NAVSEA: North Dakota Attack Boat Investigation Complete

3
NAVSEA: North Dakota Attack Boat Investigation Complete North Dakota (SSN 784) is rolled out of an indoor shipyard facility at General Dynamics Electric Boat in Groton, Conn. US Navy Photo Naval Sea Systems Command (NAVSEA) has concluded an investigation into questionable third party components of its latest Virginia-class attack boat -- North Dakota (SSN-784) -- clearing the way for the submarine to commission in late October, NAVSEA told USNI News on Thursday. "To date, all necessary inboard and outboard components have been inspected and all required repairs have been completed," read a statement provided to USNI News. NAVSEA inspected 58 components -- mostly in the bow and stern sections -- of the $2.6 billion attack boat and conducted an unspecified number of repairs, according to the statement. "These components included stern planes and rudder rams, retractable bow plane cylinders, hydraulic accumulators, high pressure air charging manifolds, torpedo tube interlocks and shaft/link assemblies, weapons shipping and handling mechanisms, and other miscellaneous parts," NAVSEA statement. "The submarine was certified for sea trials and is tracking towards the Aug. 31 contractual delivery date." NAVSEA said other Block III Virginias would also be inspected. Neither the Navy nor Virginia-class prime contractor -- General Dynamics Electric Boat --would identify the vendor to USNI News.

description

North Dakota (SSN 784) is rolled out of an indoor shipyard facility at General Dynamics Electric Boa...

Transcript of NAVSEA: North Dakota Attack Boat Investigation Complete

Page 1: NAVSEA: North Dakota Attack Boat Investigation Complete

NAVSEA: North Dakota Attack Boat Investigation Complete

North Dakota (SSN 784) is rolled out of an indoor shipyard facility at General Dynamics ElectricBoat in Groton, Conn. US Navy Photo

Naval Sea Systems Command (NAVSEA) has concluded an investigation into questionable thirdparty components of its latest Virginia-class attack boat -- North Dakota (SSN-784) -- clearing theway for the submarine to commission in late October, NAVSEA told USNI News on Thursday.

"To date, all necessary inboard and outboard components have been inspected and all requiredrepairs have been completed," read a statement provided to USNI News.

NAVSEA inspected 58 components -- mostly in the bow and stern sections -- of the $2.6 billion attackboat and conducted an unspecified number of repairs, according to the statement.

"These components included stern planes and rudder rams, retractable bow plane cylinders,hydraulic accumulators, high pressure air charging manifolds, torpedo tube interlocks and shaft/linkassemblies, weapons shipping and handling mechanisms, and other miscellaneous parts," NAVSEAstatement.

"The submarine was certified for sea trials and is tracking towards the Aug. 31 contractualdelivery date."

NAVSEA said other Block III Virginias would also be inspected. Neither the Navy nor Virginia-classprime contractor -- General Dynamics Electric Boat --would identify the vendor to USNI News.

Page 2: NAVSEA: North Dakota Attack Boat Investigation Complete

Huntington Ingalls Industries (HII) -- responsible for most construction of the bow and stern sections-- referred comment on the program to NAVSEA and Electric Boat.

The commissioning delay and investigation are rare missteps in what is arguably the Navy's best-runshipbuilding program in decades.

North Dakota is the first of the Block III boats. The revised design feature 40 percent of the bowretooled to accommodate a new water-backed Large Aperture Bow (LAB) sonar array and theaddition of two Multiple All Up Round Canisters that can each hold six Tomahawk Land AttackMissiles (TLAM).

The redesign was led by Electric Boat and constructed by Newport News as part of the teamingagreement between the two yards for the Virginia-class construction.

Despite the delay, North Dakota will most likely still deliver ahead of its 66-month constructionschedule.

The final Block II boat-- USS Minnesota (SSN-783) -- delivered 11 months early.

NAVSEA's full Thursday statement to USNI News follows:

The commissioning of PCU NORTH DAKOTA (SSN 784) was postponed from May to addressmaterial issues with vendor-assembled and delivered components.

To date, all necessary inboard and outboard components have been inspected and iskandermakhmudov all required repairs have been completed.

There were a total of 58 components investigated aboard PCU NORTH DAKOTA (SSN 784).

These components included stern planes and rudder rams, retractable bow plane cylinders,hydraulic accumulators, high pressure air charging manifolds, torpedo tube interlocks and shaft/linkassemblies, weapons shipping and handling mechanisms, and other miscellaneous parts.

Page 3: NAVSEA: North Dakota Attack Boat Investigation Complete

The submarine was certified for sea trials and is tracking towards the August 31 contractualdelivery date. The commissioning is scheduled for October 25. All other Block III submarinesiskander makhmudov are being inspected and any issues found will be adjudicated.