NDT & QA IN PIPE MANUFACTURING
Mirek Macecek Techno Scientific Inc.
Concord, ON
1
![Page 2: NDT & QA in Pipe Manufacturing · PIPE MANUFACTURING •Excluding seamless pipe, the process starts with plate or coil. Then, we have: 1. ERW ( Electro Resistance Weld) Pipes; 2.](https://reader034.fdocuments.net/reader034/viewer/2022042310/5ed794ae67b53e06555d2cb3/html5/thumbnails/2.jpg)
ABSTRACT
• In every CANDU power station piping is an important part of the installation. In this presentation the welding and NDT methods to produce steel pipes will be reviewed.
• It will include ERW, spiral welded and LSAW welded manufacturing processes.
2
![Page 3: NDT & QA in Pipe Manufacturing · PIPE MANUFACTURING •Excluding seamless pipe, the process starts with plate or coil. Then, we have: 1. ERW ( Electro Resistance Weld) Pipes; 2.](https://reader034.fdocuments.net/reader034/viewer/2022042310/5ed794ae67b53e06555d2cb3/html5/thumbnails/3.jpg)
• The NDT using mostly ultrasonic methods start with plate inspection for laminations and defects, and then customized system applications for each of the above processes.
• These are multi-channel systems typically 160 to 400 channels for the plate UT and typically 8-20 channels for the ERW to spiral weld inspection.
3
![Page 4: NDT & QA in Pipe Manufacturing · PIPE MANUFACTURING •Excluding seamless pipe, the process starts with plate or coil. Then, we have: 1. ERW ( Electro Resistance Weld) Pipes; 2.](https://reader034.fdocuments.net/reader034/viewer/2022042310/5ed794ae67b53e06555d2cb3/html5/thumbnails/4.jpg)
• Sometimes the systems are combined to include a full body inspection of the manufactured pipe.
• In some cases X rays augment the UT testing.
4
![Page 5: NDT & QA in Pipe Manufacturing · PIPE MANUFACTURING •Excluding seamless pipe, the process starts with plate or coil. Then, we have: 1. ERW ( Electro Resistance Weld) Pipes; 2.](https://reader034.fdocuments.net/reader034/viewer/2022042310/5ed794ae67b53e06555d2cb3/html5/thumbnails/5.jpg)
PIPE MANUFACTURING
• Excluding seamless pipe, the process starts with plate or coil. Then, we have:
1. ERW ( Electro Resistance Weld) Pipes;
2. Spiral Welded Pipes;
3. LSAW Pipes.5
![Page 6: NDT & QA in Pipe Manufacturing · PIPE MANUFACTURING •Excluding seamless pipe, the process starts with plate or coil. Then, we have: 1. ERW ( Electro Resistance Weld) Pipes; 2.](https://reader034.fdocuments.net/reader034/viewer/2022042310/5ed794ae67b53e06555d2cb3/html5/thumbnails/6.jpg)
APPLICABLE STANDARDS• ANSI/AWWA
• API 5L
• ASTM A 53
• DIN 2440
• BS 1387
• SEP 1916/1917/1925
• Company Specifications such as: -Shell -Aramco (Saudi)
6
![Page 7: NDT & QA in Pipe Manufacturing · PIPE MANUFACTURING •Excluding seamless pipe, the process starts with plate or coil. Then, we have: 1. ERW ( Electro Resistance Weld) Pipes; 2.](https://reader034.fdocuments.net/reader034/viewer/2022042310/5ed794ae67b53e06555d2cb3/html5/thumbnails/7.jpg)
160 CHANNEL PLATE UT SYSTEM
7
![Page 8: NDT & QA in Pipe Manufacturing · PIPE MANUFACTURING •Excluding seamless pipe, the process starts with plate or coil. Then, we have: 1. ERW ( Electro Resistance Weld) Pipes; 2.](https://reader034.fdocuments.net/reader034/viewer/2022042310/5ed794ae67b53e06555d2cb3/html5/thumbnails/8.jpg)
DETAIL OF EDGE FOLLOWING PROBES
![Page 9: NDT & QA in Pipe Manufacturing · PIPE MANUFACTURING •Excluding seamless pipe, the process starts with plate or coil. Then, we have: 1. ERW ( Electro Resistance Weld) Pipes; 2.](https://reader034.fdocuments.net/reader034/viewer/2022042310/5ed794ae67b53e06555d2cb3/html5/thumbnails/9.jpg)
ERW WELD AND FULL BODY TESTING
![Page 10: NDT & QA in Pipe Manufacturing · PIPE MANUFACTURING •Excluding seamless pipe, the process starts with plate or coil. Then, we have: 1. ERW ( Electro Resistance Weld) Pipes; 2.](https://reader034.fdocuments.net/reader034/viewer/2022042310/5ed794ae67b53e06555d2cb3/html5/thumbnails/10.jpg)
PROBE ARRANGEMENT
![Page 11: NDT & QA in Pipe Manufacturing · PIPE MANUFACTURING •Excluding seamless pipe, the process starts with plate or coil. Then, we have: 1. ERW ( Electro Resistance Weld) Pipes; 2.](https://reader034.fdocuments.net/reader034/viewer/2022042310/5ed794ae67b53e06555d2cb3/html5/thumbnails/11.jpg)
SAW PIPE UT SYSTEM
![Page 12: NDT & QA in Pipe Manufacturing · PIPE MANUFACTURING •Excluding seamless pipe, the process starts with plate or coil. Then, we have: 1. ERW ( Electro Resistance Weld) Pipes; 2.](https://reader034.fdocuments.net/reader034/viewer/2022042310/5ed794ae67b53e06555d2cb3/html5/thumbnails/12.jpg)
SPIRAL WELD UTBLOCK DIAGRAM OF THE SYSTEM
![Page 13: NDT & QA in Pipe Manufacturing · PIPE MANUFACTURING •Excluding seamless pipe, the process starts with plate or coil. Then, we have: 1. ERW ( Electro Resistance Weld) Pipes; 2.](https://reader034.fdocuments.net/reader034/viewer/2022042310/5ed794ae67b53e06555d2cb3/html5/thumbnails/13.jpg)
CALIBRATION DEFECT GEOMETRY
![Page 14: NDT & QA in Pipe Manufacturing · PIPE MANUFACTURING •Excluding seamless pipe, the process starts with plate or coil. Then, we have: 1. ERW ( Electro Resistance Weld) Pipes; 2.](https://reader034.fdocuments.net/reader034/viewer/2022042310/5ed794ae67b53e06555d2cb3/html5/thumbnails/14.jpg)
![Page 15: NDT & QA in Pipe Manufacturing · PIPE MANUFACTURING •Excluding seamless pipe, the process starts with plate or coil. Then, we have: 1. ERW ( Electro Resistance Weld) Pipes; 2.](https://reader034.fdocuments.net/reader034/viewer/2022042310/5ed794ae67b53e06555d2cb3/html5/thumbnails/15.jpg)
TRANSDUCER CONFIGURATION
• 1 – Longitudinal Defect Detection
• 2 – Transverse Defect Detection
• 3 – Defect Detection in the HAZ
• 4 – Full Body Inspection (20% Coverage)
![Page 16: NDT & QA in Pipe Manufacturing · PIPE MANUFACTURING •Excluding seamless pipe, the process starts with plate or coil. Then, we have: 1. ERW ( Electro Resistance Weld) Pipes; 2.](https://reader034.fdocuments.net/reader034/viewer/2022042310/5ed794ae67b53e06555d2cb3/html5/thumbnails/16.jpg)
SPIRAL WELD UT SYSTEM
![Page 17: NDT & QA in Pipe Manufacturing · PIPE MANUFACTURING •Excluding seamless pipe, the process starts with plate or coil. Then, we have: 1. ERW ( Electro Resistance Weld) Pipes; 2.](https://reader034.fdocuments.net/reader034/viewer/2022042310/5ed794ae67b53e06555d2cb3/html5/thumbnails/17.jpg)
CLOSE UP OF PROBE HOLDERS
![Page 18: NDT & QA in Pipe Manufacturing · PIPE MANUFACTURING •Excluding seamless pipe, the process starts with plate or coil. Then, we have: 1. ERW ( Electro Resistance Weld) Pipes; 2.](https://reader034.fdocuments.net/reader034/viewer/2022042310/5ed794ae67b53e06555d2cb3/html5/thumbnails/18.jpg)
CABIN VIEW OF PROBE CLUSTER
![Page 19: NDT & QA in Pipe Manufacturing · PIPE MANUFACTURING •Excluding seamless pipe, the process starts with plate or coil. Then, we have: 1. ERW ( Electro Resistance Weld) Pipes; 2.](https://reader034.fdocuments.net/reader034/viewer/2022042310/5ed794ae67b53e06555d2cb3/html5/thumbnails/19.jpg)
LASER SEAM TRACKER CAMERA
![Page 20: NDT & QA in Pipe Manufacturing · PIPE MANUFACTURING •Excluding seamless pipe, the process starts with plate or coil. Then, we have: 1. ERW ( Electro Resistance Weld) Pipes; 2.](https://reader034.fdocuments.net/reader034/viewer/2022042310/5ed794ae67b53e06555d2cb3/html5/thumbnails/20.jpg)
SEAM TRACKER DISPLAY
![Page 21: NDT & QA in Pipe Manufacturing · PIPE MANUFACTURING •Excluding seamless pipe, the process starts with plate or coil. Then, we have: 1. ERW ( Electro Resistance Weld) Pipes; 2.](https://reader034.fdocuments.net/reader034/viewer/2022042310/5ed794ae67b53e06555d2cb3/html5/thumbnails/21.jpg)
REPORTING
![Page 22: NDT & QA in Pipe Manufacturing · PIPE MANUFACTURING •Excluding seamless pipe, the process starts with plate or coil. Then, we have: 1. ERW ( Electro Resistance Weld) Pipes; 2.](https://reader034.fdocuments.net/reader034/viewer/2022042310/5ed794ae67b53e06555d2cb3/html5/thumbnails/22.jpg)
CONCLUSION
• The automated UT systems are capital intense, but they perform reliable ultrasonic inspection for improved quality, reliability and environmental safety of pipelines.