My Home Vihanga - Status Report as on 07.12.2013

18
Project Progress – 07 th Dec 2013

description

My Home Vihanga Status Report

Transcript of My Home Vihanga - Status Report as on 07.12.2013

Page 1: My Home Vihanga - Status Report  as on 07.12.2013

Project Progress – 07th Dec 2013

Page 2: My Home Vihanga - Status Report  as on 07.12.2013

LABOUR CAMP

Page 3: My Home Vihanga - Status Report  as on 07.12.2013

SIDE VIEW

Page 4: My Home Vihanga - Status Report  as on 07.12.2013

STUB COLUMNS DONE & BACKFILLING IN PROGRESS

Page 5: My Home Vihanga - Status Report  as on 07.12.2013

STUB COLUMNS ALSO COMPLETED FOR A-B & C-D GRIDS SOUTH SIDE VIEW

A B C D

Page 6: My Home Vihanga - Status Report  as on 07.12.2013

STUB COLUMNS ALSO COMPLETED FOR C-D & E-F GRIDS SOUTH SIDE VIEW

C D E F

Page 7: My Home Vihanga - Status Report  as on 07.12.2013

FOOTINGS IN PROGRESS FOR H-J GRIDS SOUTH SIDE VIEW

H J

Page 8: My Home Vihanga - Status Report  as on 07.12.2013

PCC & FOOTINGS IN PROGRESS SOUTH SIDE VIEW

K J G F

Page 9: My Home Vihanga - Status Report  as on 07.12.2013

PCC & FOOTINGS IN PROGRESS SOUTH SIDE VIEW

E D C A

Page 10: My Home Vihanga - Status Report  as on 07.12.2013

FOOTINGS DONE AND CURING IN PROGRESS –EAST SIDE VIEW

Page 11: My Home Vihanga - Status Report  as on 07.12.2013

FOOTINGS IN PROGRESS –NORTH EAST VIEW

Page 12: My Home Vihanga - Status Report  as on 07.12.2013

BLOCKS EXCAVATION IN PROGRESS

Page 13: My Home Vihanga - Status Report  as on 07.12.2013

BLOCKS IN PROGRESS

Page 14: My Home Vihanga - Status Report  as on 07.12.2013

BLOCKS IN PROGRESS

Page 15: My Home Vihanga - Status Report  as on 07.12.2013

WORK PROGRESS

Page 16: My Home Vihanga - Status Report  as on 07.12.2013

WORK PROGRESS

Page 17: My Home Vihanga - Status Report  as on 07.12.2013

SUB STATION WORK IN PROGRESS

Page 18: My Home Vihanga - Status Report  as on 07.12.2013

BATCHING PLANT -1 MOBALIZED;BATCHING PLANT-2 FOUNDATION IN PROGRESS