National Solidarity Manual Operations Manual (Dec 2004)

download National Solidarity Manual Operations Manual (Dec 2004)

of 60

Transcript of National Solidarity Manual Operations Manual (Dec 2004)

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    1/60

    NSP Operational Manual 15 December 2004 Page 1 of 54 Rev. Date: 15 December 04

    NATIONAL SOLIDARITY PROGRAM

    OPERATIONS MANUAL

    TABLE OF CONTENTS

    PREFACE 4

    I. INTRODUCTION 5A. Background 5B. Goal and Objectives of the NSP 5C. Core Elements and Approach 5D. Scope and Targeting 6E. Conditions for Eligibility and Project Menu 10

    II. ORGANIZATIONAL STRUCTURE 14A. Community 14B. Community Development Council and Project Management Committees 13C. Facilitating Partner 20D. Ministry of Rural Rehabilitation and Development 21E. NSP Steering Committee 22

    III. CYCLE OF ACTIVITIES 23A. Preparation 23B. Appraisal 24C. Sub-Project Implementation 27D. Monitoring by the Community 27E. Physical and Financial Progress Monitoring 28F. Sub-Project Completion 28

    IV. FINANCING AND FUND-FLOW SYSTEM 30A. Overall Fund-Flow Arrangements 30B. Fund Transfer Mechanism 32C. Tripartite Agreement 33

    D. Disbursement to Communities 34E. Fund Management at the Community level 35F. Financial Reporting by Facilitating Partners 36

    V. COMMUNITY PROCUREMENT 37A. Direct Single Source Procurement 37B. Competitive Shopping 38C. Competitive Tendering 39D. Direct Contracting 41E. Waivers 42F. Procurement above AFA 3 Million 43G. Procurement Forms 43

    VI. SOCIAL, ENVIRONMENTAL AND MINE RISK SAFEGUARDS 45

    VII. COMPLAINTS PROCESSING AND RESOLUTION 48

    VIII. MONITORING AND EVALUATION 50

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    2/60

    NSP Operational Manual 15 December 2004 Page 2 of 54 Rev. Date: 15 December 04

    Acronyms and abbreviations

    CDC Community Development Council

    DAB Da Afghanistan Bank

    FP Facilitating Partners

    IDA International Development Association

    IDP Internally Displaced Persons

    MoF Ministry of Finance

    MRRD Ministry of Rural Rehabilitation and Development

    NGO Non-governmental Organization

    NSP National Solidarity Program

    OC Oversight Consultant

    RRD Provincial office of MRRD

    UXO Unexploded ordnance

    Annex 1

    Disbursement Forms:

    NSP Disbursement Process GuidelinesDisbursement Form 1 Community Profile (Baseline Data) FormDisbursement Form 2 CDC Election & CompositionDisbursement Form 3 Community Development Council Registration ApplicationDisbursement Form 4 Signatory Authorization (for block grant withdrawals)Disbursement Form 4a Account Opening Form for NSPDisbursement Form 4b Authorized Signatures (for block grant withdrawals)Disbursement Form 5 Certificate of Registration of Community Development Council

    Disbursement Form 6 Summary of Community Development Planning ProcessDisbursement Form 7 Sub-Project Proposal FormDisbursement Form 7a Verification of Mine Risk Safety/ClearanceDisbursement Form 7b Sub-Project Summary Sheet (English)Disbursement Form 7c Project Eligibility Appraisal (English)Disbursement Form 8 Tripartite Implementation AgreementDisbursement Form 9 Block Grant Fund Request

    Annex 2

    NSP Accounting Forms

    1 Accounting Instructions

    Acc Form 1 Cash Receipt VoucherAcc Form 2 Vendors InvoiceAcc Form 3 CDC Cash BookAcc Form 4 DAB ChequeAcc Form 5 CDC Bank BookAcc Form 6 CDC Cash Advance BookAcc Form 7 CDC Petty Cash Count FormAcc Form 8 CDC Stock book

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    3/60

    NSP Operational Manual 15 December 2004 Page 3 of 54 Rev. Date: 15 December 04

    Annex 3

    NSP Procurement Forms

    Procurement Form 1 - Declaration of Impartiality and ConfidentialityProcurement Form 1.1 - Invitation to QuoteProcurement Form 1.2 - CDC Bid Evaluation Form

    Procurement Form 1.3 - Purchase OrderProcurement Form 2.1- Advertisement NoticeProcurement Form 2.2.1 - Contract for Supply of GoodsProcurement Form 2.2.2 - Contract for WorksProcurement Form 2.2.3 - Contract for ServicesProcurement Form 3.1 - Waiver/Direct Contracting Form

    Annex 4

    NSP Reporting Forms

    Reporting Form 1 - Project Completion FormReporting Form 2 - Certificate of Completion of a Sub-project

    Reporting Form 5 - Spot Check Reporting FormReporting Form 6 - Format for Monthly Status Report (Narrative)Reporting Form 6a- Format for Monthly Status ReportReporting Form 8 - Oversight Consultant Quarterly ReportReporting Form 16 - Community Quarterly ReportReporting Form 16a - Community Progress ReportReporting Form 19 - Facilitating Partner Quarterly ReportReporting Form 19a - Facilitating Partner Progress reportsInstructions for Quarterly Progress Reports

    Annex 5

    Social, Environmental and Mine Risk Safeguards Forms

    Safeguard Form 1 - Environmental Impact Identification and Assessment for NSPSafeguard Form 2 - Land Acquisition Assessment & Planning Data SheetSafeguard Form 3 - Form to Document Contribution of Assets

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    4/60

    NSP Operational Manual 15 December 2004 Page 4 of 54 Rev. Date: 15 December 04

    PREFACE

    The National Solidarity Program (NSP) is executed by the Ministry of Rural Rehabilitation

    and Development (MRRD) with funding from the International Development Association

    (IDA), the Afghanistan Reconstruction Trust Fund (ARTF) and other donors. The NSP

    operational manual provides information on key aspects of the NSP including the project

    mandate, objectives, institutional arrangements, sub-project processes, transfer of funds and

    financial management, and monitoring and evaluation procedures among others. The main

    audiences for the NSP operational manual are the national, provincial and district level

    government officials, Facilitating Partners, the Oversight Consultant, and other consultants.

    The NSP operational manual is intended to ensure consistency, transparency andaccountability in the application of project management procedures at all levels. The NSP

    operational manual is considered to be part of the Development Grant Agreement with IDA

    and is therefore a legally binding document. The NSP operational manual will be reviewed

    and revised biannually based on lessons learned from the field.

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    5/60

    NSP Operational Manual 15 December 2004 Page 5 of 54 Rev. Date: 15 December 04

    I. INTRODUCTION

    A. Background

    The National Solidarity Program (NSP) was created by the Government of Afghanistan to

    develop the ability of Afghan communities to identify, plan, manage, and monitor their own

    development projects. NSP promotes a new development paradigm whereby communities

    are empowered to make decisions and control resources during all stages of the project cycle.

    In accordance with government policy, the program is expected to lay the foundations for a

    long-term strengthening of local governance, to make it more inclusive (e.g. for women,

    Internally Displaced Persons (IDPs), returnees, ethnic minorities), and to provide assistance

    for reconstruction and development of communities.

    The NSP has an implementation framework that includes a methodology for providing direct

    financing to communities through transparent eligibility procedures for selection of sub-

    projects. This methodology focuses on the development and strengthening of inclusivecommunity institutions through participatory planning and resource management as a basis

    for community development.

    B. Goal and Objectives of the NSP

    The goal of the NSP is to reduce poverty through empowering communities with regard to

    improved governance, and social, human, and economic capital. The objectives of the

    program are to: (1) lay the foundations for a strengthening of community level governance,

    and to (2) support community-managed sub-projects comprising reconstruction and

    development that improve the access of rural communities to social and productive

    infrastructure and services. The outcomes that the NSP aims to achieve are (i) the

    establishment of a framework for village level consultative decision making and

    representative local leadership as a basis for interaction within and between communities on

    the one hand, and with the administration and aid agencies on the other, and (ii) local level

    reconstruction, development, and capacity building which will lead to a decrease in poverty

    levels.

    The NSP grants to villages are intended to act as catalysts in this process and at the same time

    provide much needed support for local reconstruction and development activities.

    C. Core Elements and Approach

    The design of NSP consists of four core elements:

    Facilitationat the community level to assist communities establish inclusivecommunity institutions through elections, reach consensus on priorities andcorresponding sub-project activities, develop eligible sub-proposals that comply with

    NSP appraisal criteria, and implement approved project sub-proposals;

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    6/60

    NSP Operational Manual 15 December 2004 Page 6 of 54 Rev. Date: 15 December 04

    A system of direct block grant transfersto support rehabilitation or developmentactivities (sub-projects) planned and implemented by the elected CommunityDevelopment Councils;

    A series of capacity building activitiesto enhance the competence of CommunityDevelopment Council members (both men and women) for financial management,

    procurement, technical skills, and transparency, and,

    Activities linking local institutions to government administration and aidagencieswith available services and resources.

    Quality of process is essential for the long term sustainability of community investments and

    for the success of a program like the NSP. As such, community level planning must follow

    an approach that complies with the basic principles below:

    participatory planningof activities through inclusive community meetings andrepresentative elected development councils;

    community contributionsto capital costs and operation and maintenance;

    transparency and accountabilityof budgeting and accounting.

    The goal of this approach is to ensure that communities are able and inclined to institute a

    broad based inclusive decision-making system (which includes women as well as members

    from marginalized sections of the villages) through community meetings and development

    councils. Through this process the communities will acquire or strengthen the skills and

    attitudes necessary to enhance their capacity to define, manage and govern their development.

    To achieve this goal, the role of the Facilitating Partners (FPs) and the NSP will be to create

    an enabling environment through facilitation of inclusive community planning, technical

    assistance, and timely release of funds, which will make possible for communities themselves

    to manage implementation of the projects they have defined.

    D. Scope and Targeting

    In the first year, three target districts in each province were selected by MRRD. In the

    second year additional districts were selected as needed to establish equity with regard to

    coverage of villages between provinces. Close to 6,000 communities were reached in Year 1,

    and operations will be expanded to reach an additional 4,800 communities in Year 2,

    equalling roughly half of Afghanistans village communities. The selection of districts has

    aimed at achieving an optimal match between quality NGO proposals and vulnerable districts

    (vulnerability caused by severity of drought and number of Internally Displaced Persons

    (IDPs) and refugees). Inputs from provincial governors and Provincial Administrative

    Councils have also been sought before district selection was finalized and NGOs contracted.

    During the first year, the program operated in a selected set of village communities in the

    selected districts (up to 72 per district), and operations will be expanded in year two to cover

    the remaining villages in the districts, if any, and/or expand operations to new districts. In

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    7/60

    NSP Operational Manual 15 December 2004 Page 7 of 54 Rev. Date: 15 December 04

    year two, operations will expand to a new set of communities with consideration of logistics

    and optimal use of field staff.1 Funds will be allocated for projects that have been appraised

    by the NSP as meeting the eligibility criteria of the NSP (See Section E below), and for

    which financing agreements have been signed between the NSP and the community

    organization and the Facilitating Partners (Disbursement Form 8).

    Definition of community

    Communities will be defined on the basis of existing available information from government

    records (e.g. the list of registered villages from the 1970s, or the list of villages prepared for

    the nomination of the members of the 2002Loya Jirga). However, since the reliability of the

    available official data on villages was inconsistent when the records were established, and

    since it is by now outdated due to population increase and/or displacements, the identification

    of communities for the purpose of the NSP would have to reflect the ground realities existing

    today. Where Facilitating Partners find that the realities on the ground deviate significantly

    from the existing official village lists, local authorities (e.g. woluswal, MRRD provincialoffice) should be consulted where possible to arrive at a more operationally practical

    definition of communities that corresponds to existing local settlement patterns. The proposed

    plan for defining communities for the purpose of NSP would always have to be approved by

    NSP Kabul. The establishment of a Community Development Council would not affect the

    village's legal standing with the Ministry of the Interior. It is important that Facilitating

    Partners thoroughly periodically monitor, verify and check actual number of families to

    avoid any inflation in family numbers which could be detrimental to the programmes

    financial integrity. Spot checks will also be conducted by the Oversight Consultant and

    MRRD.

    The definition of a community for the purposes of block grant allocation will be based on the

    following principles:

    A community is a village of more than 25 families;

    One Community Development Council will be established for each community.Development Councils can not be established for sub-sets of an existing village (e.g. avillage cannot be split into its constituent political or ethnic/qaumsub-divisions);

    One block grant (budget) will be allocated to each new community in Year II at10,000 AFA per family with an upper limit of 3 million AFA per community. This

    allocation2requires that the community develops one or more eligible sub-projectproposals within the budget frame. The possibility of introducing a second top-upgrant is currently under consideration.

    1 i.e. villages chosen for annual implementation coverage should to the extent possible be more or lessadjacent to facilitate optimal utilization of facilitation staff and transport resources.2 This new allocation is subject to formal World Bank endorsement.

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    8/60

    NSP Operational Manual 15 December 2004 Page 8 of 54 Rev. Date: 15 December 04

    The block grant of a community can be carried forward to the next year if it has notbeen fully committed or disbursed for specific projects during Year 1. It can only becarried forward from one year to the next. After that, the un-committed amountswould be cancelled.

    A family is defined as a nuclear family consisting of a man, his wife (or wives) and

    unmarried children, or a widow(er) and her/his unmarried children. The number of families

    in the targeted village communities will be assessed by the Facilitating Partner, and this

    enumeration can be verified through such means as a community meeting, consultations with

    the local mullah(s), and existing village lists for voluntary contributions towards ashar,

    mosque repair etc. Once village selection is confirmed (the community will have to confirm

    its interest to participate during a mass meeting) and the number of families is agreed, the

    block grant amount would be adjusted to reflect the more accurate population size, and

    communicated to the community. The community must also be willing to contribute at least

    10 % of the value of the block grant to development activities financed out of the block grant.

    How to deal with different community sizes?

    As stated above, the minimum size of a community potentially eligible for a block grant

    allocation would be 25 families. Smaller settlements should be encouraged to join with other

    ones to pool their block grant allocations for larger scale joint activities (e.g. a clinic, a

    school, or a multi-village pipe water supply system). Where this is not possible, isolated

    settlements below 25 families can be exceptionally included, if the rationale provided is

    approved by the Oversight Consultant and MRRD.

    While communities are encouraged to come together, it is not acceptable under NSP that they

    split up in the interest of a higher block grant. In order to avoid detrimental community

    divisions into two or more sub-areas or CDCs, which could lead to a negation or weakening

    of the principles of solidarity, the following guidelines must be followed.

    The sub-area may have a second CDC if some or all of the following criteria apply but

    subject to approval of NSP/MRRD/OC in Kabul:

    1. If the sub-area has a record or proof of separate community work, such as irrigation

    2. If the sub-area has a separate council/shura existing for some years now

    3. If the sub-area was listed as a separate entity in the nomination of representative(s) for

    the Loya Jirga

    How to facilitate the inclusion of recent returnees/IDPs?

    An option to facilitate re-integration of IDPs and returning refugees is to communicate to

    specific communities with a considerable IDP/refugee population, that the block grant

    allocation can be increased upon the return of IDPs/refugees and their participation in project

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    9/60

    NSP Operational Manual 15 December 2004 Page 9 of 54 Rev. Date: 15 December 04

    planning. This incentive could encourage communities with a high proportion of IDPs or

    refugees to initiate consultation with these about their return during the project preparation

    phase to obtain access to an increased block grant allocation. Where a return of

    IDPs/refugees is planned, and IDPs/refugee families or family members return to their

    communities during the project preparation phase, a reassessment of the population size

    should be undertaken prior to final project development and costing to enable an adjustment

    of the block grant allocation. Where such planning is undertaken, the Facilitating Partner

    should assist the community in assessing whether the additional resources provided through

    the enhanced block grant and the proposed project activities would enable a sustainable re-

    integration of the returnees.

    Hence, for all recent cases of returns of refugees or IDPs the following should be undertaken:

    1. Re-count the number of families. This should be done by the CommunityDevelopment Council, assisted by the Facilitating Partner, and be cross-checked byMRRD and the Oversight Consultant;

    2. Cross-check once again the above number with that of UNHCR to avoid any inflationof numbers and ensure consistency between data;

    3. Adjust the block grant amount to the number of additional families, within the limitsfor block grant transfer (specified above);

    4. For a return above 20 families (average cluster size), conduct in the briefest delays(not longer than 1 month after the return) a sub-election to include at least onereturnee representative member within the CDC3. If the number of returnee families is

    below 20, the CDC must ensure some form of returnee participation into communityaffairs through Project Management Committees or Thematic Committees (e.g.literacy, parent-teacher, water etc.);

    5. Ensure the inclusion of returnees, through the above mentioned participation, andthrough a full inclusion in identification, selection, implementation and/or monitoringof sub-projects which should be beneficial to returnee reintegration;

    6. A special Returnee-CDC Reintegration Application should be submitted on a needsbasis to the OC/MRRD.

    E. Conditions for Eligibility and Project Menu

    The Community Development Council will be registered (Disbursement Form 5) with

    MRRD after it has been verified that the election was conducted in compliance with the

    election rules (see Chapter II.B and Disbursement Form 2). Then the community will be

    eligible for the block Grant.

    3 The number of representatives can be increased proportionally to number of returnee families vs. size

    of community.

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    10/60

    NSP Operational Manual 15 December 2004 Page 10 of 54 Rev. Date: 15 December04

    To make use of the block grant allocation, the community must develop a Community

    Development Plan and an eligible sub-project proposal (or proposals), that fulfils the

    following criteria:

    is proposed by a representative Community Development Council(which hasbeen elected through a community-wide process),

    is endorsed through a community-wide process,

    provides equitable access to benefits,

    is technically and financially sound,

    includes an operation and maintenance plan4,

    has at least 10% community contributions towards capital costs ,

    includes a commitment to and plans for ensuring transparency of the use ofblock grant funds.

    The community contribution towards capital costs can comprise cash, labour, or in kind

    contributions such as construction materials and/or transport.5

    The activities to be completedunder each sub-project instalment must be clearly specified (including community

    contributions). The Facilitating Partner will monitor, assess and report quarterly to the NSP

    as to whether this condition is being adequately met.

    Toprepare a Sub-project proposal the community should take note that NSP will accept an

    open menu of sub-projects within four types of investments, subject to a short negative list.

    The four types of investments are6:

    1. Community infrastructure(the investments will comply with defined technicalstandards, and will only comprise public goods);

    2. Human capital development activities(e.g., time-bound literacy classes, hygieneeducation etc., that are not planned to incur recurrent costs from the state);

    3. Self-help savings schemes for women and disabledthat would draw on bestpractice lessons from other projects and be based on a predefined methodology to bedeveloped by NSP (this practice can only comprise 10% of the total value of a blockgrant with an upper limit of AFA 250,000).

    4. Productive asset transfers for vulnerable women and disabledthat would draw onbest practice lessons from other projects and will be based on a predefinedmethodology to be developed by NSP (e.g. sewing machines, looms etc. supported by

    4 The O&M plan must include not only an operating budget, but a clear indication of a community-managed cost recovery system, such as a user-payer scheme. Without an adequate cost recovery system, thesustainability of the outputs is likely to decrease. This involves careful attention on the part of CDCs andFacilitating Partners - as well as OC/MRRD.5 The time spent by members of the Development Council will not be counted towards the communitycontribution, and cannot be compensated out of the block grant. If the community decides that members of theDevelopment Council should be compensated for their time, this should be from a community contribution overand above the 10% contributed towards the capital costs of projects.6 Investments in income generating assets if later included in the menu would draw on best practicelessons from other projects.

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    11/60

    NSP Operational Manual 15 December 2004 Page 11 of 54 Rev. Date: 15 December04

    training as required) (the value of the assets can only comprise 10% of the total valueof a block grant with an upper limit of AFA 150,000).

    Increasing womens involvement in NSP Year 2

    A. Creation of separate female

    Community Development Councils

    when possible and desirable7is

    proposed in order to enhance

    womens involvement and

    decision-making.

    B. Specific investments potentially

    targeting women, see 2 to 4 above,

    now become full-fledged

    entitlements either for projects

    directly benefiting women or for

    community projects. Women can

    either choose to invest their

    entitlement into a larger

    community project, if they wish to

    do so, or alternatively, they may

    select more women-focused

    projects. Until a creative menu of

    truly beneficial and sustainable

    projects for women is further

    explored within NSP, Facilitating

    Partners and CDCs are

    encouraged, but not restricted, to

    promote human capital

    development activities (i.e. 2

    above) such as literacy and hygiene

    education, which often offer an

    initial firm basis on which to build

    income generation and other

    projects (i.e. 3 and 4 above) .

    Box 1. On the Creation of Female CDCs and Corresponding Project Entitlements

    Lessons learned from Year 1

    1. While female participation in the CDC process has been higher than expected in Year

    1, it has been found that the actual involvement of women in the selection,

    implementation, monitoring of projects and in overall decision-making remains poor

    despite a clear potential for progress in this area. To seize this opportunity for greater

    involvement of women, innovative steps must be taken in Year 2 see section on block

    grant entitlement below.

    2. Another lesson learned from Year 1 is that cultural and other religious constraints have

    been found to be obstacles which can be overcome through culturally sensitive social

    organizational skills. As such, success in reaching and involving women may be more ofa factor of: a) having an adequate number of qualified female staff and b) a sophisticated

    approach to social mobilization on the part of Facilitating Partners regardless of cultural

    or other barriers8. As such, it is expected that Facilitating Partners will continue to

    engage qualified female staff, and provide them with adequate training as a precondition

    for success in reaching and involving women.

    3. While mobilization and governance for women tends be prioritized, it is equally

    important to reflect on the viability of projects proposed to and by women. Much work

    remains to be done in this area to avoid the mushrooming of unsustainable and potentially

    detrimental business ventures. An informed and participatory discussion needs to take

    place in an effort to produce a list of adequate and promising projects for women based on

    global and Afghan best practice, in addition to increasing the capacity of the Oversight

    Consultant/MRRD to appraise these types of projects (distinct from engineering

    capacity), with a clear emphasis on sustainability and overall impact on poverty reduction.

    4. Finally, lessons from Year 1 demonstrate that more emphasis needs to be made to

    identify vulnerable women (e.g. female-headed households) as well as disabled both

    being entitled to asset transfers. Likewise, careful planning is needed of such asset

    transfers to ensure that they contribute to sustainable poverty alleviation.

    7 This measure is meant to encourage female participation and decision-making in areas where gender separationmay be appropriate to reach this objective. In more lenient areas, mixed CDCs may be more appropriate.8 In areas where the creation of female CDCs impossible due to cultural constraints, the Facilitating Partners arerequired to advise the OC/MRRD on what alternative is being chosen to address womens needs (e.g. women committees).

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    12/60

    NSP Operational Manual 15 December 2004 Page 12 of 54 Rev. Date: 15 December04

    Public infrastructure projects would include, but not necessarily be restricted to: irrigation

    works; roads including culverts and small bridges; erosion protection; structures promoting

    watershed management; water supply facilities; public baths (hamam); and school buildings.

    When school buildings are proposed by the community, endorsement would be required from

    Ministry of Education that these are included in the development plans of the ministry, and

    that funding of operational costs would be provided (fully or with committed contributions

    from other agencies). Please refer to Annex 1 for full instructions on how to proceed

    regarding schools. Where clinics are proposed for block grants, endorsement is required by

    the Ministry of Health that they are included in its development plans and that it will cover

    the associated operational costs.

    The project will notfund:

    equipment or materials that are included in the annual implementation plans by otheragencies (e.g. by other government or NGO projects that are operating in the area);

    political campaign materials or donations in any form;

    weapons including (but not limited to), mines, guns and ammunition;

    chainsaws;

    pesticides, herbicides and other chemicals;9

    investments detrimental to the environment;

    land (purchase or lease), under any conditions;

    construction, rehabilitation, or maintenance of any government office buildings;

    payments of salaries to government servants or the salaries of the staff of government

    subsidized organizations;

    payments of salaries to CDC members10;

    any activity on land that is considered dangerous due to security hazards or thepresence of unexploded mines or bombs, UXOs,

    any activity on land that has disputed ownership or tenure rights;

    any activity using child labour , i.e. labour from children below 15 years of age11;

    any activity that will support drug crop production or processing of such crops.

    The negative list will be reviewed and if necessary revised by NSP every year.

    9 Exceptions may be considered based on an assessment by the NSP (with specialized consultantassistance, if required, and after no objection from IDA) in special situations such as eradication of infestationsof locusts or sun pest.10 While the project will not fund salaries of CDC members, the project can fund travel, accommodationand food costs of CDC members exclusively linked to programme or sub-project implementation, such astravels for procurement. These costs should be part of the sub-project proposal and be clearly identified assuch. An effort should be made by the community, as pointed out later in the Manual, to devise a cost recoverystrategy for O&M, and general running costs of the CDC with a view to creating a sustainable mechanismbefore the end of Year 2.11 International Labor Organization norm, adapted to Afghanistan.

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    13/60

    NSP Operational Manual 15 December 2004 Page 13 of 54 Rev. Date: 15 December04

    The table below defines the eligibility for block grant funding of different types of

    subprojects that are not clearly public goods infrastructure. This list may not be exhaustive

    and future sub-project proposals that fall in the grey area between public and private goods

    will be reviewed by the NSP/MRRD/OC on a case by case basis.

    As part of promoting technical soundness, each activity must take into account environmentaland social impacts as defined in the governments Environmental and Social Safeguards

    Framework. Since most of the works are expected to be small community-based projects,

    environmental risks are generally considered to be minimal. To ensure compliance with the

    safeguards framework, all proposals must include completed simple environmental and social

    checklists developed by NSP, which describe impacts and mitigations measures, if any. See

    Disbursement Form 7c and Chapter 7 (Social, Environmental and Mine Risk Safeguards.

    Sub-Project Proposal

    Generally

    Eligible for

    Block Grant

    funding

    Eligible under the

    Women/Disabledcategory

    Eligible under

    the Asset

    Transfer

    category

    Comment

    Diesel Water Pump (irrigation) No No No On negative list

    Micro Hydropower Yes - - Equity & O&M plan

    Generator for electricity Yes - - Realistic O&M plan

    Public Bath (Hamam) Yes - - Realistic O&M plan

    Bakery No Yes Yes Business plan & O&M

    Mill (diesel) Yes - - O&M plan

    Mill (water) Yes - - O&M plan

    Carpet/gelim weaving No Yes Yes Equity & Business plan

    Tailoring No Yes Yes Equity & Business plan

    Farm animals (goats, cow, etc) No Yes Yes Equity & Business plan

    Farm inputs (fertilizer, seed) No Yes Yes Equity & Business plan

    Grocery store No No Yes Business plan

    Tractor No No No

    Thresher No No No

    Truck, Bus No No No

    Religious buildings No No No

    Cash donation for disabled No No No

    Land leveling for agriculture No No No

    Vocational training Yes Yes - Equity in access to benefit

    Literacy training Yes Yes - Equity in access to benefit

    Other training (computer, tractoretc)

    Yes Yes Yes Equity in access to benefit

    Check dam (over 3 metres) No No No

    Once it is determined through an appraisal of the project proposal (Disbursement Form 7 and

    Section III.B) by NSP that the eligibility criteria listed above have been complied with, the

    funds will be paid directly from the NSP to a community, according to a defined payment

    schedule based on the Tripartite Agreement (see Chapter IV.C and Disbursement Form 8).

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    14/60

    NSP Operational Manual 15 December 2004 Page 14 of 54 Rev. Date: 15 December04

    The result of the appraisal of the community project proposal will be confirmed on the first

    page of Disbursement Form 7.

    II. ORGANIZATIONAL STRUCTURE

    A. Community

    For the purposes of the NSP, a community is defined as a village consisting of at least 25

    families that is able to identify a need and come together to access NSP funds. Communities

    will be identified on the basis of existing local settlement and social patterns. However, this

    would not prevent different distinct villages from joining together to develop assets (e.g. a

    school, or a pipe water system) that serves more than one village. In such a situation, people

    from all areas that make direct use of the asset should be included as part of the community

    for the purposes of the planning, implementation, and maintenance of the joint asset. The

    block grant for such joint projects will be equal to the aggregate amount for the collaborating

    communities or a portion thereof as required and agreed by the communities. In order toprevent any potential external pressure or influence on the selection of a large project, and

    ensure the design and implementation of technically feasible and adequate projects, it is

    highly recommended that communities and/or CDCs grouping together be limited to seven.

    When more than seven communities join together for the development and management of a

    common project, special permission must be sought from the Oversight Consultant and

    MRRD.

    While a community will be assisted by NSP financially, a key characteristic of this approach

    is that it promotes a high level of community participation and ownership during all phases of

    the project cycle. As such, functions of the community will include:

    Identifying and prioritising needs;

    Electing the Community Development Council and relevant Project ManagementCommittees;

    Preparation of a community development plan and sub-project proposals;

    Providing community contributions;

    Participating in field appraisal, project launch ceremony, and all other communitymeetings related to the project;

    Management of project implementation by the community through its CommunityDevelopment Council or Project Management Committee(s);

    Providing oversight of project implementation with regard to quality and use of funds;

    Maintaining the asset after completion with community cost contributions.

    B. Community Development Council and Project Management Committees

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    15/60

    NSP Operational Manual 15 December 2004 Page 15 of 54 Rev. Date: 15 December04

    The Community Development Council (CDC) will be a community-based decision making

    body which is elected by the community through elections based on a secret ballot. As the

    representative body of the community with regard to the NSP, the Development Council will

    be responsible for overseeing the preparation of the Community Development Plan (defining

    community needs and priorities, and the project or sub-projects to address some or all of

    these priorities), and the preparation and implementation of individual sub-projects. The

    Development Council should at least comprise a Chairperson, Treasurer and Secretary. The

    Development Council should obtain the endorsement through community meetings

    regarding:

    decisions on development priorities, and the final selection of project proposalsdeveloped on the basis of agreed priorities,

    the size and composition of community contributions, and the use of project funds,

    transparency arrangements,

    arrangements for maintenance of completed projects.The Community Development Council will sign an overall Tripartite Agreement

    (Disbursement Form 8) with NSP and the Facilitating Partner on behalf of the community.

    Depending on the number of sub-projects to be managed, smaller Community Project

    Management Committees may be established to prepare and manage individual sub-projects,

    but they will report to the Community Development Council and the community-wide

    meetings. On the other hand, if a community chooses to implement only one or two sub-

    projects, the Development Council may manage implementation of those projects. These

    representative Development Councils must be registered with NSP as a condition for

    receiving assistance and overseeing the management of communally owned property(Disbursement Form 5). A Community Project Management Committee (which can be

    identical with the Development Council and should comprise at least a Chairperson,

    Secretary, Treasurer, and Storekeeper) nominated by a community wide assembly will be

    able to withdraw funds and procure goods and services for implementation of the project after

    being registered with the NSP (Disbursement Form 4).

    Specifically, the Community Development Council will be responsible for:

    Overseeing preparation of the community development plan;

    Convening community wide meetings; Overseeing planning and preparation of individual sub-projects through the

    community project management committees;

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    16/60

    NSP Operational Manual 15 December 2004 Page 16 of 54 Rev. Date: 15 December04

    Mobilizing community contributions for a) contribution to capital costs of projects;b) operation and maintenance costs of outputs/assets and c) operation andmaintenance costs of CDC 12;

    Ensuring community participation during all phases;

    Presenting the sub-project plans at appraisal;

    Managing and supervising sub-project implementation;

    Overseeing (or directly handling) procurement and financial management at thecommunity level;

    Reporting to the community and to NSP on project progress and use of funds.

    The Community Development Council will be established through an election which will be

    conducted according to the following rules:

    Everybody in the community who is entitled to vote in government elections isentitled to be registered as a voter;

    Each person has one vote ;

    The voting will be conducted through a secret ballot;

    Both men and women are eligible to vote and to be members of the CommunityDevelopment Council;

    Predefined candidate lists and electioneering are prohibited; and

    At least 40% of eligible voters must have voted for an election to be valid.

    Development councils elected under an election that does not comply with these rules will

    not be eligible for funding under the NSP.

    Regarding the first point above, registering as a voter is an entitlement, not an obligation.

    However, in declaring whether the election for the Council is valid, an estimate of all eligible

    voters, not all registered voters should be used. Whether the community wishes to extend

    voting entitlements to people who are not eligible to vote in government elections is a matter

    for the community to decide.

    In the case of the secret ballot, it is essential to remove, or at least minimise, the opportunity

    for undue influence to be exerted when people are voting. The exact mechanism to ensure

    this will need to be determined on a case-by-case basis, but the underlying principle is that

    each individual should cast his or her vote in private.13

    12 While time and input of CDC members cannot count as community contribution, the CDC may wish todiscuss its own mechanisms for compensating those dedicating themselves to community affairs management.In some communities, this has taken the form of assistance in land cultivation.With regard to additional costs of CDC members: while the CDC members initial costs of accommodation,food and travel incurred exclusively for the programme or the implementation of sub-projects can be charged toeach project (and clearly identified as such), it is imperative that the community begins to devise its ownsustainable solution for cost recovery.13 This could involve separate ballot boxes for men and women, decisions on whether the ballot paperwill have a list of all interested eligible cluster members, or whether the name of the candidate for which a vote

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    17/60

    NSP Operational Manual 15 December 2004 Page 17 of 54 Rev. Date: 15 December04

    Prohibition of candidature and electioneering is critical to reduce the likelihood of elite

    capture and intimidation, recognising that it will not remove it. To avoid the problem of

    selecting unwilling candidates, community members will prior to the election have an

    opportunity to declare, that they are not prepared to accept the position if elected. All

    members of the community are candidates until they take the positive step to declare

    themselves ineligible.

    To have functioning Development Councils, the number of representatives should be between

    5 and 15 persons depending on the size of the community. The Development Councils

    should select a Chairperson, Secretary and Treasurer. For the Development Council to have

    the authority to make decisions over resources it must also have a quorum of the community

    involved in the election. For the first round of NSP, a quorum is defined as 40% of all

    eligible voters. It is government policy to increase this percentage over the life of the

    program

    To ensure inclusiveness in terms of different socio-economic, factional, and ethnic/tribal(qaum) sub-divisions within the community, the election process should be based on division

    of the community into groups of families (clusters), which will each elect one representative

    for the Development Council. Since neighbours are usually also relatives, the division into

    clusters will also reducepurdah restrictions on women and thereby facilitate their active

    involvement in discussions of the qualities required for representatives and in the election

    itself. The size of such clusters will vary depending on the size of the community, but should

    not exceed about 20 families. The clusters would in turn serve as the framework for

    community wide consultations on proposals from the Development Council, through a

    process where the elected councillors consult with and seek feed-back from their electoratebefore decisions on priorities, sub-projects, and community contributions are finalized.

    Since communities will only have one Development Council, local solutions should be

    agreed for large communities (>300 families) with assistance from the Facilitating Partner.

    One such solution could be a two-tier voting process, where candidates elected by clusters of

    20 families elect a smaller Development Council (see diagram on following page and also

    refer to paragraph How to deal with different community sizes, earlier in the Operations

    Manual).

    The combination of high levels of illiteracy and the prohibition of predefined candidate lists

    and electioneering will present a range of challenges to the Facilitating Partners. However,

    both aspects are so central to the program that innovative and creative solutions will need to

    is cast is written on the ballot paper. If either of these solutions is agreed, assistance would have to be providedto illiterate voters by the Facilitating Partner, and a process to verify votes cast on a sample basis would alsoneed to be agreed. Another issue that may require different local solutions is whether the names of women canbe listed on ballot papers, and where this is not possible, how the number of eligible women voters isestablished, and how votes are cast for female candidates.

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    18/60

    NSP Operational Manual 15 December 2004 Page 18 of 54 Rev. Date: 15 December04

    be developed. Since the elections will take place in small clusters of households many of

    whom know each other, such solutions are possible. An obvious solution is for the

    Facilitating Partner to assist the illiterate members of the community. An alternative is to

    prepare ballot papers in the forms of maps of the village, with people marking the address of

    the person that they wish to vote for and a symbol for the person within that address (e.g.

    distinct symbol for oldest male, oldest female, etc).

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    19/60

    NSP Operational Manual 15 December 2004 Page 19 of 54 Rev. Date: 15 December04

    Box 2.

    On Governance: 5 Pillars of Governance

    Priorities for Year 2 communities - Lessons learned from Year 1

    While the issue of governance and institutional strengthening will be deepened throughout

    participatory discussions in Year 2, it is important that a few pillars of governance be

    commonly understood by Facilitating Partners and practised by Community Development

    Councils (CDCs). These include:

    Pillar 1. Maintenance of an inclusive and representative council. This entails potential

    sub-elections to integrate returnee communities, when applicable, as well as an

    attempt in Year 2 to create separate Councils for women to enable them to be full

    stakeholders in the management of their own development.

    Pillar 2. Regular meetings between the CDC and the larger community (e.g. once a

    month) in order to ensure fluid communication of proposal status, project progress

    and creation of new committees, when applicable. This is important to ensure that the

    CDC continues to nurture a democratic and participatory culture.

    Pillar 3. CDC visibility and public notice boards need to be an integral part of the

    transparency process to keep the larger community informed of project budget

    expenditure, progress as well as new ideas and opportunities. In view of the low rate

    of literacy these information tools must be visual and simple to understand for greater

    outreach.

    Pillar 4. Project books and meeting documents should be kept at the CDC level. The

    community ownership of the programme must be built through responsibility for

    adequate documentation and maintenance of records at the community level, and notlocated with Facilitating Partners .

    Pillar 5. Creation of Project Management Committees and/or thematic committees

    such as parent-teacher committees, water user associations (mir-ab), health, literacy

    or youth committees should be encouraged as a way to involve other members of the

    community (in the interest of inclusion, transparency and participation), avoid the

    over-burdening of CDC members, and create a greater dynamic of learning and self-

    management of community affairs.

    In addition to these 5 pillars, the issue of mandate of the CDC, development of by-laws or

    constitution of the CDC as well as rules for conducting new elections will be tackled in Year

    2. Further guidance on these issues will be provided through participatory exchanges between

    Facilitating Partners and the OC/MRRD as the year unfolds.

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    20/60

    NSP Operational Manual 15 December 2004 Page 20 of 54 Rev. Date: 15 December04

    Option 1: Mixed CDCs

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    21/60

    NSP Operational Manual 15 December 2004 Page 21 of 54 Rev. Date: 15 December04

    Option 2: Gender-segregated CDCs

    DEVELOPMENT COUNCIL ELECTIONS

    Male and Female

    DEVELOPMENT

    COUNCILS

    Elected Male and Female

    Cluster

    Representatives

    Household Clusters

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    22/60

    NSP Operational Manual 15 December 2004 Page 22 of 54 Rev. Date: 15 December 04

    CDC & CLUSTER CONSULTATIONS

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    23/60

    NSP Operational Manual 15 December 2004 Page 23 of 54 Rev. Date: 15 December04

    C. Facilitating Partner

    The primary role of the Facilitating Partner is to provide support and guidance to the

    community in meeting the requirements of NSP as described in this manual.The Facilitating Partner will report to the NSP. An agreement will be signed with the

    community on the community development plan regarding the exact inputs to be provided

    and services to be performed by the Facilitating Partner (Disbursement Form 8).

    In each province one or more Facilitating Partners will deploy community facilitators and

    technical specialists for three districts at a time to cover a target of up to 216 communities per

    year.14 Depending on capacity, individual Facilitating Partners will undertake these activities

    in one or more districts, or in one or more provinces.

    The roles of the Facilitating Partners are to: Facilitate elections of inclusive CDCs;

    Facilitate consultative community project planning comprising CommunityDevelopment Plans and sub-project proposals;

    Provide technical assistance to develop sub-project proposals through either:

    o facilitating community access to technical assistance available in the market orfrom other agencies; or,

    o technical assistance provided by the Facilitating Partner,15

    Provide technical assistance to communities during implementation;

    Provide training to communities (e.g. book-keeping, procurement, contracting)16;

    Conduct monitoring and reporting.

    The expected outputs of the Facilitating Partners are:

    Eligible project proposals (measured by the number of projects appraised andapproved by the NSP);

    14 Where feasible, the Facilitating Partner is expected to recruit and deploy female field staff to enable

    involvement of women in the targeted communities in the prioritisation, decision-making, and implementationof projects.15 While the preferred approach under NSP is for communities to avail themselves of technical assistancefor project design through the market, it is recognized that this may not be feasible in many rural areas, and thatin such situations, technical assistance will have to be provided by the Facilitating Partner.16 While there is a clear recognition that CDCs may have to be initially supported by Facilitating Partners(FPs) in the procurement process, it is imperative that this support be given in the form of capacity-buildingrather than substitution of the CDCs role in procurement. As such, should FPs and/or OC/MRRD get involvedin collection of bids, neither should be involved in the bid evaluation process, and at least one member of theCDC or members of the procurement committee should be part of the process, for reasons of transparency andlearning.

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    24/60

    NSP Operational Manual 15 December 2004 Page 24 of 54 Rev. Date: 15 December04

    Implementation of funded projects (measured by the number of projects completed inaccordance with design standards and in a sustainable manner);

    Depending on the number of districts and number of communities defined in the Facilitating

    Partners contract, performance will be assessed against the following annual target outputs

    for year 1. Achieving or exceeding the targets as defined in the table below will be a key

    determinant for extension/expansion of the contracts of the Facilitating Partners.

    Provinces(X)

    Districts(X)

    A

    Number ofcommunitieswith CDCs

    B 1

    Subprojectproposals

    submitted (thosemeeting appraisal

    criteria)

    B 2

    Appraised andapprovedsubprojectproposals

    C1

    Subprojectsunder

    implementation(% of funded

    projects)

    C2

    Subprojectscompleted

    D

    Percentageof

    subprojectsfunctioning3 months

    aftercompletion

    1st

    batch 24 80% of A = 19 80% of A = 19 80% of A2 = 19 80% of C1=15

    80% of C2= 12

    2nd

    batch 24 80% of A = 19 80% of A = 19 80% of A2 = 19 80% of C1=15

    3rd batch 24 80% of A = 19 80% of A = 19 80% of A2 = 19

    Aggregate

    target

    72 57 57 57 30

    The table above assumes that the Facilitating Partners staff is deployed so that facilitation of

    project preparation and implementation in a district is undertaken in three successive batches,

    each with a four month period for community planning, project preparation and appraisal,

    followed by an implementation period depending on the type of project that is undertaken.

    The table reflects that some of the target communities in the 3rdbatch would still be in the

    process of project preparation and appraisal by the end of year 1, and that implementation, if

    started, would not be completed. Likewise, for some of the target communities in the 2nd

    batch, ongoing implementation would not be completed by the end of year 1. Since not all

    Facilitating Partners may choose to deploy their field staff for coverage of their annual target

    as outlined above, an aggregate target is provided for expected outputs in a district in year 1.

    The NSP will hold Facilitating Partners accountable for performance against outputs, but the

    NSP will provide flexibility to its partners in the choice of specific facilitation methods and

    work planning. The Facilitating Partners may use facilitation methods that they deem

    appropriate while respecting the eligibility criteria to achieve the outputs against which the

    eligibility of community project proposals will be appraised (see Section I.E above), and may

    also plan the deployment of their staff and sequencing of activities in ways they consider

    optimal for achieving their overall output targets.

    D. Ministry of Rural Rehabilitation and Development

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    25/60

    NSP Operational Manual 15 December 2004 Page 25 of 54 Rev. Date: 15 December04

    MRRD will be responsible for overall management and supervision of the National Solidarity

    Program (NSP). Within the ministry, the NSP will be managed by an Oversight Consultant

    working with MRRD counterparts in the Community Led Development Department to

    strengthen capacity for community development and program management. The Oversight

    Consultant will support the Community-Led Development Department regarding:

    Management of the NSP block grants for community projects (including effectingfund transfers, tranche payments, financial management, and accounting);

    Supervision of the performance of Facilitating Partners (including contractmanagement, contracting of Facilitating Partners beyond those recruited by MRRD

    prior to the Oversight Consultant being recruited in order to secure services ofFacilitating Partners to cover all 32 provinces at the scale required);

    Appraisal of community project proposals;

    Planning and conducting training for the field staff of Facilitating Partners (eitherdirectly or through sub-contracting);

    Undertaking technical and financial monitoring, and producing consolidated progressreports, and

    Managing an information and communication campaign.

    E. NSP Steering Committee

    A Steering Committee acts in an advisory capacity to MRRD on overall program policy

    formulation and direction, and oversees program implementation. At present, the Steering

    Committee is composed of representatives from MRRD and Ministry of Finance (MoF). An

    External Review Committee consisting of donors, UN agencies, the Independent Commission

    for Human Rights, MoF and MRRD meets on a regular basis to review and endorse all policyand contractual issues.

    Discussions are underway to broaden the membership of the Steering Committee by merging

    the two bodies. An inter-ministerial committee has been established for policy advice and

    coordination. The committee is chaired by MRRD and comprises the ministries of Finance,

    Agriculture, Public Health, Education, Irrigation, Labor & Social Affairs, Womens Affairs,

    Public Works, Reconstruction, Foreign Affairs, and Refugees.

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    26/60

    NSP Operational Manual 15 December 2004 Page 26 of 54 Rev. Date: 15 December04

    ORGANIZATIONAL CHART

    III. CYCLE OF ACTIVITIES

    This section covers the activities to be undertaken during preparation, appraisal,

    implementation and completion of the sub-project cycle. The goal is to facilitate an inclusive

    participatory process within the community which results in an equitable community

    development plan including a series of sub-projects that are eligible for funding under the

    NSP and/or eligible for funding from other existing programs. The long-term goal is the

    creation of community institutions that are to strengthen the communitys ability to mobilize,

    consult, plan, finance, implement and evaluate their own development.

    A. Preparation

    During this phase of the cycle, Facilitating Partners will help:

    mobilize the community including facilitating the establishment through elections of aCommunity Development Council and related project implementation committees asagreed with the community;

    facilitate a participatory planning process that includes women and the weakersections of the community;

    Communities

    MRRD - NSPCommunity-Led DevelopmentDepartment and NSP Oversight

    Consultant

    MRRD NSPCommunity-Led DevelopmentDepartment and NSP Oversight

    Consultant

    NSP Steering

    Committee

    Facilitating

    Partner FacilitatingPartner

    FacilitatingPartner

    National Level

    ProvincialLevel

    District and

    CommunityLevel

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    27/60

    NSP Operational Manual 15 December 2004 Page 27 of 54 Rev. Date: 15 December04

    strengthen community capacity to identify and prioritise needs;

    assist the community to prepare a Community Profile with baseline data(Disbursement Form 1);

    facilitate the preparation of a Community Development Plan (Disbursement Form 6)and proposals for specific project(s) with budget(s);

    provide technical assistance to develop sub-project proposals (Disbursement Form 7)for appraisal through either:

    o facilitating community access to technical assistance available in the market orfrom other agencies; or,

    o technical assistance provided by the Facilitating Partner,

    sign off on the Community Development Plan and sub-project proposal(s) withrespect to technical quality, financial feasibility and inclusive communityinvolvement in planning and decision making before they are submitted to NSP.

    The community will:

    elect an inclusive Community Development Council and establish ProjectManagement Committees as needed for sub-projects;

    develop a Community Development Plan (including priority sub-project proposalswith budgets and community cost contributions and O&M arrangements as well as

    projects which can be financed and implemented by the community itself);

    obtain inputs and endorsement from the community (if necessary through separatemeetings with men and women) regarding the Community Development Plan;

    mobilize the required technical expertise to help develop designs within giventechnical standards;17

    agree on rules for dissemination of budget and expenditure information; submit the community development plan and proposal(s) to NSP.

    The training manual provides more in-depth guidance on the processes which can be

    followed during each phase, however, the Facilitating Partner will have flexibility in the

    choice of the facilitation methodology for undertaking the activities listed above.

    B. Appraisal

    The community (with the assistance of the Facilitating Partner) will complete and submit a

    Community Development Plan and standard sub-project proposal(s) (including technical

    designs and cost schedules) to the provincial representative of the NSP. (See DisbursementForm 6 and 7 for standard format for the community development plan and sub-project

    application form). The Community Development Plan constitutes a medium term investment

    plan for a particular community, which would provide the basis for additional future

    17 This may involve getting the required technical assistance from the market (payment can be madedirectly as part of the community contribution, or retroactively if and when a project is appraised and foundeligible for funding), or getting this assistance from the Facilitating Partner, where it is unavailable in themarket.

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    28/60

    NSP Operational Manual 15 December 2004 Page 28 of 54 Rev. Date: 15 December04

    development activities whether funded by NSP or other sources, and also represent for the

    first time ever a bottom-up input to higher level planning at the district, provincial, and

    national level.

    Appraisal of the community proposal and budget are conducted by the NSP. The Facilitating

    Partner will help communities prepare and implement sub-project proposals and bepositioned as allies of the community, while the NSP staff will formally appraise proposals

    and make funding decisions.

    The NSP will be responsible for appraisal of all community project proposals to determine

    whether they meet the eligibility criteria. This will be done using a standard appraisal tool

    (Disbursement Form 7c) by the NSP technical staff from the provincial office (and involving

    relevant government agencies, e.g. for education). The appraisal will be done using a

    transparent procedure. Eligibility criteria, indicators and means of verification are listed in

    the table below. The criteria will be made known to the community in order to limit the

    discretionary power of the NSP. A proposal is evaluated based on these criteria and assessedduring a field visit to the community. During this appraisal visit the appropriate levels of

    installments will be discussed and agreed upon. In the absence of special agreements the

    installments will be 50: 40: 10 %.

    The community is then informed by the NSP regarding the result of the appraisal, which may

    be a) approval of funding for the proposed plan, b) rejection for non-compliance with NSP

    rules (e.g. project is on the negative list), c) requiring the community to revise its proposal

    with regard to either the election of the Community Development Council, the planning

    process, the budget, or the technical standards.

    The provincial NSP office will undertake field verification on a sample basis of whether

    elections of Community Development Councils conform with the basic principles defined in

    this manual. In addition, the national level NSP office will undertake periodic field

    supervision audits on a sample basis of the appraisal process to ensure that eligibility criteria

    are complied with.

    Upon completion of appraisal and approval by NSP of a community sub-project proposal, a

    Tripartite Agreement will be signed between the Community Development Council, NSP,

    and the Facilitating Partner regarding the financing of the sub-project, disbursement schedule

    and benchmarks triggering installments and the general obligations of each of the parties tothe agreement (see Section IV, C).

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    29/60

    NSP Operational Manual 15 December 2004 Page 29 of 54 Rev. Date: 15 December04

    Sub-Project Eligibility and Appraisal Criteria

    Core

    Principles Eligibility Criteria Indicator Means of Verification

    Does Proposal

    Meet Eligibility

    Criteria?

    1.

    Representativecommunityinstitution

    Establishment of a

    community widedecision makingprocess and electionof a representativeCDC

    CDC elected with

    representation from differentgeographical and occupationalsections40% of eligible votersparticipated in the election

    CDC Registration Form; CDC registration certificate; Form 2; Proposal submitted by CDC

    (YES) (NO)

    2.BeneficiaryParticipation

    CommunityDevelopment Planendorsed through acommunity-wideprocess

    Community-wide meetingsheld;60% of families participatedin decision meeting.Decisions/priorities of womentaken into account

    Random interviews withcommunities; Interviews with womensgroup members; Minutes of decision makingcommunity meetings

    3.Equity

    Sub-project providesbeneficiariesequitable access tobenefits

    Persons from differentgeographical and occupationalsections of the community canaccess benefits

    Confirmation of sub-projectmap of beneficiaries throughrandom interviews withcommunity

    Check proposal onbeneficiaries and equity

    4.TechnicalSoundness

    Sub-project istechnically sound

    Sub-project complies withappraisal criteria for technicalquality standards, and theproject negative list.

    Check proposal for technicalquality (problem statement,goals & objectives, engineeringdesigns, implementationarrangements, risks andconstraints)

    5.FinancialSoundness

    Sub-project isfinancially sound

    Sub-project complies withappraisal criteria for financialsoundness and corresponds tothe technical layout.

    Check proposal for financialquality (project budget,procurement plan, disbursementschedule)

    6.Compatibility

    with social &environmentalsafeguards

    Sub-project issocially and

    environmental sound

    Sub-project complies withappraisal criteria,

    environmental and socialsafeguards issues, and theproject negative list.

    Check proposal forenvironmental and social quality

    7.CommunityCommitment

    Sub-project hascommunitycontribution towardscapital costs

    Minimum of 10% of capitalcosts committed (cash, kind orlabor)

    Check proposalRandom interviews withcommunities

    8.Sustainability

    Proposed project hascommunityarrangements foroperation &maintenance (O&M)

    O & M plan with budgetcommitted and training planprepared18

    Check proposalRandom interviews withcommunities

    9.Transparency

    Accept principles oftransparency

    regarding budgetingand expenditures

    Budget (and later accounts)posted in public places and

    through meetings (e.g. in themosque and womensmeetings)

    Check proposalRandom interviews with

    villagers (both men and women)

    18 The O&M plan must include not only an operating budget, but a clear indication of a community-managed cost recovery system, such as a user-payer scheme. Cost recovery rates should be established at a levelthat will enable payment of: a) running costs (e.g. fuel for a generator or pump), b) repairs and maintenance andc) replacement of the assets when its operational life-time is over. Without an adequate cost recovery system,the sustainability of the outputs is likely to decrease. This involves careful attention on the part of CDCs andFacilitating Partners - as well as OC/MRRD.

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    30/60

    NSP Operational Manual 15 December 2004 Page 30 of 54 Rev. Date: 15 December04

    10.Mine Risk

    Mine Risk Safety hasbeen assessed

    Questionnaire on Mine RiskSafety has been filled out

    Check proposalForm 7a

    C. Sub-Project Implementation

    The primary responsibility for sub-project implementation will rest with the community (the

    Community Development Council, Project Management Committee, and the greater

    community). Clear divisions of responsibility between the Development Council members

    and Project Management Committee members will increase accountability. Three or more

    persons at the community level should be identified as responsible for most implementation

    activities such as procurement, bookkeeping, supervision, storage and accounting. This will

    not only promote transparency and continuity at the community level but it will also ensure

    that more than one person in the community has the necessary skills/training to perform the

    task.

    Depending on the type of sub-project, the community may either be capable of undertaking

    implementation itself, or may require external assistance regarding specialized technical

    skills or services (e.g. masons for school construction, or lining and hand pump installation

    for dug wells for drinking water). The procurement of such services will follow established

    procedures (see Annex 3 Procurement Forms).

    If a community is using its block grant for more than one sub-project, parallel

    implementation is an option, if sufficient capacity is present, since this will speed up overall

    implementation, and enable completion of projects within the constraints defined by local

    climate and altitude.The Facilitating Partner will support the community during this process with regard to:

    technical assistance on an as needed basis (e.g. procedures for procurement of goodsor contractors);

    implementation (e.g. advice on implementation organization, and supervision ofworks and construction quality)

    training on matters such as book-keeping, contracting, maintenance tasks etc.

    D. Monitoring by the Community

    The community wide assembly will agree on the methods and schedule of reporting to thecommunity (on financial and physical progress) by the Community Development Council

    and the relevant Project Management Committees. The methods for information

    dissemination should ensure that women are informed about project activities. The

    community will also agree on key indicators to monitor joint decision making, project

    progress, and transparency. Monitoring against these indicators will be reported in the

    Community Progress Reporting Form used by the Facilitating Partners (Reporting Form 16a).

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    31/60

    NSP Operational Manual 15 December 2004 Page 31 of 54 Rev. Date: 15 December04

    In the community, all records and accounts must be available for inspection by the members

    of the community, the Facilitating Partner, and NSP. The arrangements to ensure

    transparency shall include regular community wide information meetings, display of all

    relevant information on implementation progress and expenditures on notice boards

    accessible to the public, and/or announcements of project-related information atJumma

    prayers.

    E. Physical and Financial Progress Monitoring

    The Facilitating Partner will be responsible for physical and financial progress monitoring on

    a monthly basis (Reporting Form 6) with summary progress reports and on a quarterly basis

    with more comprehensive status reporting (Reporting Forms 19 and 19a). These reports

    constitute an input to the overall quarterly progress reporting by NSP (Reporting Form 8).

    The Facilitating Partner will report to NSP on process, achievement of implementation

    benchmarks, and quality of works as defined in the Tripartite Agreement. Achievement of

    implementation benchmarks will be tied to the release of funding to the community.

    The NSP staff will perform sample audits of the support for the community carried out by the

    Facilitating Partner regarding elections of Community Development Councils, preparation of

    sub-project proposals that comply with NSP eligibility criteria, recommendations for release

    of block grant instalments based on achievement of agreed activities, and the adequacy and

    realism of progress reporting (Reporting Form 5).

    F. Sub-project Completion

    A completion report will be prepared by the community and the Facilitating Partner

    (Reporting Form 1). The completed project will be inspected by the NSP, and a Certificate of

    Completion (Reporting Form 2) will be issued to the community provided the sub-project is

    technically sound and that all funds received from NSP have been reconciled. NSP may

    approve that any savings that are remaining may be allocated to be used by the community to

    increase the scope of the community development plan during the current or following year.

    The NSP form submission / disbursement process is presented in the following diagram.

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    32/60

    NSP Operational Manual 15 December 2004 Page 32 of 54 Rev. Date: 15 December 04

    NSP Form Disbursement Process

    ilization

    PO submitsOC Kabul

    Fo

    Election

    C/FP submitsto OC PO

    Form 2

    Form 3

    Form 4

    Form 5

    Registration Phase

    Form 1

    Form 6

    Design Phase

    SubprojectIdentification Proposal Submission

    Form 7

    Project Plan

    CDCRegistration

    1. PO submits to Kabul2. Kabul final approval

    3. Block Grant Disbursementbased on Form 8,9 & SPS

    Form 8

    Form 9

    Tripartiteagreement

    SPS

    Compagreed

    Subproj

    (Summary Project Sheet)

    Proposal Approved

    $

    Planning Phase

    BankRegistration 2 Weeks

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    33/60

    NSP Operational Manual 15 December 2004 Page 33 of 54 Rev. Date: 15 December04

    IV. FINANCING AND FUND-FLOW SYSTEM

    A. Overall Fund-Flow Arrangements

    The overall flow of funds to communities will be managed by the NSP based on the process

    outlined below, which summarizes the previous chapters in this manual:

    1. The Facilitating Partner provides a Community Profile (Disbursement Form 1) including

    a preliminary assessment of the block grant entitlement of the community to the

    provincial office of NSP/RRD/OC.

    2. Elections for the Community Development Council are held, and the Facilitating Partner

    certifies that the elections were held in accordance with NSP rules (Disbursement Form

    2). The provincial NSP office (Oversight Consultant and MRRD staff) undertakes

    sample verification checks.

    3. After completion of Community Development Council elections and certification of

    these, representatives of the council go to the provincial NSP office to undertake two

    tasks:

    a. Submit an application to the provincial NSP/RRD/OC office (Disbursement Form 3)for registration of the Community Development Council (Disbursement Form 5).

    b. Submit a form authorizing three community representatives to withdraw block grantfunds on behalf of the Community Development Council (Disbursement Form 4).Where functioning bank branches exist in the provincial center, an application to opena bank account is submitted (Disbursement Form 4a) together with an authorization

    from the Community Development Council for nominated persons to makewithdrawals from the account (Disbursement Form 4b).

    4. With support from the Facilitating Partner, the Community Development Council in

    consultation with the community at large agrees on a Community Development Plan,

    which constitutes a medium term development and investment plan for the community in

    question (Disbursement Form 6). The Community Development Plan is submitted to the

    provincial NSP/RRD/OC office. Each community development plan will include a list of

    priority investment needs (i.e. one or more sub-projects) within the budget envelope

    defined by the block grant, the contribution that the community is mobilizing, and funds

    that can be accessed from other programs.

    5. If required, NSP at the provincial and central level coordinates with relevant line

    ministries, so that it is ensured that sub-project proposals for schools or clinics fit with

    the sector plans of the concerned ministry, and that operating costs are budgeted by the

    ministry in question. NSP assists the community to obtain verification regarding these

    issues from the concerned line ministries, and communicates this information in writing

    to the community in question.

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    34/60

    NSP Operational Manual 15 December 2004 Page 34 of 54 Rev. Date: 15 December04

    6. With support from the Facilitating Partner, the Community Development Council in

    consultation with the community at large develops one or more sub-project proposals

    within the available funding envelope (block grant allocation, community contribution,

    funding from other sources). The sub-project proposal(s) is submitted to the provincial

    NSP office (Disbursement Form 7).

    7. Each sub-project proposal will be appraised individually, but implementation and

    funding of sub-projects can take place simultaneously, if the community has the capacity

    to manage this. While an overall Tripartite Agreement (Disbursement Form 8) for the

    community development plan (or the elements of this plan for which funding is

    available) will be signed between the community, NSP, and the Facilitating Partner,

    copies of the first page of Disbursement Form 7 (Sub-project approval request) will be

    attached to the Tripartite Agreement. This will cover the specific plans and budgets for

    each approved sub-project.

    8. After the Tripartite Agreement has been signed the CDC requests the release of the firstinstallment by the NSP/RRD/OC. (Disbursement Form 9)

    9. Funds for approved sub-project proposals will be channeled directly from the NSP to the

    community based on an agreed installment system of financing. The nominated

    community representatives will be accompanied by the Facilitating Partner to the

    provincial NSP office for (at least) the first block grant disbursement. The NSP office

    will keep a copy of the community letter of authorization and the photos of the

    nominated representatives for future verification. A minimum of three signatories are

    required for withdrawal of funds.

    10. The first block grant installment (normally 50% of the block grant funding for a

    particular sub-project) will be released. The installment will be released from the NSP at

    central level to the community (CDC) using either the banking system, where this is

    functioning, or a government registeredHawala. Where theHawalasystem operates at

    the community level, the fund transfer may take place there to reduce security risks and

    expedite disbursements to communities.

    11. The second block grant installment (normally 40% of the sub-project block grant

    funding) will be released when 80% of the first installment has been spent or80% of the

    agreed activities under the first installment have been completed and the CDC certifiesthrough the FP that:

    a. Implementation progress toward the agreed activities under this installment asdescribed in the sub-project proposal is satisfactory;

    b. the required community cost contribution has been provided;

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    35/60

    NSP Operational Manual 15 December 2004 Page 35 of 54 Rev. Date: 15 December04

    c. the community at large has been regularly updated by the CommunityDevelopment Council about project progress and expenditures (e.g. meetings,notice board);

    d. community procurement has been undertaken in compliance with NSP rules;

    e. The installment has been requested of the NSP/RRD/OC through

    Disbursement Form 9.12. The provincial NSP office (Oversight Consultant and RRD staff) undertakes sample

    verification checks of achievement of activities under each installment and

    implementation quality.

    13. The final block grant installment (normally 10% of the sub project block grant funding)

    will be released when 80% of the second installment has been spent (supported by a

    simple financial statement) andthe FP certifies 80% sub-project completion and

    fulfillment of the same five requirements outlined above (see a to e) as conditions for the

    second installment. The CDC and the FP shall guarantee to submit a 100% sub-project

    completion report (Reporting Form 1) including a simple financial report upon

    completion of the project. Then the completion of the Sub-project will be certified from

    the NSP/RRD/OC to the community (Reporting Form 2).

    14. In the case of types of sub-projects which require large capital outlays for pieces of

    equipment that constitute the main costs of the sub-project (e.g., diesel generators and

    hnad pumps), the normal 50:40:10 breakdown of payment tranches need not necessarily

    apply, but should apply in most cases.

    15. The provincial NSP office (Oversight Consultant and RRD staff) undertakes sample

    verification checks of achievement of activities under each installment andimplementation quality.

    B. Fund Transfer Mechanism

    The Tripartite Agreement defines the schedule of disbursement installments on the basis of

    an agreed plan of physical progress of a particular sub-project. Funds will be transferred

    using a fixed price or lump-sum method of financing based on several installments (at least

    three) per sub-project. The size of individual payments under each tranche (amounts) must

    be determined based not only on the technical requirements of the sub-project, but also on

    security concerns at the community level. However as a norm, the first installment can notexceed 50% of the sub-project costs.

    Where local banks function at the provincial level, communities can maintain a checking

    account and make withdrawals and payments as required. Where a banking system is not

    functioning, and funds are transferred throughHawalaagents, the community can arrange

    with the NSP that specific payments are made directly at the NSP provincial office to

    suppliers and contractors in the presence of the community representatives. This would limit

  • 8/10/2019 National Solidarity Manual Operations Manual (Dec 2004)

    36/60

    NSP Operational Manual 15 December 2004 Page 36 of 54 Rev. Date: 15 December04

    the amount of cash that communities will have to transport, store, and handle. Likewise,

    whereHawalaagents do not agree to operate under this arrangement, the transfer of block

    grant funds may take place in the community provided theHawalasystem operates at this

    level. This would also serve to avoid that provincial NSP/RRD/OC offices would have to

    keep cash, would reduce security risks associated with transport of cash by community

    representatives, and would expedite disbursements to communities, Where practiced, the

    transaction would have to be witnessed and certified by the Facilitating Partner.

    Unless there are exceptional circumstances, payment for implementation will be made in

    three installments/tranches agreed between MRRD and the CDC on the basis of the funding

    requirements of the sub-project in question (the first installment should normally not exceed

    50% of total sub-project costs). The first installment will be paid following signing of the

    Tripartite Agreement, the second installment after achievement of agreed implementation

    activities, and the third installment upon 80% completion of the project supported by a

    financial statement accounting for 80% of sub-project funds received. Examples of financial

    reporting forms at the community, provincial and national levels, accompanied by

    explanatory text, are set out in Annex 2: NSP Accounting Forms.

    If a community is using its block grant for more than one sub-project, an assessment will be

    made by NSP whether the projects can be funded and implemented in parallel or sequentially

    (i.e. the first sub-project must be completed before funding for the next sub-project is

    released). The criterion for parallel funding and implementation is that one of the sub-

    projects must be identified by women and address their defined needs. In all other cases

    where block grants are used for more than one sub-project, these will be financed

    sequentially.

    C. Tripartite Agreement

    The Tripartite Agreement represents the contract between the NSP and the community and is

    a complete statement of the obligations and responsibilities of the parties to th