National Solar Mission India
date post
20-May-2015Category
Documents
view
4.677download
1
Embed Size (px)
description
India targets 20+2 GW Solar power by 2022. Support of $19 Billion with $922 Million for first tthree years
Transcript of National Solar Mission India
- 1. by
2.
- Introduction
- Importance & Relevance of Solar Energy in India
- Objectives & Targets
- Mission Strategy (Phase I & II)
- Proposed Roadmap
- Policy & Regulatory Framework
- Research & Development
11/24/09 3.
- Human Resource Development
- Institutional Arrangements for Mission
- International Collaboration
- Financing Mission Activities
11/24/09 4.
- Major initiative by GOI & State Governments
- Aims at promoting ecologically sustainable growth
- Also addresses energy security challenge
- Will contribute to the global effort to meet the challenges of climate change
11/24/09 5.
- Cost
- Solar is high on absolute cost as compared with other power such as coal
- Objective of Solar Mission is to drive down the cost by
- Rapid scale-up of capacity
- Technological innovation
- Mission anticipates to achieve
- Grid parity by 2022
- Parity with coal-based thermal power by 2030
11/24/09 6.
- Cost trajectory depends on
- Scale of global deployment
- Technological development & transfer
- Cost projections vary - from 22% for every doubling of capacity to a reduction of only 60% with global deployment increasing 16 times the current level
- Mission recognizes a number of off-grid applications for meeting rural needs which are cost-effective & requires rapid expansion
11/24/09 7.
- Scalability
- About 5000 Trillion Kwh energy potential is incident over Indias land area with most parts receiving 4-7 Kwh/Sq.mt/Day
- Technologies that can be used to harness the resource & provide huge scalability of solar in India Solar Photovoltaics & Solar Thermal
- Advantages of Solar technology
- Ability to provide power in a distributed basis
- Enable rapid capacity addition with short lead times.
- Apt solution for rural electrification
- Can work in diffused radiating conditions as well
11/24/09 8.
- Environmental Impact
- Zero emissions while generating heat and emissions
- Security of source
- Available abundantly
- Small fraction of total incident solar energy can meet the entire countrys power requirements
11/24/09 9.
- Objective is to establish India as a global leader in solar energy
- Mission adopts 3-phase approach
- Phase I (up to 2012/2013) remaining period of 11 thfive yr plan & first yr of 12 thyr plan
- Phase II (2013-2017) remaining 4 yrs of 12 thfive yr plan
- Phase III (2017-2022) 13 thfive yr plan
11/24/09 10.
- End of each plan there will be
- Evaluation of progress
- Review of capacity
- Targets for subsequent phases
- Above evaluations will be based on emerging cost and technology trends, both domestic and global
- Aims to protect government from subsidy exposure & expects cost reduction does not materialize or ismore rapid than expected
11/24/09 11.
- Mission Targets
- Create an enabling policy framework for the deployment of 20,000 MW of solar power by 2022
- Ramp up capacity of grid-connected solar power generation
- 2013 1000 MW
- 2017
- Additional 3000 MW(mandatory use of renewable purchase obligation by utilities backed with preferential tariff)
- Capacity could increase to 10,000 MW installed power by 2017 or more, based on enhanced & enabled international finance & technology transfer
11/24/09 12.
- 2022 20,000 MW or more will be dependent on learning of first two phases
- Create favorable conditions for solar manufacturing capability (solar thermal for indigenous production & market leadership)
- Promote programmes for off grid applications (1000 MW 2017 & 2000 MW 2022)
- Achieve 15 million sq. meters 2017 & 20 million sq. meters -2022of solar thermal collector area
- 2022 - deploy 20 million solar lighting systems for rural areas
11/24/09 13.
- Phase I
- Will provide broad framework to achieve objectives
- Will create necessary environment to attract industry & project developers to invest in research, domestic manufacturing & development of solar power generation
- Hence will help in creating the critical mass for a domestic solar industry
- Mission to work closely with State Govts., Regulators, Power utilities & Local self govt. bodies to ensure activities & policy framework being laid out can be implemented effectively
11/24/09 14.
- Utility connected applications: constructing the solar grid
- Promoting solar power through Renewable Purchase Obligation (RPO) mandated for power utilities, with specific solar component
- RPO will drive utility scale power generation(solar PV or solar thermal)
- RPO will gradually increase where as the tariff fixed for solar power purchase will decline over time
- The below 80C challenge solar collectors
- Mission sets an ambitious target for ensuring that applications, domestic & industrial, below 80C are solarised
11/24/09 15.
- Key strategy to make necessary policy changes to meet this objective
- Making solar heaters mandatory, through building byelaws and incorporation in the National Building Code
- Ensure the introduction of effective mechanisms for certification and rating of manufacturers of solar thermal applications
- Facilitate measurement and promotion of these individual devices through local agencies and power utilities
- Support the upgrading of technologies and manufacturing capacities through soft loans, to achieve higher efficiencies and further cost reduction
11/24/09 16.
- The off-grid opportunity lighting homes of the power- deprived poor
- Key problem to find optimum financial strategy to pay for the high-end initial costs in these applications through appropriate Government support
- Government has promoted the use of decentralized applications through financial incentives and promotional schemes
- Solar Mission has set a target of 1000 MW by 2017, which may appear small, but its reach will add up to bringing changes in millions of households
- 30 % capital subsidy for promoting innovative applications of solar energy
11/24/09 17.
- Mission plans to
- Provide solar lighting system under the ongoing remote village electrification programme of MNRE to cover about 10,000 villages & hamlets
- Set up stand alone rural solar power plants in special category States and remote and difficult areas such as Lakshadweep, Andaman & Nicobar Islands, Ladakh region of J&K. Border areas would also be included
- Promotion of other off grid solar power applications would also be e