National Solidarity Manual Operations Manual (Dec 2004)
-
Upload
roycewiles -
Category
Documents
-
view
217 -
download
0
Transcript of National Solidarity Manual Operations Manual (Dec 2004)
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
1/60
NSP Operational Manual 15 December 2004 Page 1 of 54 Rev. Date: 15 December 04
NATIONAL SOLIDARITY PROGRAM
OPERATIONS MANUAL
TABLE OF CONTENTS
PREFACE 4
I. INTRODUCTION 5A. Background 5B. Goal and Objectives of the NSP 5C. Core Elements and Approach 5D. Scope and Targeting 6E. Conditions for Eligibility and Project Menu 10
II. ORGANIZATIONAL STRUCTURE 14A. Community 14B. Community Development Council and Project Management Committees 13C. Facilitating Partner 20D. Ministry of Rural Rehabilitation and Development 21E. NSP Steering Committee 22
III. CYCLE OF ACTIVITIES 23A. Preparation 23B. Appraisal 24C. Sub-Project Implementation 27D. Monitoring by the Community 27E. Physical and Financial Progress Monitoring 28F. Sub-Project Completion 28
IV. FINANCING AND FUND-FLOW SYSTEM 30A. Overall Fund-Flow Arrangements 30B. Fund Transfer Mechanism 32C. Tripartite Agreement 33
D. Disbursement to Communities 34E. Fund Management at the Community level 35F. Financial Reporting by Facilitating Partners 36
V. COMMUNITY PROCUREMENT 37A. Direct Single Source Procurement 37B. Competitive Shopping 38C. Competitive Tendering 39D. Direct Contracting 41E. Waivers 42F. Procurement above AFA 3 Million 43G. Procurement Forms 43
VI. SOCIAL, ENVIRONMENTAL AND MINE RISK SAFEGUARDS 45
VII. COMPLAINTS PROCESSING AND RESOLUTION 48
VIII. MONITORING AND EVALUATION 50
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
2/60
NSP Operational Manual 15 December 2004 Page 2 of 54 Rev. Date: 15 December 04
Acronyms and abbreviations
CDC Community Development Council
DAB Da Afghanistan Bank
FP Facilitating Partners
IDA International Development Association
IDP Internally Displaced Persons
MoF Ministry of Finance
MRRD Ministry of Rural Rehabilitation and Development
NGO Non-governmental Organization
NSP National Solidarity Program
OC Oversight Consultant
RRD Provincial office of MRRD
UXO Unexploded ordnance
Annex 1
Disbursement Forms:
NSP Disbursement Process GuidelinesDisbursement Form 1 Community Profile (Baseline Data) FormDisbursement Form 2 CDC Election & CompositionDisbursement Form 3 Community Development Council Registration ApplicationDisbursement Form 4 Signatory Authorization (for block grant withdrawals)Disbursement Form 4a Account Opening Form for NSPDisbursement Form 4b Authorized Signatures (for block grant withdrawals)Disbursement Form 5 Certificate of Registration of Community Development Council
Disbursement Form 6 Summary of Community Development Planning ProcessDisbursement Form 7 Sub-Project Proposal FormDisbursement Form 7a Verification of Mine Risk Safety/ClearanceDisbursement Form 7b Sub-Project Summary Sheet (English)Disbursement Form 7c Project Eligibility Appraisal (English)Disbursement Form 8 Tripartite Implementation AgreementDisbursement Form 9 Block Grant Fund Request
Annex 2
NSP Accounting Forms
1 Accounting Instructions
Acc Form 1 Cash Receipt VoucherAcc Form 2 Vendors InvoiceAcc Form 3 CDC Cash BookAcc Form 4 DAB ChequeAcc Form 5 CDC Bank BookAcc Form 6 CDC Cash Advance BookAcc Form 7 CDC Petty Cash Count FormAcc Form 8 CDC Stock book
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
3/60
NSP Operational Manual 15 December 2004 Page 3 of 54 Rev. Date: 15 December 04
Annex 3
NSP Procurement Forms
Procurement Form 1 - Declaration of Impartiality and ConfidentialityProcurement Form 1.1 - Invitation to QuoteProcurement Form 1.2 - CDC Bid Evaluation Form
Procurement Form 1.3 - Purchase OrderProcurement Form 2.1- Advertisement NoticeProcurement Form 2.2.1 - Contract for Supply of GoodsProcurement Form 2.2.2 - Contract for WorksProcurement Form 2.2.3 - Contract for ServicesProcurement Form 3.1 - Waiver/Direct Contracting Form
Annex 4
NSP Reporting Forms
Reporting Form 1 - Project Completion FormReporting Form 2 - Certificate of Completion of a Sub-project
Reporting Form 5 - Spot Check Reporting FormReporting Form 6 - Format for Monthly Status Report (Narrative)Reporting Form 6a- Format for Monthly Status ReportReporting Form 8 - Oversight Consultant Quarterly ReportReporting Form 16 - Community Quarterly ReportReporting Form 16a - Community Progress ReportReporting Form 19 - Facilitating Partner Quarterly ReportReporting Form 19a - Facilitating Partner Progress reportsInstructions for Quarterly Progress Reports
Annex 5
Social, Environmental and Mine Risk Safeguards Forms
Safeguard Form 1 - Environmental Impact Identification and Assessment for NSPSafeguard Form 2 - Land Acquisition Assessment & Planning Data SheetSafeguard Form 3 - Form to Document Contribution of Assets
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
4/60
NSP Operational Manual 15 December 2004 Page 4 of 54 Rev. Date: 15 December 04
PREFACE
The National Solidarity Program (NSP) is executed by the Ministry of Rural Rehabilitation
and Development (MRRD) with funding from the International Development Association
(IDA), the Afghanistan Reconstruction Trust Fund (ARTF) and other donors. The NSP
operational manual provides information on key aspects of the NSP including the project
mandate, objectives, institutional arrangements, sub-project processes, transfer of funds and
financial management, and monitoring and evaluation procedures among others. The main
audiences for the NSP operational manual are the national, provincial and district level
government officials, Facilitating Partners, the Oversight Consultant, and other consultants.
The NSP operational manual is intended to ensure consistency, transparency andaccountability in the application of project management procedures at all levels. The NSP
operational manual is considered to be part of the Development Grant Agreement with IDA
and is therefore a legally binding document. The NSP operational manual will be reviewed
and revised biannually based on lessons learned from the field.
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
5/60
NSP Operational Manual 15 December 2004 Page 5 of 54 Rev. Date: 15 December 04
I. INTRODUCTION
A. Background
The National Solidarity Program (NSP) was created by the Government of Afghanistan to
develop the ability of Afghan communities to identify, plan, manage, and monitor their own
development projects. NSP promotes a new development paradigm whereby communities
are empowered to make decisions and control resources during all stages of the project cycle.
In accordance with government policy, the program is expected to lay the foundations for a
long-term strengthening of local governance, to make it more inclusive (e.g. for women,
Internally Displaced Persons (IDPs), returnees, ethnic minorities), and to provide assistance
for reconstruction and development of communities.
The NSP has an implementation framework that includes a methodology for providing direct
financing to communities through transparent eligibility procedures for selection of sub-
projects. This methodology focuses on the development and strengthening of inclusivecommunity institutions through participatory planning and resource management as a basis
for community development.
B. Goal and Objectives of the NSP
The goal of the NSP is to reduce poverty through empowering communities with regard to
improved governance, and social, human, and economic capital. The objectives of the
program are to: (1) lay the foundations for a strengthening of community level governance,
and to (2) support community-managed sub-projects comprising reconstruction and
development that improve the access of rural communities to social and productive
infrastructure and services. The outcomes that the NSP aims to achieve are (i) the
establishment of a framework for village level consultative decision making and
representative local leadership as a basis for interaction within and between communities on
the one hand, and with the administration and aid agencies on the other, and (ii) local level
reconstruction, development, and capacity building which will lead to a decrease in poverty
levels.
The NSP grants to villages are intended to act as catalysts in this process and at the same time
provide much needed support for local reconstruction and development activities.
C. Core Elements and Approach
The design of NSP consists of four core elements:
Facilitationat the community level to assist communities establish inclusivecommunity institutions through elections, reach consensus on priorities andcorresponding sub-project activities, develop eligible sub-proposals that comply with
NSP appraisal criteria, and implement approved project sub-proposals;
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
6/60
NSP Operational Manual 15 December 2004 Page 6 of 54 Rev. Date: 15 December 04
A system of direct block grant transfersto support rehabilitation or developmentactivities (sub-projects) planned and implemented by the elected CommunityDevelopment Councils;
A series of capacity building activitiesto enhance the competence of CommunityDevelopment Council members (both men and women) for financial management,
procurement, technical skills, and transparency, and,
Activities linking local institutions to government administration and aidagencieswith available services and resources.
Quality of process is essential for the long term sustainability of community investments and
for the success of a program like the NSP. As such, community level planning must follow
an approach that complies with the basic principles below:
participatory planningof activities through inclusive community meetings andrepresentative elected development councils;
community contributionsto capital costs and operation and maintenance;
transparency and accountabilityof budgeting and accounting.
The goal of this approach is to ensure that communities are able and inclined to institute a
broad based inclusive decision-making system (which includes women as well as members
from marginalized sections of the villages) through community meetings and development
councils. Through this process the communities will acquire or strengthen the skills and
attitudes necessary to enhance their capacity to define, manage and govern their development.
To achieve this goal, the role of the Facilitating Partners (FPs) and the NSP will be to create
an enabling environment through facilitation of inclusive community planning, technical
assistance, and timely release of funds, which will make possible for communities themselves
to manage implementation of the projects they have defined.
D. Scope and Targeting
In the first year, three target districts in each province were selected by MRRD. In the
second year additional districts were selected as needed to establish equity with regard to
coverage of villages between provinces. Close to 6,000 communities were reached in Year 1,
and operations will be expanded to reach an additional 4,800 communities in Year 2,
equalling roughly half of Afghanistans village communities. The selection of districts has
aimed at achieving an optimal match between quality NGO proposals and vulnerable districts
(vulnerability caused by severity of drought and number of Internally Displaced Persons
(IDPs) and refugees). Inputs from provincial governors and Provincial Administrative
Councils have also been sought before district selection was finalized and NGOs contracted.
During the first year, the program operated in a selected set of village communities in the
selected districts (up to 72 per district), and operations will be expanded in year two to cover
the remaining villages in the districts, if any, and/or expand operations to new districts. In
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
7/60
NSP Operational Manual 15 December 2004 Page 7 of 54 Rev. Date: 15 December 04
year two, operations will expand to a new set of communities with consideration of logistics
and optimal use of field staff.1 Funds will be allocated for projects that have been appraised
by the NSP as meeting the eligibility criteria of the NSP (See Section E below), and for
which financing agreements have been signed between the NSP and the community
organization and the Facilitating Partners (Disbursement Form 8).
Definition of community
Communities will be defined on the basis of existing available information from government
records (e.g. the list of registered villages from the 1970s, or the list of villages prepared for
the nomination of the members of the 2002Loya Jirga). However, since the reliability of the
available official data on villages was inconsistent when the records were established, and
since it is by now outdated due to population increase and/or displacements, the identification
of communities for the purpose of the NSP would have to reflect the ground realities existing
today. Where Facilitating Partners find that the realities on the ground deviate significantly
from the existing official village lists, local authorities (e.g. woluswal, MRRD provincialoffice) should be consulted where possible to arrive at a more operationally practical
definition of communities that corresponds to existing local settlement patterns. The proposed
plan for defining communities for the purpose of NSP would always have to be approved by
NSP Kabul. The establishment of a Community Development Council would not affect the
village's legal standing with the Ministry of the Interior. It is important that Facilitating
Partners thoroughly periodically monitor, verify and check actual number of families to
avoid any inflation in family numbers which could be detrimental to the programmes
financial integrity. Spot checks will also be conducted by the Oversight Consultant and
MRRD.
The definition of a community for the purposes of block grant allocation will be based on the
following principles:
A community is a village of more than 25 families;
One Community Development Council will be established for each community.Development Councils can not be established for sub-sets of an existing village (e.g. avillage cannot be split into its constituent political or ethnic/qaumsub-divisions);
One block grant (budget) will be allocated to each new community in Year II at10,000 AFA per family with an upper limit of 3 million AFA per community. This
allocation2requires that the community develops one or more eligible sub-projectproposals within the budget frame. The possibility of introducing a second top-upgrant is currently under consideration.
1 i.e. villages chosen for annual implementation coverage should to the extent possible be more or lessadjacent to facilitate optimal utilization of facilitation staff and transport resources.2 This new allocation is subject to formal World Bank endorsement.
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
8/60
NSP Operational Manual 15 December 2004 Page 8 of 54 Rev. Date: 15 December 04
The block grant of a community can be carried forward to the next year if it has notbeen fully committed or disbursed for specific projects during Year 1. It can only becarried forward from one year to the next. After that, the un-committed amountswould be cancelled.
A family is defined as a nuclear family consisting of a man, his wife (or wives) and
unmarried children, or a widow(er) and her/his unmarried children. The number of families
in the targeted village communities will be assessed by the Facilitating Partner, and this
enumeration can be verified through such means as a community meeting, consultations with
the local mullah(s), and existing village lists for voluntary contributions towards ashar,
mosque repair etc. Once village selection is confirmed (the community will have to confirm
its interest to participate during a mass meeting) and the number of families is agreed, the
block grant amount would be adjusted to reflect the more accurate population size, and
communicated to the community. The community must also be willing to contribute at least
10 % of the value of the block grant to development activities financed out of the block grant.
How to deal with different community sizes?
As stated above, the minimum size of a community potentially eligible for a block grant
allocation would be 25 families. Smaller settlements should be encouraged to join with other
ones to pool their block grant allocations for larger scale joint activities (e.g. a clinic, a
school, or a multi-village pipe water supply system). Where this is not possible, isolated
settlements below 25 families can be exceptionally included, if the rationale provided is
approved by the Oversight Consultant and MRRD.
While communities are encouraged to come together, it is not acceptable under NSP that they
split up in the interest of a higher block grant. In order to avoid detrimental community
divisions into two or more sub-areas or CDCs, which could lead to a negation or weakening
of the principles of solidarity, the following guidelines must be followed.
The sub-area may have a second CDC if some or all of the following criteria apply but
subject to approval of NSP/MRRD/OC in Kabul:
1. If the sub-area has a record or proof of separate community work, such as irrigation
2. If the sub-area has a separate council/shura existing for some years now
3. If the sub-area was listed as a separate entity in the nomination of representative(s) for
the Loya Jirga
How to facilitate the inclusion of recent returnees/IDPs?
An option to facilitate re-integration of IDPs and returning refugees is to communicate to
specific communities with a considerable IDP/refugee population, that the block grant
allocation can be increased upon the return of IDPs/refugees and their participation in project
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
9/60
NSP Operational Manual 15 December 2004 Page 9 of 54 Rev. Date: 15 December 04
planning. This incentive could encourage communities with a high proportion of IDPs or
refugees to initiate consultation with these about their return during the project preparation
phase to obtain access to an increased block grant allocation. Where a return of
IDPs/refugees is planned, and IDPs/refugee families or family members return to their
communities during the project preparation phase, a reassessment of the population size
should be undertaken prior to final project development and costing to enable an adjustment
of the block grant allocation. Where such planning is undertaken, the Facilitating Partner
should assist the community in assessing whether the additional resources provided through
the enhanced block grant and the proposed project activities would enable a sustainable re-
integration of the returnees.
Hence, for all recent cases of returns of refugees or IDPs the following should be undertaken:
1. Re-count the number of families. This should be done by the CommunityDevelopment Council, assisted by the Facilitating Partner, and be cross-checked byMRRD and the Oversight Consultant;
2. Cross-check once again the above number with that of UNHCR to avoid any inflationof numbers and ensure consistency between data;
3. Adjust the block grant amount to the number of additional families, within the limitsfor block grant transfer (specified above);
4. For a return above 20 families (average cluster size), conduct in the briefest delays(not longer than 1 month after the return) a sub-election to include at least onereturnee representative member within the CDC3. If the number of returnee families is
below 20, the CDC must ensure some form of returnee participation into communityaffairs through Project Management Committees or Thematic Committees (e.g.literacy, parent-teacher, water etc.);
5. Ensure the inclusion of returnees, through the above mentioned participation, andthrough a full inclusion in identification, selection, implementation and/or monitoringof sub-projects which should be beneficial to returnee reintegration;
6. A special Returnee-CDC Reintegration Application should be submitted on a needsbasis to the OC/MRRD.
E. Conditions for Eligibility and Project Menu
The Community Development Council will be registered (Disbursement Form 5) with
MRRD after it has been verified that the election was conducted in compliance with the
election rules (see Chapter II.B and Disbursement Form 2). Then the community will be
eligible for the block Grant.
3 The number of representatives can be increased proportionally to number of returnee families vs. size
of community.
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
10/60
NSP Operational Manual 15 December 2004 Page 10 of 54 Rev. Date: 15 December04
To make use of the block grant allocation, the community must develop a Community
Development Plan and an eligible sub-project proposal (or proposals), that fulfils the
following criteria:
is proposed by a representative Community Development Council(which hasbeen elected through a community-wide process),
is endorsed through a community-wide process,
provides equitable access to benefits,
is technically and financially sound,
includes an operation and maintenance plan4,
has at least 10% community contributions towards capital costs ,
includes a commitment to and plans for ensuring transparency of the use ofblock grant funds.
The community contribution towards capital costs can comprise cash, labour, or in kind
contributions such as construction materials and/or transport.5
The activities to be completedunder each sub-project instalment must be clearly specified (including community
contributions). The Facilitating Partner will monitor, assess and report quarterly to the NSP
as to whether this condition is being adequately met.
Toprepare a Sub-project proposal the community should take note that NSP will accept an
open menu of sub-projects within four types of investments, subject to a short negative list.
The four types of investments are6:
1. Community infrastructure(the investments will comply with defined technicalstandards, and will only comprise public goods);
2. Human capital development activities(e.g., time-bound literacy classes, hygieneeducation etc., that are not planned to incur recurrent costs from the state);
3. Self-help savings schemes for women and disabledthat would draw on bestpractice lessons from other projects and be based on a predefined methodology to bedeveloped by NSP (this practice can only comprise 10% of the total value of a blockgrant with an upper limit of AFA 250,000).
4. Productive asset transfers for vulnerable women and disabledthat would draw onbest practice lessons from other projects and will be based on a predefinedmethodology to be developed by NSP (e.g. sewing machines, looms etc. supported by
4 The O&M plan must include not only an operating budget, but a clear indication of a community-managed cost recovery system, such as a user-payer scheme. Without an adequate cost recovery system, thesustainability of the outputs is likely to decrease. This involves careful attention on the part of CDCs andFacilitating Partners - as well as OC/MRRD.5 The time spent by members of the Development Council will not be counted towards the communitycontribution, and cannot be compensated out of the block grant. If the community decides that members of theDevelopment Council should be compensated for their time, this should be from a community contribution overand above the 10% contributed towards the capital costs of projects.6 Investments in income generating assets if later included in the menu would draw on best practicelessons from other projects.
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
11/60
NSP Operational Manual 15 December 2004 Page 11 of 54 Rev. Date: 15 December04
training as required) (the value of the assets can only comprise 10% of the total valueof a block grant with an upper limit of AFA 150,000).
Increasing womens involvement in NSP Year 2
A. Creation of separate female
Community Development Councils
when possible and desirable7is
proposed in order to enhance
womens involvement and
decision-making.
B. Specific investments potentially
targeting women, see 2 to 4 above,
now become full-fledged
entitlements either for projects
directly benefiting women or for
community projects. Women can
either choose to invest their
entitlement into a larger
community project, if they wish to
do so, or alternatively, they may
select more women-focused
projects. Until a creative menu of
truly beneficial and sustainable
projects for women is further
explored within NSP, Facilitating
Partners and CDCs are
encouraged, but not restricted, to
promote human capital
development activities (i.e. 2
above) such as literacy and hygiene
education, which often offer an
initial firm basis on which to build
income generation and other
projects (i.e. 3 and 4 above) .
Box 1. On the Creation of Female CDCs and Corresponding Project Entitlements
Lessons learned from Year 1
1. While female participation in the CDC process has been higher than expected in Year
1, it has been found that the actual involvement of women in the selection,
implementation, monitoring of projects and in overall decision-making remains poor
despite a clear potential for progress in this area. To seize this opportunity for greater
involvement of women, innovative steps must be taken in Year 2 see section on block
grant entitlement below.
2. Another lesson learned from Year 1 is that cultural and other religious constraints have
been found to be obstacles which can be overcome through culturally sensitive social
organizational skills. As such, success in reaching and involving women may be more ofa factor of: a) having an adequate number of qualified female staff and b) a sophisticated
approach to social mobilization on the part of Facilitating Partners regardless of cultural
or other barriers8. As such, it is expected that Facilitating Partners will continue to
engage qualified female staff, and provide them with adequate training as a precondition
for success in reaching and involving women.
3. While mobilization and governance for women tends be prioritized, it is equally
important to reflect on the viability of projects proposed to and by women. Much work
remains to be done in this area to avoid the mushrooming of unsustainable and potentially
detrimental business ventures. An informed and participatory discussion needs to take
place in an effort to produce a list of adequate and promising projects for women based on
global and Afghan best practice, in addition to increasing the capacity of the Oversight
Consultant/MRRD to appraise these types of projects (distinct from engineering
capacity), with a clear emphasis on sustainability and overall impact on poverty reduction.
4. Finally, lessons from Year 1 demonstrate that more emphasis needs to be made to
identify vulnerable women (e.g. female-headed households) as well as disabled both
being entitled to asset transfers. Likewise, careful planning is needed of such asset
transfers to ensure that they contribute to sustainable poverty alleviation.
7 This measure is meant to encourage female participation and decision-making in areas where gender separationmay be appropriate to reach this objective. In more lenient areas, mixed CDCs may be more appropriate.8 In areas where the creation of female CDCs impossible due to cultural constraints, the Facilitating Partners arerequired to advise the OC/MRRD on what alternative is being chosen to address womens needs (e.g. women committees).
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
12/60
NSP Operational Manual 15 December 2004 Page 12 of 54 Rev. Date: 15 December04
Public infrastructure projects would include, but not necessarily be restricted to: irrigation
works; roads including culverts and small bridges; erosion protection; structures promoting
watershed management; water supply facilities; public baths (hamam); and school buildings.
When school buildings are proposed by the community, endorsement would be required from
Ministry of Education that these are included in the development plans of the ministry, and
that funding of operational costs would be provided (fully or with committed contributions
from other agencies). Please refer to Annex 1 for full instructions on how to proceed
regarding schools. Where clinics are proposed for block grants, endorsement is required by
the Ministry of Health that they are included in its development plans and that it will cover
the associated operational costs.
The project will notfund:
equipment or materials that are included in the annual implementation plans by otheragencies (e.g. by other government or NGO projects that are operating in the area);
political campaign materials or donations in any form;
weapons including (but not limited to), mines, guns and ammunition;
chainsaws;
pesticides, herbicides and other chemicals;9
investments detrimental to the environment;
land (purchase or lease), under any conditions;
construction, rehabilitation, or maintenance of any government office buildings;
payments of salaries to government servants or the salaries of the staff of government
subsidized organizations;
payments of salaries to CDC members10;
any activity on land that is considered dangerous due to security hazards or thepresence of unexploded mines or bombs, UXOs,
any activity on land that has disputed ownership or tenure rights;
any activity using child labour , i.e. labour from children below 15 years of age11;
any activity that will support drug crop production or processing of such crops.
The negative list will be reviewed and if necessary revised by NSP every year.
9 Exceptions may be considered based on an assessment by the NSP (with specialized consultantassistance, if required, and after no objection from IDA) in special situations such as eradication of infestationsof locusts or sun pest.10 While the project will not fund salaries of CDC members, the project can fund travel, accommodationand food costs of CDC members exclusively linked to programme or sub-project implementation, such astravels for procurement. These costs should be part of the sub-project proposal and be clearly identified assuch. An effort should be made by the community, as pointed out later in the Manual, to devise a cost recoverystrategy for O&M, and general running costs of the CDC with a view to creating a sustainable mechanismbefore the end of Year 2.11 International Labor Organization norm, adapted to Afghanistan.
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
13/60
NSP Operational Manual 15 December 2004 Page 13 of 54 Rev. Date: 15 December04
The table below defines the eligibility for block grant funding of different types of
subprojects that are not clearly public goods infrastructure. This list may not be exhaustive
and future sub-project proposals that fall in the grey area between public and private goods
will be reviewed by the NSP/MRRD/OC on a case by case basis.
As part of promoting technical soundness, each activity must take into account environmentaland social impacts as defined in the governments Environmental and Social Safeguards
Framework. Since most of the works are expected to be small community-based projects,
environmental risks are generally considered to be minimal. To ensure compliance with the
safeguards framework, all proposals must include completed simple environmental and social
checklists developed by NSP, which describe impacts and mitigations measures, if any. See
Disbursement Form 7c and Chapter 7 (Social, Environmental and Mine Risk Safeguards.
Sub-Project Proposal
Generally
Eligible for
Block Grant
funding
Eligible under the
Women/Disabledcategory
Eligible under
the Asset
Transfer
category
Comment
Diesel Water Pump (irrigation) No No No On negative list
Micro Hydropower Yes - - Equity & O&M plan
Generator for electricity Yes - - Realistic O&M plan
Public Bath (Hamam) Yes - - Realistic O&M plan
Bakery No Yes Yes Business plan & O&M
Mill (diesel) Yes - - O&M plan
Mill (water) Yes - - O&M plan
Carpet/gelim weaving No Yes Yes Equity & Business plan
Tailoring No Yes Yes Equity & Business plan
Farm animals (goats, cow, etc) No Yes Yes Equity & Business plan
Farm inputs (fertilizer, seed) No Yes Yes Equity & Business plan
Grocery store No No Yes Business plan
Tractor No No No
Thresher No No No
Truck, Bus No No No
Religious buildings No No No
Cash donation for disabled No No No
Land leveling for agriculture No No No
Vocational training Yes Yes - Equity in access to benefit
Literacy training Yes Yes - Equity in access to benefit
Other training (computer, tractoretc)
Yes Yes Yes Equity in access to benefit
Check dam (over 3 metres) No No No
Once it is determined through an appraisal of the project proposal (Disbursement Form 7 and
Section III.B) by NSP that the eligibility criteria listed above have been complied with, the
funds will be paid directly from the NSP to a community, according to a defined payment
schedule based on the Tripartite Agreement (see Chapter IV.C and Disbursement Form 8).
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
14/60
NSP Operational Manual 15 December 2004 Page 14 of 54 Rev. Date: 15 December04
The result of the appraisal of the community project proposal will be confirmed on the first
page of Disbursement Form 7.
II. ORGANIZATIONAL STRUCTURE
A. Community
For the purposes of the NSP, a community is defined as a village consisting of at least 25
families that is able to identify a need and come together to access NSP funds. Communities
will be identified on the basis of existing local settlement and social patterns. However, this
would not prevent different distinct villages from joining together to develop assets (e.g. a
school, or a pipe water system) that serves more than one village. In such a situation, people
from all areas that make direct use of the asset should be included as part of the community
for the purposes of the planning, implementation, and maintenance of the joint asset. The
block grant for such joint projects will be equal to the aggregate amount for the collaborating
communities or a portion thereof as required and agreed by the communities. In order toprevent any potential external pressure or influence on the selection of a large project, and
ensure the design and implementation of technically feasible and adequate projects, it is
highly recommended that communities and/or CDCs grouping together be limited to seven.
When more than seven communities join together for the development and management of a
common project, special permission must be sought from the Oversight Consultant and
MRRD.
While a community will be assisted by NSP financially, a key characteristic of this approach
is that it promotes a high level of community participation and ownership during all phases of
the project cycle. As such, functions of the community will include:
Identifying and prioritising needs;
Electing the Community Development Council and relevant Project ManagementCommittees;
Preparation of a community development plan and sub-project proposals;
Providing community contributions;
Participating in field appraisal, project launch ceremony, and all other communitymeetings related to the project;
Management of project implementation by the community through its CommunityDevelopment Council or Project Management Committee(s);
Providing oversight of project implementation with regard to quality and use of funds;
Maintaining the asset after completion with community cost contributions.
B. Community Development Council and Project Management Committees
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
15/60
NSP Operational Manual 15 December 2004 Page 15 of 54 Rev. Date: 15 December04
The Community Development Council (CDC) will be a community-based decision making
body which is elected by the community through elections based on a secret ballot. As the
representative body of the community with regard to the NSP, the Development Council will
be responsible for overseeing the preparation of the Community Development Plan (defining
community needs and priorities, and the project or sub-projects to address some or all of
these priorities), and the preparation and implementation of individual sub-projects. The
Development Council should at least comprise a Chairperson, Treasurer and Secretary. The
Development Council should obtain the endorsement through community meetings
regarding:
decisions on development priorities, and the final selection of project proposalsdeveloped on the basis of agreed priorities,
the size and composition of community contributions, and the use of project funds,
transparency arrangements,
arrangements for maintenance of completed projects.The Community Development Council will sign an overall Tripartite Agreement
(Disbursement Form 8) with NSP and the Facilitating Partner on behalf of the community.
Depending on the number of sub-projects to be managed, smaller Community Project
Management Committees may be established to prepare and manage individual sub-projects,
but they will report to the Community Development Council and the community-wide
meetings. On the other hand, if a community chooses to implement only one or two sub-
projects, the Development Council may manage implementation of those projects. These
representative Development Councils must be registered with NSP as a condition for
receiving assistance and overseeing the management of communally owned property(Disbursement Form 5). A Community Project Management Committee (which can be
identical with the Development Council and should comprise at least a Chairperson,
Secretary, Treasurer, and Storekeeper) nominated by a community wide assembly will be
able to withdraw funds and procure goods and services for implementation of the project after
being registered with the NSP (Disbursement Form 4).
Specifically, the Community Development Council will be responsible for:
Overseeing preparation of the community development plan;
Convening community wide meetings; Overseeing planning and preparation of individual sub-projects through the
community project management committees;
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
16/60
NSP Operational Manual 15 December 2004 Page 16 of 54 Rev. Date: 15 December04
Mobilizing community contributions for a) contribution to capital costs of projects;b) operation and maintenance costs of outputs/assets and c) operation andmaintenance costs of CDC 12;
Ensuring community participation during all phases;
Presenting the sub-project plans at appraisal;
Managing and supervising sub-project implementation;
Overseeing (or directly handling) procurement and financial management at thecommunity level;
Reporting to the community and to NSP on project progress and use of funds.
The Community Development Council will be established through an election which will be
conducted according to the following rules:
Everybody in the community who is entitled to vote in government elections isentitled to be registered as a voter;
Each person has one vote ;
The voting will be conducted through a secret ballot;
Both men and women are eligible to vote and to be members of the CommunityDevelopment Council;
Predefined candidate lists and electioneering are prohibited; and
At least 40% of eligible voters must have voted for an election to be valid.
Development councils elected under an election that does not comply with these rules will
not be eligible for funding under the NSP.
Regarding the first point above, registering as a voter is an entitlement, not an obligation.
However, in declaring whether the election for the Council is valid, an estimate of all eligible
voters, not all registered voters should be used. Whether the community wishes to extend
voting entitlements to people who are not eligible to vote in government elections is a matter
for the community to decide.
In the case of the secret ballot, it is essential to remove, or at least minimise, the opportunity
for undue influence to be exerted when people are voting. The exact mechanism to ensure
this will need to be determined on a case-by-case basis, but the underlying principle is that
each individual should cast his or her vote in private.13
12 While time and input of CDC members cannot count as community contribution, the CDC may wish todiscuss its own mechanisms for compensating those dedicating themselves to community affairs management.In some communities, this has taken the form of assistance in land cultivation.With regard to additional costs of CDC members: while the CDC members initial costs of accommodation,food and travel incurred exclusively for the programme or the implementation of sub-projects can be charged toeach project (and clearly identified as such), it is imperative that the community begins to devise its ownsustainable solution for cost recovery.13 This could involve separate ballot boxes for men and women, decisions on whether the ballot paperwill have a list of all interested eligible cluster members, or whether the name of the candidate for which a vote
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
17/60
NSP Operational Manual 15 December 2004 Page 17 of 54 Rev. Date: 15 December04
Prohibition of candidature and electioneering is critical to reduce the likelihood of elite
capture and intimidation, recognising that it will not remove it. To avoid the problem of
selecting unwilling candidates, community members will prior to the election have an
opportunity to declare, that they are not prepared to accept the position if elected. All
members of the community are candidates until they take the positive step to declare
themselves ineligible.
To have functioning Development Councils, the number of representatives should be between
5 and 15 persons depending on the size of the community. The Development Councils
should select a Chairperson, Secretary and Treasurer. For the Development Council to have
the authority to make decisions over resources it must also have a quorum of the community
involved in the election. For the first round of NSP, a quorum is defined as 40% of all
eligible voters. It is government policy to increase this percentage over the life of the
program
To ensure inclusiveness in terms of different socio-economic, factional, and ethnic/tribal(qaum) sub-divisions within the community, the election process should be based on division
of the community into groups of families (clusters), which will each elect one representative
for the Development Council. Since neighbours are usually also relatives, the division into
clusters will also reducepurdah restrictions on women and thereby facilitate their active
involvement in discussions of the qualities required for representatives and in the election
itself. The size of such clusters will vary depending on the size of the community, but should
not exceed about 20 families. The clusters would in turn serve as the framework for
community wide consultations on proposals from the Development Council, through a
process where the elected councillors consult with and seek feed-back from their electoratebefore decisions on priorities, sub-projects, and community contributions are finalized.
Since communities will only have one Development Council, local solutions should be
agreed for large communities (>300 families) with assistance from the Facilitating Partner.
One such solution could be a two-tier voting process, where candidates elected by clusters of
20 families elect a smaller Development Council (see diagram on following page and also
refer to paragraph How to deal with different community sizes, earlier in the Operations
Manual).
The combination of high levels of illiteracy and the prohibition of predefined candidate lists
and electioneering will present a range of challenges to the Facilitating Partners. However,
both aspects are so central to the program that innovative and creative solutions will need to
is cast is written on the ballot paper. If either of these solutions is agreed, assistance would have to be providedto illiterate voters by the Facilitating Partner, and a process to verify votes cast on a sample basis would alsoneed to be agreed. Another issue that may require different local solutions is whether the names of women canbe listed on ballot papers, and where this is not possible, how the number of eligible women voters isestablished, and how votes are cast for female candidates.
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
18/60
NSP Operational Manual 15 December 2004 Page 18 of 54 Rev. Date: 15 December04
be developed. Since the elections will take place in small clusters of households many of
whom know each other, such solutions are possible. An obvious solution is for the
Facilitating Partner to assist the illiterate members of the community. An alternative is to
prepare ballot papers in the forms of maps of the village, with people marking the address of
the person that they wish to vote for and a symbol for the person within that address (e.g.
distinct symbol for oldest male, oldest female, etc).
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
19/60
NSP Operational Manual 15 December 2004 Page 19 of 54 Rev. Date: 15 December04
Box 2.
On Governance: 5 Pillars of Governance
Priorities for Year 2 communities - Lessons learned from Year 1
While the issue of governance and institutional strengthening will be deepened throughout
participatory discussions in Year 2, it is important that a few pillars of governance be
commonly understood by Facilitating Partners and practised by Community Development
Councils (CDCs). These include:
Pillar 1. Maintenance of an inclusive and representative council. This entails potential
sub-elections to integrate returnee communities, when applicable, as well as an
attempt in Year 2 to create separate Councils for women to enable them to be full
stakeholders in the management of their own development.
Pillar 2. Regular meetings between the CDC and the larger community (e.g. once a
month) in order to ensure fluid communication of proposal status, project progress
and creation of new committees, when applicable. This is important to ensure that the
CDC continues to nurture a democratic and participatory culture.
Pillar 3. CDC visibility and public notice boards need to be an integral part of the
transparency process to keep the larger community informed of project budget
expenditure, progress as well as new ideas and opportunities. In view of the low rate
of literacy these information tools must be visual and simple to understand for greater
outreach.
Pillar 4. Project books and meeting documents should be kept at the CDC level. The
community ownership of the programme must be built through responsibility for
adequate documentation and maintenance of records at the community level, and notlocated with Facilitating Partners .
Pillar 5. Creation of Project Management Committees and/or thematic committees
such as parent-teacher committees, water user associations (mir-ab), health, literacy
or youth committees should be encouraged as a way to involve other members of the
community (in the interest of inclusion, transparency and participation), avoid the
over-burdening of CDC members, and create a greater dynamic of learning and self-
management of community affairs.
In addition to these 5 pillars, the issue of mandate of the CDC, development of by-laws or
constitution of the CDC as well as rules for conducting new elections will be tackled in Year
2. Further guidance on these issues will be provided through participatory exchanges between
Facilitating Partners and the OC/MRRD as the year unfolds.
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
20/60
NSP Operational Manual 15 December 2004 Page 20 of 54 Rev. Date: 15 December04
Option 1: Mixed CDCs
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
21/60
NSP Operational Manual 15 December 2004 Page 21 of 54 Rev. Date: 15 December04
Option 2: Gender-segregated CDCs
DEVELOPMENT COUNCIL ELECTIONS
Male and Female
DEVELOPMENT
COUNCILS
Elected Male and Female
Cluster
Representatives
Household Clusters
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
22/60
NSP Operational Manual 15 December 2004 Page 22 of 54 Rev. Date: 15 December 04
CDC & CLUSTER CONSULTATIONS
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
23/60
NSP Operational Manual 15 December 2004 Page 23 of 54 Rev. Date: 15 December04
C. Facilitating Partner
The primary role of the Facilitating Partner is to provide support and guidance to the
community in meeting the requirements of NSP as described in this manual.The Facilitating Partner will report to the NSP. An agreement will be signed with the
community on the community development plan regarding the exact inputs to be provided
and services to be performed by the Facilitating Partner (Disbursement Form 8).
In each province one or more Facilitating Partners will deploy community facilitators and
technical specialists for three districts at a time to cover a target of up to 216 communities per
year.14 Depending on capacity, individual Facilitating Partners will undertake these activities
in one or more districts, or in one or more provinces.
The roles of the Facilitating Partners are to: Facilitate elections of inclusive CDCs;
Facilitate consultative community project planning comprising CommunityDevelopment Plans and sub-project proposals;
Provide technical assistance to develop sub-project proposals through either:
o facilitating community access to technical assistance available in the market orfrom other agencies; or,
o technical assistance provided by the Facilitating Partner,15
Provide technical assistance to communities during implementation;
Provide training to communities (e.g. book-keeping, procurement, contracting)16;
Conduct monitoring and reporting.
The expected outputs of the Facilitating Partners are:
Eligible project proposals (measured by the number of projects appraised andapproved by the NSP);
14 Where feasible, the Facilitating Partner is expected to recruit and deploy female field staff to enable
involvement of women in the targeted communities in the prioritisation, decision-making, and implementationof projects.15 While the preferred approach under NSP is for communities to avail themselves of technical assistancefor project design through the market, it is recognized that this may not be feasible in many rural areas, and thatin such situations, technical assistance will have to be provided by the Facilitating Partner.16 While there is a clear recognition that CDCs may have to be initially supported by Facilitating Partners(FPs) in the procurement process, it is imperative that this support be given in the form of capacity-buildingrather than substitution of the CDCs role in procurement. As such, should FPs and/or OC/MRRD get involvedin collection of bids, neither should be involved in the bid evaluation process, and at least one member of theCDC or members of the procurement committee should be part of the process, for reasons of transparency andlearning.
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
24/60
NSP Operational Manual 15 December 2004 Page 24 of 54 Rev. Date: 15 December04
Implementation of funded projects (measured by the number of projects completed inaccordance with design standards and in a sustainable manner);
Depending on the number of districts and number of communities defined in the Facilitating
Partners contract, performance will be assessed against the following annual target outputs
for year 1. Achieving or exceeding the targets as defined in the table below will be a key
determinant for extension/expansion of the contracts of the Facilitating Partners.
Provinces(X)
Districts(X)
A
Number ofcommunitieswith CDCs
B 1
Subprojectproposals
submitted (thosemeeting appraisal
criteria)
B 2
Appraised andapprovedsubprojectproposals
C1
Subprojectsunder
implementation(% of funded
projects)
C2
Subprojectscompleted
D
Percentageof
subprojectsfunctioning3 months
aftercompletion
1st
batch 24 80% of A = 19 80% of A = 19 80% of A2 = 19 80% of C1=15
80% of C2= 12
2nd
batch 24 80% of A = 19 80% of A = 19 80% of A2 = 19 80% of C1=15
3rd batch 24 80% of A = 19 80% of A = 19 80% of A2 = 19
Aggregate
target
72 57 57 57 30
The table above assumes that the Facilitating Partners staff is deployed so that facilitation of
project preparation and implementation in a district is undertaken in three successive batches,
each with a four month period for community planning, project preparation and appraisal,
followed by an implementation period depending on the type of project that is undertaken.
The table reflects that some of the target communities in the 3rdbatch would still be in the
process of project preparation and appraisal by the end of year 1, and that implementation, if
started, would not be completed. Likewise, for some of the target communities in the 2nd
batch, ongoing implementation would not be completed by the end of year 1. Since not all
Facilitating Partners may choose to deploy their field staff for coverage of their annual target
as outlined above, an aggregate target is provided for expected outputs in a district in year 1.
The NSP will hold Facilitating Partners accountable for performance against outputs, but the
NSP will provide flexibility to its partners in the choice of specific facilitation methods and
work planning. The Facilitating Partners may use facilitation methods that they deem
appropriate while respecting the eligibility criteria to achieve the outputs against which the
eligibility of community project proposals will be appraised (see Section I.E above), and may
also plan the deployment of their staff and sequencing of activities in ways they consider
optimal for achieving their overall output targets.
D. Ministry of Rural Rehabilitation and Development
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
25/60
NSP Operational Manual 15 December 2004 Page 25 of 54 Rev. Date: 15 December04
MRRD will be responsible for overall management and supervision of the National Solidarity
Program (NSP). Within the ministry, the NSP will be managed by an Oversight Consultant
working with MRRD counterparts in the Community Led Development Department to
strengthen capacity for community development and program management. The Oversight
Consultant will support the Community-Led Development Department regarding:
Management of the NSP block grants for community projects (including effectingfund transfers, tranche payments, financial management, and accounting);
Supervision of the performance of Facilitating Partners (including contractmanagement, contracting of Facilitating Partners beyond those recruited by MRRD
prior to the Oversight Consultant being recruited in order to secure services ofFacilitating Partners to cover all 32 provinces at the scale required);
Appraisal of community project proposals;
Planning and conducting training for the field staff of Facilitating Partners (eitherdirectly or through sub-contracting);
Undertaking technical and financial monitoring, and producing consolidated progressreports, and
Managing an information and communication campaign.
E. NSP Steering Committee
A Steering Committee acts in an advisory capacity to MRRD on overall program policy
formulation and direction, and oversees program implementation. At present, the Steering
Committee is composed of representatives from MRRD and Ministry of Finance (MoF). An
External Review Committee consisting of donors, UN agencies, the Independent Commission
for Human Rights, MoF and MRRD meets on a regular basis to review and endorse all policyand contractual issues.
Discussions are underway to broaden the membership of the Steering Committee by merging
the two bodies. An inter-ministerial committee has been established for policy advice and
coordination. The committee is chaired by MRRD and comprises the ministries of Finance,
Agriculture, Public Health, Education, Irrigation, Labor & Social Affairs, Womens Affairs,
Public Works, Reconstruction, Foreign Affairs, and Refugees.
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
26/60
NSP Operational Manual 15 December 2004 Page 26 of 54 Rev. Date: 15 December04
ORGANIZATIONAL CHART
III. CYCLE OF ACTIVITIES
This section covers the activities to be undertaken during preparation, appraisal,
implementation and completion of the sub-project cycle. The goal is to facilitate an inclusive
participatory process within the community which results in an equitable community
development plan including a series of sub-projects that are eligible for funding under the
NSP and/or eligible for funding from other existing programs. The long-term goal is the
creation of community institutions that are to strengthen the communitys ability to mobilize,
consult, plan, finance, implement and evaluate their own development.
A. Preparation
During this phase of the cycle, Facilitating Partners will help:
mobilize the community including facilitating the establishment through elections of aCommunity Development Council and related project implementation committees asagreed with the community;
facilitate a participatory planning process that includes women and the weakersections of the community;
Communities
MRRD - NSPCommunity-Led DevelopmentDepartment and NSP Oversight
Consultant
MRRD NSPCommunity-Led DevelopmentDepartment and NSP Oversight
Consultant
NSP Steering
Committee
Facilitating
Partner FacilitatingPartner
FacilitatingPartner
National Level
ProvincialLevel
District and
CommunityLevel
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
27/60
NSP Operational Manual 15 December 2004 Page 27 of 54 Rev. Date: 15 December04
strengthen community capacity to identify and prioritise needs;
assist the community to prepare a Community Profile with baseline data(Disbursement Form 1);
facilitate the preparation of a Community Development Plan (Disbursement Form 6)and proposals for specific project(s) with budget(s);
provide technical assistance to develop sub-project proposals (Disbursement Form 7)for appraisal through either:
o facilitating community access to technical assistance available in the market orfrom other agencies; or,
o technical assistance provided by the Facilitating Partner,
sign off on the Community Development Plan and sub-project proposal(s) withrespect to technical quality, financial feasibility and inclusive communityinvolvement in planning and decision making before they are submitted to NSP.
The community will:
elect an inclusive Community Development Council and establish ProjectManagement Committees as needed for sub-projects;
develop a Community Development Plan (including priority sub-project proposalswith budgets and community cost contributions and O&M arrangements as well as
projects which can be financed and implemented by the community itself);
obtain inputs and endorsement from the community (if necessary through separatemeetings with men and women) regarding the Community Development Plan;
mobilize the required technical expertise to help develop designs within giventechnical standards;17
agree on rules for dissemination of budget and expenditure information; submit the community development plan and proposal(s) to NSP.
The training manual provides more in-depth guidance on the processes which can be
followed during each phase, however, the Facilitating Partner will have flexibility in the
choice of the facilitation methodology for undertaking the activities listed above.
B. Appraisal
The community (with the assistance of the Facilitating Partner) will complete and submit a
Community Development Plan and standard sub-project proposal(s) (including technical
designs and cost schedules) to the provincial representative of the NSP. (See DisbursementForm 6 and 7 for standard format for the community development plan and sub-project
application form). The Community Development Plan constitutes a medium term investment
plan for a particular community, which would provide the basis for additional future
17 This may involve getting the required technical assistance from the market (payment can be madedirectly as part of the community contribution, or retroactively if and when a project is appraised and foundeligible for funding), or getting this assistance from the Facilitating Partner, where it is unavailable in themarket.
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
28/60
NSP Operational Manual 15 December 2004 Page 28 of 54 Rev. Date: 15 December04
development activities whether funded by NSP or other sources, and also represent for the
first time ever a bottom-up input to higher level planning at the district, provincial, and
national level.
Appraisal of the community proposal and budget are conducted by the NSP. The Facilitating
Partner will help communities prepare and implement sub-project proposals and bepositioned as allies of the community, while the NSP staff will formally appraise proposals
and make funding decisions.
The NSP will be responsible for appraisal of all community project proposals to determine
whether they meet the eligibility criteria. This will be done using a standard appraisal tool
(Disbursement Form 7c) by the NSP technical staff from the provincial office (and involving
relevant government agencies, e.g. for education). The appraisal will be done using a
transparent procedure. Eligibility criteria, indicators and means of verification are listed in
the table below. The criteria will be made known to the community in order to limit the
discretionary power of the NSP. A proposal is evaluated based on these criteria and assessedduring a field visit to the community. During this appraisal visit the appropriate levels of
installments will be discussed and agreed upon. In the absence of special agreements the
installments will be 50: 40: 10 %.
The community is then informed by the NSP regarding the result of the appraisal, which may
be a) approval of funding for the proposed plan, b) rejection for non-compliance with NSP
rules (e.g. project is on the negative list), c) requiring the community to revise its proposal
with regard to either the election of the Community Development Council, the planning
process, the budget, or the technical standards.
The provincial NSP office will undertake field verification on a sample basis of whether
elections of Community Development Councils conform with the basic principles defined in
this manual. In addition, the national level NSP office will undertake periodic field
supervision audits on a sample basis of the appraisal process to ensure that eligibility criteria
are complied with.
Upon completion of appraisal and approval by NSP of a community sub-project proposal, a
Tripartite Agreement will be signed between the Community Development Council, NSP,
and the Facilitating Partner regarding the financing of the sub-project, disbursement schedule
and benchmarks triggering installments and the general obligations of each of the parties tothe agreement (see Section IV, C).
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
29/60
NSP Operational Manual 15 December 2004 Page 29 of 54 Rev. Date: 15 December04
Sub-Project Eligibility and Appraisal Criteria
Core
Principles Eligibility Criteria Indicator Means of Verification
Does Proposal
Meet Eligibility
Criteria?
1.
Representativecommunityinstitution
Establishment of a
community widedecision makingprocess and electionof a representativeCDC
CDC elected with
representation from differentgeographical and occupationalsections40% of eligible votersparticipated in the election
CDC Registration Form; CDC registration certificate; Form 2; Proposal submitted by CDC
(YES) (NO)
2.BeneficiaryParticipation
CommunityDevelopment Planendorsed through acommunity-wideprocess
Community-wide meetingsheld;60% of families participatedin decision meeting.Decisions/priorities of womentaken into account
Random interviews withcommunities; Interviews with womensgroup members; Minutes of decision makingcommunity meetings
3.Equity
Sub-project providesbeneficiariesequitable access tobenefits
Persons from differentgeographical and occupationalsections of the community canaccess benefits
Confirmation of sub-projectmap of beneficiaries throughrandom interviews withcommunity
Check proposal onbeneficiaries and equity
4.TechnicalSoundness
Sub-project istechnically sound
Sub-project complies withappraisal criteria for technicalquality standards, and theproject negative list.
Check proposal for technicalquality (problem statement,goals & objectives, engineeringdesigns, implementationarrangements, risks andconstraints)
5.FinancialSoundness
Sub-project isfinancially sound
Sub-project complies withappraisal criteria for financialsoundness and corresponds tothe technical layout.
Check proposal for financialquality (project budget,procurement plan, disbursementschedule)
6.Compatibility
with social &environmentalsafeguards
Sub-project issocially and
environmental sound
Sub-project complies withappraisal criteria,
environmental and socialsafeguards issues, and theproject negative list.
Check proposal forenvironmental and social quality
7.CommunityCommitment
Sub-project hascommunitycontribution towardscapital costs
Minimum of 10% of capitalcosts committed (cash, kind orlabor)
Check proposalRandom interviews withcommunities
8.Sustainability
Proposed project hascommunityarrangements foroperation &maintenance (O&M)
O & M plan with budgetcommitted and training planprepared18
Check proposalRandom interviews withcommunities
9.Transparency
Accept principles oftransparency
regarding budgetingand expenditures
Budget (and later accounts)posted in public places and
through meetings (e.g. in themosque and womensmeetings)
Check proposalRandom interviews with
villagers (both men and women)
18 The O&M plan must include not only an operating budget, but a clear indication of a community-managed cost recovery system, such as a user-payer scheme. Cost recovery rates should be established at a levelthat will enable payment of: a) running costs (e.g. fuel for a generator or pump), b) repairs and maintenance andc) replacement of the assets when its operational life-time is over. Without an adequate cost recovery system,the sustainability of the outputs is likely to decrease. This involves careful attention on the part of CDCs andFacilitating Partners - as well as OC/MRRD.
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
30/60
NSP Operational Manual 15 December 2004 Page 30 of 54 Rev. Date: 15 December04
10.Mine Risk
Mine Risk Safety hasbeen assessed
Questionnaire on Mine RiskSafety has been filled out
Check proposalForm 7a
C. Sub-Project Implementation
The primary responsibility for sub-project implementation will rest with the community (the
Community Development Council, Project Management Committee, and the greater
community). Clear divisions of responsibility between the Development Council members
and Project Management Committee members will increase accountability. Three or more
persons at the community level should be identified as responsible for most implementation
activities such as procurement, bookkeeping, supervision, storage and accounting. This will
not only promote transparency and continuity at the community level but it will also ensure
that more than one person in the community has the necessary skills/training to perform the
task.
Depending on the type of sub-project, the community may either be capable of undertaking
implementation itself, or may require external assistance regarding specialized technical
skills or services (e.g. masons for school construction, or lining and hand pump installation
for dug wells for drinking water). The procurement of such services will follow established
procedures (see Annex 3 Procurement Forms).
If a community is using its block grant for more than one sub-project, parallel
implementation is an option, if sufficient capacity is present, since this will speed up overall
implementation, and enable completion of projects within the constraints defined by local
climate and altitude.The Facilitating Partner will support the community during this process with regard to:
technical assistance on an as needed basis (e.g. procedures for procurement of goodsor contractors);
implementation (e.g. advice on implementation organization, and supervision ofworks and construction quality)
training on matters such as book-keeping, contracting, maintenance tasks etc.
D. Monitoring by the Community
The community wide assembly will agree on the methods and schedule of reporting to thecommunity (on financial and physical progress) by the Community Development Council
and the relevant Project Management Committees. The methods for information
dissemination should ensure that women are informed about project activities. The
community will also agree on key indicators to monitor joint decision making, project
progress, and transparency. Monitoring against these indicators will be reported in the
Community Progress Reporting Form used by the Facilitating Partners (Reporting Form 16a).
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
31/60
NSP Operational Manual 15 December 2004 Page 31 of 54 Rev. Date: 15 December04
In the community, all records and accounts must be available for inspection by the members
of the community, the Facilitating Partner, and NSP. The arrangements to ensure
transparency shall include regular community wide information meetings, display of all
relevant information on implementation progress and expenditures on notice boards
accessible to the public, and/or announcements of project-related information atJumma
prayers.
E. Physical and Financial Progress Monitoring
The Facilitating Partner will be responsible for physical and financial progress monitoring on
a monthly basis (Reporting Form 6) with summary progress reports and on a quarterly basis
with more comprehensive status reporting (Reporting Forms 19 and 19a). These reports
constitute an input to the overall quarterly progress reporting by NSP (Reporting Form 8).
The Facilitating Partner will report to NSP on process, achievement of implementation
benchmarks, and quality of works as defined in the Tripartite Agreement. Achievement of
implementation benchmarks will be tied to the release of funding to the community.
The NSP staff will perform sample audits of the support for the community carried out by the
Facilitating Partner regarding elections of Community Development Councils, preparation of
sub-project proposals that comply with NSP eligibility criteria, recommendations for release
of block grant instalments based on achievement of agreed activities, and the adequacy and
realism of progress reporting (Reporting Form 5).
F. Sub-project Completion
A completion report will be prepared by the community and the Facilitating Partner
(Reporting Form 1). The completed project will be inspected by the NSP, and a Certificate of
Completion (Reporting Form 2) will be issued to the community provided the sub-project is
technically sound and that all funds received from NSP have been reconciled. NSP may
approve that any savings that are remaining may be allocated to be used by the community to
increase the scope of the community development plan during the current or following year.
The NSP form submission / disbursement process is presented in the following diagram.
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
32/60
NSP Operational Manual 15 December 2004 Page 32 of 54 Rev. Date: 15 December 04
NSP Form Disbursement Process
ilization
PO submitsOC Kabul
Fo
Election
C/FP submitsto OC PO
Form 2
Form 3
Form 4
Form 5
Registration Phase
Form 1
Form 6
Design Phase
SubprojectIdentification Proposal Submission
Form 7
Project Plan
CDCRegistration
1. PO submits to Kabul2. Kabul final approval
3. Block Grant Disbursementbased on Form 8,9 & SPS
Form 8
Form 9
Tripartiteagreement
SPS
Compagreed
Subproj
(Summary Project Sheet)
Proposal Approved
$
Planning Phase
BankRegistration 2 Weeks
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
33/60
NSP Operational Manual 15 December 2004 Page 33 of 54 Rev. Date: 15 December04
IV. FINANCING AND FUND-FLOW SYSTEM
A. Overall Fund-Flow Arrangements
The overall flow of funds to communities will be managed by the NSP based on the process
outlined below, which summarizes the previous chapters in this manual:
1. The Facilitating Partner provides a Community Profile (Disbursement Form 1) including
a preliminary assessment of the block grant entitlement of the community to the
provincial office of NSP/RRD/OC.
2. Elections for the Community Development Council are held, and the Facilitating Partner
certifies that the elections were held in accordance with NSP rules (Disbursement Form
2). The provincial NSP office (Oversight Consultant and MRRD staff) undertakes
sample verification checks.
3. After completion of Community Development Council elections and certification of
these, representatives of the council go to the provincial NSP office to undertake two
tasks:
a. Submit an application to the provincial NSP/RRD/OC office (Disbursement Form 3)for registration of the Community Development Council (Disbursement Form 5).
b. Submit a form authorizing three community representatives to withdraw block grantfunds on behalf of the Community Development Council (Disbursement Form 4).Where functioning bank branches exist in the provincial center, an application to opena bank account is submitted (Disbursement Form 4a) together with an authorization
from the Community Development Council for nominated persons to makewithdrawals from the account (Disbursement Form 4b).
4. With support from the Facilitating Partner, the Community Development Council in
consultation with the community at large agrees on a Community Development Plan,
which constitutes a medium term development and investment plan for the community in
question (Disbursement Form 6). The Community Development Plan is submitted to the
provincial NSP/RRD/OC office. Each community development plan will include a list of
priority investment needs (i.e. one or more sub-projects) within the budget envelope
defined by the block grant, the contribution that the community is mobilizing, and funds
that can be accessed from other programs.
5. If required, NSP at the provincial and central level coordinates with relevant line
ministries, so that it is ensured that sub-project proposals for schools or clinics fit with
the sector plans of the concerned ministry, and that operating costs are budgeted by the
ministry in question. NSP assists the community to obtain verification regarding these
issues from the concerned line ministries, and communicates this information in writing
to the community in question.
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
34/60
NSP Operational Manual 15 December 2004 Page 34 of 54 Rev. Date: 15 December04
6. With support from the Facilitating Partner, the Community Development Council in
consultation with the community at large develops one or more sub-project proposals
within the available funding envelope (block grant allocation, community contribution,
funding from other sources). The sub-project proposal(s) is submitted to the provincial
NSP office (Disbursement Form 7).
7. Each sub-project proposal will be appraised individually, but implementation and
funding of sub-projects can take place simultaneously, if the community has the capacity
to manage this. While an overall Tripartite Agreement (Disbursement Form 8) for the
community development plan (or the elements of this plan for which funding is
available) will be signed between the community, NSP, and the Facilitating Partner,
copies of the first page of Disbursement Form 7 (Sub-project approval request) will be
attached to the Tripartite Agreement. This will cover the specific plans and budgets for
each approved sub-project.
8. After the Tripartite Agreement has been signed the CDC requests the release of the firstinstallment by the NSP/RRD/OC. (Disbursement Form 9)
9. Funds for approved sub-project proposals will be channeled directly from the NSP to the
community based on an agreed installment system of financing. The nominated
community representatives will be accompanied by the Facilitating Partner to the
provincial NSP office for (at least) the first block grant disbursement. The NSP office
will keep a copy of the community letter of authorization and the photos of the
nominated representatives for future verification. A minimum of three signatories are
required for withdrawal of funds.
10. The first block grant installment (normally 50% of the block grant funding for a
particular sub-project) will be released. The installment will be released from the NSP at
central level to the community (CDC) using either the banking system, where this is
functioning, or a government registeredHawala. Where theHawalasystem operates at
the community level, the fund transfer may take place there to reduce security risks and
expedite disbursements to communities.
11. The second block grant installment (normally 40% of the sub-project block grant
funding) will be released when 80% of the first installment has been spent or80% of the
agreed activities under the first installment have been completed and the CDC certifiesthrough the FP that:
a. Implementation progress toward the agreed activities under this installment asdescribed in the sub-project proposal is satisfactory;
b. the required community cost contribution has been provided;
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
35/60
NSP Operational Manual 15 December 2004 Page 35 of 54 Rev. Date: 15 December04
c. the community at large has been regularly updated by the CommunityDevelopment Council about project progress and expenditures (e.g. meetings,notice board);
d. community procurement has been undertaken in compliance with NSP rules;
e. The installment has been requested of the NSP/RRD/OC through
Disbursement Form 9.12. The provincial NSP office (Oversight Consultant and RRD staff) undertakes sample
verification checks of achievement of activities under each installment and
implementation quality.
13. The final block grant installment (normally 10% of the sub project block grant funding)
will be released when 80% of the second installment has been spent (supported by a
simple financial statement) andthe FP certifies 80% sub-project completion and
fulfillment of the same five requirements outlined above (see a to e) as conditions for the
second installment. The CDC and the FP shall guarantee to submit a 100% sub-project
completion report (Reporting Form 1) including a simple financial report upon
completion of the project. Then the completion of the Sub-project will be certified from
the NSP/RRD/OC to the community (Reporting Form 2).
14. In the case of types of sub-projects which require large capital outlays for pieces of
equipment that constitute the main costs of the sub-project (e.g., diesel generators and
hnad pumps), the normal 50:40:10 breakdown of payment tranches need not necessarily
apply, but should apply in most cases.
15. The provincial NSP office (Oversight Consultant and RRD staff) undertakes sample
verification checks of achievement of activities under each installment andimplementation quality.
B. Fund Transfer Mechanism
The Tripartite Agreement defines the schedule of disbursement installments on the basis of
an agreed plan of physical progress of a particular sub-project. Funds will be transferred
using a fixed price or lump-sum method of financing based on several installments (at least
three) per sub-project. The size of individual payments under each tranche (amounts) must
be determined based not only on the technical requirements of the sub-project, but also on
security concerns at the community level. However as a norm, the first installment can notexceed 50% of the sub-project costs.
Where local banks function at the provincial level, communities can maintain a checking
account and make withdrawals and payments as required. Where a banking system is not
functioning, and funds are transferred throughHawalaagents, the community can arrange
with the NSP that specific payments are made directly at the NSP provincial office to
suppliers and contractors in the presence of the community representatives. This would limit
-
8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)
36/60
NSP Operational Manual 15 December 2004 Page 36 of 54 Rev. Date: 15 December04
the amount of cash that communities will have to transport, store, and handle. Likewise,
whereHawalaagents do not agree to operate under this arrangement, the transfer of block
grant funds may take place in the community provided theHawalasystem operates at this
level. This would also serve to avoid that provincial NSP/RRD/OC offices would have to
keep cash, would reduce security risks associated with transport of cash by community
representatives, and would expedite disbursements to communities, Where practiced, the
transaction would have to be witnessed and certified by the Facilitating Partner.
Unless there are exceptional circumstances, payment for implementation will be made in
three installments/tranches agreed between MRRD and the CDC on the basis of the funding
requirements of the sub-project in question (the first installment should normally not exceed
50% of total sub-project costs). The first installment will be paid following signing of the
Tripartite Agreement, the second installment after achievement of agreed implementation
activities, and the third installment upon 80% completion of the project supported by a
financial statement accounting for 80% of sub-project funds received. Examples of financial
reporting forms at the community, provincial and national levels, accompanied by
explanatory text, are set out in Annex 2: NSP Accounting Forms.
If a community is using its block grant for more than one sub-project, an assessment will be
made by NSP whether the projects can be funded and implemented in parallel or sequentially
(i.e. the first sub-project must be completed before funding for the next sub-project is
released). The criterion for parallel funding and implementation is that one of the sub-
projects must be identified by women and address their defined needs. In all other cases
where block grants are used for more than one sub-project, these will be financed
sequentially.
C. Tripartite Agreement
The Tripartite Agreement represents the contract between the NSP and the community and is
a complete statement of the obligations and responsibilities of the parties to th