National Grid Distributed Generation Seminar

35
MA Interconnection Process Meeting July 16 th , 2020 (Webex) National Grid Distributed Generation Seminar The information summarized in this Seminar for the convenience of customers is current as of July 16, 2020 and neither the slides nor related recording should be relied on for a particular project. Customers are responsible for ensuring that they comply with all distributed generation rules and regulations, including the distributed generation Tariff, for their particular project.

Transcript of National Grid Distributed Generation Seminar

Page 1: National Grid Distributed Generation Seminar

MA Interconnection Process Meeting

July 16th 2020 (Webex)

National GridDistributed Generation Seminar

The information summarized in this Seminar for the convenience of customers is current as of July 16 2020 and neither the slides

nor related recording should be relied on for a particular project

Customers are responsible for ensuring that they comply with all

distributed generation rules and regulations including the

distributed generation Tariff for their particular project

2National Grid

This presentation has been prepared solely as an aid to discussions

between National Grid and interested stakeholders and should not be

used for any other purposes This presentation contains high-level

general information (not project specific) which may not be applicable in all

circumstances National Grid makes no guarantees of completeness

accuracy or usefulness of this information or warranties of any kind

whatsoever express or implied National Grid assumes no responsibility

or liability for any errors or omissions in the content Nothing contained in

this presentation shall constitute legal or business advice or counsel

No party is authorized to modify this presentation

The Webinar is being recorded

The information in this presentation could be affected by future revisions to

the Standards for Interconnection of Distributed Generation MPDU No

1320 (Tariff) in open docket DPU 19-55

Disclaimer

3National Grid

Agenda

| July Interconnection Webinar | July 16 2020

01 Welcome amp Opening Remarks ndash Will Kern

Safety message

COVID amp Force Majeure

2

02 Energy Storage Systems ndash Margaret Campbell 5

03

04

05

Interconnection Process Review

Simplified ndash Margaret Campbell

Expedited ndash Mike Armell

Standard ndash Nat Mahattanasakul

9

15

24

06 Process Improvement ndash Will Kern 30

07 QampA 32

4National Grid

Safety Moment Heat Exhaustion

bull Heat exhaustion symptoms include being pale ashen

or moist muscle cramps fatigue weakness or

dizziness

bull Be cognizant of compounded effects when working in

front of a grill youll get tired much faster than you

normally would based on the weather alone

bull Heat exhaustion can evolve into heat stroke quickly so

monitor symptoms and immediately move victims to

shaded or air-conditioned areas

bull Provide water or other cool nonalcoholic beverages

but dont force it

bull Seek medical attention immediately if body temperature

is above 103 or the individual is unresponsive

| July Interconnection Webinar | July 16 2020

5National Grid

COVID amp Force Majeure

| July Interconnection Webinar | July 16 2020

Payment extensions are no longer applicable

The company is working close to blue sky operations

however we will continue to monitor the situation as it develops

There have been very few Force Majeure impacts to cases which

were managed closely with the impacted developers

Payment due dates are not extended by Force Majeure per Tariff

Updates will continue to be posted

at httpsngusforcecomsarticleMA-Force-Majeure-

Declarations

Energy Storage

SystemsMargaret Campbell

02

7National Grid | July Interconnection Webinar | July 16 2020

New Storage Case Fields

New Application for Generation without Storage

New Application for Generation and Storage

New Application for Stand Alone Energy Storage

Add Storage to Existing Generation

AC-Coupled

DC-Coupled

Separate PCC

Electric Grid Only

Unrestricted Electric Grid or Generation

Restricted Electric Grid or Generation

Generation Only

Electric Grid Only

Unrestricted Electric Grid or Onsite Load

Restricted Electric Grid or Onsite Load

Onsite Load Only

AC Storage are included in the system size when determining if an application is simplified

expedited or standard so Storage AC kW is important to route application correctly

The Storage Charging Capability and Storage Discharging Capability values should match the

note on the one-line indicating how the storage will charge and discharge

8National Grid | July Interconnection Webinar | July 16 2020

Energy Storage System (ESS) Assets

The Inverter Information

This is the inverter for the ESS not the ESS itself

For DC coupled this is often the same inverter as the solar for example a SolarEdge inverter

For AC coupled this can be a separate inverter or the same as the ESS if it is a combined unit for example Powerwall

The ESS Information

Must be completed for AC and DC coupled batteries

The Storage Capacity per Device (kW DC) or (kW AC) is required (often

missed)

The Relay Information

Provides space for inputting ESS operating hours otherwise can be included in

the ESS information as an upload under special guidance

9National Grid | July Interconnection Webinar | July 16 2020

Energy Storage System (ESS) Form

The ESS Form is required and must be filled out electronically on the

portal (cannot be upload only)

Most of the fields on the ESS form are pre-populated from the Storage

case or values already entered on the case

If any of the pre-populated values look incorrect or need to be

updated please update the storage asset or reach to out to CEI

job owner thru Chatter

Link for knowledge page for adding a storage

asset httpsngusforcecomservletservletFileDownloadfile=0150W00000E

oHnv

Link for Storage Assistance httpsngusforcecomsarticleStorage-

Assistance

Simplified Review

ProcessMargaret Campbell

03

11National Grid | July Interconnection Webinar | July 16 2020

Simplified Criteria

UL Listed (1741 SA) inverter-based systems with power ratings of

15kW or less on a single phase service on a radial feed

UL Listed (1741 SA) inverter-based systems with power ratings of

25kW or less on a three phase service on a radial feed

The Simplified process does not apply for

Non-listed inverters or other generators (induction synchronous

asynchronous)

Aggregate generation capacity of listed inverters that exceed the

above-mentioned limits

Project that did not pass the Simplified process Screens

12National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Application

Simplified

Conditional Approval (to construct DG system)

Witness Test (completion package)

Authorization to Interconnect

httpswwwnationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

13National Grid | July Interconnection Webinar | July 16 2020

Simplified Review Path

Simplified Process

Eligible Facilities Listed Small Inverter

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Review of All Screens 15-20 days

Complete Supplemental Review (if needed) NA

Complete Standard Process Initial Review NA

Send Follow-on Studies CostAgreement NA

Complete Impact Study (if needed) NA

Complete Detailed Study (if needed) NA

Send Executable Agreement Done The agreement is part of the application

Total Maximum Days 25 days (30 in the case of failure of Screen 5)

Construction Schedule Varied

Witness Test Within 10 days from receipt of the Certificate of Completion or by mutual agreement

14National Grid | July Interconnection Webinar | July 16 2020

Common Holds or Concerns

Application

The application must match the customerrsquos account name address

account number and meter number

Wait to construct the system until after Conditional Approval is issued

After Conditional Approval

Complete the Service Upgrade Form so the work request can be

created and provided to the wire inspector at the before the inspection

Completion Package

Have Wire Inspection called in before submitting Completion

Documents

15National Grid | July Interconnection Webinar | July 16 2020

Recent Portal Improvements

Expedited Review

ProcessMike Armell

04

17National Grid | July Interconnection Webinar | July 16 2020

Expedited Criteria

Single phase customers with listed single-phase inverter based

systems with power ratings of gt15 kW on a radial feed

Three phase customers with listed three-phase inverter based

systems with power ratings of gt25kW on a radial feed

Any project that did not pass the Simplified process Screens

Non-Simplified projects that do not require an Impact Study

Maximum size supplemental review is based on review of

Screens

18National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application (if 500 kW or greater)

Application

Expedited

Engineering Review

Supplemental Review

Conditional Approval (to construct DG system)

Company Construction

Witness Test (where applicable)

Completion Document Review and Meter Set

Authorization to Interconnect

httpswwwnationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

19National Grid | July Interconnection Webinar | July 16 2020

Expedited Review Path

Expedited

Eligible Facilities Listed Inverter DG

Acknowledge Receipt of Application(3 days)

Review Application for Completeness10 days

Complete Review of All Screens25 days

Complete Supplemental Review (if needed)20 days or Standard Process

Send Executable Agreement10 days

Total Maximum Days 4565 days

Construction ScheduleVaried

Notice Witness TestWithin 10 days of receiving Certificate of

Completion or by mutual agreement

If any Screens are not passed the

Company may require a Supplemental Review Agreementbefore providing an Interconnection

Service Agreement

Key threshold if aggregate

generation is less than 67 of minimum load on the

feeder Other Screens review voltage quality reliability and safety to reduce the potential

need for Impact Studies

Relay control system must be well

defined to make SupplementalReview easier

20National Grid | July Interconnection Webinar | July 16 2020

Recent Improvements

Infrastructure List View-Can be found at the bottom of the home

page on the portal

Lists of all feeders in each jurisdiction (MA NY RI) that can be

sorted by Feeder Name Substation Transformer Name

Operating District Connected DG kWAC Pending DG kWAC

whether or not the Feeders are Registered with FERC

Link to

guide httpsngusforcecomservletservletFileDownloadfile=

0150W00000FKqNQ

Developers have access in portal to view muni WO for completion

21National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

For most Expedited applications a ldquoCommissioning Memordquo on

a company letterhead is provided in lieu of Witness Test

Commissioning test should consist of the following

1 Two (2) second shutdown when disconnect open test

2 Five (5) minutes before restart when disconnect is closed test

3 Confirm system matches As-built (include most recent revision

date of as built provided)

4 List the inverter relay frequency (Hz) and trip time settings

22National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

As Built Must be PE stamped and signed dated by person

that performed the commissioning test (Signature date

should match date of test)

Pictures Meter picture should show permanent plaque

(visible at eye level) that includes a warning about generator

installed

Pictures If the AC utility disconnect switch is not grouped

with and adjacent to the utility revenue meter then a

permanent plaque (visible at eye level) that clearly identifies

the location of the AC utility disconnect is required

23National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

Evidence of insurance is required for all projects gt 60kW in

MA and gt50kW in RI Refer to the ISA and Interconnection

Tariff for insurance requirements

Qualifying Facility documents

Schedule A (P-Rate) required for all QF projects

W9 (Only for projects gt60kW)

ACH (Only for projects gt60kW)

Supplier Enrollment Form (Only for projects gt60kW)

24National Grid | July Interconnection Webinar | July 16 2020

Metering Reminder

Projects greater than 60kW in MA and greater than 25kW in RI

require interval metering (Wireless or phone line)

Company needs a 4G wireless signal test on a Verizon network in

order to provide wireless metering

Phone lines must be dedicated and terminated at the meter

location Line must be 100 copper Fiber lines will not

communicate properly

These meters are long lead time items and prep time can be 6-8

weeks so it is important to work through this with your job owner

well in advance of when you intend to seek Authority to

Interconnect

Wireless test form httpsngusforcecomsarticleMA-

Interconnection-Documents

Standard Review

ProcessNat Mahattanasakul

05

26National Grid | July Interconnection Webinar | July 16 2020

Standard Criteria

Applies to

Projects that require Distribution System Impact Study (DSIS)

Large-scale DG projects

Generally greater than 500 kW but project specific

DG projects requiring System Modifications at the substation level

Non-listed inverters or generators other than PV

Induction Synchronous Asynchronous

Most CHP systems

All projects that do not qualify for the Simplified or Expedited process

27National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application

Application

Standard

Engineering Review

Impact StudyDetailed Study

Conditional Approval (to construct DG system)

Company Construction

Witness Test

Authorization to Interconnect

httpsngusforcecomsarticleMA-Complex-Standard-Application-Process

28National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Standard

Eligible Facilities Any DG

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Standard Process Initial Review 20 days

Send Impact Study Agreement 5 days

Complete Impact Study 55-60 days or by mutual agreement depending on complexity

Complete Detailed Study (if needed) 30 ndash 60 days or by mutual agreement depending on complexity

Send Executable Agreement (ISA) 15 days

Total Maximum Days 135160 days (200 days for Standard Complex)

Construction Schedule Varied

Witness Test10 days from the Companyrsquos approval of WT procedures or

by mutual agreement

29National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Impact Study will determine the level of impact on the Companyrsquos EPS and the required System

Modifications

Impact and Detailed Study (if applicable) will determine System Modifications required and cost

(Risk of Islanding)

ISO-NE Generator Notification Process will be required for applications that are greater than 1MW

but less than 5MW (ie PP5-1 or GNF) and a Proposed Plan Application (PPA) along with supporting Transmission System Impact Study (TSIS) will be required for applications 5MW or greater in size single or potentially in aggregate Size of project based on nameplate rating of

system

These requirements will add time to the DG Interconnection Process if there is an ASO hold If so

the DSIS will be placed on hold until the ISO-NE approval or determination is known likely at a point during the DSIS process

Interconnection Service Agreement (ISA) provided after Study completed or an Early ISA could be requested if Detailed Study is required

If substation modifications required Company has 60 BD for Study (MDPU 1320 ndash pg 50) or by mutual agreement if estimated construction cost greater than $1 million

30National Grid | July Interconnection Webinar | July 16 2020

New CEI Structure

Process Improvement

amp Future TopicsWill Kern

06

32National Grid | July Interconnection Webinar | July 16 2020

Process Improvement amp Future Topics

Potential webinar topics

Verizon initiatives

Hosting Capacity Maps

Metering

Mike Porcaro as Ombudsperson

Questions

07

34National Grid | July Interconnection Webinar | July 16 2020

Appendix Summary of Resources Documents amp Links

Distributed Generation Website ndash

httpswww9nationalgriduscommasselectrichomeenergyeffdistributed_gen

erationasp

Interconnection Process Resources ndash

httpswww9nationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

Storage Assistance -

httpsngusforcecomsarticleStorage-Assistance

DPU Interim Guidance for ESS -

httpsngusforcecomsarticleHow-to-Add-Energy-Storage-to-an-In-Progress-Application-in-Massachusetts

| [Insert document title] | [Insert date]

Page 2: National Grid Distributed Generation Seminar

2National Grid

This presentation has been prepared solely as an aid to discussions

between National Grid and interested stakeholders and should not be

used for any other purposes This presentation contains high-level

general information (not project specific) which may not be applicable in all

circumstances National Grid makes no guarantees of completeness

accuracy or usefulness of this information or warranties of any kind

whatsoever express or implied National Grid assumes no responsibility

or liability for any errors or omissions in the content Nothing contained in

this presentation shall constitute legal or business advice or counsel

No party is authorized to modify this presentation

The Webinar is being recorded

The information in this presentation could be affected by future revisions to

the Standards for Interconnection of Distributed Generation MPDU No

1320 (Tariff) in open docket DPU 19-55

Disclaimer

3National Grid

Agenda

| July Interconnection Webinar | July 16 2020

01 Welcome amp Opening Remarks ndash Will Kern

Safety message

COVID amp Force Majeure

2

02 Energy Storage Systems ndash Margaret Campbell 5

03

04

05

Interconnection Process Review

Simplified ndash Margaret Campbell

Expedited ndash Mike Armell

Standard ndash Nat Mahattanasakul

9

15

24

06 Process Improvement ndash Will Kern 30

07 QampA 32

4National Grid

Safety Moment Heat Exhaustion

bull Heat exhaustion symptoms include being pale ashen

or moist muscle cramps fatigue weakness or

dizziness

bull Be cognizant of compounded effects when working in

front of a grill youll get tired much faster than you

normally would based on the weather alone

bull Heat exhaustion can evolve into heat stroke quickly so

monitor symptoms and immediately move victims to

shaded or air-conditioned areas

bull Provide water or other cool nonalcoholic beverages

but dont force it

bull Seek medical attention immediately if body temperature

is above 103 or the individual is unresponsive

| July Interconnection Webinar | July 16 2020

5National Grid

COVID amp Force Majeure

| July Interconnection Webinar | July 16 2020

Payment extensions are no longer applicable

The company is working close to blue sky operations

however we will continue to monitor the situation as it develops

There have been very few Force Majeure impacts to cases which

were managed closely with the impacted developers

Payment due dates are not extended by Force Majeure per Tariff

Updates will continue to be posted

at httpsngusforcecomsarticleMA-Force-Majeure-

Declarations

Energy Storage

SystemsMargaret Campbell

02

7National Grid | July Interconnection Webinar | July 16 2020

New Storage Case Fields

New Application for Generation without Storage

New Application for Generation and Storage

New Application for Stand Alone Energy Storage

Add Storage to Existing Generation

AC-Coupled

DC-Coupled

Separate PCC

Electric Grid Only

Unrestricted Electric Grid or Generation

Restricted Electric Grid or Generation

Generation Only

Electric Grid Only

Unrestricted Electric Grid or Onsite Load

Restricted Electric Grid or Onsite Load

Onsite Load Only

AC Storage are included in the system size when determining if an application is simplified

expedited or standard so Storage AC kW is important to route application correctly

The Storage Charging Capability and Storage Discharging Capability values should match the

note on the one-line indicating how the storage will charge and discharge

8National Grid | July Interconnection Webinar | July 16 2020

Energy Storage System (ESS) Assets

The Inverter Information

This is the inverter for the ESS not the ESS itself

For DC coupled this is often the same inverter as the solar for example a SolarEdge inverter

For AC coupled this can be a separate inverter or the same as the ESS if it is a combined unit for example Powerwall

The ESS Information

Must be completed for AC and DC coupled batteries

The Storage Capacity per Device (kW DC) or (kW AC) is required (often

missed)

The Relay Information

Provides space for inputting ESS operating hours otherwise can be included in

the ESS information as an upload under special guidance

9National Grid | July Interconnection Webinar | July 16 2020

Energy Storage System (ESS) Form

The ESS Form is required and must be filled out electronically on the

portal (cannot be upload only)

Most of the fields on the ESS form are pre-populated from the Storage

case or values already entered on the case

If any of the pre-populated values look incorrect or need to be

updated please update the storage asset or reach to out to CEI

job owner thru Chatter

Link for knowledge page for adding a storage

asset httpsngusforcecomservletservletFileDownloadfile=0150W00000E

oHnv

Link for Storage Assistance httpsngusforcecomsarticleStorage-

Assistance

Simplified Review

ProcessMargaret Campbell

03

11National Grid | July Interconnection Webinar | July 16 2020

Simplified Criteria

UL Listed (1741 SA) inverter-based systems with power ratings of

15kW or less on a single phase service on a radial feed

UL Listed (1741 SA) inverter-based systems with power ratings of

25kW or less on a three phase service on a radial feed

The Simplified process does not apply for

Non-listed inverters or other generators (induction synchronous

asynchronous)

Aggregate generation capacity of listed inverters that exceed the

above-mentioned limits

Project that did not pass the Simplified process Screens

12National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Application

Simplified

Conditional Approval (to construct DG system)

Witness Test (completion package)

Authorization to Interconnect

httpswwwnationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

13National Grid | July Interconnection Webinar | July 16 2020

Simplified Review Path

Simplified Process

Eligible Facilities Listed Small Inverter

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Review of All Screens 15-20 days

Complete Supplemental Review (if needed) NA

Complete Standard Process Initial Review NA

Send Follow-on Studies CostAgreement NA

Complete Impact Study (if needed) NA

Complete Detailed Study (if needed) NA

Send Executable Agreement Done The agreement is part of the application

Total Maximum Days 25 days (30 in the case of failure of Screen 5)

Construction Schedule Varied

Witness Test Within 10 days from receipt of the Certificate of Completion or by mutual agreement

14National Grid | July Interconnection Webinar | July 16 2020

Common Holds or Concerns

Application

The application must match the customerrsquos account name address

account number and meter number

Wait to construct the system until after Conditional Approval is issued

After Conditional Approval

Complete the Service Upgrade Form so the work request can be

created and provided to the wire inspector at the before the inspection

Completion Package

Have Wire Inspection called in before submitting Completion

Documents

15National Grid | July Interconnection Webinar | July 16 2020

Recent Portal Improvements

Expedited Review

ProcessMike Armell

04

17National Grid | July Interconnection Webinar | July 16 2020

Expedited Criteria

Single phase customers with listed single-phase inverter based

systems with power ratings of gt15 kW on a radial feed

Three phase customers with listed three-phase inverter based

systems with power ratings of gt25kW on a radial feed

Any project that did not pass the Simplified process Screens

Non-Simplified projects that do not require an Impact Study

Maximum size supplemental review is based on review of

Screens

18National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application (if 500 kW or greater)

Application

Expedited

Engineering Review

Supplemental Review

Conditional Approval (to construct DG system)

Company Construction

Witness Test (where applicable)

Completion Document Review and Meter Set

Authorization to Interconnect

httpswwwnationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

19National Grid | July Interconnection Webinar | July 16 2020

Expedited Review Path

Expedited

Eligible Facilities Listed Inverter DG

Acknowledge Receipt of Application(3 days)

Review Application for Completeness10 days

Complete Review of All Screens25 days

Complete Supplemental Review (if needed)20 days or Standard Process

Send Executable Agreement10 days

Total Maximum Days 4565 days

Construction ScheduleVaried

Notice Witness TestWithin 10 days of receiving Certificate of

Completion or by mutual agreement

If any Screens are not passed the

Company may require a Supplemental Review Agreementbefore providing an Interconnection

Service Agreement

Key threshold if aggregate

generation is less than 67 of minimum load on the

feeder Other Screens review voltage quality reliability and safety to reduce the potential

need for Impact Studies

Relay control system must be well

defined to make SupplementalReview easier

20National Grid | July Interconnection Webinar | July 16 2020

Recent Improvements

Infrastructure List View-Can be found at the bottom of the home

page on the portal

Lists of all feeders in each jurisdiction (MA NY RI) that can be

sorted by Feeder Name Substation Transformer Name

Operating District Connected DG kWAC Pending DG kWAC

whether or not the Feeders are Registered with FERC

Link to

guide httpsngusforcecomservletservletFileDownloadfile=

0150W00000FKqNQ

Developers have access in portal to view muni WO for completion

21National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

For most Expedited applications a ldquoCommissioning Memordquo on

a company letterhead is provided in lieu of Witness Test

Commissioning test should consist of the following

1 Two (2) second shutdown when disconnect open test

2 Five (5) minutes before restart when disconnect is closed test

3 Confirm system matches As-built (include most recent revision

date of as built provided)

4 List the inverter relay frequency (Hz) and trip time settings

22National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

As Built Must be PE stamped and signed dated by person

that performed the commissioning test (Signature date

should match date of test)

Pictures Meter picture should show permanent plaque

(visible at eye level) that includes a warning about generator

installed

Pictures If the AC utility disconnect switch is not grouped

with and adjacent to the utility revenue meter then a

permanent plaque (visible at eye level) that clearly identifies

the location of the AC utility disconnect is required

23National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

Evidence of insurance is required for all projects gt 60kW in

MA and gt50kW in RI Refer to the ISA and Interconnection

Tariff for insurance requirements

Qualifying Facility documents

Schedule A (P-Rate) required for all QF projects

W9 (Only for projects gt60kW)

ACH (Only for projects gt60kW)

Supplier Enrollment Form (Only for projects gt60kW)

24National Grid | July Interconnection Webinar | July 16 2020

Metering Reminder

Projects greater than 60kW in MA and greater than 25kW in RI

require interval metering (Wireless or phone line)

Company needs a 4G wireless signal test on a Verizon network in

order to provide wireless metering

Phone lines must be dedicated and terminated at the meter

location Line must be 100 copper Fiber lines will not

communicate properly

These meters are long lead time items and prep time can be 6-8

weeks so it is important to work through this with your job owner

well in advance of when you intend to seek Authority to

Interconnect

Wireless test form httpsngusforcecomsarticleMA-

Interconnection-Documents

Standard Review

ProcessNat Mahattanasakul

05

26National Grid | July Interconnection Webinar | July 16 2020

Standard Criteria

Applies to

Projects that require Distribution System Impact Study (DSIS)

Large-scale DG projects

Generally greater than 500 kW but project specific

DG projects requiring System Modifications at the substation level

Non-listed inverters or generators other than PV

Induction Synchronous Asynchronous

Most CHP systems

All projects that do not qualify for the Simplified or Expedited process

27National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application

Application

Standard

Engineering Review

Impact StudyDetailed Study

Conditional Approval (to construct DG system)

Company Construction

Witness Test

Authorization to Interconnect

httpsngusforcecomsarticleMA-Complex-Standard-Application-Process

28National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Standard

Eligible Facilities Any DG

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Standard Process Initial Review 20 days

Send Impact Study Agreement 5 days

Complete Impact Study 55-60 days or by mutual agreement depending on complexity

Complete Detailed Study (if needed) 30 ndash 60 days or by mutual agreement depending on complexity

Send Executable Agreement (ISA) 15 days

Total Maximum Days 135160 days (200 days for Standard Complex)

Construction Schedule Varied

Witness Test10 days from the Companyrsquos approval of WT procedures or

by mutual agreement

29National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Impact Study will determine the level of impact on the Companyrsquos EPS and the required System

Modifications

Impact and Detailed Study (if applicable) will determine System Modifications required and cost

(Risk of Islanding)

ISO-NE Generator Notification Process will be required for applications that are greater than 1MW

but less than 5MW (ie PP5-1 or GNF) and a Proposed Plan Application (PPA) along with supporting Transmission System Impact Study (TSIS) will be required for applications 5MW or greater in size single or potentially in aggregate Size of project based on nameplate rating of

system

These requirements will add time to the DG Interconnection Process if there is an ASO hold If so

the DSIS will be placed on hold until the ISO-NE approval or determination is known likely at a point during the DSIS process

Interconnection Service Agreement (ISA) provided after Study completed or an Early ISA could be requested if Detailed Study is required

If substation modifications required Company has 60 BD for Study (MDPU 1320 ndash pg 50) or by mutual agreement if estimated construction cost greater than $1 million

30National Grid | July Interconnection Webinar | July 16 2020

New CEI Structure

Process Improvement

amp Future TopicsWill Kern

06

32National Grid | July Interconnection Webinar | July 16 2020

Process Improvement amp Future Topics

Potential webinar topics

Verizon initiatives

Hosting Capacity Maps

Metering

Mike Porcaro as Ombudsperson

Questions

07

34National Grid | July Interconnection Webinar | July 16 2020

Appendix Summary of Resources Documents amp Links

Distributed Generation Website ndash

httpswww9nationalgriduscommasselectrichomeenergyeffdistributed_gen

erationasp

Interconnection Process Resources ndash

httpswww9nationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

Storage Assistance -

httpsngusforcecomsarticleStorage-Assistance

DPU Interim Guidance for ESS -

httpsngusforcecomsarticleHow-to-Add-Energy-Storage-to-an-In-Progress-Application-in-Massachusetts

| [Insert document title] | [Insert date]

Page 3: National Grid Distributed Generation Seminar

3National Grid

Agenda

| July Interconnection Webinar | July 16 2020

01 Welcome amp Opening Remarks ndash Will Kern

Safety message

COVID amp Force Majeure

2

02 Energy Storage Systems ndash Margaret Campbell 5

03

04

05

Interconnection Process Review

Simplified ndash Margaret Campbell

Expedited ndash Mike Armell

Standard ndash Nat Mahattanasakul

9

15

24

06 Process Improvement ndash Will Kern 30

07 QampA 32

4National Grid

Safety Moment Heat Exhaustion

bull Heat exhaustion symptoms include being pale ashen

or moist muscle cramps fatigue weakness or

dizziness

bull Be cognizant of compounded effects when working in

front of a grill youll get tired much faster than you

normally would based on the weather alone

bull Heat exhaustion can evolve into heat stroke quickly so

monitor symptoms and immediately move victims to

shaded or air-conditioned areas

bull Provide water or other cool nonalcoholic beverages

but dont force it

bull Seek medical attention immediately if body temperature

is above 103 or the individual is unresponsive

| July Interconnection Webinar | July 16 2020

5National Grid

COVID amp Force Majeure

| July Interconnection Webinar | July 16 2020

Payment extensions are no longer applicable

The company is working close to blue sky operations

however we will continue to monitor the situation as it develops

There have been very few Force Majeure impacts to cases which

were managed closely with the impacted developers

Payment due dates are not extended by Force Majeure per Tariff

Updates will continue to be posted

at httpsngusforcecomsarticleMA-Force-Majeure-

Declarations

Energy Storage

SystemsMargaret Campbell

02

7National Grid | July Interconnection Webinar | July 16 2020

New Storage Case Fields

New Application for Generation without Storage

New Application for Generation and Storage

New Application for Stand Alone Energy Storage

Add Storage to Existing Generation

AC-Coupled

DC-Coupled

Separate PCC

Electric Grid Only

Unrestricted Electric Grid or Generation

Restricted Electric Grid or Generation

Generation Only

Electric Grid Only

Unrestricted Electric Grid or Onsite Load

Restricted Electric Grid or Onsite Load

Onsite Load Only

AC Storage are included in the system size when determining if an application is simplified

expedited or standard so Storage AC kW is important to route application correctly

The Storage Charging Capability and Storage Discharging Capability values should match the

note on the one-line indicating how the storage will charge and discharge

8National Grid | July Interconnection Webinar | July 16 2020

Energy Storage System (ESS) Assets

The Inverter Information

This is the inverter for the ESS not the ESS itself

For DC coupled this is often the same inverter as the solar for example a SolarEdge inverter

For AC coupled this can be a separate inverter or the same as the ESS if it is a combined unit for example Powerwall

The ESS Information

Must be completed for AC and DC coupled batteries

The Storage Capacity per Device (kW DC) or (kW AC) is required (often

missed)

The Relay Information

Provides space for inputting ESS operating hours otherwise can be included in

the ESS information as an upload under special guidance

9National Grid | July Interconnection Webinar | July 16 2020

Energy Storage System (ESS) Form

The ESS Form is required and must be filled out electronically on the

portal (cannot be upload only)

Most of the fields on the ESS form are pre-populated from the Storage

case or values already entered on the case

If any of the pre-populated values look incorrect or need to be

updated please update the storage asset or reach to out to CEI

job owner thru Chatter

Link for knowledge page for adding a storage

asset httpsngusforcecomservletservletFileDownloadfile=0150W00000E

oHnv

Link for Storage Assistance httpsngusforcecomsarticleStorage-

Assistance

Simplified Review

ProcessMargaret Campbell

03

11National Grid | July Interconnection Webinar | July 16 2020

Simplified Criteria

UL Listed (1741 SA) inverter-based systems with power ratings of

15kW or less on a single phase service on a radial feed

UL Listed (1741 SA) inverter-based systems with power ratings of

25kW or less on a three phase service on a radial feed

The Simplified process does not apply for

Non-listed inverters or other generators (induction synchronous

asynchronous)

Aggregate generation capacity of listed inverters that exceed the

above-mentioned limits

Project that did not pass the Simplified process Screens

12National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Application

Simplified

Conditional Approval (to construct DG system)

Witness Test (completion package)

Authorization to Interconnect

httpswwwnationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

13National Grid | July Interconnection Webinar | July 16 2020

Simplified Review Path

Simplified Process

Eligible Facilities Listed Small Inverter

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Review of All Screens 15-20 days

Complete Supplemental Review (if needed) NA

Complete Standard Process Initial Review NA

Send Follow-on Studies CostAgreement NA

Complete Impact Study (if needed) NA

Complete Detailed Study (if needed) NA

Send Executable Agreement Done The agreement is part of the application

Total Maximum Days 25 days (30 in the case of failure of Screen 5)

Construction Schedule Varied

Witness Test Within 10 days from receipt of the Certificate of Completion or by mutual agreement

14National Grid | July Interconnection Webinar | July 16 2020

Common Holds or Concerns

Application

The application must match the customerrsquos account name address

account number and meter number

Wait to construct the system until after Conditional Approval is issued

After Conditional Approval

Complete the Service Upgrade Form so the work request can be

created and provided to the wire inspector at the before the inspection

Completion Package

Have Wire Inspection called in before submitting Completion

Documents

15National Grid | July Interconnection Webinar | July 16 2020

Recent Portal Improvements

Expedited Review

ProcessMike Armell

04

17National Grid | July Interconnection Webinar | July 16 2020

Expedited Criteria

Single phase customers with listed single-phase inverter based

systems with power ratings of gt15 kW on a radial feed

Three phase customers with listed three-phase inverter based

systems with power ratings of gt25kW on a radial feed

Any project that did not pass the Simplified process Screens

Non-Simplified projects that do not require an Impact Study

Maximum size supplemental review is based on review of

Screens

18National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application (if 500 kW or greater)

Application

Expedited

Engineering Review

Supplemental Review

Conditional Approval (to construct DG system)

Company Construction

Witness Test (where applicable)

Completion Document Review and Meter Set

Authorization to Interconnect

httpswwwnationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

19National Grid | July Interconnection Webinar | July 16 2020

Expedited Review Path

Expedited

Eligible Facilities Listed Inverter DG

Acknowledge Receipt of Application(3 days)

Review Application for Completeness10 days

Complete Review of All Screens25 days

Complete Supplemental Review (if needed)20 days or Standard Process

Send Executable Agreement10 days

Total Maximum Days 4565 days

Construction ScheduleVaried

Notice Witness TestWithin 10 days of receiving Certificate of

Completion or by mutual agreement

If any Screens are not passed the

Company may require a Supplemental Review Agreementbefore providing an Interconnection

Service Agreement

Key threshold if aggregate

generation is less than 67 of minimum load on the

feeder Other Screens review voltage quality reliability and safety to reduce the potential

need for Impact Studies

Relay control system must be well

defined to make SupplementalReview easier

20National Grid | July Interconnection Webinar | July 16 2020

Recent Improvements

Infrastructure List View-Can be found at the bottom of the home

page on the portal

Lists of all feeders in each jurisdiction (MA NY RI) that can be

sorted by Feeder Name Substation Transformer Name

Operating District Connected DG kWAC Pending DG kWAC

whether or not the Feeders are Registered with FERC

Link to

guide httpsngusforcecomservletservletFileDownloadfile=

0150W00000FKqNQ

Developers have access in portal to view muni WO for completion

21National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

For most Expedited applications a ldquoCommissioning Memordquo on

a company letterhead is provided in lieu of Witness Test

Commissioning test should consist of the following

1 Two (2) second shutdown when disconnect open test

2 Five (5) minutes before restart when disconnect is closed test

3 Confirm system matches As-built (include most recent revision

date of as built provided)

4 List the inverter relay frequency (Hz) and trip time settings

22National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

As Built Must be PE stamped and signed dated by person

that performed the commissioning test (Signature date

should match date of test)

Pictures Meter picture should show permanent plaque

(visible at eye level) that includes a warning about generator

installed

Pictures If the AC utility disconnect switch is not grouped

with and adjacent to the utility revenue meter then a

permanent plaque (visible at eye level) that clearly identifies

the location of the AC utility disconnect is required

23National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

Evidence of insurance is required for all projects gt 60kW in

MA and gt50kW in RI Refer to the ISA and Interconnection

Tariff for insurance requirements

Qualifying Facility documents

Schedule A (P-Rate) required for all QF projects

W9 (Only for projects gt60kW)

ACH (Only for projects gt60kW)

Supplier Enrollment Form (Only for projects gt60kW)

24National Grid | July Interconnection Webinar | July 16 2020

Metering Reminder

Projects greater than 60kW in MA and greater than 25kW in RI

require interval metering (Wireless or phone line)

Company needs a 4G wireless signal test on a Verizon network in

order to provide wireless metering

Phone lines must be dedicated and terminated at the meter

location Line must be 100 copper Fiber lines will not

communicate properly

These meters are long lead time items and prep time can be 6-8

weeks so it is important to work through this with your job owner

well in advance of when you intend to seek Authority to

Interconnect

Wireless test form httpsngusforcecomsarticleMA-

Interconnection-Documents

Standard Review

ProcessNat Mahattanasakul

05

26National Grid | July Interconnection Webinar | July 16 2020

Standard Criteria

Applies to

Projects that require Distribution System Impact Study (DSIS)

Large-scale DG projects

Generally greater than 500 kW but project specific

DG projects requiring System Modifications at the substation level

Non-listed inverters or generators other than PV

Induction Synchronous Asynchronous

Most CHP systems

All projects that do not qualify for the Simplified or Expedited process

27National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application

Application

Standard

Engineering Review

Impact StudyDetailed Study

Conditional Approval (to construct DG system)

Company Construction

Witness Test

Authorization to Interconnect

httpsngusforcecomsarticleMA-Complex-Standard-Application-Process

28National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Standard

Eligible Facilities Any DG

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Standard Process Initial Review 20 days

Send Impact Study Agreement 5 days

Complete Impact Study 55-60 days or by mutual agreement depending on complexity

Complete Detailed Study (if needed) 30 ndash 60 days or by mutual agreement depending on complexity

Send Executable Agreement (ISA) 15 days

Total Maximum Days 135160 days (200 days for Standard Complex)

Construction Schedule Varied

Witness Test10 days from the Companyrsquos approval of WT procedures or

by mutual agreement

29National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Impact Study will determine the level of impact on the Companyrsquos EPS and the required System

Modifications

Impact and Detailed Study (if applicable) will determine System Modifications required and cost

(Risk of Islanding)

ISO-NE Generator Notification Process will be required for applications that are greater than 1MW

but less than 5MW (ie PP5-1 or GNF) and a Proposed Plan Application (PPA) along with supporting Transmission System Impact Study (TSIS) will be required for applications 5MW or greater in size single or potentially in aggregate Size of project based on nameplate rating of

system

These requirements will add time to the DG Interconnection Process if there is an ASO hold If so

the DSIS will be placed on hold until the ISO-NE approval or determination is known likely at a point during the DSIS process

Interconnection Service Agreement (ISA) provided after Study completed or an Early ISA could be requested if Detailed Study is required

If substation modifications required Company has 60 BD for Study (MDPU 1320 ndash pg 50) or by mutual agreement if estimated construction cost greater than $1 million

30National Grid | July Interconnection Webinar | July 16 2020

New CEI Structure

Process Improvement

amp Future TopicsWill Kern

06

32National Grid | July Interconnection Webinar | July 16 2020

Process Improvement amp Future Topics

Potential webinar topics

Verizon initiatives

Hosting Capacity Maps

Metering

Mike Porcaro as Ombudsperson

Questions

07

34National Grid | July Interconnection Webinar | July 16 2020

Appendix Summary of Resources Documents amp Links

Distributed Generation Website ndash

httpswww9nationalgriduscommasselectrichomeenergyeffdistributed_gen

erationasp

Interconnection Process Resources ndash

httpswww9nationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

Storage Assistance -

httpsngusforcecomsarticleStorage-Assistance

DPU Interim Guidance for ESS -

httpsngusforcecomsarticleHow-to-Add-Energy-Storage-to-an-In-Progress-Application-in-Massachusetts

| [Insert document title] | [Insert date]

Page 4: National Grid Distributed Generation Seminar

4National Grid

Safety Moment Heat Exhaustion

bull Heat exhaustion symptoms include being pale ashen

or moist muscle cramps fatigue weakness or

dizziness

bull Be cognizant of compounded effects when working in

front of a grill youll get tired much faster than you

normally would based on the weather alone

bull Heat exhaustion can evolve into heat stroke quickly so

monitor symptoms and immediately move victims to

shaded or air-conditioned areas

bull Provide water or other cool nonalcoholic beverages

but dont force it

bull Seek medical attention immediately if body temperature

is above 103 or the individual is unresponsive

| July Interconnection Webinar | July 16 2020

5National Grid

COVID amp Force Majeure

| July Interconnection Webinar | July 16 2020

Payment extensions are no longer applicable

The company is working close to blue sky operations

however we will continue to monitor the situation as it develops

There have been very few Force Majeure impacts to cases which

were managed closely with the impacted developers

Payment due dates are not extended by Force Majeure per Tariff

Updates will continue to be posted

at httpsngusforcecomsarticleMA-Force-Majeure-

Declarations

Energy Storage

SystemsMargaret Campbell

02

7National Grid | July Interconnection Webinar | July 16 2020

New Storage Case Fields

New Application for Generation without Storage

New Application for Generation and Storage

New Application for Stand Alone Energy Storage

Add Storage to Existing Generation

AC-Coupled

DC-Coupled

Separate PCC

Electric Grid Only

Unrestricted Electric Grid or Generation

Restricted Electric Grid or Generation

Generation Only

Electric Grid Only

Unrestricted Electric Grid or Onsite Load

Restricted Electric Grid or Onsite Load

Onsite Load Only

AC Storage are included in the system size when determining if an application is simplified

expedited or standard so Storage AC kW is important to route application correctly

The Storage Charging Capability and Storage Discharging Capability values should match the

note on the one-line indicating how the storage will charge and discharge

8National Grid | July Interconnection Webinar | July 16 2020

Energy Storage System (ESS) Assets

The Inverter Information

This is the inverter for the ESS not the ESS itself

For DC coupled this is often the same inverter as the solar for example a SolarEdge inverter

For AC coupled this can be a separate inverter or the same as the ESS if it is a combined unit for example Powerwall

The ESS Information

Must be completed for AC and DC coupled batteries

The Storage Capacity per Device (kW DC) or (kW AC) is required (often

missed)

The Relay Information

Provides space for inputting ESS operating hours otherwise can be included in

the ESS information as an upload under special guidance

9National Grid | July Interconnection Webinar | July 16 2020

Energy Storage System (ESS) Form

The ESS Form is required and must be filled out electronically on the

portal (cannot be upload only)

Most of the fields on the ESS form are pre-populated from the Storage

case or values already entered on the case

If any of the pre-populated values look incorrect or need to be

updated please update the storage asset or reach to out to CEI

job owner thru Chatter

Link for knowledge page for adding a storage

asset httpsngusforcecomservletservletFileDownloadfile=0150W00000E

oHnv

Link for Storage Assistance httpsngusforcecomsarticleStorage-

Assistance

Simplified Review

ProcessMargaret Campbell

03

11National Grid | July Interconnection Webinar | July 16 2020

Simplified Criteria

UL Listed (1741 SA) inverter-based systems with power ratings of

15kW or less on a single phase service on a radial feed

UL Listed (1741 SA) inverter-based systems with power ratings of

25kW or less on a three phase service on a radial feed

The Simplified process does not apply for

Non-listed inverters or other generators (induction synchronous

asynchronous)

Aggregate generation capacity of listed inverters that exceed the

above-mentioned limits

Project that did not pass the Simplified process Screens

12National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Application

Simplified

Conditional Approval (to construct DG system)

Witness Test (completion package)

Authorization to Interconnect

httpswwwnationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

13National Grid | July Interconnection Webinar | July 16 2020

Simplified Review Path

Simplified Process

Eligible Facilities Listed Small Inverter

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Review of All Screens 15-20 days

Complete Supplemental Review (if needed) NA

Complete Standard Process Initial Review NA

Send Follow-on Studies CostAgreement NA

Complete Impact Study (if needed) NA

Complete Detailed Study (if needed) NA

Send Executable Agreement Done The agreement is part of the application

Total Maximum Days 25 days (30 in the case of failure of Screen 5)

Construction Schedule Varied

Witness Test Within 10 days from receipt of the Certificate of Completion or by mutual agreement

14National Grid | July Interconnection Webinar | July 16 2020

Common Holds or Concerns

Application

The application must match the customerrsquos account name address

account number and meter number

Wait to construct the system until after Conditional Approval is issued

After Conditional Approval

Complete the Service Upgrade Form so the work request can be

created and provided to the wire inspector at the before the inspection

Completion Package

Have Wire Inspection called in before submitting Completion

Documents

15National Grid | July Interconnection Webinar | July 16 2020

Recent Portal Improvements

Expedited Review

ProcessMike Armell

04

17National Grid | July Interconnection Webinar | July 16 2020

Expedited Criteria

Single phase customers with listed single-phase inverter based

systems with power ratings of gt15 kW on a radial feed

Three phase customers with listed three-phase inverter based

systems with power ratings of gt25kW on a radial feed

Any project that did not pass the Simplified process Screens

Non-Simplified projects that do not require an Impact Study

Maximum size supplemental review is based on review of

Screens

18National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application (if 500 kW or greater)

Application

Expedited

Engineering Review

Supplemental Review

Conditional Approval (to construct DG system)

Company Construction

Witness Test (where applicable)

Completion Document Review and Meter Set

Authorization to Interconnect

httpswwwnationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

19National Grid | July Interconnection Webinar | July 16 2020

Expedited Review Path

Expedited

Eligible Facilities Listed Inverter DG

Acknowledge Receipt of Application(3 days)

Review Application for Completeness10 days

Complete Review of All Screens25 days

Complete Supplemental Review (if needed)20 days or Standard Process

Send Executable Agreement10 days

Total Maximum Days 4565 days

Construction ScheduleVaried

Notice Witness TestWithin 10 days of receiving Certificate of

Completion or by mutual agreement

If any Screens are not passed the

Company may require a Supplemental Review Agreementbefore providing an Interconnection

Service Agreement

Key threshold if aggregate

generation is less than 67 of minimum load on the

feeder Other Screens review voltage quality reliability and safety to reduce the potential

need for Impact Studies

Relay control system must be well

defined to make SupplementalReview easier

20National Grid | July Interconnection Webinar | July 16 2020

Recent Improvements

Infrastructure List View-Can be found at the bottom of the home

page on the portal

Lists of all feeders in each jurisdiction (MA NY RI) that can be

sorted by Feeder Name Substation Transformer Name

Operating District Connected DG kWAC Pending DG kWAC

whether or not the Feeders are Registered with FERC

Link to

guide httpsngusforcecomservletservletFileDownloadfile=

0150W00000FKqNQ

Developers have access in portal to view muni WO for completion

21National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

For most Expedited applications a ldquoCommissioning Memordquo on

a company letterhead is provided in lieu of Witness Test

Commissioning test should consist of the following

1 Two (2) second shutdown when disconnect open test

2 Five (5) minutes before restart when disconnect is closed test

3 Confirm system matches As-built (include most recent revision

date of as built provided)

4 List the inverter relay frequency (Hz) and trip time settings

22National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

As Built Must be PE stamped and signed dated by person

that performed the commissioning test (Signature date

should match date of test)

Pictures Meter picture should show permanent plaque

(visible at eye level) that includes a warning about generator

installed

Pictures If the AC utility disconnect switch is not grouped

with and adjacent to the utility revenue meter then a

permanent plaque (visible at eye level) that clearly identifies

the location of the AC utility disconnect is required

23National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

Evidence of insurance is required for all projects gt 60kW in

MA and gt50kW in RI Refer to the ISA and Interconnection

Tariff for insurance requirements

Qualifying Facility documents

Schedule A (P-Rate) required for all QF projects

W9 (Only for projects gt60kW)

ACH (Only for projects gt60kW)

Supplier Enrollment Form (Only for projects gt60kW)

24National Grid | July Interconnection Webinar | July 16 2020

Metering Reminder

Projects greater than 60kW in MA and greater than 25kW in RI

require interval metering (Wireless or phone line)

Company needs a 4G wireless signal test on a Verizon network in

order to provide wireless metering

Phone lines must be dedicated and terminated at the meter

location Line must be 100 copper Fiber lines will not

communicate properly

These meters are long lead time items and prep time can be 6-8

weeks so it is important to work through this with your job owner

well in advance of when you intend to seek Authority to

Interconnect

Wireless test form httpsngusforcecomsarticleMA-

Interconnection-Documents

Standard Review

ProcessNat Mahattanasakul

05

26National Grid | July Interconnection Webinar | July 16 2020

Standard Criteria

Applies to

Projects that require Distribution System Impact Study (DSIS)

Large-scale DG projects

Generally greater than 500 kW but project specific

DG projects requiring System Modifications at the substation level

Non-listed inverters or generators other than PV

Induction Synchronous Asynchronous

Most CHP systems

All projects that do not qualify for the Simplified or Expedited process

27National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application

Application

Standard

Engineering Review

Impact StudyDetailed Study

Conditional Approval (to construct DG system)

Company Construction

Witness Test

Authorization to Interconnect

httpsngusforcecomsarticleMA-Complex-Standard-Application-Process

28National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Standard

Eligible Facilities Any DG

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Standard Process Initial Review 20 days

Send Impact Study Agreement 5 days

Complete Impact Study 55-60 days or by mutual agreement depending on complexity

Complete Detailed Study (if needed) 30 ndash 60 days or by mutual agreement depending on complexity

Send Executable Agreement (ISA) 15 days

Total Maximum Days 135160 days (200 days for Standard Complex)

Construction Schedule Varied

Witness Test10 days from the Companyrsquos approval of WT procedures or

by mutual agreement

29National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Impact Study will determine the level of impact on the Companyrsquos EPS and the required System

Modifications

Impact and Detailed Study (if applicable) will determine System Modifications required and cost

(Risk of Islanding)

ISO-NE Generator Notification Process will be required for applications that are greater than 1MW

but less than 5MW (ie PP5-1 or GNF) and a Proposed Plan Application (PPA) along with supporting Transmission System Impact Study (TSIS) will be required for applications 5MW or greater in size single or potentially in aggregate Size of project based on nameplate rating of

system

These requirements will add time to the DG Interconnection Process if there is an ASO hold If so

the DSIS will be placed on hold until the ISO-NE approval or determination is known likely at a point during the DSIS process

Interconnection Service Agreement (ISA) provided after Study completed or an Early ISA could be requested if Detailed Study is required

If substation modifications required Company has 60 BD for Study (MDPU 1320 ndash pg 50) or by mutual agreement if estimated construction cost greater than $1 million

30National Grid | July Interconnection Webinar | July 16 2020

New CEI Structure

Process Improvement

amp Future TopicsWill Kern

06

32National Grid | July Interconnection Webinar | July 16 2020

Process Improvement amp Future Topics

Potential webinar topics

Verizon initiatives

Hosting Capacity Maps

Metering

Mike Porcaro as Ombudsperson

Questions

07

34National Grid | July Interconnection Webinar | July 16 2020

Appendix Summary of Resources Documents amp Links

Distributed Generation Website ndash

httpswww9nationalgriduscommasselectrichomeenergyeffdistributed_gen

erationasp

Interconnection Process Resources ndash

httpswww9nationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

Storage Assistance -

httpsngusforcecomsarticleStorage-Assistance

DPU Interim Guidance for ESS -

httpsngusforcecomsarticleHow-to-Add-Energy-Storage-to-an-In-Progress-Application-in-Massachusetts

| [Insert document title] | [Insert date]

Page 5: National Grid Distributed Generation Seminar

5National Grid

COVID amp Force Majeure

| July Interconnection Webinar | July 16 2020

Payment extensions are no longer applicable

The company is working close to blue sky operations

however we will continue to monitor the situation as it develops

There have been very few Force Majeure impacts to cases which

were managed closely with the impacted developers

Payment due dates are not extended by Force Majeure per Tariff

Updates will continue to be posted

at httpsngusforcecomsarticleMA-Force-Majeure-

Declarations

Energy Storage

SystemsMargaret Campbell

02

7National Grid | July Interconnection Webinar | July 16 2020

New Storage Case Fields

New Application for Generation without Storage

New Application for Generation and Storage

New Application for Stand Alone Energy Storage

Add Storage to Existing Generation

AC-Coupled

DC-Coupled

Separate PCC

Electric Grid Only

Unrestricted Electric Grid or Generation

Restricted Electric Grid or Generation

Generation Only

Electric Grid Only

Unrestricted Electric Grid or Onsite Load

Restricted Electric Grid or Onsite Load

Onsite Load Only

AC Storage are included in the system size when determining if an application is simplified

expedited or standard so Storage AC kW is important to route application correctly

The Storage Charging Capability and Storage Discharging Capability values should match the

note on the one-line indicating how the storage will charge and discharge

8National Grid | July Interconnection Webinar | July 16 2020

Energy Storage System (ESS) Assets

The Inverter Information

This is the inverter for the ESS not the ESS itself

For DC coupled this is often the same inverter as the solar for example a SolarEdge inverter

For AC coupled this can be a separate inverter or the same as the ESS if it is a combined unit for example Powerwall

The ESS Information

Must be completed for AC and DC coupled batteries

The Storage Capacity per Device (kW DC) or (kW AC) is required (often

missed)

The Relay Information

Provides space for inputting ESS operating hours otherwise can be included in

the ESS information as an upload under special guidance

9National Grid | July Interconnection Webinar | July 16 2020

Energy Storage System (ESS) Form

The ESS Form is required and must be filled out electronically on the

portal (cannot be upload only)

Most of the fields on the ESS form are pre-populated from the Storage

case or values already entered on the case

If any of the pre-populated values look incorrect or need to be

updated please update the storage asset or reach to out to CEI

job owner thru Chatter

Link for knowledge page for adding a storage

asset httpsngusforcecomservletservletFileDownloadfile=0150W00000E

oHnv

Link for Storage Assistance httpsngusforcecomsarticleStorage-

Assistance

Simplified Review

ProcessMargaret Campbell

03

11National Grid | July Interconnection Webinar | July 16 2020

Simplified Criteria

UL Listed (1741 SA) inverter-based systems with power ratings of

15kW or less on a single phase service on a radial feed

UL Listed (1741 SA) inverter-based systems with power ratings of

25kW or less on a three phase service on a radial feed

The Simplified process does not apply for

Non-listed inverters or other generators (induction synchronous

asynchronous)

Aggregate generation capacity of listed inverters that exceed the

above-mentioned limits

Project that did not pass the Simplified process Screens

12National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Application

Simplified

Conditional Approval (to construct DG system)

Witness Test (completion package)

Authorization to Interconnect

httpswwwnationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

13National Grid | July Interconnection Webinar | July 16 2020

Simplified Review Path

Simplified Process

Eligible Facilities Listed Small Inverter

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Review of All Screens 15-20 days

Complete Supplemental Review (if needed) NA

Complete Standard Process Initial Review NA

Send Follow-on Studies CostAgreement NA

Complete Impact Study (if needed) NA

Complete Detailed Study (if needed) NA

Send Executable Agreement Done The agreement is part of the application

Total Maximum Days 25 days (30 in the case of failure of Screen 5)

Construction Schedule Varied

Witness Test Within 10 days from receipt of the Certificate of Completion or by mutual agreement

14National Grid | July Interconnection Webinar | July 16 2020

Common Holds or Concerns

Application

The application must match the customerrsquos account name address

account number and meter number

Wait to construct the system until after Conditional Approval is issued

After Conditional Approval

Complete the Service Upgrade Form so the work request can be

created and provided to the wire inspector at the before the inspection

Completion Package

Have Wire Inspection called in before submitting Completion

Documents

15National Grid | July Interconnection Webinar | July 16 2020

Recent Portal Improvements

Expedited Review

ProcessMike Armell

04

17National Grid | July Interconnection Webinar | July 16 2020

Expedited Criteria

Single phase customers with listed single-phase inverter based

systems with power ratings of gt15 kW on a radial feed

Three phase customers with listed three-phase inverter based

systems with power ratings of gt25kW on a radial feed

Any project that did not pass the Simplified process Screens

Non-Simplified projects that do not require an Impact Study

Maximum size supplemental review is based on review of

Screens

18National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application (if 500 kW or greater)

Application

Expedited

Engineering Review

Supplemental Review

Conditional Approval (to construct DG system)

Company Construction

Witness Test (where applicable)

Completion Document Review and Meter Set

Authorization to Interconnect

httpswwwnationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

19National Grid | July Interconnection Webinar | July 16 2020

Expedited Review Path

Expedited

Eligible Facilities Listed Inverter DG

Acknowledge Receipt of Application(3 days)

Review Application for Completeness10 days

Complete Review of All Screens25 days

Complete Supplemental Review (if needed)20 days or Standard Process

Send Executable Agreement10 days

Total Maximum Days 4565 days

Construction ScheduleVaried

Notice Witness TestWithin 10 days of receiving Certificate of

Completion or by mutual agreement

If any Screens are not passed the

Company may require a Supplemental Review Agreementbefore providing an Interconnection

Service Agreement

Key threshold if aggregate

generation is less than 67 of minimum load on the

feeder Other Screens review voltage quality reliability and safety to reduce the potential

need for Impact Studies

Relay control system must be well

defined to make SupplementalReview easier

20National Grid | July Interconnection Webinar | July 16 2020

Recent Improvements

Infrastructure List View-Can be found at the bottom of the home

page on the portal

Lists of all feeders in each jurisdiction (MA NY RI) that can be

sorted by Feeder Name Substation Transformer Name

Operating District Connected DG kWAC Pending DG kWAC

whether or not the Feeders are Registered with FERC

Link to

guide httpsngusforcecomservletservletFileDownloadfile=

0150W00000FKqNQ

Developers have access in portal to view muni WO for completion

21National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

For most Expedited applications a ldquoCommissioning Memordquo on

a company letterhead is provided in lieu of Witness Test

Commissioning test should consist of the following

1 Two (2) second shutdown when disconnect open test

2 Five (5) minutes before restart when disconnect is closed test

3 Confirm system matches As-built (include most recent revision

date of as built provided)

4 List the inverter relay frequency (Hz) and trip time settings

22National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

As Built Must be PE stamped and signed dated by person

that performed the commissioning test (Signature date

should match date of test)

Pictures Meter picture should show permanent plaque

(visible at eye level) that includes a warning about generator

installed

Pictures If the AC utility disconnect switch is not grouped

with and adjacent to the utility revenue meter then a

permanent plaque (visible at eye level) that clearly identifies

the location of the AC utility disconnect is required

23National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

Evidence of insurance is required for all projects gt 60kW in

MA and gt50kW in RI Refer to the ISA and Interconnection

Tariff for insurance requirements

Qualifying Facility documents

Schedule A (P-Rate) required for all QF projects

W9 (Only for projects gt60kW)

ACH (Only for projects gt60kW)

Supplier Enrollment Form (Only for projects gt60kW)

24National Grid | July Interconnection Webinar | July 16 2020

Metering Reminder

Projects greater than 60kW in MA and greater than 25kW in RI

require interval metering (Wireless or phone line)

Company needs a 4G wireless signal test on a Verizon network in

order to provide wireless metering

Phone lines must be dedicated and terminated at the meter

location Line must be 100 copper Fiber lines will not

communicate properly

These meters are long lead time items and prep time can be 6-8

weeks so it is important to work through this with your job owner

well in advance of when you intend to seek Authority to

Interconnect

Wireless test form httpsngusforcecomsarticleMA-

Interconnection-Documents

Standard Review

ProcessNat Mahattanasakul

05

26National Grid | July Interconnection Webinar | July 16 2020

Standard Criteria

Applies to

Projects that require Distribution System Impact Study (DSIS)

Large-scale DG projects

Generally greater than 500 kW but project specific

DG projects requiring System Modifications at the substation level

Non-listed inverters or generators other than PV

Induction Synchronous Asynchronous

Most CHP systems

All projects that do not qualify for the Simplified or Expedited process

27National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application

Application

Standard

Engineering Review

Impact StudyDetailed Study

Conditional Approval (to construct DG system)

Company Construction

Witness Test

Authorization to Interconnect

httpsngusforcecomsarticleMA-Complex-Standard-Application-Process

28National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Standard

Eligible Facilities Any DG

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Standard Process Initial Review 20 days

Send Impact Study Agreement 5 days

Complete Impact Study 55-60 days or by mutual agreement depending on complexity

Complete Detailed Study (if needed) 30 ndash 60 days or by mutual agreement depending on complexity

Send Executable Agreement (ISA) 15 days

Total Maximum Days 135160 days (200 days for Standard Complex)

Construction Schedule Varied

Witness Test10 days from the Companyrsquos approval of WT procedures or

by mutual agreement

29National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Impact Study will determine the level of impact on the Companyrsquos EPS and the required System

Modifications

Impact and Detailed Study (if applicable) will determine System Modifications required and cost

(Risk of Islanding)

ISO-NE Generator Notification Process will be required for applications that are greater than 1MW

but less than 5MW (ie PP5-1 or GNF) and a Proposed Plan Application (PPA) along with supporting Transmission System Impact Study (TSIS) will be required for applications 5MW or greater in size single or potentially in aggregate Size of project based on nameplate rating of

system

These requirements will add time to the DG Interconnection Process if there is an ASO hold If so

the DSIS will be placed on hold until the ISO-NE approval or determination is known likely at a point during the DSIS process

Interconnection Service Agreement (ISA) provided after Study completed or an Early ISA could be requested if Detailed Study is required

If substation modifications required Company has 60 BD for Study (MDPU 1320 ndash pg 50) or by mutual agreement if estimated construction cost greater than $1 million

30National Grid | July Interconnection Webinar | July 16 2020

New CEI Structure

Process Improvement

amp Future TopicsWill Kern

06

32National Grid | July Interconnection Webinar | July 16 2020

Process Improvement amp Future Topics

Potential webinar topics

Verizon initiatives

Hosting Capacity Maps

Metering

Mike Porcaro as Ombudsperson

Questions

07

34National Grid | July Interconnection Webinar | July 16 2020

Appendix Summary of Resources Documents amp Links

Distributed Generation Website ndash

httpswww9nationalgriduscommasselectrichomeenergyeffdistributed_gen

erationasp

Interconnection Process Resources ndash

httpswww9nationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

Storage Assistance -

httpsngusforcecomsarticleStorage-Assistance

DPU Interim Guidance for ESS -

httpsngusforcecomsarticleHow-to-Add-Energy-Storage-to-an-In-Progress-Application-in-Massachusetts

| [Insert document title] | [Insert date]

Page 6: National Grid Distributed Generation Seminar

Energy Storage

SystemsMargaret Campbell

02

7National Grid | July Interconnection Webinar | July 16 2020

New Storage Case Fields

New Application for Generation without Storage

New Application for Generation and Storage

New Application for Stand Alone Energy Storage

Add Storage to Existing Generation

AC-Coupled

DC-Coupled

Separate PCC

Electric Grid Only

Unrestricted Electric Grid or Generation

Restricted Electric Grid or Generation

Generation Only

Electric Grid Only

Unrestricted Electric Grid or Onsite Load

Restricted Electric Grid or Onsite Load

Onsite Load Only

AC Storage are included in the system size when determining if an application is simplified

expedited or standard so Storage AC kW is important to route application correctly

The Storage Charging Capability and Storage Discharging Capability values should match the

note on the one-line indicating how the storage will charge and discharge

8National Grid | July Interconnection Webinar | July 16 2020

Energy Storage System (ESS) Assets

The Inverter Information

This is the inverter for the ESS not the ESS itself

For DC coupled this is often the same inverter as the solar for example a SolarEdge inverter

For AC coupled this can be a separate inverter or the same as the ESS if it is a combined unit for example Powerwall

The ESS Information

Must be completed for AC and DC coupled batteries

The Storage Capacity per Device (kW DC) or (kW AC) is required (often

missed)

The Relay Information

Provides space for inputting ESS operating hours otherwise can be included in

the ESS information as an upload under special guidance

9National Grid | July Interconnection Webinar | July 16 2020

Energy Storage System (ESS) Form

The ESS Form is required and must be filled out electronically on the

portal (cannot be upload only)

Most of the fields on the ESS form are pre-populated from the Storage

case or values already entered on the case

If any of the pre-populated values look incorrect or need to be

updated please update the storage asset or reach to out to CEI

job owner thru Chatter

Link for knowledge page for adding a storage

asset httpsngusforcecomservletservletFileDownloadfile=0150W00000E

oHnv

Link for Storage Assistance httpsngusforcecomsarticleStorage-

Assistance

Simplified Review

ProcessMargaret Campbell

03

11National Grid | July Interconnection Webinar | July 16 2020

Simplified Criteria

UL Listed (1741 SA) inverter-based systems with power ratings of

15kW or less on a single phase service on a radial feed

UL Listed (1741 SA) inverter-based systems with power ratings of

25kW or less on a three phase service on a radial feed

The Simplified process does not apply for

Non-listed inverters or other generators (induction synchronous

asynchronous)

Aggregate generation capacity of listed inverters that exceed the

above-mentioned limits

Project that did not pass the Simplified process Screens

12National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Application

Simplified

Conditional Approval (to construct DG system)

Witness Test (completion package)

Authorization to Interconnect

httpswwwnationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

13National Grid | July Interconnection Webinar | July 16 2020

Simplified Review Path

Simplified Process

Eligible Facilities Listed Small Inverter

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Review of All Screens 15-20 days

Complete Supplemental Review (if needed) NA

Complete Standard Process Initial Review NA

Send Follow-on Studies CostAgreement NA

Complete Impact Study (if needed) NA

Complete Detailed Study (if needed) NA

Send Executable Agreement Done The agreement is part of the application

Total Maximum Days 25 days (30 in the case of failure of Screen 5)

Construction Schedule Varied

Witness Test Within 10 days from receipt of the Certificate of Completion or by mutual agreement

14National Grid | July Interconnection Webinar | July 16 2020

Common Holds or Concerns

Application

The application must match the customerrsquos account name address

account number and meter number

Wait to construct the system until after Conditional Approval is issued

After Conditional Approval

Complete the Service Upgrade Form so the work request can be

created and provided to the wire inspector at the before the inspection

Completion Package

Have Wire Inspection called in before submitting Completion

Documents

15National Grid | July Interconnection Webinar | July 16 2020

Recent Portal Improvements

Expedited Review

ProcessMike Armell

04

17National Grid | July Interconnection Webinar | July 16 2020

Expedited Criteria

Single phase customers with listed single-phase inverter based

systems with power ratings of gt15 kW on a radial feed

Three phase customers with listed three-phase inverter based

systems with power ratings of gt25kW on a radial feed

Any project that did not pass the Simplified process Screens

Non-Simplified projects that do not require an Impact Study

Maximum size supplemental review is based on review of

Screens

18National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application (if 500 kW or greater)

Application

Expedited

Engineering Review

Supplemental Review

Conditional Approval (to construct DG system)

Company Construction

Witness Test (where applicable)

Completion Document Review and Meter Set

Authorization to Interconnect

httpswwwnationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

19National Grid | July Interconnection Webinar | July 16 2020

Expedited Review Path

Expedited

Eligible Facilities Listed Inverter DG

Acknowledge Receipt of Application(3 days)

Review Application for Completeness10 days

Complete Review of All Screens25 days

Complete Supplemental Review (if needed)20 days or Standard Process

Send Executable Agreement10 days

Total Maximum Days 4565 days

Construction ScheduleVaried

Notice Witness TestWithin 10 days of receiving Certificate of

Completion or by mutual agreement

If any Screens are not passed the

Company may require a Supplemental Review Agreementbefore providing an Interconnection

Service Agreement

Key threshold if aggregate

generation is less than 67 of minimum load on the

feeder Other Screens review voltage quality reliability and safety to reduce the potential

need for Impact Studies

Relay control system must be well

defined to make SupplementalReview easier

20National Grid | July Interconnection Webinar | July 16 2020

Recent Improvements

Infrastructure List View-Can be found at the bottom of the home

page on the portal

Lists of all feeders in each jurisdiction (MA NY RI) that can be

sorted by Feeder Name Substation Transformer Name

Operating District Connected DG kWAC Pending DG kWAC

whether or not the Feeders are Registered with FERC

Link to

guide httpsngusforcecomservletservletFileDownloadfile=

0150W00000FKqNQ

Developers have access in portal to view muni WO for completion

21National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

For most Expedited applications a ldquoCommissioning Memordquo on

a company letterhead is provided in lieu of Witness Test

Commissioning test should consist of the following

1 Two (2) second shutdown when disconnect open test

2 Five (5) minutes before restart when disconnect is closed test

3 Confirm system matches As-built (include most recent revision

date of as built provided)

4 List the inverter relay frequency (Hz) and trip time settings

22National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

As Built Must be PE stamped and signed dated by person

that performed the commissioning test (Signature date

should match date of test)

Pictures Meter picture should show permanent plaque

(visible at eye level) that includes a warning about generator

installed

Pictures If the AC utility disconnect switch is not grouped

with and adjacent to the utility revenue meter then a

permanent plaque (visible at eye level) that clearly identifies

the location of the AC utility disconnect is required

23National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

Evidence of insurance is required for all projects gt 60kW in

MA and gt50kW in RI Refer to the ISA and Interconnection

Tariff for insurance requirements

Qualifying Facility documents

Schedule A (P-Rate) required for all QF projects

W9 (Only for projects gt60kW)

ACH (Only for projects gt60kW)

Supplier Enrollment Form (Only for projects gt60kW)

24National Grid | July Interconnection Webinar | July 16 2020

Metering Reminder

Projects greater than 60kW in MA and greater than 25kW in RI

require interval metering (Wireless or phone line)

Company needs a 4G wireless signal test on a Verizon network in

order to provide wireless metering

Phone lines must be dedicated and terminated at the meter

location Line must be 100 copper Fiber lines will not

communicate properly

These meters are long lead time items and prep time can be 6-8

weeks so it is important to work through this with your job owner

well in advance of when you intend to seek Authority to

Interconnect

Wireless test form httpsngusforcecomsarticleMA-

Interconnection-Documents

Standard Review

ProcessNat Mahattanasakul

05

26National Grid | July Interconnection Webinar | July 16 2020

Standard Criteria

Applies to

Projects that require Distribution System Impact Study (DSIS)

Large-scale DG projects

Generally greater than 500 kW but project specific

DG projects requiring System Modifications at the substation level

Non-listed inverters or generators other than PV

Induction Synchronous Asynchronous

Most CHP systems

All projects that do not qualify for the Simplified or Expedited process

27National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application

Application

Standard

Engineering Review

Impact StudyDetailed Study

Conditional Approval (to construct DG system)

Company Construction

Witness Test

Authorization to Interconnect

httpsngusforcecomsarticleMA-Complex-Standard-Application-Process

28National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Standard

Eligible Facilities Any DG

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Standard Process Initial Review 20 days

Send Impact Study Agreement 5 days

Complete Impact Study 55-60 days or by mutual agreement depending on complexity

Complete Detailed Study (if needed) 30 ndash 60 days or by mutual agreement depending on complexity

Send Executable Agreement (ISA) 15 days

Total Maximum Days 135160 days (200 days for Standard Complex)

Construction Schedule Varied

Witness Test10 days from the Companyrsquos approval of WT procedures or

by mutual agreement

29National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Impact Study will determine the level of impact on the Companyrsquos EPS and the required System

Modifications

Impact and Detailed Study (if applicable) will determine System Modifications required and cost

(Risk of Islanding)

ISO-NE Generator Notification Process will be required for applications that are greater than 1MW

but less than 5MW (ie PP5-1 or GNF) and a Proposed Plan Application (PPA) along with supporting Transmission System Impact Study (TSIS) will be required for applications 5MW or greater in size single or potentially in aggregate Size of project based on nameplate rating of

system

These requirements will add time to the DG Interconnection Process if there is an ASO hold If so

the DSIS will be placed on hold until the ISO-NE approval or determination is known likely at a point during the DSIS process

Interconnection Service Agreement (ISA) provided after Study completed or an Early ISA could be requested if Detailed Study is required

If substation modifications required Company has 60 BD for Study (MDPU 1320 ndash pg 50) or by mutual agreement if estimated construction cost greater than $1 million

30National Grid | July Interconnection Webinar | July 16 2020

New CEI Structure

Process Improvement

amp Future TopicsWill Kern

06

32National Grid | July Interconnection Webinar | July 16 2020

Process Improvement amp Future Topics

Potential webinar topics

Verizon initiatives

Hosting Capacity Maps

Metering

Mike Porcaro as Ombudsperson

Questions

07

34National Grid | July Interconnection Webinar | July 16 2020

Appendix Summary of Resources Documents amp Links

Distributed Generation Website ndash

httpswww9nationalgriduscommasselectrichomeenergyeffdistributed_gen

erationasp

Interconnection Process Resources ndash

httpswww9nationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

Storage Assistance -

httpsngusforcecomsarticleStorage-Assistance

DPU Interim Guidance for ESS -

httpsngusforcecomsarticleHow-to-Add-Energy-Storage-to-an-In-Progress-Application-in-Massachusetts

| [Insert document title] | [Insert date]

Page 7: National Grid Distributed Generation Seminar

7National Grid | July Interconnection Webinar | July 16 2020

New Storage Case Fields

New Application for Generation without Storage

New Application for Generation and Storage

New Application for Stand Alone Energy Storage

Add Storage to Existing Generation

AC-Coupled

DC-Coupled

Separate PCC

Electric Grid Only

Unrestricted Electric Grid or Generation

Restricted Electric Grid or Generation

Generation Only

Electric Grid Only

Unrestricted Electric Grid or Onsite Load

Restricted Electric Grid or Onsite Load

Onsite Load Only

AC Storage are included in the system size when determining if an application is simplified

expedited or standard so Storage AC kW is important to route application correctly

The Storage Charging Capability and Storage Discharging Capability values should match the

note on the one-line indicating how the storage will charge and discharge

8National Grid | July Interconnection Webinar | July 16 2020

Energy Storage System (ESS) Assets

The Inverter Information

This is the inverter for the ESS not the ESS itself

For DC coupled this is often the same inverter as the solar for example a SolarEdge inverter

For AC coupled this can be a separate inverter or the same as the ESS if it is a combined unit for example Powerwall

The ESS Information

Must be completed for AC and DC coupled batteries

The Storage Capacity per Device (kW DC) or (kW AC) is required (often

missed)

The Relay Information

Provides space for inputting ESS operating hours otherwise can be included in

the ESS information as an upload under special guidance

9National Grid | July Interconnection Webinar | July 16 2020

Energy Storage System (ESS) Form

The ESS Form is required and must be filled out electronically on the

portal (cannot be upload only)

Most of the fields on the ESS form are pre-populated from the Storage

case or values already entered on the case

If any of the pre-populated values look incorrect or need to be

updated please update the storage asset or reach to out to CEI

job owner thru Chatter

Link for knowledge page for adding a storage

asset httpsngusforcecomservletservletFileDownloadfile=0150W00000E

oHnv

Link for Storage Assistance httpsngusforcecomsarticleStorage-

Assistance

Simplified Review

ProcessMargaret Campbell

03

11National Grid | July Interconnection Webinar | July 16 2020

Simplified Criteria

UL Listed (1741 SA) inverter-based systems with power ratings of

15kW or less on a single phase service on a radial feed

UL Listed (1741 SA) inverter-based systems with power ratings of

25kW or less on a three phase service on a radial feed

The Simplified process does not apply for

Non-listed inverters or other generators (induction synchronous

asynchronous)

Aggregate generation capacity of listed inverters that exceed the

above-mentioned limits

Project that did not pass the Simplified process Screens

12National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Application

Simplified

Conditional Approval (to construct DG system)

Witness Test (completion package)

Authorization to Interconnect

httpswwwnationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

13National Grid | July Interconnection Webinar | July 16 2020

Simplified Review Path

Simplified Process

Eligible Facilities Listed Small Inverter

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Review of All Screens 15-20 days

Complete Supplemental Review (if needed) NA

Complete Standard Process Initial Review NA

Send Follow-on Studies CostAgreement NA

Complete Impact Study (if needed) NA

Complete Detailed Study (if needed) NA

Send Executable Agreement Done The agreement is part of the application

Total Maximum Days 25 days (30 in the case of failure of Screen 5)

Construction Schedule Varied

Witness Test Within 10 days from receipt of the Certificate of Completion or by mutual agreement

14National Grid | July Interconnection Webinar | July 16 2020

Common Holds or Concerns

Application

The application must match the customerrsquos account name address

account number and meter number

Wait to construct the system until after Conditional Approval is issued

After Conditional Approval

Complete the Service Upgrade Form so the work request can be

created and provided to the wire inspector at the before the inspection

Completion Package

Have Wire Inspection called in before submitting Completion

Documents

15National Grid | July Interconnection Webinar | July 16 2020

Recent Portal Improvements

Expedited Review

ProcessMike Armell

04

17National Grid | July Interconnection Webinar | July 16 2020

Expedited Criteria

Single phase customers with listed single-phase inverter based

systems with power ratings of gt15 kW on a radial feed

Three phase customers with listed three-phase inverter based

systems with power ratings of gt25kW on a radial feed

Any project that did not pass the Simplified process Screens

Non-Simplified projects that do not require an Impact Study

Maximum size supplemental review is based on review of

Screens

18National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application (if 500 kW or greater)

Application

Expedited

Engineering Review

Supplemental Review

Conditional Approval (to construct DG system)

Company Construction

Witness Test (where applicable)

Completion Document Review and Meter Set

Authorization to Interconnect

httpswwwnationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

19National Grid | July Interconnection Webinar | July 16 2020

Expedited Review Path

Expedited

Eligible Facilities Listed Inverter DG

Acknowledge Receipt of Application(3 days)

Review Application for Completeness10 days

Complete Review of All Screens25 days

Complete Supplemental Review (if needed)20 days or Standard Process

Send Executable Agreement10 days

Total Maximum Days 4565 days

Construction ScheduleVaried

Notice Witness TestWithin 10 days of receiving Certificate of

Completion or by mutual agreement

If any Screens are not passed the

Company may require a Supplemental Review Agreementbefore providing an Interconnection

Service Agreement

Key threshold if aggregate

generation is less than 67 of minimum load on the

feeder Other Screens review voltage quality reliability and safety to reduce the potential

need for Impact Studies

Relay control system must be well

defined to make SupplementalReview easier

20National Grid | July Interconnection Webinar | July 16 2020

Recent Improvements

Infrastructure List View-Can be found at the bottom of the home

page on the portal

Lists of all feeders in each jurisdiction (MA NY RI) that can be

sorted by Feeder Name Substation Transformer Name

Operating District Connected DG kWAC Pending DG kWAC

whether or not the Feeders are Registered with FERC

Link to

guide httpsngusforcecomservletservletFileDownloadfile=

0150W00000FKqNQ

Developers have access in portal to view muni WO for completion

21National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

For most Expedited applications a ldquoCommissioning Memordquo on

a company letterhead is provided in lieu of Witness Test

Commissioning test should consist of the following

1 Two (2) second shutdown when disconnect open test

2 Five (5) minutes before restart when disconnect is closed test

3 Confirm system matches As-built (include most recent revision

date of as built provided)

4 List the inverter relay frequency (Hz) and trip time settings

22National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

As Built Must be PE stamped and signed dated by person

that performed the commissioning test (Signature date

should match date of test)

Pictures Meter picture should show permanent plaque

(visible at eye level) that includes a warning about generator

installed

Pictures If the AC utility disconnect switch is not grouped

with and adjacent to the utility revenue meter then a

permanent plaque (visible at eye level) that clearly identifies

the location of the AC utility disconnect is required

23National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

Evidence of insurance is required for all projects gt 60kW in

MA and gt50kW in RI Refer to the ISA and Interconnection

Tariff for insurance requirements

Qualifying Facility documents

Schedule A (P-Rate) required for all QF projects

W9 (Only for projects gt60kW)

ACH (Only for projects gt60kW)

Supplier Enrollment Form (Only for projects gt60kW)

24National Grid | July Interconnection Webinar | July 16 2020

Metering Reminder

Projects greater than 60kW in MA and greater than 25kW in RI

require interval metering (Wireless or phone line)

Company needs a 4G wireless signal test on a Verizon network in

order to provide wireless metering

Phone lines must be dedicated and terminated at the meter

location Line must be 100 copper Fiber lines will not

communicate properly

These meters are long lead time items and prep time can be 6-8

weeks so it is important to work through this with your job owner

well in advance of when you intend to seek Authority to

Interconnect

Wireless test form httpsngusforcecomsarticleMA-

Interconnection-Documents

Standard Review

ProcessNat Mahattanasakul

05

26National Grid | July Interconnection Webinar | July 16 2020

Standard Criteria

Applies to

Projects that require Distribution System Impact Study (DSIS)

Large-scale DG projects

Generally greater than 500 kW but project specific

DG projects requiring System Modifications at the substation level

Non-listed inverters or generators other than PV

Induction Synchronous Asynchronous

Most CHP systems

All projects that do not qualify for the Simplified or Expedited process

27National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application

Application

Standard

Engineering Review

Impact StudyDetailed Study

Conditional Approval (to construct DG system)

Company Construction

Witness Test

Authorization to Interconnect

httpsngusforcecomsarticleMA-Complex-Standard-Application-Process

28National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Standard

Eligible Facilities Any DG

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Standard Process Initial Review 20 days

Send Impact Study Agreement 5 days

Complete Impact Study 55-60 days or by mutual agreement depending on complexity

Complete Detailed Study (if needed) 30 ndash 60 days or by mutual agreement depending on complexity

Send Executable Agreement (ISA) 15 days

Total Maximum Days 135160 days (200 days for Standard Complex)

Construction Schedule Varied

Witness Test10 days from the Companyrsquos approval of WT procedures or

by mutual agreement

29National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Impact Study will determine the level of impact on the Companyrsquos EPS and the required System

Modifications

Impact and Detailed Study (if applicable) will determine System Modifications required and cost

(Risk of Islanding)

ISO-NE Generator Notification Process will be required for applications that are greater than 1MW

but less than 5MW (ie PP5-1 or GNF) and a Proposed Plan Application (PPA) along with supporting Transmission System Impact Study (TSIS) will be required for applications 5MW or greater in size single or potentially in aggregate Size of project based on nameplate rating of

system

These requirements will add time to the DG Interconnection Process if there is an ASO hold If so

the DSIS will be placed on hold until the ISO-NE approval or determination is known likely at a point during the DSIS process

Interconnection Service Agreement (ISA) provided after Study completed or an Early ISA could be requested if Detailed Study is required

If substation modifications required Company has 60 BD for Study (MDPU 1320 ndash pg 50) or by mutual agreement if estimated construction cost greater than $1 million

30National Grid | July Interconnection Webinar | July 16 2020

New CEI Structure

Process Improvement

amp Future TopicsWill Kern

06

32National Grid | July Interconnection Webinar | July 16 2020

Process Improvement amp Future Topics

Potential webinar topics

Verizon initiatives

Hosting Capacity Maps

Metering

Mike Porcaro as Ombudsperson

Questions

07

34National Grid | July Interconnection Webinar | July 16 2020

Appendix Summary of Resources Documents amp Links

Distributed Generation Website ndash

httpswww9nationalgriduscommasselectrichomeenergyeffdistributed_gen

erationasp

Interconnection Process Resources ndash

httpswww9nationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

Storage Assistance -

httpsngusforcecomsarticleStorage-Assistance

DPU Interim Guidance for ESS -

httpsngusforcecomsarticleHow-to-Add-Energy-Storage-to-an-In-Progress-Application-in-Massachusetts

| [Insert document title] | [Insert date]

Page 8: National Grid Distributed Generation Seminar

8National Grid | July Interconnection Webinar | July 16 2020

Energy Storage System (ESS) Assets

The Inverter Information

This is the inverter for the ESS not the ESS itself

For DC coupled this is often the same inverter as the solar for example a SolarEdge inverter

For AC coupled this can be a separate inverter or the same as the ESS if it is a combined unit for example Powerwall

The ESS Information

Must be completed for AC and DC coupled batteries

The Storage Capacity per Device (kW DC) or (kW AC) is required (often

missed)

The Relay Information

Provides space for inputting ESS operating hours otherwise can be included in

the ESS information as an upload under special guidance

9National Grid | July Interconnection Webinar | July 16 2020

Energy Storage System (ESS) Form

The ESS Form is required and must be filled out electronically on the

portal (cannot be upload only)

Most of the fields on the ESS form are pre-populated from the Storage

case or values already entered on the case

If any of the pre-populated values look incorrect or need to be

updated please update the storage asset or reach to out to CEI

job owner thru Chatter

Link for knowledge page for adding a storage

asset httpsngusforcecomservletservletFileDownloadfile=0150W00000E

oHnv

Link for Storage Assistance httpsngusforcecomsarticleStorage-

Assistance

Simplified Review

ProcessMargaret Campbell

03

11National Grid | July Interconnection Webinar | July 16 2020

Simplified Criteria

UL Listed (1741 SA) inverter-based systems with power ratings of

15kW or less on a single phase service on a radial feed

UL Listed (1741 SA) inverter-based systems with power ratings of

25kW or less on a three phase service on a radial feed

The Simplified process does not apply for

Non-listed inverters or other generators (induction synchronous

asynchronous)

Aggregate generation capacity of listed inverters that exceed the

above-mentioned limits

Project that did not pass the Simplified process Screens

12National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Application

Simplified

Conditional Approval (to construct DG system)

Witness Test (completion package)

Authorization to Interconnect

httpswwwnationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

13National Grid | July Interconnection Webinar | July 16 2020

Simplified Review Path

Simplified Process

Eligible Facilities Listed Small Inverter

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Review of All Screens 15-20 days

Complete Supplemental Review (if needed) NA

Complete Standard Process Initial Review NA

Send Follow-on Studies CostAgreement NA

Complete Impact Study (if needed) NA

Complete Detailed Study (if needed) NA

Send Executable Agreement Done The agreement is part of the application

Total Maximum Days 25 days (30 in the case of failure of Screen 5)

Construction Schedule Varied

Witness Test Within 10 days from receipt of the Certificate of Completion or by mutual agreement

14National Grid | July Interconnection Webinar | July 16 2020

Common Holds or Concerns

Application

The application must match the customerrsquos account name address

account number and meter number

Wait to construct the system until after Conditional Approval is issued

After Conditional Approval

Complete the Service Upgrade Form so the work request can be

created and provided to the wire inspector at the before the inspection

Completion Package

Have Wire Inspection called in before submitting Completion

Documents

15National Grid | July Interconnection Webinar | July 16 2020

Recent Portal Improvements

Expedited Review

ProcessMike Armell

04

17National Grid | July Interconnection Webinar | July 16 2020

Expedited Criteria

Single phase customers with listed single-phase inverter based

systems with power ratings of gt15 kW on a radial feed

Three phase customers with listed three-phase inverter based

systems with power ratings of gt25kW on a radial feed

Any project that did not pass the Simplified process Screens

Non-Simplified projects that do not require an Impact Study

Maximum size supplemental review is based on review of

Screens

18National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application (if 500 kW or greater)

Application

Expedited

Engineering Review

Supplemental Review

Conditional Approval (to construct DG system)

Company Construction

Witness Test (where applicable)

Completion Document Review and Meter Set

Authorization to Interconnect

httpswwwnationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

19National Grid | July Interconnection Webinar | July 16 2020

Expedited Review Path

Expedited

Eligible Facilities Listed Inverter DG

Acknowledge Receipt of Application(3 days)

Review Application for Completeness10 days

Complete Review of All Screens25 days

Complete Supplemental Review (if needed)20 days or Standard Process

Send Executable Agreement10 days

Total Maximum Days 4565 days

Construction ScheduleVaried

Notice Witness TestWithin 10 days of receiving Certificate of

Completion or by mutual agreement

If any Screens are not passed the

Company may require a Supplemental Review Agreementbefore providing an Interconnection

Service Agreement

Key threshold if aggregate

generation is less than 67 of minimum load on the

feeder Other Screens review voltage quality reliability and safety to reduce the potential

need for Impact Studies

Relay control system must be well

defined to make SupplementalReview easier

20National Grid | July Interconnection Webinar | July 16 2020

Recent Improvements

Infrastructure List View-Can be found at the bottom of the home

page on the portal

Lists of all feeders in each jurisdiction (MA NY RI) that can be

sorted by Feeder Name Substation Transformer Name

Operating District Connected DG kWAC Pending DG kWAC

whether or not the Feeders are Registered with FERC

Link to

guide httpsngusforcecomservletservletFileDownloadfile=

0150W00000FKqNQ

Developers have access in portal to view muni WO for completion

21National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

For most Expedited applications a ldquoCommissioning Memordquo on

a company letterhead is provided in lieu of Witness Test

Commissioning test should consist of the following

1 Two (2) second shutdown when disconnect open test

2 Five (5) minutes before restart when disconnect is closed test

3 Confirm system matches As-built (include most recent revision

date of as built provided)

4 List the inverter relay frequency (Hz) and trip time settings

22National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

As Built Must be PE stamped and signed dated by person

that performed the commissioning test (Signature date

should match date of test)

Pictures Meter picture should show permanent plaque

(visible at eye level) that includes a warning about generator

installed

Pictures If the AC utility disconnect switch is not grouped

with and adjacent to the utility revenue meter then a

permanent plaque (visible at eye level) that clearly identifies

the location of the AC utility disconnect is required

23National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

Evidence of insurance is required for all projects gt 60kW in

MA and gt50kW in RI Refer to the ISA and Interconnection

Tariff for insurance requirements

Qualifying Facility documents

Schedule A (P-Rate) required for all QF projects

W9 (Only for projects gt60kW)

ACH (Only for projects gt60kW)

Supplier Enrollment Form (Only for projects gt60kW)

24National Grid | July Interconnection Webinar | July 16 2020

Metering Reminder

Projects greater than 60kW in MA and greater than 25kW in RI

require interval metering (Wireless or phone line)

Company needs a 4G wireless signal test on a Verizon network in

order to provide wireless metering

Phone lines must be dedicated and terminated at the meter

location Line must be 100 copper Fiber lines will not

communicate properly

These meters are long lead time items and prep time can be 6-8

weeks so it is important to work through this with your job owner

well in advance of when you intend to seek Authority to

Interconnect

Wireless test form httpsngusforcecomsarticleMA-

Interconnection-Documents

Standard Review

ProcessNat Mahattanasakul

05

26National Grid | July Interconnection Webinar | July 16 2020

Standard Criteria

Applies to

Projects that require Distribution System Impact Study (DSIS)

Large-scale DG projects

Generally greater than 500 kW but project specific

DG projects requiring System Modifications at the substation level

Non-listed inverters or generators other than PV

Induction Synchronous Asynchronous

Most CHP systems

All projects that do not qualify for the Simplified or Expedited process

27National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application

Application

Standard

Engineering Review

Impact StudyDetailed Study

Conditional Approval (to construct DG system)

Company Construction

Witness Test

Authorization to Interconnect

httpsngusforcecomsarticleMA-Complex-Standard-Application-Process

28National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Standard

Eligible Facilities Any DG

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Standard Process Initial Review 20 days

Send Impact Study Agreement 5 days

Complete Impact Study 55-60 days or by mutual agreement depending on complexity

Complete Detailed Study (if needed) 30 ndash 60 days or by mutual agreement depending on complexity

Send Executable Agreement (ISA) 15 days

Total Maximum Days 135160 days (200 days for Standard Complex)

Construction Schedule Varied

Witness Test10 days from the Companyrsquos approval of WT procedures or

by mutual agreement

29National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Impact Study will determine the level of impact on the Companyrsquos EPS and the required System

Modifications

Impact and Detailed Study (if applicable) will determine System Modifications required and cost

(Risk of Islanding)

ISO-NE Generator Notification Process will be required for applications that are greater than 1MW

but less than 5MW (ie PP5-1 or GNF) and a Proposed Plan Application (PPA) along with supporting Transmission System Impact Study (TSIS) will be required for applications 5MW or greater in size single or potentially in aggregate Size of project based on nameplate rating of

system

These requirements will add time to the DG Interconnection Process if there is an ASO hold If so

the DSIS will be placed on hold until the ISO-NE approval or determination is known likely at a point during the DSIS process

Interconnection Service Agreement (ISA) provided after Study completed or an Early ISA could be requested if Detailed Study is required

If substation modifications required Company has 60 BD for Study (MDPU 1320 ndash pg 50) or by mutual agreement if estimated construction cost greater than $1 million

30National Grid | July Interconnection Webinar | July 16 2020

New CEI Structure

Process Improvement

amp Future TopicsWill Kern

06

32National Grid | July Interconnection Webinar | July 16 2020

Process Improvement amp Future Topics

Potential webinar topics

Verizon initiatives

Hosting Capacity Maps

Metering

Mike Porcaro as Ombudsperson

Questions

07

34National Grid | July Interconnection Webinar | July 16 2020

Appendix Summary of Resources Documents amp Links

Distributed Generation Website ndash

httpswww9nationalgriduscommasselectrichomeenergyeffdistributed_gen

erationasp

Interconnection Process Resources ndash

httpswww9nationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

Storage Assistance -

httpsngusforcecomsarticleStorage-Assistance

DPU Interim Guidance for ESS -

httpsngusforcecomsarticleHow-to-Add-Energy-Storage-to-an-In-Progress-Application-in-Massachusetts

| [Insert document title] | [Insert date]

Page 9: National Grid Distributed Generation Seminar

9National Grid | July Interconnection Webinar | July 16 2020

Energy Storage System (ESS) Form

The ESS Form is required and must be filled out electronically on the

portal (cannot be upload only)

Most of the fields on the ESS form are pre-populated from the Storage

case or values already entered on the case

If any of the pre-populated values look incorrect or need to be

updated please update the storage asset or reach to out to CEI

job owner thru Chatter

Link for knowledge page for adding a storage

asset httpsngusforcecomservletservletFileDownloadfile=0150W00000E

oHnv

Link for Storage Assistance httpsngusforcecomsarticleStorage-

Assistance

Simplified Review

ProcessMargaret Campbell

03

11National Grid | July Interconnection Webinar | July 16 2020

Simplified Criteria

UL Listed (1741 SA) inverter-based systems with power ratings of

15kW or less on a single phase service on a radial feed

UL Listed (1741 SA) inverter-based systems with power ratings of

25kW or less on a three phase service on a radial feed

The Simplified process does not apply for

Non-listed inverters or other generators (induction synchronous

asynchronous)

Aggregate generation capacity of listed inverters that exceed the

above-mentioned limits

Project that did not pass the Simplified process Screens

12National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Application

Simplified

Conditional Approval (to construct DG system)

Witness Test (completion package)

Authorization to Interconnect

httpswwwnationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

13National Grid | July Interconnection Webinar | July 16 2020

Simplified Review Path

Simplified Process

Eligible Facilities Listed Small Inverter

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Review of All Screens 15-20 days

Complete Supplemental Review (if needed) NA

Complete Standard Process Initial Review NA

Send Follow-on Studies CostAgreement NA

Complete Impact Study (if needed) NA

Complete Detailed Study (if needed) NA

Send Executable Agreement Done The agreement is part of the application

Total Maximum Days 25 days (30 in the case of failure of Screen 5)

Construction Schedule Varied

Witness Test Within 10 days from receipt of the Certificate of Completion or by mutual agreement

14National Grid | July Interconnection Webinar | July 16 2020

Common Holds or Concerns

Application

The application must match the customerrsquos account name address

account number and meter number

Wait to construct the system until after Conditional Approval is issued

After Conditional Approval

Complete the Service Upgrade Form so the work request can be

created and provided to the wire inspector at the before the inspection

Completion Package

Have Wire Inspection called in before submitting Completion

Documents

15National Grid | July Interconnection Webinar | July 16 2020

Recent Portal Improvements

Expedited Review

ProcessMike Armell

04

17National Grid | July Interconnection Webinar | July 16 2020

Expedited Criteria

Single phase customers with listed single-phase inverter based

systems with power ratings of gt15 kW on a radial feed

Three phase customers with listed three-phase inverter based

systems with power ratings of gt25kW on a radial feed

Any project that did not pass the Simplified process Screens

Non-Simplified projects that do not require an Impact Study

Maximum size supplemental review is based on review of

Screens

18National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application (if 500 kW or greater)

Application

Expedited

Engineering Review

Supplemental Review

Conditional Approval (to construct DG system)

Company Construction

Witness Test (where applicable)

Completion Document Review and Meter Set

Authorization to Interconnect

httpswwwnationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

19National Grid | July Interconnection Webinar | July 16 2020

Expedited Review Path

Expedited

Eligible Facilities Listed Inverter DG

Acknowledge Receipt of Application(3 days)

Review Application for Completeness10 days

Complete Review of All Screens25 days

Complete Supplemental Review (if needed)20 days or Standard Process

Send Executable Agreement10 days

Total Maximum Days 4565 days

Construction ScheduleVaried

Notice Witness TestWithin 10 days of receiving Certificate of

Completion or by mutual agreement

If any Screens are not passed the

Company may require a Supplemental Review Agreementbefore providing an Interconnection

Service Agreement

Key threshold if aggregate

generation is less than 67 of minimum load on the

feeder Other Screens review voltage quality reliability and safety to reduce the potential

need for Impact Studies

Relay control system must be well

defined to make SupplementalReview easier

20National Grid | July Interconnection Webinar | July 16 2020

Recent Improvements

Infrastructure List View-Can be found at the bottom of the home

page on the portal

Lists of all feeders in each jurisdiction (MA NY RI) that can be

sorted by Feeder Name Substation Transformer Name

Operating District Connected DG kWAC Pending DG kWAC

whether or not the Feeders are Registered with FERC

Link to

guide httpsngusforcecomservletservletFileDownloadfile=

0150W00000FKqNQ

Developers have access in portal to view muni WO for completion

21National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

For most Expedited applications a ldquoCommissioning Memordquo on

a company letterhead is provided in lieu of Witness Test

Commissioning test should consist of the following

1 Two (2) second shutdown when disconnect open test

2 Five (5) minutes before restart when disconnect is closed test

3 Confirm system matches As-built (include most recent revision

date of as built provided)

4 List the inverter relay frequency (Hz) and trip time settings

22National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

As Built Must be PE stamped and signed dated by person

that performed the commissioning test (Signature date

should match date of test)

Pictures Meter picture should show permanent plaque

(visible at eye level) that includes a warning about generator

installed

Pictures If the AC utility disconnect switch is not grouped

with and adjacent to the utility revenue meter then a

permanent plaque (visible at eye level) that clearly identifies

the location of the AC utility disconnect is required

23National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

Evidence of insurance is required for all projects gt 60kW in

MA and gt50kW in RI Refer to the ISA and Interconnection

Tariff for insurance requirements

Qualifying Facility documents

Schedule A (P-Rate) required for all QF projects

W9 (Only for projects gt60kW)

ACH (Only for projects gt60kW)

Supplier Enrollment Form (Only for projects gt60kW)

24National Grid | July Interconnection Webinar | July 16 2020

Metering Reminder

Projects greater than 60kW in MA and greater than 25kW in RI

require interval metering (Wireless or phone line)

Company needs a 4G wireless signal test on a Verizon network in

order to provide wireless metering

Phone lines must be dedicated and terminated at the meter

location Line must be 100 copper Fiber lines will not

communicate properly

These meters are long lead time items and prep time can be 6-8

weeks so it is important to work through this with your job owner

well in advance of when you intend to seek Authority to

Interconnect

Wireless test form httpsngusforcecomsarticleMA-

Interconnection-Documents

Standard Review

ProcessNat Mahattanasakul

05

26National Grid | July Interconnection Webinar | July 16 2020

Standard Criteria

Applies to

Projects that require Distribution System Impact Study (DSIS)

Large-scale DG projects

Generally greater than 500 kW but project specific

DG projects requiring System Modifications at the substation level

Non-listed inverters or generators other than PV

Induction Synchronous Asynchronous

Most CHP systems

All projects that do not qualify for the Simplified or Expedited process

27National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application

Application

Standard

Engineering Review

Impact StudyDetailed Study

Conditional Approval (to construct DG system)

Company Construction

Witness Test

Authorization to Interconnect

httpsngusforcecomsarticleMA-Complex-Standard-Application-Process

28National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Standard

Eligible Facilities Any DG

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Standard Process Initial Review 20 days

Send Impact Study Agreement 5 days

Complete Impact Study 55-60 days or by mutual agreement depending on complexity

Complete Detailed Study (if needed) 30 ndash 60 days or by mutual agreement depending on complexity

Send Executable Agreement (ISA) 15 days

Total Maximum Days 135160 days (200 days for Standard Complex)

Construction Schedule Varied

Witness Test10 days from the Companyrsquos approval of WT procedures or

by mutual agreement

29National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Impact Study will determine the level of impact on the Companyrsquos EPS and the required System

Modifications

Impact and Detailed Study (if applicable) will determine System Modifications required and cost

(Risk of Islanding)

ISO-NE Generator Notification Process will be required for applications that are greater than 1MW

but less than 5MW (ie PP5-1 or GNF) and a Proposed Plan Application (PPA) along with supporting Transmission System Impact Study (TSIS) will be required for applications 5MW or greater in size single or potentially in aggregate Size of project based on nameplate rating of

system

These requirements will add time to the DG Interconnection Process if there is an ASO hold If so

the DSIS will be placed on hold until the ISO-NE approval or determination is known likely at a point during the DSIS process

Interconnection Service Agreement (ISA) provided after Study completed or an Early ISA could be requested if Detailed Study is required

If substation modifications required Company has 60 BD for Study (MDPU 1320 ndash pg 50) or by mutual agreement if estimated construction cost greater than $1 million

30National Grid | July Interconnection Webinar | July 16 2020

New CEI Structure

Process Improvement

amp Future TopicsWill Kern

06

32National Grid | July Interconnection Webinar | July 16 2020

Process Improvement amp Future Topics

Potential webinar topics

Verizon initiatives

Hosting Capacity Maps

Metering

Mike Porcaro as Ombudsperson

Questions

07

34National Grid | July Interconnection Webinar | July 16 2020

Appendix Summary of Resources Documents amp Links

Distributed Generation Website ndash

httpswww9nationalgriduscommasselectrichomeenergyeffdistributed_gen

erationasp

Interconnection Process Resources ndash

httpswww9nationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

Storage Assistance -

httpsngusforcecomsarticleStorage-Assistance

DPU Interim Guidance for ESS -

httpsngusforcecomsarticleHow-to-Add-Energy-Storage-to-an-In-Progress-Application-in-Massachusetts

| [Insert document title] | [Insert date]

Page 10: National Grid Distributed Generation Seminar

Simplified Review

ProcessMargaret Campbell

03

11National Grid | July Interconnection Webinar | July 16 2020

Simplified Criteria

UL Listed (1741 SA) inverter-based systems with power ratings of

15kW or less on a single phase service on a radial feed

UL Listed (1741 SA) inverter-based systems with power ratings of

25kW or less on a three phase service on a radial feed

The Simplified process does not apply for

Non-listed inverters or other generators (induction synchronous

asynchronous)

Aggregate generation capacity of listed inverters that exceed the

above-mentioned limits

Project that did not pass the Simplified process Screens

12National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Application

Simplified

Conditional Approval (to construct DG system)

Witness Test (completion package)

Authorization to Interconnect

httpswwwnationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

13National Grid | July Interconnection Webinar | July 16 2020

Simplified Review Path

Simplified Process

Eligible Facilities Listed Small Inverter

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Review of All Screens 15-20 days

Complete Supplemental Review (if needed) NA

Complete Standard Process Initial Review NA

Send Follow-on Studies CostAgreement NA

Complete Impact Study (if needed) NA

Complete Detailed Study (if needed) NA

Send Executable Agreement Done The agreement is part of the application

Total Maximum Days 25 days (30 in the case of failure of Screen 5)

Construction Schedule Varied

Witness Test Within 10 days from receipt of the Certificate of Completion or by mutual agreement

14National Grid | July Interconnection Webinar | July 16 2020

Common Holds or Concerns

Application

The application must match the customerrsquos account name address

account number and meter number

Wait to construct the system until after Conditional Approval is issued

After Conditional Approval

Complete the Service Upgrade Form so the work request can be

created and provided to the wire inspector at the before the inspection

Completion Package

Have Wire Inspection called in before submitting Completion

Documents

15National Grid | July Interconnection Webinar | July 16 2020

Recent Portal Improvements

Expedited Review

ProcessMike Armell

04

17National Grid | July Interconnection Webinar | July 16 2020

Expedited Criteria

Single phase customers with listed single-phase inverter based

systems with power ratings of gt15 kW on a radial feed

Three phase customers with listed three-phase inverter based

systems with power ratings of gt25kW on a radial feed

Any project that did not pass the Simplified process Screens

Non-Simplified projects that do not require an Impact Study

Maximum size supplemental review is based on review of

Screens

18National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application (if 500 kW or greater)

Application

Expedited

Engineering Review

Supplemental Review

Conditional Approval (to construct DG system)

Company Construction

Witness Test (where applicable)

Completion Document Review and Meter Set

Authorization to Interconnect

httpswwwnationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

19National Grid | July Interconnection Webinar | July 16 2020

Expedited Review Path

Expedited

Eligible Facilities Listed Inverter DG

Acknowledge Receipt of Application(3 days)

Review Application for Completeness10 days

Complete Review of All Screens25 days

Complete Supplemental Review (if needed)20 days or Standard Process

Send Executable Agreement10 days

Total Maximum Days 4565 days

Construction ScheduleVaried

Notice Witness TestWithin 10 days of receiving Certificate of

Completion or by mutual agreement

If any Screens are not passed the

Company may require a Supplemental Review Agreementbefore providing an Interconnection

Service Agreement

Key threshold if aggregate

generation is less than 67 of minimum load on the

feeder Other Screens review voltage quality reliability and safety to reduce the potential

need for Impact Studies

Relay control system must be well

defined to make SupplementalReview easier

20National Grid | July Interconnection Webinar | July 16 2020

Recent Improvements

Infrastructure List View-Can be found at the bottom of the home

page on the portal

Lists of all feeders in each jurisdiction (MA NY RI) that can be

sorted by Feeder Name Substation Transformer Name

Operating District Connected DG kWAC Pending DG kWAC

whether or not the Feeders are Registered with FERC

Link to

guide httpsngusforcecomservletservletFileDownloadfile=

0150W00000FKqNQ

Developers have access in portal to view muni WO for completion

21National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

For most Expedited applications a ldquoCommissioning Memordquo on

a company letterhead is provided in lieu of Witness Test

Commissioning test should consist of the following

1 Two (2) second shutdown when disconnect open test

2 Five (5) minutes before restart when disconnect is closed test

3 Confirm system matches As-built (include most recent revision

date of as built provided)

4 List the inverter relay frequency (Hz) and trip time settings

22National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

As Built Must be PE stamped and signed dated by person

that performed the commissioning test (Signature date

should match date of test)

Pictures Meter picture should show permanent plaque

(visible at eye level) that includes a warning about generator

installed

Pictures If the AC utility disconnect switch is not grouped

with and adjacent to the utility revenue meter then a

permanent plaque (visible at eye level) that clearly identifies

the location of the AC utility disconnect is required

23National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

Evidence of insurance is required for all projects gt 60kW in

MA and gt50kW in RI Refer to the ISA and Interconnection

Tariff for insurance requirements

Qualifying Facility documents

Schedule A (P-Rate) required for all QF projects

W9 (Only for projects gt60kW)

ACH (Only for projects gt60kW)

Supplier Enrollment Form (Only for projects gt60kW)

24National Grid | July Interconnection Webinar | July 16 2020

Metering Reminder

Projects greater than 60kW in MA and greater than 25kW in RI

require interval metering (Wireless or phone line)

Company needs a 4G wireless signal test on a Verizon network in

order to provide wireless metering

Phone lines must be dedicated and terminated at the meter

location Line must be 100 copper Fiber lines will not

communicate properly

These meters are long lead time items and prep time can be 6-8

weeks so it is important to work through this with your job owner

well in advance of when you intend to seek Authority to

Interconnect

Wireless test form httpsngusforcecomsarticleMA-

Interconnection-Documents

Standard Review

ProcessNat Mahattanasakul

05

26National Grid | July Interconnection Webinar | July 16 2020

Standard Criteria

Applies to

Projects that require Distribution System Impact Study (DSIS)

Large-scale DG projects

Generally greater than 500 kW but project specific

DG projects requiring System Modifications at the substation level

Non-listed inverters or generators other than PV

Induction Synchronous Asynchronous

Most CHP systems

All projects that do not qualify for the Simplified or Expedited process

27National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application

Application

Standard

Engineering Review

Impact StudyDetailed Study

Conditional Approval (to construct DG system)

Company Construction

Witness Test

Authorization to Interconnect

httpsngusforcecomsarticleMA-Complex-Standard-Application-Process

28National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Standard

Eligible Facilities Any DG

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Standard Process Initial Review 20 days

Send Impact Study Agreement 5 days

Complete Impact Study 55-60 days or by mutual agreement depending on complexity

Complete Detailed Study (if needed) 30 ndash 60 days or by mutual agreement depending on complexity

Send Executable Agreement (ISA) 15 days

Total Maximum Days 135160 days (200 days for Standard Complex)

Construction Schedule Varied

Witness Test10 days from the Companyrsquos approval of WT procedures or

by mutual agreement

29National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Impact Study will determine the level of impact on the Companyrsquos EPS and the required System

Modifications

Impact and Detailed Study (if applicable) will determine System Modifications required and cost

(Risk of Islanding)

ISO-NE Generator Notification Process will be required for applications that are greater than 1MW

but less than 5MW (ie PP5-1 or GNF) and a Proposed Plan Application (PPA) along with supporting Transmission System Impact Study (TSIS) will be required for applications 5MW or greater in size single or potentially in aggregate Size of project based on nameplate rating of

system

These requirements will add time to the DG Interconnection Process if there is an ASO hold If so

the DSIS will be placed on hold until the ISO-NE approval or determination is known likely at a point during the DSIS process

Interconnection Service Agreement (ISA) provided after Study completed or an Early ISA could be requested if Detailed Study is required

If substation modifications required Company has 60 BD for Study (MDPU 1320 ndash pg 50) or by mutual agreement if estimated construction cost greater than $1 million

30National Grid | July Interconnection Webinar | July 16 2020

New CEI Structure

Process Improvement

amp Future TopicsWill Kern

06

32National Grid | July Interconnection Webinar | July 16 2020

Process Improvement amp Future Topics

Potential webinar topics

Verizon initiatives

Hosting Capacity Maps

Metering

Mike Porcaro as Ombudsperson

Questions

07

34National Grid | July Interconnection Webinar | July 16 2020

Appendix Summary of Resources Documents amp Links

Distributed Generation Website ndash

httpswww9nationalgriduscommasselectrichomeenergyeffdistributed_gen

erationasp

Interconnection Process Resources ndash

httpswww9nationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

Storage Assistance -

httpsngusforcecomsarticleStorage-Assistance

DPU Interim Guidance for ESS -

httpsngusforcecomsarticleHow-to-Add-Energy-Storage-to-an-In-Progress-Application-in-Massachusetts

| [Insert document title] | [Insert date]

Page 11: National Grid Distributed Generation Seminar

11National Grid | July Interconnection Webinar | July 16 2020

Simplified Criteria

UL Listed (1741 SA) inverter-based systems with power ratings of

15kW or less on a single phase service on a radial feed

UL Listed (1741 SA) inverter-based systems with power ratings of

25kW or less on a three phase service on a radial feed

The Simplified process does not apply for

Non-listed inverters or other generators (induction synchronous

asynchronous)

Aggregate generation capacity of listed inverters that exceed the

above-mentioned limits

Project that did not pass the Simplified process Screens

12National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Application

Simplified

Conditional Approval (to construct DG system)

Witness Test (completion package)

Authorization to Interconnect

httpswwwnationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

13National Grid | July Interconnection Webinar | July 16 2020

Simplified Review Path

Simplified Process

Eligible Facilities Listed Small Inverter

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Review of All Screens 15-20 days

Complete Supplemental Review (if needed) NA

Complete Standard Process Initial Review NA

Send Follow-on Studies CostAgreement NA

Complete Impact Study (if needed) NA

Complete Detailed Study (if needed) NA

Send Executable Agreement Done The agreement is part of the application

Total Maximum Days 25 days (30 in the case of failure of Screen 5)

Construction Schedule Varied

Witness Test Within 10 days from receipt of the Certificate of Completion or by mutual agreement

14National Grid | July Interconnection Webinar | July 16 2020

Common Holds or Concerns

Application

The application must match the customerrsquos account name address

account number and meter number

Wait to construct the system until after Conditional Approval is issued

After Conditional Approval

Complete the Service Upgrade Form so the work request can be

created and provided to the wire inspector at the before the inspection

Completion Package

Have Wire Inspection called in before submitting Completion

Documents

15National Grid | July Interconnection Webinar | July 16 2020

Recent Portal Improvements

Expedited Review

ProcessMike Armell

04

17National Grid | July Interconnection Webinar | July 16 2020

Expedited Criteria

Single phase customers with listed single-phase inverter based

systems with power ratings of gt15 kW on a radial feed

Three phase customers with listed three-phase inverter based

systems with power ratings of gt25kW on a radial feed

Any project that did not pass the Simplified process Screens

Non-Simplified projects that do not require an Impact Study

Maximum size supplemental review is based on review of

Screens

18National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application (if 500 kW or greater)

Application

Expedited

Engineering Review

Supplemental Review

Conditional Approval (to construct DG system)

Company Construction

Witness Test (where applicable)

Completion Document Review and Meter Set

Authorization to Interconnect

httpswwwnationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

19National Grid | July Interconnection Webinar | July 16 2020

Expedited Review Path

Expedited

Eligible Facilities Listed Inverter DG

Acknowledge Receipt of Application(3 days)

Review Application for Completeness10 days

Complete Review of All Screens25 days

Complete Supplemental Review (if needed)20 days or Standard Process

Send Executable Agreement10 days

Total Maximum Days 4565 days

Construction ScheduleVaried

Notice Witness TestWithin 10 days of receiving Certificate of

Completion or by mutual agreement

If any Screens are not passed the

Company may require a Supplemental Review Agreementbefore providing an Interconnection

Service Agreement

Key threshold if aggregate

generation is less than 67 of minimum load on the

feeder Other Screens review voltage quality reliability and safety to reduce the potential

need for Impact Studies

Relay control system must be well

defined to make SupplementalReview easier

20National Grid | July Interconnection Webinar | July 16 2020

Recent Improvements

Infrastructure List View-Can be found at the bottom of the home

page on the portal

Lists of all feeders in each jurisdiction (MA NY RI) that can be

sorted by Feeder Name Substation Transformer Name

Operating District Connected DG kWAC Pending DG kWAC

whether or not the Feeders are Registered with FERC

Link to

guide httpsngusforcecomservletservletFileDownloadfile=

0150W00000FKqNQ

Developers have access in portal to view muni WO for completion

21National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

For most Expedited applications a ldquoCommissioning Memordquo on

a company letterhead is provided in lieu of Witness Test

Commissioning test should consist of the following

1 Two (2) second shutdown when disconnect open test

2 Five (5) minutes before restart when disconnect is closed test

3 Confirm system matches As-built (include most recent revision

date of as built provided)

4 List the inverter relay frequency (Hz) and trip time settings

22National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

As Built Must be PE stamped and signed dated by person

that performed the commissioning test (Signature date

should match date of test)

Pictures Meter picture should show permanent plaque

(visible at eye level) that includes a warning about generator

installed

Pictures If the AC utility disconnect switch is not grouped

with and adjacent to the utility revenue meter then a

permanent plaque (visible at eye level) that clearly identifies

the location of the AC utility disconnect is required

23National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

Evidence of insurance is required for all projects gt 60kW in

MA and gt50kW in RI Refer to the ISA and Interconnection

Tariff for insurance requirements

Qualifying Facility documents

Schedule A (P-Rate) required for all QF projects

W9 (Only for projects gt60kW)

ACH (Only for projects gt60kW)

Supplier Enrollment Form (Only for projects gt60kW)

24National Grid | July Interconnection Webinar | July 16 2020

Metering Reminder

Projects greater than 60kW in MA and greater than 25kW in RI

require interval metering (Wireless or phone line)

Company needs a 4G wireless signal test on a Verizon network in

order to provide wireless metering

Phone lines must be dedicated and terminated at the meter

location Line must be 100 copper Fiber lines will not

communicate properly

These meters are long lead time items and prep time can be 6-8

weeks so it is important to work through this with your job owner

well in advance of when you intend to seek Authority to

Interconnect

Wireless test form httpsngusforcecomsarticleMA-

Interconnection-Documents

Standard Review

ProcessNat Mahattanasakul

05

26National Grid | July Interconnection Webinar | July 16 2020

Standard Criteria

Applies to

Projects that require Distribution System Impact Study (DSIS)

Large-scale DG projects

Generally greater than 500 kW but project specific

DG projects requiring System Modifications at the substation level

Non-listed inverters or generators other than PV

Induction Synchronous Asynchronous

Most CHP systems

All projects that do not qualify for the Simplified or Expedited process

27National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application

Application

Standard

Engineering Review

Impact StudyDetailed Study

Conditional Approval (to construct DG system)

Company Construction

Witness Test

Authorization to Interconnect

httpsngusforcecomsarticleMA-Complex-Standard-Application-Process

28National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Standard

Eligible Facilities Any DG

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Standard Process Initial Review 20 days

Send Impact Study Agreement 5 days

Complete Impact Study 55-60 days or by mutual agreement depending on complexity

Complete Detailed Study (if needed) 30 ndash 60 days or by mutual agreement depending on complexity

Send Executable Agreement (ISA) 15 days

Total Maximum Days 135160 days (200 days for Standard Complex)

Construction Schedule Varied

Witness Test10 days from the Companyrsquos approval of WT procedures or

by mutual agreement

29National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Impact Study will determine the level of impact on the Companyrsquos EPS and the required System

Modifications

Impact and Detailed Study (if applicable) will determine System Modifications required and cost

(Risk of Islanding)

ISO-NE Generator Notification Process will be required for applications that are greater than 1MW

but less than 5MW (ie PP5-1 or GNF) and a Proposed Plan Application (PPA) along with supporting Transmission System Impact Study (TSIS) will be required for applications 5MW or greater in size single or potentially in aggregate Size of project based on nameplate rating of

system

These requirements will add time to the DG Interconnection Process if there is an ASO hold If so

the DSIS will be placed on hold until the ISO-NE approval or determination is known likely at a point during the DSIS process

Interconnection Service Agreement (ISA) provided after Study completed or an Early ISA could be requested if Detailed Study is required

If substation modifications required Company has 60 BD for Study (MDPU 1320 ndash pg 50) or by mutual agreement if estimated construction cost greater than $1 million

30National Grid | July Interconnection Webinar | July 16 2020

New CEI Structure

Process Improvement

amp Future TopicsWill Kern

06

32National Grid | July Interconnection Webinar | July 16 2020

Process Improvement amp Future Topics

Potential webinar topics

Verizon initiatives

Hosting Capacity Maps

Metering

Mike Porcaro as Ombudsperson

Questions

07

34National Grid | July Interconnection Webinar | July 16 2020

Appendix Summary of Resources Documents amp Links

Distributed Generation Website ndash

httpswww9nationalgriduscommasselectrichomeenergyeffdistributed_gen

erationasp

Interconnection Process Resources ndash

httpswww9nationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

Storage Assistance -

httpsngusforcecomsarticleStorage-Assistance

DPU Interim Guidance for ESS -

httpsngusforcecomsarticleHow-to-Add-Energy-Storage-to-an-In-Progress-Application-in-Massachusetts

| [Insert document title] | [Insert date]

Page 12: National Grid Distributed Generation Seminar

12National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Application

Simplified

Conditional Approval (to construct DG system)

Witness Test (completion package)

Authorization to Interconnect

httpswwwnationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

13National Grid | July Interconnection Webinar | July 16 2020

Simplified Review Path

Simplified Process

Eligible Facilities Listed Small Inverter

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Review of All Screens 15-20 days

Complete Supplemental Review (if needed) NA

Complete Standard Process Initial Review NA

Send Follow-on Studies CostAgreement NA

Complete Impact Study (if needed) NA

Complete Detailed Study (if needed) NA

Send Executable Agreement Done The agreement is part of the application

Total Maximum Days 25 days (30 in the case of failure of Screen 5)

Construction Schedule Varied

Witness Test Within 10 days from receipt of the Certificate of Completion or by mutual agreement

14National Grid | July Interconnection Webinar | July 16 2020

Common Holds or Concerns

Application

The application must match the customerrsquos account name address

account number and meter number

Wait to construct the system until after Conditional Approval is issued

After Conditional Approval

Complete the Service Upgrade Form so the work request can be

created and provided to the wire inspector at the before the inspection

Completion Package

Have Wire Inspection called in before submitting Completion

Documents

15National Grid | July Interconnection Webinar | July 16 2020

Recent Portal Improvements

Expedited Review

ProcessMike Armell

04

17National Grid | July Interconnection Webinar | July 16 2020

Expedited Criteria

Single phase customers with listed single-phase inverter based

systems with power ratings of gt15 kW on a radial feed

Three phase customers with listed three-phase inverter based

systems with power ratings of gt25kW on a radial feed

Any project that did not pass the Simplified process Screens

Non-Simplified projects that do not require an Impact Study

Maximum size supplemental review is based on review of

Screens

18National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application (if 500 kW or greater)

Application

Expedited

Engineering Review

Supplemental Review

Conditional Approval (to construct DG system)

Company Construction

Witness Test (where applicable)

Completion Document Review and Meter Set

Authorization to Interconnect

httpswwwnationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

19National Grid | July Interconnection Webinar | July 16 2020

Expedited Review Path

Expedited

Eligible Facilities Listed Inverter DG

Acknowledge Receipt of Application(3 days)

Review Application for Completeness10 days

Complete Review of All Screens25 days

Complete Supplemental Review (if needed)20 days or Standard Process

Send Executable Agreement10 days

Total Maximum Days 4565 days

Construction ScheduleVaried

Notice Witness TestWithin 10 days of receiving Certificate of

Completion or by mutual agreement

If any Screens are not passed the

Company may require a Supplemental Review Agreementbefore providing an Interconnection

Service Agreement

Key threshold if aggregate

generation is less than 67 of minimum load on the

feeder Other Screens review voltage quality reliability and safety to reduce the potential

need for Impact Studies

Relay control system must be well

defined to make SupplementalReview easier

20National Grid | July Interconnection Webinar | July 16 2020

Recent Improvements

Infrastructure List View-Can be found at the bottom of the home

page on the portal

Lists of all feeders in each jurisdiction (MA NY RI) that can be

sorted by Feeder Name Substation Transformer Name

Operating District Connected DG kWAC Pending DG kWAC

whether or not the Feeders are Registered with FERC

Link to

guide httpsngusforcecomservletservletFileDownloadfile=

0150W00000FKqNQ

Developers have access in portal to view muni WO for completion

21National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

For most Expedited applications a ldquoCommissioning Memordquo on

a company letterhead is provided in lieu of Witness Test

Commissioning test should consist of the following

1 Two (2) second shutdown when disconnect open test

2 Five (5) minutes before restart when disconnect is closed test

3 Confirm system matches As-built (include most recent revision

date of as built provided)

4 List the inverter relay frequency (Hz) and trip time settings

22National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

As Built Must be PE stamped and signed dated by person

that performed the commissioning test (Signature date

should match date of test)

Pictures Meter picture should show permanent plaque

(visible at eye level) that includes a warning about generator

installed

Pictures If the AC utility disconnect switch is not grouped

with and adjacent to the utility revenue meter then a

permanent plaque (visible at eye level) that clearly identifies

the location of the AC utility disconnect is required

23National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

Evidence of insurance is required for all projects gt 60kW in

MA and gt50kW in RI Refer to the ISA and Interconnection

Tariff for insurance requirements

Qualifying Facility documents

Schedule A (P-Rate) required for all QF projects

W9 (Only for projects gt60kW)

ACH (Only for projects gt60kW)

Supplier Enrollment Form (Only for projects gt60kW)

24National Grid | July Interconnection Webinar | July 16 2020

Metering Reminder

Projects greater than 60kW in MA and greater than 25kW in RI

require interval metering (Wireless or phone line)

Company needs a 4G wireless signal test on a Verizon network in

order to provide wireless metering

Phone lines must be dedicated and terminated at the meter

location Line must be 100 copper Fiber lines will not

communicate properly

These meters are long lead time items and prep time can be 6-8

weeks so it is important to work through this with your job owner

well in advance of when you intend to seek Authority to

Interconnect

Wireless test form httpsngusforcecomsarticleMA-

Interconnection-Documents

Standard Review

ProcessNat Mahattanasakul

05

26National Grid | July Interconnection Webinar | July 16 2020

Standard Criteria

Applies to

Projects that require Distribution System Impact Study (DSIS)

Large-scale DG projects

Generally greater than 500 kW but project specific

DG projects requiring System Modifications at the substation level

Non-listed inverters or generators other than PV

Induction Synchronous Asynchronous

Most CHP systems

All projects that do not qualify for the Simplified or Expedited process

27National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application

Application

Standard

Engineering Review

Impact StudyDetailed Study

Conditional Approval (to construct DG system)

Company Construction

Witness Test

Authorization to Interconnect

httpsngusforcecomsarticleMA-Complex-Standard-Application-Process

28National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Standard

Eligible Facilities Any DG

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Standard Process Initial Review 20 days

Send Impact Study Agreement 5 days

Complete Impact Study 55-60 days or by mutual agreement depending on complexity

Complete Detailed Study (if needed) 30 ndash 60 days or by mutual agreement depending on complexity

Send Executable Agreement (ISA) 15 days

Total Maximum Days 135160 days (200 days for Standard Complex)

Construction Schedule Varied

Witness Test10 days from the Companyrsquos approval of WT procedures or

by mutual agreement

29National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Impact Study will determine the level of impact on the Companyrsquos EPS and the required System

Modifications

Impact and Detailed Study (if applicable) will determine System Modifications required and cost

(Risk of Islanding)

ISO-NE Generator Notification Process will be required for applications that are greater than 1MW

but less than 5MW (ie PP5-1 or GNF) and a Proposed Plan Application (PPA) along with supporting Transmission System Impact Study (TSIS) will be required for applications 5MW or greater in size single or potentially in aggregate Size of project based on nameplate rating of

system

These requirements will add time to the DG Interconnection Process if there is an ASO hold If so

the DSIS will be placed on hold until the ISO-NE approval or determination is known likely at a point during the DSIS process

Interconnection Service Agreement (ISA) provided after Study completed or an Early ISA could be requested if Detailed Study is required

If substation modifications required Company has 60 BD for Study (MDPU 1320 ndash pg 50) or by mutual agreement if estimated construction cost greater than $1 million

30National Grid | July Interconnection Webinar | July 16 2020

New CEI Structure

Process Improvement

amp Future TopicsWill Kern

06

32National Grid | July Interconnection Webinar | July 16 2020

Process Improvement amp Future Topics

Potential webinar topics

Verizon initiatives

Hosting Capacity Maps

Metering

Mike Porcaro as Ombudsperson

Questions

07

34National Grid | July Interconnection Webinar | July 16 2020

Appendix Summary of Resources Documents amp Links

Distributed Generation Website ndash

httpswww9nationalgriduscommasselectrichomeenergyeffdistributed_gen

erationasp

Interconnection Process Resources ndash

httpswww9nationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

Storage Assistance -

httpsngusforcecomsarticleStorage-Assistance

DPU Interim Guidance for ESS -

httpsngusforcecomsarticleHow-to-Add-Energy-Storage-to-an-In-Progress-Application-in-Massachusetts

| [Insert document title] | [Insert date]

Page 13: National Grid Distributed Generation Seminar

13National Grid | July Interconnection Webinar | July 16 2020

Simplified Review Path

Simplified Process

Eligible Facilities Listed Small Inverter

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Review of All Screens 15-20 days

Complete Supplemental Review (if needed) NA

Complete Standard Process Initial Review NA

Send Follow-on Studies CostAgreement NA

Complete Impact Study (if needed) NA

Complete Detailed Study (if needed) NA

Send Executable Agreement Done The agreement is part of the application

Total Maximum Days 25 days (30 in the case of failure of Screen 5)

Construction Schedule Varied

Witness Test Within 10 days from receipt of the Certificate of Completion or by mutual agreement

14National Grid | July Interconnection Webinar | July 16 2020

Common Holds or Concerns

Application

The application must match the customerrsquos account name address

account number and meter number

Wait to construct the system until after Conditional Approval is issued

After Conditional Approval

Complete the Service Upgrade Form so the work request can be

created and provided to the wire inspector at the before the inspection

Completion Package

Have Wire Inspection called in before submitting Completion

Documents

15National Grid | July Interconnection Webinar | July 16 2020

Recent Portal Improvements

Expedited Review

ProcessMike Armell

04

17National Grid | July Interconnection Webinar | July 16 2020

Expedited Criteria

Single phase customers with listed single-phase inverter based

systems with power ratings of gt15 kW on a radial feed

Three phase customers with listed three-phase inverter based

systems with power ratings of gt25kW on a radial feed

Any project that did not pass the Simplified process Screens

Non-Simplified projects that do not require an Impact Study

Maximum size supplemental review is based on review of

Screens

18National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application (if 500 kW or greater)

Application

Expedited

Engineering Review

Supplemental Review

Conditional Approval (to construct DG system)

Company Construction

Witness Test (where applicable)

Completion Document Review and Meter Set

Authorization to Interconnect

httpswwwnationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

19National Grid | July Interconnection Webinar | July 16 2020

Expedited Review Path

Expedited

Eligible Facilities Listed Inverter DG

Acknowledge Receipt of Application(3 days)

Review Application for Completeness10 days

Complete Review of All Screens25 days

Complete Supplemental Review (if needed)20 days or Standard Process

Send Executable Agreement10 days

Total Maximum Days 4565 days

Construction ScheduleVaried

Notice Witness TestWithin 10 days of receiving Certificate of

Completion or by mutual agreement

If any Screens are not passed the

Company may require a Supplemental Review Agreementbefore providing an Interconnection

Service Agreement

Key threshold if aggregate

generation is less than 67 of minimum load on the

feeder Other Screens review voltage quality reliability and safety to reduce the potential

need for Impact Studies

Relay control system must be well

defined to make SupplementalReview easier

20National Grid | July Interconnection Webinar | July 16 2020

Recent Improvements

Infrastructure List View-Can be found at the bottom of the home

page on the portal

Lists of all feeders in each jurisdiction (MA NY RI) that can be

sorted by Feeder Name Substation Transformer Name

Operating District Connected DG kWAC Pending DG kWAC

whether or not the Feeders are Registered with FERC

Link to

guide httpsngusforcecomservletservletFileDownloadfile=

0150W00000FKqNQ

Developers have access in portal to view muni WO for completion

21National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

For most Expedited applications a ldquoCommissioning Memordquo on

a company letterhead is provided in lieu of Witness Test

Commissioning test should consist of the following

1 Two (2) second shutdown when disconnect open test

2 Five (5) minutes before restart when disconnect is closed test

3 Confirm system matches As-built (include most recent revision

date of as built provided)

4 List the inverter relay frequency (Hz) and trip time settings

22National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

As Built Must be PE stamped and signed dated by person

that performed the commissioning test (Signature date

should match date of test)

Pictures Meter picture should show permanent plaque

(visible at eye level) that includes a warning about generator

installed

Pictures If the AC utility disconnect switch is not grouped

with and adjacent to the utility revenue meter then a

permanent plaque (visible at eye level) that clearly identifies

the location of the AC utility disconnect is required

23National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

Evidence of insurance is required for all projects gt 60kW in

MA and gt50kW in RI Refer to the ISA and Interconnection

Tariff for insurance requirements

Qualifying Facility documents

Schedule A (P-Rate) required for all QF projects

W9 (Only for projects gt60kW)

ACH (Only for projects gt60kW)

Supplier Enrollment Form (Only for projects gt60kW)

24National Grid | July Interconnection Webinar | July 16 2020

Metering Reminder

Projects greater than 60kW in MA and greater than 25kW in RI

require interval metering (Wireless or phone line)

Company needs a 4G wireless signal test on a Verizon network in

order to provide wireless metering

Phone lines must be dedicated and terminated at the meter

location Line must be 100 copper Fiber lines will not

communicate properly

These meters are long lead time items and prep time can be 6-8

weeks so it is important to work through this with your job owner

well in advance of when you intend to seek Authority to

Interconnect

Wireless test form httpsngusforcecomsarticleMA-

Interconnection-Documents

Standard Review

ProcessNat Mahattanasakul

05

26National Grid | July Interconnection Webinar | July 16 2020

Standard Criteria

Applies to

Projects that require Distribution System Impact Study (DSIS)

Large-scale DG projects

Generally greater than 500 kW but project specific

DG projects requiring System Modifications at the substation level

Non-listed inverters or generators other than PV

Induction Synchronous Asynchronous

Most CHP systems

All projects that do not qualify for the Simplified or Expedited process

27National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application

Application

Standard

Engineering Review

Impact StudyDetailed Study

Conditional Approval (to construct DG system)

Company Construction

Witness Test

Authorization to Interconnect

httpsngusforcecomsarticleMA-Complex-Standard-Application-Process

28National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Standard

Eligible Facilities Any DG

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Standard Process Initial Review 20 days

Send Impact Study Agreement 5 days

Complete Impact Study 55-60 days or by mutual agreement depending on complexity

Complete Detailed Study (if needed) 30 ndash 60 days or by mutual agreement depending on complexity

Send Executable Agreement (ISA) 15 days

Total Maximum Days 135160 days (200 days for Standard Complex)

Construction Schedule Varied

Witness Test10 days from the Companyrsquos approval of WT procedures or

by mutual agreement

29National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Impact Study will determine the level of impact on the Companyrsquos EPS and the required System

Modifications

Impact and Detailed Study (if applicable) will determine System Modifications required and cost

(Risk of Islanding)

ISO-NE Generator Notification Process will be required for applications that are greater than 1MW

but less than 5MW (ie PP5-1 or GNF) and a Proposed Plan Application (PPA) along with supporting Transmission System Impact Study (TSIS) will be required for applications 5MW or greater in size single or potentially in aggregate Size of project based on nameplate rating of

system

These requirements will add time to the DG Interconnection Process if there is an ASO hold If so

the DSIS will be placed on hold until the ISO-NE approval or determination is known likely at a point during the DSIS process

Interconnection Service Agreement (ISA) provided after Study completed or an Early ISA could be requested if Detailed Study is required

If substation modifications required Company has 60 BD for Study (MDPU 1320 ndash pg 50) or by mutual agreement if estimated construction cost greater than $1 million

30National Grid | July Interconnection Webinar | July 16 2020

New CEI Structure

Process Improvement

amp Future TopicsWill Kern

06

32National Grid | July Interconnection Webinar | July 16 2020

Process Improvement amp Future Topics

Potential webinar topics

Verizon initiatives

Hosting Capacity Maps

Metering

Mike Porcaro as Ombudsperson

Questions

07

34National Grid | July Interconnection Webinar | July 16 2020

Appendix Summary of Resources Documents amp Links

Distributed Generation Website ndash

httpswww9nationalgriduscommasselectrichomeenergyeffdistributed_gen

erationasp

Interconnection Process Resources ndash

httpswww9nationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

Storage Assistance -

httpsngusforcecomsarticleStorage-Assistance

DPU Interim Guidance for ESS -

httpsngusforcecomsarticleHow-to-Add-Energy-Storage-to-an-In-Progress-Application-in-Massachusetts

| [Insert document title] | [Insert date]

Page 14: National Grid Distributed Generation Seminar

14National Grid | July Interconnection Webinar | July 16 2020

Common Holds or Concerns

Application

The application must match the customerrsquos account name address

account number and meter number

Wait to construct the system until after Conditional Approval is issued

After Conditional Approval

Complete the Service Upgrade Form so the work request can be

created and provided to the wire inspector at the before the inspection

Completion Package

Have Wire Inspection called in before submitting Completion

Documents

15National Grid | July Interconnection Webinar | July 16 2020

Recent Portal Improvements

Expedited Review

ProcessMike Armell

04

17National Grid | July Interconnection Webinar | July 16 2020

Expedited Criteria

Single phase customers with listed single-phase inverter based

systems with power ratings of gt15 kW on a radial feed

Three phase customers with listed three-phase inverter based

systems with power ratings of gt25kW on a radial feed

Any project that did not pass the Simplified process Screens

Non-Simplified projects that do not require an Impact Study

Maximum size supplemental review is based on review of

Screens

18National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application (if 500 kW or greater)

Application

Expedited

Engineering Review

Supplemental Review

Conditional Approval (to construct DG system)

Company Construction

Witness Test (where applicable)

Completion Document Review and Meter Set

Authorization to Interconnect

httpswwwnationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

19National Grid | July Interconnection Webinar | July 16 2020

Expedited Review Path

Expedited

Eligible Facilities Listed Inverter DG

Acknowledge Receipt of Application(3 days)

Review Application for Completeness10 days

Complete Review of All Screens25 days

Complete Supplemental Review (if needed)20 days or Standard Process

Send Executable Agreement10 days

Total Maximum Days 4565 days

Construction ScheduleVaried

Notice Witness TestWithin 10 days of receiving Certificate of

Completion or by mutual agreement

If any Screens are not passed the

Company may require a Supplemental Review Agreementbefore providing an Interconnection

Service Agreement

Key threshold if aggregate

generation is less than 67 of minimum load on the

feeder Other Screens review voltage quality reliability and safety to reduce the potential

need for Impact Studies

Relay control system must be well

defined to make SupplementalReview easier

20National Grid | July Interconnection Webinar | July 16 2020

Recent Improvements

Infrastructure List View-Can be found at the bottom of the home

page on the portal

Lists of all feeders in each jurisdiction (MA NY RI) that can be

sorted by Feeder Name Substation Transformer Name

Operating District Connected DG kWAC Pending DG kWAC

whether or not the Feeders are Registered with FERC

Link to

guide httpsngusforcecomservletservletFileDownloadfile=

0150W00000FKqNQ

Developers have access in portal to view muni WO for completion

21National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

For most Expedited applications a ldquoCommissioning Memordquo on

a company letterhead is provided in lieu of Witness Test

Commissioning test should consist of the following

1 Two (2) second shutdown when disconnect open test

2 Five (5) minutes before restart when disconnect is closed test

3 Confirm system matches As-built (include most recent revision

date of as built provided)

4 List the inverter relay frequency (Hz) and trip time settings

22National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

As Built Must be PE stamped and signed dated by person

that performed the commissioning test (Signature date

should match date of test)

Pictures Meter picture should show permanent plaque

(visible at eye level) that includes a warning about generator

installed

Pictures If the AC utility disconnect switch is not grouped

with and adjacent to the utility revenue meter then a

permanent plaque (visible at eye level) that clearly identifies

the location of the AC utility disconnect is required

23National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

Evidence of insurance is required for all projects gt 60kW in

MA and gt50kW in RI Refer to the ISA and Interconnection

Tariff for insurance requirements

Qualifying Facility documents

Schedule A (P-Rate) required for all QF projects

W9 (Only for projects gt60kW)

ACH (Only for projects gt60kW)

Supplier Enrollment Form (Only for projects gt60kW)

24National Grid | July Interconnection Webinar | July 16 2020

Metering Reminder

Projects greater than 60kW in MA and greater than 25kW in RI

require interval metering (Wireless or phone line)

Company needs a 4G wireless signal test on a Verizon network in

order to provide wireless metering

Phone lines must be dedicated and terminated at the meter

location Line must be 100 copper Fiber lines will not

communicate properly

These meters are long lead time items and prep time can be 6-8

weeks so it is important to work through this with your job owner

well in advance of when you intend to seek Authority to

Interconnect

Wireless test form httpsngusforcecomsarticleMA-

Interconnection-Documents

Standard Review

ProcessNat Mahattanasakul

05

26National Grid | July Interconnection Webinar | July 16 2020

Standard Criteria

Applies to

Projects that require Distribution System Impact Study (DSIS)

Large-scale DG projects

Generally greater than 500 kW but project specific

DG projects requiring System Modifications at the substation level

Non-listed inverters or generators other than PV

Induction Synchronous Asynchronous

Most CHP systems

All projects that do not qualify for the Simplified or Expedited process

27National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application

Application

Standard

Engineering Review

Impact StudyDetailed Study

Conditional Approval (to construct DG system)

Company Construction

Witness Test

Authorization to Interconnect

httpsngusforcecomsarticleMA-Complex-Standard-Application-Process

28National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Standard

Eligible Facilities Any DG

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Standard Process Initial Review 20 days

Send Impact Study Agreement 5 days

Complete Impact Study 55-60 days or by mutual agreement depending on complexity

Complete Detailed Study (if needed) 30 ndash 60 days or by mutual agreement depending on complexity

Send Executable Agreement (ISA) 15 days

Total Maximum Days 135160 days (200 days for Standard Complex)

Construction Schedule Varied

Witness Test10 days from the Companyrsquos approval of WT procedures or

by mutual agreement

29National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Impact Study will determine the level of impact on the Companyrsquos EPS and the required System

Modifications

Impact and Detailed Study (if applicable) will determine System Modifications required and cost

(Risk of Islanding)

ISO-NE Generator Notification Process will be required for applications that are greater than 1MW

but less than 5MW (ie PP5-1 or GNF) and a Proposed Plan Application (PPA) along with supporting Transmission System Impact Study (TSIS) will be required for applications 5MW or greater in size single or potentially in aggregate Size of project based on nameplate rating of

system

These requirements will add time to the DG Interconnection Process if there is an ASO hold If so

the DSIS will be placed on hold until the ISO-NE approval or determination is known likely at a point during the DSIS process

Interconnection Service Agreement (ISA) provided after Study completed or an Early ISA could be requested if Detailed Study is required

If substation modifications required Company has 60 BD for Study (MDPU 1320 ndash pg 50) or by mutual agreement if estimated construction cost greater than $1 million

30National Grid | July Interconnection Webinar | July 16 2020

New CEI Structure

Process Improvement

amp Future TopicsWill Kern

06

32National Grid | July Interconnection Webinar | July 16 2020

Process Improvement amp Future Topics

Potential webinar topics

Verizon initiatives

Hosting Capacity Maps

Metering

Mike Porcaro as Ombudsperson

Questions

07

34National Grid | July Interconnection Webinar | July 16 2020

Appendix Summary of Resources Documents amp Links

Distributed Generation Website ndash

httpswww9nationalgriduscommasselectrichomeenergyeffdistributed_gen

erationasp

Interconnection Process Resources ndash

httpswww9nationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

Storage Assistance -

httpsngusforcecomsarticleStorage-Assistance

DPU Interim Guidance for ESS -

httpsngusforcecomsarticleHow-to-Add-Energy-Storage-to-an-In-Progress-Application-in-Massachusetts

| [Insert document title] | [Insert date]

Page 15: National Grid Distributed Generation Seminar

15National Grid | July Interconnection Webinar | July 16 2020

Recent Portal Improvements

Expedited Review

ProcessMike Armell

04

17National Grid | July Interconnection Webinar | July 16 2020

Expedited Criteria

Single phase customers with listed single-phase inverter based

systems with power ratings of gt15 kW on a radial feed

Three phase customers with listed three-phase inverter based

systems with power ratings of gt25kW on a radial feed

Any project that did not pass the Simplified process Screens

Non-Simplified projects that do not require an Impact Study

Maximum size supplemental review is based on review of

Screens

18National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application (if 500 kW or greater)

Application

Expedited

Engineering Review

Supplemental Review

Conditional Approval (to construct DG system)

Company Construction

Witness Test (where applicable)

Completion Document Review and Meter Set

Authorization to Interconnect

httpswwwnationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

19National Grid | July Interconnection Webinar | July 16 2020

Expedited Review Path

Expedited

Eligible Facilities Listed Inverter DG

Acknowledge Receipt of Application(3 days)

Review Application for Completeness10 days

Complete Review of All Screens25 days

Complete Supplemental Review (if needed)20 days or Standard Process

Send Executable Agreement10 days

Total Maximum Days 4565 days

Construction ScheduleVaried

Notice Witness TestWithin 10 days of receiving Certificate of

Completion or by mutual agreement

If any Screens are not passed the

Company may require a Supplemental Review Agreementbefore providing an Interconnection

Service Agreement

Key threshold if aggregate

generation is less than 67 of minimum load on the

feeder Other Screens review voltage quality reliability and safety to reduce the potential

need for Impact Studies

Relay control system must be well

defined to make SupplementalReview easier

20National Grid | July Interconnection Webinar | July 16 2020

Recent Improvements

Infrastructure List View-Can be found at the bottom of the home

page on the portal

Lists of all feeders in each jurisdiction (MA NY RI) that can be

sorted by Feeder Name Substation Transformer Name

Operating District Connected DG kWAC Pending DG kWAC

whether or not the Feeders are Registered with FERC

Link to

guide httpsngusforcecomservletservletFileDownloadfile=

0150W00000FKqNQ

Developers have access in portal to view muni WO for completion

21National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

For most Expedited applications a ldquoCommissioning Memordquo on

a company letterhead is provided in lieu of Witness Test

Commissioning test should consist of the following

1 Two (2) second shutdown when disconnect open test

2 Five (5) minutes before restart when disconnect is closed test

3 Confirm system matches As-built (include most recent revision

date of as built provided)

4 List the inverter relay frequency (Hz) and trip time settings

22National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

As Built Must be PE stamped and signed dated by person

that performed the commissioning test (Signature date

should match date of test)

Pictures Meter picture should show permanent plaque

(visible at eye level) that includes a warning about generator

installed

Pictures If the AC utility disconnect switch is not grouped

with and adjacent to the utility revenue meter then a

permanent plaque (visible at eye level) that clearly identifies

the location of the AC utility disconnect is required

23National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

Evidence of insurance is required for all projects gt 60kW in

MA and gt50kW in RI Refer to the ISA and Interconnection

Tariff for insurance requirements

Qualifying Facility documents

Schedule A (P-Rate) required for all QF projects

W9 (Only for projects gt60kW)

ACH (Only for projects gt60kW)

Supplier Enrollment Form (Only for projects gt60kW)

24National Grid | July Interconnection Webinar | July 16 2020

Metering Reminder

Projects greater than 60kW in MA and greater than 25kW in RI

require interval metering (Wireless or phone line)

Company needs a 4G wireless signal test on a Verizon network in

order to provide wireless metering

Phone lines must be dedicated and terminated at the meter

location Line must be 100 copper Fiber lines will not

communicate properly

These meters are long lead time items and prep time can be 6-8

weeks so it is important to work through this with your job owner

well in advance of when you intend to seek Authority to

Interconnect

Wireless test form httpsngusforcecomsarticleMA-

Interconnection-Documents

Standard Review

ProcessNat Mahattanasakul

05

26National Grid | July Interconnection Webinar | July 16 2020

Standard Criteria

Applies to

Projects that require Distribution System Impact Study (DSIS)

Large-scale DG projects

Generally greater than 500 kW but project specific

DG projects requiring System Modifications at the substation level

Non-listed inverters or generators other than PV

Induction Synchronous Asynchronous

Most CHP systems

All projects that do not qualify for the Simplified or Expedited process

27National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application

Application

Standard

Engineering Review

Impact StudyDetailed Study

Conditional Approval (to construct DG system)

Company Construction

Witness Test

Authorization to Interconnect

httpsngusforcecomsarticleMA-Complex-Standard-Application-Process

28National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Standard

Eligible Facilities Any DG

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Standard Process Initial Review 20 days

Send Impact Study Agreement 5 days

Complete Impact Study 55-60 days or by mutual agreement depending on complexity

Complete Detailed Study (if needed) 30 ndash 60 days or by mutual agreement depending on complexity

Send Executable Agreement (ISA) 15 days

Total Maximum Days 135160 days (200 days for Standard Complex)

Construction Schedule Varied

Witness Test10 days from the Companyrsquos approval of WT procedures or

by mutual agreement

29National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Impact Study will determine the level of impact on the Companyrsquos EPS and the required System

Modifications

Impact and Detailed Study (if applicable) will determine System Modifications required and cost

(Risk of Islanding)

ISO-NE Generator Notification Process will be required for applications that are greater than 1MW

but less than 5MW (ie PP5-1 or GNF) and a Proposed Plan Application (PPA) along with supporting Transmission System Impact Study (TSIS) will be required for applications 5MW or greater in size single or potentially in aggregate Size of project based on nameplate rating of

system

These requirements will add time to the DG Interconnection Process if there is an ASO hold If so

the DSIS will be placed on hold until the ISO-NE approval or determination is known likely at a point during the DSIS process

Interconnection Service Agreement (ISA) provided after Study completed or an Early ISA could be requested if Detailed Study is required

If substation modifications required Company has 60 BD for Study (MDPU 1320 ndash pg 50) or by mutual agreement if estimated construction cost greater than $1 million

30National Grid | July Interconnection Webinar | July 16 2020

New CEI Structure

Process Improvement

amp Future TopicsWill Kern

06

32National Grid | July Interconnection Webinar | July 16 2020

Process Improvement amp Future Topics

Potential webinar topics

Verizon initiatives

Hosting Capacity Maps

Metering

Mike Porcaro as Ombudsperson

Questions

07

34National Grid | July Interconnection Webinar | July 16 2020

Appendix Summary of Resources Documents amp Links

Distributed Generation Website ndash

httpswww9nationalgriduscommasselectrichomeenergyeffdistributed_gen

erationasp

Interconnection Process Resources ndash

httpswww9nationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

Storage Assistance -

httpsngusforcecomsarticleStorage-Assistance

DPU Interim Guidance for ESS -

httpsngusforcecomsarticleHow-to-Add-Energy-Storage-to-an-In-Progress-Application-in-Massachusetts

| [Insert document title] | [Insert date]

Page 16: National Grid Distributed Generation Seminar

Expedited Review

ProcessMike Armell

04

17National Grid | July Interconnection Webinar | July 16 2020

Expedited Criteria

Single phase customers with listed single-phase inverter based

systems with power ratings of gt15 kW on a radial feed

Three phase customers with listed three-phase inverter based

systems with power ratings of gt25kW on a radial feed

Any project that did not pass the Simplified process Screens

Non-Simplified projects that do not require an Impact Study

Maximum size supplemental review is based on review of

Screens

18National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application (if 500 kW or greater)

Application

Expedited

Engineering Review

Supplemental Review

Conditional Approval (to construct DG system)

Company Construction

Witness Test (where applicable)

Completion Document Review and Meter Set

Authorization to Interconnect

httpswwwnationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

19National Grid | July Interconnection Webinar | July 16 2020

Expedited Review Path

Expedited

Eligible Facilities Listed Inverter DG

Acknowledge Receipt of Application(3 days)

Review Application for Completeness10 days

Complete Review of All Screens25 days

Complete Supplemental Review (if needed)20 days or Standard Process

Send Executable Agreement10 days

Total Maximum Days 4565 days

Construction ScheduleVaried

Notice Witness TestWithin 10 days of receiving Certificate of

Completion or by mutual agreement

If any Screens are not passed the

Company may require a Supplemental Review Agreementbefore providing an Interconnection

Service Agreement

Key threshold if aggregate

generation is less than 67 of minimum load on the

feeder Other Screens review voltage quality reliability and safety to reduce the potential

need for Impact Studies

Relay control system must be well

defined to make SupplementalReview easier

20National Grid | July Interconnection Webinar | July 16 2020

Recent Improvements

Infrastructure List View-Can be found at the bottom of the home

page on the portal

Lists of all feeders in each jurisdiction (MA NY RI) that can be

sorted by Feeder Name Substation Transformer Name

Operating District Connected DG kWAC Pending DG kWAC

whether or not the Feeders are Registered with FERC

Link to

guide httpsngusforcecomservletservletFileDownloadfile=

0150W00000FKqNQ

Developers have access in portal to view muni WO for completion

21National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

For most Expedited applications a ldquoCommissioning Memordquo on

a company letterhead is provided in lieu of Witness Test

Commissioning test should consist of the following

1 Two (2) second shutdown when disconnect open test

2 Five (5) minutes before restart when disconnect is closed test

3 Confirm system matches As-built (include most recent revision

date of as built provided)

4 List the inverter relay frequency (Hz) and trip time settings

22National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

As Built Must be PE stamped and signed dated by person

that performed the commissioning test (Signature date

should match date of test)

Pictures Meter picture should show permanent plaque

(visible at eye level) that includes a warning about generator

installed

Pictures If the AC utility disconnect switch is not grouped

with and adjacent to the utility revenue meter then a

permanent plaque (visible at eye level) that clearly identifies

the location of the AC utility disconnect is required

23National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

Evidence of insurance is required for all projects gt 60kW in

MA and gt50kW in RI Refer to the ISA and Interconnection

Tariff for insurance requirements

Qualifying Facility documents

Schedule A (P-Rate) required for all QF projects

W9 (Only for projects gt60kW)

ACH (Only for projects gt60kW)

Supplier Enrollment Form (Only for projects gt60kW)

24National Grid | July Interconnection Webinar | July 16 2020

Metering Reminder

Projects greater than 60kW in MA and greater than 25kW in RI

require interval metering (Wireless or phone line)

Company needs a 4G wireless signal test on a Verizon network in

order to provide wireless metering

Phone lines must be dedicated and terminated at the meter

location Line must be 100 copper Fiber lines will not

communicate properly

These meters are long lead time items and prep time can be 6-8

weeks so it is important to work through this with your job owner

well in advance of when you intend to seek Authority to

Interconnect

Wireless test form httpsngusforcecomsarticleMA-

Interconnection-Documents

Standard Review

ProcessNat Mahattanasakul

05

26National Grid | July Interconnection Webinar | July 16 2020

Standard Criteria

Applies to

Projects that require Distribution System Impact Study (DSIS)

Large-scale DG projects

Generally greater than 500 kW but project specific

DG projects requiring System Modifications at the substation level

Non-listed inverters or generators other than PV

Induction Synchronous Asynchronous

Most CHP systems

All projects that do not qualify for the Simplified or Expedited process

27National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application

Application

Standard

Engineering Review

Impact StudyDetailed Study

Conditional Approval (to construct DG system)

Company Construction

Witness Test

Authorization to Interconnect

httpsngusforcecomsarticleMA-Complex-Standard-Application-Process

28National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Standard

Eligible Facilities Any DG

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Standard Process Initial Review 20 days

Send Impact Study Agreement 5 days

Complete Impact Study 55-60 days or by mutual agreement depending on complexity

Complete Detailed Study (if needed) 30 ndash 60 days or by mutual agreement depending on complexity

Send Executable Agreement (ISA) 15 days

Total Maximum Days 135160 days (200 days for Standard Complex)

Construction Schedule Varied

Witness Test10 days from the Companyrsquos approval of WT procedures or

by mutual agreement

29National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Impact Study will determine the level of impact on the Companyrsquos EPS and the required System

Modifications

Impact and Detailed Study (if applicable) will determine System Modifications required and cost

(Risk of Islanding)

ISO-NE Generator Notification Process will be required for applications that are greater than 1MW

but less than 5MW (ie PP5-1 or GNF) and a Proposed Plan Application (PPA) along with supporting Transmission System Impact Study (TSIS) will be required for applications 5MW or greater in size single or potentially in aggregate Size of project based on nameplate rating of

system

These requirements will add time to the DG Interconnection Process if there is an ASO hold If so

the DSIS will be placed on hold until the ISO-NE approval or determination is known likely at a point during the DSIS process

Interconnection Service Agreement (ISA) provided after Study completed or an Early ISA could be requested if Detailed Study is required

If substation modifications required Company has 60 BD for Study (MDPU 1320 ndash pg 50) or by mutual agreement if estimated construction cost greater than $1 million

30National Grid | July Interconnection Webinar | July 16 2020

New CEI Structure

Process Improvement

amp Future TopicsWill Kern

06

32National Grid | July Interconnection Webinar | July 16 2020

Process Improvement amp Future Topics

Potential webinar topics

Verizon initiatives

Hosting Capacity Maps

Metering

Mike Porcaro as Ombudsperson

Questions

07

34National Grid | July Interconnection Webinar | July 16 2020

Appendix Summary of Resources Documents amp Links

Distributed Generation Website ndash

httpswww9nationalgriduscommasselectrichomeenergyeffdistributed_gen

erationasp

Interconnection Process Resources ndash

httpswww9nationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

Storage Assistance -

httpsngusforcecomsarticleStorage-Assistance

DPU Interim Guidance for ESS -

httpsngusforcecomsarticleHow-to-Add-Energy-Storage-to-an-In-Progress-Application-in-Massachusetts

| [Insert document title] | [Insert date]

Page 17: National Grid Distributed Generation Seminar

17National Grid | July Interconnection Webinar | July 16 2020

Expedited Criteria

Single phase customers with listed single-phase inverter based

systems with power ratings of gt15 kW on a radial feed

Three phase customers with listed three-phase inverter based

systems with power ratings of gt25kW on a radial feed

Any project that did not pass the Simplified process Screens

Non-Simplified projects that do not require an Impact Study

Maximum size supplemental review is based on review of

Screens

18National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application (if 500 kW or greater)

Application

Expedited

Engineering Review

Supplemental Review

Conditional Approval (to construct DG system)

Company Construction

Witness Test (where applicable)

Completion Document Review and Meter Set

Authorization to Interconnect

httpswwwnationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

19National Grid | July Interconnection Webinar | July 16 2020

Expedited Review Path

Expedited

Eligible Facilities Listed Inverter DG

Acknowledge Receipt of Application(3 days)

Review Application for Completeness10 days

Complete Review of All Screens25 days

Complete Supplemental Review (if needed)20 days or Standard Process

Send Executable Agreement10 days

Total Maximum Days 4565 days

Construction ScheduleVaried

Notice Witness TestWithin 10 days of receiving Certificate of

Completion or by mutual agreement

If any Screens are not passed the

Company may require a Supplemental Review Agreementbefore providing an Interconnection

Service Agreement

Key threshold if aggregate

generation is less than 67 of minimum load on the

feeder Other Screens review voltage quality reliability and safety to reduce the potential

need for Impact Studies

Relay control system must be well

defined to make SupplementalReview easier

20National Grid | July Interconnection Webinar | July 16 2020

Recent Improvements

Infrastructure List View-Can be found at the bottom of the home

page on the portal

Lists of all feeders in each jurisdiction (MA NY RI) that can be

sorted by Feeder Name Substation Transformer Name

Operating District Connected DG kWAC Pending DG kWAC

whether or not the Feeders are Registered with FERC

Link to

guide httpsngusforcecomservletservletFileDownloadfile=

0150W00000FKqNQ

Developers have access in portal to view muni WO for completion

21National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

For most Expedited applications a ldquoCommissioning Memordquo on

a company letterhead is provided in lieu of Witness Test

Commissioning test should consist of the following

1 Two (2) second shutdown when disconnect open test

2 Five (5) minutes before restart when disconnect is closed test

3 Confirm system matches As-built (include most recent revision

date of as built provided)

4 List the inverter relay frequency (Hz) and trip time settings

22National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

As Built Must be PE stamped and signed dated by person

that performed the commissioning test (Signature date

should match date of test)

Pictures Meter picture should show permanent plaque

(visible at eye level) that includes a warning about generator

installed

Pictures If the AC utility disconnect switch is not grouped

with and adjacent to the utility revenue meter then a

permanent plaque (visible at eye level) that clearly identifies

the location of the AC utility disconnect is required

23National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

Evidence of insurance is required for all projects gt 60kW in

MA and gt50kW in RI Refer to the ISA and Interconnection

Tariff for insurance requirements

Qualifying Facility documents

Schedule A (P-Rate) required for all QF projects

W9 (Only for projects gt60kW)

ACH (Only for projects gt60kW)

Supplier Enrollment Form (Only for projects gt60kW)

24National Grid | July Interconnection Webinar | July 16 2020

Metering Reminder

Projects greater than 60kW in MA and greater than 25kW in RI

require interval metering (Wireless or phone line)

Company needs a 4G wireless signal test on a Verizon network in

order to provide wireless metering

Phone lines must be dedicated and terminated at the meter

location Line must be 100 copper Fiber lines will not

communicate properly

These meters are long lead time items and prep time can be 6-8

weeks so it is important to work through this with your job owner

well in advance of when you intend to seek Authority to

Interconnect

Wireless test form httpsngusforcecomsarticleMA-

Interconnection-Documents

Standard Review

ProcessNat Mahattanasakul

05

26National Grid | July Interconnection Webinar | July 16 2020

Standard Criteria

Applies to

Projects that require Distribution System Impact Study (DSIS)

Large-scale DG projects

Generally greater than 500 kW but project specific

DG projects requiring System Modifications at the substation level

Non-listed inverters or generators other than PV

Induction Synchronous Asynchronous

Most CHP systems

All projects that do not qualify for the Simplified or Expedited process

27National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application

Application

Standard

Engineering Review

Impact StudyDetailed Study

Conditional Approval (to construct DG system)

Company Construction

Witness Test

Authorization to Interconnect

httpsngusforcecomsarticleMA-Complex-Standard-Application-Process

28National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Standard

Eligible Facilities Any DG

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Standard Process Initial Review 20 days

Send Impact Study Agreement 5 days

Complete Impact Study 55-60 days or by mutual agreement depending on complexity

Complete Detailed Study (if needed) 30 ndash 60 days or by mutual agreement depending on complexity

Send Executable Agreement (ISA) 15 days

Total Maximum Days 135160 days (200 days for Standard Complex)

Construction Schedule Varied

Witness Test10 days from the Companyrsquos approval of WT procedures or

by mutual agreement

29National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Impact Study will determine the level of impact on the Companyrsquos EPS and the required System

Modifications

Impact and Detailed Study (if applicable) will determine System Modifications required and cost

(Risk of Islanding)

ISO-NE Generator Notification Process will be required for applications that are greater than 1MW

but less than 5MW (ie PP5-1 or GNF) and a Proposed Plan Application (PPA) along with supporting Transmission System Impact Study (TSIS) will be required for applications 5MW or greater in size single or potentially in aggregate Size of project based on nameplate rating of

system

These requirements will add time to the DG Interconnection Process if there is an ASO hold If so

the DSIS will be placed on hold until the ISO-NE approval or determination is known likely at a point during the DSIS process

Interconnection Service Agreement (ISA) provided after Study completed or an Early ISA could be requested if Detailed Study is required

If substation modifications required Company has 60 BD for Study (MDPU 1320 ndash pg 50) or by mutual agreement if estimated construction cost greater than $1 million

30National Grid | July Interconnection Webinar | July 16 2020

New CEI Structure

Process Improvement

amp Future TopicsWill Kern

06

32National Grid | July Interconnection Webinar | July 16 2020

Process Improvement amp Future Topics

Potential webinar topics

Verizon initiatives

Hosting Capacity Maps

Metering

Mike Porcaro as Ombudsperson

Questions

07

34National Grid | July Interconnection Webinar | July 16 2020

Appendix Summary of Resources Documents amp Links

Distributed Generation Website ndash

httpswww9nationalgriduscommasselectrichomeenergyeffdistributed_gen

erationasp

Interconnection Process Resources ndash

httpswww9nationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

Storage Assistance -

httpsngusforcecomsarticleStorage-Assistance

DPU Interim Guidance for ESS -

httpsngusforcecomsarticleHow-to-Add-Energy-Storage-to-an-In-Progress-Application-in-Massachusetts

| [Insert document title] | [Insert date]

Page 18: National Grid Distributed Generation Seminar

18National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application (if 500 kW or greater)

Application

Expedited

Engineering Review

Supplemental Review

Conditional Approval (to construct DG system)

Company Construction

Witness Test (where applicable)

Completion Document Review and Meter Set

Authorization to Interconnect

httpswwwnationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

19National Grid | July Interconnection Webinar | July 16 2020

Expedited Review Path

Expedited

Eligible Facilities Listed Inverter DG

Acknowledge Receipt of Application(3 days)

Review Application for Completeness10 days

Complete Review of All Screens25 days

Complete Supplemental Review (if needed)20 days or Standard Process

Send Executable Agreement10 days

Total Maximum Days 4565 days

Construction ScheduleVaried

Notice Witness TestWithin 10 days of receiving Certificate of

Completion or by mutual agreement

If any Screens are not passed the

Company may require a Supplemental Review Agreementbefore providing an Interconnection

Service Agreement

Key threshold if aggregate

generation is less than 67 of minimum load on the

feeder Other Screens review voltage quality reliability and safety to reduce the potential

need for Impact Studies

Relay control system must be well

defined to make SupplementalReview easier

20National Grid | July Interconnection Webinar | July 16 2020

Recent Improvements

Infrastructure List View-Can be found at the bottom of the home

page on the portal

Lists of all feeders in each jurisdiction (MA NY RI) that can be

sorted by Feeder Name Substation Transformer Name

Operating District Connected DG kWAC Pending DG kWAC

whether or not the Feeders are Registered with FERC

Link to

guide httpsngusforcecomservletservletFileDownloadfile=

0150W00000FKqNQ

Developers have access in portal to view muni WO for completion

21National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

For most Expedited applications a ldquoCommissioning Memordquo on

a company letterhead is provided in lieu of Witness Test

Commissioning test should consist of the following

1 Two (2) second shutdown when disconnect open test

2 Five (5) minutes before restart when disconnect is closed test

3 Confirm system matches As-built (include most recent revision

date of as built provided)

4 List the inverter relay frequency (Hz) and trip time settings

22National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

As Built Must be PE stamped and signed dated by person

that performed the commissioning test (Signature date

should match date of test)

Pictures Meter picture should show permanent plaque

(visible at eye level) that includes a warning about generator

installed

Pictures If the AC utility disconnect switch is not grouped

with and adjacent to the utility revenue meter then a

permanent plaque (visible at eye level) that clearly identifies

the location of the AC utility disconnect is required

23National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

Evidence of insurance is required for all projects gt 60kW in

MA and gt50kW in RI Refer to the ISA and Interconnection

Tariff for insurance requirements

Qualifying Facility documents

Schedule A (P-Rate) required for all QF projects

W9 (Only for projects gt60kW)

ACH (Only for projects gt60kW)

Supplier Enrollment Form (Only for projects gt60kW)

24National Grid | July Interconnection Webinar | July 16 2020

Metering Reminder

Projects greater than 60kW in MA and greater than 25kW in RI

require interval metering (Wireless or phone line)

Company needs a 4G wireless signal test on a Verizon network in

order to provide wireless metering

Phone lines must be dedicated and terminated at the meter

location Line must be 100 copper Fiber lines will not

communicate properly

These meters are long lead time items and prep time can be 6-8

weeks so it is important to work through this with your job owner

well in advance of when you intend to seek Authority to

Interconnect

Wireless test form httpsngusforcecomsarticleMA-

Interconnection-Documents

Standard Review

ProcessNat Mahattanasakul

05

26National Grid | July Interconnection Webinar | July 16 2020

Standard Criteria

Applies to

Projects that require Distribution System Impact Study (DSIS)

Large-scale DG projects

Generally greater than 500 kW but project specific

DG projects requiring System Modifications at the substation level

Non-listed inverters or generators other than PV

Induction Synchronous Asynchronous

Most CHP systems

All projects that do not qualify for the Simplified or Expedited process

27National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application

Application

Standard

Engineering Review

Impact StudyDetailed Study

Conditional Approval (to construct DG system)

Company Construction

Witness Test

Authorization to Interconnect

httpsngusforcecomsarticleMA-Complex-Standard-Application-Process

28National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Standard

Eligible Facilities Any DG

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Standard Process Initial Review 20 days

Send Impact Study Agreement 5 days

Complete Impact Study 55-60 days or by mutual agreement depending on complexity

Complete Detailed Study (if needed) 30 ndash 60 days or by mutual agreement depending on complexity

Send Executable Agreement (ISA) 15 days

Total Maximum Days 135160 days (200 days for Standard Complex)

Construction Schedule Varied

Witness Test10 days from the Companyrsquos approval of WT procedures or

by mutual agreement

29National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Impact Study will determine the level of impact on the Companyrsquos EPS and the required System

Modifications

Impact and Detailed Study (if applicable) will determine System Modifications required and cost

(Risk of Islanding)

ISO-NE Generator Notification Process will be required for applications that are greater than 1MW

but less than 5MW (ie PP5-1 or GNF) and a Proposed Plan Application (PPA) along with supporting Transmission System Impact Study (TSIS) will be required for applications 5MW or greater in size single or potentially in aggregate Size of project based on nameplate rating of

system

These requirements will add time to the DG Interconnection Process if there is an ASO hold If so

the DSIS will be placed on hold until the ISO-NE approval or determination is known likely at a point during the DSIS process

Interconnection Service Agreement (ISA) provided after Study completed or an Early ISA could be requested if Detailed Study is required

If substation modifications required Company has 60 BD for Study (MDPU 1320 ndash pg 50) or by mutual agreement if estimated construction cost greater than $1 million

30National Grid | July Interconnection Webinar | July 16 2020

New CEI Structure

Process Improvement

amp Future TopicsWill Kern

06

32National Grid | July Interconnection Webinar | July 16 2020

Process Improvement amp Future Topics

Potential webinar topics

Verizon initiatives

Hosting Capacity Maps

Metering

Mike Porcaro as Ombudsperson

Questions

07

34National Grid | July Interconnection Webinar | July 16 2020

Appendix Summary of Resources Documents amp Links

Distributed Generation Website ndash

httpswww9nationalgriduscommasselectrichomeenergyeffdistributed_gen

erationasp

Interconnection Process Resources ndash

httpswww9nationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

Storage Assistance -

httpsngusforcecomsarticleStorage-Assistance

DPU Interim Guidance for ESS -

httpsngusforcecomsarticleHow-to-Add-Energy-Storage-to-an-In-Progress-Application-in-Massachusetts

| [Insert document title] | [Insert date]

Page 19: National Grid Distributed Generation Seminar

19National Grid | July Interconnection Webinar | July 16 2020

Expedited Review Path

Expedited

Eligible Facilities Listed Inverter DG

Acknowledge Receipt of Application(3 days)

Review Application for Completeness10 days

Complete Review of All Screens25 days

Complete Supplemental Review (if needed)20 days or Standard Process

Send Executable Agreement10 days

Total Maximum Days 4565 days

Construction ScheduleVaried

Notice Witness TestWithin 10 days of receiving Certificate of

Completion or by mutual agreement

If any Screens are not passed the

Company may require a Supplemental Review Agreementbefore providing an Interconnection

Service Agreement

Key threshold if aggregate

generation is less than 67 of minimum load on the

feeder Other Screens review voltage quality reliability and safety to reduce the potential

need for Impact Studies

Relay control system must be well

defined to make SupplementalReview easier

20National Grid | July Interconnection Webinar | July 16 2020

Recent Improvements

Infrastructure List View-Can be found at the bottom of the home

page on the portal

Lists of all feeders in each jurisdiction (MA NY RI) that can be

sorted by Feeder Name Substation Transformer Name

Operating District Connected DG kWAC Pending DG kWAC

whether or not the Feeders are Registered with FERC

Link to

guide httpsngusforcecomservletservletFileDownloadfile=

0150W00000FKqNQ

Developers have access in portal to view muni WO for completion

21National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

For most Expedited applications a ldquoCommissioning Memordquo on

a company letterhead is provided in lieu of Witness Test

Commissioning test should consist of the following

1 Two (2) second shutdown when disconnect open test

2 Five (5) minutes before restart when disconnect is closed test

3 Confirm system matches As-built (include most recent revision

date of as built provided)

4 List the inverter relay frequency (Hz) and trip time settings

22National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

As Built Must be PE stamped and signed dated by person

that performed the commissioning test (Signature date

should match date of test)

Pictures Meter picture should show permanent plaque

(visible at eye level) that includes a warning about generator

installed

Pictures If the AC utility disconnect switch is not grouped

with and adjacent to the utility revenue meter then a

permanent plaque (visible at eye level) that clearly identifies

the location of the AC utility disconnect is required

23National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

Evidence of insurance is required for all projects gt 60kW in

MA and gt50kW in RI Refer to the ISA and Interconnection

Tariff for insurance requirements

Qualifying Facility documents

Schedule A (P-Rate) required for all QF projects

W9 (Only for projects gt60kW)

ACH (Only for projects gt60kW)

Supplier Enrollment Form (Only for projects gt60kW)

24National Grid | July Interconnection Webinar | July 16 2020

Metering Reminder

Projects greater than 60kW in MA and greater than 25kW in RI

require interval metering (Wireless or phone line)

Company needs a 4G wireless signal test on a Verizon network in

order to provide wireless metering

Phone lines must be dedicated and terminated at the meter

location Line must be 100 copper Fiber lines will not

communicate properly

These meters are long lead time items and prep time can be 6-8

weeks so it is important to work through this with your job owner

well in advance of when you intend to seek Authority to

Interconnect

Wireless test form httpsngusforcecomsarticleMA-

Interconnection-Documents

Standard Review

ProcessNat Mahattanasakul

05

26National Grid | July Interconnection Webinar | July 16 2020

Standard Criteria

Applies to

Projects that require Distribution System Impact Study (DSIS)

Large-scale DG projects

Generally greater than 500 kW but project specific

DG projects requiring System Modifications at the substation level

Non-listed inverters or generators other than PV

Induction Synchronous Asynchronous

Most CHP systems

All projects that do not qualify for the Simplified or Expedited process

27National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application

Application

Standard

Engineering Review

Impact StudyDetailed Study

Conditional Approval (to construct DG system)

Company Construction

Witness Test

Authorization to Interconnect

httpsngusforcecomsarticleMA-Complex-Standard-Application-Process

28National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Standard

Eligible Facilities Any DG

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Standard Process Initial Review 20 days

Send Impact Study Agreement 5 days

Complete Impact Study 55-60 days or by mutual agreement depending on complexity

Complete Detailed Study (if needed) 30 ndash 60 days or by mutual agreement depending on complexity

Send Executable Agreement (ISA) 15 days

Total Maximum Days 135160 days (200 days for Standard Complex)

Construction Schedule Varied

Witness Test10 days from the Companyrsquos approval of WT procedures or

by mutual agreement

29National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Impact Study will determine the level of impact on the Companyrsquos EPS and the required System

Modifications

Impact and Detailed Study (if applicable) will determine System Modifications required and cost

(Risk of Islanding)

ISO-NE Generator Notification Process will be required for applications that are greater than 1MW

but less than 5MW (ie PP5-1 or GNF) and a Proposed Plan Application (PPA) along with supporting Transmission System Impact Study (TSIS) will be required for applications 5MW or greater in size single or potentially in aggregate Size of project based on nameplate rating of

system

These requirements will add time to the DG Interconnection Process if there is an ASO hold If so

the DSIS will be placed on hold until the ISO-NE approval or determination is known likely at a point during the DSIS process

Interconnection Service Agreement (ISA) provided after Study completed or an Early ISA could be requested if Detailed Study is required

If substation modifications required Company has 60 BD for Study (MDPU 1320 ndash pg 50) or by mutual agreement if estimated construction cost greater than $1 million

30National Grid | July Interconnection Webinar | July 16 2020

New CEI Structure

Process Improvement

amp Future TopicsWill Kern

06

32National Grid | July Interconnection Webinar | July 16 2020

Process Improvement amp Future Topics

Potential webinar topics

Verizon initiatives

Hosting Capacity Maps

Metering

Mike Porcaro as Ombudsperson

Questions

07

34National Grid | July Interconnection Webinar | July 16 2020

Appendix Summary of Resources Documents amp Links

Distributed Generation Website ndash

httpswww9nationalgriduscommasselectrichomeenergyeffdistributed_gen

erationasp

Interconnection Process Resources ndash

httpswww9nationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

Storage Assistance -

httpsngusforcecomsarticleStorage-Assistance

DPU Interim Guidance for ESS -

httpsngusforcecomsarticleHow-to-Add-Energy-Storage-to-an-In-Progress-Application-in-Massachusetts

| [Insert document title] | [Insert date]

Page 20: National Grid Distributed Generation Seminar

20National Grid | July Interconnection Webinar | July 16 2020

Recent Improvements

Infrastructure List View-Can be found at the bottom of the home

page on the portal

Lists of all feeders in each jurisdiction (MA NY RI) that can be

sorted by Feeder Name Substation Transformer Name

Operating District Connected DG kWAC Pending DG kWAC

whether or not the Feeders are Registered with FERC

Link to

guide httpsngusforcecomservletservletFileDownloadfile=

0150W00000FKqNQ

Developers have access in portal to view muni WO for completion

21National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

For most Expedited applications a ldquoCommissioning Memordquo on

a company letterhead is provided in lieu of Witness Test

Commissioning test should consist of the following

1 Two (2) second shutdown when disconnect open test

2 Five (5) minutes before restart when disconnect is closed test

3 Confirm system matches As-built (include most recent revision

date of as built provided)

4 List the inverter relay frequency (Hz) and trip time settings

22National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

As Built Must be PE stamped and signed dated by person

that performed the commissioning test (Signature date

should match date of test)

Pictures Meter picture should show permanent plaque

(visible at eye level) that includes a warning about generator

installed

Pictures If the AC utility disconnect switch is not grouped

with and adjacent to the utility revenue meter then a

permanent plaque (visible at eye level) that clearly identifies

the location of the AC utility disconnect is required

23National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

Evidence of insurance is required for all projects gt 60kW in

MA and gt50kW in RI Refer to the ISA and Interconnection

Tariff for insurance requirements

Qualifying Facility documents

Schedule A (P-Rate) required for all QF projects

W9 (Only for projects gt60kW)

ACH (Only for projects gt60kW)

Supplier Enrollment Form (Only for projects gt60kW)

24National Grid | July Interconnection Webinar | July 16 2020

Metering Reminder

Projects greater than 60kW in MA and greater than 25kW in RI

require interval metering (Wireless or phone line)

Company needs a 4G wireless signal test on a Verizon network in

order to provide wireless metering

Phone lines must be dedicated and terminated at the meter

location Line must be 100 copper Fiber lines will not

communicate properly

These meters are long lead time items and prep time can be 6-8

weeks so it is important to work through this with your job owner

well in advance of when you intend to seek Authority to

Interconnect

Wireless test form httpsngusforcecomsarticleMA-

Interconnection-Documents

Standard Review

ProcessNat Mahattanasakul

05

26National Grid | July Interconnection Webinar | July 16 2020

Standard Criteria

Applies to

Projects that require Distribution System Impact Study (DSIS)

Large-scale DG projects

Generally greater than 500 kW but project specific

DG projects requiring System Modifications at the substation level

Non-listed inverters or generators other than PV

Induction Synchronous Asynchronous

Most CHP systems

All projects that do not qualify for the Simplified or Expedited process

27National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application

Application

Standard

Engineering Review

Impact StudyDetailed Study

Conditional Approval (to construct DG system)

Company Construction

Witness Test

Authorization to Interconnect

httpsngusforcecomsarticleMA-Complex-Standard-Application-Process

28National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Standard

Eligible Facilities Any DG

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Standard Process Initial Review 20 days

Send Impact Study Agreement 5 days

Complete Impact Study 55-60 days or by mutual agreement depending on complexity

Complete Detailed Study (if needed) 30 ndash 60 days or by mutual agreement depending on complexity

Send Executable Agreement (ISA) 15 days

Total Maximum Days 135160 days (200 days for Standard Complex)

Construction Schedule Varied

Witness Test10 days from the Companyrsquos approval of WT procedures or

by mutual agreement

29National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Impact Study will determine the level of impact on the Companyrsquos EPS and the required System

Modifications

Impact and Detailed Study (if applicable) will determine System Modifications required and cost

(Risk of Islanding)

ISO-NE Generator Notification Process will be required for applications that are greater than 1MW

but less than 5MW (ie PP5-1 or GNF) and a Proposed Plan Application (PPA) along with supporting Transmission System Impact Study (TSIS) will be required for applications 5MW or greater in size single or potentially in aggregate Size of project based on nameplate rating of

system

These requirements will add time to the DG Interconnection Process if there is an ASO hold If so

the DSIS will be placed on hold until the ISO-NE approval or determination is known likely at a point during the DSIS process

Interconnection Service Agreement (ISA) provided after Study completed or an Early ISA could be requested if Detailed Study is required

If substation modifications required Company has 60 BD for Study (MDPU 1320 ndash pg 50) or by mutual agreement if estimated construction cost greater than $1 million

30National Grid | July Interconnection Webinar | July 16 2020

New CEI Structure

Process Improvement

amp Future TopicsWill Kern

06

32National Grid | July Interconnection Webinar | July 16 2020

Process Improvement amp Future Topics

Potential webinar topics

Verizon initiatives

Hosting Capacity Maps

Metering

Mike Porcaro as Ombudsperson

Questions

07

34National Grid | July Interconnection Webinar | July 16 2020

Appendix Summary of Resources Documents amp Links

Distributed Generation Website ndash

httpswww9nationalgriduscommasselectrichomeenergyeffdistributed_gen

erationasp

Interconnection Process Resources ndash

httpswww9nationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

Storage Assistance -

httpsngusforcecomsarticleStorage-Assistance

DPU Interim Guidance for ESS -

httpsngusforcecomsarticleHow-to-Add-Energy-Storage-to-an-In-Progress-Application-in-Massachusetts

| [Insert document title] | [Insert date]

Page 21: National Grid Distributed Generation Seminar

21National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

For most Expedited applications a ldquoCommissioning Memordquo on

a company letterhead is provided in lieu of Witness Test

Commissioning test should consist of the following

1 Two (2) second shutdown when disconnect open test

2 Five (5) minutes before restart when disconnect is closed test

3 Confirm system matches As-built (include most recent revision

date of as built provided)

4 List the inverter relay frequency (Hz) and trip time settings

22National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

As Built Must be PE stamped and signed dated by person

that performed the commissioning test (Signature date

should match date of test)

Pictures Meter picture should show permanent plaque

(visible at eye level) that includes a warning about generator

installed

Pictures If the AC utility disconnect switch is not grouped

with and adjacent to the utility revenue meter then a

permanent plaque (visible at eye level) that clearly identifies

the location of the AC utility disconnect is required

23National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

Evidence of insurance is required for all projects gt 60kW in

MA and gt50kW in RI Refer to the ISA and Interconnection

Tariff for insurance requirements

Qualifying Facility documents

Schedule A (P-Rate) required for all QF projects

W9 (Only for projects gt60kW)

ACH (Only for projects gt60kW)

Supplier Enrollment Form (Only for projects gt60kW)

24National Grid | July Interconnection Webinar | July 16 2020

Metering Reminder

Projects greater than 60kW in MA and greater than 25kW in RI

require interval metering (Wireless or phone line)

Company needs a 4G wireless signal test on a Verizon network in

order to provide wireless metering

Phone lines must be dedicated and terminated at the meter

location Line must be 100 copper Fiber lines will not

communicate properly

These meters are long lead time items and prep time can be 6-8

weeks so it is important to work through this with your job owner

well in advance of when you intend to seek Authority to

Interconnect

Wireless test form httpsngusforcecomsarticleMA-

Interconnection-Documents

Standard Review

ProcessNat Mahattanasakul

05

26National Grid | July Interconnection Webinar | July 16 2020

Standard Criteria

Applies to

Projects that require Distribution System Impact Study (DSIS)

Large-scale DG projects

Generally greater than 500 kW but project specific

DG projects requiring System Modifications at the substation level

Non-listed inverters or generators other than PV

Induction Synchronous Asynchronous

Most CHP systems

All projects that do not qualify for the Simplified or Expedited process

27National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application

Application

Standard

Engineering Review

Impact StudyDetailed Study

Conditional Approval (to construct DG system)

Company Construction

Witness Test

Authorization to Interconnect

httpsngusforcecomsarticleMA-Complex-Standard-Application-Process

28National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Standard

Eligible Facilities Any DG

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Standard Process Initial Review 20 days

Send Impact Study Agreement 5 days

Complete Impact Study 55-60 days or by mutual agreement depending on complexity

Complete Detailed Study (if needed) 30 ndash 60 days or by mutual agreement depending on complexity

Send Executable Agreement (ISA) 15 days

Total Maximum Days 135160 days (200 days for Standard Complex)

Construction Schedule Varied

Witness Test10 days from the Companyrsquos approval of WT procedures or

by mutual agreement

29National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Impact Study will determine the level of impact on the Companyrsquos EPS and the required System

Modifications

Impact and Detailed Study (if applicable) will determine System Modifications required and cost

(Risk of Islanding)

ISO-NE Generator Notification Process will be required for applications that are greater than 1MW

but less than 5MW (ie PP5-1 or GNF) and a Proposed Plan Application (PPA) along with supporting Transmission System Impact Study (TSIS) will be required for applications 5MW or greater in size single or potentially in aggregate Size of project based on nameplate rating of

system

These requirements will add time to the DG Interconnection Process if there is an ASO hold If so

the DSIS will be placed on hold until the ISO-NE approval or determination is known likely at a point during the DSIS process

Interconnection Service Agreement (ISA) provided after Study completed or an Early ISA could be requested if Detailed Study is required

If substation modifications required Company has 60 BD for Study (MDPU 1320 ndash pg 50) or by mutual agreement if estimated construction cost greater than $1 million

30National Grid | July Interconnection Webinar | July 16 2020

New CEI Structure

Process Improvement

amp Future TopicsWill Kern

06

32National Grid | July Interconnection Webinar | July 16 2020

Process Improvement amp Future Topics

Potential webinar topics

Verizon initiatives

Hosting Capacity Maps

Metering

Mike Porcaro as Ombudsperson

Questions

07

34National Grid | July Interconnection Webinar | July 16 2020

Appendix Summary of Resources Documents amp Links

Distributed Generation Website ndash

httpswww9nationalgriduscommasselectrichomeenergyeffdistributed_gen

erationasp

Interconnection Process Resources ndash

httpswww9nationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

Storage Assistance -

httpsngusforcecomsarticleStorage-Assistance

DPU Interim Guidance for ESS -

httpsngusforcecomsarticleHow-to-Add-Energy-Storage-to-an-In-Progress-Application-in-Massachusetts

| [Insert document title] | [Insert date]

Page 22: National Grid Distributed Generation Seminar

22National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

As Built Must be PE stamped and signed dated by person

that performed the commissioning test (Signature date

should match date of test)

Pictures Meter picture should show permanent plaque

(visible at eye level) that includes a warning about generator

installed

Pictures If the AC utility disconnect switch is not grouped

with and adjacent to the utility revenue meter then a

permanent plaque (visible at eye level) that clearly identifies

the location of the AC utility disconnect is required

23National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

Evidence of insurance is required for all projects gt 60kW in

MA and gt50kW in RI Refer to the ISA and Interconnection

Tariff for insurance requirements

Qualifying Facility documents

Schedule A (P-Rate) required for all QF projects

W9 (Only for projects gt60kW)

ACH (Only for projects gt60kW)

Supplier Enrollment Form (Only for projects gt60kW)

24National Grid | July Interconnection Webinar | July 16 2020

Metering Reminder

Projects greater than 60kW in MA and greater than 25kW in RI

require interval metering (Wireless or phone line)

Company needs a 4G wireless signal test on a Verizon network in

order to provide wireless metering

Phone lines must be dedicated and terminated at the meter

location Line must be 100 copper Fiber lines will not

communicate properly

These meters are long lead time items and prep time can be 6-8

weeks so it is important to work through this with your job owner

well in advance of when you intend to seek Authority to

Interconnect

Wireless test form httpsngusforcecomsarticleMA-

Interconnection-Documents

Standard Review

ProcessNat Mahattanasakul

05

26National Grid | July Interconnection Webinar | July 16 2020

Standard Criteria

Applies to

Projects that require Distribution System Impact Study (DSIS)

Large-scale DG projects

Generally greater than 500 kW but project specific

DG projects requiring System Modifications at the substation level

Non-listed inverters or generators other than PV

Induction Synchronous Asynchronous

Most CHP systems

All projects that do not qualify for the Simplified or Expedited process

27National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application

Application

Standard

Engineering Review

Impact StudyDetailed Study

Conditional Approval (to construct DG system)

Company Construction

Witness Test

Authorization to Interconnect

httpsngusforcecomsarticleMA-Complex-Standard-Application-Process

28National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Standard

Eligible Facilities Any DG

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Standard Process Initial Review 20 days

Send Impact Study Agreement 5 days

Complete Impact Study 55-60 days or by mutual agreement depending on complexity

Complete Detailed Study (if needed) 30 ndash 60 days or by mutual agreement depending on complexity

Send Executable Agreement (ISA) 15 days

Total Maximum Days 135160 days (200 days for Standard Complex)

Construction Schedule Varied

Witness Test10 days from the Companyrsquos approval of WT procedures or

by mutual agreement

29National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Impact Study will determine the level of impact on the Companyrsquos EPS and the required System

Modifications

Impact and Detailed Study (if applicable) will determine System Modifications required and cost

(Risk of Islanding)

ISO-NE Generator Notification Process will be required for applications that are greater than 1MW

but less than 5MW (ie PP5-1 or GNF) and a Proposed Plan Application (PPA) along with supporting Transmission System Impact Study (TSIS) will be required for applications 5MW or greater in size single or potentially in aggregate Size of project based on nameplate rating of

system

These requirements will add time to the DG Interconnection Process if there is an ASO hold If so

the DSIS will be placed on hold until the ISO-NE approval or determination is known likely at a point during the DSIS process

Interconnection Service Agreement (ISA) provided after Study completed or an Early ISA could be requested if Detailed Study is required

If substation modifications required Company has 60 BD for Study (MDPU 1320 ndash pg 50) or by mutual agreement if estimated construction cost greater than $1 million

30National Grid | July Interconnection Webinar | July 16 2020

New CEI Structure

Process Improvement

amp Future TopicsWill Kern

06

32National Grid | July Interconnection Webinar | July 16 2020

Process Improvement amp Future Topics

Potential webinar topics

Verizon initiatives

Hosting Capacity Maps

Metering

Mike Porcaro as Ombudsperson

Questions

07

34National Grid | July Interconnection Webinar | July 16 2020

Appendix Summary of Resources Documents amp Links

Distributed Generation Website ndash

httpswww9nationalgriduscommasselectrichomeenergyeffdistributed_gen

erationasp

Interconnection Process Resources ndash

httpswww9nationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

Storage Assistance -

httpsngusforcecomsarticleStorage-Assistance

DPU Interim Guidance for ESS -

httpsngusforcecomsarticleHow-to-Add-Energy-Storage-to-an-In-Progress-Application-in-Massachusetts

| [Insert document title] | [Insert date]

Page 23: National Grid Distributed Generation Seminar

23National Grid | July Interconnection Webinar | July 16 2020

Common Errors in Completion Documents

Evidence of insurance is required for all projects gt 60kW in

MA and gt50kW in RI Refer to the ISA and Interconnection

Tariff for insurance requirements

Qualifying Facility documents

Schedule A (P-Rate) required for all QF projects

W9 (Only for projects gt60kW)

ACH (Only for projects gt60kW)

Supplier Enrollment Form (Only for projects gt60kW)

24National Grid | July Interconnection Webinar | July 16 2020

Metering Reminder

Projects greater than 60kW in MA and greater than 25kW in RI

require interval metering (Wireless or phone line)

Company needs a 4G wireless signal test on a Verizon network in

order to provide wireless metering

Phone lines must be dedicated and terminated at the meter

location Line must be 100 copper Fiber lines will not

communicate properly

These meters are long lead time items and prep time can be 6-8

weeks so it is important to work through this with your job owner

well in advance of when you intend to seek Authority to

Interconnect

Wireless test form httpsngusforcecomsarticleMA-

Interconnection-Documents

Standard Review

ProcessNat Mahattanasakul

05

26National Grid | July Interconnection Webinar | July 16 2020

Standard Criteria

Applies to

Projects that require Distribution System Impact Study (DSIS)

Large-scale DG projects

Generally greater than 500 kW but project specific

DG projects requiring System Modifications at the substation level

Non-listed inverters or generators other than PV

Induction Synchronous Asynchronous

Most CHP systems

All projects that do not qualify for the Simplified or Expedited process

27National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application

Application

Standard

Engineering Review

Impact StudyDetailed Study

Conditional Approval (to construct DG system)

Company Construction

Witness Test

Authorization to Interconnect

httpsngusforcecomsarticleMA-Complex-Standard-Application-Process

28National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Standard

Eligible Facilities Any DG

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Standard Process Initial Review 20 days

Send Impact Study Agreement 5 days

Complete Impact Study 55-60 days or by mutual agreement depending on complexity

Complete Detailed Study (if needed) 30 ndash 60 days or by mutual agreement depending on complexity

Send Executable Agreement (ISA) 15 days

Total Maximum Days 135160 days (200 days for Standard Complex)

Construction Schedule Varied

Witness Test10 days from the Companyrsquos approval of WT procedures or

by mutual agreement

29National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Impact Study will determine the level of impact on the Companyrsquos EPS and the required System

Modifications

Impact and Detailed Study (if applicable) will determine System Modifications required and cost

(Risk of Islanding)

ISO-NE Generator Notification Process will be required for applications that are greater than 1MW

but less than 5MW (ie PP5-1 or GNF) and a Proposed Plan Application (PPA) along with supporting Transmission System Impact Study (TSIS) will be required for applications 5MW or greater in size single or potentially in aggregate Size of project based on nameplate rating of

system

These requirements will add time to the DG Interconnection Process if there is an ASO hold If so

the DSIS will be placed on hold until the ISO-NE approval or determination is known likely at a point during the DSIS process

Interconnection Service Agreement (ISA) provided after Study completed or an Early ISA could be requested if Detailed Study is required

If substation modifications required Company has 60 BD for Study (MDPU 1320 ndash pg 50) or by mutual agreement if estimated construction cost greater than $1 million

30National Grid | July Interconnection Webinar | July 16 2020

New CEI Structure

Process Improvement

amp Future TopicsWill Kern

06

32National Grid | July Interconnection Webinar | July 16 2020

Process Improvement amp Future Topics

Potential webinar topics

Verizon initiatives

Hosting Capacity Maps

Metering

Mike Porcaro as Ombudsperson

Questions

07

34National Grid | July Interconnection Webinar | July 16 2020

Appendix Summary of Resources Documents amp Links

Distributed Generation Website ndash

httpswww9nationalgriduscommasselectrichomeenergyeffdistributed_gen

erationasp

Interconnection Process Resources ndash

httpswww9nationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

Storage Assistance -

httpsngusforcecomsarticleStorage-Assistance

DPU Interim Guidance for ESS -

httpsngusforcecomsarticleHow-to-Add-Energy-Storage-to-an-In-Progress-Application-in-Massachusetts

| [Insert document title] | [Insert date]

Page 24: National Grid Distributed Generation Seminar

24National Grid | July Interconnection Webinar | July 16 2020

Metering Reminder

Projects greater than 60kW in MA and greater than 25kW in RI

require interval metering (Wireless or phone line)

Company needs a 4G wireless signal test on a Verizon network in

order to provide wireless metering

Phone lines must be dedicated and terminated at the meter

location Line must be 100 copper Fiber lines will not

communicate properly

These meters are long lead time items and prep time can be 6-8

weeks so it is important to work through this with your job owner

well in advance of when you intend to seek Authority to

Interconnect

Wireless test form httpsngusforcecomsarticleMA-

Interconnection-Documents

Standard Review

ProcessNat Mahattanasakul

05

26National Grid | July Interconnection Webinar | July 16 2020

Standard Criteria

Applies to

Projects that require Distribution System Impact Study (DSIS)

Large-scale DG projects

Generally greater than 500 kW but project specific

DG projects requiring System Modifications at the substation level

Non-listed inverters or generators other than PV

Induction Synchronous Asynchronous

Most CHP systems

All projects that do not qualify for the Simplified or Expedited process

27National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application

Application

Standard

Engineering Review

Impact StudyDetailed Study

Conditional Approval (to construct DG system)

Company Construction

Witness Test

Authorization to Interconnect

httpsngusforcecomsarticleMA-Complex-Standard-Application-Process

28National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Standard

Eligible Facilities Any DG

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Standard Process Initial Review 20 days

Send Impact Study Agreement 5 days

Complete Impact Study 55-60 days or by mutual agreement depending on complexity

Complete Detailed Study (if needed) 30 ndash 60 days or by mutual agreement depending on complexity

Send Executable Agreement (ISA) 15 days

Total Maximum Days 135160 days (200 days for Standard Complex)

Construction Schedule Varied

Witness Test10 days from the Companyrsquos approval of WT procedures or

by mutual agreement

29National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Impact Study will determine the level of impact on the Companyrsquos EPS and the required System

Modifications

Impact and Detailed Study (if applicable) will determine System Modifications required and cost

(Risk of Islanding)

ISO-NE Generator Notification Process will be required for applications that are greater than 1MW

but less than 5MW (ie PP5-1 or GNF) and a Proposed Plan Application (PPA) along with supporting Transmission System Impact Study (TSIS) will be required for applications 5MW or greater in size single or potentially in aggregate Size of project based on nameplate rating of

system

These requirements will add time to the DG Interconnection Process if there is an ASO hold If so

the DSIS will be placed on hold until the ISO-NE approval or determination is known likely at a point during the DSIS process

Interconnection Service Agreement (ISA) provided after Study completed or an Early ISA could be requested if Detailed Study is required

If substation modifications required Company has 60 BD for Study (MDPU 1320 ndash pg 50) or by mutual agreement if estimated construction cost greater than $1 million

30National Grid | July Interconnection Webinar | July 16 2020

New CEI Structure

Process Improvement

amp Future TopicsWill Kern

06

32National Grid | July Interconnection Webinar | July 16 2020

Process Improvement amp Future Topics

Potential webinar topics

Verizon initiatives

Hosting Capacity Maps

Metering

Mike Porcaro as Ombudsperson

Questions

07

34National Grid | July Interconnection Webinar | July 16 2020

Appendix Summary of Resources Documents amp Links

Distributed Generation Website ndash

httpswww9nationalgriduscommasselectrichomeenergyeffdistributed_gen

erationasp

Interconnection Process Resources ndash

httpswww9nationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

Storage Assistance -

httpsngusforcecomsarticleStorage-Assistance

DPU Interim Guidance for ESS -

httpsngusforcecomsarticleHow-to-Add-Energy-Storage-to-an-In-Progress-Application-in-Massachusetts

| [Insert document title] | [Insert date]

Page 25: National Grid Distributed Generation Seminar

Standard Review

ProcessNat Mahattanasakul

05

26National Grid | July Interconnection Webinar | July 16 2020

Standard Criteria

Applies to

Projects that require Distribution System Impact Study (DSIS)

Large-scale DG projects

Generally greater than 500 kW but project specific

DG projects requiring System Modifications at the substation level

Non-listed inverters or generators other than PV

Induction Synchronous Asynchronous

Most CHP systems

All projects that do not qualify for the Simplified or Expedited process

27National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application

Application

Standard

Engineering Review

Impact StudyDetailed Study

Conditional Approval (to construct DG system)

Company Construction

Witness Test

Authorization to Interconnect

httpsngusforcecomsarticleMA-Complex-Standard-Application-Process

28National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Standard

Eligible Facilities Any DG

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Standard Process Initial Review 20 days

Send Impact Study Agreement 5 days

Complete Impact Study 55-60 days or by mutual agreement depending on complexity

Complete Detailed Study (if needed) 30 ndash 60 days or by mutual agreement depending on complexity

Send Executable Agreement (ISA) 15 days

Total Maximum Days 135160 days (200 days for Standard Complex)

Construction Schedule Varied

Witness Test10 days from the Companyrsquos approval of WT procedures or

by mutual agreement

29National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Impact Study will determine the level of impact on the Companyrsquos EPS and the required System

Modifications

Impact and Detailed Study (if applicable) will determine System Modifications required and cost

(Risk of Islanding)

ISO-NE Generator Notification Process will be required for applications that are greater than 1MW

but less than 5MW (ie PP5-1 or GNF) and a Proposed Plan Application (PPA) along with supporting Transmission System Impact Study (TSIS) will be required for applications 5MW or greater in size single or potentially in aggregate Size of project based on nameplate rating of

system

These requirements will add time to the DG Interconnection Process if there is an ASO hold If so

the DSIS will be placed on hold until the ISO-NE approval or determination is known likely at a point during the DSIS process

Interconnection Service Agreement (ISA) provided after Study completed or an Early ISA could be requested if Detailed Study is required

If substation modifications required Company has 60 BD for Study (MDPU 1320 ndash pg 50) or by mutual agreement if estimated construction cost greater than $1 million

30National Grid | July Interconnection Webinar | July 16 2020

New CEI Structure

Process Improvement

amp Future TopicsWill Kern

06

32National Grid | July Interconnection Webinar | July 16 2020

Process Improvement amp Future Topics

Potential webinar topics

Verizon initiatives

Hosting Capacity Maps

Metering

Mike Porcaro as Ombudsperson

Questions

07

34National Grid | July Interconnection Webinar | July 16 2020

Appendix Summary of Resources Documents amp Links

Distributed Generation Website ndash

httpswww9nationalgriduscommasselectrichomeenergyeffdistributed_gen

erationasp

Interconnection Process Resources ndash

httpswww9nationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

Storage Assistance -

httpsngusforcecomsarticleStorage-Assistance

DPU Interim Guidance for ESS -

httpsngusforcecomsarticleHow-to-Add-Energy-Storage-to-an-In-Progress-Application-in-Massachusetts

| [Insert document title] | [Insert date]

Page 26: National Grid Distributed Generation Seminar

26National Grid | July Interconnection Webinar | July 16 2020

Standard Criteria

Applies to

Projects that require Distribution System Impact Study (DSIS)

Large-scale DG projects

Generally greater than 500 kW but project specific

DG projects requiring System Modifications at the substation level

Non-listed inverters or generators other than PV

Induction Synchronous Asynchronous

Most CHP systems

All projects that do not qualify for the Simplified or Expedited process

27National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application

Application

Standard

Engineering Review

Impact StudyDetailed Study

Conditional Approval (to construct DG system)

Company Construction

Witness Test

Authorization to Interconnect

httpsngusforcecomsarticleMA-Complex-Standard-Application-Process

28National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Standard

Eligible Facilities Any DG

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Standard Process Initial Review 20 days

Send Impact Study Agreement 5 days

Complete Impact Study 55-60 days or by mutual agreement depending on complexity

Complete Detailed Study (if needed) 30 ndash 60 days or by mutual agreement depending on complexity

Send Executable Agreement (ISA) 15 days

Total Maximum Days 135160 days (200 days for Standard Complex)

Construction Schedule Varied

Witness Test10 days from the Companyrsquos approval of WT procedures or

by mutual agreement

29National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Impact Study will determine the level of impact on the Companyrsquos EPS and the required System

Modifications

Impact and Detailed Study (if applicable) will determine System Modifications required and cost

(Risk of Islanding)

ISO-NE Generator Notification Process will be required for applications that are greater than 1MW

but less than 5MW (ie PP5-1 or GNF) and a Proposed Plan Application (PPA) along with supporting Transmission System Impact Study (TSIS) will be required for applications 5MW or greater in size single or potentially in aggregate Size of project based on nameplate rating of

system

These requirements will add time to the DG Interconnection Process if there is an ASO hold If so

the DSIS will be placed on hold until the ISO-NE approval or determination is known likely at a point during the DSIS process

Interconnection Service Agreement (ISA) provided after Study completed or an Early ISA could be requested if Detailed Study is required

If substation modifications required Company has 60 BD for Study (MDPU 1320 ndash pg 50) or by mutual agreement if estimated construction cost greater than $1 million

30National Grid | July Interconnection Webinar | July 16 2020

New CEI Structure

Process Improvement

amp Future TopicsWill Kern

06

32National Grid | July Interconnection Webinar | July 16 2020

Process Improvement amp Future Topics

Potential webinar topics

Verizon initiatives

Hosting Capacity Maps

Metering

Mike Porcaro as Ombudsperson

Questions

07

34National Grid | July Interconnection Webinar | July 16 2020

Appendix Summary of Resources Documents amp Links

Distributed Generation Website ndash

httpswww9nationalgriduscommasselectrichomeenergyeffdistributed_gen

erationasp

Interconnection Process Resources ndash

httpswww9nationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

Storage Assistance -

httpsngusforcecomsarticleStorage-Assistance

DPU Interim Guidance for ESS -

httpsngusforcecomsarticleHow-to-Add-Energy-Storage-to-an-In-Progress-Application-in-Massachusetts

| [Insert document title] | [Insert date]

Page 27: National Grid Distributed Generation Seminar

27National Grid | July Interconnection Webinar | July 16 2020

Interconnection Process Steps

Pre-Application

Application

Standard

Engineering Review

Impact StudyDetailed Study

Conditional Approval (to construct DG system)

Company Construction

Witness Test

Authorization to Interconnect

httpsngusforcecomsarticleMA-Complex-Standard-Application-Process

28National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Standard

Eligible Facilities Any DG

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Standard Process Initial Review 20 days

Send Impact Study Agreement 5 days

Complete Impact Study 55-60 days or by mutual agreement depending on complexity

Complete Detailed Study (if needed) 30 ndash 60 days or by mutual agreement depending on complexity

Send Executable Agreement (ISA) 15 days

Total Maximum Days 135160 days (200 days for Standard Complex)

Construction Schedule Varied

Witness Test10 days from the Companyrsquos approval of WT procedures or

by mutual agreement

29National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Impact Study will determine the level of impact on the Companyrsquos EPS and the required System

Modifications

Impact and Detailed Study (if applicable) will determine System Modifications required and cost

(Risk of Islanding)

ISO-NE Generator Notification Process will be required for applications that are greater than 1MW

but less than 5MW (ie PP5-1 or GNF) and a Proposed Plan Application (PPA) along with supporting Transmission System Impact Study (TSIS) will be required for applications 5MW or greater in size single or potentially in aggregate Size of project based on nameplate rating of

system

These requirements will add time to the DG Interconnection Process if there is an ASO hold If so

the DSIS will be placed on hold until the ISO-NE approval or determination is known likely at a point during the DSIS process

Interconnection Service Agreement (ISA) provided after Study completed or an Early ISA could be requested if Detailed Study is required

If substation modifications required Company has 60 BD for Study (MDPU 1320 ndash pg 50) or by mutual agreement if estimated construction cost greater than $1 million

30National Grid | July Interconnection Webinar | July 16 2020

New CEI Structure

Process Improvement

amp Future TopicsWill Kern

06

32National Grid | July Interconnection Webinar | July 16 2020

Process Improvement amp Future Topics

Potential webinar topics

Verizon initiatives

Hosting Capacity Maps

Metering

Mike Porcaro as Ombudsperson

Questions

07

34National Grid | July Interconnection Webinar | July 16 2020

Appendix Summary of Resources Documents amp Links

Distributed Generation Website ndash

httpswww9nationalgriduscommasselectrichomeenergyeffdistributed_gen

erationasp

Interconnection Process Resources ndash

httpswww9nationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

Storage Assistance -

httpsngusforcecomsarticleStorage-Assistance

DPU Interim Guidance for ESS -

httpsngusforcecomsarticleHow-to-Add-Energy-Storage-to-an-In-Progress-Application-in-Massachusetts

| [Insert document title] | [Insert date]

Page 28: National Grid Distributed Generation Seminar

28National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Standard

Eligible Facilities Any DG

Acknowledge Receipt of Application (3 days)

Review Application for Completeness 10 days

Complete Standard Process Initial Review 20 days

Send Impact Study Agreement 5 days

Complete Impact Study 55-60 days or by mutual agreement depending on complexity

Complete Detailed Study (if needed) 30 ndash 60 days or by mutual agreement depending on complexity

Send Executable Agreement (ISA) 15 days

Total Maximum Days 135160 days (200 days for Standard Complex)

Construction Schedule Varied

Witness Test10 days from the Companyrsquos approval of WT procedures or

by mutual agreement

29National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Impact Study will determine the level of impact on the Companyrsquos EPS and the required System

Modifications

Impact and Detailed Study (if applicable) will determine System Modifications required and cost

(Risk of Islanding)

ISO-NE Generator Notification Process will be required for applications that are greater than 1MW

but less than 5MW (ie PP5-1 or GNF) and a Proposed Plan Application (PPA) along with supporting Transmission System Impact Study (TSIS) will be required for applications 5MW or greater in size single or potentially in aggregate Size of project based on nameplate rating of

system

These requirements will add time to the DG Interconnection Process if there is an ASO hold If so

the DSIS will be placed on hold until the ISO-NE approval or determination is known likely at a point during the DSIS process

Interconnection Service Agreement (ISA) provided after Study completed or an Early ISA could be requested if Detailed Study is required

If substation modifications required Company has 60 BD for Study (MDPU 1320 ndash pg 50) or by mutual agreement if estimated construction cost greater than $1 million

30National Grid | July Interconnection Webinar | July 16 2020

New CEI Structure

Process Improvement

amp Future TopicsWill Kern

06

32National Grid | July Interconnection Webinar | July 16 2020

Process Improvement amp Future Topics

Potential webinar topics

Verizon initiatives

Hosting Capacity Maps

Metering

Mike Porcaro as Ombudsperson

Questions

07

34National Grid | July Interconnection Webinar | July 16 2020

Appendix Summary of Resources Documents amp Links

Distributed Generation Website ndash

httpswww9nationalgriduscommasselectrichomeenergyeffdistributed_gen

erationasp

Interconnection Process Resources ndash

httpswww9nationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

Storage Assistance -

httpsngusforcecomsarticleStorage-Assistance

DPU Interim Guidance for ESS -

httpsngusforcecomsarticleHow-to-Add-Energy-Storage-to-an-In-Progress-Application-in-Massachusetts

| [Insert document title] | [Insert date]

Page 29: National Grid Distributed Generation Seminar

29National Grid | July Interconnection Webinar | July 16 2020

Standard Review Path

Impact Study will determine the level of impact on the Companyrsquos EPS and the required System

Modifications

Impact and Detailed Study (if applicable) will determine System Modifications required and cost

(Risk of Islanding)

ISO-NE Generator Notification Process will be required for applications that are greater than 1MW

but less than 5MW (ie PP5-1 or GNF) and a Proposed Plan Application (PPA) along with supporting Transmission System Impact Study (TSIS) will be required for applications 5MW or greater in size single or potentially in aggregate Size of project based on nameplate rating of

system

These requirements will add time to the DG Interconnection Process if there is an ASO hold If so

the DSIS will be placed on hold until the ISO-NE approval or determination is known likely at a point during the DSIS process

Interconnection Service Agreement (ISA) provided after Study completed or an Early ISA could be requested if Detailed Study is required

If substation modifications required Company has 60 BD for Study (MDPU 1320 ndash pg 50) or by mutual agreement if estimated construction cost greater than $1 million

30National Grid | July Interconnection Webinar | July 16 2020

New CEI Structure

Process Improvement

amp Future TopicsWill Kern

06

32National Grid | July Interconnection Webinar | July 16 2020

Process Improvement amp Future Topics

Potential webinar topics

Verizon initiatives

Hosting Capacity Maps

Metering

Mike Porcaro as Ombudsperson

Questions

07

34National Grid | July Interconnection Webinar | July 16 2020

Appendix Summary of Resources Documents amp Links

Distributed Generation Website ndash

httpswww9nationalgriduscommasselectrichomeenergyeffdistributed_gen

erationasp

Interconnection Process Resources ndash

httpswww9nationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

Storage Assistance -

httpsngusforcecomsarticleStorage-Assistance

DPU Interim Guidance for ESS -

httpsngusforcecomsarticleHow-to-Add-Energy-Storage-to-an-In-Progress-Application-in-Massachusetts

| [Insert document title] | [Insert date]

Page 30: National Grid Distributed Generation Seminar

30National Grid | July Interconnection Webinar | July 16 2020

New CEI Structure

Process Improvement

amp Future TopicsWill Kern

06

32National Grid | July Interconnection Webinar | July 16 2020

Process Improvement amp Future Topics

Potential webinar topics

Verizon initiatives

Hosting Capacity Maps

Metering

Mike Porcaro as Ombudsperson

Questions

07

34National Grid | July Interconnection Webinar | July 16 2020

Appendix Summary of Resources Documents amp Links

Distributed Generation Website ndash

httpswww9nationalgriduscommasselectrichomeenergyeffdistributed_gen

erationasp

Interconnection Process Resources ndash

httpswww9nationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

Storage Assistance -

httpsngusforcecomsarticleStorage-Assistance

DPU Interim Guidance for ESS -

httpsngusforcecomsarticleHow-to-Add-Energy-Storage-to-an-In-Progress-Application-in-Massachusetts

| [Insert document title] | [Insert date]

Page 31: National Grid Distributed Generation Seminar

Process Improvement

amp Future TopicsWill Kern

06

32National Grid | July Interconnection Webinar | July 16 2020

Process Improvement amp Future Topics

Potential webinar topics

Verizon initiatives

Hosting Capacity Maps

Metering

Mike Porcaro as Ombudsperson

Questions

07

34National Grid | July Interconnection Webinar | July 16 2020

Appendix Summary of Resources Documents amp Links

Distributed Generation Website ndash

httpswww9nationalgriduscommasselectrichomeenergyeffdistributed_gen

erationasp

Interconnection Process Resources ndash

httpswww9nationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

Storage Assistance -

httpsngusforcecomsarticleStorage-Assistance

DPU Interim Guidance for ESS -

httpsngusforcecomsarticleHow-to-Add-Energy-Storage-to-an-In-Progress-Application-in-Massachusetts

| [Insert document title] | [Insert date]

Page 32: National Grid Distributed Generation Seminar

32National Grid | July Interconnection Webinar | July 16 2020

Process Improvement amp Future Topics

Potential webinar topics

Verizon initiatives

Hosting Capacity Maps

Metering

Mike Porcaro as Ombudsperson

Questions

07

34National Grid | July Interconnection Webinar | July 16 2020

Appendix Summary of Resources Documents amp Links

Distributed Generation Website ndash

httpswww9nationalgriduscommasselectrichomeenergyeffdistributed_gen

erationasp

Interconnection Process Resources ndash

httpswww9nationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

Storage Assistance -

httpsngusforcecomsarticleStorage-Assistance

DPU Interim Guidance for ESS -

httpsngusforcecomsarticleHow-to-Add-Energy-Storage-to-an-In-Progress-Application-in-Massachusetts

| [Insert document title] | [Insert date]

Page 33: National Grid Distributed Generation Seminar

Questions

07

34National Grid | July Interconnection Webinar | July 16 2020

Appendix Summary of Resources Documents amp Links

Distributed Generation Website ndash

httpswww9nationalgriduscommasselectrichomeenergyeffdistributed_gen

erationasp

Interconnection Process Resources ndash

httpswww9nationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

Storage Assistance -

httpsngusforcecomsarticleStorage-Assistance

DPU Interim Guidance for ESS -

httpsngusforcecomsarticleHow-to-Add-Energy-Storage-to-an-In-Progress-Application-in-Massachusetts

| [Insert document title] | [Insert date]

Page 34: National Grid Distributed Generation Seminar

34National Grid | July Interconnection Webinar | July 16 2020

Appendix Summary of Resources Documents amp Links

Distributed Generation Website ndash

httpswww9nationalgriduscommasselectrichomeenergyeffdistributed_gen

erationasp

Interconnection Process Resources ndash

httpswww9nationalgriduscommasselectrichomeenergyeff4_interconnection-processasp

Storage Assistance -

httpsngusforcecomsarticleStorage-Assistance

DPU Interim Guidance for ESS -

httpsngusforcecomsarticleHow-to-Add-Energy-Storage-to-an-In-Progress-Application-in-Massachusetts

| [Insert document title] | [Insert date]

Page 35: National Grid Distributed Generation Seminar

| [Insert document title] | [Insert date]