NEC3 Early Warning System Benefits and Pitfalls - Vol IV Issue No. 7
Transcript of NEC3 Early Warning System Benefits and Pitfalls - Vol IV Issue No. 7
7/14/2019 NEC3 Early Warning System Benefits and Pitfalls - Vol IV Issue No. 7
http://slidepdf.com/reader/full/nec3-early-warning-system-benefits-and-pitfalls-vol-iv-issue-no-7-563109dfd60b6 1/1
Volume IV Issue No. 7
The Global Leader in Managing Construction Risk
NEC3 Early Warning System – benefits and pitfalls
Disclaimer: This article does not constitute advice, legal or
otherwise, and is provided only as general
commentary. Appropriate professional advice should
always be obtained before taking or refraining from taking
any action in relation to such information and/or the
application of applicable law. This article and the materials
contained in it are provided on the basis that all liability for
any loss or damage, whether direct or indirect, arising out of
or in connection with any use or reliance up on this article is
excluded to the fullest extent permitted by law.
David Brodie-StedmanSenior Vice President & Managing Director
Asia, Middle East and Africa
Abu Dhabi Office
Butti Al Otaiba Bldg., Suite 1601 & 1602
Sh. Khalifa St., P.O. Box: 5201, Abu Dhabi – U.A.E
Tel : +971 – 2 – 627 2855
Fax: +971 – 2 – 627 2042E-mail: [email protected]
David MerrittSenior Vice President & Managing Director
Middle East and Africa
Sultan Business Centre
5th Floor, Suite 501
P.O. Box: 71467, Dubai - U.A.E. Tel. : +971 - 4 - 337 2145
Fax : +971 - 4 - 335 6077
E-mail : [email protected]
Most standard form contracts require
Contractors to give notice of events
that could give rise to a potential delay
or monetary claim, and specify that
failure to do so could lead to a rejection
of the claim. This is an issue that always
seems to be present in the
consideration of claims. But, is there a
better way of doing things?
The NEC ‘family’ of contracts takes a
different approach. It sets out
requirements for the Contractor to
notify the Project Manager of
Compensation Events. But it also has
taken a further step by putting in place
additional provisions for an ‘early
warning system’ which is designed to
promote collaborative effort and a
proactive risk management process.
The early warning procedure contained
in NEC3 places an obligation on the
Project Manager and the Contractor to
notify each other as soon as eitherbecomes aware of any matter that may
affect the works. These provisions give
each party the right to instruct the
other to attend a risk reduction
meeting, thereby preventing the
Contractor from dealing with the issues
unilaterally. The purpose and the spirit
behind the risk reduction meeting is to
focus on resolving problems and
mitigating risks, rather than looking for
blame, in order to make a positive
change to the course of events when it
is still possible.
The NEC3 contract still contains a bar
for the late notification of
Compensation Events, but the
Contractor will not lose its entitlement
due to failure to submit an early
warning. However, it has been argued
that the assessment of the Contractor’s
compensation may be affected if an
early warning is not issued. The logic
behind this argument is that clause 63.5
implies that if a warning had been given
earlier, mitigation measures could have
been taken to reduce the time and cost
impact of the event; the Project
Manager may therefore take this into
account in his assessment of the
“value” of any mitigation measures
which could have been taken.
Notwithstanding the above, caution
should be taken, when dealing with the
NEC3 form of contract, not to fall into a
blame game regarding early warnings.
On larger projects, numerous events
may occur for which an early warning
could be issued. It may, however, not
be possible or practicable for a
Contractor to raise an early warning for
every single issue. Further, the Project
Manager needs to be fair and
reasonable when assessing the events
for which the Contractor has not given
an early warning, bearing in mind that
early warnings are separate from the
Compensation Event process despite
there being some connection as stated
above.
In order to benefit from the advantages
that the early warning system can bring
to a project, it is crucial for the parties
to understand the principles under
which the NEC3 form of contract has
been designed. The opening core
clause of NEC3 requires the parties to
act “in a spirit of mutual trust and co-
operation” . This provision is often
ignored by the parties, as it does not
appear to impose any “real” obligation.
However, a recent English case
(Compass v Mid Essex Hospital Trust)
might be seen as heralding a shift in
that position, causing parties to think
more carefully about these and similar
obligations.
UAE law requires that a contract must
be performed in a manner consistent
with the requirements of ‘good faith’.
With this apparent shift in thinking in
common law jurisdictions, these and
similar contract terms should cause
parties to consider their obligations
more carefully. Current thinking seems
to be to give real meaning to these
obligations. So, ignore them at your
peril (or cost!).
Ali Akbar Fard
Senior Consultant
Hill International, Claims Group
Hill International, with 3,200
employees in 110 offices worldwide,
provides program management,project management, construction
management and construction claims
and consulting services. Engineering
News - Record magazine recently
ranked Hill as the 11th largest
construction management firm in the
United States.
For more information on Hill, please
visit our website at www.hillintl.com.