Muon Campus Projects Mary Convery

20
Muon Campus Projects Mary Convery 1

description

Muon Campus Projects Mary Convery. Background on Muon Campus plan. Earlier Plan had 5 Common Projects:  MC1 Building (GPP) MC Beamline Enclosure (GPP) MC Site Preparation (GPP) MC Cryo Plant (AIP) MC Delivery Ring Upgrades (AIP) This plan has evolved in response to - PowerPoint PPT Presentation

Transcript of Muon Campus Projects Mary Convery

Page 1: Muon  Campus Projects Mary  Convery

Muon Campus ProjectsMary Convery

1

Page 2: Muon  Campus Projects Mary  Convery

Background on Muon Campus plan

• Earlier Plan had 5 Common Projects:  MC1 Building (GPP) MC Beamline Enclosure (GPP) MC Site Preparation (GPP) MC Cryo Plant (AIP) MC Delivery Ring Upgrades (AIP)

• This plan has evolved in response to Recommendations made at Mu2e

DOE CD-1 review Maturing designs for (g-2) and Mu2e

• Recycler AIP was added in response to DOE recommendation and includes scope that was originally part of the g-2 project

• Scope of Site-Prep GPP changed in response to DOE recommendation that resulted in acceleration of Mu2e civil construction schedule

2

• Muon Campus projects plan actively orchestrated and managed via regular program meetings

• Although the packaging of the projects has been in flux, most of the individual jobs to be done are well-known and mature

• Aiming for Director’s review of full program in next few months

Page 3: Muon  Campus Projects Mary  Convery

Beam path to Muon Campus

3

Page 4: Muon  Campus Projects Mary  Convery

Aerial view

Recycler Ring

Beam Transfer and Delivery Ring

MC1 Mu2e

Muon Campus

g-2 Target Station

4

Page 5: Muon  Campus Projects Mary  Convery

MC-1 GPP

MC-1 building to house g-2 and future experiments, cryo system for g-2 and Mu2e, and power supplies for some beamline components

• 80’ x 80’ high-bay with 30 T crane

• internal loading dock • floor stable, load-

bearing to 700 T• good temperature

control• 70’ x 70’ low-bay for

staging, assembly, control room

• Includes extension of existing communication duct to replace duct which is interrupted during tunnel excavation

5

Page 6: Muon  Campus Projects Mary  Convery

MC-1 GPP WBS

Muon Campus MC-1 Building

1 Engineering, Design and Inspection

1.1 Preliminary Design ED&I

1.2 Final Design ED&I

1.3 Construction ED&I

2 Administration

2.1 Preliminary Design Administration

2.2 Final Design Administration

2.3 Construction Administration

3 Construction

3.1 Fixed Price Construction

3.2 Time and Materials Construction

3.3 Advanced Procurement

6

• Total cost expected to be $9M, costing is mature

Page 7: Muon  Campus Projects Mary  Convery

Beamline enclosure GPP Civil construction of enclosures for M4 and

g-2 extraction lines• Delivery Ring to Mu2e – M4: 10’ wide x 8’

high concrete box type enclosure with 16’ equivalent earth shielding. Base slab at El:728’-8”.

• M4 line to g-2: 8’wide x 8’ high enclosure. Base slab slopes from El: 728’-8” to El 734’-6”.

• Beamline power supplies from AP-30, g-2 and Mu2e. Low Conductivity Water extended from Delivery Ring.

• Includes lighting, grounding, electrical power distribution, cable tray, fire detection, life safety egress, drainage and sumps. Installs beam abort.

7

Page 8: Muon  Campus Projects Mary  Convery

Beamline enclosure GPP WBSMuon Campus Beamline Enclosure GPP

1 Engineering, Design and Inspection

1.1 Preliminary Design ED&I

1.2 Final Design ED&I

1.3 Construction ED&I

2 Administration

2.1 Preliminary Design Administration

2.2 Final Design Administration

2.3 Construction Administration

3 Construction

3.1 Fixed Price Construction

3.2 Time and Materials Construction

3.3 Advanced Procurement

8

• Current estimate $9.2M, could increase as plans become better defined (beamline design still in progress)

Page 9: Muon  Campus Projects Mary  Convery

A-0 Cooling Pond Civil construction to renew the A-0

pond heat rejection capacity and provide capacity for the 13.8 kv feeder from Master Substation to F-3 Switch.• A-0 Pond – Restore pond depth to

the original profile; replace pond pumps and intake; relocate and replace discharge.

• 13.8 KV Electrical Upgrade – Install new feeder (24B) in existing Main Ring duct bank from Master Substation to the F-3 Switch

9

• Costing still in progress

Page 10: Muon  Campus Projects Mary  Convery

Site prep GPP• Originally (early 2012) the Site Prep GPP included:

1. removal of an old spoils pile2. relocation of Kautz Rd3. installation of an additional power feeder

• Issues since then: items 1) and 2) above need to be accelerated in order to accommodate

accelerated Mu2e civil construction schedule items 1) and 2) above total ~$2M, not in lab's FY14 budget unclear feeder is needed: the estimated (g-2)+Mu2e needs are on the edge

of current capabilities and carry a large uncertainty

• Current plan    eliminate this GPP? move items 1) and 2) to Mu2e project

• Mu2e funding profile can accommodate this• will identify scope to swap out of Mu2e

revisit need for feeder once beamline designs are more mature and power needs can be estimated more accurately• if needed, would require funding in FY16-17 to be ready for Mu2e

solenoid commissioning in late FY1710

Page 11: Muon  Campus Projects Mary  Convery

Cryo AIP

Compressor and refrigeration systems g-2 and Mu2e cryogenic distribution system

Reuse Tevatron compressors at A0• Compressed He line from A0 to MC-1 building

Refurbish Tevatron refrigeration components to be housed in MC-1 building• 4 refrigerators to support simultaneous steady-

state operation of both g-2 and Mu2e Cold lines extending to both experimental

halls

to A0

piping headers

11

Page 12: Muon  Campus Projects Mary  Convery

Cryo AIP WBS

1 Muon Campus Cryogenics

1.01 Interface milestones

1.02 Project management

1.03 System engineering

1.04 Cryogenic plant sub systems

1.05 Experiment interfaces

1.06 Safety documents

1.07 Commissioning

1.08 Acceptance tests

12

• Total cost $9.8M, contingency is well understood

Page 13: Muon  Campus Projects Mary  Convery

Recycler AIP

Allows 8 GeV proton beam to be rebunched in the Recycler and extracted to the P1 line for transport to experimental areas• 2.5 MHz RF for re-bunching beam• Extraction kickers• Beamline connection from Recycler to P1 line• MI52 building extension for kickers (civil – move to separate FESS

project?)

13

RF cavity production• Cavities must have active cooling• Reuse ferrites from MI coalescing

cavities• Labor intensive• 7 RF systems (cavities + PA’s) for

Recycler• 2 cavities for Mu2e to be installed

in the Delivery Ring

Page 14: Muon  Campus Projects Mary  Convery

Recycler AIP WBS

1 Muon Campus Recycler Modifications

1.01 Project management

1.02 RF

1.03 Extraction kickers

1.04 RR to P1 beamline connection

1.05 MI52 building extension

14

• Costing and scheduling in progress, costs of some pieces are well-known

Page 15: Muon  Campus Projects Mary  Convery

Delivery Ring and Beam Transport AIP

15

P1, P2, M1 line aperture improvements for 8 GeV beam DR injection DR aperture improvements

• Removal of unneeded devices such as stochastic cooling tanks

DR abort• Beam abort for Mu2e• Proton removal for g-2

DR and beamline instrumentation needed for both Mu2e and g-2

Electrical infrastructure improvements

DR injection area

Page 16: Muon  Campus Projects Mary  Convery

Delivery Ring AIP WBSMuon Campus Beam Transport and Delivery Ring Modifications

1 Project management

2 Beam Transport to Delivery Ring

2.01 Beam transport to DR general

2.02 RR to DR beamline modifications

2.03 Beamline instrumentation

2.04 Beam transport intrastructure improvements

3 Delivery Ring conversion

3.01 DR general

3.02 DR injection

3.03 DR modifications

3.04 Beam abort system

3.05 DR instrumentation

3.06 DR infrastructure improvements16

• Unescalated costs well understood, scheduling in progress, current estimate $9.5M

Page 17: Muon  Campus Projects Mary  Convery

Muon Campus Project

Scope Notes

MC1 bldg GPP MC1 building which will house g-2 ring, g-2/Mu2e cryo systems and, some beamline power suppliesReconnect interrupted controls duct

Beamline enclosure GPP

M4 and g-2 line tunnels

Cryo AIP Compressor and refrigeration systemsCryogenic storage and inventory managementg-2 and Mu2e cryogenic distribution systemAuxiliary systems

Recycler AIP RF for re-bunching beamExtraction kickersBeamline connection to P1 lineMI52 building extension for kickers Move off AIP?

Delivery Ring AIP P1, P2, M1 line aperture improvements for 8 GeV beamDR injection and abortDR and beam transport instrumentation (common)Electrical infrastructure improvements

g-2 M3 line and reconfiguration of DR inject/extract regionDR extraction and shared portion of M4 linecomponents needed only for g-2

timeline and spec driven by g-2

Mu2e Kautz Rd relocationcomponents needed only for Mu2e

17

Page 18: Muon  Campus Projects Mary  Convery

Timeline

18

Page 19: Muon  Campus Projects Mary  Convery

Current funding plan for GPPs and AIPs

• The additional site power feeder that was part of site-prep GPP ($1M) is not included here, may be needed in 2017 or 2018

on critical path for g-2

on critical path for g-2

longer lead time for RF

19

Page 20: Muon  Campus Projects Mary  Convery

Status of Muon Campus project plans

Preparing for comprehensive Director’s review in next few months

Muon Campus Project

Requirements Project Execution Plan

Costing Schedule Notes

Cryo AIP signed off draft Recycler AIP in progress in progress in progress

Delivery Ring AIP in progress in progress

MC1 building GPP site prep package out for bid

Beamline enclosure GPP

in progress in progress in progress in progress

20