetic fields

4. Accuracy of the current transformer ratio in addition to the accuracy of the secondary meter.

3. Selection of metering equipment shall be based on a knowledge of the waveform of the variable being measured. Digital multimeters may be average or RMS sensing and may include or exclude the dc component. When the variable contains harmonics or dc offset and, in general, any deviation from a pure sine wave, average sensing, RMS scaled meters may be misleading.

4. Field test metering used to check power system meter calibration must have an accuracy higher than that of the instrument being checked.

5. Accuracy of metering in test equipment shall be appropriate for the test being performed but not in excess of two percent of the scale used.

6. Waveshape and frequency of test equipment output waveforms shall be appropriate for the test and tested equipment.

5.3 Test Instrument Calibration

1. The testing firm shall have a calibration program which assures that all applicable test instruments are maintained within rated accuracy.

2. The accuracy shall be directly traceable to the National Institute of Standards and Technology (NIST).

3. Instruments shall be calibrated in accordance with the following frequency schedule:

1. Field instruments: Analog, 6 months maximum; Digital, 12 months maximum

2. Laboratory instruments: 12 months

3. Leased specialty equipment: 12 months where accuracy is guaranteed by lessor.

4. Dated calibration labels shall be visible on all test equipment.

5. Records, which show date and results of instruments calibrated or tested, shall be kept up-to-date.

10 ATS – 1999

Page 21: NETA_ATS-1999

5. GENERAL (cont.)

6. Up-to-date instrument calibration instructions and procedures shall be maintained for each test instrument.

7. Calibrating standard shall be of higher accuracy than that of the instrument tested.

5.4 Test Report

1. The test report shall include the following:

1. Summary of project.

2. Description of equipment tested.

3. Description of test.

4. Test data.

5. Analysis and recommendations.

2. Test data records shall include the following minimum requirements:

1. Identification of the testing organization.

2. Equipment identification.

3. Humidity, temperature, and other atmospheric conditions that may affect the results of the tests/calibrations.

4. Date of inspections, tests, maintenance, and/or calibrations.

5. Identification of the testing technician.

6. Indication of inspections, tests, maintenance, and/or calibrations to be performed and recorded.

7. Indication of expected results when calibrations are to be performed.

8. Indication of “as-found” and “as-left” results.

9. Sufficient spaces to allow all results and comments to be indicated.

3. The testing firm shall furnish a copy or copies of the complete report to the owner as required in the acceptance contract.

ATS – 1999 11

Page 22: NETA_ATS-1999

6. POWER SYSTEM STUDIES

6.1 Short-Circuit and Coordination Studies

1. Scope of Services

1. Provide a current and complete short-circuit study, equipment-interrupting or withstand evaluation, and a protective-device coordination study for the electrical distribution system.

The studies shall include all portions of the electrical distribution system from the normal and alternate sources of power throughout the low-voltage distribution system. Normal system operating method, alternate operation, and operations which could result in maximum-fault conditions shall be thoroughly covered in the study.

2. Short-Circuit Study

1. The study shall be in accordance with applicable ANSI and IEEE standards.

2. The study input data shall include the utility company’s short-circuit single- and three-phase contribution, with the X/R ratio, the resistance and reactance components of each branch impedance, motor and generator contributions, base quantities selected, and all other applicable circuit parameters.

3. Short-circuit momentary duties and interrupting duties shall be calculated on the basis of maximum available fault current at each switchgear bus, switchboard, motor control center, distribution panelboard, pertinent branch circuit panelboards, and other significant locations through the system.

3. Equipment Evaluation Study

An equipment evaluation study shall be performed to determine the adequacy of circuit breakers, controllers, surge arresters, busways, switches, and fuses by tabulating and comparing the short-circuit ratings of these devices with the maximum short-circuit momentary and interrupting duties. The evaluation study should be submitted prior to final approval of equipment submittals.

12 ATS – 1999

Page 23: NETA_ATS-1999

6. POWER SYSTEM STUDIES (cont.) 6.1 Short-Circuit and Coordination Studies (cont.)

4. Protective-Device Coordination Study

1. A protective-device coordination study shall be performed to select or to verify the selection of power fuse ratings, protective-relay characteristics and settings, ratios and characteristics of associated voltage and current transformers, and low-voltage breaker trip characteristics and settings.

2. The coordination study shall include all voltage classes of equipment from the utility’s incoming line protective device down to and including each motor control center and/or panelboard. The phase and ground overcurrent protection shall be included as well as settings for all other adjustable protective devices.

3. Coordination shall be in accordance with requirements of the National Electrical Code and the recommendations of ANSI/IEEE Standard 399, as applicable.

4. Protective device selection and settings shall be in accordance with requirements of the National Electrical Code and the recommendations of ANSI/IEEE Standard 399, as applicable.

5. Study Report

1. Discrepancies, problem areas, or inadequacies shall be promptly brought to the owner’s attention.

2. The results of the power-system studies shall be summarized in a final report.

3. The report shall include the following sections:

1. Description, purpose, basis, and scope of the study and a single-line diagram of the portion of the power system which is included within the scope of study.

2. Tabulations of circuit breaker, fuse, and other equipment ratings versus calculated short-circuit duties and commentary regarding same.

3. Protective device coordination curves, with commentary.

ATS – 1999 13

Page 24: NETA_ATS-1999

6. POWER SYSTEM STUDIES (cont.) 6.1 Short-Circuit and Coordination Studies (cont.)

4. The selection and settings of the protective devices shall be provided separately in a tabulated form listing circuit identification, IEEE device number, current transformer ratios, manufacturer, type, range of adjustment, and recommended settings. A tabulation of the recommended power fuse selection shall be provided for all fuses in the system.

5. Fault-current tabulations including a definition of terms and a guide for interpretation.

6. Implementation

The owner shall engage an independent testing organization for the purpose of inspecting, setting, testing, and calibrating the protective relays, circuit breakers, fuses, and other applicable devices as recommended in the power-system study report.

6.2 Load Flow Studies - Reserved

6.3 Stability Studies - Reserved

6.4 Switching Transients Studies - Reserved

6.5 Motor Starting Studies - Reserved

6.6 Harmonic Analysis - Reserved

6.7 Ground Mat Studies - Reserved

6.8 Cable Ampacity Studies - Reserved

6.9 Reliability Studies – Reserved

14 ATS – 1999

Page 25: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES

7.1 Switchgear and Switchboard Assemblies

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Verify appropriate anchorage, required area clearances, physical damage, and correct alignment.

4. Inspect all doors, panels, and sections for corrosion, dents, scratches, fit, and missing hardware.

5. Verify that fuse and/or circuit breaker sizes and types correspond to drawings and coordination study as well as to the circuit breaker’s address for microprocessor-communication packages.

6. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.1.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

7. Verify that current and potential transformer ratios correspond to drawings.

8. Compare equipment nameplate data with latest one-line diagram when available.

9. Confirm correct operation and sequencing of electrical and mechanical interlock systems.

ATS – 1999 15 *Optional

Page 26: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.1 Switchgear and Switchboard Assemblies (cont.)

1. Attempt closure on locked-open devices. Attempt to open locked-closed devices.

2. Make key exchange with devices operated in off-normal positions.

10. Thoroughly clean switchgear prior to testing.

11. Lubrication

1. Verify appropriate contact lubricant on moving current-carrying parts.

2. Verify appropriate lubrication on moving and sliding surfaces.

12. Inspect insulators for evidence of physical damage or contaminated surfaces.

13. Verify correct barrier and shutter installation and operation.

14. Exercise all active components.

15. Inspect all mechanical indicating devices for correct operation.

16. Verify that filters are in place and/or vents are clear.

17. Perform visual and mechanical inspection on all instrument transformers in accordance with Section 7.10.1 (Visual and Mechanical Inspection).

18. Inspect control power transformers.

1. Inspect physical damage, cracked insulation, broken leads, tightness of connections, defective wiring, and overall general condition.

2. Verify that primary and secondary fuse ratings or circuit breakers match drawings.

3. Verify correct functioning of drawout disconnecting and grounding contacts and interlocks

16 ATS – 1999 *Optional

Page 27: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.1 Switchgear and Switchboard Assemblies (cont.)

2. Electrical Tests

1. Perform tests on all instrument transformers in accordance with Section 7.10.2 (Electrical Tests).

2. Perform ground-resistance tests in accordance with Section 7.13.

3. Perform resistance tests through all bus joints with a low-resistance ohmmeter, if applicable, in accordance with Section 7.1.1 (Visual and Mechanical Inspection).

4. Perform insulation-resistance tests on each bus section, phase-to-phase and phase-to-ground, for one minute in accordance with Table 10.1.

5. Perform an overpotential test on each bus section, each phase to ground with phases not under test grounded, in accordance with manufacturer’s published data. If manufacturer has no recommendation for this test, it shall be in accordance with Table 10.2. The test voltage shall be applied for one minute. Refer to Section 7.1.3.4 before performing test.

6. Perform insulation-resistance tests at 1000 volts dc on all control wiring. For units with solid-state components, follow manufacturer’s recommendations.

7. Perform control wiring performance test in accordance with Section 8.

8. Perform current injection tests on the entire current circuit in each section of switchgear.

1. Perform current tests by primary injection, where possible, with magnitudes such that a minimum of 1.0 ampere flows in the secondary circuit.

2. Where primary injection is impractical, utilize secondary injection with a minimum current of 1.0 ampere.

3. Test current at each device.

9. Determine accuracy of all meters and calibrate watthour meters in accordance with Section 7.11. Verify multipliers.

ATS – 1999 17 *Optional

Page 28: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.1 Switchgear and Switchboard Assemblies (cont.)

10. Perform phasing check on double-ended switchgear to insure correct bus phasing from each source.

11. Control Power Transformers

1. Perform insulation-resistance tests. Perform measurements from winding-to-winding and each winding-to-ground. Test voltages shall be in accordance with Table 10.1 unless otherwise specified by manufacturer.

2. Perform secondary wiring integrity test. Disconnect transformer at secondary terminals and connect secondary wiring to correct secondary voltage. Confirm potential at all devices.

3. Verify correct secondary voltage by energizing primary winding with system voltage. Measure secondary voltage with the secondary wiring disconnected.

4. Verify correct function of control transfer relays located in switchgear with multiple power sources.

12. Voltage Transformers

1. Perform insulation-resistance tests. Perform measurements from winding-to-winding and each winding-to-ground. Test voltages shall be in accordance with Table 10.1 unless otherwise specified by manufacturer.

2. Perform secondary wiring integrity test. Confirm correct potential at all devices.

3. Verify secondary voltages.

13. Verify operation of switchgear/switchboard heaters.

18 ATS – 1999 *Optional

Page 29: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.1 Switchgear and Switchboard Assemblies (cont.)

3. Test Values

1. Compare bus connection resistances to values of similar connections.

2. Bolt-torque levels shall be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar bus by more than 50 percent of the lowest value.

4. Insulation-resistance values for bus, control wiring, and control power transformers shall be in accordance with manufacturer’s published data. In the absence of manufacturer’s published data, use Table 10.1. Values of insulation resistance less than this table or manufacturer’s minimum shall be investigated. Overpotential tests should not proceed until insulation-resistance levels are raised above minimum values.

5. The insulation shall withstand the overpotential test voltage applied.

ATS – 1999 19 *Optional

Page 30: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES

7.2 Transformers 1. Dry Type

1. Air-Cooled, 600 Volt and Below - Small (167 kVA Single-Phase, 500 kVA Three-Phase, and Smaller)

1. Visual and Mechanical Inspections

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Verify that resilient mounts are free and that any shipping brackets have been removed.

4. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.2.1.1.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

20 ATS – 1999 *Optional

Page 31: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.2 Transformers (cont.) 1. Dry-Type (cont.) 1. Air-Cooled, 600 Volt and Below – Small (167 kVA Single-Phase, 500 kVA Three-Phase, and Smaller) (cont.)

2. Electrical Tests

1. Perform resistance measurements through all bolted connections with a low-resistance ohmmeter, if applicable, in accordance with Section 7.2.1.1.1 (Visual and Mechanical Inspection).

2. Perform insulation-resistance tests winding-to-winding and each winding-to-ground with test voltage in accordance with Table 10.5.

3. Calculate polarization index.

*4. Perform turns ratio tests at all tap positions.

*5. Verify that as-left tap connections are as specified.

ATS – 1999 21 *Optional

Page 32: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.2 Transformers (Continued) 1. Dry-Type (cont.)

1. Air-Cooled, 600 Volt and Below – Small (167 kVA Single-Phase, 500 kVA Three-Phase, and Smaller) (cont.)

3. Test Values

1. Compare bolted connection resistances to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. Insulation-resistance test values at one minute should not be less than the values calculated in accordance with the formula in Table 10.5. Results shall be temperature corrected in accordance with Table 10.14.

5. The polarization index shall be greater than 1.0 and shall be recorded for future reference.

6. Turns-ratio test results should not deviate more than one-half percent from either the adjacent coils or the calculated ratio.

22 ATS – 1999 *Optional

Page 33: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.2 Transformers (cont.) 1. Dry-Type (cont.)

2. Air-Cooled, All Above 600 Volt and 600 Volt and Below – Large (Greater than 167 kVA Single-Phase and 500 kVA Three-Phase)

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical, electrical, and mechanical condition.

3. Verify that control and alarm settings on temperature indicators are as specified.

4. Verify that cooling fans operate and that fan motors have correct overcurrent protection.

5. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.2.1.2.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

6. Perform specific inspections and mechanical tests as recommended by manufacturer.

7. Verify that resilient mounts are free and that any shipping brackets have been removed.

8. Verify that the core, frame, and enclosure groundings are correct.

9. Verify the presence of transformer surge arresters.

10. Verify that as-left tap connections are as specified.

ATS – 1999 23 *Optional

Page 34: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.2 Transformers (cont.) 1. Dry Type (cont.) 2. Air-Cooled, All Above 600 Volt and 600 Volt and Below – Large (Greater than 167 kVA Single-Phase and 500 kVA Three-Phase) ( ont.)

24 ATS – 1999

c

*Optional

2. Electrical Tests

1. Perform insulation-resistance tests winding-to-winding and each winding-to-ground with test voltage in accordance with Table 10.5.

2. Calculate polarization index.

3. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.2.1.2.1 (Visual and Mechanical inspection).

4. Perform power-factor or dissipation-factor tests in accordance with the test equipment manufacturer’s published data.

5. Perform a turns-ratio test on all tap connections. Verify that winding polarities are in accordance with nameplate.

*6. Perform an excitation-current test on each phase.

*7. Measure the resistance of each winding at each tap connection.

8. Measure core insulation resistance at 500 volts dc if core is insulated and if the core ground strap is removable.

*9. Perform an overpotential test on all high- and low-voltage windings-to-ground.

10. Verify correct secondary voltage phase-to-phase and phase-to-neutral after energization and prior to loading.

Page 35: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.2 Transformers (cont.) 1. Dry Type (cont.) 2. Air-Cooled, All Above 600 Volt and 600 Volt and Below – Large (Greater than 167 kVA Single-Phase and 500 kVA Three-Phase) (cont.)

3. Test Values

1. Compare bolted connection resistances to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. Insulation-resistance test values at one minute should not be less than the values calculated in accordance with the formula in Table 10.5. Results shall be temperature corrected in accordance with Table 10.14.

5. The polarization index shall be greater than 1.0 and shall be recorded for future reference.

6. Turns-ratio test results shall not deviate more than one-half percent from either the adjacent coils or the calculated ratio.

7. CH and CL dissipation-factor/power-factor values will vary due to support insulators and bus work utilized on dry transformers. The following is expected on CHL power factors:

Power Transformers: one percent or less Distribution Transformers: three percent or less

Consult transformer manufacturer’s or test equipment manufacturer’s data for additional information.

ATS – 1999 25 *Optional

Page 36: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.2 Transformers (cont.) 1. Dry Type (cont.) 2. Air-Cooled, All Above 600 Volt and 600 Volt and Below – Large (Greater than 167 kVA Single-Phase and 500 kVA Three-Phase) (cont.)

8. Winding resistance test results, after factoring in temperature corrections, should compare within one percent of factory obtained results except in instances of extremely low resistance values.

9. Typical excitation current test data pattern for a three-legged core transformer is two similar current readings and one lower current reading.

10. Core insulation resistance values should be comparable to factory obtained results but not less than one megohm at 500 volts dc.

11. AC overpotential test shall not exceed 75 percent of factory test voltage for one minute duration. DC overpotential test shall not exceed 100 percent of the factory RMS test voltage for one minute duration. The insulation shall withstand the overpotential test voltage applied.

26 ATS – 1999 *Optional

Page 37: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.2 Transformers (Cont.)

2. Liquid-Filled

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Verify removal of any shipping bracing after final placement.

4. Inspect impact recorder prior to unloading, if applicable.

5. Verify settings and operation of all temperature devices, if applicable.

6. Verify that cooling fans and pumps operate correctly and that fan and pump motors have correct overcurrent protection, if applicable.

7. Verify operation of all alarm, control, and trip circuits from temperature and level Indicators, pressure relief device, and fault pressure relay, if applicable.

8. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.2.2.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

9. Verify correct liquid level in all tanks and bushings.

10. Verify that positive pressure is maintained on nitrogen-blanketed transformers.

ATS – 1999 27 *Optional

Page 38: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.2 Transformers (cont.) 2. Liquid-Filled (cont.)

11. Perform specific inspections and mechanical tests as recommended by manufacturer.

12. Verify correct equipment grounding.

13. Verify the presence of transformer surge arresters.

2. Electrical Tests

1. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.2.2.1 (Visual and Mechanical Inspection).

2. Perform insulation-resistance tests, winding-to-winding and each winding-to-ground in accordance with Table 10.5.

*3. Calculate polarization index.

4. Perform turns-ratio tests at all tap positions.

5. Test load tap-changer in accordance with Section 7.12, if applicable.

6. Perform insulation power-factor/dissipation-factor tests on windings in accordance with test equipment manufacturer’s published data.

7. Perform power-factor/dissipation-factor tests or hot collar watts-loss tests on bushings in accordance with test equipment manufacturer’s published data.

*8. Perform excitation-current tests in accordance with test equipment manufacturer’s published data.

9. Measure resistance of each high-voltage winding in each no-load tap-changer position. Measure resistance of each low-voltage winding in each load tap-changer position, if applicable.

28 ATS – 1999 *Optional

Page 39: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.2 Transformers (cont.)

2. Liquid-Filled (cont.)

10. If core ground strap is accessible, measure core insulation resistance at 500 volts dc.

11. Measure the percentage of oxygen in the nitrogen gas blanket, if applicable.

12. Remove a sample of insulating liquid in accordance with ASTM D-923. Sample shall be tested for the following:

1. Dielectric breakdown voltage: ASTM D-877 and/or ASTM D-1816.

2. Acid neutralization number: ANSI/ASTM D-974.

*3. Specific gravity: ANSI/ASTM D-1298.

4. Interfacial tension: ANSI/ASTM D-971 or ANSI/ASTM D-2285.

5. Color: ANSI/ASTM D-1500.

6. Visual Condition: ASTM D-1524.

*7. Water in insulating liquids: ASTM D-1533. (Required on 25 kV or higher voltages and on all silicone-filled units.)

*8. Measure dissipation factor or power factor in accordance with ASTM D-924.

13. Remove a sample of insulating liquid in accordance with ASTM D3613 and perform dissolved gas analysis (DGA) in accordance with ANSI/IEEE C57.104 or ASTM D-3612.

14. Perform tests on all instrument transformers in accordance with Section 7.10.

ATS – 1999 29 *Optional

Page 40: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.2 Transformers (cont.) 2. Liquid-Filled (cont.)

3. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. Insulation-resistance test values at one minute should not be less than the values calculated in accordance with the formula in Table 10.5. Results shall be temperature corrected in accordance with Table 10.14.

5. The polarization index shall be greater than 1.0 and shall be recorded for future reference.

6. Turns-ratio test results shall not deviate more than one-half percent from either the adjacent coils or the calculated ratio.

7. Maximum power factor of liquid-filled transformers shall be in accordance with manufacturer’s published data. Representative values are indicated in Table 10.3.

8. Investigate bushing power factors and capacitances that vary from nameplate values by more than ten percent. Investigate any bushing hot collar watts-loss results that exceed the test equipment manufacturer’s published data.

9. Typical excitation-current test data pattern for three-legged core transformer is two similar current readings and one lower current reading.

10. Winding-resistance test results, after factoring in temperature correction, should compare within one percent of factory obtained results except in instances of extremely low resistance values.

30 ATS – 1999 *Optional

Page 41: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.2 Transformers (cont.)

2. Liquid-Filled (cont.) 11. Consult manufacturer if core insulation is less than one

megohm at 500 volts dc.

12. Investigate presence of oxygen in the gas nitrogen blanket.

13. Insulating liquid test results shall be in accordance with Table 10.4.

14. Evaluate results of dissolved-gas analysis in accordance with ANSI/IEEE Standard C57.104. Use results as baseline for future tests.

ATS – 1999 31 *Optional

Page 42: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES

7.3 Cables

1. Low-Voltage, Low-Energy - Reserved

2. Low-Voltage, 600 Volt Maximum

1. Visual and Mechanical Inspection

1. Compare cable data with drawings and specifications.

2. Inspect exposed sections of cables for physical damage and correct connection in accordance with single-line diagram.

3. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.3.2.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

4. Inspect compression-applied connectors for correct cable match and indentation.

5. Verify cable color coding with applicable specifications and the National Electrical Code.

32 ATS – 1999 *Optional

Page 43: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.3 Cables (cont.)

2. Low-Voltage, 600 Volt Maximum (cont.)

2. Electrical Tests

1. Perform insulation-resistance test on each conductor with respect to ground and adjacent conductors. Applied potential shall be 500 volts dc for 300 volt rated cable and 1000 volts dc for 600 volt rated cable. Test duration shall be one minute.

2. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.3.2.1 (Visual and Mechanical Inspection).

3. Perform continuity test to insure correct cable connection.

3. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by the manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. Minimum insulation-resistance values should not be less than 50 megohms.

5. Investigate deviations between adjacent phases.

ATS – 1999 33 *Optional

Page 44: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.3 Cables (cont.)

3. Medium-Voltage, 69 kV Maximum

1. Visual and Mechanical Inspection

1. Compare cable data with drawings and specifications.

2. Inspect exposed sections of cables for physical damage.

3. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.3.3.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

4. Inspect compression-applied connectors for correct cable match and indention.

5. Inspect for shield grounding, cable support, and termination.

6. Verify that visible cable bends meet or exceed ICEA and/or manufacturer’s minimum allowable bending radius.

7. Inspect fireproofing in common cable areas, if specified.

8. If cables are terminated through window-type current transformers, make an inspection to verify that neutral and ground conductors are correctly placed and that shields are correctly terminated for operation of protective devices.

9. Visually inspect jacket and insulation condition.

10. Inspect for correct identification and arrangements.

34 ATS – 1999 *Optional

Page 45: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.3 Cables (cont.) 3. Medium-Voltage, 69 kV Maximum (cont.)

2. Electrical Tests

1. Perform a shield-continuity test on each power cable by ohmmeter method.

2. Perform an insulation-resistance test utilizing a megohmmeter with a voltage output of at least 2500 volts. Individually test each conductor with all other conductors and shields grounded. Test duration shall be one minute.

3. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.3.3.1 (Visual and Mechanical Inspection).

4. Perform a dc high-potential test on all cables. Adhere to all precautions and limits as specified in the applicable NEMA/ICEA Standard for the specific cable. Perform tests in accordance with ANSI/IEEE Standard 400. Test procedure shall be as follows, and the results for each cable test shall be recorded as specified herein. Test voltages shall not exceed 80 percent of cable manufacturer’s factory test value or the maximum test voltage in Table 10.6.

1. Insure that the input voltage to the test set is regulated.

2. Current-sensing circuits in test equipment shall measure only the leakage current associated with the cable under test and shall not include internal leakage of the test equipment.

3. Record wet- and dry-bulb temperatures or relative humidity and temperature.

4. Test each section of cable individually.

5. Individually test each conductor with all other conductors grounded. Ground all shields.

6. Terminations shall be adequately corona-suppressed by guard ring, field reduction sphere, or other suitable methods as necessary.

ATS – 1999 35 *Optional

Page 46: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.3 Cables (cont.) 3. Medium-Voltage, 69 kV Maximum (cont.)

7. Insure that the maximum test voltage does not exceed the limits for terminators specified in ANSI/IEEE Standard 48, IEEE 386, or manufacturer’s specifications.

8. Apply a dc high-potential test in at least five equal increments until maximum test voltage is reached. No increment shall exceed the voltage rating of the cable. Record dc leakage current at each step after a constant stabilization time consistent with system charging current.

9. Raise the conductor to the specified maximum test voltage and hold for 15 minutes on shielded cable and five minutes on nonshielded cable. Record readings of leakage current at 30 seconds and one minute and at one minute intervals thereafter.

10. Reduce the conductor test potential to zero and measure residual voltage at discrete intervals.

11. Apply grounds for a time period adequate to drain all insulation stored charge.

12. When new cables are spliced into existing cables, the dc high-potential test shall be performed on the new cable prior to splicing in accordance with Section 7.3.2. After test results are approved for new cable and the splice is completed, an insulation-resistance test and a shield-continuity test shall be performed on the length of new and existing cable including the splice. After a satisfactory insulation-resistance test, a dc high-potential test shall be performed on the cable utilizing a test voltage acceptable to owner and not exceeding 60 percent of factory test value.

36 ATS – 1999 *Optional

Page 47: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.3 Cables (cont.) 3. Medium-Voltage, 69 kV Maximum (cont.)

3. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. Shielding shall exhibit continuity. Investigate resistance values in excess of ten ohms per 1000 feet of cable.

*5. Graphic plots may be made of leakage current versus step voltage at each increment and leakage current versus time at final test voltages.

1. The step voltage slope should be reasonably linear.

2. Capacitive and absorption current should decrease continually until steady state leakage is approached.

ATS – 1999 37 *Optional

Page 48: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.3 Cables (cont.)

4. High-Voltage

1. Visual and Mechanical Inspection

1. Compare cable data with drawings and specifications.

2. Inspect exposed sections of cables for physical damage.

3. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.3.4.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

4. Inspect compression-applied connectors for correct cable match and indention.

5. Inspect for shield grounding, cable support, and termination.

6. Verify that visible cable bends meet or exceed ICEA and/or manufacturer’s minimum allowable bending radius.

7. Inspect fireproofing in common cable areas, if specified.

8. If cables are terminated through window-type current transformers, make an inspection to verify that neutral and ground conductors are correctly placed and that shields are correctly terminated for operation of protective devices.

9. Visually inspect jacket and insulation condition.

10. Inspect for correct identification and arrangements.

38 ATS – 1999 *Optional

Page 49: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.3 Cables (cont.)

4. High-Voltage (cont.)

2. Electrical Tests

1. Perform a shield-continuity test on each power cable by ohmmeter method.

2. Perform an insulation-resistance test utilizing a megohmmeter with a voltage output of at least 2500 volts. Individually test each conductor with all other conductors and shields grounded. Test duration shall be one minute.

3. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.3.4.1 (Visual and Mechanical Inspection).

4. Perform a dc high-potential test on all cables. Adhere to all precautions and limits as specified in the applicable NEMA/ICEA Standard for the specific cable. Perform tests in accordance with ANSI/IEEE Standard 400. Test procedure shall be as follows, and the results for each cable test shall be recorded as specified herein. Test voltages shall not exceed 80 percent of cable manufacturer’s factory test value or the maximum test voltage in Table 10.6.

1. Insure that the input voltage to the test set is regulated.

2. Current-sensing circuits in test equipment shall measure only the leakage current associated with the cable under test and shall not include internal leakage of the test equipment.

3. Record wet- and dry-bulb temperatures or relative humidity and temperature.

4. Test each section of cable individually.

5. Individually test each conductor with all other conductors grounded. Ground all shields.

6. Terminations shall be adequately corona-suppressed by guard ring, field reduction sphere, or other suitable methods as necessary.

ATS – 1999 39 *Optional

Page 50: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.3 Cables (cont.) 4. High-Voltage (cont.)

7. Insure that the maximum test voltage does not exceed the limits for terminators specified in ANSI/IEEE Standard 48 or manufacturer’s specifications.

8. Apply a dc high-potential test in at least five equal increments until maximum test voltage is reached. No increment shall exceed the voltage rating of the cable. Record dc leakage current at each step after a constant stabilization time consistent with system charging current.

9. Raise the conductor to the specified maximum test voltage and hold for 15 minutes on shielded cable and five minutes on nonshielded cable. Record readings of leakage current at 30 seconds and one minute and at one minute intervals thereafter.

10. Reduce the conductor test potential to zero and measure residual voltage at discrete intervals.

11. Apply grounds for a time period adequate to drain all insulation stored charge.

12. When new cables are spliced into existing cables, the dc high-potential test shall be performed on the new cable prior to splicing in accordance with Section 7.3.2. After test results are approved for new cable and the splice is completed, an insulation-resistance test and a shield-continuity test shall be performed on the length of new and existing cable including the splice. After a satisfactory insulation-resistance test, a dc high-potential test shall be performed on the cable utilizing a test voltage acceptable to owner and not exceeding 60 percent of factory test value.

40 ATS – 1999 *Optional

Page 51: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.3 Cables (cont.)

4. High-Voltage (cont.)

3. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. Shielding shall exhibit continuity. Investigate resistance values in excess of ten ohms per 1000 feet of cable.

*5. Graphic plots may be made of leakage current versus step voltage at each increment and leakage current versus time at final test voltages.

1. The step voltage slope should be reasonably linear.

2. Capacitive and absorption current should decrease continually until steady state leakage is approached.

ATS – 1999 41 *Optional

Page 52: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES

7.4 Metal-Enclosed Busways

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect busway for physical damage and correct connection in accordance with single-line diagram.

3. Inspect for appropriate bracing, suspension, alignment, and enclosure ground.

4. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.4.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

5. Confirm physical orientation in accordance with manufacturer’s labels to insure adequate cooling.

6. Examine outdoor busway for removal of “weep-hole” plugs, if applicable, and the correct installation of joint shield.

2. Electrical Tests

1. Measure insulation resistance of each busway, phase-to-phase and phase-to-ground for one minute, in accordance with Table 10.1.

2. Perform an overpotential test on each busway, phase-to-ground with phases not under test grounded, in accordance with manufacturer’s published data. If manufacturer has no recommendation for this test, it shall be in accordance with Table 10.17. Where no dc test value is shown in Table 10.17, ac value shall be used. The test voltage shall be applied for one minute.

42 ATS – 1999 *Optional

Page 53: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.4 Metal-Enclosed Busways (cont.)

3. Perform contact-resistance test on each connection point of noninsulated busway. On insulated busway, measure resistance of assembled busway sections and compare values with adjacent phases.

4. Perform phasing test on each busway tie section energized by separate sources. Tests must be performed from their permanent sources.

3. Test Values

1. Compare bolted connection resistances and bus joint resistances to values of similar connections.

2. Bus bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. Insulation-resistance test voltages and resistance values shall be in accordance with manufacturer’s published data or Table 10.1. Minimum resistance values are for a nominal 1000 foot busway run. Use the following formula to convert the measured resistance value to the 1000-foot nominal value:

1000RunofLengthxResistanceMeasuredR1000ft =

Converted values of insulation resistance less than those in Table 10.1 or manufacturer’s minimum shall be investigated. Overpotential tests shall not proceed until insulation-resistance levels are raised above minimum values.

5. The insulation shall withstand the overpotential test voltage applied.

ATS – 1999 43 *Optional

Page 54: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES

7.5 Switches 1. Air Switches

1. Low-Voltage

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Confirm correct application of manufacturer’s recommended lubricants.

4. Verify appropriate anchorage and required area clearances.

5. Verify appropriate equipment grounding.

6. Verify correct blade alignment, blade penetration, travel stops, and mechanical operation.

7. Verify that fuse sizes and types are in accordance with drawings and short-circuit and coordination studies.

8. Verify that each fuse holder has adequate mechanical support.

9. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.5.1.1.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

10. Test all interlocking systems for correct operation and sequencing.

44 ATS – 1999 *Optional

Page 55: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.5 Switches (cont.) 1. Air Switches (cont.) 1. Low-Voltage (cont.)

11. Verify correct phase barrier materials and installation.

12. Inspect all indicating and control devices for correct operation.

2. Electrical Tests

1. Perform insulation-resistance tests on each pole, phase-to-phase and phase-to-ground with switch closed and across each open pole for one minute. Test voltage shall be in accordance with manufacturer’s published data or Table 10.1.

2. Measure contact-resistance across each switchblade and fuse holder.

3. Measure fuse resistance.

4. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.5.1.1.1 (Visual and Mechanical Inspection).

5. Verify heater operation.

ATS – 1999 45 *Optional

Page 56: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES

7.5 Switches (cont.) 1. Air Switches (cont.) 1. Low-Voltage (cont.)

3. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. Minimum insulation resistance shall be in accordance with manufacturer’s published data or Table 10.1.

5. Investigate any contact resistance values which deviate from adjacent poles or similar switches by more than 25 percent.

6. Investigate fuse-resistance values that deviate from each other by more than 15 percent.

46 ATS – 1999 *Optional

Page 57: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.5 Switches (cont.) 1. Air Switches (cont.)

2. Medium-Voltage, Metal-Enclosed

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Confirm correct application of manufacturer’s recommended lubricants.

4. Verify appropriate anchorage and required area clearances.

5. Verify appropriate equipment grounding.

6. Verify correct blade alignment, blade penetration, travel stops, and mechanical operation.

7. Verify that fuse sizes and types are in accordance with drawings and short-circuit and coordination studies.

8. Verify that expulsion-limiting devices are in place on all holders having expulsion-type elements.

9. Verify that each fuse holder has adequate mechanical support.

10. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.5.1.2.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

ATS – 1999 47 *Optional

Page 58: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.5 Switches (cont.) 1. Air Switches (cont.) 2. Medium-Voltage, Metal-Enclosed (cont.)

11. Test all interlocking systems for correct operation and sequencing.

12. Verify correct phase-barrier materials and installation.

13. Compare switchblade clearances with industry standards.

14. Inspect all indicating and control devices for correct operation.

2. Electrical Tests

1. Perform insulation-resistance tests on each pole, phase-to-phase and phase-to-ground with switch closed and across each open pole for one minute. Test voltage shall be in accordance with manufacturer’s published data or Table 10.1.

2. Perform an overpotential test on each pole with switch closed. Test each pole-to-ground with all other poles grounded. Test voltage shall be in accordance with manufacturer’s published data or Table 10.2.

3. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.5.1.2.1 (Visual and Mechanical Inspection).

4. Measure contact resistance across each switchblade and fuse holder.

5. Measure fuse resistance.

6. Verify heater operation.

48 ATS – 1999 *Optional

Page 59: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.5 Switches (cont.) 1. Air Switches (cont.) 2. Medium-Voltage, Metal-Enclosed (cont.)

3. Test Values

1. Compare bolted connection resistances to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. The insulation should withstand the overpotential test voltage applied.

5. Minimum insulation resistance shall be in accordance with manufacturer’s published data or Table 10.1.

6. Investigate fuse resistance values that deviate from each other by more than 15 percent.

ATS – 1999 49 *Optional

Page 60: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.5 Switches (cont.) 1. Air Switches (cont.)

3. High- and Medium-Voltage, Open

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Confirm correct application of manufacturer’s recommended lubricants.

4. Verify that grounding is in accordance with industry standards and project specifications.

5. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.5.1.3.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10. 12.

3. Perform thermographic survey in accordance with Section 9.

6. Perform mechanical operator tests in accordance with manufacturer’s published data.

7. Verify correct operation and adjustment of motor operator limit-switches and mechanical interlocks, if applicable.

8. Verify correct blade alignment, blade penetration, travel stops, arc interrupter operation, and mechanical operation, if applicable.

50 ATS – 1999 *Optional

Page 61: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.5 Switches (cont.) 1. Air Switches (cont.) 3. High- and Medium-Voltage, Open (cont.)

2. Electrical Tests

*1. Perform insulation-resistance tests on each pole, phase-to-phase and phase-to-ground with switch closed and across each open pole for one minute. Test voltage shall be in accordance with manufacturer’s published data or Table 10.1.

2. Perform an overpotential test on each pole with switch closed. Test each pole-to-ground with all other poles grounded. Test voltage shall be in accordance with manufacturer’s published data or Table 10.11.

3. Perform contact-resistance test across each switchblade and fuse holder.

3. Test Values

1. Compare bolted connection resistances to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. Insulation resistance values shall be in accordance with manufacturer’s data or Table 10.1.

5. The insulation shall withstand the overpotential test voltage applied.

6. Contact resistance shall be determined in microhms. Investigate any value exceeding 500 microhms or any values which deviate from adjacent poles or similar switches by more than 25 percent.

ATS – 1999 51 *Optional

Page 62: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.5 Switches (cont.) 2. Oil Switches: Medium-Voltage

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Inspect anchorage, alignment, and grounding.

4. Perform all mechanical operation and contact alignment tests on both the switch and its operating mechanism.

5. Check each fuse holder for adequate support and contact.

6. Verify that fuse sizes and types correspond to drawings.

7. Test all electrical and mechanical interlock systems for correct operation and sequencing.

8. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.5.2.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

9. Verify that insulating oil level is correct.

52 ATS – 1999 *Optional

Page 63: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.5 Switches (cont.) 2. Oil Switches: Medium-Voltage (cont.)

2. Electrical Tests

1. Perform a contact resistance test.

2. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.5.2.1 (Visual and Mechanical Inspection).

3. Remove a sample of insulating liquid in accordance with ASTM D-923. Sample shall be tested in accordance with the referenced standard.

1. Dielectric breakdown voltage: ASTM D-877.

2. Color: ASTM D-1500.

3. Visual condition: ASTM D-1524.

4. Perform insulation-resistance tests pole-to-pole, pole-to-ground, and across open poles at 2500 volts minimum.

5. Perform insulation resistance tests on all control wiring at 1000 volts dc. For solid-state components, follow manufacturer’s recommendations.

ATS – 1999 53 *Optional

Page 64: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.5 Switches (cont.) 2. Oil Switches: Medium-Voltage (cont.)

3. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. Insulating liquid test results shall be in accordance with Table 10.4.

5. Control wiring insulation resistance should be a minimum of two megohms.

54 ATS – 1999 *Optional

Page 65: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.5 Switches (cont.)

3. Vacuum Switches: Medium-Voltage

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Inspect anchorage, alignment, and grounding.

4. Perform all mechanical operation and contact alignment tests on both the switch and its operating mechanism.

5. Check each fuse holder for adequate support and contact.

6. Verify that fuse sizes and types correspond to drawings.

7. Test all electrical and mechanical interlock systems for correct operation and sequencing.

8. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.5.3.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

9. Verify that insulating oil level is correct, if applicable.

ATS – 1999 55 *Optional

Page 66: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.5 Switches (cont.) 3. Vacuum Switches: Medium-Voltage (cont.)

2. Electrical Tests

1. Perform resistance measurements through all bolted electrical connections with a low-resistance ohmmeter, if applicable. See Section 7.5.3.1 (Visual and Mechanical Inspection).

2. Perform a contact-resistance test.

3. Verify open and close operation from control devices, if applicable.

4. Perform insulation-resistance tests pole-to-pole, pole-to-ground, and across open poles at 2500 volts minimum.

5. Perform vacuum bottle integrity (overpotential) test across each vacuum bottle with the switch in the open position in strict accordance with manufacturer’s published data. Do not exceed maximum voltage stipulated for this test. Provide adequate barriers and protection against x-radiation during this test. Do not perform this test unless the contact displacement of each interrupter is within manufacturer’s tolerance. (Be aware that some dc high-potential test sets are half-wave rectified and may produce peak voltages in excess of the switch manufacturer’s recommended maximum.)

6. Remove a sample of insulating liquid, if applicable, in accordance with ASTM D-923. Sample shall be tested in accordance with the referenced standard.

1. Dielectric breakdown voltage: ASTM D-877

2. Color: ASTM D-1500

3. Visual condition: ASTM D-1524

*7. Perform insulation-resistance tests on all control wiring at 1000 volts dc. For units with solid-state components, follow manufacturer’s recommendations.

*8. Perform an overpotential test in accordance with manufacturer’s published data.

56 ATS – 1999 *Optional

Page 67: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.5 Switches (cont.) 3. Vacuum Switches: Medium-Voltage (cont.)

3. Test Values

1. Compare bolted connection resistances to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from adjacent poles or similar switches by more than 50 percent of the lowest value.

4. Contact displacement shall be in accordance with factory recorded data marked on the nameplate of each vacuum switch or bottle.

5. The vacuum bottles shall withstand the overpotential voltage applied.

6. Control wiring insulation resistance should be a minimum of two megohms.

7. The insulation shall withstand the overpotential test voltage applied.

8. Insulating liquid test results shall be in accordance with Table 10.4.

4. SF6 Switches: Medium-Voltage - Reserved

5. Cutouts - Reserved

ATS – 1999 57 *Optional

Page 68: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES

7.6 Circuit Breakers 1. Low-Voltage

1. Insulated Case/Molded Case

1. Visual and Mechanical Inspection

1. Compare nameplate data with drawings and specifications.

2. Inspect circuit breaker for correct mounting.

3. Operate circuit breaker to insure smooth operation.

4. Inspect case for cracks or other defects.

5. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.6.1.1.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

6. Inspect mechanism contacts and arc chutes in unsealed units.

2. Electrical Tests

1. Perform a contact-resistance test.

2. Perform an insulation-resistance test at 1000 volts dc from pole-to-pole and from each pole-to-ground with breaker closed and across open contacts of each phase

58 ATS – 1999 *Optional

Page 69: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) 1. Low-Voltage (cont.) 1. Insulated Case/Molded Case (cont.)

3. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.6.1.1.1 (Visual and Mechanical Inspection).

*4. Perform insulation resistance tests at 1000 volts dc on all control wiring. Do not perform the test on wiring connected to solid state components.

5. Perform adjustments for final settings in accordance with coordination study supplied by owner.

6. Perform long-time delay time-current characteristic tests by passing 300 percent rated primary current through each pole separately unless series testing is required to defeat ground fault functions.

7. Determine short-time pickup and delay by primary current injection.

8. Determine ground-fault pickup and time delay by primary current injection.

9. Determine instantaneous pickup current by primary injection using run-up or pulse method.

10. Verify correct operation of any auxiliary features such as trip and pickup indicators, zone interlocking, electrical close and trip operation, trip-free, and antipump function.

*11. Verify the calibration of all functions of the trip unit by means of secondary injection.

.

ATS – 1999 59 *Optional

Page 70: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) 1. Low-Voltage (cont.) 1. Insulated Case/Molded Case (cont.)

3. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. Circuit breaker insulation resistance should be in accordance with Table 10.1.

5. Control wiring insulation resistance should be a minimum of two megohms.

6. Trip characteristic of breakers shall fall within manufacturer’s published time-current characteristic tolerance band, including adjustment factors. If manufacturer’s curves are not available trip times shall be equal to or less than the values shown in Table 10.7. Circuit breakers exceeding specified trip time at 300 percent of pickup shall be tagged defective.

7. Instantaneous pickup values of molded-case circuit breakers shall be within the tolerances shown in Table 10.8.

60 ATS – 1999 *Optional

Page 71: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) 1. Low-Voltage (cont.)

2. Power

1. Visual and Mechanical Inspection

1. Compare nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Confirm correct application of manufacturer’s recommended lubricants.

4. Inspect anchorage, alignment, and grounding. Inspect arc chutes. Inspect moving and stationary contacts for condition, wear, and alignment.

5. Verify that all maintenance devices are available for servicing and operating the breaker.

6. Verify that primary and secondary contact wipe and other dimensions vital to satisfactory operation of the breaker are correct.

7. Perform all mechanical operator and contact alignment tests on both the breaker and its operating mechanism.

8. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.6.1.2.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

9. Verify cell fit and element alignment.

10. Verify racking mechanism.

ATS – 1999 61 *Optional

Page 72: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) 1. Low-Voltage (cont.) 2. Power (cont.)

2. Electrical Tests

1. Perform a contact-resistance test.

2. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.6.1.2.1 (Visual and Mechanical Inspection).

3. Perform an insulation-resistance test at 1000 volts dc from pole-to-pole and from each pole-to-ground with breaker closed and across open contacts of each phase.

*4. Perform insulation-resistance tests at 1000 volts dc on all control wiring. Do not perform the test on wiring connected to solid state components.

5. Make adjustments for the final settings in accordance with the coordination study supplied by owner.

6. Determine minimum pickup current by primary current injection.

7. Determine long-time delay by primary current injection.

8. Determine short-time pickup and delay by primary current injection.

9. Determine ground-fault pickup and delay by primary current injection.

10. Determine instantaneous pickup value by primary current injection.

*11. Verify the calibration of all functions of the trip unit by means of secondary injection.

62 ATS – 1999 *Optional

Page 73: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) 1. Low-Voltage (cont.) 2. Power (cont.)

12. Activate auxiliary protective devices, such as ground-fault or undervoltage relays, to insure operation of shunt trip devices. Check the operation of electrically-operated breakers in their cubicles.

13. Verify correct operation of any auxiliary features such as trip and pickup indicators, zone interlocking, electrical close and trip operation, trip-free, and antipump function and verify trip unit battery condition.

14. Verify operation of charging mechanism.

3. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. Circuit breaker insulation resistance should be in accordance with Table 10.1.

5. Central wiring insulation resistance should be a minimum of two megohms.

6. Trip characteristics of breakers shall fall within manufacturer’s published time-current tolerance bands.

ATS – 1999 63 *Optional

Page 74: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) 2. Medium-Voltage (cont.)

1. Air

1. Visual and Mechanical Inspection

1. Compare nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Confirm correct application of manufacturer’s recommended lubricants.

4. Inspect anchorage, alignment, and grounding. Inspect arc chutes. Inspect moving and stationary contacts for condition, wear, and alignment.

5. Verify that all maintenance devices are available for servicing and operating the breaker.

6. Verify that primary and secondary contact wipe and other dimensions vital to satisfactory operation of the breaker are correct.

7. Perform all mechanical operator and contact alignment tests on both the breaker and its operating mechanism.

8. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.6.2.1.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

9. Check cell fit and element alignment.

64 ATS – 1999 *Optional

Page 75: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) 2. Medium-Voltage (cont.) 1. Air (cont.)

10. Check racking mechanism.

11. Inspect puffer operation.

*12. Perform circuit breaker timing tests.

13. Record as-found and as-left operation-counter readings.

2. Electrical Tests

1. Perform a contact resistance test.

2. Measure insulation resistance pole-to-pole, pole-to-ground, and across open poles. Use a minimum test voltage of 2500 volts.

3. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.6.2.1.1 (Visual and Mechanical Inspection).

*4. Perform insulation-resistance tests at 1000 volts dc on all control wiring. Do not perform the test on wiring connected to solid-state components.

5. With breaker in the test position, make the following tests:

1. Trip and close breaker with the control switch.

2. Trip breaker by operating each of its protective relays.

3. Verify trip-free and antipump function.

*4. Test trip and close circuit at reduced control voltages, if applicable.

*6. Perform dissipation-factor/power-factor test with breaker in both open and closed positions.

ATS – 1999 65 *Optional

Page 76: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) 2. Medium-Voltage (cont.) 1. Air (cont.)

*7. Perform an overpotential test in accordance with manufacturer’s published data.

8. Measure blow-out coil circuit resistance.

3. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. Circuit breaker insulation resistance should be in accordance with Table 10.1.

5. Control wiring insulation resistance should be a minimum of two megohms.

6. Dissipation-factor/power-factor test results shall be compared with previous tests of similar breakers or manufacturer’s published data.

7. The insulation shall withstand the overpotential test voltage applied.

8. Minimum pickup for trip and close coils shall conform to manufacturer’s published data.

66 ATS – 1999 *Optional

Page 77: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) 2. Medium-Voltage (cont.)

2. Oil

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Confirm correct application of manufacturer’s recommended lubricants.

4. Inspect anchorage, alignment, and grounding.

5. Verify that breather vents are clear.

6. Perform all mechanical operation and contact alignment tests on both the circuit breaker and its operating mechanism in accordance with manufacturer’s published data.

7. If performing internal inspection:

1. Remove oil. Lower tanks or remove manhole covers as necessary. Inspect bottom of tank for broken parts and debris.

2. Inspect lift rod and toggle assemblies, contacts, interrupters, bumpers, dashpots, bushing current transformers, tank liners, and gaskets.

3. Slow-close breaker and check for binding, friction, contact alignment, penetration, and overtravel. Verify that all phases make contact simultaneously.

4. Refill tank(s) with filtered oil to correct levels.

ATS – 1999 67 *Optional

Page 78: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) 2. Medium-Voltage (cont.) 2. Oil (cont.)

8. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.6.2.2.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

9. Test alarms and lockouts for pneumatic and/or hydraulic operators as recommended by the manufacturer.

10. Perform circuit breaker time-travel analysis.

11. Record as-found and as-left operation counter readings.

2. Electrical Tests

1. Perform a contact resistance test.

2. Remove a sample of insulating liquid in accordance with ASTM D-923. Sample shall be tested for the following:

1. Dielectric breakdown voltage: ASTM D-877.

2. Color: ANSI/ASTM D-1500.

*3. Power factor: ASTM D-924.

*4. Interfacial tension: ANSI/ASTM D-971 or ANSI/ASTM D-2285.

5. Visual condition: ASTM D-1524.

68 ATS – 1999 *Optional

Page 79: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) 2. Medium-Voltage (cont.) 2. Oil (cont.)

3. Trip circuit breaker by operation of each protective device.

4. Perform insulation-resistance tests pole-to-pole, pole-to-ground, and across open poles at 2500 volts minimum.

5. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.6.2.2.1 (Visual and Mechanical Inspection).

*6. Perform insulation-resistance tests on all control wiring at 1000 volts dc. Do not perform this test on wiring connected to solid-state relays.

7. Perform dissipation factor/power factor tests on each pole with breaker open and each phase with breaker closed. Determine tank loss index.

8. Perform dissipation-factor/power-factor tests on each bushing. Use conductive straps and hot collar procedures if bushings are not equipped with a power-factor tap.

9. Verify trip, close, trip-free, and antipump functions.

*10. Perform minimum pickup voltage tests on trip and close coils.

*11. Perform an overpotential test in accordance with manufacturer’s instructions.

ATS – 1999 69 *Optional

Page 80: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) 2. Medium-Voltage (cont.) 2. Oil (cont.)

3. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. Compare circuit breaker travel and velocity values to manufacturer’s acceptable limits.

5. Insulating-liquid test results should comply with Table 10.4.

6. Circuit breaker insulation resistance should be in accordance with Table 10.1.

7. Control wiring insulation resistance should be a minimum of two megohms.

8. Dissipation-factor/power-factor test results and tank loss index shall be compared to manufacturer’s published data. In the absence of manufacturer’s published data, the comparison shall be made to similar breakers.

9. Dissipation-factor/power-factor and capacitance test results should be within ten percent of nameplate rating for bushings.

10. The insulation shall withstand the overpotential test voltage applied.

11. Minimum pickup for trip and close coils shall conform to manufacturer’s published data.

70 ATS – 1999 *Optional

Page 81: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) 2. Medium-Voltage (cont.)

3. Vacuum

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Confirm correct application of manufacturer’s recommended lubricants.

4. Inspect anchorage, alignment, and grounding.

5. Perform all mechanical operational tests on both the circuit breaker and its operating mechanism.

6. Measure critical distances such as contact gap as recommended by manufacturer.

7. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.6.2.3.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

8. Perform timing tests.

9. Record as-found and as-left operation counter readings.

ATS – 1999 71 *Optional

Page 82: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) 2. Medium-Voltage (cont.) 3. Vacuum (cont.)

2. Electrical Tests

1. Perform a contact-resistance test.

*2. Perform minimum pickup voltage tests on trip and close coils.

3. Verify trip, close, trip-free, and antipump function.

4. Trip circuit breaker by operation of each protective device.

5. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.6.2.3.1 (Visual and Mechanical Inspection).

6. Perform insulation-resistance tests pole-to-pole, pole-to-ground, and across open poles at 2500 volts minimum

7. Perform vacuum bottle integrity (overpotential) test across each vacuum bottle with the breaker in the open position in strict accordance with manufacturer’s instructions.

*8. Perform insulation-resistance tests at 1000 volts on all control wiring dc. For units with solid-state components, follow manufacturer’s recommendations.

*9. Perform dissipation-factor/power-factor tests on each pole with the breaker open and each phase with the breaker closed.

*10. Perform dissipation-factor/power-factor tests on each bushing. Use conductive straps and hot collar procedures if bushings are not equipped with a power factor tap.

*11. Perform an overpotential test in accordance with manufacturer’s instructions.

72 ATS – 1999 *Optional

Page 83: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) 2. Medium-Voltage (cont.) 3. Vacuum (cont.)

3. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. Circuit breaker insulation resistance should be in accordance with Table 10.1.

5. Contact displacement shall be in accordance with factory recorded data marked on the nameplate of each vacuum breaker or bottle.

6. The interrupter shall withstand the overpotential voltage applied.

7. Compare circuit breaker timing values to manufacturer’s published data.

8. Control wiring insulation resistance should be a minimum of two megohms.

9. Dissipation-factor/power-factor test results shall be compared to manufacturer’s published data. In the absence of manufacturer’s published data the comparison shall be made to similar breakers.

ATS – 1999 73 *Optional

Page 84: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) 2. Medium-Voltage (cont.) 3. Vacuum (cont.)

10. Dissipation-factor/power-factor and capacitance test results should be within ten percent of nameplate rating for bushings.

11. The insulation shall withstand the overpotential test voltage applied.

74 ATS – 1999 *Optional

Page 85: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) 2. Medium-Voltage (cont.)

4. SF6

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Confirm correct application of manufacturer’s recommended lubricants.

4. Inspect anchorage and grounding.

5. Inspect and verify adjustments of mechanism in accordance with manufacturer’s published data.

6. Inspect air compressor in accordance with manufacturer’s published data.

7. Inspect hydraulic system in accordance with manufacturer’s published data.

8. Test for gas leaks.

9. Verify correct operation of all air and SF6 gas pressure alarms and cutouts.

10. Slow close/open breaker and check for binding.

11. Perform time-travel analysis.

12. Test SF6 gas for moisture and nitrogen content.

ATS – 1999 75 *Optional

Page 86: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) 2. Medium-Voltage (cont.) 4. SF6 (cont.)

13. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.6.2.4.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

14. Record as-found and as-left counter operations.

15. Verify operation of all heaters.

76 ATS – 1999 *Optional

Page 87: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) 2. Medium-Voltage (cont.) 4. SF6 (cont.)

2. Electrical Tests

1. Perform a contact resistance test.

2. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.6.2.4.1 (Visual and Mechanical Inspection).

3. Perform insulation-resistance tests pole-to-pole, pole-to-ground, and across open poles at 2500 volts minimum.

*4. Perform insulation-resistance tests on all control wiring at 1000 volts dc. For units with solid-state components, follow manufacturer’s recommendations.

*5. Perform dissipation-factor/power-factor tests on breaker and bushings.

*6. Perform overpotential test in accordance with manufacturer’s instructions.

*7. Perform minimum pick-up voltage test on trip and close coils.

8. Verify trip, close, trip-free, and antipump functions.

9. Trip circuit breaker by operation of each protective device.

ATS – 1999 77 *Optional

Page 88: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) 2. Medium-Voltage (cont.) 4. SF6 (cont.)

3. Test Values.

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. Compare time-travel data with manufacturer’s published data.

5. Control wiring insulation resistance should be a minimum of two megohms.

6. Circuit breaker insulation resistance should be in accordance with Table 10.1.

7. Dissipation-factor/power-factor test results shall be compared to manufacturer’s published data. In the absence of manufacturer’s published data, the comparison shall be made to similar breakers.

8. Dissipation-factor/power-factor and capacitance test results should be within ten percent of nameplate rating for bushings.

9. The insulation shall withstand the overpotential test voltage applied.

10. Minimum pickup for trip and close coils shall conform to manufacturer’s published data.

78 ATS – 1999 *Optional

Page 89: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.)

3. High-Voltage 1. Oil

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Confirm correct application of manufacturer’s recommended lubricants.

4. Inspect anchorage, alignment, and grounding.

5. Verify that breather vents are clear.

6. Perform all mechanical operation and contact alignment tests on both the circuit breaker and its operating mechanism.

7. If performing internal inspection:

1. Remove oil. Lower tanks or remove manhole covers as necessary. Inspect bottom of tank for broken parts and debris.

2. Inspect lift rod and toggle assemblies, contacts, interrupters, bumpers, dashpots, bushing current transformers, tank liners, and gaskets.

3. Slow-close breaker and check for binding, friction, contact alignment, penetration, and overtravel. Check that all phases make contact simultaneously.

4. Refill tank(s) with filtered oil to correct levels.

ATS – 1999 79 *Optional

Page 90: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) 3. High-Voltage (cont.) 1. Oil (cont.)

8. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.6.3.1.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

9. Test alarms and lockouts for pneumatic and/or hydraulic operators as recommended by the manufacturer.

10. Perform circuit breaker time-travel analysis.

11. Record as-found and as-left operation counter readings.

2. Electrical Tests

1. Perform a contact resistance test.

2. Remove a sample of insulating liquid in accordance with ASTM D-923. Sample shall be tested for the following:

1. Dielectric breakdown voltage: ASTM D-877

2. Color: ANSI/ASTM D-1500

*3. Power factor: ASTM D-924

*4. Interfacial tension: ANSI/ASTM D-971 or ANSI/ASTM D-2285

5. Visual condition: ASTM D-1524

80 ATS – 1999 *Optional

Page 91: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) 3. High-Voltage (cont.) 1. Oil (cont.)

3. Trip circuit breaker by operation of each protective device.

4. Verify trip, close, trip-free, and antipump function.

5. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.6.3.1.1 (Visual and Mechanical Inspection).

*6. Perform insulation-resistance tests pole-to-pole, pole-to-ground, and across open poles at 15,000 volts minimum.

*7. Perform insulation-resistance tests on all control wiring at 1000 volts dc. For units with solid-state components, follow manufacturer’s recommendations.

8. Perform power-factor tests on each pole with breaker open and each phase with breaker closed. Determine tank loss index.

9. Perform power-factor tests on each bushing. Use conductive straps and hot collar procedures if bushings are not equipped with a power-factor tap.

*10. Perform minimum pickup voltage tests on trip and close coils.

*11. Perform an overpotential test in accordance with manufacturer’s published data.

3. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

ATS – 1999 81 *Optional

Page 92: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) 3. High Voltage (cont.) 1. Oil (cont.)

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. Compare circuit breaker travel and velocity values to manufacturer’s published data.

5. Insulating liquid test results should be in accordance with Table 10.4.

6. Circuit breaker insulation resistance should comply with Table 10.1.

7. Control wiring insulation resistance should be a minimum of two megohms.

8. Dissipation-factor/power-factor test results and tank loss index shall be compared to manufacturer’s published data. In the absence of manufacturer’s published data, the comparison shall be made to similar breakers.

9. Dissipation-factor/power-factor and capacitance test results should be within ten percent of nameplate rating for bushings.

10. The insulation shall withstand the overpotential test voltage applied.

11. Minimum pickup for trip and close coils shall conform to manufacturer’s published data.

82 ATS – 1999 *Optional

Page 93: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) 3. High-Voltage (cont.)

2. SF6

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Confirm correct application of manufacturer’s recommended lubricants.

4. Inspect anchorage and grounding.

5. Inspect and verify adjustments of mechanism in accordance with manufacturer’s published data.

6. Inspect air compressor in accordance with manufacturer’s published data.

7. Inspect hydraulic system in accordance with manufacturer’s published data.

8. Test for gas leaks.

9. Verify correct operation of all air and SF6 gas pressure alarms and cutouts.

10. Slow close/open breaker and check for binding.

11. Perform time-travel analysis.

12. Test SF6 gas for moisture and nitrogen content.

ATS – 1999 83 *Optional

Page 94: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) 3. High-Voltage (cont.) 2. SF6 (cont.)

13. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.6.3.2.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

14. Record as-found and as-left counter operations.

15. Check spring charging motor starts counter and compare with operations counter, if applicable.

16. Verify operation of all heaters.

84 ATS – 1999 *Optional

Page 95: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) 3. High-Voltage (cont.) 2. SF6 (cont.)

2. Electrical Tests

1. Perform a contact resistance test.

2. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.6.3.2.1 (Visual and Mechanical Inspection).

3. Perform insulation-resistance tests pole-to-pole, pole-to-ground, and across open poles at 15,000 volts minimum.

*4. Perform insulation-resistance tests on all control wiring at 1000 volts dc. For units with solid-state components, follow manufacturer’s recommendations.

*5. Perform dissipation-factor/power-factor tests on breaker and bushings.

*6. Perform overpotential test in accordance with manufacturer’s instructions.

*7. Perform minimum pick-up voltage test on trip and close coils.

8. Verify trip, close, trip-free, and antipump functions.

9. Trip circuit breaker by operation of each protective device.

ATS – 1999 85 *Optional

Page 96: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) 3. High-Voltage (cont.) 2. SF6 (cont.)

3. Test Values.

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. Compare time-travel data with manufacturer’s published data.

5. Control wiring insulation resistance should be a minimum of two megohms.

6. Circuit breaker insulation resistance should be in accordance with Table 10.1.

7. Dissipation-factor/power-factor test results shall be compared to manufacturer’s published data. In the absence of manufacturer’s published data, the comparison shall be made to similar breakers.

8. Dissipation-factor/power-factor and capacitance test results should be within ten percent of nameplate rating for bushings.

9. The insulation shall withstand the overpotential test voltage applied

10. Minimum pickup for trip and close coils shall conform to manufacturer’s published data.

86 ATS – 1999 *Optional

Page 97: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.)

4. Extra-High-Voltage 1. SF6

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Confirm correct application of manufacturer’s recommended lubricants.

4. Inspect anchorage and grounding.

5. Inspect and verify adjustments of mechanism in accordance with manufacturer’s published data.

6. Inspect air compressor in accordance with manufacturer’s published data.

7. Inspect and service hydraulic system in accordance with manufacturer’s published data.

8. Test for gas leaks.

9. Verify correct operation of all air and SF6 gas pressure alarms and cutouts.

10. Slow close/open breaker and check for binding.

11. Perform time-travel analysis.

12. Test SF6 gas for moisture and nitrogen content.

ATS – 1999 87 *Optional

Page 98: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) 4. Extra-High-Voltage (cont.) 1. SF6 (cont.)

13. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.6.4.1.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

14. Record as-found and as-left counter operations.

15. Check spring charging motor starts counter and compare with operations counter, if applicable.

.

88 ATS – 1999 *Optional

Page 99: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) 4. Extra-High-Voltage (cont.) 1. SF6 (cont.)

2. Electrical Tests

1. Perform a contact resistance test.

2. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.6.4.1.1 (Visual and Mechanical Inspection).

3. Perform insulation-resistance tests pole-to-pole, pole-to-ground, and across open poles at 15,000 volts minimum.

*4. Perform insulation-resistance tests on all control wiring at 1000 volts dc. For units with solid-state components, follow manufacturer’s recommendations.

*5. Perform dissipation-factor/power-factor tests on breaker and bushings.

*6. Perform overpotential test in accordance with manufacturer’s instructions

*7. Perform minimum pick-up voltage test on trip and close coils.

8. Verify trip, close, trip-free, and antipump functions.

9. Trip circuit breaker by operation of each protective device.

ATS – 1999 89 *Optional

Page 100: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) 4. Extra-High-Voltage (cont.) 1. SF6 (cont.)

3. Test Values.

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. Compare time-travel data with manufacturer’s published data.

5. Control wiring insulation resistance should be a minimum of two megohms.

6. Circuit breaker insulation resistance should be in accordance with Table 10.1.

7. Dissipation-factor/power-factor test results shall be compared to manufacturer’s published data. In the absence of manufacturer’s published data, the comparison shall be made to similar breakers.

8. Dissipation-factor/power-factor and capacitance test results should be within ten percent of nameplate rating for bushings.

9. The insulation shall withstand the overpotential test voltage applied

10. Minimum pickup for trip and close coils shall conform to manufacturer’s published data.

90 ATS – 1999 *Optional

Page 101: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES

7.7 Circuit Switchers

1. Visual and Mechanical Inspection

1. Inspect physical and mechanical condition.

2. Confirm correct application of manufacturer’s recommended lubricants.

3. Inspect anchorage, alignment, and grounding.

4. Perform all mechanical operational tests on both the circuit switcher and its operating mechanism.

5. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter. See Section 7.7.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

6. Verify correct operation of SF6 interrupters.

7. Verify correct SF6 pressure.

8. Verify correct operation of isolating switch.

9. Perform timing tests.

10. Record as-found and as-left operation counter readings.

2. Electrical Tests

1. Perform resistance measurements through all connections with a low-resistance ohmmeter, if applicable, in accordance with Section 7.7.1 (Visual and Mechanical Inspection).

2. Perform contact-resistance test of interrupters and isolating switches.

ATS – 1999 91 *Optional

Page 102: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.7 Circuit Switches (cont.)

3. Perform minimum pickup voltage tests on trip and close coils.

4. Trip circuit switcher by operation of each protective device.

5. Verify correct operation of electrical shunt trip of interrupters.

*6. Perform insulation-resistance tests pole-to-pole, pole-to-ground, and across open poles at 15,000 volts minimum.

*7. Perform insulation-resistance tests on all control wiring at 1000 volts dc. For units with solid-state components, follow manufacturer’s recommendations.

8. Perform an overpotential test in accordance with manufacturer’s published data.

3. Test Values

1. Compare bolted connection resistances to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from adjacent poles or similar switchers by more than 50 percent of the lowest value.

4. Minimum pickup for trip and close coils shall conform to manufacturer’s published data.

5. Circuit switcher insulation resistance should be in accordance with Table 10.1.

6. Control wiring insulation resistance should be a minimum of two megohms.

7. The insulation shall withstand the overpotential test voltage applied.

8. Timing tests shall be in accordance with manufacturer’s published data.

92 ATS – 1999 *Optional

Page 103: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES

7.8 Network Protectors, 600 Volt Class

1. Visual and Mechanical Inspection

1. Open the protector and rack it out of the enclosure. Note that the network bus and transformer generally will be energized. Exercise extreme caution. Observe clearances and check for smoothness of operation when racking.

2. Compare equipment nameplate data with drawings and specifications.

3. Inspect physical and mechanical condition.

4. Confirm correct application of manufacturer’s recommended lubricants.

5. Inspect the enclosure door gasket and sight glass for damage.

6. Inspect the interior of the enclosure for debris or damaged components. Inspect insulating components, current carrying parts, and secondary disconnecting devices. Exercise extreme caution when working around the network bus conductors.

7. Check for missing parts on the protector. Verify tightness of electrical and mechanical connections. Tighten as necessary according to manufacturer’s published data.

8. Inspect insulating barriers for damage and correct mounting.

9. Inspect network protector fuse covers, fuses, and blown fuse indicators for damage.

10. Inspect closing motor brushes and commutator surface for damage. Inspect motor brake mechanism, if applicable.

11. Remove and inspect arc chutes for damage.

12. Verify sequence of main and arcing contacts by slow-closing the protector. Adjust as necessary according to manufacturer’s published data.

13. Manually open and close the protector and verify that the mechanism latches correctly in each position. Verify correct operation of the position indicator.

ATS – 1999 93 *Optional

Page 104: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.8 Network Protectors, 600 Volt Class (cont.)

14. Verify electrical connections to network and auxiliary relays. Inspect electromechanical relays for freedom of movement of internal parts.

15. Verify electrical connections to auxiliary switches, secondary disconnects, current transformers, voltage transformers, control power transformers, closing motors, contactors, trip coils, loading resistors, and any other auxiliary devices.

16. Record the as-found and as-left operations counter reading.

17. Perform a leak test on submersible enclosure in accordance with manufacturer’s published data.

2. Electrical Tests

1. Perform insulation-resistance tests at 1000 volts dc for one minute across the contacts of each pole with the protector open and from pole-to-pole and each pole-to-ground with the protector closed.

*2. Perform insulation-resistance tests at 1000 volts dc for one minute on all control wiring and electromechanical components. For units with solid-state components, follow manufacturer’s recommendations.

*3. Verify current transformer ratios in accordance with Section 7.10.

4. Perform a contact resistance test.

*5. Measure the resistance of each protector power fuse.

6. Measure minimum pickup voltage of motor control relay.

*7. Verify that the motor can charge the closing mechanism at the minimum voltage specified by the manufacturer.

8. Measure minimum pickup voltage of the trip actuator. Verify that the actuator resets correctly.

9. Calibrate the network protector relays in accordance with Section 7.9.

94 ATS – 1999 *Optional

Page 105: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.8 Network Protectors, 600 Volt Class (cont.)

10. Perform operational tests.

1. Verify correct operation of all mechanical and electrical interlocks.

2. Verify trip-free operation.

3. Verify correct operation of the auto-open-close control handle.

4. Verify the protector will close with voltage on the transformer side only.

5. Verify the protector will open when the source feeder breaker is opened.

3. Test Values

1. Insulation resistance of the protector components should be in accordance with Table 10.1.

2. Control wiring insulation resistance should be a minimum of two megohms.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. Resistance of power fuses shall be evaluated on a comparative basis.

5. Minimum voltage to operate the trip actuator shall be in accordance with manufacturer’s published data.

6. Minimum acceptable motor closing voltage shall be in accordance with manufacturer’s published data.

7. Network protector shall automatically close upon closing the feeder breaker with normal load demand and shall automatically trip when source feeder breaker is opened.

ATS – 1999 95 *Optional

Page 106: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES

7.9 Protective Relays

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect relays and cases for physical damage. Remove shipping restraint material.

3. Tighten case connections. Inspect cover for correct gasket seal. Clean cover glass. Inspect shorting hardware, connection paddles, and/or knife switches. Remove any foreign material from the case. Verify target reset.

4. Inspect relay for foreign material, particularly in disk slots of the damping and electromagnets. Verify disk clearance. Verify contact clearance and spring bias. Inspect spiral spring convolutions. Inspect disk and contacts for freedom of movement and correct travel. Verify tightness of mounting hardware and connections. Burnish contacts. Inspect bearings and/or pivots.

5. Set relays in accordance with coordination study supplied by owner.

2. Electrical Tests

1. Perform insulation-resistance test on each circuit-to-frame. Determine from the manufacturer’s instructions the allowable procedures for this test for solid-state and microprocessor-based relays.

2. Inspect targets and indicators.

1. Determine pickup and dropout of electromechanical targets.

2. Verify operation of all light-emitting diode indicators.

3. Set contrast for liquid-crystal display readouts.

96 ATS – 1999 *Optional

Page 107: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.9 Protective Relays (cont.)

3. Functional Operation

1. 2/62 Timing Relay

1. Determine time delay.

2. Determine instantaneous contacts.

2. 21 Distance Relay

1. Determine maximum reach.

2. Determine maximum torque angle.

3. Determine offset.

*4. Plot impedance circle.

3. 24 Volts/Hertz Relay

1. Determine pickup frequency at rated voltage.

2. Determine pickup frequency at a second voltage level.

3. Determine time delay.

4. 25 Sync Check Relay

1. Determine closing zone at rated voltage.

2. Determine maximum voltage differential that permits closing at zero degrees.

3. Determine live line, live bus, dead line, and dead bus set points.

4. Determine time delay.

5. Verify dead bus/live line, dead line/live bus and dead bus/dead line control functions.

ATS – 1999 97 *Optional

Page 108: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.9 Protective Relays (cont.)

5. 27 Undervoltage Relay

1. Determine dropout voltage.

2. Determine time delay.

3. Determine the time delay at a second point on the timing curve for inverse time relays.

6. 32 Directional Power Relay

1. Determine minimum pickup at maximum torque angle.

2. Determine closing zone.

3. Determine maximum torque angle.

4. Determine time delay.

5. Verify the time delay at a second point on the timing curve for inverse time relays.

*6. Plot the operating characteristic.

7. 40 Loss of Field (Impedance) Relay

1. Determine maximum reach.

2. Determine maximum torque angle.

3. Determine offset.

*4. Plot impedance circle.

8. 46 Current Balance Relay

1. Determine pickup of each unit.

2. Determine percent slope.

3. Determine time delay.

98 ATS – 1999 *Optional

Page 109: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.9 Protective Relays (cont.)

9. 46N Negative Sequence Current Relay

1. Determine negative sequence alarm level and trip.

2. Determine negative sequence minimum trip level.

3. Determine maximum time delay.

4. Verify two points on the (I2)2t curve.

10. 47 Phase Sequence or Phase Balance Voltage Relay

1. Determine positive sequence voltage to close the normally open contact.

2. Determine positive sequence voltage to open the normally closed contact (undervoltage trip).

3. Verify negative sequence trip.

4. Determine time delay to close the normally open contact with sudden application of 120 percent of pickup.

5. Determine time delay to close the normally closed contact upon removal of voltage when previously set to rated system voltage.

11. 49R Thermal Replica Relay

1. Determine time delay at 300 percent of setting.

2. Determine a second point on the operating curve.

*3. Determine pickup.

12. 49T Temperature (RTD) Relay

1. Determine trip resistance.

2. Determine reset resistance.

ATS – 1999 99 *Optional

Page 110: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.9 Protective Relays (cont.)

13. 50 Instantaneous Overcurrent Relay

1. Determine pickup.

2. Determine dropout.

*3. Determine time delay.

14. 51 Time Overcurrent

1. Determine minimum pickup.

2. Determine time delays at two points on the time current curve.

15. 55 Power Factor Relay

1. Determine tripping angle.

2. Determine time delay.

16. 59 Overvoltage Relay

1. Determine overvoltage pickup.

2. Determine time delay to close the contact with sudden application of 120 percent of pickup.

17. 60 Voltage Balance Relay

1. Determine voltage difference to close the contacts with one source at rated voltage.

*2. Plot the operating curve for the relay.

100 ATS – 1999 *Optional

Page 111: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.9 Protective Relays (cont.)

18. 63 Transformer Sudden Pressure Relay

1. Determine rate-of-rise or the pickup level of suddenly applied pressure in accordance with manufacturer’s specifications.

2. Verify operation of the 63 FPX seal-in circuit.

3. Verify trip circuit to remote breaker.

19. 64 Ground Detector Relay

1. Determine maximum impedance to ground causing relay pickup.

20. 67 Directional Overcurrent Relay

1. Determine directional unit minimum pickup at maximum torque angle.

2. Determine closing zone.

*3. Determine maximum torque angle.

*4. Plot operating characteristics.

5. Determine overcurrent unit pickup.

6. Determine overcurrent unit time delay at two points on the time current curve.

ATS – 1999 101 *Optional

Page 112: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.9 Protective Relays (cont.)

21. 79 Reclosing Relay

1. Determine time delay for each programmed reclosing interval.

2. Verify lockout for unsuccessful reclosing.

3. Determine reset time.

*4. Determine close pulse duration.

5. Verify instantaneous overcurrent lockout.

22. 81 Frequency Relay

1. Verify frequency set points.

2. Determine time delay.

3. Determine undervoltage cutoff.

23. 85 Pilot Wire Monitor

1. Determine overcurrent pickup.

2. Determine undercurrent pickup.

3. Determine pilot wire ground pickup level.

24. 87 Differential

1. Determine operating unit pickup.

2. Determine the operation of each restraint unit.

3. Determine slope.

4. Determine harmonic restraint.

5. Determine instantaneous pickup.

*6. Plot operating characteristics for each restraint.

102 ATS – 1999 *Optional

Page 113: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.9 Protective Relays (cont.)

3. Control Verification

Verify that each of the relay contacts performs its intended function in the control scheme including breaker trip tests, close inhibit tests, 86 lockout tests, and alarm functions.

4. System Tests

After the equipment is initially energized, measure magnitude and phase angle of all inputs and compare to expected values.

5. Test Values

1. Use manufacturer’s recommended tolerances when other tolerances are not specified.

2. When critical test points are specified, the relay shall be calibrated to those points even though other test points may be out of tolerance.

ATS – 1999 103 *Optional

Page 114: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES

7.10 Instrument Transformers

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Verify correct connection of transformers with system requirements.

4. Verify that adequate clearances exist between primary and secondary circuit wiring.

5. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.10.2 and 7.10.3 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

6. Verify that all required grounding and shorting connections provide contact.

7. Verify correct operation of transformer withdrawal mechanism and grounding operation.

8. Verify correct primary and secondary fuse sizes for potential transformers.

2. Electrical Tests - Current Transformers

1. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.10.1 (Visual and Mechanical Inspection).

2. Perform insulation-resistance tests of the current transformer and wiring-to-ground at 1000 volts dc. For units with solid-state components, follow manufacturer’s recommendations.

104 ATS – 1999 *Optional

Page 115: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.10 Instrument Transformers (cont.)

3. Perform a polarity test of each current transformer.

4. Perform a ratio-verification test using the voltage or current method in accordance with ANSI C57.13.1 (IEEE Guide for Field Testing of Relaying Current Transformers).

5. Perform an excitation test on transformers used for relaying applications in accordance with ANSI C57.13.1. (IEEE Guide for Field Testing of Relaying Current Transformers).

6. Measure current circuit burdens at transformer terminals and determine the total burden.

7. When applicable, perform insulation-resistance and dielectric withstand tests on the primary winding with secondary grounded. Test voltages shall be in accordance with Tables 10.13 and 10.9 respectively.

3. Electrical Tests - Voltage Transformers

1. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.10.1 (Visual and Mechanical Inspection).

2. Perform insulation-resistance tests winding-to-winding and each winding-to-ground with test voltage in accordance with Table 10.5. Test voltages shall be applied for one minute. For units with solid-state components, follow manufacturer’s recommendations.

3. Perform a polarity test on each transformer to verify the polarity marks or H1-X1 relationship as applicable.

4. Perform a turns ratio test on all tap positions, if applicable.

5. Measure potential circuit burdens at transformer terminals and determine the total burden.

*6. Perform a dielectric withstand test on the primary windings with the secondary windings connected to ground. The dielectric voltage shall be in accordance with Table 10.9. The test voltage shall be applied for one minute.

ATS – 1999 105 *Optional

Page 116: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.10 Instrument Transformers (cont.)

4. Electrical Tests - Coupling-Capacitance Voltage Transformers

1. Perform all tests from 7.10.3 Voltage Transformers.

2. Measure capacitance of capacitor sections.

3. Measure power factor/dissipation factor in accordance with test equipment manufacturer’s published data.

5. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. Insulation-resistance measurement on any instrument transformer should be not less than that shown in Table 10.1.

5. Polarity results shall agree with system drawings.

6. Compare measured burdens to calculated burdens supplied by owner.

7. Ratio accuracies shall be in accordance with manufacturer’s published data.

8. The insulation shall withstand the overpotential test voltage applied.

9. Capacitance of capicator sections of coupling-capacitance voltage transformers shall be in accordance with manufacturer’s published data.

10. Power factor/dissipation factor shall be in accordance with test equipment manufacturer’s published data.

106 ATS – 1999 *Optional

Page 117: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES

7.11 Metering

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Verify tightness of electrical connections.

4. Inspect cover gasket, cover glass, condition of spiral spring, disk clearance, contacts, and case-shorting contacts, as applicable.

5. Verify freedom of movement, end play, and alignment of rotating disk(s).

2. Electrical Tests

1. Verify accuracy of meters at all cardinal points.

2. Calibrate watthour meters according to manufacturer’s published data.

3. Verify all instrument multipliers.

4. Verify that current transformer and voltage transformer secondary circuits are intact.

ATS – 1999 107 *Optional

Page 118: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES

7.12 Regulating Apparatus 1. Voltage

1. Step-Voltage Regulators

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Inspect impact recorder prior to unloading regulator, if applicable.

4. Verify removal of any shipping bracing and vent plugs after final placement.

5. Verify auxiliary device operation.

6. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.12.1.1.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

7. Verify motor and drive train for correct operation and automatic motor cut-off at maximum lower and maximum raise.

8. Verify correct liquid level in all tanks and bushings.

9. Perform specific inspections and mechanical tests as recommended by the manufacturer.

10. Verify equipment grounding.

11. Verify operation of heaters.

108 ATS – 1999 *Optional

Page 119: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.12 Regulating Apparatus (cont.) 1. Voltage (cont.) 1. Step-Voltage Regulators (cont.)

2. Electrical Tests

1. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.12.1.1.1 (Visual and Mechanical Inspection).

2. Perform insulation-resistance tests on each winding-to-ground in the neutral position with the test voltage in accordance with Table 10.5.

3. Calculate polarization index.

4. Perform insulation power-factor/dissipation-factor tests on windings and in accordance with test equipment manufacturer’s published data.

5. Perform power-factor/dissipation-factor tests (or hot collar watts-loss test) on bushings and in accordance with test equipment manufacturer’s published data.

6. Measure winding-resistance of source windings in the neutral position. Measure resistance of all taps on load windings.

7. Perform special tests and adjustments as recommended by manufacturer.

*8. If the regulator has a separate tap-changer compartment, measure the percentage of oxygen in the nitrogen gas blanket in the main tank.

9. Perform turns ratio test on each voltage step position. Verify that the indicator correctly identifies all tap positions.

10. Perform insulation-resistance test on each winding at each tap position.

11. Verify accurate operation of voltage range limiter.

ATS – 1999 109 *Optional

Page 120: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.12 Regulating Apparatus (cont.) 1. Voltage (cont.) 1. Step-Voltage Regulators (cont.)

12. Verify functioning and accuracy of bandwidth, time delay, voltage and line-drop compensation adjustments.

*13. If regulator has a separate tap-changer compartment, sample insulating liquid in the main tank in accordance with ASTM D3613 and perform dissolved gas analysis in accordance with ANSI/IEEE C57.104 or ASTM D3612.

14. Remove a sample of insulating liquid from the main tank or common tank in accordance with ASTM D923. Sample shall be tested in accordance with the referenced standard.

1. Dielectric breakdown voltage: ASTM D877 and/or ASTM D1816.

2. Acid neutralization number: ANSI/ASTM D-974.

3. Specific gravity: ANSI/ASTM D-1298.

4. Interfacial tension: ANSI/ASTM D971 or ASTM D2285.

5. Color: ANSI/ASTM D1500.

6. Visual condition: ASTM D1524.

*7. Power factor: ASTM D924. Required when the regulator voltage is 46 kV or higher.

*8. Water in insulating liquids: ASTM D1533. Required on 25 kV or higher voltages and on all silicone-filled units.

110 ATS – 1999 *Optional

Page 121: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.12 Regulating Apparatus (cont.) 1. Voltage (cont.) 1. Step-Voltage Regulators (cont.)

15. Remove a sample of insulating liquid in the tap-changer tank in accordance with ASTM D923. Sample shall be tested for the following:

1. Dielectric breakdown voltage: ASTM D877.

2. Color: ANSI/ASTM D-1500.

3. Visual condition: ASTM D1524.

3. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by the manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. Insulation-resistance values at one minute should not be less than the values calculated in accordance with the formula in Table 10.5. Results shall be temperature corrected in accordance with Table 10.14.

5. The polarization index shall be compared to manufacturer’s factory test results. If manufacturer’s data is not available, the acceptance test results will serve as baseline data.

ATS – 1999 111 *Optional

Page 122: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.12 Regulating Apparatus (cont.) 1. Voltage (cont.) 1. Step-Voltage Regulators (cont.)

6. Maximum power factor/dissipation factor of liquid-filled regulators shall be in accordance with manufacturer’s published data. In the absence of manufacturer’s data compare to test equipment manufacturer’s published data. Representative values are indicated in Table 10.3.

7. Investigate bushing power factor/dissipation factor and capacitances that vary from nameplate values by more than ten percent. Investigate any bushing hot collar watts-loss results that exceed the test equipment manufacturer’s published data.

8. Consult manufacturer if winding-resistance test results vary more than one percent from test results of adjacent windings.

9. Turns-ratio test results should maintain a normal deviation between each voltage step and should not deviate more than one-half percent from the calculated voltage ratio.

10. There should be no indication of oxygen present in gas blanket.

11. Insulating liquid test results shall be in accordance with Table 10.4.

.

112 ATS – 1999 *Optional

Page 123: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.12 Regulating Apparatus (cont.) 1. Voltage (cont.)

2. Induction Regulators

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Inspect impact recorder prior to unloading regulator, if applicable.

4. Verify removal of any shipping bracing and vent plugs after final placement.

5. Verify correct auxiliary device operation.

6. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.12.1.2.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

7. Check motor and drive train for correct operation and automatic motor cut-off at maximum lower and maximum raise.

8. Verify appropriate liquid level in all tanks and bushings, if applicable.

9. Perform specific inspections and mechanical tests as recommended by the manufacturer.

10. Verify correct equipment grounding.

ATS – 1999 113 *Optional

Page 124: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.12 Regulating Apparatus (cont.) 1. Voltage (cont.) 2. Induction Regulators (cont.)

2. Electrical Tests

1. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.12.1.2.1 (Visual and Mechanical Inspection).

2. Perform insulation-resistance tests winding-to-winding and each winding-to-ground with test voltage in accordance with Table 10.5.

3. Calculate polarization index.

4. Perform winding insulation power-factor/dissipation-factor tests on windings and in accordance with test equipment manufacturer’s instructions.

5. Perform power-factor/dissipation-factor or hot collar watts-loss tests on bushings and in accordance with test equipment manufacturer’s publishers data.

6. Verify that regulation corresponds to nameplate utilizing the voltage comparison method.

7. Verify that the indicator correctly identifies neutral position.

8. Perform winding resistance tests on each winding at neutral position.

114 ATS – 1999 *Optional

Page 125: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.12 Regulating Apparatus (cont.) 1. Voltage (cont.) 2. Induction Regulators (cont.)

9. Sample insulating liquid, if applicable, in accordance with ASTM D923. Sample shall be tested in accordance with the referenced standard.

1. Dielectric breakdown voltage: ASTM D877 and/or ASTM D1816.

2. Acid neutralization number: ASTM D974.

*3. Specific gravity: ANSI/ASTM D1298.

4. Interfacial tension: ANSI/ASTM D971 or ASTM D2285.

5. Color: ANSI/ASTM D1500.

6. Visual condition: ASTM D1524.

*7. Power factor: ASTM D924 required when the regulator voltage is 46 kV or higher. .

*8. Water in insulating liquids: ASTM D1533. Required when the regulator voltage is 25 kV or higher.

3. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Insulation-resistance value at one minute should not be less than the values calculated in accordance with the formula in Table 10.5. Results shall be temperature corrected in accordance with Table 10.14.

ATS – 1999 115 *Optional

Page 126: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.12 Regulating Apparatus (cont.) 1. Voltage (cont.) 2. Induction Regulators (cont.)

4. The polarization index shall be compared to manufacturer’s factory test results. If manufacturer’s data is not available, this information will serve as baseline data.

5. Maximum power factor of liquid-filled regulators shall be in accordance with manufacturer’s specifications. In the absence of manufacturer’s data compare to test equipment manufacturer’s published data. Representative values are indicated in Table 10.3

6. Bushing power factors and capacitances should not vary by more than ten percent of nameplate values. Any hot collar watts-loss results that exceed the test equipment manufacturer’s recommendations should be investigated.

7. The regulation should be a linear ratio throughout the range between the maximum raise and the maximum lower positions.

8. Insulating liquid test results shall be in accordance with Table 10.4.

9. If winding-resistance measurements vary by more than one percent from adjacent windings, consult manufacturer.

2. Current - Reserved

116 ATS – 1999 *Optional

Page 127: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.12 Regulating Apparatus (cont.)

3. Load Tap-Changers

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Inspect impact recorder, if applicable.

4. Verify removal of any shipping bracing and vent plugs.

5. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.12.3.2.

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data on Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

6. Verify correct auxiliary device operation.

7. Verify motor and drive train for correct operation and automatic motor cut-off at maximum lower and maximum raise.

8. Verify correct liquid level in all tanks.

9. Perform specific inspections and mechanical tests as recommended by the manufacturer.

10. Verify correct equipment grounding.

ATS – 1999 117 *Optional

Page 128: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.12 Regulating Apparatus (cont.) 3. Load Tap-Changers (cont.)

2. Electrical Tests

1. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.12.3.1 (Visual and Mechanical Inspection).

2. Perform insulation-resistance tests in accordance with Section 7.2.

3. Perform insulation power-factor/dissipation-factor tests in accordance with Section 7.2.

*4. Perform winding-resistance tests in accordance with Section 7.2.

5. Perform special tests and adjustments as recommended by the manufacturer.

6. Perform turns-ratio test in accordance with Section 7.2.

7. Remove a sample of insulating liquid in accordance with ASTM D923. The sample shall be tested for the following:

1. Dielectric breakdown voltage: ASTM D877.

2. Color: ANSI/ASTM D1500.

3. Visual condition: ASTM D1524.

118 ATS – 1999 *Optional

Page 129: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.12 Regulating Apparatus (cont.) 3. Load Tap-Changers (cont.)

3. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Insulation-resistance test values at one minute should not be less than the values calculated in accordance with the formula in Table 10.5. Results shall be temperature corrected in accordance with Table 10.14.

3. The polarization index shall be compared to manufacturer’s factory test results. If manufacturer’s data is not available, the acceptance test results will serve as baseline data.

4. Turns ratio test results should maintain a normal deviation between each voltage step and should not deviate more than one-half percent from the calculated voltage ratio

5. Maximum winding insulation power factor/dissipation factor of liquid-filled transformers shall be in accordance with manufacturer’s specifications. Representative values are indicated in Table 10.3. Also, compare with test equipment manufacturer’s published data.

6. Consult manufacturer if winding-resistance test results vary more than one percent from test results of adjacent windings.

7. Insulating liquid test results shall be in accordance with Table 10.4.

ATS – 1999 119 *Optional

Page 130: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES

7.13 Grounding Systems

1. Visual and Mechanical Inspection

1. Verify ground system is in compliance with drawings and specifications.

2. Electrical Tests

1. Perform fall-of-potential test or alternative in accordance with IEEE Standard 81 on the main grounding electrode or system.

2. Perform point-to-point tests to determine the resistance between the main grounding system and all major electrical equipment frames, system neutral, and/or derived neutral points.

3. Test Values

1. The resistance between the main grounding electrode and ground should be no greater than five ohms for commercial or industrial systems and one ohm or less for generating or transmission station grounds unless otherwise specified by the owner. (Reference: ANSI/IEEE Standard 142.)

2. Investigate point-to-point resistance values which exceed 0.5 ohm.

120 ATS – 1999 *Optional

Page 131: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES

7.14 Ground-Fault Protection Systems

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Visually inspect the components for damage and errors in polarity or conductor routing.

1. Verify that ground connection is made ahead of neutral disconnect link and on the line side of any ground fault sensor.

2. Verify that neutral sensors are connected with correct polarity on both primary and secondary.

3. Verify that all phase conductors and the neutral pass through the sensor in the same direction for zero sequence systems.

4. Verify that grounding conductors do not pass through zero sequence sensors.

5. Verify that the grounded conductor is solidly grounded.

3. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.14.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

4. Verify correct operation of all functions of the self-test panel.

5. Verify that the control power transformer has adequate capacity for the system.

ATS – 1999 121 *Optional

Page 132: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.14 Ground-Fault Protection Systems (cont.)

6. Set pickup and time-delay settings in accordance with the settings provided in the owner’s specifications. Record appropriate operation and test sequences as required by NEC Article 230-95.

2. Electrical Tests

1. Measure the system neutral-to-ground insulation resistance with the neutral disconnect link temporarily removed. Replace neutral disconnect link after testing.

2. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.14.1 (Visual and Mechanical Inspection).

*3. Perform insulation resistance tests at 1000 volts dc on all control wiring. For units with solid state components, follow manufacturer’s recommendations.

4. Perform the following pickup tests using primary injection:

1. Verify that the relay does not operate at 90 percent of the pickup setting.

2. Verify pickup is less than 125 percent of setting or 1200 amperes, whichever is smaller.

5. For summation type systems utilizing phase and neutral current transformers, verify correct polarities by applying current to each phase-neutral current transformer pair. This test also applies to molded-case breakers utilizing an external neutral current transformer.

1. The relay shall operate when current direction is the same relative to polarity marks in the two current transformers.

2. The relay shall not operate when current direction is opposite relative to polarity marks in the two current transformers.

6. Measure time delay of the relay at 150 percent or greater of pickup.

122 ATS – 1999 *Optional

Page 133: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.14 Ground-Fault Protection Systems (cont.)

7. Verify reduced control voltage tripping capability: 55 percent for ac systems and 80 percent for dc systems.

8. Verify blocking capability of zone interlock systems.

3. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. System neutral-to-ground insulation resistance shall be a minimum of one megohm.

5. Control wiring insulation resistance values shall be in accordance with Table 10.1.

6. Relay timing shall be in accordance with manufacturer’s specifications but shall not exceed one second at 3000 amperes.

ATS – 1999 123 *Optional

Page 134: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES

7.15 Rotating Machinery 1. Motors

1. AC Motors

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Confirm correct application of manufacturer’s recommended lubricants.

4. Inspect anchorage, and grounding.

5. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.15.1.1.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

6. When applicable, perform special tests such as air gap spacing and pedestal alignment.

7. Verify the absence of unusual mechanical or electrical noise or signs of overheating during initial test run.

2. Electrical Tests - Induction Motors

1. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.15.1.1.1 (Visual and Mechanical Inspection).

124 ATS – 1999 *Optional

Page 135: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.15 Rotating Machinery (cont.) 1. Motors (cont.) 1. AC Motors (cont.)

2. Perform insulation-resistance tests in accordance with ANSI/IEEE Standard 43.

1. Motors larger than 200 horsepower: Test duration shall be for ten minutes. Calculate polarization index.

2. Motors 200 horsepower and less: Test duration shall be for one minute. Calculate the dielectric-absorption ratio.

*3. Perform dc overpotential tests on motors in accordance with ANSI/IEEE Standard 95.

*4. Perform insulation power-factor or dissipation-factor tests.

*5. Perform surge comparison tests.

6. Perform insulation-resistance test on pedestal in accordance with manufacturer’s published data.

7. Test surge protection devices in accordance with Section 7.19.

8. Test motor starter in accordance with Section 7.16.

9. Verify that resistance temperature detector (RTD) circuits conform to drawings. Verify that metering or relaying devices using the RTD’s have the correct rating.

10. Verify that the motor space heater is functional.

11. Perform a rotation test to insure correct shaft direction.

12. Measure running current and evaluate relative to load conditions and nameplate full-load amperes.

ATS – 1999 125 *Optional

Page 136: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.15 Rotating Machinery (cont.) 1. Motors (cont.) 1. AC Motors (cont.)

3. Electrical Tests - Synchronous Motors

1. Perform all tests as indicated in Section 7.15.1.1.2 for induction motors.

*2. Perform a voltage-drop test on all salient poles.

3. Perform insulation-resistance tests on the main rotating field winding, the exciter-field winding, and the exciter-armature winding in accordance with ANSI/IEEE Standard 43.

*4. Perform a high-potential test on the excitation system in accordance with ANSI/IEEE Standard 421B.

5. Measure and record resistance of motor field winding, exciter-stator winding, exciter-rotor windings, and field discharge resistors.

*6. Perform front-to-back resistance tests on diodes and gating tests of silicon controlled rectifiers for field application semiconductors.

7. Prior to initial start, apply voltage to the exciter supply and adjust exciter-field current to nameplate value.

8. Verify that the field application timer and the enable timer for the power-factor relay have been tested and set to the motor drive manufacturer’s recommended values.

126 ATS – 1999 *Optional

Page 137: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.15 Rotating Machinery (cont.) 1. Motors (cont.) 1. AC Motors (cont.)

*9. Record stator current, stator voltage, and field current by strip chart recorder for the complete acceleration period including stabilization time for a normally loaded starting condition. From the recording determine the following information:

1. Bus voltage prior to start.

2. Voltage drop at start.

3. Bus voltage at motor full-load.

4. Locked-rotor current.

5. Current after synchronization but before loading.

6. Current at maximum loading.

7. Acceleration time to near synchronous speed.

8. RPM just prior to synchronization.

9. Field application time.

10. Time to reach stable synchronous operation.

*10. Plot a V-curve of stator current versus excitation current at approximately 50 percent load to check correct exciter operation.

*11. If the range of exciter adjustment and motor loading permit reduce excitation to cause power factor to fall below the trip value of the power-factor relay. Verify relay operation.

ATS – 1999 127 *Optional

Page 138: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.15 Rotating Machinery (cont.) 1. Motors (cont.) 1. AC Motors (cont.)

4. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. Insulation-resistance test results shall be in accordance with Table 10.1. Investigate dielectric absorption ratios less than 1.4 and polarization index ratios less than 2.0 for Class B insulation and Class F insulation.

NOTE: Overpotential, and surge comparison tests shall not be made on motors having values lower than those indicated above.

5. Stator winding dc overpotential test voltage shall be in accordance with NEMA publication MG 1, paragraph 3.01. Test results are dependent on ambient conditions, and evaluation is on a withstand basis. If phase windings can be separately tested, values of leakage current may be compared for similar windings.

6. Vibration amplitudes shall not exceed values shown in Table 10.10.

128 ATS – 1999 *Optional

Page 139: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.15 Rotating Machinery (cont.) 1. Motors (cont.) 1. AC Motors (cont.)

7. Salient pole voltage drop shall be equal for each pole

NOTE: For dc tests each pole (or pair of poles) shall not vary more than two percent from the average. An ac test is more sensitive than a dc test in determining shorted turns. A pole with shorted turns will have a substantially lower voltage than sound coils. Coils adjacent to coils with shorted turns will exhibit slightly lower voltage.

8. The measured resistance values of motor-field windings, exciter-stator windings, exciter-rotor windings, and field-discharge resistors shall be compared to manufacturer’s recommended values.

ATS – 1999 129 *Optional

Page 140: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.15 Rotating Machinery (cont.) 1. Motors (cont.)

2. DC Motors

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Confirm correct application of manufacturer’s recommended lubricants.

4. Inspect anchorage and grounding.

5. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.15.1.2.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

6. When applicable, perform special tests such as air gap spacing and pedestal alignment.

7. Verify the absence of unusual mechanical or electrical noise or signs of overheating during initial test run.

130 ATS – 1999 *Optional

Page 141: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.15 Rotating Machinery (cont.) 1. Motors (cont.) 2. DC Motors (cont.)

2. Electrical Tests

1. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.15.1.2.1 (Visual and Mechanical Inspection).

2. Perform insulation-resistance tests on all windings in accordance with ANSI/IEEE Standard 43.

1. Motors larger than 200 horsepower: Test duration shall be for ten minutes. Calculate polarization index.

2. Motors 200 horsepower and less: Test duration shall be for one minute. Calculate the dielectric absorption ratio.

3. Perform high-potential test in accordance with NEMA publication MG 1, paragraph 3.01.

*4. Perform a voltage-drop test on all field poles.

*5. Perform insulation power-factor or dissipation-factor tests.

6. Measure armature running current and field current or voltage. Compare to nameplate.

7. Perform vibration baseline tests.

8. Verify that all protective devices are in accordance with Section 7.16.

ATS – 1999 131 *Optional

Page 142: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.15 Rotating Machinery (cont.) 1. Motors (cont.) 2. DC Motors (cont.)

3. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. Insulation-resistance test values shall be in accordance with those listed in Table 10.1. Investigate dielectric absorption ratios less than 1.4 and polarization index ratios less than 2.0 for Class B insulation and Class F insulation.

NOTE: Overpotential, and surge comparison tests shall not be made on motors having values lower than those indicated above.

5. Overpotential test evaluation shall be on a withstand basis.

6. Vibration amplitudes shall not exceed values shown in Table 10.10.

132 ATS – 1999 *Optional

Page 143: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.15 Rotating Machinery (cont.)

2. Generators 1. AC Generators

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Confirm correct application of manufacturer’s lubricants.

4. Inspect anchorage and grounding.

5. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.15.2.1.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

6. When applicable, perform special tests such as air gap spacing and pedestal alignment.

7. Verify the absence of unusual mechanical or electrical noise or signs of overheating during initial test run.

ATS – 1999 133 *Optional

Page 144: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.15 Rotating Machinery (cont.) 2. Generators (cont.) 1. AC Generators (cont.)

2. Electrical Tests - Induction Generators

1. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.15.2.1.1 (Visual and Mechanical Inspection).

2. Perform insulation-resistance tests in accordance with ANSI/IEEE Standard 43.

1. All generators: Record insulation-resistance value at one minute, test voltage, and winding temperature.

2. Generators rated above 600 volts: Test duration shall be for 10 minutes. Calculate polarization index.

3. Generators rated 600 volts and less: Test duration shall be for one minute. Calculate the dielectric-absorption ratio.

*3. Perform dc overpotential tests on generators in accordance with ANSI/IEEE Standard 95.

*4. Perform insulation power-factor or dissipation-factor tests.

*5. Perform surge comparison tests.

6. Verify operation of overspeed protection on prime mover.

7. Verify that resistance temperature detector (RTD) circuits conform to drawings. Verify that metering or relay devices using the RTD’s have the correct rating.

8. Verify that the generator space heater(s) is functional.

134 ATS – 1999 *Optional

Page 145: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.15 Rotating Machinery (cont.) 2. Generators (cont.) 1. AC Generators (cont.)

9. Perform load test in accordance with manufacturer’s recommendations.

*10. Perform vibration baseline test.

3. Electrical Tests - Synchronous Generators

NOTE: If generator is in a health care facility, also perform tests in accordance with NFPA 110.

1. Perform all tests as indicated in 7.15.2.1.2 for induction generators.

*2. Perform an ac voltage-drop test on all salient poles.

3. Perform insulation-resistance tests on the main field winding, the exciter-field winding, and the exciter-armature winding in accordance with ANSI/IEEE Standard 43.

*4. Perform a high-potential test on the excitation system in accordance with NEMA publication MG 1, paragraph 3.01.

5. Measure and record resistance of generator field winding, exciter-stator winding, and exciter-rotor windings.

*6. Perform front-to-back resistance tests on diodes and gating test of silicon controlled rectifiers for field application semiconductors. Perform resistance test on any MOV or surge suppression devices.

*7. Simulate the following transient conditions to verify generator operation in accordance with manufacturer’s specifications. Load to be maximum attainable, up to full load.

1. Drop out of generator under load.

2. Reconnection of generator with load.

ATS – 1999 135 *Optional

Page 146: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.15 Rotating Machinery (cont.) 2. Generators (cont.) 1. AC Generators (cont.)

3. Transfer load to utility power system and back to generator.

4. Generator output voltage deviation from no load to 25 percent load and return, and 60 percent to 100 percent and return.

4. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by the manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. Insulation-resistance test results shall be in accordance with values listed in Table 10.1. Investigate dielectric absorption ratios less than 1.4 and polarization index ratios less than 2.0 for Class B insulation and Class F insulation.

NOTE: Overpotential and surge comparison tests shall not be made on generators having insulation-resistance test values lower than those indicated above.

5. Stator winding dc overpotential test voltage shall be in accordance with NEMA publication MG 1, paragraph 3.01. Test results are dependent on ambient conditions, and evaluation is on a withstand basis. If phase windings can be separately tested, values of leakage current may be compared for similar windings.

136 ATS – 1999 *Optional

Page 147: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.15 Rotating Machinery (cont.) 2. Generators (cont.) 1. AC Generators (cont.)

6. Salient pole voltage drop shall be equal for each pole. Investigate values that differ by more than ten percent.

7. The measured resistance values of generator-field winding, exciter-stator winding, and exciter-rotor windings shall be compared to manufacturer’s recommended values.

ATS – 1999 137 *Optional

Page 148: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.15 Rotating Machinery (cont.) 2. Generators (cont.)

2. DC Generators

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Confirm correct application of manufacturer’s lubricants.

4. Inspect anchorage and grounding.

5. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.15.2.2.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

6. When applicable, perform special tests such as air gap spacing and pedestal alignment.

7. Verify the absence of unusual mechanical or electrical noise or signs of overheating during initial test run.

8. Inspect brushes and brush rigging.

138 ATS – 1999 *Optional

Page 149: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.15 Rotating Machinery (cont.) 2. Generators (cont.) 2. DC Generators (cont.)

2. Electrical Tests

1. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.15.2.2.1 (Visual and Mechanical Inspection).

2. Perform insulation-resistance tests on all windings in accordance with ANSI/IEEE Standard 43.

1. All generators: Record insulation-resistance value of armature

and fields at 1 minute, test voltage, and winding temperature.

2. Generator armatures larger than 150 kilowatts: Test duration shall be for 10 minutes. Calculate

polarization index.

3. Generator armatures rated 150 kilowatts and less: Test duration shall be for 1 minute. Calculate the dielectric-absorption ratio.

*3. Perform overpotential test in accordance with NEMA publication MG 1, paragraph 3.01.

*4. Perform an ac voltage-drop test on all field poles.

5. Measure armature running current and field current or voltage. Compare to nameplate.

*6. Perform vibration baseline test.

ATS – 1999 139 *Optional

Page 150: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.15 Rotating Machinery (cont.) 2. Generators (cont.) 2. DC Generators (cont.)

3. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by the manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. Insulation-resistance test results shall comply with values listed in Table 10.1. Investigate dielectric absorption ratios less than 1.4 and polarization index ratios less than 2.0 for Class B insulation and Class F insulation.

NOTE: Overpotential tests shall not be made on generators having insulation-resistance test values lower than those indicated above.

5. Overpotential test evaluation shall be on a withstand basis.

140 ATS – 1999 *Optional

Page 151: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES

7.16 Motor Control 1. Motor Starters

1. Low-Voltage

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Inspect and adjust contact gap, wipe, alignment, and pressure in accordance with manufacturer’s published data.

*4. Motor-Running Protection

1. Compare overload element rating with motor full-load current rating to verify correct sizing.

2. If power-factor correction capacitors are connected on the load side of the overload protection, include the effect of the capacitive reactance in determining appropriate overload element size.

3. If motor-running protection is provided by fuses, verify correct rating considering motor characteristics and power-factor correction capacitors.

5. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.16.1.1.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

ATS – 1999 141 *Optional

Page 152: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.16 Motor Control (cont.) 1. Motor Starters (cont.) 1. Low-Voltage (cont.)

2. Electrical Tests

1. Insulation Tests

1. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.16.1.1.1 (Visual and Mechanical Inspection).

2. Measure insulation resistance of each combination starter, phase-to-phase and phase-to-ground, with the starter contacts closed and the protective device open. Test voltage shall be in accordance with Table 10.1. Refer to manufacturer’s instructions for devices with solid-state components.

*3. Measure insulation resistance of each control circuit-to-ground.

*4. Perform an insulation resistance test at 1000 volts dc on all control wiring. For units with solid-state components, follow manufacturer’s recommendations.

2. Test the motor overload relay elements by injecting primary current through the overload circuit and monitoring trip time of the overload element.

NOTE: Test times for thermal trip units will, in general, be longer than manufacturer’s curve if single-pole testing is performed. Optionally test with all poles in series for time test and each pole separately for comparison. (Refer to ANSI/NEMA ICS 2, Part 4.)

3. Test circuit breakers, including motor circuit protectors, in accordance with Section 7.6.1.1.

4. Perform operational tests by initiating control devices.

142 ATS – 1999 *Optional

Page 153: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.16 Motor Control (cont.) 1. Motor Starters (cont.) 1. Low-Voltage (cont.)

3. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. Insulation-resistance values shall be in accordance with Table 10.1.

5. Control wiring insulation test resistance should be a minimum of two megohms.

6. Overload trip times shall be in accordance with manufacturer’s published data.

ATS – 1999 143 *Optional

Page 154: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.16 Motor Control (cont.) 1. Motor Starters (cont.)

2. Medium-Voltage

1. Visual and Mechanical Inspection

1. Compare equipment nameplate information with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Confirm correct application of manufacturer’s recommended lubricants.

4. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.16.1.2.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

5. Test all electrical and mechanical interlock systems for correct operation and sequencing.

6. Inspect insulators for evidence of damage or contaminated surfaces.

7. Verify correct barrier and shutter installation and operation.

8. Exercise all active components and confirm correct operation of all indicating devices.

144 ATS – 1999 *Optional

Page 155: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.16 Motor Control (cont.) 1. Motor Starters (cont.) 2. Medium-Voltage (cont.)

9. Inspect contactors.

1. Verify mechanical operation.

2. Inspect and adjust contact gap, wipe, alignment, and pressure in accordance with manufacturer’s published data.

10. Compare overload protection rating with motor nameplate to verify correct size. Set adjustable or programmable devices according to the protective device coordination study.

2. Electrical Tests

1. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.16.1.2.1 (Visual and Mechanical Inspection).

2. Perform ratio and polarity tests on all current and voltage transformers in accordance with Section 7.10.

*3. Perform system function tests at 1000 volts dc on control wiring. For units with solid-state components, follow manufacturer’s recommendations.

4. Perform control wiring performance test. Use the elementary diagrams to identify each remote control and protective device. Verify satisfactory performance of each control feature.

5. Test control power transformers in accordance with Section 7.1.2.11.

6. Perform insulation-resistance tests on contactor, phase-to-ground, phase-to-phase, and across the open contacts for one minute in accordance with Table 10.1.

ATS – 1999 145 *Optional

Page 156: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.16 Motor Control (cont.) 1. Motor Starters (cont.) 2. Medium-Voltage (cont.)

*7. Perform an overpotential test, in accordance with manufacturer’s published data. If manufacturer has no recommendation for this test, it shall be in accordance with Table 10.11.

8. Perform vacuum bottle integrity test (overpotential), if applicable, across each vacuum bottle with the contacts in the open position in strict accordance with manufacturer’s instructions. Do not exceed maximum voltage stipulated for this test.

9. Perform contact resistance tests.

10. Measure blowout coil circuit resistance.

11. Measure resistance of power fuses.

12. Energize contactor using an auxiliary source. Adjust armature to minimize operating vibration where applicable.

13. Test motor overload relay elements by injecting primary current through overload circuit and monitoring trip time of the overload element.

NOTE: Test times for thermal trip units will, in general, be longer than manufacturer’s curve if single-pole testing is performed. Optionally test with all poles in series for time test and each pole separately for comparison.

14. Test ground-fault protection by injecting primary current through sensor. Confirm pickup level and timing.

15. If solid-state or microprocessor-type protective relaying is used, test in accordance with Section 7.9.

16. Verify operation of cubicle space heater.

146 ATS – 1999 *Optional

Page 157: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.16 Motor Control (cont.) 1. Motor Starters (cont.) 2. Medium-Voltage (cont.)

3. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque values should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. Insulation-resistance values for bus, control wiring, and control power transformers shall be in accordance with manufacturer’s published data. In the absence of manufacturer’s published data, use Table 10.1. Values of insulation resistance less than this table or manufacturer’s minimum shall be investigated. Overpotential tests shall not proceed until insulation-resistance levels are raised above minimum values.

5. The insulation shall withstand the overpotential test voltage applied.

6. Resistance values should not deviate by more than 15 percent between identical fuses.

7. Overload trip times shall be in accordance with manufacturer’s published data.

ATS – 1999 147 *Optional

Page 158: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.16 Motor Control (cont.)

2. Motor Control Centers 1. Low-Voltage

1. Refer to Section 7.1, Switchgear and Switchboard Assemblies, for appropriate inspections and tests of the motor control center bus.

2. Refer to Section 7.5.1.1, Low-Voltage Switches, for appropriate inspections and tests of the motor control center switches.

3. Refer to Section 7.6.1, Low-Voltage Circuit Breakers, for appropriate inspections and tests of the motor control center circuit breakers.

4. Refer to Section 7.16.1, Low-Voltage Motor Starters, for appropriate inspections and tests of the motor control center starters.

2. Medium-Voltage

1. Refer to Section 7.1, Switchgear and Switchboard Assemblies, for appropriate inspections and tests of the motor control center bus.

2. Refer to Section 7.5.1.2, Medium-Voltage Air Switches, for appropriate inspections and tests of the motor control center switches.

3. Refer to Section 7.6.2, Medium-Voltage Circuit Breakers, for appropriate inspections and tests of the motor control center circuit breakers.

4. Refer to Section 7.16.2, Medium-Voltage Motor Starters, for appropriate inspections and tests of the motor control center starters.

148 ATS – 1999 *Optional

Page 159: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES

7.17 Adjustable Speed Drive Systems

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Ensure vent path openings are free from debris and that heat transfer surfaces are not fouled by oil, dust, or dirt.

4. Motor Running Protection

1. Compare drive overcurrent setpoints with motor full-load current rating to verify correct settings.

2. If drive is used to operate multiple motors, compare individual overload element ratings with motor full-load current ratings.

3. Apply minimum and maximum speed setpoints. Confirm setpoints are within limitations of the load coupled to the motor.

5. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.17.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

ATS – 1999 149 *Optional

Page 160: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.17 Adjustable Speed Drive Systems (cont.)

2. Electrical Tests

1. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.17.1 (Visual and Mechanical Inspection).

2. Test the motor overload relay elements by injecting primary current through the overload circuit and monitoring trip time of the overload element.

NOTE: Test times for thermal trip units will, in general, be longer than the manufacturer’s curve if single-pole testing is performed. Optionally test with all poles in series for time test and each pole separately for comparison (Refer to ANSI/NEMA ICS 2, Part 4.)

3. Perform startup of drive in accordance with manufacturer’s published data. Calibrate drive to the system’s minimum and maximum speed control signals.

4. Perform operational tests by initiating control devices.

1. Check motor rotation operating on the drive and on the bypass.

2. Slowly vary drive speed between minimum and maximum. Observe motor and load for unusual vibration. If excessive vibration occurs enter these critical frequencies into the drive’s programmed step-over frequencies so operation at these speeds will not occur.

3. Verify operation of drive from remote start/stop and speed control signals.

4. Measure and record total harmonic distortion of current and voltage in accordance with IEEE 1159-1995.

5. Test input circuit breaker by primary injection in accordance with Section 7.6.

150 ATS – 1999 *Optional

Page 161: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.17 Adjustable Speed Drive systems (cont.)

6. Test for the following parameters in accordance with relay calibration procedures outlined in Section 7.9 protective relays:

1. Input phase loss protection (7.9.3.10)

2. Input overvoltage protection (7.9.3.16)

3. Output phase rotation (7.9.3.10)

4. Overtemperature protection (7.9.3.11)

5. DC overvoltage protection (7.9.3.16)

6. Overfrequency protection (7.9.3.22)

7. Drive overload protection (7.9.3.14 or 7.6.1.1)

8. Fault alarm outputs (7.9.3 or 7.9.4)

3. Test Values

1. Overload test trip times at 300 percent of overload element rating shall be in accordance with manufacturer’s published time-current curve.

2. Harmonic values at the point of common coupling shall be in accordance with ANSI/IEEE 519.

3. When critical test points are specified, the relay shall be calibrated to specified critical points even though other test points may be out of tolerance.

4. Bolt-torque levels shall be in accordance with Table 10.12 unless otherwise specified by the manufacturer.

ATS – 1999 151 *Optional

Page 162: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES

7.18 Direct-Current Systems 1. Batteries

1. Visual and Mechanical Inspection

1. All Cell Types

1. Compare equipment nameplate with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.18.1.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

4. Verify adequacy of battery support racks or cabinets, mounting, anchorage, and clearances.

5. Inspect for evidence of corrosion at terminals, connections, racks or cabinet.

6. Verify correct application of manufacturer’s approved corrosion inhibiting grease on contact surface areas of all cell-to-cell and terminal connections including connection hardware.

7. Verify ventilation of battery room or enclosure.

8. Verify existence of suitable eyewash equipment.

152 ATS – 1999 *Optional

Page 163: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.18 Direct-Current Systems (cont.) 1. Batteries (cont.)

2. Vented Lead-Acid Cells

1. Verify correct electrolyte levels of each cell.

2. Measure electrolyte specific gravity and temperature of all cells.

3. Verify presence and correct installation of flame arresters.

3. Nickel Cadmium Cells

1. Verify correct electrolyte levels of each cell.

2. Measure electrolyte temperature.

3. Verify presence and correct installation of flame arresters on vented cells.

4. Valve Regulated lead Acid (VRLA) Cells

1. Check for excessive jar/cover distortion.

2. Measure temperature of the negative terminal of each cell.

2. Electrical Tests - All Cell Types

1. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.18.1.1 (Visual and Mechanical Inspection).

2. Set charger float and equalizing voltage levels.

3. Measure each cell voltage and total battery voltage with charger energized and in float mode of operation.

4. Measure intercell/jar connection resistance.

*5. Perform cell impedance test.

ATS – 1999 153 *Optional

Page 164: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.18 Direct-Current Systems (cont.) 1. Batteries (cont.)

6. Measure ac ripple voltage and current imposed on the battery (VRLA only).

7. Perform a capacity load test in accordance with manufacturer’s specifications and ANSI/IEEE standards.

ANSI/IEEE Std 450-1994. Recommended Practice for Maintenance, Testing and Replacement of Large Lead Storage Batteries for Generating Stations and Substations.

ANSI/IEEE Std 1106-1995. Recommended Practice for Maintenance, Testing and Replacement of Nickel-Cadmium Storage Batteries for Generating Stations and Substations.

ANSI/IEEE Std 1188-1996. Recommended Practice for Maintenance, Testing, and Replacement of Valve-Regulated Lead-Acid (VRLA) Batteries for Stationary Applications.

3. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. Specific gravity shall be in accordance with manufacturer’s recommended values.

5. Temperature differential between cells should not be greater than 3°C (5°F) for lead acid cells and 5°C (9°F) for nickel cadmium cells.

6 Temperature of the negative terminal of VRLA cells should not be greater than 3°C (5°F) above ambient in a free standing condition.

154 ATS – 1999 *Optional

Page 165: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.18 Direct-Current Systems (cont.) 1. Batteries (cont.)

7. Electrolyte level shall be at the manufacturer’s recommended reference point for vented lead acid cells and at the high level mark for nickel cadmium cells.

8. Cell voltage shall be in accordance with manufacturer’s published data.

9. Battery terminal float and equalize voltage shall be within the manufacturer’s recommended operating range for the cell type.

10. Intercell connection resistance shall be within the manufacturer’s allowable values for the cell type and application. Intercell/jar resistance should not vary by more than ten percent or five microhms, whichever is greater, over the average for each type of connection (i.e., intercell, intertier, interrack).

11. Consult the battery manufacturer for cell internal ohmic values in excess of 20 percent from the average.

12. Capacity load tests of new installation may be less than rated capacity when delivered. Unless 100 percent capacity upon delivery is specified for lead acid cells, initial capacity can be as low as 90 percent of rated capacity. Capacity usually increases in the first several years until rated capacity is reached.

13. AC ripple voltage and current imposed on VRLA batteries shall be within acceptable limits for the battery as specified by the battery manufacturer.

ATS – 1999 155 *Optional

Page 166: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.18 Direct-Current Systems (cont.)

2. Battery Chargers

1. Visual and Mechanical Inspection

1. Compare equipment nameplate with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.18.2.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

2. Electrical Tests

1. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.18.2.1 (Visual and Mechanical Inspection).

2. Verify correct ac input voltage.

3. Verify charger output voltage regulation from no load to full load.

4. Verify output voltage range in both float and equalize modes.

5. Measure ac input current with charger at full rated load.

6. Measure the current limit output of the charger.

7. Measure charger ac ripple voltage and current.

156 ATS – 1999 *Optional

Page 167: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.18 Direct-Current Systems (cont.) 2. Battery Chargers (cont.)

8. Verify temperature compensation function of charger, if applicable.

9. Verify charger instrumentation and alarms.

10. Set the float and equalized voltages in accordance with battery manufacturer’s published data.

3. Test Values

1. Output voltage regulation shall be within charger specification.

2. Output voltage range shall be within charger specification.

3. AC input current with charger at full rated load shall be within charger specification.

4. Current limit output and voltage shall be within charger specification.

5. AC ripple voltage and current shall be within charger specification and acceptable limits of the battery as specified by the battery manufacturer.

6. Temperature compensation function of the charger shall be within specification of the charger and battery.

3. Rectifiers - Reserved

ATS – 1999 157 *Optional

Page 168: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES

7.19 Surge Arresters 1. Low-Voltage Surge Protection Devices

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Inspect for correct mounting and adequate clearances.

4. Inspect all bolted electrical connections for high resistance using one of the following methods.

1. Use of low-resistance ohmmeter in accordance with Section 7.19.1.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

5. Verify that the ground lead on each device is individually attached to a ground bus or ground electrode.

2. Electrical Tests

1. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.19.1.1 (Visual and Mechanical Inspection).

2. Perform insulation-resistance tests. Use manufacturer’s recommended values or Table 10.1.

3. Test grounding connection in accordance with Section 7.13.

158 ATS – 1999 *Optional

Page 169: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.19 Surge Arresters (cont.) 1. Low-Voltage Surge-Protection Devices (cont.)

3. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. Insulation-resistance values should be in accordance with Table 10.1.

5. Resistance between the arrester ground terminal and the ground system should be less than 0.5 ohm.

ATS – 1999 159 *Optional

Page 170: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.19 Surge Arresters (cont.)

2. Medium- and High-Voltage Surge Protection Devices

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Inspect for correct mounting and adequate clearances.

4. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.19.2.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

5. Verify that the ground lead on each device is individually attached to a ground bus or ground electrode.

6. Verify that stroke counter, if present, is correctly mounted and electrically connected.

2. Electrical Tests

1. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.19.2.1 (Visual and Mechanical Inspection).

2. Perform insulation-resistance tests. Use manufacturer’s recommended values or Table 10.1.

3. Test grounding connection in accordance with Section 7.13.

160 ATS – 1999 *Optional

*4. Perform a watts-loss test.

Page 171: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.19 Surge Arresters (cont.) 2. Medium- and High-Voltage Surge Protection Devices (cont.)

3. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. Insulation-resistance values should be in accordance with Table 10.1.

5. Compare watts loss to similar units.

6. Resistance between the arrester ground terminal and the ground system should be less than 0.5 ohm.

ATS – 1999 161 *Optional

Page 172: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES

7.20 Capacitors and Reactors 1. Capacitors

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Inspect capacitors for correct mounting and required clearances.

4. Verify that capacitors are electrically connected in their specified configuration.

5. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.20.1.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

2. Electrical Tests

1. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.20.1.1 (Visual and Mechanical Inspection).

2. Perform insulation-resistance tests from terminal(s) to case for one minute on capacitors with more than one bushing. Test voltage and minimum resistance shall be in accordance with manufacturer’s published data or Table 10.1.

3. Measure the capacitance of all terminal combinations.

4. Measure resistance of internal discharge resistors.

162 ATS – 1999 *Optional

Page 173: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.20 Capacitors and Reactors (cont.) 1. Capacitors (cont.)

3. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. Insulation-resistance should be in accordance with Table 10.1.

5. Investigate capacitance values differing from manufacturer’s published data.

6. Investigate discharge resistor values differing from manufacturer’s published data. In accordance with NEC Article 460, residual voltage of a capacitor shall be reduced to 50 volts in the following time intervals after being disconnected from the source of supply:

Rated Voltage Discharge Time

>600V 1 minute >600V 5 minutes

2. Capacitor Control Devices - Reserved

ATS – 1999 163 *Optional

Page 174: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.20 Capacitors and Reactors (cont.)

3. Reactors (Shunt and Current Limiting) 1. Dry-Type

1. Visual and Mechanical Inspections

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Verify removal of any shipping bracing, brackets, or fixtures, after final placement.

4. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.20.3.1.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

5. Verify that all frame and enclosure grounds are correct.

6. Verify that tap connections are as specified, if applicable.

164 ATS – 1999 *Optional

Page 175: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.20 Capacitors and Reactors (cont.) 3. Reactors (Shunt and Current Limiting) (cont.) 1. Dry-Type (cont.)

2. Electrical Tests

1. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.20.3.1.1 (Visual and Mechanical Inspection).

2. Perform winding-to-ground insulation-resistance tests in accordance with Table 10.1.

3. Measure winding resistance.

*4. Perform overpotential tests on each winding-to-ground.

3. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Insulation-resistance should be in accordance with Table 10.1.

4. If winding-resistance test results vary more than one percent from factory tests, consult the manufacturer.

5. AC overpotential test shall not exceed 75 percent of factory test voltage for one minute duration. DC overpotential test shall not exceed 100 percent of the factory RMS test voltage for one minute duration. The insulation shall withstand the overpotential test voltage applied.

ATS – 1999 165 *Optional

Page 176: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.20 Capacitors and Reactors (cont.) 3. Reactors (Shunt and Current Limiting) (cont.)

2. Liquid-Filled

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Inspect impact recorder prior to unloading, if applicable.

4. Verify removal of any shipping bracing after final placement.

5. Verify settings and operation of all temperature devices, if applicable.

6. Verify that cooling fans and pumps operate correctly and that fan and pump motors have correct overcurrent protection, if applicable.

7. Verify operation of all alarm, control, and trip circuits from temperature and level indicators, pressure relief device, and fault pressure relay, if applicable.

8. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.20.3.2.2(Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

9. Verify correct liquid level in all tanks and bushings.

166 ATS – 1999 *Optional

Page 177: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.20 Capacitors and Reactors (cont.) 3. Reactors (Shunt and Current Limiting) (cont.) 2. Liquid-Filled (cont.)

10. Verify that positive pressure is maintained on nitrogen-blanketed reactors.

11. Perform specific inspections and mechanical tests as recommended by manufacturer.

12. Verify correct equipment grounding.

13. Verify that tap connections are as specified, if applicable.

2. Electrical Tests

1. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.20.3.2.1 (Visual and Mechanical Inspection).

2. Perform winding-to-ground, in accordance with Table 10.5.

3. Calculate polarization index.

4. Perform insulation power-factor/dissipation-factor tests on winding in accordance with the test equipment manufacturer’s published data.

5. Perform power-factor/dissipation-factor or hot collar watts-loss tests on bushings in accordance with the test equipment manufacturer’s published data.

6. Measure winding resistance.

7. Measure the percentage of oxygen in the nitrogen gas blanket, if applicable.

ATS – 1999 167 *Optional

Page 178: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.20 Capacitors and Reactors (cont.) 3. Reactors (Shunt and Current Limiting) (cont.) 2. Liquid-Filled (cont.)

8. Remove a sample of insulating liquid in accordance with ASTM D-923. Sample shall be tested for the following:

1. Dielectric breakdown voltage: ASTM D-877 and/or ASTM D-1816.

2. Acid neutralization number: ASTM D-974.

*3. Specific gravity: ASTM D-1298.

4. Interfacial tension: ASTM D-971 or ASTM D-2285.

5. Color: ASTM D-1500.

6. Visual Condition: ASTM D-1524.

7. Water in insulating liquids: ASTM D-1533. (Required on 25 kV or higher voltages and on all silicone-filled units.)

*8. Measure dissipation-factor or power-factor in accordance with ASTM D-924.

9. Remove a sample of insulating liquid in accordance with ASTM D-3613 and perform dissolved-gas-analysis (DGA) in accordance with ANSI/IEEE C57.104 or ASTM D-3612.

168 ATS – 1999 *Optional

Page 179: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.20 Capacitors and Reactors (cont.) 3. Reactors (Shunt and Current Limiting) (cont.) 2. Liquid-Filled (cont.)

2. Test Values

1. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

2. Insulation-resistance test values should not be less than values calculated in accordance with the formula in Table 10.5. Results shall be temperature corrected in accordance with Table 10.14.

3. The polarization index shall be greater than 1.0 and shall be recorded for future reference.

4. Maximum power factor/dissipation factor of liquid-filled reactors shall be in accordance with manufacturer’s published data. In the absence of manufacturer’s data, compare to test equipment manufacturer’s published data. Representative values are indicated in Table 10.3.

5. Investigate bushing power factor/dissipation factor and capacitances that vary from nameplate values by more than ten percent. Investigate any bushing hot collar watts-loss results that exceed the test equipment manufacturer’s published data.

6. Consult manufacturer if winding-resistance measurements vary more than one percent from factory tests.

7. Investigate presence of oxygen in the nitrogen gas blanket.

8. Insulating liquid test results shall be in accordance with Table 10.4.

9. Evaluate results of dissolved-gas-analysis in accordance with IEEE Standard C57.104. Use results as baseline for future tests.

ATS – 1999 169 *Optional

Page 180: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES

7.21 Outdoor Bus Structures

1. Visual and Mechanical Inspection

1. Compare bus arrangement with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.21.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

2. Electrical Tests

1. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.21.1 (Visual and Mechanical Inspection).

*2. Measure insulation resistance of each bus, phase-to-ground with other phases grounded.

3. Perform overpotential test on each bus phase, phase-to-ground with other phases grounded. Potential application shall be for one minute.

4. Measure resistance of bus section joints with low-resistance ohmmeter.

170 ATS – 1999 *Optional

Page 181: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.21 Outdoor Bus Structures (cont.)

3. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. Insulation-resistance tests should be in accordance with Table 10.1.

5. Compare measured bus connector joint resistance to an equal length of bus and to similar connections.

6. Overpotential test voltage shall be in accordance with manufacturer’s published data or Table 10.11. The insulation shall withstand the overpotential test voltage applied.

ATS – 1999 171 *Optional

Page 182: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES

7.22 Emergency Systems 1. Engine Generator

NOTE: The prime mover is not addressed in these specifications.

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Inspect correct anchorage and grounding.

2. Electrical and Mechanical Tests

1. Perform an insulation-resistance test on generator winding with respect to ground in accordance with ANSI/IEEE Standard 43.

2. Calculate polarization index.

3. Test protective relay devices in accordance with Section 7.9.

4. Perform phase-rotation test to determine compatibility with load requirements.

5. Functionally test engine shutdown for low oil pressure, overtemperature, overspeed, and other features as applicable.

6. Perform vibration baseline test. Plot amplitude versus frequency for each main bearing cap.

7. Conduct performance test in accordance with ANSI/NFPA Standard 110, Section 5-13 (Installation Acceptance).

8. Verify correct functioning of governor and regulator.

172 ATS – 1999 *Optional

Page 183: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.22 Emergency Systems (cont.) 1. Engine Generator (cont.)

3. Test Values

1. Polarization index values shall be in accordance with ANSI/IEEE Standard 43.

2. Vibration levels shall be in accordance with manufacturer’s published data.

3. Performance tests shall conform to manufacturer’s published data and ANSI/NFPA Standard 110.

ATS – 1999 173 *Optional

Page 184: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.22 Emergency Systems (cont.)

2. Uninterruptible Power Systems

1. Visual and Mechanical Inspection

1. Compare equipment nameplate information with drawings and specifications.

2. Inspect physical, and mechanical condition.

3. Check for correct anchorage, required area clearances, and alignment.

4. Verify that fuse sizes and types correspond to drawings.

5. Test all electrical and mechanical interlock systems for correct operation and sequencing.

6. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.22.2.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

7. Check operation of forced ventilation.

8. Verify that filters are in place and/or vents are clear.

174 ATS – 1999 *Optional

Page 185: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.22 Emergency Systems (cont.) 2. Uninterruptible Power Systems (cont.)

2. Electrical Tests

1. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.22.2.1 (Visual and Mechanical Inspection).

2. Test static transfer from inverter to bypass and back. Use normal load, if possible.

3. Set free-running frequency of oscillator.

4. Test dc undervoltage trip level on inverter input breaker. Set according to manufacturer’s published data.

5. Test alarm circuits.

6. Verify sync indicators for static switch and bypass switches.

7. Perform electrical tests for UPS system breakers in accordance with Section 7.6.1.

8. Perform electrical tests for UPS system automatic transfer switches in accordance with Section 7.22.3.

9. Perform electrical tests for UPS system batteries in accordance with Section 7.18.

10. Perform electrical tests for UPS rotating machinery in accordance with Section 7.15.

ATS – 1999 175 *Optional

Page 186: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.22 Emergency Systems (cont.) 2. Uninterruptible Power Systems (cont.)

3. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

176 ATS – 1999 *Optional

Page 187: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.22 Emergency Systems (cont.)

3. Automatic Transfer Switches

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Confirm correct application of manufacturer’s recommended lubricants.

4. Verify that manual transfer warnings are attached and visible.

5. Verify tightness of all control connections.

6. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.22.3.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

7. Perform manual transfer operation.

8. Verify positive mechanical interlocking between normal and alternate sources.

2. Electrical Tests

1. Perform a contact-resistance test.

2. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.22.3.1 (Visual and Mechanical Inspection).

ATS – 1999 177 *Optional

Page 188: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.22 Emergency Systems (cont.) 3. Automatic Transfer Switches (cont.)

3. Perform insulation-resistance on each pole, phase-to-phase and phase-to-ground with switch closed and across each open pole for one minute. Perform tests in both source positions. Test voltage shall be in accordance with manufacturer’s published data or Table 10.1.

4. Calculate polarization index.

5. Verify settings and operation of control devices.

6. Calibrate and set all relays and timers in accordance with Section 7.9.

7. Perform automatic transfer tests:

1. Simulate loss of normal power.

2. Return to normal power.

3. Simulate loss of emergency power.

4. Simulate all forms of single-phase conditions.

8. Verify correct operation and timing of the following functions:

1. Normal source voltage-sensing relays.

2. Engine start sequence.

3. Time delay upon transfer.

4. Alternate source voltage-sensing relays.

5. Automatic transfer operation.

6. Interlocks and limit switch function.

7. Time delay and retransfer upon normal power restoration.

8. Engine cooldown and shutdown feature.

178 ATS – 1999 *Optional

Page 189: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.22 Emergency Systems (cont.) 3. Automatic Transfer Switches (cont.)

3. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Minimum insulation-resistance shall be in accordance with manufacturer’s published data or Table 10.1.

4. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

7.23 Telemetry/Pilot Wire/Scada - Reserved

ATS – 1999 179 *Optional

Page 190: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES

7.24 Automatic Circuit Reclosers and Line Sectionalizers 1. Automatic Circuit Reclosers, Oil/Vacuum

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Inspect anchorage, alignment, and grounding.

4. Perform all mechanical operation and contact alignment tests on both the recloser and its operating mechanism in accordance with manufacturer’s published data.

5. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.24.1.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

6. Inspect for correct insulating liquid level.

2. Electrical Tests

1. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.24.1.1 (Visual and Mechanical Inspection).

2. Perform a contact resistance test.

180 ATS – 1999 *Optional

Page 191: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.24 Automatic Circuit Reclosers and Line Sectionalizers (cont.) 1. Automatic Circuit Reclosers, Oil/Vacuum (cont.)

3. Remove a sample insulating liquid, if applicable, in accordance with ASTM D923. Sample shall be tested in accordance with the referenced standard.

1. Dielectric breakdown voltage: ASTM D877.

2. Color: ANSI/ASTM D1500.

3. Visual condition: ASTM D1524.

4. Test all protective functions in accordance with Section 7.9.

5. Test all metering and instrumentation in accordance with Section 7.11.

6. Perform vacuum bottle integrity test (overpotential) across each vacuum bottle with the breaker in the open position in strict accordance with manufacturer’s instructions. Do not exceed maximum voltage stipulated for this test. Provide adequate barriers and protection against x-radiation during this test. Do not perform this test unless the contact displacement of each interrupter is within manufacturer’s tolerance. Be aware that some dc high-potential test sets are half-wave rectified and may produce peak voltages in excess of the breaker manufacturer’s recommended maximum.

7. Perform overpotential test on each pole-to-ground and pole-to-pole with recloser in closed position.

*8. Perform insulation-resistance test on all control wiring at 1000 volts dc. For units with solid-state components follow manufacturer’s recommendations.

*9. Perform overall power-factor/dissipation-factor test.

*10. Perform power-factor/dissipation-factor test on each bushing equipped with power-factor taps. Use hot-collar method if taps are not available.

*11. Test all current and/or voltage transformers in accordance with Section 7.10.

ATS – 1999 181 *Optional

Page 192: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.24 Automatic Circuit Reclosers and Line Sectionalizers (cont.) 1. Automatic Circuit Reclosers, Oil/Vacuum (cont.)

3. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. Overpotential test voltages shall be in accordance with manufacturer’s published data or Table 10.15.

5. Insulating liquid test results shall be in accordance with Table 10.4.

6. Control wiring insulation resistance should be a minimum of two megohms.

7. Dissipation-factor/power-factor test results and tank loss index should not exceed the manufacturer’s published data. In the absence of manufacturer’s published data, the comparison shall be made to similar reclosers.

8. Dissipation-factor/power-factor and capacitance test results should be within ten percent of nameplate rating for bushings.

9. Test values for protective functions shall be within manufacturer’s recommendations.

182 ATS – 1999 *Optional

Page 193: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.24 Automatic Circuit Reclosers and Line Sectionalizers (cont.)

2. Automatic Line Sectionalizers, Oil

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Inspect anchorage, alignment, and grounding.

4. Perform all mechanical operation and contact alignment tests on both the sectionalizer and its operating mechanism in accordance with manufacturer’s instructions.

5. Inspect all bolted electrical connections for high resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance with Section 7.24.2.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer’s published data or Table 10.12.

3. Perform thermographic survey in accordance with Section 9.

6. Inspect for correct insulating liquid level.

ATS – 1999 183 *Optional

Page 194: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.24 Automatic Circuit Reclosers and Line Sectionalizers (cont.) 2. Automatic Line Sectionalizers, Oil (cont.)

2. Electrical Tests

1. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.24.2.1 (Visual and Mechanical Inspection).

2. Perform a contact resistance test.

3. Remove a sample insulating liquid in accordance with ASTM D923. Sample shall be tested for the following:

1. Dielectric breakdown voltage: ASTM D877.

2. Color: ANSI/ASTM D1500.

3. Visual condition: ASTM D1524.

4. Perform an overpotential test on each pole-to-ground and pole-to-pole.

*5. Perform an insulation-resistance test on all control wiring at 1000 volts dc. For units with solid-state components, follow manufacturer’s recommendations.

6. Test sectionalizer counting function by application of simulated fault current (greater than 160 percent of continuous current rating).

7. Test sectionalizer lockout function for all counting positions.

8. Test for reset timing on trip actuator.

*9. Perform overall power-factor/dissipation-factor test.

*10. Perform power-factor/dissipation-factor test on each bushing equipped with power-factor taps. Use hot-collar method if taps are not available.

184 ATS – 1999 *Optional

Page 195: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES 7.24 Automatic Circuit Reclosers and Line Sectionalizers (cont.) 2. Automatic Line Sectionalizers, Oil (cont.)

3. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

4. Overpotential test voltages shall be in accordance with manufacturer’s published data or Table 10.16.

5. Insulating liquid test results shall be in accordance with Table 10.4.

6. Control wiring insulation resistance should be in accordance with Table 10.4.

7. Dissipation-factor/power-factor test results and tank loss index shall not exceed the manufacturer’s published data. In the absence of manufacturer’s published data, the comparison shall be made to similar line sectionalizers.

8. Test values for protective functions shall be within manufacturer’s recommendations.

ATS – 1999 185 *Optional

Page 196: NETA_ATS-1999

7. INSPECTION AND TEST PROCEDURES

7.25 Fiber-Optic Cables

1. Visual and Mechanical Inspection

1. Compare cable, connector, and splice data with drawings and specifications.

2. Inspect cable and connections for physical and mechanical damage.

3. Verify that all connectors and splices are correctly installed.

2. Electrical Tests

1. Perform cable length measurement, fiber fracture inspection, and construction defect inspection using an optical time domain reflectometer.

2. Perform connector and splice integrity test using an optical time domain reflectometer.

3. Perform cable attenuation loss measurement with an optical power loss test set.

4. Perform connector and splice attenuation loss measurement from both ends of the optical cable with an optical power loss test set.

3. Test Values

1. The optical time domain reflectometer signal should be analyzed for excessive connection, splice, or cable backscatter by viewing the reflected power/distance graph.

2. Attenuation loss measurement shall be expressed in dB/km. Losses shall be within the manufacturer’s recommendations when no local site specifications are available.

7.26 Electrostatic/Electromagnetic Field Testing - Reserved

7.27 Special Systems - Reserved

186 ATS – 1999 *Optional

Page 197: NETA_ATS-1999

8. SYSTEM FUNCTION TESTS

8.1 General

1. Perform system function tests upon completion of equipment tests as defined in Section 7. It is the purpose of system function tests to prove the correct interaction of all sensing, processing, and action devices.

2. Implementation

1. Develop test parameters for the purpose of evaluating performance of all integral components and their functioning as a complete unit within design requirements.

Perform these tests.

2. Verify the correct operation of all interlock safety devices for fail-safe functions in addition to design function.

3. Verify the correct operation of all sensing devices, alarms, and indicating devices.

ATS – 1999 187 *Optional

Page 198: NETA_ATS-1999

9. THERMOGRAPHIC SURVEY

9.1 Visual and Mechanical Inspection

1. Inspect physical, electrical, and mechanical condition.

2. Remove all necessary covers prior to thermographic inspection. Utilize appropriate caution, safety devices, and personal protective equipment.

9.2 Equipment to be inspected shall include all current-carrying devices.

9.3 Provide report including the following:

1. Description of equipment to be tested.

2. Discrepancies.

3. Temperature difference between the area of concern and the reference area.

4. Probable cause of temperature difference.

5. Areas inspected. Identify inaccessible and/or unobservable areas and/or equipment.

6. Identify load conditions at time of inspection.

*7. Provide photographs and/or thermograms of the deficient area.

8. Recommended action.

188 ATS – 1999 *Optional

Page 199: NETA_ATS-1999

9. THERMOGRAPHIC SURVEY

9.4 Test Parameters

1. Inspect distribution systems with imaging equipment capable of detecting a minimum temperature difference of 1°C at 30°C.

2. Equipment shall detect emitted radiation and convert detected radiation to visual signal.

3. Thermographic surveys should be performed during periods of maximum possible loading but not less than 40 percent of rated load of the electrical equipment being inspected. Refer to ANSI/NFPA 70B-1994, Section 18-16 (Infrared Inspection).

9.5 Test Values

Suggested actions based on temperature rise can be found in Table 10.18.

ATS – 1999 189 *Optional

Page 200: NETA_ATS-1999

TABLE 10.1

Insulation Resistance Tests

Electrical Apparatus and Systems

Maximum Rating of Equipment in Volts

Minimum Test Voltage, dc Recommended Minimum

Insulation Resistance in Megohms

250 500 25

600 1,000 100

5,000 2,500 1,000

8,000 2,500 2,000

15,000 2,500 5,000

25,000 5,000 20,000

35,000 15,000 100,000

46,000 15,000 100,000

69,000 15,000 100,000 In the absence of consensus standards dealing with insulation-resistance tests, the NETA Standards Review Council suggests the above representative values.

See Table 10.14 for temperature correction factors.

Actual test results are dependent on the length of the conductor being tested, the temperature of the insulating material, and the humidity of the surrounding environment at the time of the test. In addition, insulation resistance tests are performed to establish a trending pattern and a deviation from the baseline information obtained during maintenance testing enabling the evaluation of the insulation for confined use.

190 ATS – 1999

Page 201: NETA_ATS-1999

TABLE 10.2

Switchgear Withstand Test Voltages

Maximum Test Voltage kV Type of Switchgear Rated Maximum Voltage

(kV) (rms) ac dc

Low-Voltage Power Circuit Breaker Switchgear

.254/.508/.635

1.6

2.3

4.76 14 20 8.25 27 37

15.0 27 37 27.0 45 *

Metal-Clad Switchgear

38.0 60 * 15.5 37 * 38.0 60 *

Station-Type Cubicle

Switchgear 72.5 120 *

4.76 14 20 8.25 19 27

15.0 27 37 15.5 37 52 25.8 45 *

Metal Enclosed Interrupter Switchgear

38.0 60 * Derived from ANSI/IEEE C37.20.1-1993, Paragraph 5.5, Standard for Metal-Enclosed Low-Voltage Power Circuit-Breaker Switchgear, C37.20.2-1993, Paragraph 5.5, Standard for Metal-Clad and Station-Type Cubicle Switchgear and C37.20.3-1987 (R1992), Paragraph 5.5, Standard for Metal-Enclosed Interrupter Switchgear, and includes 0.75 multiplier with fraction rounded down.

The column headed “DC Withstand” is given as a reference only for those using dc tests to verify the integrity of connected cable installations without disconnecting the cables from the switchgear. It represents values believed to be appropriate and approximately equivalent to the corresponding power frequency withstand test values specified for voltage rating of switchgear. The presence of this column in no way implies any requirement for a dc withstand test on ac equipment or that a dc withstand test represents an acceptable alternative to the low-frequency withstand tests specified in this specification, either for design tests, production tests, conformance tests, or field tests. When making dc tests, the voltage should be raised to the test value in discrete steps and held for a period of one minute.

•Because of the variable voltage distribution encountered when making dc withstand tests, the manufacturer should be contacted for recommendations before applying dc withstand tests to the switchgear. Voltage transformers above 34.5kV should be disconnected when testing with dc. Refer to ANSI/IEEE C57.13-1993 (IEEE Standard Requirements for Instrument Transformers) paragraph 8.8.2.

ATS – 1999 191

Page 202: NETA_ATS-1999

TABLE 10.3

Recommended Dissipation Factor/Power Factor

of Liquid-Filled Transformers, Regulators, and Reactors

Oil, Silicone, and Less-Flammable Hydrocarbon Maximum

New Power Transformers and Reactors

0.5%

New Distribution Transformers and Regulators

1.0%

Remanufactured Power Transformers and Reactors

1.0%

Remanufactured Distribution Transformers and Regulators

1.5%

In the absence of consensus standards dealing with transformer dissipation factor/power factor values, the NETA Standards Review Council suggests the above representative values.

192 ATS – 1999

Page 203: NETA_ATS-1999

TABLE 10.4

Test Limits for New Insulating Oil Received in New Equipment

Mineral Oil1

Test ASTM Method 69 kV and Below

Above 69 kV through 230 kV

345 kV Class and Above

Dielectric breakdown, kV minimum

D877

30

30

30

Dielectric breakdown, kV minimum @ 0.04” gap

D1816

20

30

30

Dielectric breakdown, kV minimum @ 0.08” gap

D1816

40

48

60

Interfacial tension MN/m minimum

D971

35

35

40

Neutralization number, mg KOH/g maximum

D974

0.03

0.03

0.03

Water content, ppm maximum

D1533

25

20

10

Power factor at 25°C, % D924 0.15 0.10 0.05

Power factor at 100°C, % D924 1.50 1.00 0.30

Color D1500 1.0 1.0 0.5

Visual condition D1524 Bright & Clear Bright & Clear Bright & Clear 1 IEEE C57,106-1991 (Guide for Acceptance and Maintenance of Insulating Oil in Equipment), Tables 1, 2, and 3.

Test Limits for Silicone Insulating Liquid in New Transformers

Test ASTM Method Acceptable2 Values

Dielectric breakdown, kV minimum D877 30

Visual D2129 clear, free of particles

Water content, ppm maximum D1533 50

Dissipation factor, % max. @ 25°C D924 0.1

Viscosity, cSt @ 25°C D445 47.5 – 52.5

Fire point, °C, minimum D92 340

Neutralization number, mg KOH/g max.

D974

0.01 2 IEEE C57.111-1989 (R1995) (Guide for Acceptance of silicone Insulating Fluid and Its Maintenance in Transformers), Table 2.

ATS – 1999 193

Page 204: NETA_ATS-1999

Table 10.4 (cont.)

Typical Values for Less-Flammable Hydrocarbon Insulating Liquid

Received in New Equipment

Test ASTM Method Less-Flammable

Hydrocarbon

34.5 kV Class and Below D1816 20 Above 34.5 kV Class D1816 25

Dielectric breakdown, kV minimum 0.04” gap Desirable D1816 30

34.5 kV Class and Below D1816 40 Above 34.5 kV Class D1816 50

Dielectric breakdown, kV minimum 0.08” gap Desirable D1816 60 Dielectric breakdown, kV minimum D877 30 Visual D1524 Clear Water content, ppm maximum D1533B 25 Dissipation factor, % maximum @ 25°C D924 0.1 Dissipation factor, % maximum @ 100°C D924 1.0 Fire Point, (°C) minimum D92 300 Flash Point (°C) typical D92 270-290 Neutralization number, mg KOH/g maximum D974 or D664 0.03 Interfacial tension, mN/m minimum @ 25°C, minimum D971 38

IEEE C57.121-1988 (R1995) (Guide for Acceptance and Maintenance of Less Flammable Hydrocarbon Fluid in Transformers),Table 2.

194 ATS – 1999

Page 205: NETA_ATS-1999

TABLE 10.5

Transformer Insulation-Resistance

Acceptance Test Voltage and Minimum Results

Transformer Insulation Resistance Test Voltages

Transformer Winding Rated Voltage Minimum DC Test Voltage

0-600 1000

601-5000 2500

>5000 5000

Recommended Minimum Transformer Insulation Resistance Results: In the absence of consensus standards for minimum acceptable transformer insulation resistance, the NETA Standards Review Council recommends the use of the following formula. Although the origin of this formula is not identified, NETA recognizes its wide use in the electrical testing industry. CE

kVAIR = IR = Minimum recommended one minute insulation resistance C = Constant E = Phase-to-phase voltage for delta connected windings; phase-to-neutral voltage for star connected windings. kVA = Rated kVA of transformer Values of C @ 20°C for 60 Hz transformers

Oil-filled C = 1.5 Dry-type C = 30

ATS – 1999 195

Page 206: NETA_ATS-1999

TABLE 10.6

Medium-Voltage Cables

Maximum Field Acceptance Test Voltages (kV, dc) Insulation Type Rated Cable Voltage Insulation Level Test Voltage kV, dc

5 kV 100% 25 5 kV 133% 25

15 kV 100% 55 15 kV 133% 65

Elastomeric:

Butyl and Oil Base

25 kV 100% 80 5 kV 100% 25 5 kV 133% 25 8 kV 100% 35 8 kV 133% 45

15 kV 100% 55 15 kV 133% 65 25 kV 100% 80 25 kV 133% 100 28 kV 100% 85

Elastomeric: EPR

35 kV 100% 100 5 kV 100% 25 5 kV 133% 25 8 kV 100% 35 8 kV 133% 45

15 kV 100% 55 15 kV 133% 65 25 kV 100% 80 25 kV 133% 100

Polyethylene

35 kV 100% 100 Derived from ANSI/IEEE Standard 141-1993 Table 12-9 and by factoring the applicable ICEA/NEMA Standards.

NOTE: AEIC CS5 and CS6, and ANSI/IEEE Standard 400 do not differentiate cables based upon insulation thickness and, consequently, list differing test voltages.

Insure that the maximum test voltage does not exceed the voltage limits for potheads and terminators specified in IEEE Std. 48 (IEEE Standard Test Procedures and Requirements for High-Voltage AC Cable Terminations) or for molded rubber terminations specified in IEEE Std. 386 (IEEE Standard for Separable Insulated Connector Systems for Power Distribution systems Above 600V), or manufacturer’s published data.

196 ATS – 1999

Page 207: NETA_ATS-1999

TABLE 10.7

Molded-Case Circuit Breakers

Inverse Time Trip Test

(At 300% of Rated Continuous Current of Circuit Breaker)

Maximum Trip Time in Seconds For Each Maximum Frame Rating1

Range of Rated Continuous

Current Amperes <250V 251-600V

0-30 50 70

31-50 80 100

51-100 140 160

101-150 200 250

151-225 230 275

226-400 300 350

401-600 - - - - - 450

601-800 - - - - - 500

801-1000 - - - - - 600

1001 – 1200 - - - - - 700

1201-1600 - - - - - 775

1601-2000 - - - - - 800

2001-2500 - - - - - 850

2501-5000 - - - - - 900

6000 - - - - - 1000

Derived from Table 5-3, NEMA Standard AB 4-1996.

1 Trip times may be substantially longer for integrally-fused circuit breakers if tested with the fuses replaced by solid links (shorting bars).

ATS – 1999 197

Page 208: NETA_ATS-1999

TABLE 10.8

Instantaneous Trip Tolerances

for Field Testing of Circuit Breakers

Tolerances of Manufacturers’

Published Trip Range Breaker Type Tolerance of Settings High Side Low Side

Adjustable +40% -30%

- - - - -

- - - - -

Nonadjustable - - - - - +25% -25%

Reproduction of Table 5-4 from NEMA publication AB4-1996.

For circuit breakers with nonadjustable instantaneous trips, tolerances apply to the manufacturer’s published trip range, i.e., +40 percent on high side, -30 percent on low side.

198 ATS – 1999

Page 209: NETA_ATS-1999

TABLE 10.9

Instrument Transformer Dielectric Tests

Acceptance

Applied Potential Tests Field Test Voltage (kV)

Nominal System (kV)

BIL (kV)

ac dc1 0.6 10 3 4 1.1 30 7.5 10 2.4 45 11.2 15 4.8 60 14.2 19 8.32 75 19.5 26

13.8 95 25.5 34 13.8 110 25.5 34 25 125 30 40 25 150 37.5 50 34.5 150 37.5 50 34.5 200 52.5 70 46 250 71.2 N/A 69 350 105 N/A

115 450 138 N/A 115 550 172 N/A 138 550 172 N/A 138 650 206 N/A 161 650 206 N/A 161 750 243 N/A 230 900 296 N/A 230 1050 345 N/A 345 1300 431 N/A 500 1675 562 N/A 500 1800 600 N/A 765 2050 690 N/A

Derived from Paragraph 8.8.2 and Table 2 of ANSI/IEEE C57.13-1993 (Standard Requirements for Instrument Transformers).

1 DC potential tests are not recommended for transformers rated higher than 200 kV BIL. DC tests may prove beneficial as a reference for future testing. In such cases the test direct voltage shall not exceed the original factory test RMS alternating voltages.

ATS – 1999 199

Page 210: NETA_ATS-1999

200 ATS – 1999

TABLE 10.10

Maximum Allowable Vibration Amplitude

Speed - RPM Amplitude - Inches Peak to Peak 3000 and above 0.001

1500 - 2999 0.002 1000 - 1499 0.0025

999 and below 0.003 Derived from NEMA publication MG 1-1993, Sections 20.53, 21.54, 22.54, 23.52, and 24.50.

Page 211: NETA_ATS-1999

Table 10.11

Overpotential Test Voltages for Electrical Apparatus Other than Inductive Equipment

Nominal

System (Line) Voltage1 (kV)

Insulation

Class

AC Factory Test (kV)

Maximum Field Applied AC Test (kV)

Maximum Field Applied DC Test (kV)

1.2 1.2 10 6.0 8.5

2.4 2.5 15 9.0 12.7

4.8 5.0 19 11.4 16.1

8.3 8.7 26 15.6 22.1

14.4 15.0 34 20.4 28.8

18.0 18.0 40 24.0 33.9

25.0 25.0 50 30.0 42.4

34.5 35.0 70 42.0 59.4

46.0 46.0 95 57.0 80.6

69.0 69.0 140 84.0 118.8

In the absence of consensus standards, the NETA Standards Review Council suggests the above representative values.

1 Intermediate voltage ratings are placed in the next higher insulation class.

ATS – 1999 201

Page 212: NETA_ATS-1999

TABLE 10.12

US Standard

Bolt Torques for Bus Connections Heat-Treated Steel - Cadmium or Zinc Plated

Grade SAE 1&2 SAE 5 SAE 7 SAE 8

Head Marking

Minimum Tensile (P.S.I.) 64K 105K 133K 150K Bolt Diameter

in Inches Torque (Foot Pounds)

1/4 4.0 5.6 8.0 8.4

5/16 7.2 11.2 15.2 17.6

3/8 12.0 20.0 27.2 29.6

7/16 19.2 32.0 44.0 48.0

1/2 29.6 48.0 68.0 73.6

9/16 42.4 70.4 96.0 105.6

5/8 59.2 96.0 133.6 144.0

3/4 96.0 160.0 224.0 236.8

7/8 152.0 241.6 352.0 378.4

1.0 225.6 372.8 528.0 571.2

202 ATS – 1999

Page 213: NETA_ATS-1999

TABLE 10.12 (CONT.)

Bolt Torques for Bus Connections

Silicon Bronze Fasteners1

Torque (Foot Pounds)

Bolt Diameter in Inches Nonlubricated Lubricated 5/16 15 10 3/8 20 14 1/2 40 25 5/8 55 40 3/4 70 60

1 Bronze alloy bolts shall have a minimum tensile strength of 70,000 pounds per square inch.

Aluminum Alloy Fasteners2

Torque (Foot Pounds)

Bolt Diameter in Inches Lubricated 5/16 8.0 3/8 11.2 1/2 20.0 5/8 32.0 3/4 48.0

2Aluminum alloy bolts shall have a minimum tensile strength of 55,000 pounds per square inch.

ATS – 1999 203

Page 214: NETA_ATS-1999

TABLE 10.12 (CONT.)

Bolt Torques for Bus Connections

Stainless Steel Fasteners3

Torque (Foot Pounds)

Bolt Diameter in Inches Uncoated 5/16 14 3/8 25 1/2 45 5/8 60 3/4 90

3 Bolts, cap screws, nuts, flat washers, locknuts: 18-8 alloy.

Belleville washers: 302 alloy.

204 ATS – 1999

Page 215: NETA_ATS-1999

TABLE 10.13

Reserved

ATS – 1999 205

Page 216: NETA_ATS-1999

TABLE 10.14

Insulation Resistance Conversion Factors

for Conversion of Test Temperature to 20ºC

Temperature Multiplier

ºC

ºF Apparatus Containing

Immersed Oil Insulations Apparatus Containing

Solid Insulations 0 32 0.25 0.40 5 41 0.36 0.45 10 50 0.50 0.50 15 59 0.75 0.75 20 68 1.00 1.00 25 77 1.40 1.30 30 86 1.98 1.60 35 95 2.80 2.05 40 104 3.95 2.50 45 113 5.60 3.25 50 122 7.85 4.00 55 131 11.20 5.20 60 140 15.85 6.40 65 149 22.40 8.70 70 158 31.75 10.00 75 167 44.70 13.00 80 176 63.50 16.00

206 ATS – 1999

Page 217: NETA_ATS-1999

TABLE 10.15

AC High-Potential Test Voltage

for Automatic Circuit Reclosers

Nominal Voltage Class, kV

Maximum Voltage, kV Rated Impulse Withstand Voltage, kV

Maximum Field Test Voltage, kVAC

14.4 (1∅ and 3∅) 15.0 95 35

14.4 (1∅ and 3∅) 15.5 110 50

24.9 (1∅ and 3∅) 27.0 150 60

34.5 (1∅ and 3∅) 38.0 150 70

46.0 (3∅) 48.3 250 105

69.0 (3∅) 72.5 350 160

Derived from ANSI/IEEE C37.61-1973(R1993) (Standard Guide for the Application, Operation, and Maintenance of Automatic Circuit Reclosers), C37.60-1981(R1993) (Standard Requirements for Overhead, Pad-Mounted, Dry-Vault, and Submersible Automatic Circuit Reclosers and Fault Interrupters for AC Systems).

TABLE 10.16

AC High-Potential Test Voltage for Automatic Line Sectionalizers

Nominal Voltage

Class kV Maximum Voltage

kV Rated Impulse

Withstand Voltage kV

Maximum Field Test Voltage kVAC

DC 15 Minute Withstand (kV)

14.4 (1∅) 15.0 95 35 53

14.4 (1∅) 15.0 125 42 53

14.4 (3∅) 15.5 110 50 53

24.9 (1∅) 27.0 125 60 78

34.5 (3∅) 38.0 150 70 103

Derived from ANSI/IEEE C37.63-1984(R1990) Table 2 (Standard Requirements for Overhead, Pad-Mounted, Dry-Vault, and Submersible Automatic Line Sectionalizers of AC Systems).

In the absence of consensus standards, the NETA Standards Review Council suggests the above representative values.

NOTE: Values of ac voltage given are dry test one minute factory test values.

ATS – 1999 207

Page 218: NETA_ATS-1999

TABLE 10.17

Metal Enclosed Bus Dielectric Withstand Test Voltages

Maximum Test Voltage, kV

Type of Bus

Rated kV ac dc Isolated Phase for Generator Leads 24.5

29.5 34.5

37 45 60

52.0 - - - -

Isolated Phase for Other than Generator Leads

15.5 25.8 35.0

37 45 60

52.0 - - - -

Nonsegregated Phase

0.635 4.76

15.0 25.8 38.0

1.6 14 27 45 60

2.3 20.0 37.0 63.0 - -

Segregated Phase

15.5 25.8 38.0

37 45 60

52.0 63.0 - -

DC Bus Duct

0.3 0.8 1.2 1.6 3.2

1.6 2.7 3.4 4.0 6.6

2.3 3.9 4.8 5.7 9.3

Derived from ANSI-IEEE C37.23-1987, Tables 3A, 3B, 3C, 3D and paragraph 6.4.2. The table includes a 0.75 multiplier with fractions rounded down to two significant digits.

Note: The presence of the column headed “dc withstand” does not imply any requirement for a dc withstand test on ac equipment. This column is given as a reference only for those using dc tests and represents values believed to be appropriate and approximately equivalent to the corresponding power frequency withstand test values specified for each class of bus.

Direct current withstand tests are recommended for flexible bus to avoid the loss of insulation life that may result from the dielectric heating that occurs with rated frequency withstand testing.

Because of the variable voltage distribution encountered when making dc withstand tests and variances in leakage currents associated with various insulation systems, the manufacturer should be consulted for recommendations before applying dc withstand tests to this equipment.

208 ATS – 1999

Page 219: NETA_ATS-1999

TABLE 10.18

Thermographic Survey

Suggested Actions Based on Temperature Rise

Temperature difference (∆T)

based on comparisons between similar components

under similar loading.

Temperature difference (∆T) based upon comparisons between component and ambient air temperatures.

Recommended Action

1ºC - 3ºC 1ºC - 10ºC Possible deficiency; warrants investigation

4ºC - 15ºC 11ºC - 20ºC Indicates probable deficiency; repair as time permits

- - - - - - 21ºC - 40ºC Monitor continuously until corrective measures can be accomplished

>15ºC >40ºC Major discrepancy; repair immediately

Temperature specifications vary depending on the exact type of equipment. Even in the same class of equipment (i.e., cables) there are various temperature ratings. Heating is generally related to the square of the current; therefore, the load current will have a major impact on ∆T. In the absence of consensus standards for ∆T, the values in this table will provide reasonable guidelines.

An alternative method of evaluation is the standards-based temperature rating system as discussed in Section 8.9.2, conducting an IR Thermographic Inspection, Electrical Power Systems Maintenance and Testing, by Paul Gill, PE.

It is a necessary and valid requirement that the person performing the electrical inspection be thoroughly trained and experienced concerning the apparatus and systems being evaluated as well as knowledgeable of thermographic methodology.

ATS – 1999 209

Page 220: NETA_ATS-1999

ABOUT THE INTERNATIONAL ELECTRICAL TESTING ASSOCIATION The InterNational Electrical Testing Association (NETA) is an accredited standards developer for the American National Standards Institute (ANSI) and defines the standards by which electrical equipment is deemed safe and reliable. NETA Certified Technicians conduct the tests that ensure this equipment meets the association’s stringent specifications. NETA is the leading source of specifications, procedures, testing, and requirements, not only for commissioning new equipment but for testing the reliability and performance of existing equipment.

Certification Certification of competency is particularly important in the electrical testing industry. Inherent in the determination of the equipment’s serviceability is the prerequisite that individuals performing the tests be capable of conducting the tests in a safe manner and with complete knowledge of the hazards involved. They must also evaluate the test data and make a judgmental opinion on the continued serviceability, deterioration, or nonserviceability of the specific equipment. NETA, a nationally-recognized certification agency, provides recognition of four levels of competency within the electrical testing industry.

Qualifications of the Testing Organization An independent overview is the only method of determining the long-term usage of electrical apparatus and its suitability for the intended purpose. NETA companies best support the interest of the owner, as the objectivity and competency of the testing firm is as important as the competency of the individual technician. NETA Members are part of an independent, third-party electrical testing association dedicated to setting world standards in electrical maintenance and acceptance testing. Hiring a NETA Member company, assures the customer that: • The NETA Technician has broad-based knowledge -- this person is trained to inspect,

test, maintain, and calibrate all types of electrical equipment in all types of industries. • NETA Technicians meet stringent educational and experience requirements. • A Registered Professional Engineer will review all engineering reports. • All tests will be performed objectively, according to NETA specifications, using calibrated

instruments traceable to the National Institute of Science and Technology (NIST). • The firm is a well-established, full-service electrical testing and maintenance business.

Specifications and Publications As a part of its service to the industry, the InterNational Electrical Testing Association provides two nationally-recognized publications: the NETA Electrical Maintenance Testing Specifications and the NETA Electrical Acceptance Testing Specifications. The Association also produces a quarterly technical journal, NETA World, which is available through subscription. It features articles of interest to electrical testing and maintenance companies, consultants, engineers, architects, and plant personnel directly involved in electrical testing and maintenance.

Educational Programs The NETA Technical Conference and Seminars are held annually in March, providing useful information to the industry about electrical safety, state-of-the-art testing technologies, and new testing equipment and approaches. A trade show is also a part of this four-day event.