Namibia - Airport Study - Approved

download Namibia - Airport Study - Approved

of 15

Transcript of Namibia - Airport Study - Approved

  • 8/20/2019 Namibia - Airport Study - Approved

    1/37

    AFRICAN DEVELOPMENT BANK

    Language: English

    Original: English

    MIDDLE INCOME COUNTRIES (MIC) TECHNICAL ASSISTANCE FUND

    PROJECT: NAMIBIA AIRPORT STUDY - FEASIBILITY STUDIES, PRELIMINARY

    DESIGN AND MASTER PLANS FOR NAMIBIA AIRPORTS

    COUNTRY: NAMIBIA

    Date: April 2010

    Appraisal Team

    Team Leader: P. Opoku-Darkwa, Transport Engineer, OITC.2

    Sector Manager (OITC.2): J Rwamabuga

    Sector Director (OITC): G Mbesherubusa

    Regional Director(ORSA): A Beileh

    Peer ReviewersM. Benard, OITC.1; A. Babalola, OPSM.3; D. Etienne, OITC.1, K I Mfalila, OSAN.4;

  • 8/20/2019 Namibia - Airport Study - Approved

    2/37

     

    TABLE OF CONTENTS

    1.  INTRODUCTION  1 

    1.1. Background 1 1.2. Study Objectives 11.3. Justification for use of MIC TAF Resources 2

    1.4. Financial considerations for implementation of HKIA Master Plan –  Study Component 1. 3

    2.  DESCRIPTION OF STUDY  4 2.1. Study Components 4

    3.  STUDY COST ESTIMATES AND FINANCING PLAN  5 3.1. Cost Estimates 53.2. Financing Plan 5

    4.  PROCUREMENT  6 4.1. Procurement Arrangement 64.2. Disbursements Arrangements 6

    5.  IMPLEMENTATION strategy  6 5.1. Proposed Implementation Schedule 65.2. Executing Agency 7

    6.  LETTER OF AGREEMENT  7 

    7.  CONCLUSIONS AND RECOMMENDATIONS  7 7.1. Conclusions 77.2. Recommendations 8

    ANNEXES 

    ANNEX 1 –  MAP OF NAMIBIA, AIRPORT LOCATION 

    ANNEX 2 - PHOTOGRAPHS 

    ANNEX 3 - IMPLEMENTATION SCHEDULE 

    ANNEX 4 –  COST ESTIMATE SCHEDULE (in USD) 

    ANNEX 5 – REQUEST FORM 

    ANNEX 6 – LETTER OF AGREEMENT 

    ANNEX 7 –  ABRIDGED TERMS OF REFERENCE FOR TECHNICAL ASSISTANCE FOR THE ENHANCEMENTOF EXISTING AIRPORT INFRASTRUCTURE 

    This report has been prepared by Mr P. Opoku-Darkwa, OITC.2 (Ext 3142). Any matters relating to this report may be referred to Mr.J. Rwamabuga, Manager, OITC.2, (Ext. 2181), Mr. G. Mbesherubusa, Director, OITC (Ext. 2034) and Mr. A Beileh, RegionalDirector, ORSA (Ext 2039).

  • 8/20/2019 Namibia - Airport Study - Approved

    3/37

     

    LIST OF ABBREVIATIONS

    ADB = African Development Bank

    CSP = Country Strategy PaperDANIDA = Danish International Development Assistance

    EMP = Environmental Master Plan

    ESMP = Environmental and Social Master Plan

    GRN = Government of the Republic of Namibia

    HKIA = Hosea Kutako International Airport

    ICAO = International Civil Aviation Organisation

    MIC = Middle Income Countries

    MoWT = Ministry of Works and Transport

     NAC = Namibia Airports Company

     NDP3 = Third National Development Plan

    PPP = Public Private Partnership

    QCBS = Quality and Cost Based Selection

    QBS = Quality-Based Selection

    SADC = Southern Africa Development Community

    TAF = Technical Assistance Fund

    TOR = Terms of Reference

    UA = Unit of Account

    USD = United States Dollar

  • 8/20/2019 Namibia - Airport Study - Approved

    4/37

    ii

    GRANT INFORMATION

    Client’s Information 

    BORROWER: Government of the Republic of Namibia (GRN)

    IMPLEMENTING AGENCY: Namibia Airports Company (NAC)

    Financing Plan

    Source Amount Instrument

    ADB (95%) UA 594,000 MIC Grant

    GRN/NAC (5%) UA 31,000 NAC Budget

    Total Cost UA 625,000**Based on preliminary cost estimate

    MIC Grant Currency: UA

    Currency Equivalents (April, 2010),

    1 UA=11.136 NAD

    1 UA=1.518 USD

    1 UA=1.126 EURO

    Proposed Timeframe for Main Milestones

    Submission of MIC Grant to Country teams: February 2010

    Submission to MIC Grant Committee (OIVP): May 2010

    MIC Grant Submission for Board approval: June 2010 (Lapse of Time Basis)

    MIC Grant Approval: June 2010

    Grant Effectiveness: July 2010

    First Disbursement: post- September 2010

    Last Disbursement: September 2011

  • 8/20/2019 Namibia - Airport Study - Approved

    5/37

    HIERARCHY OF

    OBJECTIVES

    EXPECTED RESULTS REACH/ BENEFICIARIES PERFORMANCE INDICATORS INDICATIVE

    TARGETS AND

    TIME FRAME

    ASSUMPTIONS /

    RISKS

    GOAL:

    To promote economic and social development byenhancing existing infrastructure to meet increasedoperational activities of the airports.

    IMPACT:

    Efficient operational Transportsystem leads to:

     Financial independence andcompetitiveness of parastatals(NAC) Relieve government of capacityconstraints Creating new SMEs 

    Employment opportunities to ruraland urban population Facilitates/Fosters Private participation

      Namibia economy Environment (wild lifeimpact)

     Tourism industry

     Rural and Urban population

     SMEs and Private investors

     Economic growth and productivity(%). Increased Revenue by NAC (%turnover increase) Revenue from tourism sector. number of SMEs –  lodging &accommodation industry Reduced unemployment (%workforce unemployment) 

    Meet the objectives of section 4.2.2(Transport Infrastructure) of NDP3 Growth in SMEs competitiveness(No. of new businesses, tax revenues)

    Provides theframework to meetVision 2030/NDP3targets and timeframe.

     NAC/GRNcommitments toadhere to NamibiaVision 2030 &NDP3goals.

    Risk: Not meeting theVision 2030/NDP3

    goals

    Decline in tourism

    OBJECTIVES: An output that facilitates enhanced operationalefficiencies and capacity, optimises land-use with strictadherence to environment and social parameters.

    OUTCOMES:Efficient air transport infrastructuresystem. Study outcomes: Completed and submitted Finalenvironmental and land-use master plans. Completed and submittedfeasibility study and designdeliverables in readiness forimplementation for HKIA.

     GRN  NAC Population of Namibia Customers/Passengers Local aviation industry

     Readiness for implementation (%design completion) Meets long term objectives (%design completion) Facilitates private sectorinvolvement (%of private sectorinterest) Meeting the conditions on Climatechange

    Completion ofconsultancy serviceswithin 12months ofcontract award.(forecast July 2011)

    Timely approval ofGrant agreement andeffectiveness

    Risks:Stalled implementationdue to fundinglimitations

    ACTIVITIES

    Consulting Services for developing Feasibility study & design of HKIA (terminal buildings) -  Reviewing the 2004 feasibility study report, update study,design optioneering and preliminary detailed design. Environmental master plan (8no. airports) - Performingstudies and surveys in establishing balance betweenoperations, infrastructure systems and the environmentincluding social systems.Land-use planning (5no. airport) - Studies and surveys onairport operations to develop airport layout that opt imisesland-use for operational facilities.

    Costs (‘000 UA,)* 

    Source FE LC TotalMIC Fund 282 312 594GRN/NAC 15 16 31

    Total 297 328 625

    * including contingencies

    OUTPUTS

    Deliverables Feasibility Study Report andDetailed Design of HKIA TerminalBuildings;

     Environmental Master Plan(Reports/Drawings);

     

    Master /Land Use Plan Deliverable(Reports/Drawings)

    Consultant

     NAC

    Public (public consultation)

     Contract award and completion (May2010)

     Timely delivery of outputs(12months).

     All deliverables meet requirement onreadiness for implementation (%design completion)

     Cost (against output) within budget

    Submission ofdeliverables by July2011.

    Assumptions

     Timely delivery of project output.

     Minimal scopechange.

    Risk

     Delay to the

    submission of thecompleteddeliverables by theconsultant.

     Cost escalation

     Scope change

  • 8/20/2019 Namibia - Airport Study - Approved

    6/37

    1

    1.  INTRODUCTION

    1.1.  Background

    1.1.1.  The Government of the Republic of Namibia (GRN) has requested financial assistancefrom the African Development Bank (ADB),  proposing to utilise the Bank‟s MIC TechnicalAssistance Fund facility, to undertake project preparation activities on existing airport infrastructure.Launched in 2004, Namibia‟s Vision 2030 Paper   laid out the fundamental framework anddevelopment objectives to transform the economic and social landscape for the future.Complementing the Vision 2030 report is the Third National Development Plans (NDP3, June 2008), both aligned with the Bank‟s CSP, in which strategies to enhance transport infrastructure form a key part.

    1.1.2.  Consistent with GRN‟s strategy on parastatals to  provide effective and efficient transportinfrastructure, the National Airport Company (NAC), a wholly state-owned and autonomousenterprise and executing agency, was established to operate eight (8) regional airports. Due toincreased aviation and passenger activities, taking into consideration the growth potential of the sectorthrough increased tourism which is a major source of employment, the existing infrastructure has progressively been rendered obsolete with limited operational capacity.

    1.1.3. 

    In 2004, a study funded by the Danish Trust Fund, managed by the African DevelopmentsBank, was carried out to develop a conceptual master-plan for the international airport Hosea KutakoInternational Airport (HKIA) with a limited scope to investigate design concepts and framework forfuture development of the airport. The remit excluded other airports.

    1.1.4.  GRN‟s request for assistance to enable NAC manage and execute the infrastructureimprovement programme was formally received in July 2009 accompanied by draft Terms ofReference (TOR) prepared by selected consultants. A project identification mission subsequentlyfollowed in early November 2009. The information collated and evaluated forms the basis of the proposal report.

    1.1.5.  The purpose of the study is to facilitate the upgrade of existing airport infrastructure to astandard that aligns with current and future aviation demands by providing sustainable solutions

    which at its core also addresses the environmental and socio-economic issues directly impacting the population and the country as whole.

    1.1.6.  The study constitutes a „ project preparation activity’   and falls under the heading of„Priority Activities‟ described in relevant parts of section 3.4 of the Bank‟s Revised Guidelines for the Administration and Utilization of the Technical Assistance Fund (TAF) for Middle Income Countries(MIC).

    1.2.  Study Objectives

    1.2.1.  The objective of this Study is to develop relevant output of master plans and designs,facilitating enhanced operational efficiencies and capacity, optimise land-use with strict adherence toenvironment, including climate change, and social parameters. This study, on completion, brings forth

    deliverables in readiness for future implementation. The associated activities are:

    a.  For HKIA, follow-up on the 2004 master-plan study, update and expand the scope asrequired.

     b.  For other airports, to have fully developed master-plans (environmental and land-use planning) for the development of regional airports which is to form the basis for futuredevelopment.

  • 8/20/2019 Namibia - Airport Study - Approved

    7/37

    2

    1.3.  Justification for use of MIC TAF Resources

    The justification is based on two viewpoints:

      GRN‟s objectives and strategy for development, and

     

    ADB‟s objectives and strategy for positive intervention in Namibia;

    i)   Justification based on GRN’s strategy

    1.3.1.  In defining the country‟s Vision 2030 targets, objectives and strategies were identified todevelop an effective and efficient transport infrastructure that ensure safe operations of transportservices. The focus area in addition to enhancing the road network was the development of capacity inthe civil aviation sector by recognition of the importance of achieving a balanced transportinfrastructure and, given its direct link with tourism, the employment creating attributes of the sector.

    1.3.2.  In spite of the government efforts to create employment opportunities, unemploymentremains high (over 30% of the working population). The tourism industry has traditionally proved a

    reliable source for income generation and employment for the rural and urban population alike and,with the vastness and remoteness of its attractions, the industry relies heavily on its aviationinfrastructure to deliver appropriate services.

    1.3.3.  GRN‟s NDP3 acknowledges the significant contributions the air transport infrastructuremakes to the economy, integrated with road and rail, and highlights the shortfall of the NDP2 targetsin the upgrading of existing aerodromes due to the lack of financial resources. Interlinked withtourism, the improvement of the existing infrastructure is fundamental to the economic well-being ofthe population, particularly, the rural community.

    1.3.4.  Aligned with aspiration to promote private-public partnerships and SMEs, NAC is well placed to be the facilitator in engaging the private sector, leveraging its experiences, although at arelatively modest scale so far, in commercial collaborations for development such as retail outlets, car

    rental facilities, aircraft hangers and storage facilities, etc.

    ii)   Justification based on ADB strategy (2009-2013 CSP)

    1.3.5.  The Bank‟s Country Strategy Paper (CSP) takes a holistic approach on the significance oftransport infrastructure development vis-à-vis addressing the country‟s development shortcomings. Inorder to justify the funding request, it is essential to demonstrate credible linkage between therationale for intervention and the goals of this development activity.

    1.3.6.  The CSP prescribes three underlying pillars as a basis for intervention and these are i) Enhancing private sector competitiveness, i) Enhancing rural productivity in the agricultural sectors,and iii) Partnership for Trade and Regional integration. The project‟s long term aspirations which is

    to be realised upon completion of the implementation phase and commencement of subsequentoperational activities, is consistent with all three pillars. Some of the linkages with pillars are outlinedin below.

    1.3.7.  The project will strengthen the capacity of the private sector (including SMEs) to improve productivity of the country‟s human resources, create employment opportunities and increase incomelevels. It is also to complement the diversification programme of the government away from thereliance on mineral sector and stimulate development at local and regional level.

    1.3.8.  The significance of tourism to the economy and the direct association with the aviationsector is a high-employment generation tool and facilitates growth of SMEs such as B&Bs, smalllodges, guest houses, car rental and specialist retailers etc, to gain the opportunity to enter mainstreamtourism thus creating new investment opportunities and local entr epreneurship. The Banks‟ aspiration

    to enhance private sector capacity and competence is complementary to the anticipated short tomedium-term demands in the anticipated growth in tourism.

  • 8/20/2019 Namibia - Airport Study - Approved

    8/37

    3

    1.3.9.  With regards to partnership agreements and joint ventures, NAC has implemented severalstrategic infrastructure and commercial developments with the aim of improving its overall servicedelivery. Projects have been undertaken in collaboration with private developers aligned with themodern concepts of Public Private Partnerships (PPP). The business environment potentially thereforelends itself to a PPP approach at the implementation phase as well as operational level.

    1.3.10.  While the road network serve a greater part of the country, an integrated air transport

    infrastructure complements the conventional road and rail modes of transport for bulk haulage. Theease to access markets with less bulky agricultural produce is an incentive to local farmers. Forexample, Walvis Bay Airport is at a location that forms part of the Namibia Processing Zone and isintended to serve as a major export hub of fish and other resources.

    1.3.11.  Typical of other regional airports, there is potential for expansion and infrastructure suchas access roads and cargo-handling facilities to add value and boost functionality by serving theexisting railway. For example, container depots are planned atOndangwa Airport  to interlink betweenOndangwa, Oshikango and Oshakati. Other airports have storage facilities for cargo to Angola andserve the tourism industry as hub for the chartered flights for tourist and businesses attracted by thegame parks of Khaudom, Mahango, Popa Falls and Buchman land. Katima Mulilo Airport is thegateway for the tropical Caprivi region, located close to the Zambesi River, northeast of the country,

    and serves other attraction in Botswana and Zimbabwe. It also serves as a refuelling hub for air trafficfrom South Africa en route to Central Africa. There is an aspiration by NAC to upgrade the accessroad to the airport.

    1.3.12.  With particular reference to the international airport HKIA, some improvement initiativeson the terminal building such as duty free facilities, tourism centres, car rentals and retail outlets, hasenhanced functionality to a degree that contributes to the NAC‟s financial  bottom-line andemployment-creating capability.

    1.3.13.  The Bank also acknowledges the constraints that currently prevail in forming sustainable partnerships with Namibia citing the competition with other multilateral and unilateral institutions as acontributing factor. The commitment of GRN, to ensure the benefits of the enhancement programmeis materialised, was discussed and documented during the mission. With the desire to enhance

    relationship and ultimately contribute to addressing the social challenges of poverty andunemployment, this financial assistance, if granted, provides the Bank with the opportunity to positionitself and enhance its effectiveness in sustainable investment in the country.

    1.4. 

    Financial considerations for implementation of HKIA Master Plan –   Study

    Component 1.

    1.4.1.  The study covered in this proposal report does not include a financial analysis component.The purpose of this section is to provide supplementary information, in support of the grant request,on the financial considerations and activities independently undertaken by NAC to evaluate thefinancial challenges in the implementation of terminal building extension of HKIA. Although thefinancial analyses fall outside the scope of this report, this section is included to appreciate theviability of the project, albeit based on a previous study and subject to an update. This section on

    „financial consideration‟ is therefore considered as complementary, yet key, information to supportthis proposal report.

    1.4.2.  Since commencing operations in 1999, NAC has become one of the flagship products ofthe government‟s strategy to reform the parastatals to boost competitiveness and efficiency within thetransport sector. As part of the strategy for growth, NAC commissioned and funded an appraisal in2006 to assess the financial viability on HKIA terminal building extension scheme based on themaster plan previously developed in 2004. The appraisal was executed by a specialist consultantConsultancy Services Africa (CSA) of South Africa with the remit to develop a Business Plan thatanalyses the financial strength of NAC based on current (2004) and potential operational capability.The „Business Plan‟ report, now obsolete and subject to review and update, was to form the basis for potential negotiations with interested financial institutions in the evaluation of NAC financial status as

    a „going concern‟ and its ability to service any credit facilities. The business plan which includedfinancial analysis took into consideration several factors such as:

  • 8/20/2019 Namibia - Airport Study - Approved

    9/37

    4

      Revenue growth and trend based on forecast in passenger traffic and growth in business

    environment

      The current and future operational expenditure and budget

      Inflationary factors

     

    Sensitivity analysis  Financial risks to NAC revenue stream and operations

      Capital development projects under the NAC portfolio

      Passenger and aircraft movement projection, updated forecast to 2006

      Cost estimates of scheme (2007 figures based on the 2004 master plan)

      Proposed draw-down, payback period of loan facility.

    1.4.3.  Based on assumed parameters, some covered in the preceding paragraph, the reportconcluded the scheme as being financially viable citing the revenue generation capability and capacity

    of HKIA operations as an indication of the profitability to successfully service credit facilities andimplement the project. The report makes no recommendation on the financial instrument to fund the project but rather focused its conclusion on the financial health of NAC.

    1.4.4.  For the purpose of aligning this MIC grant request and its objectives with the financialviability of the project, the current business plan report requires further review and update to accountfor the updated scope of the scheme that enhances the functionality of the airport and the associatedrevised cost estimate. The revised business plan would be commissioned, managed and fundedindependently by NAC and is intended to commence in earnest, subject to the successful outcome ofthis application. The findings of the business plan will subsequently form the basis for any futurefunding request to prospective financial institutions or investors (private, bilateral or multilateralinstitutions) and which the Bank may wish to participate.

    2.  DESCRIPTION OF STUDY

    2.1.  Study Components

    2.1.1.  The study covers a total of eight (8no) airports located in Windhoek (Hosea KutakoInternational and Eros Airports), Walvis Bay, Keetmanshoop, Luderitz, Rundu, Katima Mulilo andOndangwa. The study will be managed by the Namibia Airports Company (NAC), the ExecutingAgency and designated infrastructure owner. The output would determine final scope of detaileddesign and, in some cases, scope of works on future implementation.

    2.1.2.  The study components are summarised as follows:

    i)  Feasibility Studies and Basic Design of Terminal Building for HKIA

    Reviewing the 2004 Feasibility Study Report to permit an updated feasibility study, designoptioneering and preliminary design to be carried out. Key Outputs: Feasibility Study Report,Preliminary Detailed Design Deliverable, Works Implementation Programme and EngineersEstimate. 

  • 8/20/2019 Namibia - Airport Study - Approved

    10/37

    5

    ii)  Preparation of Environmental Master-Plan for NAC Airports (8no. Airports) ;

    Performing studies and surveys in establishing balance between air-traffic and infrastructuresystems and the environment including climate change and natural resources, ecological andsocial systems and wildlife, considered in unison with future airport developments. Key Output:Conceptual Planning Report, Detailed Environmental Master Plan covering all NAC airports.

    iii)  Studies for upgrading (Master Planning & Land-Use Planning) of NAC Regional Airport

    (5no. Airports).

    2.1.3.  Performing studies and surveys that consider all components of an efficient operationalairport based on sound engineering, economic and environmental information to create an airportlayout that optimises land-use for operational facilities while taking into account future development.Key Output: Inception Report, Conceptual Planning Report, Draft and Final Master Plan and FutureLand Use Plan Reports. 

    2.1.4.  An abridged TOR is provided Annex 6. A detailed TOR will be prepared and submitted by the Applicant prior to contract award to ensure the project complies fully with the relevant

    requirements of the Bank‟s guidelines.

    3. 

    STUDY COST ESTIMATES AND FINANCING PLAN

    3.1.  Cost Estimates

    3.1.1.  The total cost of the study based on estimated fee proposals provided by consultants, netof taxes and duties excluding contingencies, is estimated as US$947,500 (UA596,000 approx) with a proposed local and foreign exchange cost components of US$497,000 (UA312,800 approx) andUS$450,000 (UA283,200 approx) respectively. Cost per study component, including five (5) percentfor contingency, is provided in Table 3.1 below. The corresponding preliminary cost breakdownschedule (in USD) per study is provided in annex 4.

    Table 3.1- Cost Estimate: Breakdown per Study Component

    3.2.  Financing Plan

    3.2.1.  The contribution by the fund is based on „95%:5%' split between the Bank and GRNrespectively subject to the Bank‟s maximum contribution of UA600,000 sourced from the MIC-TAF.The five (5) percent will be contributed by GRN/NAC from its own funds. The maximumcontribution from the fund, net of taxes and including contingencies, is estimated as UA 594,000(table 3.2).

    USD (million) UA(million)

    Consulting Services COMPONENT FC LCTOTA

    LFC LC

    TOTA

    L

    HKIA Feasibility Study and terminal building design 0.4 0.047 0.447 0.252 0.030 0.281

    Environmental Master Plan (8no. Airport) 0.05 0.25 0.3 0.031 0.157 0.189

    Master-Plan/Land Use Plan (5no. Airport) 0 0.2 0.2 0.126 0.126

    Subtotal 0.45 0.497 0.947 0.283 0.313 0.5961

    Contingencies (5%) 0.023 0.025 0.047 0.014 0.016 0.030

    Total 0.473 0.522 0.995 0.297 0.328 0.6251 November Rates US$1.59 = 1 UA

  • 8/20/2019 Namibia - Airport Study - Approved

    11/37

    6

    Table 3.2 –  Financing Plan

    4.  PROCUREMENT

    4.1. 

    Procurement Arrangement

    4.1.1.  The procurement plan including type of contract, consultant selection and review processes will be in accordance with theBank‟s Rules and Procedures for the Use of Consultants. The procurement of the consultancy services will be undertaken on the basis of shortlisted firms throughexpression of interest evaluated by the Executing Agency in accordance with Bank‟s rules  and

     procedures.

    4.1.2.  The Request for Proposals including all respective TORs will be reviewed by the Bank prior to submission to the short-listed consultants.

    Table 4.1- Procurement Arrangements (in UA)

    4.1.3. 

    The contract will be let on a Lump Sum contract basis with fixed and reimbursablecomponents. Table 4-1 shows the total procured amount of the study without any external funds. Anyincrease in cost over and above the total estimated cost will be additional to NAC‟s five (5) percent

    contribution.

    4.2. 

    Disbursements Arrangements

    4.2.1.  The disbursement arrangements for the MIC Funds will be either of the following

    methods:

      The Direct Payment Method

      The Reimbursement Method

      The Special Account Method

    4.2.2.  All disbursements will be subject to the Bank‟s rules as set out in the Bank‟sDisbursement Handbook. The Bank‟s  Disbursement Rules including the rules on suspension ofdisbursements will apply.

    5.  IMPLEMENTATION STRATEGY

    5.1.  Proposed Implementation Schedule

    5.1.1.  The expected duration for the study is twelve (12) months from the date the contract

     becomes effective on the basis or assumption that critical path activities commence simultaneously.The tentative programme is shown in table 5.1 below.

    Funding Source US$ (million) UA(million)

    FE LC TOTAL FE LC TOTAL

    MIC (95%) 0.449 0.496 0.945 0.282 0.312 0.594

    GRN/NAC (5%) 0.024 0.026 0.050 0.015 0.016 0.031

    Total 0.473 0.522 0.995 0.297 0.328 0.625

    UA(million)

    Consulting Services COMPONENT Selection

    Non-banking

    funding TOTAL

    Total 0.625 [0.594] - 0.625

    Total 0.625 [0.594] - 0.625

    [ ] figure in bracket financed from MIC TAF.

  • 8/20/2019 Namibia - Airport Study - Approved

    12/37

    7

    Table 5.1 - Implementation Schedule

    5.2.  Executing Agency

    5.2.1.  The Executing Agency, Namibia Airports Company (NAC), will manage the delivery ofthe study from inception to completion and will assign a competent senior staff member as the ProjectCoordinator. The nominated person will ensure consistency and harmonisation of all the studycomponents, ensure compliance with project remit and will be the NAC contact person for allcorrespondence with the Bank.

    6.  LETTER OF AGREEMENT

    6.1.1.  Upon approval of grant request, a Letter of Agreement will be drafted by the Bank(GECL) in accordance with the format provided in Annex 3 of the Guidelines for Administration andutilization of the Technical Assistance Fund for MIC and signed by authorised representatives of the

    Bank and GRN. The latter will be a representative from the Ministry of Finance signing on behalf ofGRN. A template of the Letter of Agreement is drafted and provided in Annex 6 of this document.

    7.  CONCLUSIONS AND RECOMMENDATIONS

    7.1.  Conclusions

    7.1.1.  In the current CSP (2009-2012), the Bank cites new strategy to address poverty,inequality and unemployment. In addition, the CSP stipulates the enhancement strategies to beadopted by the Bank to strengthen its position of competitiveness to expand operations in Namibia.These complementary strategies are linked to the three major pillars identified in section 15 of the

    CSP which is to enhance the competitiveness and growth of private sector (SMEs) as well as offeringdiversification opportunities from mining into areas such as tourism.

    7.1.2.  In spite of the poverty, inequality and employment challenges, the Bank recognisesaspects of sound governance, low crime and natural landscape as complimentary attributes that can beleveraged. The development in the aviation sector has its lifeline in the tourism industry whichconsequently provides the much needed employment and business opportunities for the populationand SMEs respectively. The impact of tourism is countrywide affecting both rural and urban population and this assistance facilitates the means to improving the social and economic conditionsof the greater population.

    7.1.3.  The proposed study, for which finance is being sought, constitutes a significant phase indesign and feasibility study that brings the enhancement programme of the airports much closer to

    reality and ultimately meeting some of the country‟s key objectives and that of the Bank. It also putsthe Bank in the prime position for sustainable and future investment in Namibia.

    Activity Responsibility Target Dates

    1.  Board Approval of MIC Trust Fund ADB June 2010

    2.  Issue of RFP to Consultants NAC July 2010

    3.  Receipt/Review and Approve of Proposal NAC/ADB Aug 2010

    4.  Contract Award (all components) 2. NAC September 2010

    5.  Completion/submission of Final Environmental Master Plan

    (8no. Airports) - 9 months from start date. NAC/Consultant February 2011

    6.  Completion/Submission of Final HKIA Feasibility, Mater Plan

    & Design - 12months from start date1 

     NAC/Consultant September 2011

    7.  Completion/Submission of Final Master-Plans &Land-Use (5no.

    Airports) - 12 months from start date1 

     NAC/Consultant September 2011

    1.Critical path activities 2.Start date = date contract become effective

  • 8/20/2019 Namibia - Airport Study - Approved

    13/37

    8

    7.2.  Recommendations

    7.2.1.  It is recommended that a grant not exceeding UA 594,000 from the resources of the MICTAF be extended to the Government of the Republic of Namibia to carry out the study described inthis memorandum.

  • 8/20/2019 Namibia - Airport Study - Approved

    14/37

     

    ANNEXES

  • 8/20/2019 Namibia - Airport Study - Approved

    15/37

     

    ANNEX 1 –  MAP OF NAMIBIA, AIRPORT LOCATION

    (Indicatively Showing Airport Locations)

    This map was provided by the African Development Bank exclusively for the use of the readers of the report to which it is att ached. The namesused and the borders shown do not imply on the part of the Bank and its members any judgement concerning the legal status of a territory norany approval or acceptance of these borders.

    HKIA & Eros

    Katima MuliloRundu

    KeetmanshoopLuderitz

    Walvis Bay  

    Ondangwa

  • 8/20/2019 Namibia - Airport Study - Approved

    16/37

     

    ANNEX 2 - PHOTOGRAPHS 

    Figure 1: Eros Airport: Land Use and Master Planning to optimise land use and revenue generation

  • 8/20/2019 Namibia - Airport Study - Approved

    17/37

    Figure 3: HKIA Existing Terminal Building (Terminal 2)Feasibility Study/Master Planning/Design/Environmental Master Planning 

    Figure 4: HKIA Existing Terminal Building (Terminal 1)Feasibility Study/Master Planning/Design/Environmental Master Planning

  • 8/20/2019 Namibia - Airport Study - Approved

    18/37

     

    ANNEX 3 - IMPLEMENTATION SCHEDULE

    ActivityJun-10

    Jul-10

    Aug-10

    Sep-10

    Oct-10

     Nov-10

    Dec-10

    Jan-11

    Feb-11

    Mar-11

    Apr-11

    May-11

    Jun-11

    Jul-11

    Sept-11

    Responsibility

    TargetDates

    Board Approval of MIC Trust Fund/Letter of Agreement Signed ADB Jun- 10

    Issue of RFP to Consultants  NAC Jul-10

    Receipt/Review and Approve of Proposal  NAC/ADB Aug-10

    Contract Award (all components)  NAC Sept-10

    Completion/submission of Final Environmental Master Plan NAC/Consultant

    Feb-11

    Completion/Submission of Final HKIA Feasibility, Mater Plan &

    Design

     NAC/Consul

    tantSept-11

    Completion/Submission of Final Master-Plans &Land-Use NAC/Consultant

    Sept-11

    ----------------- ADB responsibility; Others (NAC/GRN/Consultant)

  • 8/20/2019 Namibia - Airport Study - Approved

    19/37

     

    ANNEX 4 –  COST ESTIMATE SCHEDULE (IN USD)

    Preliminary Cost Estimate for HKIA Feasibility Study and Basic Master Plan-Study Component 1

    Professional Fee (international Consultant) Cost reimbursable –  Travels, Misc

    Man

    days Rate Cost (USD) No

    Rate

    USD Cost

    TOTAL

    Project Leader 15 1300 19500

    Lead Airport Architect 60 1200 72000International air travel 10 1600 16000

    Airport Architects 120 600 72000 Domestic travel 20 50 1000

    Lead Airport planner 50 1200 60000 Per diem 50 100 5000

    Airport Planner 120 600 72000Misc

    (reporgraphics,etc 1 12000 12000

    Lead Airport Civil/Structural Engineer 40 1200 48000

    Airport Engineers 100 600 60000

    Quantity Surveyor 15 600 9000

    Subtotal 520 $412,500 Sub-Total $34,000 $446,500

    Preliminary Cost Estimate for 8no Airports Environmental Master Plans - Study Component 2Professional Fee (International/Local Consultant) Cost reimbursable –  Travels, Misc

    Man

    days Rate Cost (USD)

    Project Leader 20 1300 26000 NoRate

    USD Cost

    TOTAL

    Lead Airport/Transport Planner 40 1200 48000

    Lead Environmental Specialist 50 1200 60000 International air fares 10 1500 15000

    Environmental Specialist - Biologist 40 900 36000 Domestic air travel 20 250 5000

    Environmental Specialist  –   Noisespecialist 40 900 36000 Per diem 25 100 2500

    Soil and Ground Specialist 40 900 36000Misc (reprographics,

    car rentals1 5000 5000

    Socio-Economic Specialist 50 600 30000

    Subtotal 280 $272,000 Sub-Total $27,500 $299,500

    Preliminary Cost Estimate for 5no. Airports M aster Plans and Land Use -Study Component 3

    Professional Fee (International/Local Consultant) Cost reimbursable –  Travels, Misc

    Man

    days Rate Cost (USD) No

    Rate

    USD Cost

    TOTAL

    Project Leader 15 1000 15000

    Lead Airport Planner 30 900 27000 International air travel 10 600 6,000

    Airport Planners 100 450 45000 Domestic air travel 20 250 5,000

    Lead Airport Architect 30 900 27000 Per diem 40 100 4,000

    Airport Architect 60 450 27000Misc (reprographics,

    car rentals1 5,000 5,000

    Airport Infrastructure Engineer 30 450 13500Transport Economist 60 450 27000

    Subtotal 325 $181,500 Subtotal $20,000 $201,500

    TOTAL ESTIMATE COST, USD (EXCLUDING CONTINGENCIES) $947,500

  • 8/20/2019 Namibia - Airport Study - Approved

    20/37

     

    ANNEX 5 – REQUEST FORM

  • 8/20/2019 Namibia - Airport Study - Approved

    21/37

    - 2 -

  • 8/20/2019 Namibia - Airport Study - Approved

    22/37

    - 3 -

  • 8/20/2019 Namibia - Airport Study - Approved

    23/37

    - 1 -

    ANNEX 6 – LETTER OF AGREEMENT

    AFRICAN DEVELOPMENT BANK

    13 Avenue du GhanaB.P. 3231002 Tunis BelvédèreTunisieTelephone: (216) 71 102 181Fax : (216) 71 333 675Web Site : www.afdb.org 

    The Permanent Secretary,

    Ministry of Finance,

    Private Bag 13295

    WINDHOEK, NAMIBIA

    Dear Mr C Schlettwin:

    LETTER OF AGREEMENT: UTILISATION OF MIC TECHNICAL ASSISTANCE FUND TOFINANCE FEASIBILITY STUDIES, DESIGN AND MASTER PLANNING OF NAMIBIA AIRPORTS

    I am writing on behalf of the African Development Bank to indicate the Bank‟s decision to provide to the

    Republic of Namibia, (the Recipient) a Grant in an amount not exceeding UA 594,000 (Five Hundred and

     Ninety Four Thousand Units of Account) (the “Grant”) from the Bank‟s Middle Income Countries Trust

    Fund. The purpose of the Grant is to finance the Namibia Airport Study activities.

    The Grant is being provided for the purposes and on the terms and conditions set forth in the Attachments

    hereto, and the Recipient hereby represents, by confirming its agreement hereunder, that it is authorised to

    contract, withdraw, and utilize the Grant for the said purposes and on the said terms and conditions.

    The provision of the Grant does not constitute or imply any commitment on the part of the Bank to assist

    to finance or part finance any project developed as a result of the study for which the Grant is provided.

    Please confirm your agreement with the foregoing and the conditions and terms attached hereto, on behalf

    of Republic of Namibia, by signing, dating, and returning to us the enclosed copy of this letter. This

    agreement will become effective on the date of countersignature by the Bank.

    http://www.afdb.org/http://www.afdb.org/http://www.afdb.org/

  • 8/20/2019 Namibia - Airport Study - Approved

    24/37

  • 8/20/2019 Namibia - Airport Study - Approved

    25/37

    - 1 -

    ANNEX 7 –  ABRIDGED TERMS OF REFERENCE FOR TECHNICAL ASSISTANCE

    FOR THE ENHANCEMENT OF EXISTING AIRPORT INFRASTRUCTURE

    A.  GENERAL INFORMATION

    1.  INTRODUCTION

    1.1.  Background

    1.1.1.  The Government of Republic of Namibia has a vision for the future in the Vision 2030

    Paper addressing medium and long term objectives as well as the policies and strategies to meet

    those objectives. The transport sector is identified as critical to those visions and the Government,

    in a bid to redress the shortcoming, published the White Paper on Transport Policy in 1995 and

    the Third National Development Plan (NDP3) setting out recommendations for implementation.

    One of the bold strategies in support of the objectives in respect of the proposed study included:

    a.  Review of the parastatals in the sector by commercialising functions that can be more

    efficiently performed in a commercial environment.

     b.  Draw up and implement a master plan of the development for each of the regional

    airports/aerodromes of the airport company Namibia Airports Company (NAC).

    1.1.2.  It is on the basis of the Government‟s vision that the NAC was formed under the Airport

    Company Act, Act 25 of 1998 as an autonomous 100% state-owned entity with the Ministry of

    Works and Transport as the regulatory body. The NAC is responsible for the operations and

    management of licensed regional airports in Namibia.

    The proposed study is endorsed by the Government of the Republic of Namibia

    2.  NAMIBIA AIRPORTS COMPANY

    2.1.  Introduction

    2.1.1. 

    The NAC commenced operations in February 1999 after the Airport Company Act, Act

    25 of 1998 came into force. The main objectives are to ensure:

     

    The arrival, surface movement, parking and departure of aircrafts; 

    The servicing of aircrafts, including the supply of fuel and lubricants;

      Ground handling of aircrafts, passengers, baggage and cargo;

    2.1.2.  The key focus areas to achieve the above objectives:

     

    Infrastructure development, maintenance, technology and modernisation;

  • 8/20/2019 Namibia - Airport Study - Approved

    26/37

    - 2 -

     

    Aeronautical revenue growth;

      Commercial revenue growth;

      Cost efficiencies and internal processes and;

      Human capital development

     

    Commercial revenue growth

    2.1.3.  The NAC is a member of the Airport Council international (ACI) and the International

    Air Cargo Association (TIACA). The company is also committed to observe and follow the

    ICAO (International Civil Aviation Organisation) conventions and practices regarding airport

    operations and management.

    2.2.  Governance

    2.2.1.   NAC functions under the Board of Directors, appointed by the Ministry of Works and

    Transport in his/her capacity as the Portfolio Minister. The Board appoints the Chief Executive

    Officer, CEO, tasked with managing and exercising control the company operations. The Board

    formulates policies and strategies that guide the company towards attaining it vision and mission.

    2.2.2.   NAC recognises the need for a strategic corporate focus to better enable it to serve it

    clients and improve its financial sustainability and is guided by high standard of ethics and

    integrity to industry benchmarks and guidelines. It is also guided by Act 25 of 1998, the

    country‟s Vision 2030 and Performance Agreements with shareholders.

    2.3.  Airports

    2.3.1.  The NAC owns and manages the operations of eight (8) airports and they are; Hosea

    Kutako International, Eros, Walvis Bay, Keetmanshoop, Luderitz, Rundu, Katima Mulilo and

    Ondangwa airports

    2.3.2.   NCA‟s operational partners are the international and domestic airlines and aircraft

    operators, government agencies, private retailers as well as concessionaires licensed to operate at

    the airport premises. NAC values the importance of developing and maintaining good

    infrastructure and facilities at its airports to maintain world-class standards in line with its master

     plans and the company has been undertaking several strategic infrastructure and commercial

    development project with the aim of improving its overall service delivery. Projects have been

    undertaken in collaboration with private developers and investors aligned with the modernconcepts of Public Private Partnerships (PPP).

    2.3.3.  The features of each airports and how they serve and impact the country‟s economy are

    described below.

  • 8/20/2019 Namibia - Airport Study - Approved

    27/37

    - 3 -

    a.   Hosea Kutako International Airport(HKIA)

    HKIA is the only international airport situated 45km east of Windhoek, the capital of Namibia. It

    complements the airport capacity of other hubs on the Southern African region. It handles over

    half a million passengers annually and over fourteen thousand aircraft movement with frequent

    connections to Johannesburg, Cape Town and Luanda (Angola). The schedules airlines connect

    HKIA to international hubs in Europe and other regional destinations.

    Recent terminal building improvement has seen the some expansion and refurbishment to

    enhance customer experience such as public parking, vat refund facilities and retail outlets.

    b.   Eros Airport(HKIA)

    Eros airport is located in Windhoek, 5km from the business district and classified as the NAC‟s

     busiest airport in terms of aircraft movement. It is the centre of aircraft maintenance and is the

    hub for general and leisure aviation serving the tourism industry. It has key facilities for aircraft

    operations such as cargo handling, fire stations, ground handling as well as land for prospecting

    commercial developer for hangers, warehousing and offices.

    Recent works completed at the airport include: renovation of office block for customs and excise,

    general upgrading of terminal building; car park facilities and construction of air cargo terminal.

    Other projects are planned following the development of the mater-plan.

    c. 

    Walvis Bay Airport

    Located in Walvis Bay, 15km east of the town. The airport has undergone some upgrading in its

    facilities to handle wide-bodied aircrafts with the objective of elevating the airport to

    commensurate as the second international airport. Expansion of the terminal building is also

     planned to coincide with the projected growth in passenger numbers. Other aviation facilities

    have been upgraded with state-of-the-art landing system for flight operations given the prevailing

    and persistent overcast weather conditions at its location. In a location that forms part of the

     Namibia‟s Economic Processing Zones (NEPZ), the airport is intended to be the major export

    hub of fish and other resources to the rest of Africa and Europe.

  • 8/20/2019 Namibia - Airport Study - Approved

    28/37

    - 4 -

    d.  Ondangwa Airport

    Ondangwa airport is located in the north-central part of the country with a catchment area that

    includes regions of highest population density (Oshana, Oshikoto,Ohangwena, Omusati, Kunene)

    and serves as the fastest air-link into southern Angola. Typical of other regional airports, there is

     potential for expansion and project such as new terminal building and services, access roads and

     passenger- and cargo-handling facilities, to name a few, are envisaged. Container depots are also

     planned to add value by serving the existing railway interlink between Ondangwa, Oshikango

    and Oshakati.

    e.   Keetmanshoop Airport

    The town of Keetmanshoop is some 500km from the capital Windhoek and the airport is the

    home of the Namibia Aviation Training Academy (NATA). There is currently an aspiration to

    make this airport the aircraft maintenance centre for Namibia given its potential capacity and

     physical conditions. It has also been identified as having the potential to serve as the tourism hub

    for charter operations after the proclamation of mining town such as Oranjemund and Rosh

    Pinah. It also has a customs and immigration services and is able to handle cross-border traffic

    into southern Namibia.

     f.   Luderitz Airport

    Luderitz is located on the coast and in proximity to the mines of Rish Pinah, Oranjemund and

    Elizabeth Bay hence the airport has significant economic importance to the country. There has been steady traffic growth at the airport over the years therefore required upgrading works is

    required which is align with the proposed study. Other upgrading activities to enable night

    operations and overcome adverse overcast weather conditions have been implemented.

     g.   Rundu Airport

    Rundu airport is located 5km southwest of the town of Rundu in the region bordering on southern

    Angola and has the benefit of vast land setting ideal for storage facilities and unlimited potential

    infrastructure development. It has excellent storage facilities for cargo to Angola and serves thetourism industry as hub for the chartered flights for tourist and businesses attracted by the game

     parks such as Khaudom, Mahango, Popa Falls and Buchman land.

  • 8/20/2019 Namibia - Airport Study - Approved

    29/37

    - 5 -

    h.   Katima Mulilo Airport

    Katima Mulilo Airport is the gateway for the tropical Caprivi region and the home-town of the

    „African BIG 5‟ attraction. It is located close to the Zambesi River, northeast of the country,  and

    serves other attraction in Botswana and Zimbabwe. It also serves as a refuelling hub for air traffic

    from South Africa en route to Central Africa. There is an aspiration by NAC to upgrade the

    access road to the airport.

    3.  THE PROPOSED STUDY

    3.1.  Introduction

    3.1.1.  To upgrade the existing airport infrastructure to a standard that aligns with the economic

    and social development in the country, taking cognisance if the environmental issues, while

    generating business opportunities for all stakeholders. It is to meet future aviation demands while

     providing a sustainable solution that addresses the environmental and socio-economic issues.

    3.1.2. 

    The study has three components each requiring the services of specialised consultants

    which in combination provide NAC with an aggregate output to facilitate the implementation of

    the enhancement programme on all eight regional airports. Although some improvements have

     been made to the physical facilities, airport operations and services offered to customers,

    currently falls short of meeting present and future demands as well as operational requirements

    associated with increased air traffic and usage. The intended purpose of the proposed study is to

    address the shortcomings and formulating appropriate solutions in aspects relevant to the

    enhancement objectives.

    3.2.  Study Interface

    3.2.1.  To ensure an integrated output, each consultant shall work very closely with key

    stakeholders as deemed appropriate including the community, public and private institutions,

    civil society organizations, international statutory and regulatory bodies, governmental and non-

    governmental organisation etc. The views, preferences and limitations of these groups shall be

    taken into account in the study.

    3.3.  NAC Coordinator

    3.3.1. 

     NAC will appoint a Coordinator to oversee the study to ensure close integration andcompliance with all aspect of the study remit. The Coordinator will be NAC main contact with all

    consultants and other parties involved in the Study and shall participate actively in the execution,

    administration, monitoring and supervision of the activities of the study. Although it is the

    responsibility of NAC to mange the interface of the studies, it is expected that respective

    Consultant maintain open dialogue among all parties to ensure that fully integrated and complete

    output is accomplished.

  • 8/20/2019 Namibia - Airport Study - Approved

    30/37

    - 6 -

    B.  TECHNICAL INFORMATION

    4.  THE STUDY

    4.1.  STUDY COMPONENTS

    4.1.1. 

    The objective of this Study is two-fold, each to develop the relevant output of master plans and designs to bring forth deliverables in readiness for future implementation. The

    consultancy services being procured broadly cover the following:

    a.  For HKIA, follow-up on the 2004 master-plan study, expanding the scope and

    updating as prescribed, in readiness for future implementation.

     b.  For other specified airports, to fully prepare master-plans for the development of

    regional airports that will subsequently form the basis for future design and

    implementation.

    The scope of each service component described below highlights the key areas of interest. It is

    advisable that, where necessary, clarification of the scope is sought with NAC prior to pricing

    and commencement of work.

    4.2.  Consultancy Services Components 1- Feasibility Studies and Basic Design of

    Terminal Building for HKIA

    4.2.1.  The scope of services is to review the 2004 Feasibility Study Report (enclosed) prepared

     by others to facilitate development of an updated study, perform design optioneering and option

    selection followed by preliminary design for the upgrading of the passenger terminal complex atHosea Kutako International Airport (HKIA). Based on the above, the following is envisaged as

    the three key activities.

    a.  Investigate two design alternatives for terminal buildings and shall comprise:

      A revision to the layout of the existing Terminal 2 (T2) and Terminal 1 (T1)

     buildings connected by a new link structure the two buildings. T1 and T2 will be

    designated arrival and departure building respectively.

     

    A new T1 building and new link structure to the existing T2 building with the T2layout upgrades to suit.

     b.  Prepare an outline design of the two alternative options described in item a) above.

    c.  Prepare preliminary detailed design of the preferred and selected option.

  • 8/20/2019 Namibia - Airport Study - Approved

    31/37

    - 7 -

    4.2.2.  The scope excludes studies on airport infrastructure external to the terminal buildings,

    such as but not limited to, flight stands, apron, runways, access roads, parking, exterior signage

    and lighting. These exclusions are typically facilities specific for aircraft operations and or

    facilities that have no direct passenger interface.

    4.2.3. 

    It is expected that a business plan will be prepared following completion of the study toascertain the financial viability of the project, if implemented, and will consequently form the

     basis for developing a financing strategy for the project.

     Proposed Specific Activities

    4.2.4.  The following are the activities proposed to execute the works: The consultant shall:

    a.  Review the existing master-plan of 2004 and ascertain through dialogue with NAC

    current development needs, objectives and trends. b.

     

    Update forecast and analysis of flight traffic, passenger flow, security measures,

    immigration and emigration and all other functions and activities relevant to the layout of

    the terminals buildings

    c.  Prepare drawings and or sketches, as appropriate, of the design possibilities for the

    terminal complex for discussion with NAC

    d.  Produce a 1:500 drawing (plans, elevation, etc.) proposals of the terminal complex

    e.  Based on the preferred/approved design, develop programme and budget for the

    executing preliminary detail design.

    f. 

    Develop and complete the master-plan as per the programme and budget.g.

      Develop and complete preliminary detailed design including technical specifications as

     per the programme and budget.

     Proposed Output

    4.2.5.  The output for the works shall include but not limited to:

    a.   New Feasibility Study Report (Master-Plan),

     b.  Preliminary Detailed Design Deliverable (Drawings, Technical specifications etc) ,

    c.  Programme and Engineers Estimate for future implementation

     Proposed Schedule

    4.2.6.  This activity is schedule for completion twelve (12) months from the date contract

     becomes effective.

  • 8/20/2019 Namibia - Airport Study - Approved

    32/37

    - 8 -

     Proposed Resource

    4.2.7.  The consultant shall in general have the following expertise to carry out the services:

      Project Leader ((20yrs minimum experience)

     

    Lead Architect (15yrs minimum experience)

      Architects (local and international mix)

      Lead Airport Planner (15yrs minimum experience)

      Airport Planner

      Lead (Airport) Civil/Structural (15yrs minimum experience)

      Civil/Structural Engineers

      Quantity Surveyor

    Unless stated otherwise, all specialists shall have at least 10years of working experience.

    4.3.  Consultancy Services Components 2 -Preparation of Environmental Master-

    Plan for NAC Airports (8no. Airports);

    4.3.1.   NAC‟s objectives is put focus on the environmental issues associated with the

    development of the airport to ensure an environmentally sustainable development is achieved.

    Based on the above, the consultant shall prepare a set of comprehensive Environmental Master

    Plans for the eight airports in question that meets, as a minimum, the objectives below.

    4.3.2.  For each of the activities described below, the consultant shall include in the EMP,

     proposed actions for sustainable development of the airport and implementation plans.

    a.  Consideration for the natural resources and environment in the greater airport areas

     b.  Establish a sustainable balance between air-traffic systems and infrastructure on one side

    and the ecological and social systems on the other.

    c.  Improving safety through a better separation air-traffic and the surrounding nature such

    as wildlife

    d.  To provide an environmental framework for future planning, development and

    investments.

    e. 

    Proposed activitiesf.

      Establish framework for the EMP with NAC

    g.  Perform desk study of all relevant documents, rules and regulations, development plans

    and drawings.

    h.  Assess ALL relevant aircraft-related activities at the airports including but not limited to

    fuel supply, storage facilities, fuelling procedures, noise, emissions, etc against

    international, regional and national requirement.

  • 8/20/2019 Namibia - Airport Study - Approved

    33/37

    - 9 -

    i.  Carry out a Strategic Environmental Assessment (SEA), a tool developed by the African

    Development Bank, to ensure integration of social and economic aspects into the study

    thus providing a holistic appreciation of the impact and developing alternative where

    necessary

     j. 

    Assess ALL relevant operations procedures at the airport including but not limited tomaintenance procedures, waste handling, wastewater treatment, contamination, etc.

    k.  Assess ALL risks associated with bird and animal strikes.

    l.  Assess ALL activities associated with the runway system including but not limited to sue

    of herbicides, energy usage, emission of service vehicles, surface water contaminations,

    etc

    m.  Assess ALL relevant activities associated with the use of the Terminal Building

    including, but not limited to, water supply system, energy system, waste-water and solid

    waste handling systems

    n. 

    Assess ALL aspects of social impact associated with future development including butnot limited to, economic effects of the airport in the region, the impact on local

    community (employment, HIV/AIDS etc), the stress effect from the noise generated by

    aircraft activities

    o.  Assess the gender-related implication of the increased operational capacity of the

    infrastructure. This will not to be limited to the implementation works but the rather the

    employment opportunities generated, particularly by a potentially vitalized leisure

    tourism industry.

     p.  Assess the threats of climatic change, near term and long term, locally and globally, of

    the airports development as a result of the forecasted growth in air traffic at someselected airport.

     Proposed Output

    4.3.3.  The output for the works shall include but not limited to:

    a.  A set of final and detailed Environmental Master Plans/Report covering all NAC airports

    with each airport covered by a separate EMP.

     b.  Drawings, images, technical investigation data, etc.

     Proposed Schedule

    4.3.4.  This activity is schedule for completion six (6) months from the date contract becomes

    effective.

  • 8/20/2019 Namibia - Airport Study - Approved

    34/37

    - 10 -

     Proposed Resource

    4.3.5.  The consultant shall in general have the following expertise to carry out the services:

      Project Leader ((20yrs minimum experience)

     

    Lead Environmental Specialist

      Environmental Specialist - Biologist with local experience*

      Environmental Specialist  –   Climate Change & Noise specialist with international and

    local experience*

      Soil and Ground Specialist

      Socio-economic Specialist *

      Airport/Transport Planner

    Unless stated otherwise, all specialists shall have at least 10years of working experience.

    *A minimum of 5yrs of local experience is required.

    4.4.  Consultancy Services Components 3- Studies for Upgrading (Master

    Planning & Land-Use Planning) of NAC Regional Airport (5no. Airports).

    4.4.1. 

    This study is to be carried out on five (5) airports; Keetmanshoop, Luderitz, Rundu,

    Katima Mulilo and Ondangwa airports. The scope covers studies and surveys that consider all

    components of an efficient operational airport based on sound engineering, economic and

    environmental information to create an airport layout that optimises land-use and operational

    facilities while taking into account future development.

    4.4.2.  As minimum, the activities for the preparation of the master and land-use plans for each

    airport shall be based on the following key areas. Consideration for a medium and long term

     planning period of twenty (20) and thirty years respectively as well as short-term intervention

    needs. The latter is necessary to address immediate issues related to say operational safety in

    compliance with ICAO requirements.

    Familiarisation with previous master plan and land use plan as well as NAC current planning

    documents and needs.

    a.  Identifying the future and present needs of the airport users taking into account latest air-

    traffic and passenger movement data.

     b.  Identifying the existing infrastructure facilities against new safety standards and norms

    c.  Although not exhaustive, it is vital that the physical conditions, integrity and

    functionality of all the facilities are fully appreciated and understood. In the context of

  • 8/20/2019 Namibia - Airport Study - Approved

    35/37

    - 11 -

    airport master-plan development, the following facilities are to be included in long-term

    development scenario

    d.  Runways, aircraft movement areas and parking aprons

    e. 

    Passenger terminal building in as far as interface with external infrastructure and aircraft

    operationsf.

      Cargo terminal and air traffic control buildings

    g.  Visual and non-visual navigational aids

    h.  Fire, crash and rescue services

    i.  Utility and telecommunication services

     j.  Car parking areas and road accesses

    k.  Perimeter security

     Proposed activities

    4.4.3.  In achieving the above, the following activities are envisaged,

    a.  Confirmation with NAC on objectives, methodology, scope and programme

     b.  Collection an review of available data,

    c.  Conduct an inventory/surveys on all facilities

    d.  Air-traffic and passenger forecasting

    e. 

    Prepare long-term development scenarios

    f.  Prepare a schedule of short term needs

    g.  Compile concept master plan report

    h.  Develop final master plan and detailed land use plan

     Proposed Schedule

    4.4.4.  This activity is schedule for completion twelve (12) months from the date contract

     becomes effective.

     Proposed Resource

    4.4.5.  The consultant shall in general have the following expertise assigned to carry out the

    services:

      Project Leader ((20yrs minimum experience)

      Lead Architect (15yrs minimum experience)

      Architects (local and international mix)

      Lead Airport Planner (15yrs minimum experience)

  • 8/20/2019 Namibia - Airport Study - Approved

    36/37

    - 12 -

      Airport Planners

      Transport Economist

      Civil/Structural Engineers

    All specialists shall have at least 10years of working experience in the sector and each shall havea combination of local and international experience.

     Proposed Output

    4.4.6.  The output for the works, including interim outputs, shall include but not limited to:

    a.  Inception report

     b. 

    Conceptual planning report

    c.  Draft Report (including Master Plan and Future Land use plan for each airport)

    d.  Final Report (including Master Plan and Future Land use plan for each airport)

    5.  COST ESTIMATE

    Each consultant shall prepare a cost estimate for their respective components of the study and

    submit the cost-time-resources schedule making up the fixed cost component of the service to be

     provided. Each contract shall be let on Lump Sum basis with fixed and reimbursable components.

    6.  BID DOCUMENTS (DETAILED TERMS OF REFERENCE)

    In addition to the cost estimate, each consultant shall supply to NAC a detailed TOR for

    respective study. A draft TOR for discussion and agreement with NAC prior to finalisation and

    costing may be provided, as necessary. In order to appreciate full scope of the study, it is

    expected that all draft TOR are reviewed concurrently to enable NAC to ensure an integrated

    scope is developed for the study.

    In general, the procurement process for the study shall follow the African Development Bank‟s

    Rules of Procedures for the Use of Consultants.

  • 8/20/2019 Namibia - Airport Study - Approved

    37/37

     

    AFRICAN DEVELOPMENT BANK

    BOARD OF DIRECTORS

    Resolution N° B/NA/2010/15

    Adopted on a lapse-of-time basis, on 20 July 2010

    Grant from the Middle Income Countries Technical Assistance Fund to the Republic of Namibia to finance part of the cost of the Feasibility studies, Preliminary design and Master

     plans for the Namibia Airport

    THE BOARD OF DIRECTORS, 

    HAVING REGARD  to: (i) the Agreement Establishing the African Development Bank (the"Bank"), in particular Articles 1, 2, 12, 14 and 17; (ii) the Financial Regulations of the Bank, in particular Regulation 8.1; (iii) the Revised Guidelines for the Administration and Utilization of theTechnical Assistance Fund for Middle Income Countries (MIC-TAF) contained in DocumentADB/BD/WP/2005/90/Rev.1/Approved; and (iv) the Grant proposal contained in documentADB/BD/WP/2010/115/Approval (the "Proposal");

    HEREBY DECIDES:

    1. 

    To award to the  Republic of Namibia, a Grant of an amount not exceeding theequivalent of Five Hundred and Ninety Four Thousand Units of Account (UA 594,000)from the MIC-TAF to finance part of the cost of the feasibility studies, preliminarydesign and Master Plans for the Namibia Airport;

    2.  To authorize the President of the Bank to conclude a Letter of Agreement between theBank and the  Republic of Namibia under the terms and conditions specified in theRevised Guidelines for the MIC-TAF, and in the Proposal;

    3.  The President may cancel the Grant if the Letter of Agreement is not signed withinninety (90) days from the date of approval of the Grant;

    4.  This Resolution shall become effective on the date above-mentioned.