Organisation of the work - proposal
04/19/23 1PD/DT/PO-MH
NA62 – TC activities – Organisation of the work – proposals
Integrationteam
Experimental Areateam
Sub-system teams
Design phase Installation phase
Integrationteam
Experimental Areateam
Sub-system teams
04/19/23 2PD/DT/PO-MH
NA62 – Integration team– Design phase
Tasks of the INTEGRATION team:
-CATIA model and layout drawing of the NA62 experiment
-Envelope models & Envelope drawings of individual sub-detectors
-Check and agreement with ‘Beatch files’
AIM = All partners working to agreed layout & dimensions
-Manage change requests in an official/agreed way
-Manage CDD/EDMS/CATIA CAD files
-Check that the individual parts can be fixed together = no clashes
-Check with the surrounding environment – cavern & services
-Studies of proximity services routing, support structures, access structures (in collaboration with Experimental area team).
-Installation studies
04/19/23 3PD/DT/PO-MH
NA62 – Experimental Area team– Design phase
Tasks of the EXPERIMENTAL AREA team:
-Scheduling of the design and installation phases of the work
- Liason with CERN groups for the provision of services: WATER, COOLING, GAS, VACUUM, VENTILATION, ELECTRICITY, CRYOGENICS, VACUUM, etc. Studies of external services routing by the CERN groups: support structures, access structures (in collaboration with Integration team).
- Design of the Beamline /Liason with the machine
- Study of the Beam dump.
- Together with the GLIMOS, the planning of the work incorporating the safety aspects and conformity with CERN rules: work package descriptions, procedures, etc.
- Arranging/Organising the removal of NA60
- Study of MNP33 Magnet displacement
- TSO of Experimental area and buildings.
04/19/23 4PD/DT/PO-MH
NA62 – Sub-detector teams– Design phase
Tasks of the SUB-SYSTEM teams:
-The conceptual and detailed design of the DELIVERABLES = SUB-SYSTEMS. In accordance with the agreed envelopes (Integration team).
- Managing envelope changes in an agreed way (Change request procedure).
- Working in accordance with the agreed schedule (Experimental Area team).
- Working together with the integration team for the exchange of CAD models, installation studies, cross-checks.
- Detailed assembly and installation studies of the sub-detectors.
04/19/23 5PD/DT/PO-MH
NA62 – Integration team– Installation phase
Tasks of the INTEGRATION team:
-Installation study cross-checks for the sub-systems
-Detailed design, supply and installation of any missing parts (services, supports, etc)
-Follow-up in the cavern of installation studies
-Manage change requests in an official/agreed way
-Manage CDD/EDMS/CATIA CAD files
04/19/23 6PD/DT/PO-MH
NA62 – Experimental Area team– Installation phase
Tasks of the EXPERIMENTAL AREA team:
-Scheduling and progress tracking of the work
- Installation of external services / Liason with the CERN groups for the installation of services: WATER, COOLING, GAS, VACUUM, VENTILATION, ELECTRICITY, CRYOGENICS, VACUUM…..
- Together with the GLIMOS, the planning of the work incorporating the safety aspects and conformity with CERN rules: installation procedure descriptions (work package analysis WPA’s ), procedures, etc. The management of the WPA’s: documents, approval procedures, realisation.
- Manage the installation of the experiment (together with the TC & GLIMOS)
- MNP33 Magnet : displacement, integration & services
- Manage the technical assistance (technicians, travelling crane operators, surveyors..)
- Installation and the setting up of the beamline
-Liason with the machine
-Realisation of the beam dump
-TSO of the Experimental Area and buildings.
04/19/23 7PD/DT/PO-MH
NA62 – Sub-detector teams– Installation phase
Tasks of the SUB-SYSTEM teams:
- Working in accordance with the agreed schedule (Experimental Area team).
- The writing of installation procedures (WPA’s) that describe: what work has to be executed, when it needs to be done, how it will be done (manpower and tooling), what safety measures will be taken, etc.
- Interacting with the Experimental area team to prepare for, and obtain approval of, the installation procedures (WPA’s).
- All workers to attend CERN safety training courses (in order to obtain access, etc).
-Providing the sub-detectors on the agreed dates and with the agreed means (manpower and tooling) to execute the work in accordance with the approved procedures. Respecting the safety rules.
- Attendance at progress meetings.