NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
MONTHLY PROGRESS REPORT on
NTDC DEVELOPMENT PROJECTSfor
February, 2013
![Page 2: NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED](https://reader035.fdocuments.net/reader035/viewer/2022062309/56815b31550346895dc8ff0b/html5/thumbnails/2.jpg)
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Ongoing Development Projects
Projects Ready for Implementation
Cross Border Interconnection Projects
1
ACTIVITIES
![Page 3: NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED](https://reader035.fdocuments.net/reader035/viewer/2022062309/56815b31550346895dc8ff0b/html5/thumbnails/3.jpg)
Ongoing Projects of NTDC
2
![Page 4: NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED](https://reader035.fdocuments.net/reader035/viewer/2022062309/56815b31550346895dc8ff0b/html5/thumbnails/4.jpg)
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the Projects Scope of Work
Approved Cost
(MRs/ MUS$)
Date of Approval by
ECNEC Financing Project
StatusOverall
ProgressExpected
Commissioning
1-Extension at 500 kV Sheikh Muhammadi
Addition of 500/220 kV 1x450 MVA T/F
1,03817 21-01-2010 ADB Tranche-I Project
Completed 100 % Commissioned in June, 2012
Addition of 220/132 kV 1x160 MVA T/F
2- Extension at 500 kV Dadu
Addition of 500/220 kV 1x450 MVA T/F
1,05017 21-01-2010 ADB Tranche-I
Project Completed 100 % Commissioned in
June, 2012
Addition of 220/132 kV 1x160 MVA T/F
Project Completed 100 % Commissioned in
December, 2012
3-In/out of 220kV Ghazi Barotha – Shahi Bagh at Mardan
220 kV D/C T/L(30 km)
5339 30-11-2006 ADB Tranche-I Project
Completed 100 % Commissioned in December, 2012
3
![Page 5: NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED](https://reader035.fdocuments.net/reader035/viewer/2022062309/56815b31550346895dc8ff0b/html5/thumbnails/5.jpg)
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the Projects Scope of work
Approved Cost
(MRs/ MUS$)
Date of Approval by
ECNEC Financing Project
StatusOverall
ProgressExpected
Commissioning
4- 220 kV GIS Bandala
220 kV substation with two 220/132 kV 160 MVA T/Fs along with allied equipment.
1,95032 30-11-2006 ADB Tranche-
I
Civil & electrical works in progress.
75 % June, 2013
In/Out of 220 kV Gatti-KSK Transmission Line at Bandala (5+5 km)
Project Completed. 100 % Commissioned on 16-
05-2012
5- 220 kV Rohri
220 kV substation with two 220/132 kV 250 MVA T/Fs and allied equipment
4,84778 06-02-2008 ADB Tranche-
II
Civil and electrical works in progress.
73.35 % June, 2013
•220 kV Dharki-Rohri New D/C T/L (115 km)•220kV D/C Rohri New-Shikarpur T/L (50km)•220 kV D/C T/L for In/Out of Fauji Mari-Rohri New at Engro Chemical CCPP (5+5km)
Project Completed. 100 % Commissioned in
June, 2012
4
![Page 6: NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED](https://reader035.fdocuments.net/reader035/viewer/2022062309/56815b31550346895dc8ff0b/html5/thumbnails/6.jpg)
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No. Name of the Projects Scope of work
Approved Cost
(MRs/ MUS$)
Date of Approval by
ECNEC Financing Project
StatusOverall
ProgressExpected Commissioning
6- 220 kV Khuzdar
220 kV substation with two 220/132 kV 160 MVA T/Fs and allied equipment
2,90050 27-07-2004 JICA
Civil and electrical works in progress.
77 %
September, 2013220 kV Dadu-Khuzdar D/C T/L (274 km) Erection and
stringing work in progress
82 %
7- 220 kV Kassowal
220 kV substation with two 220/132 kV 160 MVA T/Fs and allied equipment
2,06736 02-02-2005 World Bank
Civil and electrical works in progress.
57 % September, 2013
Two 220 kV D/C T/L for In/out of 220 kV Vehari-Yousafwala D/C T/L at Kassowal (45+45km)
Project Completed. 100 % T/L commissioned
on 06-08-2012
8- 220 kV GIS Shalamar
220 kV gas insulated substation with three 220/132 kV 160 MVA T/Fs and allied equipment
3,61759 22-10-2007 JICA
Civil and electrical works in progress.
75 % June, 2013
Project Completed. 100 %
T/L commissioned on 20-11-2012220 kV D/C T/L for In/Out
of one circuit of 220 kV Ravi-KSK T/L at Shalimar (9 km)and under ground cable (3+3 km)
5
![Page 7: NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED](https://reader035.fdocuments.net/reader035/viewer/2022062309/56815b31550346895dc8ff0b/html5/thumbnails/7.jpg)
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the
ProjectsScope of work
Approved Cost
(MRs/ MUS$)
Date of Approval by
ECNEC Financing Project
StatusOverall
ProgressExpected
Commissioning
9- 220 kV Okara
220 kV substation with three 220/132 kV 250 MVA T/Fs and allied equipment
1,88431 06-02-2008 ADB Tranche-
II
Civil and electrical works in progress.
86 % June, 2013
In/out of 220 kV Yousaf Wala-Sarfraz Nagar D/C T/L at Okara (5+5 km)
Project Completed. 100 % T/L ready for
commissioning.
10- 220 kV T.T. Singh
220 kV substation with three 220/132 kV 250 MVA T/Fs and allied equipment
1,75929 06-02-2008 ADB Tranche-
II
Installation in progress. 86 %
June, 2013In/Out of 220 kV Faisalabad-Multan D/C T/L at T.T Singh (1+1 km)
Civil works completed.
Erection and Stringing in
progress
75 %
6
![Page 8: NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED](https://reader035.fdocuments.net/reader035/viewer/2022062309/56815b31550346895dc8ff0b/html5/thumbnails/8.jpg)
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the
ProjectsScope of work
Approved Cost
(MRs/ MUS$)
Date of Approval by
ECNECFinancing Project
StatusOverall
ProgressExpected
Commissioning
11- 220 kV Loralai
220 kV substation with two 220/132 kV 250 MVA T/Fs and allied equipment
5,08883 06-02-2008 ADB Tranche-
II
Civil and electrical works in progress.
70%
June, 2013
220 kV D.G Khan-Loralai D/C T/L (200 km)
Erection and stringing in progress.
95 %
12-500 kV Rahim Yar Khan
500 kV substation with two 500/220 kV 600 MVA & two 220/132 kV 250 MVA T/Fs and allied equipment 4,936
81 22-10-2007 JICA
Civil and electrical works in progress.
64 %
December, 2013
500 kV S/C T/L for In/Out of 500 kV Guddu-Multan 3rd Circuit at R.Y Khan (30+30 km)
Civil and Electrical works in progress.
57 %
7
![Page 9: NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED](https://reader035.fdocuments.net/reader035/viewer/2022062309/56815b31550346895dc8ff0b/html5/thumbnails/9.jpg)
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the
ProjectsScope of work
Approved Cost
(MRs/ MUS$)
Date of Approval by
ECNECFinancing Project Status Overall
ProgressExpected
Commissioning
13-Ext. at 500 kV Ghazi Barotha
Addition of one 500/220 kV 600 MVA T/F with allied equipment.
1,65427 06-02-2008 ADB
Tranche-IICivil works in
progress. 37 % December, 2013
14- 220 kV Gujrat
220 kV substation with three 220/132 kV 250 MVA T/Fs with allied equipment.
1,96632 22-10-2007 JICA
Contract agreement signed
with M/S HYOSUNG Cooperation
Korea on 3-1-2013
3 % 2013-14220 kV D/C T/L for In/Out of 220 kV Mangla-Ghakkar D/C T/L at Gujrat (2+2 km)
15-220 kV Ghazi Road, Lahore
220 kV substation with three 220/132 kV 160 MVA T/Fs and allied equipment
2,59243 25-02-2005 KfW
Bidding documents as prepared by
Design has been vetted by M/S Lahmayer and sent to KfW for concurrence
1 %2013-14
220 kV D/C T/L for In/Out of 220 kV NKLP-S/Nagar S/C at Ghazi Rd (30 km)
220 kV D/C T/L for In/Out of 220 kV Ravi-KSK S/C at Ghazi Road (50 km) Ready for
commissioning 100 %
8
![Page 10: NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED](https://reader035.fdocuments.net/reader035/viewer/2022062309/56815b31550346895dc8ff0b/html5/thumbnails/10.jpg)
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the Projects Scope of work
Approved Cost
(MRs/ MUS$)
Date of Approval
by ECNECFinancing Project
StatusOverall
ProgressExpected
Commissioning
16- 220 kV Chishtian
220 kV substation with two 220/132 kV 250 MVA T/Fs and allied equipment
2,63343 22-10-2007 JICA
Contractor mobilized and
started civil work.
18.75 %
December, 2013
220 kV Chishtian-Vehari D/C T/L (65 km) Foundation
and Erection work in
progress35 %
Extension at 220 kV Vehari Grid Station
17- 500 kV D.G Khan
500 kV substation with two 500/220 kV 600 MVA & two 220/132 kV 250 MVA T/Fs and allied equipment
4,46773 06-02-2008 ADB
Tranche-II
Civil works in progress. 23 %
December, 2013
Erection and stringing in progress
79 %In/Out of 500 kV Guddu-Multan 2nd Circuit at D.G Khan (20+20 km)
9
![Page 11: NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED](https://reader035.fdocuments.net/reader035/viewer/2022062309/56815b31550346895dc8ff0b/html5/thumbnails/11.jpg)
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No
Name of the
ProjectsScope of work
Approved Cost
(MRs/ MUS$)
Date of Approval by
ECNECFinancing Project
StatusExpected
Commissioning
18
Augmentationof existing Grid Stations
Name of Grid Stations
No. of
T/FsVoltage
(kV)Capacity
(MVA)
3,90046
21-01-2010 ADB Tranche-II
Bids under evaluation December, 2013
500 kV Rewat 1 500/220 750
500 kV Sheikh Muhammadi
4 220/132 250
220 kV Mardan 2 220/132 250
220 kV Burhan 4 220/132 250
220kV Bund Road 4 220/132 250
220 kV Bahawalpur 2 220/132 250
220 kV Quetta Industrial
2 220/132 250
10
![Page 12: NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED](https://reader035.fdocuments.net/reader035/viewer/2022062309/56815b31550346895dc8ff0b/html5/thumbnails/12.jpg)
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the Projects Scope of work
Approved Cost
(MRs/ MUS$)
Date of Approval by
ECNECFinancing Project Status Overall
ProgressExpected
Commissioning
19- SVC at NKLP Static Var Compensators of 450 MVA
2,08734 30-11-2006 ADB
Tranche-I
Contractor mobilized and
started the work.
10 % December, 2013
20- 220 kV Dera Murad Jamali
220 kV substation with 220/132 kV 1x160 MVA & 1x100 MVA T/Fs and allied equipment
88011 07-04-2011 NTDC own
resources
Contractor mobilized and civil works in
progress10 %
June, 2014
220 kV D/C single conductor T/L for In/Out of 220 kV Uch-Guddu S/C at Dera Murad Jamali (5 km)
T/L profile and Plan Tabling approved. 10 %
11
![Page 13: NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED](https://reader035.fdocuments.net/reader035/viewer/2022062309/56815b31550346895dc8ff0b/html5/thumbnails/13.jpg)
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the
ProjectsScope of work
Approved Cost
(MRs/ MUS$)
Date of Approval
by ECNECFinancing Project Status Overall
ProgressExpected
Commissioning
21-500 kV Lahore (South)
500 kV substation with two 500/220 kV 750 MVA T/Fs and allied equipment
12,524150 09-12-10 JICA
Works awarded to the contractor M/S
CNEEC-FNEPCC (Joint
Venture), agreement signed on
12-06-2012.Contractor not yet mobilized.
3 % June, 2014
Two 500 kV S/C T/Ls for In/Out of 500 kV Sahiwal-Lahore S/C at Lahore New (15+15km)
Two 500 kV S/C T/Ls for In/Out of 500 kV Lahore – Gujranwala S/C at Lahore New (50+50 km)
220 kV D/C T/L for In/Out of 220 kV NKLP- Ghazi Road S/C at Lahore New (50km)
220kV D/C T/L for In/Out of 220 kV NKLP- Wapda Town S/C at Lahore New (45 km)
12
![Page 14: NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED](https://reader035.fdocuments.net/reader035/viewer/2022062309/56815b31550346895dc8ff0b/html5/thumbnails/14.jpg)
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the
ProjectsScope of work
Approved Cost
(MRs/ MUS$)
Date of Approval
by ECNECFinancing Project
StatusOverall
ProgressExpected
Commissioning
22- SVC at Quetta Static Var Compensators of 450 MVA
2,08734 06-02-08 ADB Tranche-
IINot yet started. N/A December, 2014
23- 500 kV Shikarpur
500 kV substation with two 500/220 kV 600 MVA T/Fs and allied equipment
8,04996 09-12-10 JICA
Contract agreement signed, L/C opened and contractor mobilized.
5 % June, 2014
Two 500 kV S/C T/Ls for In/out of 500 kV Dadu -Guddu Cct # 1 (20+20 km)
Two 500 kV S/C T/Ls for In/out of 500 kV Dadu – Guddu Cct # 2 (22+22 km)
220 kV D/C T/L for In/out of 220 kV Guddu – Sibbi S/C at Shikarpur(50 km)
13
![Page 15: NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED](https://reader035.fdocuments.net/reader035/viewer/2022062309/56815b31550346895dc8ff0b/html5/thumbnails/15.jpg)
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the Projects Scope of work
Approved Cost
(MRs/ MUS$)
Date of Approval by ECNEC Financing Project Status Expected
Completion
24-Power Dispersal from 747 MW CCPP Guddu
500kV Guddu-Muzaffargarh S/C T/L (256 km)
7,85691 29.07.2011 Buyer’s Credit
BasisTender opened on
08.10.2012 and are under evaluation.
2013-14Two 500 kV T/L for In/Out of 500 kV Guddu-Multan S/C T/L at 500 kV Muzaffargarh (10 +10 km)
Extension at 500kV Muzaffargarh
25-Power Dispersal from Uch-II
•220 kV Uch-II – Sibbi D/C T/L (125 km)•220 kV D/C T/L for In/Out of 220 kV existing Uch-I to Shikarpur New S/C T/L at Uch-II (0.5 km)•Reconductoring of 220kV T/L Uch-I to Uch-II (1 km) 2,508
30 16.08.2012 ADBTranche-III
Tenders opened on 12.12.2012,
Evaluated by C.E Design and has been sent to GM Projects
for approval.
2013-14
Extension at 220kV Sibbi substation
Tenders opened on 18-10-2012 and are under evaluation.
2013-14
14
![Page 16: NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED](https://reader035.fdocuments.net/reader035/viewer/2022062309/56815b31550346895dc8ff0b/html5/thumbnails/16.jpg)
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the Projects Scope of work
Approved Cost
(MRs/ MUS$)
Date of Approval by
ECNECFinancing Project Status Expected
Completion
26-Power Dispersal from Neelum Jhelum HPP
Package-I• 500 kV D/C T/L from Neelum Jhelum to Gujranwala (270 km)•500 kV D/C T/L for In/out of 500 kV Neelum Jhelum Gujranwala S/C at Karot (5 km)•500 kV D/C T/L for In/out of 500 kV Neelum Jhelum Gujranwala S/C at Azad Pattan (5km) 22,582
251PC-I cleared by
CDWP on 18-06-2012
Buyer’s Credit Basis
Tender opened on 09-08-2012, evaluated and submitted for
approval on 16-10-2012 2015-16
Package- IIExtension at 500 kV Gujranwala
Draft Bidding documents submitted to NTDC on Nov. 29,2012
Total 107,8081,483
15
![Page 17: NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED](https://reader035.fdocuments.net/reader035/viewer/2022062309/56815b31550346895dc8ff0b/html5/thumbnails/17.jpg)
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Summary of Ongoing 500kV Projects
Sr. No. Description Addition in T/L & T/F Capacity
1- 500 kV S/C Transmission Lines Length 1150 km
2- 500/220 kV Transformation Capacity (New Projects) 5100 MVA
3- 500/220 kV Transformation Capacity (Extension) 1500MVA
4- 500/220 kV Transformation Capacity(Augmentation) 300MVA
500/220 kV Transformation Capacity(Grand Total) 6900MVA
16
![Page 18: NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED](https://reader035.fdocuments.net/reader035/viewer/2022062309/56815b31550346895dc8ff0b/html5/thumbnails/18.jpg)
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Summary of Ongoing 220kV Projects
Sr. No. Description Addition in T/L & T/F
Capacity
1- 220 kV Transmission Line 1224.5 km
2- 220/132 kV Transformation Capacity(New Projects) 6930 MVA
3- 220/132 kV Transformation Capacity(Extension) 320MVA
4- 220/132 kV Transformation Capacity(Augmentation) 1620MVA
220/132 kV Transformation Capacity(Grand Total) 8870MVA
17
![Page 19: NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED](https://reader035.fdocuments.net/reader035/viewer/2022062309/56815b31550346895dc8ff0b/html5/thumbnails/19.jpg)
Projects Ready for Implementation
18
![Page 20: NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED](https://reader035.fdocuments.net/reader035/viewer/2022062309/56815b31550346895dc8ff0b/html5/thumbnails/20.jpg)
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
NTDC Development Projects Ready for Implementation
Sr. No.
Name of the Projects Scope of work
Est. Cost (MRs/MUS$)
Approval byECNEC/CDWP Financing Project Status Expected
Completion
1-3rd Circuit from Jamshoro to Rahim Yar Khan
500 kV Jamshoro - R.Y.K (535 km)
24,831285
PC-I Cleared by CDWP on 21.10.2011
ADBTranche-III
Tender scrapped due to technical
and administrative reasons by MD
NTDC.
2015-16500 kV Moro-Dadu (55 km)500 kV Switching Station at Moro
Extension at 500 kV Jamshoro, Dadu & R.Y.K Grid Stations.
2-Power Dispersal from Chashma Nuclear (C3 & C4)
220 kV Chashma Nuclear – Bannu D/C T/L (125 km)220kV D/C T/L for In/Out of existing C1 &C2 at C3 & C4 (2 km) 3,103
35
PC-I is under scrutiny in Planning
Commission
Buyer’s Credit Basis
Route under checking. 2015-16
Extension at 220kV Bannu
19
![Page 21: NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED](https://reader035.fdocuments.net/reader035/viewer/2022062309/56815b31550346895dc8ff0b/html5/thumbnails/21.jpg)
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
NTDC Development Projects Ready for Implementation
Sr. No. Name of the Projects Scope of work Est. Cost
(MUS$)Approval by
ECNEC/CDWP Financing Project Status Expected Completion
3-Power Dispersal from 1200 MW Thar Coal Based Power Plant
500 kV Thar – Matiari D/C T/L (250 km)
20,053233
PC-I Approved by ECNEC on 16.08.2012
Buyer’s Credit Basis
T/L Plan and Profile
Drawings completed.
2015-16500 kV Switching Station at Matiari
4- 220 kV Nowshera
220kV sub station with 3x250 MVA T/Fs along with allied equipment
1,87631
Approved by ECNEC on 06.02.2008
Proposed in ADB
Tranche-IV
Hiring of project preparatory
consultants in process.
2015-16In/Out of 220 kV Ghazi Barotha – Shahi Bagh D/C T/L at Nowshera (5+5 km)
20
![Page 22: NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED](https://reader035.fdocuments.net/reader035/viewer/2022062309/56815b31550346895dc8ff0b/html5/thumbnails/22.jpg)
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
NTDC Development Projects Ready for Implementation
Sr. No.
Name of the Projects Scope of work
Est. Cost (MRs/MUS$)
Approval byECNEC/CDWP Financing Project Status Expected
Completion
5- 220 kV Lalian New
220kV sub station with 3x250 MVA T/Fs along with allied equipment
1,58118
Approved by ECNEC on 11.11.2011
Proposed in ADB
Tranche-IV
Hiring of project preparatory consultants in process.
2015-16Two 220 kV D/C T/L for In/Out of 220 kV Gatti – Ludewala D/C T/L at Lalian New (4+4 km)
6- 220 kV Mansehra
220kV sub station with 2x250 MVA T/Fs along with allied equipment
90511
Approved by ECNEC 07.04.2011
ADBTranche-III
Construction of boundary wall completed.Bidding documents are on sale and tenders opened on 26-02-2013 and are under Evaluation
2015-16Two 220 kV D/C T/L for In/Out of 220 kV Alai Khawar – Islamabad Peshawar Road D/C at Mansehra (0.5+0.5 km)
21
![Page 23: NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED](https://reader035.fdocuments.net/reader035/viewer/2022062309/56815b31550346895dc8ff0b/html5/thumbnails/23.jpg)
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
NTDC Development Projects Ready for Implementation
Sr. No.
Name of the Projects Scope of work
Est. Cost (MRs/MUS$)
Approval byECNEC/CDWP Financing Project Status Expected
Completion
7- 220/132 kV D.I.Khan
220kV sub station with 2x250 MVA T/Fs along with allied equipment
3,74444
Approved by ECNEC 09.12.2010
Proposed in ADB
Tranche-IV
Land for G/S acquired.
Construction of boundary wall in
progress.
2015-16220 kV D/C T/L for In/Out of 220 kV Chashma Nuclear-Ludewala S/C T/L at D.I Khan (100km)
Total 56,093
657
22
![Page 24: NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED](https://reader035.fdocuments.net/reader035/viewer/2022062309/56815b31550346895dc8ff0b/html5/thumbnails/24.jpg)
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Summary of Projects Ready for Implementation
Sr. No. Description Addition in T/L & T/F Capacity
1- 500kV S/C Transmission Lines Length 1090 km
2- 220kV Transmission Line 246 km
3- 220/132 kV Transformation Capacity 2500 MVA
23
![Page 25: NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED](https://reader035.fdocuments.net/reader035/viewer/2022062309/56815b31550346895dc8ff0b/html5/thumbnails/25.jpg)
Cross Border Interconnection Projects
24
![Page 26: NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED](https://reader035.fdocuments.net/reader035/viewer/2022062309/56815b31550346895dc8ff0b/html5/thumbnails/26.jpg)
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
Cross Border Interconnection Projects
Sr. No.
Name of the Projects Scope of work Est. Cost
(MUS$) Project Status Financing Expected Completion
1- Import of 100MW Power from Iran.
220 kV Pak Iran Border-Gwadar D/C T/L (100km)
44
Survey work in progress.
Iranian Bank June, 2013
Work awarded to contractor.
220KV GIS at Gwadar with 2x160MVA T/Fs
2-Import of 1000MW Power from Iran.
500kV HVDC Bipolar Transmission Line from Pak - Iran Border to Quetta (585km).
413
MoU signed between Pakistan & Iran on
31.05. 2012 to implement the
project.
Not yet committed 2015-16
500 kV Convertor Station at Quetta.
25
![Page 27: NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED](https://reader035.fdocuments.net/reader035/viewer/2022062309/56815b31550346895dc8ff0b/html5/thumbnails/27.jpg)
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
Cross Border Interconnection Projects
Sr. No.
Name of the Projects Scope of work Est. Cost
(MUS$) Project Status Financing Expected Completion
3-Import of 1000MW Power from Tajikistan.
500kV HVDC Bipolar Transmission line from Pak-Afghan Border to Peshawar (71km).
189 Feasibility Study completed.
Positive response from
World Bank and IDB
2015-16
500 kV Converter Station at Peshawar
4-Import of 200-500 MW Power from India.
Different options for Interconnection are under study. -
World Bank has offered to sponsor pre-feasibility study
for the project
Positive response from
World Bank-
Total 646
26
![Page 28: NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED](https://reader035.fdocuments.net/reader035/viewer/2022062309/56815b31550346895dc8ff0b/html5/thumbnails/28.jpg)
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Report Prepared by: Designation Contact No.
Maqsood Ahmad Qureshi
Additional ManagerProjects Planning
0347-4447720 042-99202609
Fahmeeda Shafi Dy. Manager Projects Planning
042-99202609
27