Neighborhood Conservation Program Review › wp-content › uploads › ... · 2019-09-27 · •...
Transcript of Neighborhood Conservation Program Review › wp-content › uploads › ... · 2019-09-27 · •...
Neighborhood ConservationProgram ReviewWorking Group Meeting #4
September 19, 2019
2
Meeting Agenda
1. Opening
2. Updates to Draft “Work Plan” document
3. Overview of Project Execution
4. Civic Engagement
5. Next Steps + Business
6. Adjourn
(approx. time)
5 min
5 min
75 min
25 min
5 min
3
Updates to Draft “Work Plan” Document
4
Introduction to Draft “Work Plan” Document
(see accompanying deck)
A. Policy and Planning Considerations
5
Introduction to Draft “Work Plan” Document
(see accompanying deck)
B. Infrastructure Delivery Programs
6
C. Prioritizing Projects to Advance
7
Introduction to Draft “Work Plan” Document
(see accompanying deck)
D. Project Execution
8
Introduction to Draft “Work Plan” Document
(see accompanying deck)
E. Funding, Costs and Timing: Then and Now
9
Introduction to Draft “Work Plan” Document
(see accompanying deck)
F. Spatial Distribution and Equity Aspects
10
Introduction to Draft “Work Plan” Document
(see accompanying deck)
G. Civic Engagement Elements
11
Introduction to Draft “Work Plan” Document
(see accompanying deck)
G. Tentative Schedule for DiscoveryMEETING POTENTIAL TOPICS
June 20, 2019 A. Policy and Planning Considerations
(including “Deep Dive” into NC Program / NCProject life cycle timeline and scoring)
July 25 B. Infrastructure Delivery Programs C. Prioritizing Projects to Advance G. Civic Engagement
Sept. 19 D. Project Execution G. Civic Engagement
Oct./Nov. – Two (2) Dates TBD
E. Funding / Costs / Timing: Then and Now F. Spatial / Equity Aspects G. Civic Engagement Other Remaining Items
12
Project Execution Overview
13
Discovery Questions
D. Project Execution
Follow-up Item
14
Transportation Projects
NC Project Process (typical)
Varies
• Pre-Scoping• Project Goals Identified• Clipboard Petition• Points Accumulation
3 to 9 Months
• Scoping• Preliminary Concept Plan• Neighborhood Input• Preliminary Concept Plan Revisions
3 to 6 Months
• Concept Design• Final Concept Plan• Resident Approval (Civic Association Letter of
Support)
2 – 3 Months
• Funding• NCAC Approval• Board Approval
15
Notes / Risk Factors
• Level of community involvement has inverse relationship with length of time for this phase
TIMELINE(slide 1 of 2)
TRANSPORTATION
NC Project Process (typical), cont’d
16
9 to 12 Months
• Final Engineering• 90% Plan • Neighborhood Review Meeting• 90% Plan Revisions and Final Plans
3 to 6 Months • Permits
• County Land Disturbance Permits• State Land Use Permits (e.g. VDOT, etc.)
3 to 12 Months
• Right-of-Way (ROW)• Temporary Construction Easements• Wall Maintenance Agreements
3 to 12 Months
• Utility Clearance• Relocate Known Underground Utility Conflicts• Relocate Overhead Utility Pole Conflicts
Notes / Risk Factors
• Level of community involvement has inverse relationship with length of time for this phase
TIMELINE
(slide 2 of 2)
TRANSPORTATION
• Permits• County Land Disturbance Permits• State Land Use Permits (e.g. VDOT, etc.)
• Right-of-Way (ROW)• Temporary Construction Easements• Wall Maintenance Agreements
• Utility Clearance• Relocate Known Underground Utility
Conflicts• Relocate Overhead Utility Pole Conflicts
• Procurement
3 to 24 Months
• Some of these processes can run concurrently/overlap, depending on alignment of critical paths
• ROW and Utility Clearance is done only if required; work may not apply in all cases
NON - NC Project Process (typical)
Varies
• Sector / Area / Corridor Plan / Capital Improvement Plan
• Needs identified based on future vision• Projects identified
3 to 9 Months
• Scoping• Preliminary Concept Plan• Community Outreach• Preliminary Concept Plan Revisions
3 to 6 Months
• Concept Design• Final Concept Plan
17
Notes / Risk Factors
• Outreach after preliminary concept plan is with community, not just residents
TIMELINE
• Final concept plan arrived at based on community input, but does not require “community approval” a la “resident approval” with NC projects
• County-led planning efforts can take several years, depending on scope / scale
(slide 1 of 2)
TRANSPORTATION
Non- NC Project Process (typ.), cont’d
18
9 to 12 Months
• Final Engineering• 90% Plan • Neighborhood Review Meeting• 90% Plan Revisions and Final Plans
3 to 6 Months
• Permits• County Land Disturbance Permits• State Land Use Permits (e.g. VDOT, etc.)
3 to 12 Months
• Right-of-Way (ROW)• Temporary Construction Easements• Wall Maintenance Agreements
3 to 12 Months
• Utility Clearance• Relocate Known Underground Utility Conflicts• Relocate Overhead Utility Pole Conflicts
Notes / Risk Factors
• Level of community involvement has inverse relationship with length of time for this phase
TIMELINE
(slide 2 of 2)
TRANSPORTATION
• Permits• County Land Disturbance Permits• State Land Use Permits (e.g. VDOT, etc.)
• Right-of-Way (ROW)• Temporary Construction Easements• Wall Maintenance Agreements
• Utility Clearance• Relocate Known Underground Utility
Conflicts• Relocate Overhead Utility Pole Conflicts
• Procurement
• Some of these processes can run concurrently/overlap, depending on alignment of critical paths
• ROW and Utility Clearance is done only if required; work may not apply in all cases
3 to 24 Months
NC vs. Non-NC Process
19
KEY Difference between two processes
NC PROJECTS
NON - NC PROJECTS
TRANSPORTATION
• Duration of Pre-Scoping for each project is Neighborhood-Driven to a large degree
• Once plan/policy is set, duration of Pre-Scoping for each project is largely driven by staff/program capacity
• Community involvement happening in real-time with pre-scoping of NC projects
• In most cases, past community involvement helped inform plans/policy decisions, with additional (yet different) community input going forward
CPHD Staffing for NC Program
NC Program Manager
Project Manager
Project Manager
Project Manager
Budget & Finance Support
Landscape Architect
20
TRANSPORTATION
NC-Dedicated Staff
DES Staffing for NC Program
Engineering Supervisor
Engineer Engineer
Engineer
Engineering Supervisor
Engineer Engineer
Engineer
21
TRANSPORTATION
NC-Dedicated Staff
Survey Supervisor
Pool of Surveyors
Construction Management Supervisor
Pool of Construction
Managers
Contract Inspector
Contract Inspector
22
DES Staffing for NC Program
Construction Contractor
Construction Contractor
COUNTYSTAFF
CONTRACTORS TO COUNTY
TRANSPORTATION
Staff Not Dedicated to the NC Program
Current Staffing Model
Primarily Dedicated Staff with Some Pooled Staff & Contractor Support
– Advantages• Program Knowledge= Efficiency• No Competing Priorities for Project Management
and Design
– Disadvantages• Challenge to Operate with Varying Funding Levels• Construction Volume Varies = Overload or
Underuse of Construction Management Staff• Higher Inspection Costs
23
TRANSPORTATION
Contractor Staffing Model
Primarily Contractors w/Some Staff Oversight
– Advantages• Effective for Varied Funding Levels• Effective for Varied Volume of Construction
– Disadvantages• More Costly for Program• Erosion of Knowledge Base and Capability
Creates Reliance on Contractor’s Quality• Contractor Turnover More Likely = Less Program
Knowledge and Retained Experience24
TRANSPORTATION
Cost Estimating and Funding
Funding Allocated to Individual Projects Based on Cost Estimate From Concept Design
• General Project Information is Known• Details Not Known - Assumptions Based on Typical
Conditions• Forecasting Contractor’s Likely Prices in Future
• Assumptions Based on Recent Pricing• Adjust for Project Timing- Forecast Future Market Conditions Based
on Recent Observations • Contingency to Account for Risk
25
TRANSPORTATION
Cost Estimating and Funding
Final Engineering Uncovers New Information that Impacts Cost
• Example: Project area is more flood prone than typical-more storm drain pipe and larger size is needed
• Example: Depth of gas main differs from record information- our storm drain pipe needs to be buried deeper
• Example: Lot re-developed and retaining wall needs to be longer and higher than typical
26
TRANSPORTATION
Cost Estimating and Funding
Procurement Results Display True Cost
• Market Conditions Become Evident• Construction Contractors Tell Us How Much We Must Pay
For the Work• Measuring Against Forecast Estimates from A Few Years
Prior• Savings from Other Projects Fill Funding Gap• County requirement to select responsive contractor with
lowest bid
27
TRANSPORTATION
Cost Estimating and Funding
Reliability of Estimates
• Greatest Exposure is to Construction Cost Inflation
• Adequate Staffing Levels Reduce Time Between Preliminary Cost Estimate and Construction Start = Less Exposure to Inflation
• Higher Contingencies Can Accommodate More Uncertainty at a Cost
• Higher Contingencies Tie Up Funding that Could Otherwise be Allocated to Other Projects
28
TRANSPORTATION
Cost Estimating and Funding
Value Engineering and Scope Reduction• Little Opportunity for Value Engineering
• Most Project Elements are Discrete• Example: Sidewalk, Storm Sewer Pipe, Pavement Cannot be Value
Engineered
• Limited Opportunity for Scope Reduction• Most Project Elements Essential to Project Goals
• Example: Sidewalk, Storm Sewer Pipe, Pavement Needed as a Whole to Meet Project Goals
• Some Scope Reduction Opportunities• Streetlights• Multi-block Projects (reduce geographic extent of project)
29
TRANSPORTATION
Pilot Funding Approach
Fund Projects After Final Engineering
• More Project Details Known and Fewer Assumptions• Less Exposure to Cost Inflation Because Project is
Closer to Procurement• Still Forecasting Contractor’s Likely Prices
30
TRANSPORTATION
*** Staff are currently piloting this approach with several NC projects in progress ***
Alternate Funding Approaches
Fund as a Program- Allocate to Projects After Procurement
– Advantages• No Predictive Element to Cost Estimating
– Disadvantages• Uncertainty Over Timing of Funds Availability for Projects
31
TRANSPORTATION
32
Parks Projects
NC Project Process
33
PARKS
Varies
• Pre-Scoping• Project Goals Identified• Points Accumulation
3 to 9 Months
• Project Scoping• Civic Association/Neighborhood input• Project Goals or Features identified• Prelim. Site Assessment / Cost Estimates• Civic Association Approval
2 to 3 Months
• Scope Funding• NCAC Approval• County Board Approval
3 – 6 Months
• Concept Design Phase• Public design meetings• Conceptual Design Plan (30%)• Civic Association Approval
33
Notes / Risk Factors
• Level of community involvement has inverse relationship with length of time for this phase
TIMELINE
• Minimum of two scoping meetings in addition to CA meeting for final approval
• Typically 2 -3 meetings, but can vary depending on the public engagement level
NC Project Process
34
PARKS
6 to 9 Months
• Construction Documents• 30% - 100% Plans and Specifications• Design and Engineering
3 to 6 Months
• Permitting• Land Disturbance Activity (LDA)• Civil Engineering Plan (CEP)• Building Permits (where applicable)• Stormwater Management• State Permits (DEQ, VSMP, SWPPP)
3 to 6 Months
• Procurement• Prepare bidding documents and post bid
announcement• Bids opened and reviewed• County Board award of contract• Contract signed
34
Notes / Risk FactorsTIMELINE
Parks Maintenance Capital Project Process
3 to 9 Months
• Identification and Scoping (CIP)• Maintenance Requirements• Current Condition (age, life, safety, ordinance code compliance)• Preliminary Cost Estimate• Funding Approved (CIP)
3 to 6 Months
• Preliminary Design Phase • Topographical Survey Conducted• Community Engagement Plan (Six-Step Public Engagement Guide)• Online Survey (gather public feedback)
3 to 6 Months
• Design Phase• Public Design Meetings (typically 2-3, but can vary depending on the public
engagement level)• Conceptual Design Plan (30%)
35
TIMELINE
PARKS
Parks Maintenance Capital Project Process
6 to 9 Months
• Construction Documents • 30%-100% Plans and Specifications• Design and Engineering
3 to 6 Months
• Permitting• Land Disturbance Activity (LDA)• Storm Water Management• State Permits (DEQ VSMP, SWPPP)
3 to 6 Months
• Bidding Phase • Prepare bidding documents and post bid announcement• Bids open and reviewed.• County Board Award of Contract• Contract signed
36
PARKS
TIMELINE
CPHD Staffing for NC Program
NC Program Manager
Project Manager
Project Manager
Project Manager
Budget & Finance Support
Landscape Architect
37
NC-Dedicated Staff
PARKS
DPR Staffing
Planning Supervisor
Construction Manager
Park Development Division Chief
Facilities and NC Studio Supervisor
Project Manager/Landscape Architect
38
PARKS
NC-Dedicated
NC-Dedicated
* Actual # of DPR staff dedicated to NC varies based on project volume
Project Manager/Landscape Architect
NC-Dedicated (at times)*
Current Staffing Model
Dedicated Staff with Architectural & Engineering (A&E) Support Services Outsourced
39
Advantages• Effective for Varied Funding Levels• Effective for Varied Volume of Construction
Disadvantages• More Costly for Program• Erosion of Knowledge Base and Capability Creates Reliance on
Contractor’s Quality• Contractor Turnover More Likely = Less Program Knowledge and
Retained Experience
PARKS
Alternative Staffing Model
Dedicated Staff with Internal Staff A&E Support
– Advantages• Program Knowledge = Efficiency• No Competing Priorities for Project Management
and Design– Disadvantages
• Challenge to Operate with Varying Funding Levels (although some opportunity to reduce impact)
40
PARKS
Cost Estimating and Funding
Funding Allocated to Individual Projects Based on Cost Estimate From Scoping Approved by NCAC
• General Project Scope is Known• Details Not Known- Stormwater management cost
Forecasting Contractor’s Likely Prices in Future• Assumptions Based on Recent Pricing• Adjust for Project Timing- Forecast Future Market Conditions
Based on Recent Observations
• Contingency to Account for Risk
41
PARKS
Cost Estimating and Funding
Procurement Results Reveal True Cost • Market Conditions Become Evident
• Bids indicate How Much We Must Pay For the Work
• Cost estimates are based on bids received during the previous year
• Greatest Exposure is to Construction Cost Inflation
• Higher Contingencies Can Accommodate More Uncertainty at a Cost
• Higher Contingencies Tie Up Funding that Could Otherwise be Allocated to Other Projects
42
PARKS
Cost Estimating and Funding
Value Engineering and Scope Reduction• Opportunity for Value Engineering happens during the
Construction Document Phase• Many Project Elements are Discrete
• Generally, No Scope Reduction After Funding Approval• Most Project Elements Essential to Project Goals
43
PARKS
44
Civic Engagement
51
Next Steps and Business Items
52
Introduction to Draft “Work Plan” Document
(see accompanying deck)
G. Tentative Schedule for DiscoveryMEETING POTENTIAL TOPICS
June 20, 2019 A. Policy and Planning Considerations
(including “Deep Dive” into NC Program / NCProject life cycle timeline and scoring)
July 25 B. Infrastructure Delivery Programs C. Prioritizing Projects to Advance G. Civic Engagement
Sept. 19 D. Project Execution G. Civic Engagement
Oct./Nov. – Two (2) Dates TBD
E. Funding / Costs / Timing: Then and Now F. Spatial / Equity Aspects G. Civic Engagement Other Remaining Items
53
Introduction to Draft “Work Plan” Document
(see accompanying deck)
G. Next Meeting Candidate Dates?
10/8 10/9 10/16 10/17 11/5 11/7
4 of 7 4 of 7 3 of 7 4 of 7 5 of 7 7 of 7
7 community working group members responding thus far
Can attend